Alasan Penghakiman NO: 22-920-2001 DALAM MAHKAMAH TINGGI MALAYA DI SHAH ALAM (BAHAGIAN SIVIL) GUAMAN SIVIL NO: 22-920-2001 ANTARA CHUNG NYAP YOON SDN BHD … PLAINTIF … DEFENDAN DAN CYPARK SDN BHD ALASAN PENGHAKIMAN OLEH YANG ARIF HAKIM DATO’ TENGKU MAIMUN BINTI TUAN MAT 1 Alasan Penghakiman NO: 22-920-2001 The plaintiff’s claim against the defendant is for RM1,894,720.49. The defendant has a counterclaim for the sum of RM42,000.00 THE BACKGROUND FACTS The defendant was appointed by Setia Haruman Sdn Bhd as the turnkey contractor for ‘Cyber Park Development Project Phase 1 (the project). The defendant then appointed the plaintiff as its subcontractor for the construction of Bulk Earthworks to finish platform level covering the Oval, Main Plaza, VIC Platform and Permanent Car Parks for the project for a contractual sum of RM5.2 million. For this purpose, the defendant issued letters of instruction dated 2.10.1999 for works up to RM1.5 million, 2.11.1999 for works up to RM1.2 million and 2.3.2000 to the plaintiff for works up to RM1.1 million. These letters of instructions, the Bill of Quantities, the working earthworks drawings and technical requirements formed part of the contract between the plaintiff and the defendant. The relevant contractual provisions are as follows:(i) The earthworks shall be carried out according to the design and specifications at the agreed rates in accordance to the working drawings and based on the submitted Bill of Quantities. 2 Alasan Penghakiman NO: 22-920-2001 (ii) Records of labour, plant and materials necessary to carry out these works will be maintained by the plaintiff. (iii) Invoices for work completed shall be submitted at the end of the working month and will be processed on a back to back basis with Setia Haruman. Issuance of payment shall be within 2 weeks of the defendant receiving the same from Setia Haruman. Pursuant to the award, the method to be used by the plaintiff in carrying out the earthworks was the ‘replacement method’. But soon after the plaintiff commenced work at the site, it was discovered that the ground condition of the site makes the replacement method ineffective. Parties therefore agreed that the method be changed to ‘displacement method’. Without going into the specifics of the actual work involved in these two methods, suffice it to state that they involved different work processes. The change of method was confirmed by a letter dated 25.11.1999 from the defendant’s consultant. The letter reads:“CYBERPARK DEVELOPMENT PHASE 1 - Subsoil Improvement Works for Road, Oval Roundabout and Carpark Areas We refer to the meeting held at PLB office on 24th November 1999 … and would like to confirm the following which was discussed and agreed:i) The current adopted method of displacing the peat with sand shall be used for the rest of the areas. 3 Alasan Penghakiman NO: 22-920-2001 ii) Suitable materials which were used for displacing peat below ground water table shall be removed and replaced with sand. iii) After completion of peat displacement, additional soil investigation shall be carried out to determine the actual improved ground condition. Surcharging will then be designed in order to comply with the allowable post-construction settlement. iv) Settlement plates and ground settlement markers shall be installed to monitor the settlements of the fill. Settlement rates shall reduce to an acceptable value before the surcharge fill above the formation level be removed and road pavement constructed. We would like to remind you to exercise great care in the filling works to avoid pockets of soft material/peat being trapped within the fill. We will amend the earthwork drawings based on the above.” THE EVIDENCE Insofar as the documents are concerned, parties agreed that the documents in Part B of the Bundle of Documents be admitted as evidence. The oral and documentary evidence led by the plaintiff shows the following:(i) that the Bill of Quantities provides for replacement method; (ii) that after the instruction to change the method in November 1999, the plaintiff carried out the earthworks using the displacement method; 4 Alasan Penghakiman NO: 22-920-2001 (iii) that the plaintiff submitted its claim no. 1 up to No. 6 to the defendant based on the rates in the Bill of Quantities; (iv) that the defendant had approved the claim and had made payments