EE 369 POWER SYSTEM ANALYSIS Lecture 14 Power Flow Tom Overbye and Ross Baldick 1 Announcements Read Chapter 12, concentrating on sections 12.4 and 12.5. Homework 11 is 6.24, 6.26, 6.28, 6.30 (see figure 6.18 and table 6.9 for system), 6.38, 6.42 (note in Ybus in problem 6.34 should have Y32 = Y23 = j5, not j2 as stated), 6.43, 6.46, 6.49, 6.50; due Tuesday 11/24. Note that HW is due on Tuesday because Thanksgiving is on Thursday. 2 The N-R Power Flow: 5-bus Example 1 T1 5 T2 800 MVA 4 345/15 kV Line 3 345 kV 50 mi 345 kV 100 mi Line 1 400 MVA 15/345 kV Line 2 400 MVA 15 kV 345 kV 200 mi 3 520 MW 800 MVA 15 kV 40 Mvar 80 MW 2 280 MVAr 800 MW Single-line diagram 3 The N-R Power Flow: 5-bus Example Table 1. Bus input data θ degrees PG per unit QG per unit PL per unit Bus Type |V| per unit 1 Slack 1.0 0 0 2 Load 0 0 8.0 2.8 3 Constant voltage 1.05 5.2 0.8 0.4 4.0 -2.8 4 Load 0 0 0 0 5 Load 0 0 0 0 Table 2. Line input data QL per unit QGmax per unit QGmin per unit 0 R per unit X per unit G per unit B per unit Maximum MVA per unit 2-4 0.0090 0.100 0 1.72 12.0 2-5 0.0045 0.050 0 0.88 12.0 4-5 0.00225 0.025 0 0.44 12.0 Bus-toBus 4 The N-R Power Flow: 5-bus Example Table 3. Transformer input data R per unit X per unit Gc per unit Bm per unit Maximum MVA per unit Maximum TAP Setting per unit 1-5 0.00150 0.02 0 0 6.0 — 3-4 0.00075 0.01 0 0 10.0 — Bus-toBus Bus Table 4. Input data and unknowns Input Data Unknowns 1 |V1 |= 1.0, θ1 = 0 P1, Q1 2 P2 = PG2-PL2 = -8 Q2 = QG2-QL2 = -2.8 |V2|, θ2 3 |V3 |= 1.05 P3 = PG3-PL3 = 4.4 Q3, θ3 4 P4 = 0, Q4 = 0 |V4|, θ4 5 P5 = 0, Q5 = 0 |V5|, θ5 5 Let the Computer Do the Calculations! (Ybus Shown) 6 Selected Ybus Details Entries of Ybus relating to elements connected to bus 2. Note that resistances, inductive reactances, and admittances come from Table 2; subscripts on them refer to line from-to. Subscripts on Ybus correspond to entries of that matrix. Y21 Y23 0 Y24 1 1 0.89276 j 9.91964 per unit R24 jX 24 0.009 j 0.1 Y25 1 1 1.78552 j19.83932 per unit R25 jX 25 0.0045 j 0.05 Y22 1 1 B B j 24 j 25 R24 jX 24 R25 jX 25 2 2 (0.89276 j 9.91964) (1.78552 j19.83932) j 1.72 0.88 j 2 2 2.67828 j 28.4590 28.5847 84.624 per unit 7 Here are the Initial Bus Mismatches 8 And the Initial Power Flow Jacobian 9 Five Bus Power System Solved One 395 MW 114 Mvar A MVA Five Four A MVA Three 520 MW A MVA 337 Mvar slack 1.000 pu 0.000 Deg 0.974 pu -4.548 Deg 0.834 pu -22.406 Deg A A MVA MVA 1.019 pu -2.834 Deg 80 MW 40 Mvar 1.050 pu -0.597 Deg Two 800 MW 280 Mvar 10 Good Power System Operation • Good power system operation requires that there be no “reliability” violations (needing to shed load, have cascading outages, or other unacceptable conditions such as overloads past capacity) for either the current condition or in the event of statistically likely contingencies: • Reliability requires as a minimum that there be no transmission line/transformer capacity limit violations and that bus voltages be within acceptable limits (perhaps 0.95 to 1.08) • Example contingencies are the loss of any single 11 device. This is known as n-1 reliability. Good Power System Operation • North American Electric Reliability Corporation now has legal authority to enforce reliability standards (and there are now lots of them). • See http://www.nerc.com for details (click on Standards) • Consider impact of line contingency on 37 bus design example case. 12 37 Bus Example Design Case Metropolis Light and Power Electric Design Case 2 SLA C K3 4 5 A MVA A MVA 1 .0 3 pu sla ck System Losses: 10.70 MW 1 .0 2 pu T IM 3 4 5 A A MVA MVA A SLA C K1 3 8 1 .0 2 pu MVA RA Y 1 3 8 A A 1 .0 3 pu A MVA MVA T IM 1 3 8 1 .0 0 pu 3 3 MW 1 3 M var A A 1 .0 2 pu 1 5 .9 M var 2 3 MW 7 M var 1 .0 1 pu M O RO 1 3 8 3 7 MW A FERNA 6 9 A 1 .0 0 pu DEM A R6 9 KYLE69 A A 2 0 MW 1 2 M var UIUC 6 9 1 .0 0 pu 