Chapter 14 Resource Planning Operations Management - 5th Edition Roberta Russell & Bernard W. Taylor, III Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Lecture Outline Material Requirements Planning (MRP) Capacity Requirements Planning (CRP) Enterprise Resource Planning (ERP) Customer Relationship Management (CRM) Supply Chain Management (SCM) Collaborative Product Commerce (CPC) Copyright 2006 John Wiley & Sons, Inc. 14-2 Resource Planning for Manufacturing Copyright 2006 John Wiley & Sons, Inc. 14-3 Material Requirements Planning (MRP) Computerized inventory control and production planning system When to use MRP? Dependent demand items Discrete demand items Complex products Job shop production Assemble-to-order environments Copyright 2006 John Wiley & Sons, Inc. 14-4 Demand Characteristics Independent demand Dependent demand 100 x 1 = 100 tabletops 100 x 4 = 400 table legs 100 tables Continuous demand Discrete demand 400 – 300 – No. of tables No. of tables 400 – 200 – 100 – 1 2 3 Week 4 300 – 200 – 100 – 5 Copyright 2006 John Wiley & Sons, Inc. M T W Th F M T W Th F 14-5 Material Requirements Planning Product structure file Master production schedule Material requirements planning Item master file Planned order releases Work orders Copyright 2006 John Wiley & Sons, Inc. Purchase orders Rescheduling notices 14-6 MRP Inputs and Outputs Inputs Master production schedule Product structure file Item master file Outputs Planned order releases Work orders Purchase orders Rescheduling notices Copyright 2006 John Wiley & Sons, Inc. 14-7 Master Production Schedule Drives MRP process with a schedule of finished products Quantities represent production not demand Quantities may consist of a combination of customer orders and demand forecasts Quantities represent what needs to be produced, not what can be produced Quantities represent end items that may or may not be finished products Copyright 2006 John Wiley & Sons, Inc. 14-8 Master Production Schedule (cont.) MPS ITEM Clipboard Lapdesk Lapboard Pencil Case 1 85 0 75 125 Copyright 2006 John Wiley & Sons, Inc. PERIOD 2 3 4 95 50 120 125 120 0 47 125 100 50 20 125 5 100 0 17 125 14-9 Product Structure Clipboard Top clip (1) Pivot (1) Bottom clip (1) Spring (1) Rivets (2) Finished clipboard Pressboard (1) Copyright 2006 John Wiley & Sons, Inc. 14-10 Product Structure Tree Clipboard Pressboard (1) Top Clip (1) Level 0 Clip Ass’y (1) Bottom Clip (1) Copyright 2006 John Wiley & Sons, Inc. Rivets (2) Pivot (1) Level 1 Spring (1) Level 2 14-11 Intended BOM List LEVEL 0----1----2---2---2---2--1---1--- ITEM Clipboard Clip Assembly Top Clip Bottom Clip Pivot Spring Rivet Press Board Copyright 2006 John Wiley & Sons, Inc. UNIT OF MEASURE QUANTITY ea ea ea ea ea ea ea ea 1 1 1 1 1 1 2 1 14-12 Specialized BOMs Phantom bills Transient subassemblies Never stocked Immediately consumed in next stage K-bills Group small, loose parts under pseudo-item number Reduces paperwork Copyright 2006 John Wiley & Sons, Inc. 14-13 Specialized BOMs (cont.) Modular bills Product assembled from major subassemblies and customer options Modular bill kept for each major subassembly Simplifies forecasting and planning X10 automobile example 3 x 8 x 3 x 8 x 4 = 2,304 configurations 3 + 8 + 3 + 8 + 4 = 26 modular bills Time-phased bills an assembly chart shown against a time scale Copyright 