Infrastructure Delivery Management Toolkit: 2010 Edition Practice Guide 2: Construction Procurement Strategy 1 cidb development through partnership Contents of this presentation • Introduction • Challenges in current construction procurement practice • Traditional approach to construction • Alternative delivery options • Alternative pricing strategies • Framework Agreements • Construction Procurement Strategy 2 cidb development through partnership Challenges in the current construction practice To name a few: • Too many projects • Few people to manage and monitor projects • Too many relationships to manage • Scarcity of professionals in the public service • Consultant driven • Low skill levels and poor quality • Building in contractor development and job creation objectives • Too little time • Long decision making processes – regulations & policies • Stop – start implementation • Political influences 3 cidb development through partnership Fundamental considerations in delivery cost Quantum service delivery targets quality / performance delivery / time Bottom line – infrastructure delivery needs to meet expectations Current capacity constraints CIDB (2006) attributed the SA capacity constraints within government to deliver infrastructure to: • the project approach where for each and every project, consultants are appointed, briefed, directed and overseen by a gradually disappearing cadre of skilled staff • unbundling strategies aimed at reducing the size of contracts in order to target small or local enterprises which place increased demands on the client’s resources to manage and oversee these small contracts CIDB proposal CIDB inform practice note No 1: SCALING UP DELIVERY AND ACCELERATING EMPOWERMENT (August 2006) In a nutshell • Use larger contracts • Use longer contracts • Adopt a programmatic and a systems approach What this does is to: 1) Reduce the work load of the SCM units 2) Reduce the number of relationships to a manageable level which frees up government’s capacity to brief service provides, manage contracts and to make payments 3) Allow skills to be rapidly replicated and certain tasks to be de-skilled 4) Improve job creation and SMME development outcomes Search for alternative delivery models Problem statement Capacity constraints exist due to the continued use of an outdated delivery approach Solution Require a delivery model which: CIDB / National Treasury IDMS 2010 • matches the capabilities and capacities of the client to effectively oversee its implementation • takes account of the capabilities of the private sector • accommodates current socio-economic delivery imperatives Have in place well developed targeted procurement procedures to address this aspect of delivery Traditional approach to construction Procurement strategy for traditional approach to delivery - One project one contract (or a group of smaller contracts) - Discipline specific consultants appointed on a percentage fee basis - Open tenders are called for when the design is complete - Contractors are contracted on a bills of quantities basis No need to consider procurement strategy – a one size fits all approach suffices Traditional approach to construction Fee based on percentage of cost of construction – allows project to be developed as it unfolds Scope of work for consulting services contract Outline statement Master Procure consulting services Stage 1: Preparation Scope of work for construction work contract Stage 2: Definition Master – servant relationship Stage 3: Design Development Procure construction works Stage 4: Production information Servant Priced contract based on lump sums or bill of quantities Traditional approach to construction John Smeaton in 1768 during the construction of the Clyde Canel (Scotland) established the master / servant between designers and contractors Sir Joseph Bazalgette’s standard form of contract for London’s major sewer projects and the embankments on the Thames 1860s was adopted by the Metropolitan Board of Works Institution of Civil Engineers’s standard form of contract published in 1945 based on the 1860 standard form of contract South African current traditional forms of contract based on ICE form of contract Are their different ways of delivery projects to improve outcomes? Design by Employer Contract under which a contractor undertakes only construction on the basis of full designs issued by the employer. Suitable where: • The client wishes to make significant technical inputs into design process and design details. • The client requires flexibility in the development of the design. • The risks are to be balanced between the parties, or • Reasonable certainty in cost and time is required before a commitment to build is made. • Suitable client accepted production information is available to be incorporated into the scope of work for the contract. Alternative allocation of design responsibilities Design and construct Develop and construct Contractor designs a project based on a brief provided by the client and constructs it Contract based on a scheme design prepared by the client under which a contractor produces drawings and constructs it Alternative contracting strategies Stage 1 Preparation 2 Definition 3 Design development 4 Production information 5 Manufacture, fabrication and construction information 6 Works 7 Handover 8 Close out Award works contract Design and construct contract Scope of work based on concept report Note Contractor responsible for later design stages Consultant reviews contractor’s design against