to the plaintiff back-to-back with the payment it received from Setia Haruman and had made part payment amounting to RM2,852,407.16 to the plaintiff; (v) that vide letters dated 8.6.2000 and 14.6.2000 the plaintiff informed the defendant that they have completed the whole works as instructed. (vi) that the plaintiff submitted claim No. 7 on 25.6.2000 and that the defendant did not protest or make any adjustment to the contents of this claim (see pg 112 B2); (vii) that a reminder on claim No. 7 was issued to the defendant dated 30.6.2000 (see pg 116 B2); (viii) that on 12.8.2000 the plaintiff wrote to the defendant confirming that parties agreed in a meeting that the final certificate would be prepared by 15.8.2000 based on the original Bill of Quantities; (ix) that on 7.9.2000 the defendant proposed the final claim in the sum of RM4,715,827.65. Of this amount, RM4,477,127.65 is for Bill No. 2 and RM240,000.00 for preliminary works. The plaintiff accepted the figure of RM4,477,127.65 but disputed the sum of RM240,000.00. 5 Alasan Penghakiman NO: 22-920-2001 (x) that by a letter dated 2.10.2000 the defendant agreed to increase the figure of RM240,000.00 to RM270,000.00. The plaintiff was not paid for claim No. 7, hence this suit. It is the plaintiff’s case that they had completed the contracted works in April 2000 in the value of RM4,747,127.65. Given that the defendant had made payment of RM2,852,407.16 the plaintiff contends that the amount of RM1,894,720.49 is still due and outstanding from the defendant. The defendant’s case is that the Bill of Quantities sets out a replacement method where the scope of work involves 3 steps i.e. excavation, backfilling and importing suitable material but the actual work done by the plaintiff through the displacement method involves only 2 steps; that by reason of the difference in methods, the quantity of filling material became different from that as set out in the Bill of Quantities; that the original Bill of Quantities based on the replacement method is no longer applicable; that the plaintiff’s claim for the balance of the contract sum amounting to RM1,894,720.49 based on the Bill of Quantities is erroneous and baseless. The defendant is counterclaiming against the plaintiff for the sum of RM42,000.00. The defendant alleged that due to the plaintiff’s defective work, a 3rd party contractor, Sungai Suasa Sdn Bhd was engaged to stabilize the soil and RM42,000.00 was the amount paid to Sungai Suasa. 6 Alasan Penghakiman NO: 22-920-2001 DW1, the defendant’s CEO testified among others that:- (i) the change of method was accepted by the defendant subject to re-measurement of the actual quantity of the work done in the final accounts stage after completion of the work; (ii) the defendant has received full payment from the client for the project on 3.11.2004 for the works as a whole; (iii) based on the methodology adopted by the plaintiff, the defendant had paid the plaintiff in accordance with the re-measurement of the work done pending the final accounts, but the final accounts stage was not reached due to this legal suit; (iv) to date the plaintiff is unable to satisfy the defendant as to the fair value of work done based on the displacement method. On the counterclaim, the evidence of DW1 is that the plaintiff has failed to perform the works in accordance with the terms and conditions of the contract; that the Consultant engaged by the defendant has not accepted some of the works which required subsequent rectification to stabilize the soil; that due to the plaintiff’s failure to carry out the rectification works, the plaintiff had to appoint the 3rd party contractor, Sungai Suasa Sdn Bhd to do the 7 Alasan Penghakiman NO: 22-920-2001 rectification work to stabilize the soil and that the defendant had paid Sungai Suasa the amount of RM42,000.00. An independent quantity surveyor (DW6) testified that the effect of the changes on the method rendered the rates in the Bill of Quantities no longer applicable. DW6 opines that the remeasurement and valuation of the plaintiff’s works has to be done by way of establishing the actual work physically carried out by the plaintiff on site and that in order to estimate the costs of the work carried out by the plaintiff, the plaintiff has to furnish the following information:- (i) The records of the number of lorry loads of sandy materials brought in; and (ii) The records of the heaved peat brought out. FINDINGS I do not think that there is any real issue on the agreed contractual terms in respect of the earthworks to be carried out by the plaintiff. The method and the rates have been set out and the mode of payment had been agreed. The main issue to be considered is whether the change in the method from replacement to displacement has rendered the Bill of Quantities inapplicable and consequently whether the plaintiff’s claim based on the Bill of Quantities is erroneous and incorrect. 