1 2 .8 M var A MVA MVA 2 5 MW 3 6 M var A M A NDA 6 9 5 6 MW 1 .0 1 pu A MVA MVA MVA SH IM KO 6 9 7 .4 M var 5 5 MW 2 5 M var 1 5 MW 5 M var A P A T T EN6 9 A MVA 1 .0 1 pu A A MVA MVA 2 3 MW 6 M var 1 0 MW 5 M var LA UF1 3 8 BUC KY 1 3 8 RO GER6 9 2 M var A MVA SA V O Y 6 9 1 .0 2 pu A 3 8 MW 3 M var JO 1 3 8 MVA A MVA 1 4 MW 1 4 MW 3 M var 1 .0 2 pu 1 .0 1 pu MVA MVA 4 5 MW 0 M var WEBER6 9 2 2 MW 1 5 M var 1 .0 1 pu A 1 .0 0 pu LA UF6 9 1 .0 2 pu A MVA 1 .0 0 pu A MVA MVA A 7 .3 M var 1 .0 2 pu MVA A 3 6 MW 1 0 M var MVA 0 .0 M var 1 .0 0 pu A BLT 6 9 MVA 2 0 MW 2 8 M var MVA A MVA 6 0 MW 1 2 M var LY NN1 3 8 1 4 MW 4 M var A BLT 1 3 8 1 .0 0 pu 1 .0 1 pu H A LE6 9 MVA A A 1 3 M var 1 6 MW -1 4 M var A MVA A 2 0 MW 3 M var 1 .0 0 pu BO B6 9 1 2 4 MW 4 5 M var A A 2 5 MW 1 0 M var MVA A MVA 1 .0 2 pu A A MVA BO B1 3 8 A MVA MVA MVA MVA MVA H O M ER6 9 A 1 .0 1 pu 2 8 .9 M var 1 .0 0 pu WO LEN6 9 4 .9 M var 5 8 MW 4 0 M var MVA 1 4 .2 M var 0 .9 9 pu 1 .0 1 pu 1 2 MW 3 M var MVA A 1 3 M var MVA A P ET E6 9 A 3 9 MW 1 3 M var H A NNA H 6 9 6 0 MW 1 9 M var 0 .9 9 pu GRO SS6 9 MVA MVA 1 2 MW 5 M var RA Y 6 9 1 7 MW 3 M var A H ISKY 6 9 MVA 1 .0 2 pu MVA MVA A A 1 .0 3 pu MVA A MVA 1 8 MW 5 M var P A I6 9 1 .0 1 pu T IM 6 9 A MVA A MVA A MVA MVA 1 .0 0 pu 2 2 0 MW 5 2 M var RA Y 3 4 5 1 .0 1 pu A MVA SA V O Y 1 3 8 JO 3 4 5 A 1 5 0 MW 0 M var MVA A MVA 1 5 0 MW 0 M var A MVA 1 .0 2 pu A 1 .0 3 pu MVA 13 Looking at the Impact of Line Outages Metropolis Light and Power Electric Design Case 2 SLA C K3 4 5 A MVA A MVA 1 .0 3 pu 1 .0 2 pu sla ck System Losses: 17.61 MW T IM 3 4 5 A A MVA MVA A SLA C K1 3 8 1 .0 2 pu MVA RA Y 1 3 8 A A 1 .0 3 pu A MVA MVA T IM 1 3 8 1 .0 1 pu 3 3 MW 1 3 M var A A 1 .0 2 pu 1 6 .0 M var 2 3 MW 7 M var 1 .0 1 pu MVA 1 .0 0 pu 0 .9 0 pu GRO SS6 9 3 7 MW A FERNA 6 9 A 1 .0 0 pu DEM A R6 9 KYLE69 A A 2 0 MW 1 2 M var UIUC 6 9 1 .0 0 pu 1 2 .8 M var A MVA MVA 2 5 MW 3 6 M var A M A NDA 6 9 110% 5 6 MW 1 .0 1 pu MVA MVA 5 5 MW 3 2 M var A 3 6 MW 1 0 M var MVA 0 .9 9 pu 1 5 MW 5 M var 1 .0 0 pu A MVA 2 3 MW 6 M var A 80% A A 1 0 MW 5 M var MVA LA UF1 3 8 BUC KY 1 3 8 RO GER6 9 2 M var A MVA SA V O Y 6 9 1 .0 2 pu A 3 8 MW 9 M var JO 1 3 8 MVA A MVA 1 4 MW 1 4 MW 3 M var 1 .0 1 pu 1 .0 0 pu MVA MVA 4 5 MW 0 M var WEBER6 9 2 2 MW 1 5 M var 1 .0 1 pu P A T T EN6 9 A MVA A A MVA 1 .0 0 pu LA UF6 9 1 .0 1 pu 1 .0 2 pu MVA MVA A 7 .2 M var 1 .0 0 pu 0 .0 M var 2 0 MW 4 0 M var SH IM KO 6 9 7 .3 M var MVA MVA 6 0 MW 1 2 M var MVA A BLT 6 9 MVA A A MVA A 1 .0 1 pu H A LE6 9 MVA LY NN1 3 8 1 4 MW 4 M var A BLT 1 3 8 1 .0 0 pu A 135% 1 3 M var 1 6 MW -1 4 M var A MVA A 2 0 MW 3 M var 0 .9 4 pu BO B6 9 1 2 4 MW 4 5 M var A A 2 5 MW 1 0 M var MVA A MVA 1 .0 2 pu A A MVA BO B1 3 8 A MVA MVA MVA MVA MVA H O M ER6 9 A 1 .0 1 pu 2 8 .9 M var 1 .0 0 pu WO LEN6 9 4 .9 M var 5 8 MW 4 0 M var MVA 1 1 .6 M var 0 .9 0 pu 1 .0 1 pu 1 2 MW 3 M var P ET E6 9 MVA A 1 3 M var MVA A MVA A 3 9 MW 1 3 M var H A NNA H 6 9 6 0 MW 1 9 M var 1 2 MW 5 M var RA Y 6 9 1 7 MW 3 M var A H ISKY 6 9 M O RO 1 3 8 1 .0 2 pu MVA MVA MVA 1 .0 3 pu MVA A A 1 8 MW 5 M var P A I6 9 1 .0 1 pu T IM 6 9 A MVA A MVA A MVA MVA Opening one line (Tim69Hannah69) causes overloads. This would not be acceptable under NERC standards. 2 2 7 MW 4 3 M var RA Y 3 4 5 1 .0 1 pu A MVA SA V O Y 1 3 8 JO 3 4 5 A 1 5 0 MW 4 M var MVA A MVA 1 5 0 MW 4 M var A MVA 1 .0 2 pu A 1 .0 3 pu MVA 14 Contingency Analysis Contingency analysis provides an automatic way of looking at all the contingencies in a specified “contingency set.” In this example the contingency set is all the single line/transformer outages 15 Power Flow And Design • One common usage of the power flow is to determine how the system should be modified to remove contingencies problems or serve new load • In an operational context this requires working