2006 John Wiley & Sons, Inc. 14-14 Modular BOMs X10 Automobile Engines (1 of 3) Exterior color (1 of 8) Interior (1 of 3) Interior color (1 of 8) Body (1 of 4) 4-Cylinder (.40) Bright red (.10) Leather (.20) Grey (.10) Sports coupe (.20) 6-Cylinder (.50) White linen (.10) Tweed (.40) Light blue (.10) Two-door (.20) 8-Cylinder (.10) Sulphur yellow (.10) Plush (.40) Rose (.10) Four-door (.30) Neon orange (.10) Off-white (.20) Station wagon (.30) Metallic blue (.10) Cool green (.10) Emerald green (.10) Black (.20) Jet black (.20) Brown (.10) Champagne (.20) B/W checked (.10) Copyright 2006 John Wiley & Sons, Inc. 14-15 Time-phased Bills Forward scheduling: start at today‘s date and schedule forward to determine the earliest date the job can be finished. If each item takes one period to complete, the clipboards can be finished in three periods Backward scheduling: start at the due date and schedule backwards to determine when to begin work. If an order for clipboards is due by period three, we should start production now Copyright 2006 John Wiley & Sons, Inc. 14-16 Item Master File DESCRIPTION Item Pressboard Item no. 734 Item type Purch Product/sales class Comp Value class B Buyer/planner RSR Vendor/drawing 07142 Phantom code N Unit price/cost 1.25 Pegging Y LLC 1 Copyright 2006 John Wiley & Sons, Inc. INVENTORY POLICY Lead time Annual demand Holding cost Ordering/setup cost Safety stock Reorder point EOQ Minimum order qty Maximum order qty Multiple order qty Policy code 1 5000 1 50 0 39 316 100 500 3 14-17 Item Master File (cont.) PHYSICAL INVENTORY On hand Location On order Allocated Cycle Last count Difference 100 W142 100 75 3 9/5 -2 USAGE/SALES YTD usage/sales MTD usage/sales YTD receipts MTD receipts Last receipt Last issue 1100 75 1200 0 8/25 10/5 CODES Cost acct. Routing Engr Copyright 2006 John Wiley & Sons, Inc. 00754 00326 07142 14-18 MRP Processes 1. Exploding the bill of material 2. Netting out inventory 3. Lot sizing 4. Time-phasing requirements Copyright 2006 John Wiley & Sons, Inc. 14-19 MRP Matrix Copyright 2006 John Wiley & Sons, Inc. 14-20 MRP: Example Master Production Schedule Clipboard Lapdesk 1 2 3 4 5 85 0 95 60 120 0 100 60 100 0 Item Master File On hand On order (sch receipt) LLC Lot size Lead time CLIPBOARD 25 175 (Period 1) LAPDESK 20 0 PRESSBOARD 150 0 0 L4L 1 0 Mult 50 1 1 Min 100 1 Copyright 2006 John Wiley & Sons, Inc. 14-21 MRP: Example (cont.) Product Structure Record Clipboard Level 0 Clip Ass’y (1) Pressboard (1) Rivets (2) Level 1 Lapdesk Pressboard (2) Trim (3’) Copyright 2006 John Wiley & Sons, Inc. Level 0 Beanbag (1) Glue (4 oz) Level 1 14-22 MRP: Example (cont.) ITEM: CLIPBOARD LLC: 0 LOT SIZE: L4L 1 2 3 4 5 Gross Requirements 85 95 120 100 100 Scheduled Receipts 175 Projected on Hand LT: 1 PERIOD 25 Net Requirements Planned Order Receipts Planned Order Releases Copyright 2006 John Wiley & Sons, Inc. 14-23 MRP: Example (cont.) ITEM: CLIPBOARD LLC: 0 LOT SIZE: L4L 1 2 3 4 5 Gross Requirements 85 95 120 100 100 Scheduled Receipts 175 Projected on Hand LT: 1 PERIOD 25 Net Requirements 115 0 Planned Order Receipts Planned Order Releases (25 + 175) = 200 units available (200 - 85) = 115 on hand at the end of Period 1 Copyright 2006 John Wiley & Sons, Inc. 14-24 MRP: Example (cont.) ITEM: CLIPBOARD LLC: 0 LOT SIZE: L4L 1 2 3 4 5 Gross Requirements 85 95 120 100 100 