TRIO CONSULTING & MANAGEMENT, LLC DYSINGER NO. 1 DAILY REPORT August 14, 2012 (Tuesday) MI Lear Dozer Service & started location for Rockin “R” Drilling Rig No. 1. August 18, 2012 (Saturday) Jerry’s Waterline Service set 500 bbl frac tank for drilling water & laid 2” poly line from tank to location. Greco Oilfield Service installed 12’ gate in addition to existing 16’ gate for rig. Rocking “R” Drilling to move in 8/20/12. August 21, 2012 (Tuesday) ORT: WOC. Depth @ 227’. Dev. @ 227’ – ½°. PP=350, SPM=56, RPM=85, wt. on bit 10,000 lbs. Bit #1, 12¼” PDC, Ser. No. 3465’, in @ 40’, hrs. on bit 4¼, ftg on bit 187’. Spudded @ 2:15 p.m. 8/20/12. Drilled 4¼ hrs., made 187’. Down: 8 hrs. MIRU; ¼ hr. circ.; ¼ hr. POOH; 3¼ hrs. run & cement csg; 5 hrs. WOC; 4½ hrs. NU BOP; ½ hr. TIH. TIH w/Texas pattern GS, 1 jt 8 5/8”, 24#/ft csg, insert float & 4 jts of csg w/centralizer on top of each jt for a total of 4. MIRU Quasar Energy Services. Cemented csg w/140 sxs Class “A” + 2% CC + ¼#/sx Cellflake. Cmt circ. to surface. Circ. total of 11 bbs cmt to pit. PD @ 8:05 p.m. Checked float. Leaking. Closed csg in & RD Quasar. Cmt holding @ surface. Notified Cynthia, RRC District 7B @ 11:00 a.m. Job #9337. Surface csg set as follows: Length(ft) Depth(ft) Set below KB 12.50 12.50 4 jts new 8 5/8”, 24#/ft, J-55 csg 161.56 174.06 Insert Float 0.00 174.06 1 jt new 8 5/8”, 24#/ft, J-55 csg 40.34 214.40 Texas Pattern Guide Shoe 1.00 215.40 August 22, 2012 (Wednesday) ORT: Drilling. Depth @ 1763’. Dev. @ 724’ – ½°, @ 1227’ – bullseye. PP=680, SPM=56, RPM=70, wt. on bit 8,000 lbs. Bit #2, hrs. on bit 19, ftg on bit 1536’. MW=9.3, Vis=33, Chlorides – 300. Drilled 19 hrs., made 1536’. Down: 1½ hrs. WOC; ¼ hr. test BOP; 2¾ hrs. drlg cmt; ½ hr. surveys. August 23, 2012 (Thursday) ORT: Drilling. Depth @ 2664’. Dev. @ 1723’ – ¼°, @ 2213’ – ¾°. PP=720, SPM=56, RPM=70, wt. on bit 12,000 lbs. Bit #2, hrs. on bit 41¾, ftg on bit 2437’. MW=9.2, Vis=35, pH=10, WL=12.4, Chlorides – 1800. Drilled 23 hrs., made 901’. Down: ½ hr. survey; ½ hr. circ. samples. Cumulative cost through today $99,581. August 24, 2012 (Friday) ORT: Circ. for DST. Depth @ 3192’. Dev. @ 2685 - ¾°. PP=700, SPM=56, RPM=65, wt. on bit 12,000 lbs. Bit #2, hrs. on bit 58½, ftg on bit 2965’. MW=9, Vis=54, pH=10, WL=16.8, Chlorides – 1800. Drilled 16¾ hrs., made 528’. Down: ½ hr. survey; 1¼ hrs. POOH and repack swivel; ½ hr. repair rotary chain; 5 hrs. circ. samples & cond. mud. Daily cost - $15,924. Cumulative cost - $115,505. August 25, 2012 (Saturday) ORT: DST #1. Down: 1 hr. circ. & cond. mud; ½ hr. POOH w/8 stands for wiper trip; 5 hrs. circ. & WO elevators; 2 hrs. wiper trip to DCs’ 2¾ hrs. circ. & cond. mud; 2½ hrs. POOH for DST; ½ hr. WO tester; 1 hr. PU test tool; 2½ hrs. TIH w/DST #1; 4 hrs. testing. Daily cost - $12,698. Cumulative cost - $128,203. August 26, 2012 (Sunday) ORT: Drilling. Depth @ 3760’. Dev. @ 3683’ – ¾°. PP=800, SPM=56, RPM=65, wt. on bit 10,000 lbs. Bit #2, hrs. on bit 78, ftg on bit 3533’. MW=9.2, Vis=42, pH=9, WLO=10.8, Chlorides – 4800. Drilled 19½ hrs., made 568’. Down: ½ hr. survey; 2 hrs. TOOH & load out test