Estimation THE FAMU-CIS ALUMNI SYSTEM CEN5055 Project Management Feb 23rd 2009 TEAM ORANGE Jamin Bao Martin Brown Sherene Campbell Saidi Mchumo Xian Long INTRODUCTION Tools used for estimation Function Points DVC Units of measure based on functionality The amount of data going through the system Cocomo “COnstructive COst MOdel” model for estimating effort, cost, and schedule for software projects Developed 1981 Cocomo II Same as Cocomo but for newer/more modern practices Developed 1997 – published in 2001 PROPOSED SSS MATRIX 21 Data Tables 11 Forms 7 Reports Proposed Matrix LINES OF CODE (SLOC) Team Member Lower Bound Expected Upper Bound Jiamin Bao 7900 8600 9100 Martin Brown 4340 6507 10143 Sherene Campbell 3530 4515 6125 Saidi Mchumo 9640 10850 Xian Long 8530 9850 10410 12020 Average 6830 7934 9647 FUNCTION POINTS:::OVERVIEW What is a Function Point? A standard unit of measure that represent the functional size of a software application. An application can be measured by the number of function points it delivers to the users of the application. A SIMPLE SIX STEP COUNTING PROCESS Identify all instances of each function type in the system. Assign a complexity weight to each instance of a function type. Calculate a weighted sum for each function type. Determine the unadjusted function count (FC). Determine the Value Adjustment Factor (VAF). Calculate FP Count. CALCULATING FUNCTION POINTS Calculate unadjusted Function Count (FC) Determine the Value Adjustment Factor (VAF) Calculate Function Points IDENTIFY FIVE STANDARD “FUNCTION TYPES” AND COMPLEXITY WEIGHT Data Functions: Internal logical files (ILFs) External interface files (EIFs) Transactional Functions: External Inputs (EIs) External Outputs (EOs) External Inquiries (EIs) CALCULATE UNADJUSTED FUNCTION COUNT (FC) FUNCTION POINTS FOR ALUMNI SYSTEM RESULTS LINES OF CODE (SLOC) ESTIMATE FROM FUNCTION POINTS Past date indicate that one FP translate into 25 times of code LOCs = 25 * 256 =6400 (approximately) Factor 25 45 60 SLOC 6400 11520 15360 DATA VOLUME COUNTER:::DATA DICTIONARY DATA VOLUME COUNTER:::DATA DICTIONARY DATA VOLUME COUNTER:::DATA DICTIONARY DATA VOLUME COUNTER:::OVERVIEW Needs Data Dictionary Purpose To calculate the input data volume DATA VOLUME COUNTER:::RESULTS (FROM XIAN LONG) DVC = 146 vs. function point 256 DATA VOLUME COUNTER:::RESULTS (FROM MARTIN) DVC = 161 vs. function point 256 COCOMO II ::: OVERVIEW To develop a software cost and schedule estimation model tuned to the life cycle practices of the 1990's and 2000's. To develop software cost database and tool support To provide a set of tools and techniques for evaluating the effects of software technology improvements on software life cycle costs and schedules. COCOMO II:::MODELS The Post-Architecture Model Most detailed COCOMO 2 model. Used after you've developed your project's overall architecture. It has new cost drivers, new line counting rules & new equations. The Early Design Model Get rough estimates of a project's cost and duration before you've determined it's entire architecture. It uses a small set of new Cost Drivers, and new estimating equations. Based on Unadjusted Function Points or KSLOC. Application composition model • Used when software is composed from existing parts. Reuse model • Used to compute the effort of integrating reusable components. COCOMO II:::EARLY DESIGN MODEL Estimates can be made after the requirements have been done Based on a standard formula for algorithmic models Effort (person-months) = A SizeB M where M = PERS RCPX RUSE PDIF PREX FCIL SCED; A = 2.94 in initial calibration Size in KLOC B varies from 1.1 to 1.24 depending on novelty of the project, development flexibility, risk management approaches and the process maturity. COCOMO II ::: SCALE FACTORS (B) COCOMO II ::: EFFORT ADJUSTMENT FACTOR(M) EM RCPX RUSE PDIF PERS PREX FCIL Name Product Reliability and Complexity Developed for Reusability Platform Difficulty Personnel Capability and Mapping Example Personnel Experience Facilites COCOMO II ::: RESULTS results CONCLUSION Function Points Team DVC Value: 256 SLOC: 11520 SLOC: 7934 (average) Martin: 161 Xian: 145 Cocomo I Cocomo II Effort: 21 (Likely) Effort: 28.7 (Likely) Cost: Student: $50,399 OutSource: $210,000 Cost: Student: $68,885 OutSource:$287,022.62 QUESTIONS