Southern Natural Gas Company 2013 Outage Review Meeting Customer con call and Lync Online Meeting August 21, 2013 1 Welcome 2 Agenda • Review of Unscheduled Outages • Review of Current and Upcoming Outages – September through December • North System • South System • South Louisiana • Contacts 3 Disclaimers • Anticipated Impacts are estimates. Actual nominations, market demand, weather and pipeline conditions, etc. will determine if, and through what level, restrictions become necessary. • Unless otherwise stated, all scheduled dates represent gas days as defined in the Southern Natural Gas Pipeline tariff to mean a period of twenty-four consecutive hours, beginning and ending at 9:00 a.m. (Central Clock Time). • Scheduled dates are subject to change. • Projects may be added, altered, delayed or cancelled. • SNG will provide notice of such additions or changes via SoNet Premier postings. • Dates as posted on SoNet should be deemed correct in the event of conflicts between SoNet posted dates and dates within this presentation. 4 Color Key for Maps • Green – No Impact Anticipated • Yellow – Restrictions are possible – With extended duration, restrictions could be necessary from time to time – Meter(s) affected are denoted with (M) • Red – Restrictions are probable 5 Southern Natural Gas Pipeline Chattanooga Muldon MS North System GA SC Aiken Atlanta Bear Creek Thomaston Enterprise Gwinville LA South System AL Elba Albany Pearl River South Louisiana Franklinton White Castle Toca FL Compressor Station Storage Field LNG 6 Southern Natural Gas Pipeline Unscheduled Outage Update Chattanooga Muldon GA MS SC Aiken Atlanta Bear Creek Thomaston Enterprise Gwinville AL LA Elba Albany Pearl River Franklinton White Castle Toca FL Compressor Station 20” Duck Lake – Franklinton Line Anomaly repairs under way. Return to service mid October Cap reduced up to 65 MMcf/d Storage Field LNG 7 SNG North System Maintenance Review September through December Chattanooga Anomaly repairs on the Gadsden Branch and loop lines-oneHuntsville line at a time. Now thru end of October. Pressure D/S could be lower Muldon Fall Shut-in Test 10/01/13 thru 10/07/13 DIQ and DWQ allocated 36% AL Muldon Storage Bear Creek Fall Shut-in Test 10/15/13 thru 10/21/13 DIQ and DWQ allocated 64% Tarrant Providence Louisville Pickens Atlanta Bell Mills Pell City McConnells MS Rome DeArmanville GA Reform Onward Bear Creek Storage Rankin Bienville Logansport LA Bienville Station 8-10 hour outage 10-8-13 receipt points west of Bienville impacted Southern will be conducting other general maintenance during this period Pressure Test 2nd North Main East of Louisville 9/03/13 thru 10/8/13 North system receipts may be reduced Muldon inj & w/d could be limited Pipe replacement North Main Loop Line west of Dearmanville October No Capacity reductions anticipated Dearmanville Engine maintenance beginning September thru mid October. No additional impact anticipated Pressure Test 2nd North Main East of Reform 10/13 thru 11/13 Capacity reduced significantly Compressor Station Storage Field 8 SNG South System Maintenance Review September through December MS Pipeline work related to DOT highway relocation 7-29-13 thru 9-5-13 10-25-13 thru 11-9-13 CapacityAtlanta reductions may occur Selma unit maintenance In October Hartwell Aiken GA Ocmulgee Wrens Hallgate Enterprise Station Outage until sometime in October Rose Hill (M) 504002 Cap reduced up to 400 MMcf/d AL Ellerslie Ocmulgee Station outage for two days mid November Cap reduced up to 200 MMcf/d Thomaston Gallion York Selma Elmore Maintenance on the 16” South Riceboro Main Loop. 4 weeks in October Cap reduced up to 50 MMcf/d Auburn Holy Trinity Enterprise Bay Springs Gwinville Rose Hill (504001 and 504002) Station shut-in 7/29/13 until early September. Auburn unit maintenance In November Anomaly repairs North Clay line in OctoberCustomers may experience lower pressures Elba Albany Brookman Pavo Compressor Station Storage Field LNG Southern will be conducting other general maintenance during this period 9 SNG South Louisiana System Maintenance Review September through December Gwinville MS LA Pearl River Franklinton White Castle, Shadyside Unit Maintenance Mid September - mid October West Leg White Castle Shadyside East Leg TOCA Toca 20” Duck Lake – Franklinton Line Anomaly repairs under way. Return to service mid October Cap reduced up to 65 MMcf/d Southern will be conducting other general maintenance during this period Compressor Station Storage Field 10 Gas Control Contacts • Nancy Barton – Manager (713) – 420 – 6191 (office) (713) – 204 – 4815 (cell) nancy_barton@kindermorgan.com • Kal Dankovich – Outage Coordinator (713) – 420 – 7522 (office) (205) – 325 – 7305 (Gas Control) kalman_dankovich@kindermorgan.com • Jerry Peterson – Operations Analyst (205) – 325 – 7345 (office) (205) – 325 – 7305 (Gas Control) jerry_peterson@kindermorgan.com • Paul Reed – Operations Analyst (205) – 325 – 7655 (office) (205) – 325 – 7305 (Gas Control) paulr_reed@kindermorgan.com 11 Questions? 12