project brief Design and Construct Contract in which a contractor designs a project based on a brief provided by the client and constructs it Suitable where the employer requires • Integrated design and construction and single point accountability • That most risks lie with the contractor in return for price certainty, or • The cost and completion date is almost guaranteed when a commitment to build is made. Suitable for simple and moderately complex projects, particularly where the client has limited technical capability. Alternative contract strategies Stage 1 Preparation 2 Definition 3 Design development 4 Production information 5 Manufacture, fabrication and construction information 6 Works 7 Handover 8 Close out Award works contract Develop and construct contract Scope of work based on design development report Note Contractor responsible for later design stages Consultant reviews contractor’s design against project brief Develop and Construct Contract based on a scheme design prepared by the client under which a contractor produces drawings and constructs it. Suitable where the employer requires • Integrated detailed design and construction and single point accountability • Reasonable certainty in cost and time before a commitment to build is made. Suitable for simple and moderately complex projects Alternative allocation of management responsibilities Management Contractor is responsible for planning contractor and managing all post-contract activities and for the performance of the whole of the contract Management Contract Contract under which contractor provides consultation during the design stage and is responsible for planning and managing all post contract activities and for the performance of the whole of the contract. Suitable where: • The employer has limited capability or capacity to advance the work beyond a strategic brief. • The employer retains most of the risks • The contractor needs to work alongside the design team to develop the programme for construction design and tender. Suitable for sophisticated projects, particularly where the client has limited technical capability. Management contractor relationship Employer Example Management contractor Subcontractor (construction work sub contract) Subcontractor (construction work sub contract) Subcontractor (construction work sub contract) Design consultant (professional service contract) Design consultant (professional service contract) Management contractor subcontracts out the bulk of the work Alternative contracting strategies Stage 1 Award works contract Preparation 2 Definition 3 Design development 4 Production information 5 Manufacture, fabrication and construction information 6 Works 7 Handover 8 Close out Alternative Alternative Management contractor Scope of work based on design strategic Alternative Note Contractor can be made responsible for all or some of the design and all construction Construction Management Contract under which a contractor is responsible for planning and managing all post-contract activities and for the performance of the whole contract. Where it is desirable to • Have direct contracts with specialists trade contractors or small contractors, and • Manage the interfaces between interrelated packages within a project. • Suitable for projects where a number of trade contractors are appointed. Alternative pricing strategies Starting point Tender prices can be built up by considering a number of components including: • General items: items to cover the charges for compliance with contractual obligations • Construction (work) content: price of constructing all the items that are to be constructed or built • Overheads: operating (every day) expenses incurred in the upkeep of the business and its offices that are not directly attributable to individual contracts • Risk allowance: an allowance (contingency) to cover the perceived risk associated with uncertainty • Profit Bill of quantities Build up of tender price General item or Construction content – Overheads Risk labour, materials, plant Profit allowance and equipment or Subcontracted work Item No. Description Unit of Measure Quantity Rate Total Bill of quantities • is useful only to develop a tender price for the contract • cannot be used to control costs on site Bill of Quantities • Client takes the risk for changes • Contractor takes the risk of rate changes • Use where • a clear, unambiguous scope of works exists, which is complete save for uncertainty on the actual quantity of work to be done e.g. earthworks • Where little or no change to programme is envisaged • The level of risk is low and quantifiable 24 Pricing strategies: Activity schedule Break the scope of work down into activities related to a programme and price each activity as a lump sum TIME IN WEEKS: W1 W2 W3 W4 W5 W6 W7 Alternative pricing strategies No ACTIVITY 1 Establish Out… 2 Excavation 3 Foundation Concrete & Brickwork. 