with the existing electric grid, typically involving redispatch of generation. • In a planning context additions to the grid can be considered as well as re-dispatch. • In the next example we look at how to add a new line in order to remove the existing contingency violations while serving new load. 16 An Unreliable Solution: some line outages result in overloads Metropolis Light and Power Electric Design Case 2 SLA C K3 4 5 A MVA A MVA 1 .0 2 pu Case now has nine separate contingencies having reliability violations (overloads in post-contingency system). sla ck System Losses: 14.49 MW 1 .0 2 pu T IM 3 4 5 A A MVA MVA A SLA C K1 3 8 1 .0 1 pu MVA RA Y 1 3 8 A A 1 .0 3 pu A MVA MVA T IM 1 3 8 0 .9 9 pu 3 3 MW 1 3 M var A A 1 .0 2 pu 1 5 .9 M var 2 3 MW 7 M var 1 .0 1 pu 0 .9 7 pu 3 7 MW A FERNA 6 9 A 1 .0 0 pu DEM A R6 9 KYLE69 A 2 0 MW 1 2 M var UIUC 6 9 1 .0 0 pu 1 2 .8 M var A MVA 2 5 MW 1 0 M var 1 2 4 MW 4 5 M var A 5 6 MW A MVA MVA 5 5 MW 2 8 M var A 3 6 MW 1 0 M var MVA 1 5 MW 5 M var MVA 1 .0 1 pu A A MVA MVA 2 3 MW 6 M var A P A T T EN6 9 1 0 MW 5 M var LA UF1 3 8 BUC KY 1 3 8 RO GER6 9 2 M var A MVA SA V O Y 6 9 1 .0 2 pu A 3 8 MW 4 M var JO 1 3 8 MVA A MVA 1 4 MW 1 4 MW 3 M var 1 .0 2 pu 1 .0 1 pu MVA MVA 4 5 MW 0 M var WEBER6 9 2 2 MW 1 5 M var 1 .0 1 pu A 1 .0 0 pu LA UF6 9 A A MVA A 1 .0 2 pu 1 .0 2 pu MVA MVA A 7 .3 M var 1 .0 0 pu 0 .0 M var 1 .0 0 pu SH IM KO 6 9 7 .4 M var MVA MVA 2 0 MW 4 0 M var A MVA 6 0 MW 1 2 M var LY NN1 3 8 1 4 MW 4 M var MVA BLT 6 9 1 .0 1 pu H A LE6 9 MVA A A MVA BLT 1 3 8 1 .0 0 pu A A A 1 3 M var 1 6 MW -1 4 M var A MVA 1 .0 1 pu A M A NDA 6 9 BO B6 9 MVA A 0 .9 7 pu MVA A MVA A 2 5 MW 3 6 M var MVA MVA 1 .0 2 pu A MVA MVA 2 0 MW 3 M var 0 .9 9 pu BO B1 3 8 A MVA A MVA A 1 .0 1 pu 2 8 .9 M var 1 .0 0 pu WO LEN6 9 4 .9 M var 5 8 MW 4 0 M var MVA 1 3 .6 M var H O M ER6 9 1 .0 1 pu 1 2 MW 3 M var MVA A 1 3 M var MVA A P ET E6 9 A 3 9 MW 1 3 M var H A NNA H 6 9 6 0 MW 1 9 M var 1 2 MW 5 M var GRO SS6 9 MVA MVA MVA RA Y 6 9 1 7 MW 3 M var A H ISKY 6 9 96% M O RO 1 3 8 1 .0 2 pu MVA MVA A A 1 .0 2 pu MVA A MVA 1 8 MW 5 M var P A I6 9 1 .0 1 pu T IM 6 9 A MVA A MVA A MVA MVA 1 .0 0 pu 2 6 9 MW 6 7 M var RA Y 3 4 5 1 .0 1 pu A MVA SA V O Y 1 3 8 JO 3 4 5 A 1 5 0 MW 1 M var MVA A MVA 1 5 0 MW 1 M var A MVA 1 .0 2 pu A 1 .0 3 pu MVA 17 A Reliable Solution: no line outages result in overloads Metropolis Light and Power Electric Design Case 2 SLA C K3 4 5 A MVA A MVA 1 .0 2 pu sla ck System Losses: 11.66 MW 1 .0 2 pu T IM 3 4 5 A A MVA MVA A SLA C K1 3 8 1 .0 1 pu MVA RA Y 1 3 8 A A 1 .0 3 pu A MVA MVA T IM 1 3 8 1 .0 0 pu Previous case was augmented with the addition of a 138 kV Transmission Line 3 3 MW 1 3 M var A A 1 .0 2 pu 1 5 .8 M var 2 3 MW 7 M var 1 .0 1 pu M O RO 1 3 8 3 7 MW A FERNA 6 9 A 1 .0 0 pu Kyle138 KYLE69 A A 2 0 MW 1 2 M var UIUC 6 9 1 .0 0 pu 1 2 .8 M var A MVA MVA 2 5 MW 3 6 M var MVA 5 6 MW 2 5 MW 1 0 M var MVA MVA 5 5 MW 2 9 M var MVA MVA 1 5 MW 5 M var 1 .0 1 pu A A MVA MVA 2 3 MW 6 M var A A 1 0 MW 5 M var LA UF1 3 8 BUC KY 1 3 8 RO GER6 9 2 M var A MVA SA V O Y 6 9 1 .0 2 pu A 3 8 MW 4 M var JO 1 3 8 MVA A MVA 1 4 MW 1 4 MW 3 M var 1 .0 2 pu 1 .0 1 pu MVA MVA 4 5 MW 0 M var WEBER6 9 2 2 MW 1 5 M var 1 .0 1 pu P A T T EN6 9 A MVA A A MVA 1 .0 0 pu LA UF6 9 1 .0 2 pu 1 .0 2 pu MVA MVA A 7 .3 M var 1 .0 0 pu 0 .0 M var 1 .0 0 pu SH IM KO 6 9 7 .4 M var MVA A 3 6 MW 1 0 M var A 2 0 MW 3 8 M var A BLT 6 9 MVA 6 0 MW 1 2 M var MVA MVA A 1 .0 1 pu H A LE6 9 MVA LY NN1 3 8 1 4 MW 4 M var A BLT 1 3 8 1 .0 0 pu A A 2 0 MW 3 M var 1 .0 0 pu A A MVA 1 .0 1 pu 1 3 M var 1 6 MW -1 4 M var A A M A NDA 6 9 BO B6 9 1 2 4 MW 4 5 M var A A 0 .9 9 pu A MVA 1 .0 2 pu A MVA MVA MVA MVA MVA BO B1 3 8 A MVA MVA A 1 .0 1 pu DEM A R6 9 A WO LEN6 9 4 .9 M var 5 8 MW 4 0 M var 2 8 .9 M var 1 4 .1 M var H O M ER6 9 1 .0 1 pu 1 2 