Early Delivery Systems
Status
Daryl Cote
TPTF
December 18, 2007
EDS Status Update
2008
2007
Sep
E1 R2
Oct
Nov
Dec
Jan
Feb
ICCP Fail-over / P2P
SE Verification
E2 R3
R3: SE / Telemetry Criteria (SE Tuning)
NOMCR Checkout
Reporting
Network Model Verification
R4: NOMCR / Network Model verification
E2 R4
6-month LMP Posting
RT ICCP
E3 R5
E3 R6
E3 R7
E4 R9
SCED R5.1
SCED R5.2
SCED R5.3: RT ICCP
SCED R5.4: LMP Post
LFC R6.1: ACE
CRR R7.1
R9
% of
MPs
% of
Points
MPs have completed PtP checkout and topology review for all
submitted Nodal points (MP5)
95%
(95%)
99%
(99%)
ERCOT has completed local failover testing with each MP (MP6)
87%
(84%)
n/a
 Tenaska, AEP QSE in 12/07, BTU and Xtend in 01/08.
ERCOT has completed Alarm Processing Configuration and
testing
n/a
10%
 Alarm processing testing will be phased by category and
systems availability.
ERCOT has completed all PtP process documentation to support
checkout for new construction / future changes to telemetry
95%
n/a
 Final process handoff and transition to Operations will occur
by year end.
Outstanding ICCP issues <= 3% per MP (MP5)
100%
(80%)
n/a
 Overall error rate ~1%.
 9 MPs are at a 0% error rate.
 15 MPs tested are at or below 1% error rate.
Quality Code Retesting (MP5)
100%
(92%)
n/a
 36 of 36 MPs regression tested with quality code fix.
EDS 1 Exit Criteria
Comments
XTend having link problems, RCEC completed 1st phase.
 Adding Magic Valley (Q1 ‘08) and College Station (Jan ’08)
– approximately 1000 points.
Legend: % in parentheses are from the 11/26 TPTF update
12/17/2007
2
2
TPTF
• EDS 1 by 12/15
• EDS 2 by 1/15
• EDS 3 by 2/15
MPs
• OnCor
• CenterPoint
• Reliant
• Luminant
# Category Name
1
Frequency Deviation
2
Ancillary Service Capacity
System Operating Limits
SCADA and SE Overloads
3
Participants will perform
limit testing and work with
ERCOT to verify procedures.
SPS
Voltage Limits
4
Resource Control Errors
Forced Outage Detector
5
Planned Outage
Switching Device Status
Forced Outage Detector
6
Planned Outage
Switching Device Status
7
Forced Outage Detector
Planned Outage
Application Status
8
System Status
EMS Security
Definition
ED
Implementation
S
Pr
oc
e
Te du
st re
ed s
C
Te
st by rea
ed Op te
Te
s d
st by
S
ed Op up
by er po
M ato rt
Ps rs
Alarm Processing Approach – Expected Delivery Schedule
When frequency deviation is above the RRS recovery limits
When RRS is deployed partially and frequency deviation above RRS limit
If the real time frequency is above defined threshold
When reserve capacity is below Operator specified limits
When un-deployed regulation-up is below Operator entered threshold
When un-deployed regulation-down is below Operator entered threshold
When telemetered HSL is higher than Net Dependable Capability
When difference between HASL and total energy req < Operator threshold
When the difference between HDL sum and total energy req < Operator threshold
If scheduled LAAR and RT LAAR are differed by threshold
Need to send selected alarms to MIS
When SOL is more than 95% of the limit specified
When MVA line or trans flow > 98% dynamic emer rating or 100% normal rating
When RT flow close to 95% of SPS triggering condition
If real time status of SPS goes disabled, alarms shall be generated
When 345Kv bus voltages are outside specified limits
When 138/69 Kv bus voltages are outside specified limits
When RE (Resource Error) is outside the limits defined by the Operator
Forced line/transformer outages for 345Kv
Forced Bus outages for 345Kv