4 Superstructure 5 Roof 6 Services (1st; 2nd; Final) 7 External Works 8 Finishing and cleaning 9 Hand over to client Site; Set W8 W9 Activity schedule Item No. Programme Activity description Reference General item or Construction content – labour, materials, plant and equipment or Subcontracted work Price excluding VAT Build up of tender price Overheads Profit Risk allowance An Activity Schedule is a list of activities which represents the activities expected to be carried out The Contractor enters lump sum prices against each of these activities (Total = contract sum) Paid for completed activity Lump sum Lump sum Contractor is paid a lump sum to perform the works (Interim payments which reflect the progress made towards the completion of the works may be made) Contractor is : • at risk for costs associated with completing the contract • not compensated for any errors or omissions of his own Price list Price list / Contractor is paid the price for each lump schedule sum item in the Price List that has been completed and, where a quantity is stated in the Price List / Schedule, an amount calculated by multiplying the quantity which the contractor has completed by the rate Contractor is only paid amounts in Price List for priced work Lump Sum, price list, activity schedule Price-based strategy • Contractor takes the risk for changes in quantities • Client takes risk of change of scope • Use where • A clear, unambiguous scope of work exists, which is complete in all respects and as such can be priced with certainty. • Changes to requirements are not anticipated 29 Bill of quantities vs other price-based pricing strategies The primary purpose of a bill of quantities is to arrive at a tender price within relatively short time frames so that a tender can be evaluated and a contract awarded The employer is liable for increases in the tender price arising from increases in quantities and mistakes in compiling the bill of quantities In lump sum, activity schedules and pricing list contractor is at risk as price is all inclusive What about other pricing strategies? Price based: • • • • bill of quantities activity schedule lump sum price list Cost based: • cost reimbursable • target cost Cost Reimbursable • Contract in which the contractor is paid for his actual expenditure plus a percentage or fee. • Use where an emergency exists • the scope of work cannot be priced ahead of the works • the employer cannot transfer the project risk to the contractor or the risk pricing is prohibitive • the contract is likely to be disrupted by uncontrollable events 32 Cost reimbursable contract Fee includes profit and overheads Wages and salaries + Fee Site overhead percentage Materials at open market rates + Fee includes profit and overheads Fee Equipment at agreed rates, market related rates or percentage up or down on a hire list Subcontract costs Target cost contract Target Price (initial) Target Price (final) adjusted for compensation events Final “cost” pain (share of gain (share cost of savings) overrun) payment to contractor (cost + fee) Scenario 1: Contractor gain Sharing of cost savings / overruns Scenario 2: Contractor pain Target Cost Pricing • Cost reimbursable contract in which a target cost is estimated and on completion of the works the difference between the target cost and the actual cost is apportioned between the employer and contractor on an agreed basis. • Use where: • The employer wishes to reward strong contractor performance, share financial risk or promote collaboration • An early contractor involvement is required to make inputs into the design process • Framework agreements are entered into 35 Target price contracts Procurement of contractors Option 1 (design is not sufficiently developed) • Tenderers tender cost parameters • Target price negotiated when sufficient information available to price the works Option 2 (design is sufficiently developed to price) • Tenderers tender cost parameters • Assumptions are made about any uncertainties so that the tenderers can price the works (adjust target if assumptions turn out to be incorrect e.g. quantum of reinforcement) • Tenderer tenders a target price Management contractor relationship Employer Example Management contractor Design consultant (professional service contract) Subcontractor Subcontractor Subcontractor Design (construction (construction consultant (construction Management contractor subcontracts out the bulk of work sub sub (professional sub the work and work is paid on a costwork reimbursable basis i.e contract) contract) service contract) contract) subcontract amount plus a fee + prices for work done by the contractor himself This allows cost to be controlled Pricing strategies Activity schedule / lump sum Activity schedule (lump sum) Price List Min Employer’s flexibility to effect scope changes Bill of Quantities Bill Employer’s flexibility to effect change Max Pricing strategy of quantities Target cost Target cost Cost Cost reimbursable reimbursable Min Max Employer’s riskrisk Employer’s Contractor’s incentive / risk Contractor’s risk Max Min The relationship between the employer’s risk and flexibility to effect scope cha in the different pricing strategies Benefits of Target Cost Pricing • Allows early contractor involvement • Facilitates collaborative / partnering / developmental relationships • Suitable for use in framework agreements because: − allows the employer to procure work on an asinstructed basis over a set term without necessarily committing to any quantum of work − offers flexibility in attaining secondary procurement objectives as requirements can be adjusted from one package order to another 39 Lean construction To provide higher value and less waste the fragmentation in design needs to be addressed, preferably before 25% of the design is complete Target cost contracts can enable this to happen even where a design by employer approach is adopted This allows a specialist in construction to be appointed at the same time as the design team Such a contractor may or may not be responsible for managing the design team Consideration Contracting strategy Design by employer