tool; 2 hrs. TIH. DST #1. Open 30 mins., SI 30 mins., open 60 mins., SI 120 mins. IHYP 1558 psi 1st IF 14 psi 1st FF 14 psi ISIP 157 psi 2nd IF 14 psi 2nd FF 14 psi FSIP 1403 psi FHYP 1477 psi Opened tool w/very weak blow. B low remained very weak throughout flow period. Recovered 200’ of gas in DCs, 10’ of slightly gas TRIO CONSULTING & MANAGEMENT, LLC DYSINGER NO. 1 DAILY REPORT cut mud. Samples: 15 psi, 0.16 cuft gas, 1600 cc’s gas cut mud. Daily cost - $24,727. Cumulative cost - $152,930. August 27, 2012 (Monday) ORT: DST #2. Depth @ 3950’. Dev. @ 3950’ – ½°. PP=880, SPM=56, RPM=65, wt. on bit 10,000 lbs. Bit #2, hrs. on bit 87, ftg on bit 3723’. MW=9.4, Vis=80, pH=10.8, WL=8.4, Chlorides – 3900. Drilled 9 hrs., made 190’. Down: 1 hr. repair swivel packing; 1 hr. circ. samples; 1¼ hrs. 15 stand wiper trip; 4 hrs. circ. & cond. mud; 2¼ hrs. POOH for DST #2; ¾ hr. PU & MU test tool; 2½ hrs. TIH w/test tool; 2¼ hrs. testing. Daily cost - $10,121. Cumulative cost - $163,051. August 28, 2012 (Tuesday) ORT: Drilling. Depth @ 4070’. PP=830, SPM=56, RPM=65, wt. on bit 15,000 lbs. Bit #2, hrs. on bit 98, ftg on bit 3843’. MW=9.4, Vis=56, pH=10, WL=8, Chlorides – 3700. Drilled 11 hrs., made 120’. Down: 2¾ hrs. testing, 5½ hrs. TOOH; 1 hr. load out test tool; 2 hrs. TIH; 2 hrs. circ. & cond. mud. DST #2 interval 3941-50’. Open 30 ins., SI 60, mins., open 60 mins., SI 120 mins. IHYP 1st IF 1st FF ISIP 2nd IF 2nd FF FSIP FHYP 2005 358 496 1377 562 828 1387 2003 psi psi psi psi psi psi psi psi Opened tool w/good blow. GTS in 15 mins. Recovered 33 BO in DP & 2 BO in DCs, 62’ of HG&OCM, no wtr. Sampler: 800 psi, 1620 cc’s free oil, 1.2 cuft gas. 40.9 gravity @ 60°. Daily cost $17,517. Cumulative cost - $180,568. August 29, 2012 (Wednesday) ORT: Drilling. Depth @ 4430’. PP=830, SPM=56. RP=65, wt. on bit 18,000 lbs. Bit #2, hrs. on bit 121¾, ftg on bit 4203’. MW=9.5, Vis=56, pH=10.5, WL=7.8, Chlorides – 3700. Drilled 23¾ hrs., made 360’. Down: ¼ hr. replace belts on LP. Daily cost - $9329. Cumulative cost - $189,897. August 30, 2012 (Thursday) ORT: Logging. Depth @ 4611’. Dev. @ 4611’ – 1°. PP=950, SPM=56, RPM=65, wt. on bit 14,000 lbs. Bit #2, hrs. on bit 134¾, ftg on bit 4384’. MW=9.5, Vis=90, pH=10.5, WL=7.4, Chlorides – 3200. Drilled 13 hrs., made 181’. Down: 2 hrs. circ. samples; 1¾ hrs. wiper trip; 2 hrs. circ. for logs; 2¾ hrs. POOH for logs; 2½ hrs. logging. Daily cost - $11,023. Cumulative cost $200,920. August 31, 2012 (Friday) ORT: ND BOP. Down: 3½ hrs. logging; 4 hrs. TIH; 1¾ hrs. circ. & cond. mud; 4½ hrs. LDDP; ¾ hr. WO csg crew; 3½ hrs. run csg; 4¼ hrs. circ. csg & cond. mud; ¾ hr. cmt csg; 1 hr. ND BOP. Daily cost - $101,609. Cumulative cost - $302,529. September 1, 2012 (Saturday) Down: 5 hrs. ND & clean pits; 3 hrs. RD. Rig released @ 11:30 a.m. 8/31/12. Daily cost - $2200. Cumulative cost - $304,729. TRIO CONSULTING & MANAGEMENT, LLC DYSINGER NO. 1 DAILY REPORT August 31, 2012 (Friday) Production csg ran as follows: Set above KB 91 jts new 5½”, 15.5#/ft, J-55 csg 1 marker jt 5½”, 15.5#/ft, J-55 csg 17 jts new 5½”, 15.5#/ft, J-55 csg Latch Baffle 1 jt new 5½”, 