MW 3 M var MVA M VA A 1 3 M var MVA A P ET E6 9 A 3 9 MW 1 3 M var H A NNA H 6 9 6 0 MW 1 9 M var 0 .9 9 pu GRO SS6 9 A MVA 1 2 MW 5 M var RA Y 6 9 1 7 MW 3 M var MVA H ISKY 6 9 MVA 1 .0 2 pu MVA MVA A A 1 .0 3 pu MVA A MVA 1 8 MW 5 M var P A I6 9 1 .0 1 pu T IM 6 9 A MVA A MVA A MVA MVA 0 .9 9 pu 2 6 6 MW 5 9 M var RA Y 3 4 5 1 .0 1 pu A MVA SA V O Y 1 3 8 JO 3 4 5 A 1 5 0 MW 1 M var MVA A MVA 1 5 0 MW 1 M var A MVA 1 .0 2 pu A 1 .0 3 pu MVA 18 Generation Changes and The Slack Bus • The power flow is a steady-state analysis tool, so the assumption is total load plus losses is always equal to total generation • Generation mismatch is made up at the slack bus • When doing generation change power flow studies one always needs to be cognizant of where the generation is being made up • Common options include “distributed slack,” where the mismatch is distributed across multiple generators by participation factors or by economics. 19 Generation Change Example 1 SLA C K3 4 5 A Display shows “Difference Flows” between original 37 bus case, and case with a BLT138 generation outage; note all the power change is picked up at the slack MVA A Slack bus MVA 0 .0 0 pu 1 6 2 MW 3 5 M var RA Y 3 4 5 sla ck 0 .0 0 pu T IM 3 4 5 A A MVA MVA A SLA C K1 3 8 -0 .0 1 pu A MVA RA Y 1 3 8 A 0 .0 0 pu A MVA T IM 1 3 8 0 .0 0 pu MVA 0 MW 0 M var A A A 0 .0 0 pu -0 .1 M var 0 MW 0 M var MVA MVA MVA MVA -0 .0 1 pu RA Y 6 9 0 .0 0 pu T IM 6 9 P A I6 9 0 .0 0 pu 0 MW 0 MW 0 M var A MVA A 0 M var MVA A A 0 MW 0 M var 0 .0 0 pu GRO SS6 9 A MVA FERNA 6 9 MVA A MVA H ISKY 6 9 MVA MVA -0 .1 M var A MVA 0 .0 0 pu WO LEN6 9 A A 0 MW 0 M var 0 .0 0 pu 0 MW 0 M var A M O RO 1 3 8 0 MW 0 M var -0 .0 1 pu -0 .0 3 pu A P ET E6 9 DEM A R6 9 MVA H A NNA H 6 9 0 MW 0 M var 0 MW 0 M var -0 .2 M var MVA MVA 0 MW 0 M var A 0 .0 0 pu 0 .0 0 pu 0 .0 0 pu -0 .1 M var 0 MW MVA 0 MW 0 M var MVA 0 .0 0 pu BLT 1 3 8 -0 .0 3 pu 0 MW 0 M var MVA A A A H O M ER6 9 0 MW 0 M var MVA SH IM KO 6 9 0 .0 M var MVA MVA 0 .0 0 pu A A H A LE6 9 0 .0 0 pu A BLT 6 9 -0 .0 1 pu A 0 MW 0 M var 0 .0 0 pu LY NN1 3 8 A A MVA A M A NDA 6 9 0 M var 0 MW 0 M var MVA MVA A -0 .0 0 2 pu BO B6 9 MVA -1 5 7 M W -4 5 M var A A A MVA A A MVA UIUC 6 9 -0 .1 M var BO B1 3 8 A MVA MVA MVA MVA 0 MW 5 1 M var A MVA 0 MW 0 M var A MVA 0 MW 0 M var A A 0 MW 0 M var MVA MVA MVA A 0 .0 M var A A 0 .0 0 pu 0 .0 M var 0 .0 0 pu MVA 0 .0 0 pu P A T T EN6 9 MVA MVA A MVA 0 .0 0 pu LA UF6 9 0 .0 0 pu 0 MW 4 M var 0 .0 0 pu A A MVA MVA 0 MW 0 M var 0 MW 0 M var 0 MW 0 M var LA UF1 3 8 0 .0 0 pu 0 MW 0 M var WEBER6 9 0 .0 0 pu BUC KY 1 3 8 RO GER6 9 0 M var 0 MW 0 M var A MVA SA V O Y 6 9 0 .0 0 pu 0 MW 3 M var A A MVA 0 MW JO 1 3 8 MVA 0 .0 0 pu A MVA SA V O Y 1 3 8 JO 3 4 5 A 0 MW 2 M var MVA A MVA 0 MW 2 M var A MVA 0 .0 0 pu A 0 .0 0 pu MVA 20 Generation Change Example 2 SLA C K3 4 5 A MVA A MVA 0 .0 0 pu 0 MW 3 7 M var RA Y 3 4 5 sla ck 0 .0 0 pu T IM 3 4 5 A A MVA MVA A SLA C K1 3 8 -0 .0 1 pu A MVA RA Y 1 3 8 A 0 .0 0 pu A MVA T IM 1 3 8 0 .0 0 pu MVA 0 MW 0 M var A A A 0 .0 0 pu -0 .1 M var 0 MW 0 M var MVA MVA MVA MVA 0 .0 0 pu RA Y 6 9 T IM 6 9 P A I6 9 0 .0 0 pu 0 MW 0 MW 0 M var A 0 .0 0 pu MVA A 0 M var MVA A A 0 MW 0 M var 0 .0 0 pu GRO SS6 9 A MVA FERNA 6 9 MVA A MVA H ISKY 6 9 MVA MVA 0 .0 M var A MVA 0 .0 0 pu WO LEN6 9 A A 0 MW 0 M var 0 .0 0 pu 0 MW 0 M var A M O RO 1 3 8 0 MW 0 M var 0 .0 0 pu -0 .0 3 pu A P ET E6 9 DEM A R6 9 MVA H A NNA H 6 9 0 MW 0 M var 0 MW 0 M var -0 .2 M var MVA MVA 0 MW 0 M var A 0 .0 0 pu 0 .0 0 pu 0 .0 0 pu -0 .1 M var -1 5 7 M W -4 5 M var A 0 MW -0 .0 0 3 pu 0 MW 0 M var MVA 0 .0 0 pu BLT 1 3 8 -0 .0 3 pu MVA 0 MW 0 M var MVA A A A H O M ER6 9 0 MW 0 M var MVA SH IM KO 6 9 -0 .1 M var MVA MVA -0 .0 1 pu A A H A LE6 9 0 .0 0 pu A BLT 6 9 -0 .0 1 pu A 0 MW 0 M var 0 .0 0 pu LY NN1 3 8 A A A M A NDA 6 9 0 M var 0 