AFFORDABILITY MANAGEMENT ASSESSMENT Objective The objective of the Affordability Management Assessment is to offer a standardized approach that promotes Affordability Management excellence in an organization. The process is to identify specific areas (tenets) of Affordability Management to be measured, and then to compare performance in these areas against established qualitative criteria. This process determines the level of achievement of Affordability Management excellence. This single set of 20 tenets facilitates an assessment of the level of Affordability Management excellence at both the program and the enterprise levels. All of these principles apply to programs, and approximately half apply to the enterprise. Unique applications of tenets common to both the program and the enterprise are identified in the descriptions of the levels of achievement to be attained. The objective of a program-level Affordability Management assessment is to measure the extent to which a given program is implementing the Affordability Management Tenets. Specific implementation is tailored to meet customer and stakeholder requirements. The objective of an enterprise-level Affordability Management assessment is to measure the extent to which the enterprise supports its programs in implementing the Affordability Management Tenets across the enterprise. Programs that are deemed highly effective in selected areas can serve as models for programs that struggle in these same areas. The ultimate goal is improved performance across the enterprise. Definition Each of the 20 tenets (see Appendix A) has five rating levels (Level 1 to Level 5) representing increasing capabilities with respect to the tenet. The ultimate goal is to achieve a Level 5 in each of the 20 tenets. Characteristics of each level are written in general terms and are shown conceptually in Figure 1. Every program or enterprise is able to claim credit for Level 1. On a scorecard (see Table 1), achievement of a Level 1 in all 20 tenets is worth 20 points with a score of 100 representing total and complete Affordability Management excellence in all tenets. In other words, 20 points are awarded for process participation (20 tenets * Level 1). As capabilities mature, scores increase. Although the approach described here has yet to be used, the current judgment is that, using by systematic improvement efforts, low initial scores can improve at the rate of twenty points per year while higher scores at the rate of ten points per year until further improvement is deemed not value added. Therefore, improvement only comes with concentrated effort. The methodology whereby assessments are made and improvement planning occurs is covered in the following sections. 1 Level Level Characteristics 5 Seamless, transparent excellence, automatic, so good it’s hard to believe it could happen 4 World--class, outstanding, not quite always automatic, little management action required 3 Systems installed to ensure very good performance with an occasional glitch (sometimes serious) 2 Awareness established of what good is, first small steps taken, still many big problems 1 The usual mess, traditional management by direction, reactive, few or bad systems, many problems, most accepted as “oh, well....” Figure 1: Affordability Management Tenet Level Characteristics 2 Table 0: Affordability Management Tenet Scorecard Tenet # Title 1 Understanding the Customer/User 2 PTW Process and Technical Approach Level 1 (1 Point) 3 Requirements Flexibility 4 KPPs and Requirements 5 Cost of Requirements 6 Cost Drivers 7 Cost Targets 8 Architecture and Cost Baselines 9 Subcontractor Involvement 10 Rewards 11 Continuous Cost Reduction 12 Life Cycle Costs and the Trade Process 13 Cost Database and Its Usage 14 Parametric Cost Models 15 Constraint /Risk Identification and Management 16 Integrated Tools 17 Trade Study Levels 18 Selection and Optimization 19 Cost Reviews 20 Affordability Measures Total Score (100 Points Maximum) > 3 Level 2 (2 Points) Level 3 (3 Points) Level 4 (4 Points) Level 5 (5 Points) Charting the status of progress toward attaining excellence in Affordability Management in all 20 tenets brings to focus areas needing attention in order to achieve the improvement goals. Capturing the status on a chart similar to that shown in Figure 2 illustrates which of the 20 tenets requires more attention. Note that small improvements in many principles achieve greater over-all ratings over a shorter time period than do fewer improvements in more difficult areas. Current stages of improvement can be plotted to show how planned improvement is progressing toward the original goals. Figure 2: Affordability Management Tenet Status Chart 4 Methodology Overall Description The process by which improvement occurs relies on the power of the Affordability Management Tenets methodology to identify the areas that must be improved by unifying, combining and integrating all implementation activities under a single umbrella. All levels of the organization are given one scorecard (Table 1) that is easy to understand. Every unit (e.g. group, area, office, or cell) is allowed to develop its own action plan for Affordability Management improvement, and everyone is encouraged to be involved and active. Long-term management involvement and support is required. The planning and action cycle to apply the Affordability Management Tenets is illustrated in Figure 3. A 15-to-30 minute orientation session is held with each work group (unit). Each work group then assesses its status. Enterprise leaders, department managers, and program managers then set long-term (3 to 4 years) point goals that every unit must meet. Each unit selects the tenets and levels on which it will focus during a specified time. Under the guidance of a supervisor, each unit develops an action plan for attaining each additional point. Enterprise leaders, department managers, and program managers conduct periodic audits and visits to congratulate and to coach. This approach can be adjusted as needed, and eventually, improvement is ingrained in the units. 