Planned line/transformer outages for 345Kv
Planned Bus outages for 345Kv
When 345Kv/unit breakers change status
Forced line/transformer outages for 138/69Kv
Forced Bus outages for 138/69Kv
Planned line/transformer outages for 138/69Kv
Planned Bus outages for 138/69Kv
When 138Kv/unit breakers change status
When 69Kv/unit breakers change status
When FOD detects Forced unit outages
When FOD detects Planned unit outages
ICCP Link
TCM, Dynamic Ratings, SE, NSA, PI
LFC, SCED, VSAT, TSAT, FOD
Generate system alarms for, Site Failover, EMS failover, MMS failover
For unauthorized logins to EMS system
3
3
3
3
3
3
3
3
3
3
3
2
2
2
2
2
2
3
2
2
2
2
1
2
2
2
2
1
1
2
2
1
2
3
3
2
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
Start 12/17
Start 12/17
Start 12/17
x
3
12/17/2007
3
TPTF
Release 3 – State Estimator and Telemetry
2008
2007
Sep
E1 R2
Oct
Nov
Dec
Jan
Feb
ICCP Fail-over / P2P
SE Verification
E2 R3
R3: SE / Telemetry Criteria (SE Tuning)
NOMCR Checkout
Reporting
Network Model Verification
R4: NOMCR / Network Model verification
E2 R4
6-month LMP Posting
RT ICCP
E3 R5
E3 R6
E3 R7
E4 R9
SCED R5.1
SCED R5.2
SCED R5.3: RT ICCP
SCED R5.4: LMP Post
LFC R6.1: ACE
CRR R7.1
R9
EDS 2 Release 3 Exit Criteria
TSP/QSE data points reasonably conform to Telemetry
Performance criteria
%
Complete
Comments
40%
SCADA Mappings for Generation in progress – see next slide
324 unobservable points (communicated to TSPs) + ~170 loads to be
mapped by ERCOT; polarity correction with one TSP
Quality of MW and GMW provided by QSEs remains at ~40%
ERCOT Operations have operating procedures in place to address
performance issues
30%
(30%)
8 of 27 procedures have been updated. The remaining will be
completed when Release 3 processes are verified.
Network Security Analysis functions are verified and ERCOT
Operations have procedures in place to manage
76%
(76%)
SE STAT is 95% tested; Contingency Analysis is 95% tested;
Dynamic Ratings is 30% tested; RTMONI is 90% tested.
ERCOT SE is tuned and meets performance criteria
50%
(9%)
See detailed slide for SE Convergence rates over time.
MW/MVar tolerance is 50, SE convergence varies.
Load Modeling restructured, load adaptation and bus load forecast
verified
50%
(25%)
 Schedules have been successfully load and have been verified.
 Load Adaptation cannot be tested until a bug is fixed.
EDW reports correctly post to MIS and can be accessed
0%
SE and Performance Report Schedule is being re-planned.
EDW reports have been verified within ERCOT and by MPs
0%
Telemetry and State Estimator standards in stakeholder process.
Legend: % in parentheses are from the 11/26 TPTF update
12/17/2007
4
4
TPTF
x
x
x
x
x
x
x
x
x
x
Previous Total
10
Current Total
13
0
439
111
811
316
241
271
550
243
143
558
359
0
391
190
546
983
269
760
294
96
1,034
1,238
4%
1%
0%
1%
0%
0%
1%
0%
0%
1%
1%
1%
1%
0%
1%
2%
0%
1%
1%
0%
2%
2%
100%
95%
76%
100%
100%
89%
100%
100%
100%
96%
100%
0%
92%
100%
100%
100%
100%
94%
100%
100%
97%
93%
8,910
9,598
100%
93%
9,843
100%
96%
9,408
nte
red
by
ER
CO
T
ed/
e
rec
e iv
439
106
619
316
241
242
550
243
143
538
359
0
358
190
546
983
269
716
294
96
1,008
1,152
Da
ta
ot a
lP
oin
ts
%o
f P
oi n
ts C
ER
he
CO
cke
TE
d
r ro
rD
eta
il
hec
k
oC
oin
ts t
Po
int
of
%o
fT
x
x
#o
fP
x
tal
#
AEN - Austin Energy
AEP - American Electric Power
APX
BEC - Brazos Electric Coop
BP Energy
BTU - Bryan Texas Utilities
Calpine Power Management
Constellation Energy
Coral Power
CPS - City Public Services
Exelon*
Xtend