15.5#/ft, J-55 csg Float Shoe Length(ft) Depth(ft) 3.00 -3.00 3834.04 3831.04 13.70 3844.74 716.45 4561.19 0.00 4561.19 42.18 4603.37 1.00 4604.37 Ran centralizers on csg as follows: middle of 1st jt, top of 1st jt, top of 2nd, 4th, 10th, 11th, 12th, 13th, 14th, 15th, 16th, 17th, 31st, 32nd, 34th & 36th jts for a total of 16. Midwestern Mud check prior to cmt job: Vis=50, MW=9.45, YP=13, WL=8. Cemented long string w/310 sxs Class “H” + 2% gel + 10% salt + .5 C15 + 5#/sx Kolseal as follows: 10 BFW spacer, 24 bbls mudflush, 12 bbls PV spacer, 10 BFW spacer, 82 bbls cmt slurry & displaced w/108 BFW. Good circ. throughout job. Plug bumped on schedule & held. Set csg slips w/75k string wt. PD @ 5:00 a.m. 8/31/12. September 5, 2012 (Wednesday) MI Lear Dozer Service. Cleaned up around wellhead. Welded on 5½” Larkin bell nipple. Cleaned up rest of location. MIRU Express Energy Service. Ran CBL. Estimated TOC @ 2550’. 80-90% pipe bond across Caddo. 95% bond thru remainder of cmt. Called for pump truck to pressure csg & rerun CBL. Pressured csg to 1000 psi & reran log. Maximum change on amplitude 2%. RD Express & MOL. Daily cost - $6244. September 11, 2012 (Tuesday) PU wellhead, pkr & wellhead connections in Wichita Falls & drove to location. MIRU Silverado Well Service WO unit. Unloaded 134 jts of new 2 3/8” 4.7#/ft tbg. Installed tbg head & TIH w/132 jts of tbg open ended to a depth of 4264’ KBM. Secured well & SDFN @ 6:00 p.m. Will displace FW out of well in a.m. w/3% KCL wtr. Daily cost - $26,218. September 12, 2012 (Wednesday) MI Texas Tank Trucks. Checked KCL wtr. Fresh. Called out 2nd load. CHL 3,000 ppm, wt. 8.45. Displaced FW out of well w/3% KCL wtr (95 bbls). TOOH w/tbg. MIRU Express Energy Service. Perforated Caddo 3962-68’ (OH-GR) with 3 3/8” tag gun as follows: 26 gram charge; .41 EH, 60° phasing, 4 SPF w/54” penetration. RD Express. TIH w/Arrowset 1X pkr, SN & 121 jts tbg. Pkr depth 3914’ KBM (48’ above perfs). Set pkr w/10k tension. Packed wellhead off & installed 2 3/8”, EUE, 8rd, 5K gate valve on tbg. RU swab. 1st run FL 100’ FS. Swabbed down 16 bbls in 3 runs. Strong blow of gas behind swab. No oil cut at swab down. Swabbed down 16 bbls. Flowed tbg to frac tank full open for 30 mins. w/40 psi FP. SWI & RD swab. Installed gauge in top of swab tree & installed adjustable choke on flowline. Opened tbg w/360 psi SIP. Flowed tbg on 18/64” choke for 1 hr. w/450 psi FP & no fluid. Opened choke on 42/64” choke for 1 hr. w/100 psi constant FP. SWI & gauged frac tank – no fluid recovered during flow tests. SITP after 5 mins. 600 psi. SWI & SDFN. Will RU GW Wireline in a.m. & run static pressure gradient. Daily cost - $8443. September 13, 2012 (Thursday) SITP 1300 psi. MIRU GW Wireline. TIH w/static pressure gradient. Set test tool @ 3960’ for 2 hrs. TOOH w/tool. 1st BHP 1439 psi. Ending BHP 1440 psi. Avg. pressure gradient 040. No fluid in well. RD GW Wireline. Secured well & SDFN @ 2:00 p.m. Daily cost - $2046. September 17, 2012 (Monday) SITP 1300 psi. Opened well & blew down to frac tank. Production Meter caught gas sample for analysis. MI Texas Tank Trucks. Loaded tbg w/16 