5 The 20 Tenet Planning Cycle …and Prioritize Our 20 Tenets 1. Understanding the Customer/User 2. PTW Process and Technical Approach 3. Requirements Flexibility 4. KPPs and Requirements 5. Cost of Requirements 6. Cost Drivers 7. Cost Targets 8. Architecture and Cost Baselines 9. Subcontractor Involvement 10. Rewards 11. Continuous Cost Reductions 12. Life Cycle Costs and the Trade Process 13. Cost Database and It’s Usage ….. Figure 3: The Affordability Management Tenet Application Cycle Specific Measures for Affordability Management Excellence A complete definition table, outlining the steps to Affordability Management excellence, is provided in Appendix A. Initial and follow-on capability assessments are made against the description for each tenet. An example of the application of this approach for one of the 20 Affordability Management Tenets, Integrated Tools, is shown in Figure 4. 6 Tenet #16 Figure 4: Example - Affordability Management Tenet Level Definitions Organizational Roles Evaluation Process Organizational Roles The Affordability Management Tenet evaluation process needs firm commitments from senior-level management to ensure the assessment process addresses both the enterprise and its programs. This may include the designation of an overall Affordability Management Tenets application process manager and/or focus team. Beyond the top-down focus, functional and program management need to ensure that commitments are made to support the Affordability Management Tenets assessment effort. The functional areas expected to be involved in leading Affordability Management Tenets assessments and process improvements are systems engineering, product development, cost estimating, business development, subcontract management and information technologies. Within a program, the systems engineers and cost analysts may lead the Affordability Management Tenets assessments and process improvement recommendations. Evaluation Organizational Roles A team, consisting of management and functional personnel, perform the Affordability Management Tenets assessments. A notional sharing of responsibility for this assessment is illustrated in Table 2. 7 This sharing can be augmented by other enterprise, functional and program personnel as necessary. There is a direct correlation between the commitment that is made by management to this approach and the improvement associated with the application of the Affordability Management Tenets methodology. Tenet # 1 2 Title Lead Support Understanding the Customer/User PTW Process and Technical Approach Program Management Business Development, Systems Engineering, Cost Estimating Program Management, Systems Engineering, Product Development, Cost Estimating Business Development (PTW) Systems Engineering (Technical Approach) Systems Engineering Systems Engineering Systems Engineering Cost Estimating Enterprise Management 3 4 5 6 7 Requirements Flexibility KPPs and Requirements Cost of Requirements Cost Drivers Cost Targets 8 Architecture and Cost Baselines 9 Subcontractor Involvement Systems Engineering, Cost Estimating Subcontract Management 10 11 Rewards Continuous Cost Reduction Enterprise Management Program Management 12 Enterprise Management 16 Life Cycle Costs and the Trade Process Cost Database and Its Usage Parametric Cost Models Constraint/Risk Identification and Management Integrated Tools 17 18 Trade Study Levels Selection and Optimization Systems Engineering Systems Engineering 19 Cost Reviews Enterprise Management 20 Affordability Measures Enterprise Management 13 14 15 Cost Estimating Cost Estimating Program Management Enterprise Management Program Management, Enterprise Management Program Management, Business Development Cost Estimating Systems Engineering, Product Development Business Development, Program Management, Cost Estimating Program Management Program Management, Systems Engineering, Cost Estimating Program Management Systems Engineering, Cost Estimating, Product Development Systems Engineering, Cost Estimating, Product Development Enterprise Management Information Technologies Systems Engineering, Cost Estimating, Product Development Systems Engineering, Cost Estimating, Information Technologies Product Development Product Development, Cost Estimating, Information Technologies Program Management, Systems Engineering, Cost Estimating Program Management, Systems Engineering, Cost Estimating Table 2: Affordability Management Tenets Assessment Organizational Roles 8 Improvement Plan Development In defining a plan, the first step is to establish the long-range goals as shown in Figure 2 and the total number of years for implementation. From this the average number of points to be earned annually in order to achieve the improvement goals can be calculated. Average Annual Pts/Year = points assigned to goal – points assigned to current status Year n n = year of plan, in which goal to be attained - i.e. 1, 2, 3, etc. Sorting the 20 tenets by Average Annual Points/Year, from high to low, places tenets where great strides might be made in relatively short periods of time at the top of the list. Focusing on the tenet at the top of this list, early in the plan, results in rapid advancement in goal attainment ratings. For each tenet, a formal plan should be