MW 0 M var MVA MVA A MVA BO B6 9 MVA A A MVA A A MVA UIUC 6 9 -0 .1 M var BO B1 3 8 A MVA MVA MVA MVA 1 9 MW 5 1 M var A MVA 0 MW 0 M var A MVA 0 MW 0 M var A A 0 MW 0 M var MVA MVA MVA A 0 .0 M var A A 0 .0 0 pu 0 .0 M var 0 .0 0 pu MVA 0 .0 0 pu P A T T EN6 9 MVA MVA A MVA 0 .0 0 pu LA UF6 9 0 .0 0 pu 9 9 MW -2 0 M var 0 .0 0 pu A A MVA MVA 0 MW 0 M var 0 MW 0 M var 0 MW 0 M var LA UF1 3 8 0 .0 0 pu 0 MW 0 M var WEBER6 9 0 .0 0 pu BUC KY 1 3 8 RO GER6 9 0 M var 0 MW 0 M var A MVA SA V O Y 6 9 0 .0 0 pu A A MVA 0 MW 4 2 MW -1 4 M var JO 1 3 8 MVA 0 .0 0 pu A MVA SA V O Y 1 3 8 JO 3 4 5 A 0 MW 0 M var MVA A MVA 0 MW 0 M var A MVA 0 .0 0 pu A 0 .0 0 pu Display repeats previous case except now the change in generation is picked up by other generators using a “participation factor” (change is shared amongst generators) approach. MVA 21 Voltage Regulation Example: 37 Buses Automatic voltage regulation system controls voltages. SLA C K3 4 5 A MVA A MVA 1 .0 2 pu System Losses: 11.51 MW 1 .0 2 pu sla ck T IM 3 4 5 A MVA MVA A SLA C K1 3 8 1 .0 1 pu A MVA RA Y 1 3 8 A 1 .0 3 pu A MVA 3 3 MW 1 3 M var A A T IM 6 9 1 5 .9 M var 1 8 MW 5 M var 1 .0 2 pu RA Y 6 9 1 .0 1 pu 3 7 MW 1 7 MW 3 M var A MVA A 2 3 MW 7 M var 1 .0 3 pu MVA P A I6 9 1 .0 1 pu MVA A MVA MVA 1 .0 2 pu A MVA T IM 1 3 8 1 .0 0 pu 2 1 9 MW 5 2 M var RA Y 3 4 5 A GRO SS6 9 A 1 3 M var MVA A MVA FERNA 6 9 MVA A MVA M O RO 1 3 8 MVA H ISKY 6 9 4 .8 M var MVA 2 0 MW 8 M var 1 .0 0 pu A P ET E6 9 DEM A R6 9 H A NNA H 6 9 5 1 MW 1 5 M var 5 8 MW 4 0 M var 2 9 .0 M var A MVA 1 .0 0 pu 1 2 .8 M var 0 .9 9 7 pu MVA 5 6 MW MVA H O M ER6 9 5 8 MW 3 6 M var 3 3 MW MVA MVA 1 .0 1 pu H A LE6 9 3 6 MW 1 0 M var A A 7 .2 M var MVA 1 .0 0 pu LA UF6 9 A 1 .0 0 pu MVA 2 3 MW 6 M var A MVA P A T T EN6 9 0 MW 0 M var LA UF1 3 8 1 .0 1 pu 1 4 MW 1 .0 2 pu BUC KY 1 3 8 RO GER6 9 2 M var 1 4 MW 3 M var A MVA SA V O Y 6 9 1 .0 2 pu A 3 8 MW 3 M var JO 1 3 8 MVA A MVA MVA MVA 4 5 MW 0 M var WEBER6 9 2 2 MW 1 5 M var A A 1 .0 0 pu A 1 .0 2 pu 1 .0 1 pu MVA MVA 1 .0 0 pu 2 0 .8 M var 1 5 MW 5 M var 9 2 MW 1 0 M var A A MVA 1.010 pu MVA MVA MVA 1 .0 2 pu BLT 6 9 1 .0 1 pu MVA 2 0 MW 9 M var SH IM KO 6 9 7 .4 M var MVA 6 0 MW 1 2 M var 1 4 MW 4 M var MVA A A A MVA BLT 1 3 8 1 .0 0 pu MVA A A LY NN1 3 8 A MVA A 0.0 Mvar 1 0 M var 1 5 MW 3 M var 1 .0 0 pu 1 3 M var 0 MW A 0 M var A A M A NDA 6 9 BO B6 9 1 5 7 MW 4 5 M var MVA MVA 0 .9 9 pu MVA A MVA 1 .0 2 pu A A MVA MVA MVA A A A BO B1 3 8 A 4 5 MW 1 2 M var 0 .9 9 pu UIUC 6 9 1 4 .3 M var A A 1 .0 0 pu MVA 1 .0 0 pu WO LEN6 9 A A 1 2 MW 5 M var 1 .0 1 pu 2 1 MW 7 M var A MVA 1 .0 1 pu A MVA SA V O Y 1 3 8 JO 3 4 5 A 1 5 0 MW 0 M var MVA A MVA 1 5 0 MW 0 M var A MVA 1 .0 2 pu A 1 .0 3 pu MVA Display shows voltage contour of the power system 22 Real-sized Power Flow Cases • Real power flow studies are usually done with cases with many thousands of buses • Outside of ERCOT, buses are usually grouped into various balancing authority areas, with each area doing its own interchange control. • Cases also model a variety of different automatic control devices, such as generator reactive power limits, load tap changing transformers, phase shifting transformers, switched capacitors, HVDC transmission lines, and (potentially) FACTS devices. 23 Sparse Matrices and Large Systems • Since for realistic power systems the model sizes are quite large, this means the Ybus and Jacobian matrices are also large. • However, most elements in these matrices are zero, therefore special techniques, sparse matrix/vector methods, are used to store the values and solve the power flow: • Without these techniques large systems would be essentially unsolvable. 