FPL
Garland Power and Light
LCRA - Lower Colorado River
NRG
OXY - Occidental Power Svcs
Reliant
STEC - South Texas Electric
Suez Energy Marketing
Tenaska Power Services
Luminant Energy Company
Breaker Status
Combine-cycle Configuration
High Emergency Limit
High Sustained Limit
Low Emergency Limit
Low Sustained Limit
Plant Auxiliary Load
Resource Status
To
QSE List








To
tal
M
Verifying the following:
Ps
Co
Me
mp
tric
lete
s
d
EDS 2 – Generation Verification Status
COMPLETED
Responded to request
Responded to request
COMPLETED
COMPLETED
Responded to request
COMPLETED
COMPLETED
COMPLETED
Responded to request
COMPLETED
Installing new system
Responded to request
COMPLETED
COMPLETED
COMPLETED
COMPLETED
Responded to request
COMPLETED
COMPLETED
Emailed 12/5/2007
Responded to request
on 12/12/2007
on 12/13/2007
on 12/10/2007
on 12/10/2007
on 12/12/2007
on 12/13/2007
on 12/12/2007
‘Complete’ indicates ERCOT mapping is complete and does not reflect data quality
5
12/17/2007
5
TPTF
No
ve
No mb
ve e r
2
No mb 6th
ve e r
2
No mb 7th
ve e r
2
No mb 8th
ve e r
m 2
De be 9th
ce r 3
De mb 0th
ce e r
m 1
De be st
ce r 2
De mb nd
ce e r
3
De mb rd
ce e r
4
De mb th
ce e r
5
De mb th
ce e r
6
De mb th
ce e r
7
De mb th
ce e r
De m 8th
ce be
r
De mb 9th
ce e r
1
De mb 0th
ce e r
m 11
be th
r1
2t
h
Convergence Percentage
100.00
90.00
80.00
70.00
60.00
50.00
40.00
30.00
20.00
10.00
0.00
No Convergence due to
System Problems
12/17/2007
250
200
150
Convergence Rate (%)
6
Tolerance
Release 3 – State Estimator Convergence Rate Status
Convergence Rate
350
300
100
50
0
Convergence
Tolerance
TPTF
6
EDS 2 – State Estimator and Telemetry Criteria
Status of SE and Telemetry Criteria
Telemetry Criteria
Status
At 50
Data Quality (MW/MVar Tolerance)
Comment
Standard is 15 MV/MVar
Telemetry Availability
tbd
Need EDW Report
Critically Important Telemetry
tbd
Need EDS Report
Availability for Critically Important Telemetry
tbd
Need EDW Report
Requests for Redundant Telemetry
tbd
Need Critical Measurement functionality
State Estimator Criteria
Status
Comment
Stable at 50MW variance when
application is running (e.g. not down
due to hardware or database loads)
SE Convergence
Transmission Element SE Accuracy
tbd
Need EDW Report
Critical Transmission Element SE Accuracy
tbd
Need EDW Report
Critical Bus Voltage Accuracy
tbd
Need EDW Report
SCADA Measurement Accuracy
tbd
Need EDW Report
7
12/17/2007
7
TPTF
Oncor
AEP
Texas New Mexico Power
STEC
Rayburn Country Electric
LCRA
Brownsville
CenterPoint Energy
Brazos
Total Points
147 104
134 134
22
22
16
4
15
15
15
15
11
11
11
11
10
8
381 324
85%
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
N
N
N
N
N
Y
N
N
Y
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
N
12/31/2007
tbd
12/15/2007
12/15/2007
12/15/2007
12/10/2007
12/15/2007
12/15/2007
12/15/2007
of
12
/1
4/
20
07
A
s
N
um
be
r
Observability Status
of
po
R
ev
in
is
ts
ed
nu
Li
m
st
be
/e
ro
-m
fp
ai
Li
ls
st
oi
/e
en
nt
-m
s
tB
ai
Se
y
lr
rv
ER
ec
ic
C
ei
e
O
ve
R
Po
T
eq
d
in
by
ue
ts
st
T
L
SP
M
s
oa
iti
R
de
ec
ga
ei
tin d b
ve
y
g
B
us Ac ERC d by
es tion O
ER
C
no s fo T
O
T
rd
w
a
O
t
a
bs
Es
no
er
tim
va t su
at
bm
bl
ed
e
itt
D
ed
at
e
to
su
bm
it
SR
Observability Status
Initial response received
Initial response. Sent e-mail
Questions resolved.
Questions resolved.
Initial response received
Questions resolved.
Resent data
Initial response. Sent e-mail
Initial response received
Observability Status
147
160
134 134
Points (No.)
