Liaison Committee Presentation
April 10th, 2013
As part of this project, a Liaison Committee is being established to facilitate the participation of the community in the development of the wind farm.
The Liaison Committee will ensure that the interests of landowners are considered and participation of local businesses and services is encouraged.
The objectives of the committee are to:
Ensure effective communication between all stakeholders and EDF EN
Canada Development Inc.;
Understand issues related to the development and construction of the wind farm;
Recommend satisfactory solutions to stakeholders;
Identify potential opportunities for local business and services
Liaison Office
As Manager of the Blackspring Ridge Wind Project, EDF EN Canada
Development Inc. is committed to working with all stakeholders during the development, construction and operation phases of the Project.
If you have any questions or comments, please do not hesitate to contact the Blackspring Ridge Liaison Office at:
Kimberli Kenna, Site and Liaison Administrator
If meetings are needed or requested, Paul Lawson is available by appointment.
Tel.
: 403-671-4000
E-mail : blackspringridge@edf-en.ca
More information on the Project can also be found at www.blackspringridge.ca.
As the project approaches Commercial Operation, various teams are preparing for the Operations phase of the project which will last for the next
20 years.
Following is a brief description of each of the teams responsibilities:
EDF EN Canada Development Inc.
: ECDI will continue to be the
Manager of the Project and will continue to be the main point of contact for all stakeholders and manage tasks such as landowner payments.
Enbridge : Enbridge will be the Balance of Plant Operations &
Maintenance (BOP O&M) Manager and will be responsible for the maintenance of the site and the substation.
Vestas : With approximately 20 technicians on site, Vestas will be the
Operations & Maintenance Manager and will be responsible for the day to day Operations & Maintenance (O&M) of all the turbines.
Operations Team Contact Information
Contact information for the Operations team will be communicated to all project landowners and other stakeholders through letters and our future project monthly newsletter updates.
AltaLink has completed construction on the 13 kilometres (eight miles) of new transmission line that will connect the Blackspring Ridge
Substation to Alberta’s transmission system.
AltaLink’s project also completed a new switching station, as well as a new telecommunications tower within the fence line at
Traverse Switching Station.
On March 31 st , AltaLink’s project team successfully energized the Traverse Switching
Station and 240kv transmission line!!!
For more information on
AltaLink’s Blackspring
Ridge Wind Farm Connection visit www.altalink.ca/projects
Altalink Substation
All 166 turbines have been erected
Construction on the Operation & Maintenance building is complete.
The Blackspring Ridge substation was successfully energized on March 31 st !!
During the month of April, we plan to energize the 12 underground collection feeder circuits.
Turbine commissioning will be starting within this period as well.
The Blackspring Ridge Wind Project will soon be providing 300 MW of clean renewable energy to the province of Alberta
Enough to power the equivalent of 120,000 homes.
Operations & Maintenance Building
Blackspring Ridge Landscape
Activities on site
With erection complete and Commercial Operation rapidly approaching, stakeholders can expect:
Important reduction of traffic on site
130 manpower & subcontractors on site as of March 31 st
Down from peak of 330+ on site
Reduction of laydown area footprint
Commissioning of the turbines
Occupation of O&M building
Restoration/Reclamation
An energized project
The complete site should be considered energized
Underground cables
Junction boxes
Overhead line
Substation
Call “ Alberta One Call ” prior any excavating or digging
Landowner Payment Schedule
Landowner payments related to the:
2014 crop compensation will be issued during the months of June/July.
Royalty payments related to the production of the Blackspring Ridge Wind Project will be issued in July/August.
In accordance with the Environmental Protection Plan, before restoration work can begin, the frost must come out of the ground and the ground must be dry enough to prevent damage to the soil structure and re-growth problems.
Native Prairie Protection
Bird Sensitive Areas
The work is expected to begin in early May, but could start earlier if the conditions allow for it and will be completed over the course of the next few months.
It is anticipated that over 30 equipment operators and laborers will be onsite to complete the restoration work.
Many different activities will be starting at the same time when weather allows:
Removal of public radii improvements
Removal of access road entrances
Removal of crane crossings
Installation of cattle guards
EDF EN Canada and Enbridge consider environmental protection to be an important and integral part of the
Project.
As per ESRD requirements, ECDI and
Enbridge plan to run Post Construction
Monitoring of birds and bats for 2 years post June 2014.
Noise assessment will also be conducted on site and all documents and findings will be publically available online.
Community Project Funding
ECDI and Enbridge finalized the community project funding application form and requirements.
The 2014 community project funding envelope will be announced shortly and the selected projects will be announced during the Blackspring Ridge dedication ceremony (July).
Guidelines of the program and applications will be advertised through local media and other outlets
Suggested Timeline
May 2014
May 2014
June 2014
July 2014
Meeting in Carmangay with identified and/or interested community members, organisations and projects to present the guidelines and the timeline of this initiative.
Launch Community Project Funding Application Window
Deadline for application
Announce recipients of 2014 Community Project Funding at dedication ceremony
Projects that will be supported include:
Community services and development
Medical research and infrastructure
Arts
Education
Environmental
Health
Social services
Criteria used to evaluate the project:
Background of the applicant (how long it has been in operation and prior experience)
The projects long term impact to the community
Quality of life/community enhancement
Demographics served
Community Support for the project
Tentative Schedule
Date/Time
Tuesday, July 15
Time
11am – 2pm
Location
Operations & Maintenance facility parking lot
Guest list will include:
Blackspring Ridge landowners
Local, municipal, provincial and federal leaderships
First Nations dignitaries
Other special guests
For questions, comments or inquiries, please contact the Blackspring
Ridge Liaison Office:
Tel.: 403-671-4000
E-mail: blackspringridge@edf-en.ca
A wealth of renewable experience in Canada.
Liaison Committee Presentation 10/04/2014 13