Management contract Develop and construct Design and build Pricing strategy Activity schedule NEC3 Yes Cost reimbursable Target cost GCC FIDIC Yes Yes No Red Silver Yes Yellow & Silver No Lump sum & breakdown No No No Lump sum Bill of quantities JBCC Yes Yes Yes Yes Yes Yellow & Silver Red No No No No No No What is a framework agreement? ISO 10845-1, Construction procurement – Part 1: Processes, methods and procedures A framework agreement is an agreement between an employer and one or more contractors, the purpose of which is to establish the terms governing contracts to be awarded during a given period, in particular with regard to price and, where appropriate, the quantity envisaged Allows the employer to procure construction services to provide work packages on an as-instructed basis (call offs) over a set term without necessarily committing to any quantum of work Current paradigm Client appoints a professional team to design the works Open tenders are called once the production information has been finalised by the professional team (production information = final detailing, performance definition, specification, sizing and positioning of all systems and components) Contractor prices the production information Contractors are contracted on a bills of quantity basis for a single project (which may or may not include budgetary items to cover aspects of the works which have not been finalised) Packages in a framework contract Hand over works C o n c e p t Construct works Document works P #2 P #1 Scope works Develop concept for works Packages delivered over a term by a single contractor Design works P #3 P #4 etc Procuring a service over a period of time Package orders University of the Witwatersrand Package #1 Package #2 Start November 2009 Start January 2009 Chamber of Mines – fourth quadrant (R70 m) Package #3 April 2010 Wits Art Museum (R68m) Undergraduate Science Centre– phase 1 (R178 m) Package #4 Start October2010 Refurbishment of Chamber of Mines – (R45m) Same contractor but different professional teams Principles of Framework Agreements Framework agreements • are entered into following a competitive selection process • need to establish the following as a minimum: - the basic terms of the contract the term of the contract (3 -4 years) the scope of the work which may form the basis of a package order the basis by which contractors are to be remunerated for instructed work the manner in which competition between framework contractors may take place Essential elements of a framework • A package is works within the scope of work of a framework agreement which is instructed within a stated period of time (start and end date) • A package order is an instruction to carry out a task and may only be issued within the term of the agreement Start date Framework contract Start Start End End Start Package orders • End date Start End End A framework contract is only entered into with those who have the capability and capacity to carry out the likely work Outcomes of Alternative Delivery Approaches FROM TO • Master-servant relationship of adversity • Fragmentation of design & construction • Allowing risks to take their course • Short-term “hit and run” relationships • Constructability & cost model determined by design team and consultant only • “pay as you go” delivery culture • Collaboration towards shared goals • Integration of design and construction • Proactive, collaborative risk management and mitigation • Long-term relationships focused on maximising efficiency & shared value • Constructability and cost model developed with contractor’s insight • Discipline of continuous budget control 48 Key question Question: How does one appoint a contractor in the absence of a scope of work? Answer: Look at: • • cost based pricing strategies as apposed to price based strategies rates based contracts (where P and G costs are fairly constant and work is very straightforward) Pricing strategies for framework contracts A framework agreement is a contract where the terms of payment are agreed in the absence of a detailed scope of work Pricing strategies Lump sum Not suitable –require scope of work to price the work Bills of quantities Activity schedule Possibly in simple works but need to deal with costs Price list associated with different sites Cost reimbursable Target cost Yes – if linked to a management contractor Suitable – as cost parameters can be pre-agreed and target can be initially tendered and thereafter negotiated Standard provisions for pricing strategies Look at NEC3 Lump sum & breakdown Consideration Activity schedule / lump sum Bill of quantities Cost reimbursable Target cost NEC3 JBCC GCC Yes Yes Yes Yes No Yes No FIDIC Yellow & Silver Red No No No No eThekwini AC secondary water mains • identified a project for the replacement of 2500 km of AC water pipes over a period of 3 years • appointed one programme manager + 4 design consultants + 4 contractors Time frames Feb 2007 - concept introduced and work shopped with officials, consultants and contractors Mar 2007 - calls for expressions of interest May 2007 - shortlisted respondents invited to tender May 2007 - tenders closed June 2007 - tenders evaluated and awarded 1 July 2007 - work starts (new financial year) eThekwini AC secondary water mains Expenditure R400 million spent in first 14 months Productivity: 80 km of water mains replaced each month. Socio economic: • ± 3800 temporary unemployed workers employed to excavate trenches and are rotated every 4 months to allow others to financially