Scheduled Receipts 175 Projected on Hand LT: 1 PERIOD 25 Net Requirements 115 20 0 0 Planned Order Receipts Planned Order Releases 115 units available (115 - 85) = 20 on hand at the end of Period 2 Copyright 2006 John Wiley & Sons, Inc. 14-25 MRP: Example (cont.) ITEM: CLIPBOARD LLC: 0 LOT SIZE: L4L 1 2 3 4 5 Gross Requirements 85 95 120 100 100 Scheduled Receipts 175 115 20 0 0 0 100 Projected on Hand LT: 1 PERIOD 25 Net Requirements Planned Order Receipts Planned Order Releases 100 100 20 units available (20 - 120) = -100 — 100 additional Clipboards are required Order must be placed in Period 2 to be received in Period 3 Copyright 2006 John Wiley & Sons, Inc. 14-26 MRP: Example (cont.) ITEM: CLIPBOARD LLC: 0 LOT SIZE: L4L 1 2 3 4 5 Gross Requirements 85 95 120 100 100 Scheduled Receipts 175 115 20 0 0 0 0 0 100 100 100 100 100 100 100 100 Projected on Hand LT: 1 PERIOD 25 Net Requirements Planned Order Receipts Planned Order Releases 100 Following the same logic Gross Requirements in Periods 4 and 5 develop Net Requirements, Planned Order Receipts, and Planned Order Releases Copyright 2006 John Wiley & Sons, Inc. 14-27 MRP: Example (cont.) ITEM: LAPDESK LLC: 0 LOT SIZE: MULT 50 LT: 1 Gross Requirements PERIOD 1 2 0 60 3 4 0 60 5 0 Scheduled Receipts Projected on Hand 20 Net Requirements Planned Order Receipts Planned Order Releases Copyright 2006 John Wiley & Sons, Inc. 14-28 MRP: Example (cont.) ITEM: LAPDESK LLC: 0 LOT SIZE: MULT 50 LT: 1 Gross Requirements PERIOD 1 2 3 4 5 0 60 0 60 0 20 10 10 0 0 0 40 50 50 50 Scheduled Receipts Projected on Hand 20 Net Requirements Planned Order Receipts Planned Order Releases 50 50 Following the same logic, the Lapdesk MRP matrix is completed as shown Copyright 2006 John Wiley & Sons, Inc. 14-29 MRP: Example (cont.) ITEM: CLIPBOARD LOT SIZE: L4L LLC: 0 LT: 1 1 Planned Order Releases ITEM: LAPDESK LOT SIZE: MULT 50 LLC: 0 LT: 1 Planned Order Releases ITEM: PRESSBOARD LLC: 0 LOT SIZE: MIN 100 LT: 1 Gross Requirements Scheduled Receipts Projected on Hand 150 Net Requirements Planned Order Receipts Planned Order Releases Copyright 2006 John Wiley & Sons, Inc. 1 2 PERIOD 3 4 100 100 100 2 PERIOD 3 4 5 4 5 50 50 1 PERIOD 3 2 5 14-30 MRP: Example (cont.) ITEM: CLIPBOARD LOT SIZE: L4L LLC: 0 LT: 1 1 Planned Order Releases ITEM: LAPDESK LOT SIZE: MULT 50 1 Planned Order Releases Copyright 2006 John Wiley & Sons, Inc. 4 100 100 100 x1 x1 2 PERIOD 3 4 5 x1 LLC: 0 LT: 1 ITEM: PRESSBOARD LLC: 0 LOT SIZE: MIN 100 LT: 1 Gross Requirements Scheduled Receipts Projected on Hand 150 Net Requirements Planned Order Receipts Planned Order Releases 2 PERIOD 3 50 x2 1 100 5 50 x2 PERIOD 2 3 4 100 200 100 5 0 14-31 MRP: Example (cont.) ITEM: CLIPBOARD LOT SIZE: L4L LLC: 0 LT: 1 1 Planned Order Releases ITEM: LAPDESK LOT SIZE: MULT 50 LLC: 0 LT: 1 Planned Order Releases ITEM: PRESSBOARD LLC: 0 LOT SIZE: MIN 100 LT: 1 Gross Requirements Scheduled Receipts Projected on Hand 150 Net Requirements Planned Order Receipts Planned Order Releases Copyright 2006 John Wiley & Sons, Inc. 1 2 PERIOD 3 4 100 100 100 2 PERIOD 3 4 50 50 1 100 PERIOD 2 3 4 100 200 100 50 100 50 50 100 150 0 150 150 100 0 100 100 5 5 5 0 0 14-32 MRP: Example (cont.) Planned Order Report PERIOD ITEM Clipboard Lapdesk Pressboard Copyright 2006 John Wiley & Sons, Inc. 1 50 100 2 3 4 100 100 50 100 100 150 5 14-33 Lot Sizing in