developed which shows the tasks to be completed, the timeline for completion, and the person(s) responsible for task completion. An example of a plan to improve Tenet 9 – Subcontractor Involvement, is shown in Figure 5. This plan delineates the specific activities, by weeks, which are required to improve the tenet level assessment rating within the schedule constraints. TTenet enet 99 Figure 5: Example - Affordability Management Tenet Improvement Plan Controls and Reviews Each enterprise establishes its own approach to controls and reviews for the assessment and improvement utilizing the Affordability Management Tenets. This process, as explained earlier, takes 3 to 5 years to advance 50 to 60 points, even with aggressive, organized efforts. Initially monthly, bimonthly, or quarterly reviews may be required. Once the improvement process is established, semi-annual re9 views may suffice. Whatever schedule of review is adopted, it is incumbent upon enterprise management to be the driving force in seeing that improvement occurs. Enterprise management should expect both functional management and program management to report at the Affordability Management Tenets Improvement Reviews. An incentive program commensurate with goal achievement may maintain the impetus for the improvement process. Award criteria may include goal attainment ahead of schedule. 10 Appendix A Affordability Management Tenet Definition Table Tenet Number 1 Title Level 1 Level 2 Level 3 Level 4 Level 5 Understanding the Customer/User Understanding of customer/user values and needs is derived from program documentation (e.g., ORD, O&O, SOO, spec, etc). Contact is encouraged to clarify these documents. Understanding of customer/user values and needs is derived from program documentation and minimal interaction with customer program acquisition personnel. No direct contact with users results in a basic understanding of program needs. Understanding of customer/user values and needs is derived from program documentation, interaction with customer program acquisition personnel and some contact with users. Project team has solid understanding of the customer's program acquisition values and a good understanding of users' needs. Understanding of customer/user values and needs is derived from program documentation and significant interaction with customer program acquisition personnel and users. Project team understands all customer/user values and needs. Project team also has basic understanding of external elements influencing the program (e.g., political, international, system-of-systems view). Project team has examined, defined and fully understands customer/user values and needs. All customers, users, and external influences have been identified and were engaged early in the project process. Project team and customer interaction has resulted in beneficial adjustments to the program prior to acquisition. 11 Tenet Number 2 Title Level 1 Level 2 Level 3 Level 4 Level 5 PTW Process and Technical Approach Business Development is solely responsible for developing the PTW based on market analyses, perceived customer funding and desires, and product familiarity. Minimal contact occurs with the technical staff prior to actual proposal writing. A multi-functional team led by Business Development prepares the PTW based on market analyses, perceived customer funding and desires, and product familiarity. Resources are in place for engineering and cost analysts to become involved pre-proposal to fine-tune the PTW. A multi-functional team led by Business Development prepares the PTW based on market analyses, perceived customer funding and desires, product familiarity and cost iterations. Resources are in place for engineering and cost analysts to iterate toward the PTW value preproposal. The technical approach is validated by engineering pre-proposal. A multi-functional team led by Business Development prepares the PTW based on market analyses, perceived customer funding and desires, product familiarity and cost iterations. Resources are in place for engineering and cost analysts to iterate toward the PTW value preproposal. The technical approach is validated by engineering pre-proposal. Risk and sensitivity analyses are included to identify potential pitfalls associated with decisions and the threshold of bid/nobid. A multi-functional team led by Business Development prepares the PTW based on market analyses, perceived customer funding and desires, product familiarity and cost iterations. The market analysis includes extensive studies to understand the goodness of competitors’ capabilities. Resources are in place for engineering and cost analysts to iterate toward the PTW value preproposal. The technical approach is validated by engineering pre-proposal. Risk and sensitivity analyses are included to identify potential pitfalls associated with decisions and the threshold of bid/nobid. 