benefit • Temporary workers paid 21% of total project expenditure. • 16 subcontractors (or “co-contractors”) developed to increase their share of the construction work from 10% to 20% over time (should double their turnover over time) • A full time mentor engaged to assist the “cocontractors” in the establishing of business systems Staff demands on client: one staff member eThekwini AC secondary water mains Awards • won the coveted KAMOSO award for Best Construction Project in the Infrastructure category (Department of Public Works which recognizes and rewards excellence in the implementation of Expanded Public Works (EPWP) programmes • Philiswe Mthethwa of Abangani Projects, an emerging sub contractor came third in the CIDB National Women in Construction Excellence Awards All subcontractors have doubled their CIDB grading during the term of the contract! Construction procurement strategy Construction procurement strategy is the combination of: • delivery management strategy • contracting arrangements • procurement arrangements A procurement strategy can be developed for: • • • a single project a programme of projects a portfolio of projects It identifies the best way of achieving objectives and value for money, whilst taking into account risks and constraints Portfolio = the total extent of infrastructure controlled or used by an institution Portfolio of projects over next few years Programmes packages A strategic approach Package = works which have been grouped together for delivery under a single contract or a package order issued in terms of a framework agreement The Benefit of Developing a Procurement Strategy The central objective of developing a construction procurement strategy is: • to determine possible procurement and contracting options • that will maximise value-for-money, • deal with capacity constraints • and ensure long term sustainability • Different options are most suitable under different conditions • The choice of options is dependent on local conditions. 57 cidb development through partnership Construction Procurement Strategy 1 Gather & Analyse information Version 1.1 March 2011 1 – Delivery Management Strategy 2 Formulate procurement objectives 3 Make strategic delivery management decisions 4 Decide on delivery mode Package Works 5 Spend Analysis Primary Implementing Agent (IA - SLA) FA opportunities Organisational Analysis Programme of Projects Secondary Another organ of state FA Individual Projects Packages Market Analysis Leasing Outsourcing Own Resources Quality Strategy Options Specifications Life cycle costing Pre-qualification Evaluations Criteria Undertakings at tender stage Preference Eligibility Criteria Procurement Procedure Options Competitive selection Negotiation Competitive negotiation Targeted Procurement Procedure Options Preferencing Incentives for KPI’s Mandatory Subcontracting Contractual Obligations PPP – follow NT PPP procedures Decide on quality strategy Decide on procurement arrangements Decide on targeted procurement strategy Decide on tender evaluation procedure 1 2 3 4 3 - Procurement Arrangements 1 Allocate risks for packages 2 - Contracting Arrangements Service Requirements Pricing Strategy Form of Contract 2 3 4 Establish requirements for outsourced professionals Package professional service contracts Allocate risks for professional service contracts Contracting Strategy Type of Contract Pricing Strategy Form of Contract Contracting Strategy Design by employer Develop & Construct Design & Construct Construction Management Management Contractor Pricing Strategy Activity based / lump sum Bill of Quantities Cost reimbursable Target Cost Form of Contract NEC3 FIDIC JBCC GCC 2010 Decide on delivery management strategy Gather and analyse information Formulate procurement objectives Meet need for works through: Make strategic delivery management decisions Decide on delivery mode (project or programme) Package works a PPP an Implementing agent (IA) another organ of state’s framework agreement (FA) leasing of property outsourcing own resources Contracting arrangements Allocate risks for packages Contracting strategy Design by employer Develop & construct Options for services: Design & construct construction Construction management construction & maintenance Management contractor maintenance Pricing strategy: construction, maintenance & operation Priced contract with a priced list CIDB Establish requirements Cost reimbursable accepted for outsourced Target cost Form of professional services Activity based / Lump sum Contract Bill of quantities Discipline specific or Package professional service multidisciplinary service contracts Package specific, programme related or framework agreement Priced contract, percentage of Allocate risks for professional cost of construction, cost service contracts reimbursable or target cost Contracting arrangements Activity 1: Allocate risks for packages Options for service requirements Option Construction only Pricing strategy Activity based / lump sum Bill of quantities Cost reimbursable Target Cost Maintenance only Priced contract with a priced list Cost reimbursable Target cost Maintenance and construction As for maintenance and construction services As for maintenance and construction services Construction maintenance and operation Form of contract NEC3 Engineering and Construction Contract NEC3 Engineering and Construction Short Contract. FIDIC Conditions of Contract for Construction and Building and Engineering Works Designed by the Employer FIDIC Conditions of