MRP Systems Lot-for-lot ordering policy Fixed-size lot ordering policy Minimum order quantities Maximum order quantities Multiple order quantities Economic order quantity Periodic order quantity Copyright 2006 John Wiley & Sons, Inc. 14-34 Advanced Lot Sizing Rules: L4L Total cost of L4L = (4 X $60) + (0 X $1) = $240 Copyright 2006 John Wiley & Sons, Inc. 14-35 Advanced Lot Sizing Rules: EOQ EOQ 2(30)(60 60 minimum order quantity 1 Total cost of EOQ = (2 X $60) + [(10 + 50 + 40) X $1)] = $220 Copyright 2006 John Wiley & Sons, Inc. 14-36 Advanced Lot Sizing Rules: POQ POQ Q / d 60 / 30 2 periods worth of requirements Total cost of POQ = (2 X $60) + (20 X $1) = $180 Copyright 2006 John Wiley & Sons, Inc. 14-37 Planned Order Report Item On hand On order Allocated DATE 9-26 9-30 10-01 10-08 10-10 10-15 10-23 10-27 Key: #2740 100 200 50 ORDER NO. Date Lead time Lot size Safety stock SCHEDULED GROSS REQS. RECEIPTS AL 4416 AL 4147 GR 6470 SR 7542 CO 4471 GR 6471 GR 6471 GR 6473 AL = allocated CO = customer order PO = purchase order 25 25 50 200 75 50 25 50 PROJECTED ON HAND 50 25 0 - 50 150 75 25 0 - 50 9 - 25 - 05 2 weeks 200 50 ACTION Expedite SR 10-01 Release PO 10-13 WO = work order SR = scheduled receipt GR = gross requirement Copyright 2006 John Wiley & Sons, Inc. 14-38 MRP Action Report Current date 9-25-05 ITEM DATE #2740 #3616 #2412 #3427 #2516 #2740 #3666 10-08 10-09 10-10 10-15 10-20 10-27 10-31 ORDER NO. QTY. 7542 200 7648 100 200 50 Copyright 2006 John Wiley & Sons, Inc. ACTION Expedite Move forward Move forward Move backward De-expedite Release Release SR PO PO PO SR PO WO 10-01 10-07 10-05 10-25 10-30 10-13 10-24 14-39 Capacity Requirements Planning (CRP) Creates a load profile Identifies under-loads and over-loads Inputs Planned order releases Routing file Open orders file Copyright 2006 John Wiley & Sons, Inc. 14-40 CRP MRP planned order releases Routing file Capacity requirements planning Open orders file Load profile for each machine center Copyright 2006 John Wiley & Sons, Inc. 14-41 Leveling Under-load Conditions 1. Acquire more work 2. Pull work ahead that is scheduled for later time periods 3. Reduce normal capacity Copyright 2006 John Wiley & Sons, Inc. 14-42 Reducing Over-load Conditions 1. Eliminating unnecessary requirements 2. Rerouting jobs to alternative machines, workers, or work centers 3. Splitting lots between two or more machines 4. Increasing normal capacity 5. Subcontracting 6. Increasing efficiency of the operation 7. Pushing work back to later time periods 8. Revising master schedule Copyright 2006 John Wiley & Sons, Inc. 14-43 Hours of capacity Initial Load Profile 120 – 110 – 100 – 90 – 80 – 70 – 60 – 50 – 40 – 30 – 20 – 10 – 0– Normal capacity 1 2 3 4 5 6 Time (weeks) Copyright 2006 John Wiley & Sons, Inc. 14-44 Hours of capacity Adjusted Load Profile 120 – 110 – 100 – 90 – 80 – 70 – 60 – 50 – 40 – 30 – 20 – 10 – 0– Pull ahead Overtime 1 2 Work an extra shift 3 Push back Push back 4 Normal capacity 5 6 Time (weeks) Copyright 2006 John Wiley & Sons, Inc. 14-45 Relaxing MRP Assumptions Material is not always the most constraining resource Lead times can vary Not every transaction needs to be recorded Shop floor may require a more sophisticated scheduling system Scheduling in advance may not be appropriate for on-demand production. Copyright 2006 John Wiley & Sons, Inc. 