12 Tenet Number 3 Title Level 1 Level 2 Level 3 Level 4 Level 5 Requirements Flexibility Requirements are met during the execution of a program. While some may be shown to cause cost growth, there is not a documented procedure for challenging the requirement(s). The enterprise leads program managers to satisfy customer/user at all times. A plan to develop the process to define notional "threshold" and "goal" values for requirements (as appropriate) is formulated. Dialogue is occurring between program management and the customer/user to enter into requirements tailoring based on costperformance trade studies that address cost drivers (Tenet 6). Customer/user reluctance to relax requirements is noted. The process to define notional "threshold" and "goal" values for requirements (as appropriate) is being applied to a limited extent. Dialogue is encouraged (although not required) between program management and the customer / user to enter into requirements tailoring based on costperformance trade studies that address cost drivers (Tenet 6). Enterprise rewards program managers for surfacing requirements change to customer/user. Customer/user reluctance to relax requirements is noted. The process to define notional "threshold" and "goal" values for requirements (as appropriate) is being applied across all programs. Dialogue is required between program management and the customer/user to enter into requirements tailoring based on costperformance trade studies that address the cost drivers (Tenet 6). Enterprise rewards program managers for surfacing requirements change to customer/user. Customer/user reluctance to relax requirements is strongly challenged. Customer and user establish "threshold" and "goal" values to allow identification of optimal alternatives. Customer, user and contractor actively discuss and relax requirements based on sound trade studies. Enterprise rewards program managers for successful requirements change that have been surfaced to customer / user. 13 Tenet Number 4 Title Level 1 Level 2 Level 3 Level 4 Level 5 KPPs and Requirements Customer and user are aware of performance specification guidance (MIL-STD-967) to minimize numbers of KPPs and fixed constraints. A plan to identify overly constrained problems that may provide insight into overly constrained requirements and excessive KPPs is formulated. The optimal solution approach of reducing the numbers of constraints is introduced to the customer on a case–by- case basis. Customer/user is encouraged to consider and reveal to the subcontractor what may be unwritten absolute, rigid requirements The plan to identify overly constrained problems that may provide insight into overly constrained requirements and excessive KPPs is applied to a limited extent. Costs of requirements are beginning to be calculated and the benefits in the optimal solution approach can be shown. Customer/user is expected to consider and reveal to the contractor what may be unwritten absolute, rigid requirements and show a willingness to limit these. The plan to identify overly constrained problems that may provide insight into overly constrained requirements and excessive KPPs is applied across all programs. Costs of requirements are calculated for the most part and the benefits of the optimal solution approach are clearly explained. Customer/user is engaged in limiting unchangeable, fixed constraints, including those that may be unwritten. Customer, user and contractor are actively engaged in limiting numbers of KPPs and fixed constraints to allow best opportunity for optimal solution. Cost of requirements is available for consideration by the team. 14 Tenet Number Title Level 1 Level 2 Level 3 Level 4 Level 5 5 Cost of Requirements Cost and requirements are managed to the subsystem level. However, no attempt is made to map the two and prioritization for cost is not done. Cost and requirements are allocated to a common level and mapped to the program WBS. Cost and requirements are allocated to a common level and mapped to the program WBS. Cost of requirements is determined and used to prioritize requirements for cost. Prioritized cost of requirements is used as a tool to separate true requirements versus “desirements” and to optimize solutions at the system (not subsystem) level. Prioritized cost of requirements is used to establish firm requirements and to minimize implementation of “desirements”. Lessons learned and insights are provided to the enterprise. The enterprise facilitates use of these findings on other programs. 6 Cost Drivers Identification of cost drivers occurs during program execution. However, the interdependency of cost and requirements is not clearly known or quantified. Cost drivers are quantified and ranked (prioritized). Sensitivity analyses are performed to determine relative cost sensitivity of the driving requirement, technology, and schedule. Cost drivers identified early. Cost influences tied to requirements, technology, and schedule as appropriate. Risk identified and managed based on identified interdependencies. Cost drivers identified early. Cost influences are quantified. Risk mitigation and opportunity strategies are identified. Program resources are tailored to best balance technical, cost, schedule, and risk mitigation requirements. Cost drivers identified early. Cost influences are quantified. Risk mitigation and opportunity strategies are identified. Resources are adequately applied. Lessons learned and insights are provided to the enterprise for benefit to other programs. 15 Tenet Number Title Level 1 Level 2 Level 3 Level 4 Level 5 7 Cost Targets Costs are arbitrarily set at the system and major subsystem level. No feedback from IPTs to validate cost targets. Design trade studies quantify system and major subsystem costs during product development. Program management adjusts funding between IPTs using an "equal pain" approach to meet targets, and uses the management reserve as a last measure to meet funding shortfalls. Costs are set at the system and major subsystem level using data from a cost database. No feedback from IPTs to validate cost targets. Program management establishes measures to track costs. Design trade studies quantify system and major subsystem costs during product development. Program management uses measures to adjust funding between IPTs to meet targets, and uses the management reserve as a last measure to meet funding shortfalls. Costs are set at the system and