24 Eastern Interconnect Example VIK 138 BIG BEN D WH TWTR3 EEN 138 ST RITA M UKWO N GO WH TWTR4 SUN 138 TRIPP WH TWTR5 UN IVRSTY Raci ne JAN 138 SGR CK4 UN IV N EU LBT 138 SGR CK5 LAN 138 BRLGTN 2 SO M ERS ALB 138 RO R 138 N LK GV T BRLGTN 1 ALBERS-2 Paddock PO T 138 N O M 138 M RE 138 PARIS WE TICH IGN H LM 138 BAIN 4 WIB 138 D AR 138 N LG 138 N ED 138 Pl easant Prai ri e N WT 138 N ED 161 Kenosha LIBERTY5 BCH 138 TRK RIV5 CASVILL5 BLK 138 LEN A ; B CO R 138 WBT 138 ELK 138 LAKEVIEW D IK 138 LEN A ; R 8TH ST. 5 LO RE Zi on ELERO ; RT SO . GVW. 5 Wempl eton PECAT; B Zi on (138 kV) Ant i och Rockford 5 ELERO ; BT ASBURY 5 M cHenr y G ur nee Round Lake CN TRGRV5 Waukegan LAN CA; R JULIAN 5 SALEM N 5 H arl em Sal em FREEP; Bel vi dere M arengo Woodstock Wi l son Roscoe Lakehur st P Val GALEN A 5 Cr yst al Lake Sand Park Pi erpont Li ber t yvi l l e 345 kV Si l ver Lake Hunt l ey B465 FO RD A; R Li ber t yvi l l e 138 kV Nor t h Chi cago Al gonqui n S PEC; R E. Rockf ord U. S. N Tr ai ni ng Al pi ne Abbot t Labs Par k Lest hon Charl es B427 ; 1T Sabrooke Apt aki si c Cherry Val l ey O l d El m Lake Zur i ch Buf f al o G r oove Bar r i ngt on Bl aw khaw k Wheel i ng Deer f i el d Pal at i ne D undee SAVAN N A5 Pr ospect Hei ght s Ar l i ngt on STILL; RT M Q O KETA5 WYO M IN G5 Pr ospect Hof f m an Est at es Nor t hbr ook Hei ght s C434 M ount Pr ospect Tol l w ay Schaum ber g M T VERN 5 PCI El m w ood 5 Byron Hanover S. Schaum ber g G ol f M i l l Busse Landm BERTRAM 5 Skoki e Spaul di ng Bar t l et t El gi n YO RK Evanst on Des Pl ai nes Tonne 5 Ni l es How ar d M ARYL; B Devon Wayne Sout h El gi n Des Pl ai nes I t asca Hi ggi ns Al t G E Rose Hi l l Nor di G l endal e Nor t hr i dge M i chi gan Ci ty West Chi cago W407 ( Fer m i ) LEECO ; BP W. De Kal b H 445 ; 3B Addi son -0. 40 deg Nor t hw est Nat om a Chur ch G l i dden Aur or a 2. 35 deg El m hur st Dr i ver Lom bar d Rockw el l G al ew ood O ak Par k Rock Crk. -13. 4 deg -13. 3 deg Fr ankl i n Par k H 440 ; R GR M N D 5 E CALM S5 Cl ybour n ALBAN Y 6 BVR CH 65 D EWITT 5 BVR CH 5 ALBAN Y 5 Sugar Grove M EN D O ; T D IXO N ; BT GARD E; G l en El l yn Ber kel ey Congr ess O akbr ook N Aurora Wat er m an STEWA; B Yor k Cent er El ect r i c Junct i on Ki ngsbur y Cl i nt Bel l w ood H 440 ; RT H 71 ; B Cr osby O hi o But t e H 71 ; BT Y450 Jef f erson D ekov Tayl or La G r ange H 71 ; R STERL; B Uni versi ty Ri dgel and D unacr Li sl e H -471 (N W Steel ) M cCook Lasal l e Fi sk D799 Washi ngton Park Craw f ord War r envi l l e State D775 -1. 1 deg H arbor Garf i el d D ow ners Groove Frontenac Woodri dge Wol f Creek Q uad Ci ti es M ECCO RD 3 W604 O sw ego J307 W602 Wi l l Co. N ELSO ; RT W507 D avenport Wal cott Lockport Kenda H i l l crest Rockdal e SB 88 5 H egew i sch Wi l dw ood M unster Z-524 Bl ue Isl and Green Acres Ti nl ey Park South H ol l and Jo456 Shore 3 IPSCO Tow er Rd Goodi ngs Grove J322 SB 76 5 IPSCO Lake George Z-100 Green Lake N O RM A; B SB 78 5 SB JIC 5 Shef i el d Z-715 Burnham J-332 Bel l Road N O RM A; R Crestw ood Archer Pl ai nf i el d SB 17 5 SB 71 5 Babcock State Li ne Z-494 G3851 G3852 M endota SB 74 5 1. 9 deg Wal l ace Beverl y G394 O rl an SB 49 5 SB 90 5 SUB 77 5 D AVN PRT5 SB 89 5 D amen Chi ave Evergreen Al si p Roberts Romeo Pal os SBH YC5 SB UIC 5 Sub 92 H ayf ord Sayre Bri dgevi ew Bol i ngbrook M ontgomery R FAL; R Cal umet Ri ver W603 Pl ano N ELSO ; R R FAL; B 0. 