8 Alasan Penghakiman NO: 22-920-2001 I agree with learned counsel for the defendant that the method of valuation of the works constructed based on the displacement method was not stated in any of the documents. However, having tested the oral testimony of the witnesses against the contemporaneous documents, I find that even after the change of the method, parties still conducted themselves according to the Bill of Quantities. Whether the Bill of Quantities is still applicable in light of the change of method of works from replacement to displacement Before going into this issue, it must be highlighted that there was no response from the defendant to the plaintiff’s letter informing the defendant about the completion of the work for the full contract value of RM5.2 million. On whether the Bill of Quantities is still applicable, vide a letter dated 12.8.2000, the plaintiff wrote to the defendant as follows:“CYBERPARK DEVELOPMENT – PHASE 1 Re: SITE CLEARANCE AND EARTHWORKS .. Final Certificate Reference to the above, it was agreed at the meeting in your office in the presence of Encik Mohamad Ariffin Karim, Encik Suhairi bin Ramly and Mr. Oh Boon Kuang that the Final Certificate would be prepared based on the original BQ by 15th August 2000.” 9 Alasan Penghakiman NO: 22-920-2001 The letter was acknowledged receipt by the defendant. There was no denial from the defendant of the meeting and of the agreement that the final certificate would be based on the original Bill of Quantities. The plaintiff again wrote to the defendant dated 7.9.2000 (addressed to DW1) stating:“CYBERPARK DEVELOPMENT – PHASE 1 - SITE CLEARANCE AND EARTHWORKS TO CYBERPARK, CYBERJAYA Re: Final Statement of Progress Claim Thank you for your fax on the proposed final claim amounting to RM4,715,827.65 (as per copy attached). We confirm our acceptance of Bill No. 2 amounting to RM4,477,127.65 but Bill No. 1 has deviated from the original tender which is not acceptable by us. Please be informed that we have arranged for a meeting with your office on Monday, 11th September 2000 at 3.00 pm to finalize the above and the schedule of payment.” DW1 in his evidence denied that he had faxed the proposed final claim amounting to RM4,715,827.65 to the plaintiff. Instead he said he had expected the plaintiff to send him the proposed final claim computed based on the displacement method. I find the evidence inherently improbable. 10 Alasan Penghakiman NO: 22-920-2001 If there wasn’t any proposal by the defendant, then the acceptance by the plaintiff is misplaced as the issue of acceptance does not arise. Yet, the defendant in their reply dated 2.10.2000 did not address the issue of Bill No. 2 amounting to RM4,477,127.65 by either denying any proposal on the final claim and/or dismissing the plaintiff’s acceptance on the ground that the same does not arise or that the plaintiff’s claim is erroneous or baseless (see Wong Hon Leong David v Noorazman bin Adnan [1995] 3 MLJ 283). This is how the defendant responded by their letter dated 2.10.2000:“CYBERPARK PHASE 1 SITE CLEARANCE AND EARTHWORK TO CYBERPARK, CYBERJAYA We refer to the discussion held in our office between your representatives and our representatives today in respect of the above captioned matter. Listed below are items agreed in the meeting:i) To allow the additional preliminaries from the original of RM240,000 to RM270,000.00 ii) For October 2000, Cypark is to undertake to pay M/S Chung Nyap Yoon Sdn Bhd the amount of RM500,000.00 if CNY could successfully secure payment of RM1.2 million from our client (M/S Setia Haruman Sdn Bhd) by 15/10/00. iii) After the month of October, the balance of the outstanding amount from the above will be paid RM150,000 a month until the amount is fully paid.” 11 Alasan Penghakiman NO: 22-920-2001 