major subsystem level using data from a cost database. IPTs validate cost targets with bottom-up feedback. Program management establishes measures to track costs. Design trade studies quantify system and major subsystem costs during product development. Program management uses measures to adjust funding between IPTs to meet targets, and uses the management reserve as a last measure to meet funding shortfalls. Costs are set at the system and major subsystem level using data from a cost database. IPTs validate cost targets with bottom-up feedback. Program management establishes measures to track costs. IPTs work within an assigned "trade space" to develop products. Design trade studies quantify system and major subsystem costs during product development. Program management uses measures to adjust funding between IPTs to meet targets only when an IPT has exhausted an assigned trade space without developing a viable product. Program management uses the management reserve as a last measure to meet funding shortfalls. Aggressive target costs are set prior to or during proposal phase. Cost targets carry over into contract execution. Cost targets are allocated to the lowest level. Cost targets provide framework for design tradeoffs. Cost targets are clearly owned at an appropriate level of the organization. Reasonableness of target costs is measured against cost database and program definition parameters. Current cost baseline clearly visible to appropriate program personnel. Cost targets and current assessments tracked on a regular basis. 16 Tenet Number 8 Title Level 1 Level 2 Level 3 Level 4 Level 5 Architecture and Cost Baselines Cost baselines are established using a few techniques but may vary from program to program. The enterprise does not provide process or procedural guidance. Cost baselines development processes are well documented in standard procedures. Multiple baselines development techniques are established and provided by the enterprise. Cost baseline is reviewed by the enterprise when completed. Feedback loops are established between the reviewers and the baseline creators. Cost Baseline development training is provided by the enterprise for all program managers. Cost baseline development templates are provided by the enterprise. Tools/models are evaluated and provided by the enterprise. Customer requirements are compared the cost baseline. As a matter of practice, cost baselines are established early in a program's life cycle (preproposal) and reflect a convergence of top-down and bottom-up estimating techniques. Most probable cost based on multiples of estimates is also used. Reconciliation involves assumptions, risks and areas to be explored for future cost reduction activities. The cost baseline is cascaded from top-level targets to lower sub-tiers mapping to the WBS and maintains traceability to the WBS, MEL, organization and structure for the program. Enterprise cost modeling and estimating toolset supports all cost baseline needs. 17 Tenet Number 9 Title Level 1 Level 2 Level 3 Level 4 Level 5 Subcontractor Involvement Subcontractors are allocated cost and performance targets. Design engineers and subcontract management see that these targets are being met during the execution of the subcontract. Subcontractors are allocated cost and performance targets using a cost and performance database. Subcontractors validate cost and performance targets prior to buy-in. Design engineers and subcontract management see that these targets are being met during the execution of the subcontract. Subcontractors are allocated cost and performance targets using a cost and performance database. Subcontractors validate cost and performance targets prior to buy-in. Program management and subcontractor management establish measures to track targets. Design engineers and subcontract management see that these targets are being met during the execution of the subcontract. Subcontractors are allocated cost and performance targets using a cost and performance database. Subcontractors validate cost and performance targets prior to buy-in. Program management and subcontractor management establish measures to track targets. Design engineers and subcontract management see that these targets are being met during the execution of the subcontract. Subcontractors are active participants during program reviews. Subcontractors are integral to the Affordability Management Process. Subcontractors are allocated cost and performance targets using a cost and performance database. Subcontractors validate cost and performance targets prior to buy-in. Program management and subcontractor management establish measures to track targets. Design engineers and subcontract management see that these targets are being met during the execution of the subcontract. Subcontractors are active participants during program reviews. 18 Tenet Number Title Level 1 Level 2 Level 3 Level 4 Level 5 10 Rewards Rewards are based solely on the enterprise’s normal reward system that recognizes outstanding individual and team effort. Individual programs within an enterprise establish a rewards program that is extended beyond the normal enterprise reward system to account for implementation of “best value” solutions within the bounds of affordability. Individual and team awards are available. Best features of individual programs’ reward program institutionalized at enterprise level to reward employees and subcontractors for implemented “best value” solutions within bounds of affordability. Individual and team awards are available. Reward program institutionalized at enterprise level to reward employees and subcontractors for implemented “best value” solutions within bounds of affordability. Individual and team rewards are available. Customer and user are encouraged to recognize and reward their participants in programs. Reward program institutionalized at enterprise level to reward employees and subcontractors for implemented “best value” solutions within bounds of affordability. Freely contributed suggestions and/or ideas are eligible for some lower level reward. Individual and team rewards are available. Customer and user actively participate in the rewards program through appropriate means. 