140
120
Number of points
Revised number of points
104
100
80
60
40
22
22
16
20
15
4
15
15
15
11
11
11
11
10
8
zo
s
B
ra
er
gy
te
rP
oi
nt
w
En
ns
vi
ll
e
A
C
en
n
R
ay
bu
r
8
LC
R
B
ro
tr
ou
n
C
M
N
ew
xa
s
Te
12/17/2007
El
ec
tr
ic
y
ex
ic
o
ST
EC
er
Po
w
nc
or
O
Status as of 12/14
A
EP
0
TSP
8
TPTF
Release 4 – NMMS / NOMCR
2008
2007
Sep
E1 R2
Oct
Nov
Dec
Jan
Feb
ICCP Fail-over / P2P
SE Verification
E2 R3
R3: SE / Telemetry Criteria (SE Tuning)
NOMCR Checkout
Reporting
Network Model Verification
R4: NOMCR / Network Model verification
E2 R4
6-month LMP Posting
RT ICCP
E3 R5
E3 R6
E3 R7
SCED R5.1
SCED R5.2
SCED R5.3: RT ICCP
SCED R5.4: LMP Post
LFC R6.1: ACE
CRR R7.1
R9
EDS 2 Release 4 Entry Criteria
NMMS Phase 2A has completed FAT Testing
%
Complete
0%
MIS/NMMS link has completed ITest and is installed in EDS
Comments
Planned release of NMMS 2A on January 2, 2008
47%
(25%)
 9 of 17 TSPs have successfully connected through Citrix to
notepad (not all the way to NMMS)
NMMS is installed in EDS
0%
Hardware build in progress
EMS Nodal Importer has completed ITest and is installed in EDS
0%
EMS 4 FAT end scheduled for 2/15; will not migrate to EDS until
MMS importer also available
NMMS database has been successfully loaded with:
•ERCOT NOM database; ICCP modeling point database;
Ownership / operatorship data
0%
Currently working with TSPs/MPs (and ERCOT working groups) on
data information for loading. Waiting on NMMS 2A delivery to install
and configure data
NMMS database is placed under full change control
0%
Once data is loaded and verified by MPs, DB will be under ERCOT
change control.
Any direct communication with John Hall or John Webb should be sent to
EDS2@ercot.com effective immediately
Legend: % in parentheses are from the last update
12/17/2007
9
9
TPTF
Release 5 - SCED
2008
2007
Sep
E1 R2
Oct
Nov
Dec
Jan
Feb
ICCP Fail-over / P2P
SE Verification
E2 R3
R3: SE / Telemetry Criteria (SE Tuning)
Reporting
Network Model Verification
NOMCR Checkout
R4: NOMCR / Network Model verification
E2 R4
6-month LMP Posting
RT ICCP
E3 R5
E3 R6
E3 R7
E4 R9
SCED R5.1
SCED R5.2
SCED R5.3: RT ICCP
SCED R5.4: LMP Post
LFC R6.1: ACE
CRR R7.1
R9
EDS 3 Release 5 Exit Criteria
%
Complete
Comments
QSEs w/ Resources able to submit COP & TPO for entire
portfolio
100%
•Known issues with Output Schedules and Performance issues (root
cause analysis done on performance issues and passed to teams)
SCED Inputs verified: HRL, LRL, SURAMP, SDRAMP, HDL,
LDL; GTBD, ICCP
40%
(40%)
See next slide
SCED Outputs verified: QSE’s ability to receive Resource
Base Points and LMPs via ICCP
10%
(10%)
Verifications began November 1st. A number of QSEs have reported
receiving Base Points and LMPs – ERCOT reviewing SCADA mapping.
Base Point and LMP calculation verified for Resources with
Offer Curves or Output Schedules
0%
Reports
50%
(0%)
LMPs verified for Reasonability and posted to MIS for Market
Participant review
12/17/2007
Verifications to begin in January.
Reports related to SCED are available in draft form on MIS and
nodal.ercot.com
See next slide
0%
Legend: % in parentheses are from the 10/22 TPTF update
10
10
TPTF
SCED Issues
1.
2.
3.
4.
5.
6.
7.
8.
EMS Hardware insufficient for user base and functionality
– INF prioritized production hardware for EMS – will use for EMS 3B
SCADA mapping resulted in all Combined Cycles MW telemetry levels set to 0
– Corrected in SCADA load on Friday 12/14; still needs to be verified
Interface table for Constraint Names incorrect so SCED is not able to process
constraint names & shift factors
MPs sending Incorrect values for CC configuration causes SCED failure
– Working with EMS team to implement data check and MPs to send valid
configuration values
MPs sending HSL < LSL resulting in SCED failure
– Working with MPs to resolve and adding validation in EMS to set LSL = HSL
when telemeter HSL<LSL
MPs sending resource status of off when actual telemeter MW output is > 0
– SCED sets basepoint = 0
MPs sending invalid resource status (e.g. 050)
– SCED ignores the unit
DC TIE Telemetry missing and DC Tie calculation not working
– Adding telemetry and EMS team resolving calculation function
Joint effort between ERCOT and MPs to resolve most of these will enable
reasonableness declaration
11
12/17/2007
11
TPTF
Release 6 - LFC
2008
2007
Jan
Feb
Mar
Apr
May
Jun
R4: NOMCR / Network Model verification
E2 R4
6-month LMP Posting
E3 R5
E3 R6
R5.3
SCED R5.4: LMP Post
R6.1: ACE
R6.2: QSE Testing
R7.1
E3 R7
R7.2
R7.3
R6.3: TST
R7.4
E4 R9
EDS 3 Release 6.1 Entry Criteria
%
Complete
Comments
ICCP and the Generation Subsystem (LFC, RLC and Resource
Qualification Testing) has passed FAT and completed
acceptable portions of the ITEST.