In respect of the above letter, DW1 said that it was an interim arrangement pending the submission of the proposed final claim by the plaintiff. The document does not support his position. His letter to the plaintiff categorically listed out the items agreed in the meeting without any qualification. Nowhere did he state in the letter dated 2.10.2000 that the agreement was subject to the submission of proposed final claim by the plaintiff or subject to re-measurement and/or that the plaintiff must provide records of lorry loads of sand poured in and the records of number of dump trucks used in connection with the disposal of the heaved peat. Neither did the defendant state that the work must be verified by a licensed land surveyor or quantity surveyor before the plaintiff can be paid. It must be noted that the subject of the plaintiff’s letter dated 7.9.2000 is the final statement of progress claim. The plaintiff had, vide the said letter requested for a meeting to “finalize the above and the schedule of payment” and the defendant’s letter dated 2.10.2000 referred to a meeting. It cannot be denied that item (i) in the defendant’s letter relates to Bill No. 1 in the plaintiff’s letter dated 7.9.2000 wherein vide the same letter the plaintiff has confirmed acceptance of Bill No. 2 amounting to RM4,477,127.65. There cannot be an acceptance by the plaintiff unless there was a proposal by the defendant. 12 Alasan Penghakiman NO: 22-920-2001 I respectfully echo Zulkefli Makinudin JCA (as his Lordship then was) in Fawziah Holdings Sdn Bhd v Metramac Corp Sdn Bhd [2006] 1 MLJ 505 where he said at page 537:“.. it is too late for the defendant to set the clock back. The law is clear that if parties to a contract had construed a contract as operating in a particular way and acted on it, they are both bound by the meaning they had given to the contract .” (See also Boustead Trading (1985) Sdn Bhd v ArabMalaysian Merchant Bank Bhd [1995] 3 MLJ 331). There is also the plaintiff’s letter dated 17.10.2000 to the defendant (which was acknowledged receipt by the defendant) which states among others:“We refer to your letter dated 2nd October 2000 concerning the discussion held in your office .. Your Encik Suhairi Bin Ramly has given the undertaking to release the Final Certificate to us by 4th October 2000 but to today, despite our numerous reminders, we are still waiting for the Certificate. You need to release the relevant documents to us so that we can help you to secure RM1.2 million from your Client, M/s Setia Haruman Sdn Bhd.” The plaintiff followed up with a letter dated 8.11.2000 (also acknowledged receipt by the defendant) stating as follows:- 13 Alasan Penghakiman NO: 22-920-2001 “CYBERPARK DEVELOPMENT – PHASE 1 Re: Final Certificate Referring to our letter …. and a further meeting in your office on 2 nd October 2000 on the above, we are still waiting for the Final Certificate which you had agreed to issue to us by 4th October 2000.” DW1 said that as far as he knows, the defendant did not give any undertaking to the plaintiff as to the release of the Final Certificate to the plaintiff by 4.10.2000. Again I find the testimony of DW1 inherently improbable. If indeed there was no undertaking to release the Final Certificate or that the contents of the plaintiff’s letter is not true, then it is reasonable to expect the defendant to deny the plaintiff’s letter. But there was no such response. In the circumstances I am not able to accept the defendant’s position that plaintiff’s claim No. 7 is only an estimate. The statement has been finalized by the parties hence the schedule of payment listed by the defendant. And given paragraphs (ii) and (iii) of the defendant’s letter dated 2.10.2000 setting out the mode of payment, I find that there had been an agreement on the amount to be paid to the plaintiff. This is a proper case where the defendant should be estopped from taking a different position from their earlier stand as shown by the documentary evidence. Having regard to all the above, I therefore find that the Bill of Quantities is still applicable despite the change of method. There is clear evidence that the total agreed sum of the plaintiff’s work is in the amount of RM4,747,127.65. This amount comprises of 14 Alasan Penghakiman NO: 22-920-2001 RM4,477,127.65 as proposed by the defendant and accepted by