6 deg Bedf ord Park Bur r Ri dge W601 CO RD O ; SB 79 5 Q uarry Wi l l ow Sandw i ch Sub 91 Saw yer Ford Ci ty Cl earni ng W600 ( Naper vi l l e) N el son SB 58 5 Sand Ri dge H arvey J323 Lansi ng Jol i et J370 Gl enw ood SB 70 5 5 Chi cago H ei ghts F-503 Bri gg J-371 SB A 5 M oken J-326 J-390 SB 28 5 SB 52 5 J-375 F-575 East Frankf ort Frankf ort Country Cl ub H i l l s El w ood M atteson N Len SB 48 5 PRIN C TP SB 47 5 Park Forest Bl oom J-339 U. Park SB 31T 5 Woodhi l l St. John J-305 SB 53 5 PRIN CTN SB 85 5 Col l i ns LTV TP E Wi l ton Center LTV TP N KEWAN ; SB 43 5 S ST TAP B ESK TAP B Schahf er 105% 93% H EN N E; T SB 112 5 Crete D resden M ason East M ol i ne SB 18 5 Upnor Goose Lake LTV STL KEWAN IP E M O LIN E H EN N EPIN Kendra O TTAWA T MVA MVA 1556A TP N LASAL O GLES; T O GLESBY Lasal l e O GLSBY M M arsei l l es La Sal l e Wi l mi ngton K-319 # 1 Loui sa D avi s Creek K-319 # 2 KPECKTP5 WEST 5 Bradl ey SO . SUB 5 Streator Br ai dw ood H WY61 5 9 SUB 5 M IN O N K T GALESBR5 Kankakee GALESBRG RICH LAN D N EWPO RT5 M O N M O UTH SPN G BAY Ponti ac M i dpoi nt D equi ne M PWSPLIT H ALLO CK ELPASO T Peoria WATSEKA 17GO D LN D GILM AN FARGO CAT M O SS RSW EAST RAD N O R CAT SUB1 PIO N EERC E PEO RIA Example, which models the Eastern Interconnect contains about 43,000 buses. CAT TAP 25 Solution Log for 1200 MW Outage In this example the losss of a 1200 MW generator in Northern Illinois was simulated. This caused a generation imbalance in the associated balancing authority area, which was corrected by a redispatch of local generation. 26 Interconnected Operation Power systems are interconnected across large distances. For example most of North America east of the Rockies is one system, most of North America west of the Rockies is another. Most of Texas and Quebec are each interconnected systems. 27 Balancing Authority Areas A “balancing authority area” (previously called a “control area”) has traditionally represented the portion of the interconnected electric grid operated by a single utility or transmission entity. Transmission lines that join two areas are known as tie-lines. The net power out of an area is the sum of the flow on its tie-lines. The flow out of an area is equal to total gen - total load - total losses = tie-line flow 28 Area Control Error (ACE) The area control error is a combination of: the deviation of frequency from nominal, and the difference between the actual flow out of an area and the scheduled (agreed) flow. That is, the area control error (ACE) is the difference between the actual flow out of an area minus the scheduled flow, plus a frequency deviation component: ACE Pactual tie-line flow Psched 10f ACE provides a measure of whether an area is producing more or less than it should to satisfy schedules and to contribute to controlling frequency. 29 Area Control Error (ACE) The ideal is for ACE to be zero. Because the load is constantly changing, each area must constantly change its generation to drive the ACE towards zero. For ERCOT, the historical ten control areas were amalgamated into one in 2001, so the actual and scheduled interchange are essentially the same (both small compared to total demand in ERCOT). In ERCOT, ACE is predominantly due to frequency deviations from nominal since there is very little scheduled flow to or from other areas outside of ERCOT. 30 Automatic Generation Control Most systems use automatic generation control (AGC) to automatically change generation to keep their ACE close to zero. Usually the control center (either ISO or utility) calculates ACE based upon tie-line flows and frequency; then the AGC module sends control signals out to the generators every four seconds or so. 31 Power Transactions Power transactions are contracts between generators and (representatives of) loads. Contracts can be for any amount of time at any price for any amount of power. Scheduled power transactions between balancing areas are called “interchange” and implemented by setting the value of Psched used in the ACE calculation: ACE = Pactual tie-line flow – Psched + 10β Δf …and then controlling the generation to bring ACE towards zero. 32 “Physical” power Transactions • For ERCOT, interchange is only relevant over asynchronous connections between ERCOT and Eastern Interconnection or Mexico. • In Eastern and Western Interconnection, interchange occurs between areas connected by AC lines. 