14-46 Enterprise Resource Planning (ERP) Software that organizes and manages a company’s business processes by sharing information across functional areas integrating business processes facilitating customer interaction providing benefit to global companies Copyright 2006 John Wiley & Sons, Inc. 14-47 ERP Modules Copyright 2006 John Wiley & Sons, Inc. 14-48 Organizational Data Flows Source: Adapted from Joseph Brady, Ellen Monk, and Bret Wagner, Concepts in Enterprise Resource Planning (Boston: Course Technology, 2001), pp. 7–12 Copyright 2006 John Wiley & Sons, Inc. 14-49 Selected Enterprise Software Vendors Copyright 2006 John Wiley & Sons, Inc. 14-50 ERP Implementation Analyze business processes Choose modules to implement Which processes have the biggest impact on customer relations? Which process would benefit the most from integration? Which processes should be standardized? Align level of sophistication Finalize delivery and access Link with external partners Copyright 2006 John Wiley & Sons, Inc. 14-51 Customer Relationship Management (CRM) Software that Plans and executes business processes Involves customer interaction Changes focus from managing products to managing customers Analyzes point-of-sale data for patterns used to predict future behavior Copyright 2006 John Wiley & Sons, Inc. 14-52 Supply Chain Management Software that plans and executes business processes related to supply chains Includes Supply chain planning Supply chain execution Supplier relationships Distinctions between ERP and SCM are becoming increasingly blurred Copyright 2006 John Wiley & Sons, Inc. 14-53 Collaborative Product Commerce (CPC) Software that Incorporates new product design and development and product life cycle management Integrates customers and suppliers in the design process though the entire product life cycle Copyright 2006 John Wiley & Sons, Inc. 14-54 ERP and Software Systems Customer Relationship Management (CRM) Collaborative Design Collaborative Product Commerce (CPC) Product Design Collaborative Manufacture DFMA Collaborative Design Manufacture & Delivery Collaborative Manufacture Enterprise Resource Planning (ERP) Time to Customer Time to Market Customers Suppliers Supply Chain Management (SCM) Source: Adapted from George Shaw, “Building the Lean Enterprise: Reducing Time to Market.” Industry Week (Webcast, June 14, 2001), http://www.industryweek.com/Events/TimeToMarket/ pent0614.html Copyright 2006 John Wiley & Sons, Inc. 14-55 Connectivity Application programming interfaces (APIs) give other programs well-defined ways of speaking to them Enterprise Application Integration (EAI) solutions EDI is being replaced by XML Copyright 2006 John Wiley & Sons, Inc. 14-56 Copyright 2006 John Wiley & Sons, Inc. All rights reserved. Reproduction or translation of this work beyond that permitted in section 117 of the 1976 United States Copyright Act without express permission of the copyright owner is unlawful. Request for further information should be addressed to the Permission Department, John Wiley & Sons, Inc. The purchaser may make back-up copies for his/her own use only and not for distribution or resale. The Publisher assumes no responsibility for errors, omissions, or damages caused by the use of these programs or from the use of the information herein. Copyright 2006 John Wiley & Sons, Inc. 14-57