Southern Natural Gas Company

advertisement
Southern Natural Gas Company
2013 Outage Review Meeting
Customer con call and Lync Online
Meeting
August 21, 2013
1
Welcome
2
Agenda
• Review of Unscheduled Outages
• Review of Current and Upcoming Outages
– September through December
• North System
• South System
• South Louisiana
• Contacts
3
Disclaimers
• Anticipated Impacts are estimates. Actual nominations, market
demand, weather and pipeline conditions, etc. will determine if, and
through what level, restrictions become necessary.
• Unless otherwise stated, all scheduled dates represent gas days as
defined in the Southern Natural Gas Pipeline tariff to mean a period of
twenty-four consecutive hours, beginning and ending at 9:00 a.m.
(Central Clock Time).
• Scheduled dates are subject to change.
• Projects may be added, altered, delayed or cancelled.
• SNG will provide notice of such additions or changes via SoNet Premier
postings.
• Dates as posted on SoNet should be deemed correct in the event of
conflicts between SoNet posted dates and dates within this
presentation.
4
Color Key for Maps
• Green
– No Impact Anticipated
• Yellow
– Restrictions are possible
– With extended duration, restrictions could be
necessary from time to time
– Meter(s) affected are denoted with (M)
• Red
– Restrictions are probable
5
Southern Natural Gas Pipeline
Chattanooga
Muldon
MS
North System
GA
SC
Aiken
Atlanta
Bear Creek
Thomaston
Enterprise
Gwinville
LA
South System
AL
Elba
Albany
Pearl River
South Louisiana
Franklinton
White Castle
Toca
FL
Compressor Station
Storage Field
LNG
6
Southern Natural Gas Pipeline
Unscheduled Outage Update
Chattanooga
Muldon
GA
MS
SC
Aiken
Atlanta
Bear Creek
Thomaston
Enterprise
Gwinville
AL
LA
Elba
Albany
Pearl River
Franklinton
White Castle
Toca
FL
Compressor Station
20” Duck Lake – Franklinton Line
Anomaly repairs under way. Return
to service mid October
Cap reduced up to 65 MMcf/d
Storage Field
LNG
7
SNG North System
Maintenance Review September through
December
Chattanooga
Anomaly repairs on the
Gadsden Branch and loop
lines-oneHuntsville
line at a time. Now
thru end of October.
Pressure D/S could be lower
Muldon Fall Shut-in Test
10/01/13 thru 10/07/13
DIQ and DWQ allocated 36%
AL
Muldon Storage
Bear Creek Fall Shut-in Test
10/15/13 thru 10/21/13
DIQ and DWQ allocated 64%
Tarrant
Providence
Louisville
Pickens
Atlanta
Bell Mills
Pell City
McConnells
MS
Rome
DeArmanville
GA
Reform
Onward
Bear Creek Storage
Rankin
Bienville
Logansport
LA
Bienville Station 8-10 hour
outage 10-8-13 receipt points
west of Bienville impacted
Southern will be conducting other
general maintenance during this
period
Pressure Test 2nd North Main
East of Louisville
9/03/13 thru 10/8/13
North system receipts may be reduced
Muldon inj & w/d could be limited
Pipe replacement North Main
Loop Line west of Dearmanville
October
No Capacity reductions
anticipated
Dearmanville Engine
maintenance beginning
September thru mid
October.
No additional impact
anticipated
Pressure Test 2nd North Main
East of Reform
10/13 thru 11/13
Capacity reduced significantly
Compressor Station
Storage Field
8
SNG South System
Maintenance Review September through
December
MS
Pipeline work related to DOT
highway relocation
7-29-13 thru 9-5-13
10-25-13 thru 11-9-13
CapacityAtlanta
reductions may occur
Selma unit maintenance
In October
Hartwell
Aiken
GA
Ocmulgee
Wrens
Hallgate
Enterprise Station Outage
until sometime in October
Rose Hill (M) 504002
Cap reduced up to 400 MMcf/d
AL
Ellerslie
Ocmulgee Station outage for
two days mid November
Cap reduced up to 200 MMcf/d
Thomaston
Gallion
York
Selma
Elmore
Maintenance on the 16” South
Riceboro
Main Loop. 4 weeks in October
Cap reduced up to 50 MMcf/d
Auburn
Holy Trinity
Enterprise
Bay Springs
Gwinville
Rose Hill (504001 and 504002)
Station shut-in 7/29/13 until
early September.
Auburn unit maintenance
In November
Anomaly repairs North
Clay line in OctoberCustomers may
experience lower
pressures
Elba
Albany
Brookman
Pavo
Compressor Station
Storage Field
LNG
Southern will be conducting other general
maintenance during this period
9
SNG South Louisiana System
Maintenance Review September through
December
Gwinville
MS
LA
Pearl River
Franklinton
White Castle, Shadyside
Unit Maintenance
Mid September - mid October
West Leg
White Castle
Shadyside
East Leg
TOCA
Toca
20” Duck Lake – Franklinton Line
Anomaly repairs under way. Return
to service mid October
Cap reduced up to 65 MMcf/d
Southern will be conducting other general
maintenance during this period
Compressor Station
Storage Field
10
Gas Control Contacts
• Nancy Barton – Manager
(713) – 420 – 6191 (office)
(713) – 204 – 4815 (cell)
nancy_barton@kindermorgan.com
• Kal Dankovich – Outage Coordinator
(713) – 420 – 7522 (office)
(205) – 325 – 7305 (Gas Control)
kalman_dankovich@kindermorgan.com
• Jerry Peterson – Operations Analyst
(205) – 325 – 7345 (office)
(205) – 325 – 7305 (Gas Control)
jerry_peterson@kindermorgan.com
• Paul Reed – Operations Analyst
(205) – 325 – 7655 (office)
(205) – 325 – 7305 (Gas Control)
paulr_reed@kindermorgan.com
11
Questions?
12