Contract for Plant and Design FIDIC Conditions of contract for EPC Turnkey Projects FIDIC Short Form of Contract General Conditions (Short Form) JBCC Principal Building Agreement JBCC Minor Works Agreement GCC 2010 CIDB General conditions of contract NEC3 Term Service Contract NEC3 Short Term Service Contract NEC3 Engineering and Construction Contract with or without NEC3 Term Service Contracts FIDIC Conditions of Contract for Design, Build and Operate Projects NEC3 Engineering and Construction Contract plus NEC3 Term Service Contracts 61 cidb development through partnership Deciding on the procurement arrangements Decide on quality strategy Decide on procurement procedure Decide on targeted procurement strategy Decide on tender evaluation procedure Step 1: Decide on Quality Strategy Refer to Practice Guide 2, Section 7.2, page 41, Table 14 for options and decision criteria for building quality into the procurement arrangements. Quality may be achieved through: • Specifications • Life cycle costing • Prequalification • Eligibility criteria • Undertakings at tender stage • Preference • Evaluation criteria 63 Step 2: Decide on Procurement Procedure Practice Guide 2, Section 7.3, page 42, Table 15 You will select one of the three basic procurement procedures, using the criteria set out in Table 15: • A negotiation procedure where a tender offer is solicited from a single tenderer • A competitive selection procedure • A competitive negotiation procedure • Eligibility criteria (Call for expressions of interest) 64 Options within Competitive Selection •If you have chosen a competitive selection procedure, you must make further choices: • Nominated • Open • Qualified • Quotation • Proposal procedure using the two-envelope system • Proposal procedure using the two-stage tendering system 65 Options within a Competitive Negotiation If you have chosen a competitive negotiation selection procedure, you must make further choices. Restrictive competitive negotiations Open competitive negotiations 66 Step 3: Decide on Targeted Procurement Strategy There are four options for targeted procurement procedures: • Preferencing • Incentives for KPIs • Mandatory subcontracting • Contractual obligations. You will select one or more of the targeted procurement procedures for your packages. 67 Step 4: Decide on Tender Evaluation Procedure • Method 1: Financial offer • Method 2: Financial offer and preferences • Method 3: Financial offer and quality • Method 4: Financial offer, quality and preferences. 68 Document choices A B data data data data data data Targeted procurement strategy Procurement arrangements Contracting Procurement arrangements arrangements for strategy for works work Quality strategy Category Delivery of spend management strategy Evaluation procedure Procurement strategy for works data data data data data data data data data data data data Document choices Procurement strategy for professional services data data data data data A data data data data data data data data data data data data Evaluation procedure data data data Targeted procurement strategy Procurement arrangements for professional services Procurement arrangements Contracting arrangements for professional services Quality strategy Category Delivery of spend management strategy Document choices Contents 1 Background 2 Delivery management strategy 2.1 Nature and spatial arrangement of projects and clusters 2.2 Client organisation characteristics 2.3 Market characteristics 2.4 Primary procurement objectives 3 Contracting arrangements 3.1 Risk allocations for packages 4 Procurement arrangements 4.1 Quality strategy 4.2 Procurement procedure 5 Satisfying primary and secondary procurement objectives 5.1 Construction procurement strategy 2.5 Secondary procurement objectives 2.6 Delivery management plan 2.7 Delivery mode 2.8 Packaging strategy 3.2 Professional service contracts 4.3 Targeted procurement strategy 4.4 Tender evaluation procedure 5.2 Issues to be dealt with in the contracts which are not addressed elsewhere Challenges Envisaged challenges to rolling out the methodology • Client difficulty in deciding on objectives • Clients unwilling to balance opposing objectives • Absence of open-minded programme managers • Resistance to change, particularly from professional service providers Dr Sean Phillips Construction symposium: The project management profession: adding value University of the Witwatersrand (August 2009) Documenting a procurement strategy The procurement strategy arrived at by applying the aforementioned procedures needs to be documented in such a manner that the logic behind the choices that are made at each step can be communicated to and reviewed by others. Accordingly, the specific inputs and outputs of the actions at each step in the stages of the development of a strategy need to be documented. A procurement strategy at a portfolio level should be documented in a tabular form which links each category or portion of a category of spend to a number of high level descriptions. Procurement strategies at a programme level can be similarly presented, with perhaps, more detailed descriptors. The strategic brief that is developed for a package during the package information stage of the package planning phase must, however, set out all the choices made in relation to the package in sufficient detail to enable procurement documents to be drafted to enable the necessary procurement processes to commence. 73 cidb development through partnership Conclusion and questions Thank you cidb 74