0%
EMS 3B FAT expected to complete 12/21 (revised from 12/7)
ERCOT has validated that the RLC outputs and Emergency
Base Point calculator values are calculated in the ERCOT
Nodal system as expected per the Nodal EMS Design
documents.
0%
Same as above
QSEs with Resources have submitted the 6.1 test form to
ERCOT
0%
ERCOT expects to distribute the form on January 2. QSEs complete the
form and send it back to ERCOT 2 business days before their scheduled
6.1 testing date.
Any direct correspondence with Brain Davison should be directed to
EDS3@ercot.com effective immediately
12/17/2007
Legend: % in parentheses are from the 10/22 TPTF update
12
12
TPTF
EDS 3 – LFC Testing Schedule
13
12/17/2007
13
TPTF
EDS 3 – LFC Testing Schedule
14
12/17/2007
14
TPTF
Release 7 - CRR
• Kick-off meeting scheduled for January 18th from 1-3pm
– http://www.ercot.com/calendar/2008/01/20080118-EDS3.html
• Working on 7.0 activities
– Discrepancies between CRR Account Holder forms and emails
to eds3 indicating intention to participate
• See next slide
• Planning to present an updated version of CRR handbook to
TPTF at the January 21-23rd meeting. Updated version available
at http://nodal.ercot.com/docs/pd/eds/index.html#oth
15
12/17/2007
15
TPTF
Release 7 - Participants
16
12/17/2007
16
TPTF
EDS 4 – Release 9.1
• MMS, EIP, and INT teams working aggressively to support a
January 15th start of Release 9.1
– Will schedule support calls similar to SCED
– Might have to start with QSEs desiring to use Web Services first
if ERCOT developed UI not available by January 15th
• Scheduled a Release 9.1 kick-off WebEx for Thursday 12/20
from 9-11 am: http://www.ercot.com/calendar/2007/12/20071220EDS4.html
• Significant number of QSEs have missed deadline to submitted
intent emails to EDS4@ercot.com.
– See next slide
17
12/17/2007
17
TPTF
EDS 4 Release 9
•
QSEs expected for EDS4, but not
yet registered
– Affordable Power Plan
– Alcoa Power Marketing
– Alliance Power Company
– Ambit Energy
– Ambridge Energy
– Amigo Energy
– Andeler Corporation
– APN Starfirst
– APNA Holding
– Aquila
– Barclays Bank
– Bear Energy
– Blu Power of Texas
– Brilliant Energy
–
–
–
–
–
–
–
–
–
–
–
–
–
–
–
–
Cargill Power Markets
Citadel Energy Products
Clearview Electric
ConocoPhillips Company
Constellation NewEnergy
DPI Energy
Duke Energy Ohio
Eagle Energy Partners
Econnergy Energy Company
Electric Now
First Choice Power
Formosa Utility Venture
Freedom Power
Fulcrum Power Service
Glacial Energy
Himalaya Power
18
12/17/2007
18
TPTF
EDS4 Release 9
•
QSEs expected for EDS4, but not yet
registered (continued)
– Integrys Energy Services
– JP Morgan Ventures Energy
Corporation
– Just Energy Texas
– Kansas City Power and Light
– Keystone Energy Partners
– Lehman Brothers Commodity Services
– Liberty Power
– Merrill Lynch Commodities
– Mirant Energy Trading
– National Power Company
– North American Energy Credit and
Clearing Delivery
– NRG
– ONPAC Energy
– PEPCO Energy Services
– Pre Buy Electric
– Repower
–
–
–
–
–
–
–
–
–
–
–
–
–
–
Scurry County Wind
Sitara Energy
Spark Energy
Stream Gas and Electric
Tara Energy
Texas Retail Energy
Texas Star Energy
Texpo Energy
Topaz Power Management
Trieagle Energy Supply
Urban Energy Source
Viasyn
WCW International
Xtend Energy
19
12/17/2007
19
TPTF