the plaintiff vide its letter dated 7.9.2000 and RM270,000.00 as agreed by the defendant vide its letter dated 2.10.2000. Taking into account the payment that has been received from the defendant in the sum of RM2,852,407.16, the plaintiff is entitled to be paid RM1,894,720.49, more so when the defendant has received full payment from Setia Haruman. Is the sum prematurely claimed in this suit? It is not specifically pleaded by the defendant that the plaintiff’s claim is premature. Vide paragraph 10 of the amended statement of defence and counterclaim, the defendant pleads “In addition, even if the Plaintiff’s claim is valid, which is denied, the obligation of the Defendant to pay the Plaintiff, which is also denied, only arises if the Defendant has been paid by the Client.” This issue on premature claim was raised by learned counsel for the defendant in his written submission after the trial. From the testimony of PW2, the Head of Legal and Corporate Services of Setia Haruman, the defendant’s client, it came to light that the defendant was paid for the earthworks on 30.4.2002 whilst the suit was filed in December 2001. It was thus the submission of learned counsel for the defendant that the plaintiff’s claim is premature and incompetent as the defendant is only obliged to pay the plaintiff if the defendant correspondingly receives the same from Setia Haruman. As at the date of filing of the writ, learned counsel argued, the cause of action has yet to accrue. Simetech (M) Sdn Bhd v Yeoh Cheng Liam Construction Sdn Bhd [1992] 1 MLJ 11; Pernas 15 Alasan Penghakiman NO: 22-920-2001 Otis Elevator Co Sdn Bhd v Syarikat Pembenaan Yeoh tiong Lay Sdn Bhd & Anor [2004] 5 CLJ 34 and AsiaPools (M) Sdn Bhd v IJM Construction Sdn Bhd [2010] 2 CLJ 28 were cited in support thereof. For the plaintiff it was submitted that the plaintiff did have a valid cause of action against the defendant as at the date of the commencement of this suit. Learned counsel referred to pg 64 of Bundle B6 which shows that the defendant has been paid in full by Setia Haruman on claim No. 7 on 12.9.2000 i.e. prior to the commencement of this suit and that pursuant to the back-to-back arrangement, the defendant ought to have paid the plaintiff 14 days after 12.9.2000. My view is that this defence of premature claim is not valid. Looking at the evidence, that the plaintiff’s claim is premature is not the reason why the defendant refuted the plaintiff’s claim. From the evidence, the reason for non-payment by the defendant is the issue of valuation. Even in the defendant’s solicitors’ letter dated 2.2.2001 replying to the plaintiff’s letter of demand, there was no issue that the defendant’s obligation to pay has not arisen under the back-toback agreement. The defendant’s counterclaim Besides the bare statement of DW1, there is not a single document to support his testimony that the Consultant has not accepted some of the works of the plaintiff; that the plaintiff has 16 Alasan Penghakiman NO: 22-920-2001 been asked to and has failed to do the rectification works and that Sungai Suasa was engaged by the defendant to do the rectification works. The defendant sought to rely on a letter of award dated 16.11.2001 to Sungai Suasa to show the appointment of Sungai Suasa for the soil stabilization works. The letter of appointment was for main bridge and piled embankment. It makes no reference to rectification works or soil stabilization as alleged. Absent any proof of rectification works done by Sungai Suasa, I find that the defendant has failed to prove its counterclaim. To conclude, judgment is entered against the defendant for RM1,894,720.49 with interest at the rate of 4% per annum from the date of judgment until realization and costs. The defendant’s counterclaim is dismissed with costs. (DATO’ TENGKU MAIMUN BINTI TUAN MAT) HAKIM MAHKAMAH TINGGI MALAYA BAHAGIAN SIVIL SHAH ALAM Dated 10th January 2012 17 Alasan Penghakiman NO: 22-920-2001 Cik Soo San San bersama Cik Elaine Gan bagi pihak Plaintif Tetuan Paul Ong & Associates Peguambela dan Peguamcara Unit No. B-2-8, Blok B Tingkat 2 Megan Avenue 1 No. 189 Jalan Tun Razak 50400 Kuala Lumpur. Encik Lim Chong Fong bersma Cik Karen Ng Yueh Ying bagi pihak Defendan Tetuan Azman Davidson & Co. Peguambela dan Peguamcara Suite 13.03, Tingkat 13 Menara Tan & Tan 207 Jalan Tun Razak 50400 Kuala Lumpur. 18