SPP - Power Costs, Inc.

advertisement
Analyze
Optimize
Enterprise
PCI Outage-Management &
GADS Modules
August 11, 2011
 Power Costs, Inc. 2010 All rights reserved. Confidential and Proprietary to
Power Costs, Inc. May not be distributed or reproduced without permission
PCI GSMS Bid-to-Bill Solution
for SPP Market
PCI GenManager
 Bid Formulator
 Bid Evaluator
 LMP Manager
 ISO Communication
 Wind Module
 Pre-Settlement
 Shadow Settlement
 Settlement Allocation
 P&L Analyzer
PCI GenPortal & GenBase
 Datamart
 Deal Capture
 Gas Management
 Outage Management &
GADS
PCI GenTrader
 Unit Commitment
 Power Costs, Inc. Confidential and Proprietary 2010
www.PowerCosts.com
Page 1
Who currently Uses
PCI Software Solutions?
PCI GSMS Suite is currently used to Manage around 50% of the US Generation Capacity.
ERCOT (80%), MISO (70%), CAISO (90 %), PJM (30%), SPP (85%)
 Power Costs, Inc. Confidential and Proprietary 2010
www.PowerCosts.com
Who currently Uses
PCI Software Solutions?
PCI GSMS Suite is currently used to Manage around 50% of the US Generation Capacity.
ERCOT (80%), MISO (70%), CAISO (90 %), PJM (30%), SPP (85%)
PCI
GT
PCI
GP
PCI
GT
PCI
GP
American Electric Power
X
X
Duke Energy
X
X
City Public Service – San Antonio
X
X
ERCOT
Direct Energy
X
X
CAISO
Xcel Energy
X
X
X
MISO
MISO
SPP
CDWR
X
CAISO
Optim Energy
X
X
ERCOT
Alliant Energy
X
MISO
Sempra Energy
X
X
CAISO
Pacific Gas & Electric
X
NRG (Texas)
X
Bryan Texas Utilities
X
GDF Suez North America
X
X
ERCOT
MidAmerican Energy
X
X
MISO
Progress Energy
X
X
PA
Westar Energy
X
X
SPP
Orlando Utilities Commission
X
NIPSCO
X
X
MISO
FirstEnergy
X
X
PJM
San Diego Gas & Electric
X
X
CAISO
GenOn
X
X
Customer
NV Energy
Consumers Energy
X
PCI
GM
Ameren Energy (UE & AEM)
X
X
MISO
Dominion
X
X
PJM
Kansas City Power & Light
X
X
SPP
X
SPP
Empire District
Florida Power & Light
X
Madison Gas & Electric
X
X
MISO
Calpine Energy
X
X
ERCOT
Topaz Power
X
X
ERCOT
Lower Colorado River Authority
X
X
ERCOT
City of Ames
MISO
Southern California Edison
X
X
CAISO
Oklahoma Gas & Electric
X
X
SPP
 Power Costs, Inc. Confidential and Proprietary 2010
Customer
www.PowerCosts.com
PCI
GM
CAISO
X
Objectives for PCI
Outage-Management Module
 Automate workflow to:
– Capture all Plant Outage
information required by ISO
– Submit outage & deratings to
the new SPP Outage Scheduler
system
– Manage all Communications and
approval process with ISO
schedulers
– Manage Communications and
approval process with Plant
Managers
 Submit outage data to NERC GADS
and produce plant performance
reports
 Use outage & derating data to
formulate DA & RT offers and
forecast DA awards for generators
 Power Costs, Inc. Confidential and Proprietary 2010
www.PowerCosts.com
Page 4
1/1/2007
SPP Outage Management
SPP is replacing their “OPS1” Outage Scheduler Solution
 SPP Go-Live is 9/13 using SPP Web page.
 API becomes available on 9/20.
 Option to keep existing business process or migrate to
direct submit by Generators.
 SPP Outage Scheduler will be integrated into Current
Market now and pushed over to future market.
 PCI Outage Management can implement with SPP API so
clients can manage outages from PCI instead of from
SPP Web page.
 PCI Outage Management functionality can be delivered
for use with new SPP Outage Scheduler.
 Power Costs, Inc. Confidential and Proprietary 2010
www.PowerCosts.com
Page 5
1/1/2007
Major changes from OPS1
Important Differences between OPS1 and CROW
 No longer limited to submission at a Balancing Authority
level, may submit at the GOC level.
 SPP’s CROW will use complete names. PCI automatically
translates from your in house names to the SPP names.
 Generation derates will be handled differently from what is
currently in OPS1. Generation derates reflect the unit’s Net
Available Capacity.
– Ex: 100 MW unit is derated to 75 MW. Unit is available to
produce 75 MW. (In OPS2 you would enter a 25 MW
curtailment.)
 Power Costs, Inc. Confidential and Proprietary 2010
www.PowerCosts.com
Page 6
1/1/2007
Capabilities of PCI
Outage-Management Module
 Enter, edit, and submit outage requests:
–
–
–
–
Planned (>= 48 hours Lead Time)
Urgent (>= 24 hours to 7 days Lead Time)
Emergency (<= 24 hours Lead Time)
Forced (<= 1 hours Lead Time)
 Manage 3-way communication between
plant managers, portfolio managers,
and ISO operators:
– Submit requests internally for
approval and manage approval
process
– Submit outage requests to ISO
Outage Schedule for ISO approval
– Track ISO approvals
– Manage pending requests
– Track submissions and alarms
 Power Costs, Inc. Confidential and Proprietary 2010
www.PowerCosts.com
Page 7
Main Outage-Management
Screen
 Provide Web-Based GUI to enter &
update outages
 Provide XML data links to
communicate with ISO
 Provide filters & validation rules to
speed up and automate outagemanagement workflow
 Power Costs, Inc. Confidential and Proprietary 2010
www.PowerCosts.com
Page 8
1/1/2007
 Sections
divide up
read-only,
required, and
optional fields
 Access to
historic
reviews
 Create
recurring
outages on
new
 Power Costs, Inc. Confidential and Proprietary 2010
www.PowerCosts.com
Page 9
Sample Workflow Process
Single, coordinated stream of data.
 Power Costs, Inc. Confidential and Proprietary 2010
www.PowerCosts.com
Provide Gantt Chart to
Easily Track Ouatges
 View outages
using a Gant chart.
 Filter units and
types of outage.
 Select / Edit outage
details.
 Power Costs, Inc. Confidential and Proprietary 2010
www.PowerCosts.com
Page 11
1/1/2007
Using PCI Outage-Management Module
to Automate NERC GADS Reporting

