DESIGN AND STABLISHMENT OF THE ELECTRICAL

advertisement
PROJECT 1: PRE ENGINEERING EVALUATION
Engr. Fernan D. Dematera, Project 1 Leader
1.
To determine the existing electrical equipment and
devices (ex. Size of wires, type of connection, type
of electrical devices) of Bicol University Main
Campus
2. 2. To find out if each building in the Main Campus
comply with standards based on Philippine
Electrical Code latest edition (2009
1.
To determine the existing kVA installed capacity
of transformers at the B.U. Main Campus and to
determine the buildings supplied by each
transformer
2.
To determine the peak load for each building at
the Main Campus
3.
To determine if BU Main can comply with all the
requirements of N.G.C.P. for direct connection
A. PROJECT 1:PRE – ENGINEERING EVALUATION
STUDY 1: Status of Existing Electrical Equipments and Devices
SCHEDULE
OBJECTIVES
EXPECTED OUTPUT
ACCOMPLISHMENT
Work Activity
1. To determine
the existing
electrical
equipment and
devices (ex. Size
of wires, type of
connection, type
of electrical
devices) of Bicol
University Main
Campus
1. Inventory of Electrical
Equipment and Devices
Sent letters of request to
Offices of the Deans and
Heads of the buildings at
main campus of Bicol
University asking for the
permission to have a cite
survey of the electrical
equipment and devices
Time Frame
April 2011 to
June 2011
Made the inventory form
for the existing electrical
equipment and devices
2. To find out if
each building in
the Main
Campus comply
with standards
based on
Philippine
Electrical Code
latest edition
(2009)
Conduct ocular inspection
of the service entrance of
each building , listing the
types of wire being used,
and identify the
connection.
Refer to the latest edition
of PEC which is the 2009
edition.
September to
December
2011
December
2011
1
2
3
4
5
6
7
8
9
1
0
1
1
1
2
A. PROJECT 1:PRE – ENGINEERING EVALUATION
STUDY 2: Analysis of Installed Transformers at the BU Main Campus
ACCOMPLISHMENT
OBJECTIVES
EXPECTED OUTPUT
1. To determine
the existing
kVA installed
capacity of
transformers at
the B.U. Main
Campus and to
determine the
buildings
supplied by
each
transformer
Work Activity
Time Frame
1. List of KVA installed
capacity of the existing
transformers and the
buildings connected to
it.
1. Coordinate with the
PDMO for the complete
list of transformers at BU
main campus including
the connection to the
buildings
April 2011
2. To determine
the peak load
for each
building at the
Main Campus
2. Tabulation of the
peak load for each
building the Main
Campus
2. Tabulate the peak load
for every building using
clamp–on ammeter
3. To determine if
BU Main can
comply with all the
requirements of
N.G.C.P. for direct
connection
3. List of requirements
for direct connection to
NGCP
3. Coordinate with the
proper agencies for the
requirements of direct
connection like NGCP &
ERC.
April 2011 to
March 2012
January 2012March 2012
SCHEDULE
1
2
3
4 5
6
7
8
9
1
0
1
1
1
2
1. Based on the data of the peak load being measured
in every building, the approximate daily KW
consumption by the BU Main Campus ranges from
500 – 600.
2. Service entrance conductor shall not be located in
wet locations such as down spout, gutters and etc.,
Such case involves BU College of arts and Letters
were in, the service drop conductors are located near
the down spout of the college building.
3.
Service raceway shall be equipped with a raintight service
head at the point of connection to service drop conductors.
Some of the building in the BU Main Campus does not
comply with the code. Some are already damage and subjected
for replacement: IPESR and other establishment of BUCE.
4.
Service conductors must be readily accessible and must be at
standard clearance and height.
-service drop supplying loads into some college building
does not comply with the code likewise in the case of BU
admission office wherein service head are not readily
accessible and excide the standard height prescribe by the
code.
5. The smallest service conductor shall be at 8.Omm2
at 60 ampere trip.
- some establishments in BU Main Campus did not
comply in the code.
6. Standard mounting height for Kilo-watt Hour meter
shall be implemented.
Standard mounting height must be 6ft.
1. The requested research equipments such as Megger,
heavy duty clamp ammeter, ladder was not yet
delivered/purchased.
2. Two succeeding Research Assistants hadn’t renew for
the contract.
3. WEC was not considered to the Project Leader due
to its part time status from June to October 2011.