19 Tenet Number 11 Title Level 1 Level 2 Level 3 Level 4 Level 5 Continuous Cost Reduction Continuous cost reduction suggestions and ideas occur on a random basis. Continuous cost reduction suggestions and ideas are encouraged through Design to Value (DTV) training. On a subset of enterprise programs, continuous cost reduction suggestions and ideas are expected of program personnel on a regular basis. Some program-specific reward program may be in place. On most of an enterprise’s programs, continuous cost reduction suggestions and ideas are expected of program personnel on a regular basis. The enterprise has instituted a rewards program from the best features of program-specific rewards programs (Tenet 10). Continuous cost reduction is an in-bred practice in the enterprise. Less expensive ways to accomplish customer or user requirements are regularly recommended and implemented. The enterprise has a program that rewards suggestions and ideas (Tenet10). 20 Tenet Number 12 Title Level 1 Level 2 Level 3 Level 4 Level 5 Life Cycle Costs and the Trade Process Ad hoc trade studies are performed but there is neither a standard process nor a method of assigning responsibility. A process for performing trade studies is standardized and documented at the program level. Trade studies are conducted on a program-by-program basis. Responsibility is assigned and studies are managed at the program level. A standardized trade study process is defined and managed at the enterprise level. The standardized process can be tailored from the enterprise set of standard practices for each program under guidelines specified within the process. Deviations beyond those allowed by tailoring guidelines are documented, justified, reviewed and approved. Measures are assigned to the standardized trade study process such that adherence to the enterprise process is measured. Measures can consist of the number of trade studies performed on a program, the number of options considered in each trade, cost avoidance realized resulting from each trade, cost performance index (CPI) and schedule performance index (SPI) trend analysis, etc. Programs are quantitatively measured and statistics are logged for program design/cost/schedule influence. Standard procedure for trade study management is in place and expected to be followed. Costperformance trade study approach is part of the design process training. Standard trade study formats, derived from standard procedure, are followed within each program. Oversight of the trade study process is assigned at the enterprise level, along with the keeping measures for all programs. The measures are analyzed at the enterprise level, and fed back to the programs for optimization of the trade study process. An enterprise repository of trade study findings is available for the benefit of all programs. 21 Tenet Number 13 Title Level 1 Level 2 Level 3 Level 4 Level 5 Cost Database and Its Usage Historical cost data are available but difficult to find and use. Greater use is made of parametric and program unique data. The enterprise has not assigned historical cost data maintenance. In each program, the WBS has been crafted to allow easy accumulation of labor cost and purchased product cost data. Labor cost and purchased cost data are electronically available from labor charging system and can be parsed and imported into simple office automation software. The enterprise has assigned historical cost data planning and collection to a single functional organization. Programs continue to use the WBS to accumulate and make cost data available electronically. The enterprise-assigned functional organization has defined requirements for an historical cost database and requirements for kinds of costs and effort measures that will be tracked. A plan is in place for improving industry-wide parametric cost models with enterpriseunique data and factors. Programs continue to use the WBS to accumulate and make cost data available electronically. Effort has expanded to capture program costs across all phases. Enterprise-wide, parametric cost models have been customized and calibrated to reflect program actuals, rather than industry averages. The enterprise-wide functional organization has developed a plan for maintaining currency. Enterprise historical cost data is used to develop bottom-up cost estimates. The historical database is continuously expanded. The enterprise-assigned functional organization creates, maps, updates and disseminates historical cost data. 22 Tenet Number 14 Title Level 1 Level 2 Level 3 Level 4 Level 5 Parametric Cost Models Commercial parametric cost modeling and estimating tools are used to generate cost estimates. Within the enterprise, each program is allowed to choose its own tools without toolset standardization. Parametric cost models are used to generate program costs. The company’s historical cost database is used to calibrate the program cost estimates. Parametric cost models are used to generate program costs. The company’s historical cost database is used to calibrate the program cost estimates. Supplemental modeling and estimating tools are developed to enable faster, more accurate estimates. Tools are shared among more than one program, but not enterprise-wide. Parametric cost modeling and estimating is an integral part of every program. The company's historical cost data and CERs are integrated with CERs derived from parametric estimates through cost modeling and estimating tools. An enterprise-wide toolset is in place and used on every program. Parametric cost modeling and estimating is an integral part of every program. The company's historical cost data and CERs are integrated with CERs derived from parametric estimates through cost modeling and estimating tools. An enterprise-wide toolset is in place and used on every program. Lessons learned and insights are provided to the enterprise for benefit to other programs and future enhancements and improvements. 