Capture all outage & derating
data required to support
NERC GADS reporting:
– Assign unique GADS Id
for each outage
– Provide combo box to
allow user to select
GADS cause code
– Allow user to specify unit
code and utility code
required for NERC
reporting
– Assign a 2-character
event type to describe
outage
– Specify an equipment
type associated with
outage event
 Power Costs, Inc. Confidential and Proprietary 2010
www.PowerCosts.com
Page 12
Using PCI Outage-Management Module
to Create GADS Performance Reports






Capture EMS Breaker
Status.
Can automatically
Generate Outage
Tickets based on the
breaker status
Compute GADS
Performance
Statistics
Generate GADS
Performance Reports
by Plant/Unit
Generate NERCcompliant files
Option to ETL GADS
Data to PCI Data
Warehouse for BI
Reporting
 Power Costs, Inc. Confidential and Proprietary 2010
www.PowerCosts.com
Page 13
Business Intelligence / Data Warehouse Analytics
 Example 1
–
–
GADS Reporting
Event Reporting and Analysis
 Example 2
–
–
“In the Money” Analysis
Compare GADS Performance Records to
Performance History in the ISO
 Power Costs, Inc. Confidential and Proprietary 2010
www.PowerCosts.com
Page 14
Sample PCI Report to Summarize
Turbine Service Hours
 Power Costs, Inc. Confidential and Proprietary 2010
www.PowerCosts.com
Page 15
Fully Integrated
with PCI GSMS Modules
• PCI Outage Manager is fully
integrated with other PCI Modules
• Outages can be entered in the PCI
Outage-Management Module. After
outage is approved:
 PCI Bid Formulator can
automatically adjust offer
parameters to reflect the
current outage status
 PCI Bid Evaluator can be run to
Forecast DA Awards
 PCI GenTrader can use outage
information for unitcommitment and production
costing runs
 Power Costs, Inc. Confidential and Proprietary 2010
www.PowerCosts.com
Page 16
Summary of PCI Extended
Outage-Management Module
 Manage outage lifecycle:
– Submit new outage requests
– Update existing requests
– Download status of existing
outages
 Fully integrated with:
– ISO Outage Scheduler
– Other PCI GSMS modules
(GenTrader, Bid Evaluator, Bid
Formulator)
 Automate NERC GADS Reports
 Power Costs, Inc. Confidential and Proprietary 2010
www.PowerCosts.com
Page 17
For More Information
Ali Merchant
630-770-1055
[email protected]
Stuart Wright
303-940-1444
[email protected]
Bryan Kelly
916-799-2006
[email protected]
Jason Hebert
713-231-7454
[email protected]
PCI GENERATION SUPPLY MANAGEMENT SYSTEM™

Operations & Trading
– Optimal unit commitment and
economic dispatch
– Fuel scheduling
– Ancillary services optimization

Post Analysis
– P&L Analyzer

Gas Management
– Forecast Gas Burn
– Optimize Pipeline Uses
– Nominate Gas & Pipeline Volumes
 Power Costs, Inc. Confidential and Proprietary 2010

Bid-To-Bill Automation
– Forecast LMPs
– Automate XML Communications with
ISO
– Create Unit & Demand Bids
– Evaluate Bidding Strategies
– Perform Shadow Settlement
– Manage Outages & Deratings

Transaction Management
– Deal Capture
– Create MISO Financial Contracts
– Settlement of Bilateral Transactions