33 Three Bus Case on AGC: no interchange. Bus 2 -40 MW 8 MVR 40 MW -8 MVR Bus 1 1.00 PU 266 MW 133 MVR 1.00 PU 101 MW 5 MVR 150 MW AGC ON 166 MVR AVR ON -39 MW -77 MW 25 MVR 12 MVR 78 MW -21 MVR Home Area Generation is automatically changed to match change in load 100 MW 39 MW -11 MVR Bus 3 1.00 PU 133 MW 67 MVR 250 MW AGC ON 34 MVR AVR ON Net tie-line flow is close to zero 34 100 MW Transaction between areas in Eastern or Western Bus 2 8 MW -2 MVR -8 MW 2 MVR Bus 1 1.00 PU 225 MW 113 MVR 1.00 PU 0 MW 32 MVR 150 MW AGC ON 138 MVR AVR ON -92 MW -84 MW 27 MVR 30 MVR 85 MW -23 MVR Home Area 93 MW -25 MVR Bus 3 Scheduled Transactions 100.0 MW Scheduled 100 MW Transaction from Left to Right 100 MW 1.00 PU 113 MW 56 MVR 291 MW AGC ON 8 MVR AVR ON Net tie-line flow is now 100 MW 35 PTDFs Power transfer distribution factors (PTDFs) show the linearized impact of a transfer of power. PTDFs can be estimated using the fast decoupled power flow B matrix: θ B 1P Once we know θ we can derive the change in the transmission line flows to evaluate PTDFs. Note that we can modify several elements in P, in proportion to how the specified generators would participate in the power transfer. 36 Nine Bus PTDF Example Figure shows initial flows for a nine bus power system 300.0 MW 400.0 MW A 300.0 MW 250.0 MW B D 71% 10% C 71.1 MW 57% 60% 92% 0.00 deg 55% 11% F G 74% 250.0 MW 64% E 150.0 MW 250.0 MW 44% 32% 24% H 200.0 MW I 150.0 MW 37 Nine Bus PTDF Example, cont'd Figure now shows percentage PTDF flows for a change in transaction from A to I 300.0 MW 400.0 MW A 300.0 MW 250.0 MW B D 30% 43% C 71.1 MW 10% 57% 13% 0.00 deg 35% 2% F G 34% 250.0 MW 20% E 150.0 MW 250.0 MW 34% 32% 34% H 200.0 MW I 150.0 MW 38 Nine Bus PTDF Example, cont'd Figure now shows percentage PTDF flows for a change in transaction from G to F 300.0 MW 400.0 MW A 300.0 MW 250.0 MW B D 18% 6% C 71.1 MW 6% 6% 12% 0.00 deg 61% 19% F G 21% 250.0 MW 12% 150.0 MW 250.0 MW E 20% 21% H 200.0 MW I 150.0 MW 39 WE to TVA PTDFs 40 Line Outage Distribution Factors (LODFs) • LODFs are used to approximate the change in the flow on one line caused by the outage of a second line – typically they are only used to determine the change in the MW flow compared to the precontingency flow if a contingency were to occur, – LODFs are used extensively in real-time operations, – LODFs are approximately independent of flows but do depend on the assumed network topology. 41 Line Outage Distribution Factors (LODFs) Pl change in flow on line l , due to outage of line k . Pk pre-contingency flow on line k Pl LODFl ,k Pk , Estimates change in flow on line l if outage on line k were to occur. 42 Line Outage Distribution Factors (LODFs) If line k initially had Pk 100 MW of flow on it, and line l initially had Pl 50 MW flow on it, and then there was an outage of line k , if LODFl ,k =0.1 then the increase in flow on line l after a contingency of line k would be: Pl LODFl ,k Pk 0.1 100 10 MW from 50 MW to 60 MW. 43 Flowgates • The real-time loading of the power grid can be assessed via “flowgates.” • A flowgate “flow” is the real power flow on one or more transmission elements for either base case conditions or a single contingency – Flows in the event of a contingency are approximated in terms of pre-contingency flows using LODFs. • Elements are chosen so that total flow has a relation to an underlying physical limit. 44 Flowgates • Limits due to voltage or stability limits are often represented by effective flowgate limits, which are acting as “proxies” for these other types of limits. • Flowgate limits are also often used to represent thermal constraints on corridors of multiple lines between zones or areas. • The inter-zonal constraints that were used in ERCOT until December 2010 are flowgates that represent inter-zonal corridors of lines. 45