23 Tenet Number 15 Title Level 1 Level 2 Level 3 Level 4 Level 5 Constraint /Risk Identification and Management Risk identification and management are applied to programs according to enterprise standard procedures. Constraints are identified and managed as appropriate. Risk and constraint identification and management are extended beyond the enterprise standard procedures to address surfacing optimal solutions. However, risk minimization remains program focus. Risk and constraint identification and management are an integral part of cost-performance trades. Acceptance of manageable risk may occur on a case-by-case basis. Risk and constraint identification and management are an integral part of cost-performance trades. Acceptance of manageable risk may occur on a case-by-case basis. Risk tolerance guidance is beginning to surface in the enterprise’s program leadership training. Risk and constraint identification and management are an integral part of cost-performance trades. Acceptance of manageable risk occurs on all programs to enable costeffective solutions. Risk tolerance guidance is a critical element of the enterprise’s program leadership training. 24 Tenet Number Title Level 1 Level 2 Level 3 Level 4 Level 5 16 Integrated Tools Cost modeling and estimating tools and requirements management tools are used. However, they are not electronically linked. Tools for performing cost modeling and estimating and requirements management remain at Level 1 maturity. However, a plan now exists for integrating these tools that will eventually achieve Level 5 maturity, including requirements and specifications for interfacing the disparate cost modeling and estimating tools. The enterprise has begun to execute the plan for creating a suite of integrated cost modeling and estimating tools with the requirements management tools. Requirements and interface specifications, defined during Level 2, are agreed upon and complete, and integration of some of the more easily integrated tools has entered the verification phase. Some of the more easily integrated tools are now executing in a cooperative manner thus proving the integration concept defined during Level 2. Some programs have begun to use the toolsets. Integration of cost modeling and estimating tools with the requirements management tools continues with about 50% of the tools now executing cooperatively and exchanging data in a seamless manner. All programs are using the toolset to a degree commensurate with need. Cost modeling and estimating tools tightly integrated with requirements management tools. Enterprise has provided the linkage, preferably electronically. All programs use the common toolset. 25 Tenet Number 17 Title Level 1 Level 2 Level 3 Level 4 Level 5 Trade Study Levels Trade studies are performed at the lowest level of design implementation/component selection. A methodology for system-level trades is rudimentary at best, perhaps done by system level simulations. A plan to develop a system level trade study process, optimizing the results of subsystem and component trade studies and selections, has been formulated. The enterprise continually monitors industry trends such that no levels of trade study are plagued by obsolescence issues. The level of trade studies is determined at the program level. The process of conducting trade studies to achieve subsystem optimization is standard throughout the organization. The enterprise plan to conduct trade studies such that system designs are optimized at all levels has been initiated. Some pilot programs have begun the process of conducting trade studies from the lowest to the highest level, then refining the result to achieve the best value at the system level. The enterprise has documented the methodology of employing trade studies at all levels. Measures are applied to the trade study levels such that programs can quantitatively assess the difference between a rolled up subsystem trade result and optimization among subsystems, for system level optimization. Measures can include the number of subsystems being studied, the time needed (cost) to conduct the various levels of trade, the number of options considered at each level of trade, cost avoidance achieved by identifying the best value system, etc. Trade study methodology, measures and results are documented by the program. Trade studies are conducted at all levels of the system from the system level down to the lowest level where trade studies are realizable. Systemlevel trade study methodology is deployed by the enterprise. Responsibility for ensuring uniform application of the systemlevel trade study methodology, along with maintaining a central repository of methodology, measures and trade results is assigned at the enterprise level. Results of trade study level activity is made generally available, and fed back to the programs for optimization of the process. 