Excavator X63 Verification

This Webinar is LISTEN only

QUESTIONS?

Questions will be answered in writing at the end of the

Webinar.

Correction on installation information

No software termination for bucket sensor

Hardware termination on bucket sensor

CAN filter for GX60

7010-0916

Last Week Webinar Update

Bucket Termination

CAN Isolator

7010-0697

Reference Material

Excel Verification

Excavator X63 Verification

Webinar September 11 th , 2009

Verification Excel Work Sheets

TS-1 Calibration Verification

MC-A1 Position Verification

Excel Verification Work Sheet

Verification

No Verification

(Rotation error)

Graphics only

Not critical

TS-1 Calibration and Implement Length Verification

Start 3DMC and enter simulation mode.

TS-1 Calibration and Implement Length Verification

In Simulation

Set Level String

Match Elevation

Antenna Measurements (using GPS)

Compare GPS measured distance to the physical measured distance to adjust

Main/Aux Antenna position

RTK Solution (Single point localization )

Planner Surface

Rover with Pocket 3D

Verifying Main Antenna to Boom Length

Position the machine directly North

Mark bucket location and record Northing value

Rotate 180 o

Position the machine directly North

 Mark bucket location and record Northing value

Verifying Main Antenna to Boom Length

Subtract the two Northing values to get a GPS distance

• 15.50’

Using a tape or Rover measure the actual distance

• 15.30’

Subtract the two values and divide by 2

(15.50-15.30 = .20)/2 = .10

If the GPS measured(Northing) value is larger shorten the length in 3D-MC

If the tape measured value is larger lengthen the length in

3D-MC

Excel Verifying Main Antenna to Boom Length

Rotational Heading

Verifying Aux Antenna to Boom Length

Verifying Aux Antenna to Boom Length

Position the machine directly North

Curl the bucket in and record:

3DMC Easting of a bucket corner (position screen)

Easting with Rover and Pocket 3D

Extend the bucket to its fullest and record:

3DMC Easting of the same corner (position screen)

Easting with Rover and Pocket 3D

Verifying Aux Antenna to Boom Length

 Curled bucket Easting:

• 3DMC 520.35

• Rover 520.38

 Extended bucket Easting:

• 3DMC 520.36

• Rover 520.51

 The difference in curled position

• 520.38 - 520.35 = .03

 The difference in extended position

• 520.51 – 520.36 = .15

 Measured distance from curled to extended

• 20’

Verifying Aux Antenna to Boom Length

 Determine the Aux antenna correction amount using this formula:

A(Distance Between Antennas) C(Ext Easting – D (Curl Easting)

=

X B (Curl To Ext Distance)

7.5

=

.15 - .03

X 20

X=.045

Rover Easting's larger (decrease)

3DMC Easting’s larger (Increase)

Curled bucket Easting:

3DMC 520.35

Rover 520.38

Extended bucket Easting:

3DMC 520.36

Rover 520.51

Excel Verifying Aux Antenna to Boom Length

Verifying Main Antenna Offset

Position the machine directly North

Curl the bucket in and record:

3DMC Easting of a bucket corner (position screen)

Easting with Rover and Pocket 3D

Extend the bucket to its fullest and record:

3DMC Easting of the same bucket corner (position screen)

Easting with Rover and Pocket 3D

Verifying Main Antenna Offset

 Curled bucket Easting:

• 3DMC 520.35

• Rover 520.38

 Extended bucket Easting:

• 3DMC 520.48

• Rover 520.51

 The difference in curled position

• 520.38 - 520.35 = .03

 The difference in extended position

• 520.51 – 520.48 = .03

If Rover Easting's are larger (increase)

 If 3DMC Easting’s are larger (decrease)

Excel Verifying Main Antenna Offset

Verifying Main Antenna Height

Record several 3DMC bucket elevations and corresponding survey rover elevations

Subtract the elevations and find the average

•If 3DMC elevations are higher than the rover increase the antenna height

•If 3DMC elevations are lower than the rover decrease the antenna height.

Excel Verifying Main Antenna Height

Testing Machine Sensors for Accuracy

Elevation/Position Errors

Wedge errors or Inconsistent elevation errors

Perform Elevation Accuracy Verification to check machine and sensor calibration

Overall bias between machine and rover

Perform Main Antenna Height Verification

Northing Errors:

Perform Main Antenna to Boom Length Verification

Rotational Errors: (curled to extended)

 Perform Aux Antenna to Boom Length Verification

Easting Errors:

 Perform Main Antenna Offset Verification

Questions?

• Address to download all TU-Live Webinars: ftp://TUlive+topconuniversity.com:tulive@ftp.topconuniversity.com/

– Recorded Webinar

– PP Presentation; Introduction to Paver System

Five

– Webinar Q & A

• Additional requests for TU staff:

Email: training@topcon.com

Download