26 Tenet Number 18 Title Level 1 Level 2 Level 3 Level 4 Level 5 Selection and Optimization Selection and optimization of a system is performed at the subsystem level. The system reflects a "roll up" of the subsystems that meet allocated costs and requirements. Costs, performance, schedule and risk are monitored on a regular basis. A plan to develop a system selection and optimization methodology that balances cost, performance, schedule and risk has been formulated. A procedure to direct the tradeoff process that assesses multiple, interrelated factors and determines their impact on affordability and LCC has been initiated. Costs, performance, schedule and risk continue to be monitored and applied to developing utility factors, as appropriate. The plan to develop a system selection and optimization methodology that balances cost, performance, schedule and risk has been initiated and is being practiced to a limited extent on pilot programs. A procedure to direct the tradeoff process that assesses multiple, interrelated factors and determines their impact on affordability and LCC has been completed and documented. Costs, performance, schedule and risk continue to be monitored and applied to developing utility factors, as appropriate, for system optimization. The plan to develop a system selection and optimization methodology that balances cost, performance, schedule and risk is complete and applied to most programs. The tradeoff process that assesses multiple, interrelated factors and determines their impact on affordability and LCC is defined and documented in enterprise procedures. Costs, performance, schedule and risk continue to be monitored and applied to developing utility factors and weighting factors, as appropriate, for system optimization. A system selection and optimization methodology that balances cost, performance, schedule and risk has been developed and is applied to every program. The tradeoff process that assesses multiple, interrelated factors and determines their impact on affordability and LCC is defined and documented in enterprise procedures. Utility functions and weighting factors are used to optimize the system in this process based on collected costs, performance, schedule, and risk data. 27 Tenet Number Title Level 1 Level 2 Level 3 Level 4 Level 5 19 Cost Reviews Cost reviews occur at the program level in conjunction with normal program review events and are usually "statusing" events. Enterprise review of costs occurs for programs with cost "problems". Cost reviews occur at the program level in conjunction with normal program review events and are detail-oriented events. Enterprise review of costs occurs for programs with cost "problems". A dedicated cost control person is assigned to the program. Enterprise and programlevel cost reviews are required at regularly scheduled intervals beyond the normal program reviews. Updates are required on a weekly or biweekly basis. A dedicated cost control person is assigned to all programs. Enterprise and programlevel cost reviews are required at regularly scheduled intervals beyond the normal program reviews. Updates are required on a weekly or biweekly basis. A dedicated cost control person is assigned to all programs. Cost containment plans for out-of-tolerance cost items are required. Cost review procedures policies are well documented and included in the program manager’s guide. Earned Value Management systems are established to facilitate the cost review process. Enterprise and programlevel cost reviews are required on a weekly basis for all programs including IR&D and company-funded activities. For programs with an IPT structure, cost issues are regularly addressed at IPT meetings. Cost control persons are assigned to all programs and IPTs within programs. Cost containment plans for out-of-tolerance cost items are required. Cost review procedures policies are well documented and included in the program manager’s guide. Earned Value Management systems are established to facilitate the cost review process. Subcontractors are included in program/IPT cost reviews. 28 Tenet Number 20 Title Level 1 Level 2 Level 3 Level 4 Level 5 Affordability Measures Performance, cost, schedule and risk are tracked program by program but no standard exists by which to quantify and measure them. No automated tools are used to track these parameters. Performance, cost, schedule and risk are tracked program by program. Standards are developed to establish a common format. No automated tools are used to track data. Key performance, cost, schedule and risk parameters are selected and tracked program by program. Standards are developed to establish a common format. No automated tools are used to track data. Key performance, cost, schedule and risk parameters are selected and tracked program by program. Standards are developed to establish a common format. Automated tools are used to track data. A standard procedure for identifying and tracking Affordability measures is in place. Key performance, cost, schedule and risk parameters are selected and tracked program by program. Standards are developed to establish a common format. Automated tools are used to track data. 29 Appendix B Acronyms Acronym CER CPI DTV IPT IR&D KPP LCC MEL O&O ORD PTW SOO SPI WBS Definition Cost Estimating Relationship Cost Performance Index Design to Value Integrated Product Team Independent Research and Development Key Performance Parameter Life Cycle Cost Master Equipment List Organization and Operation Operational Requirements Document Price-to-Win Statement of Objectives Schedule Performance Index Work Breakdown Structure 30