bbls 2% KCL wtr. TP rose to 1100 psi @ 1.5 BPM. Tbg would not go on vacuum. Released pkr & circ. 75 bbls 3% KCL down tbg. Both sides static. NU 7 1/16”, 3k manual BOP. TOOH w/tbg & pkr. MI Express Energy Service. Perforated 4016-23’ (OHGR), 4 SFP, 60° phase, 26 gram charge, .41 EH for a total of 29 holes with 3 3/8” tag gun. TOOH w/gun. All shots fired. RD Express. TIH w/Arrowset 1X pkr, SN, 123 jts tbg & 12’ tbg sub. Set pkr @ 3989’ KBM w/10k tension. Closed BOP & tested backside to 900 psi. No communications on tbg. RU swab. 1st swab run FL @ TRIO CONSULTING & MANAGEMENT, LLC DYSINGER NO. 1 DAILY REPORT surface. Swabbed down 14 bbls in 3 runs. No show of oil or gas. Made cleanup run recovering 1 bbl w/show of gas. Waited 1 hr. & ran swab. Gas @ surface w/no oil show recovered and ½ bbl dirty wtr. 2nd hr. recovered ½ bbl w/gas @ surface w/show of oil. Last test 30 mins. recovered ¼ bbl w/gas @ surface w/100% oil cut. Total fluid recovered for day 16.25 bbls. Secured well & SDFN @ 6:00 p.m. Will acidize in a.m. Daily cost - $10,185. September 18, 2012 (Tuesday) SITP 220 psi. Blew tbg down & RU swab. 1st swab run FL 3800’ FS. Recovered 1.5 bbls w/gas @ surface & 90% oil cut. RD swab & RU Quasar Energy Service. Acidized perfs 4016-23’ w/300 gals 15% NFE acid as follows: formation broke @ 2600 psi @ .25 BPM. Increased rate to .50 BPM @ 1960 psi. Established rate of .80 BPM @ 1760 psi. Ending rate .80 BPM @ 1120 psi. ISIP – 920 psi 5 min. SI 610 psi, 10 min. SI 500 psi, 15 min. SI 430 psi. LTR 26 bbls. RD Quasar. RU swab & started swabbing load back @ 9:00 a.m. Swabbed down 18 bbls in 5 swab runs w/acid gas & natural gas mix @ surface w/60% oil cut on 5th run. 1st hr. swab test recovered 1.7 bbls in 4 swab runs w/mixed gas @ surface w/55% oil cut. 2nd hr. recovered 1.7 bbls in 2 swab runs w/mixed gas @ surface w/55% oil cut. 3 rd hr. .57 bbl w/gas @ surfaced w/40% oil cut. 4th hr. .57 bbl w/gas @ surface w/40% oil cut. 5th hr. .29 bbl w/gas @ surface w/45% oil cut. 6th hr. .29 bbl w/gas @ surface w/45% oil cut. 7th hr. .29 bbl w/gas @ surface w/45% oil cut. FL last 5 hrs. 3800-3900’ FS. Total load recovered 23.6 bbls (2.25 BO & 21.37 BW). LTR 4.63 bbls. Secured well & SDFN @ 6:00 p.m. Daily cost – $6613. September 19, 2012 (Wednesday) SITP 820 psi. Blew tbg down w/no flow. RU swab. 1st swb run FL 3200’ FS. Recovered 2 bbls w/gas @ surface & 50% oil cut. MI Texas Tank Trucks. Loaded tbg w/15 bbls 3% KCL wtr. Released pkr. Circ. 35 bbls down csg & out tbg. Started TOOH w/tbg. Rig broke down. Down 3 hrs. waiting on parts. Repaired rig & finished TOOH. LD pkr & RU Express Energy Service. Set CIBP @ 4008’ KBM. TOOH w/setting tool. TIH with 3 3/8” tag gun & perforated 3986-92’ (OH-GR), 4 SPF, 26 gram charge, 60° phase, 50” penetration for a total of 25 .41 entry holes. TOOH w/gun. All shots fired. RD wireline. TIH w/Arrowset 1X pkr, SN & 123 jts tbg. RU wireline. Spotted pkr @ 3977’. TOOH w/wireline & RD. Set pkr w/10k tension. Loaded csg & tested pkr to 600 psi – held OK. Released wireline & pump truck. RU swab. 1st swab run FL @ surface. Swabbed down 4 runs and recovered 3.39 bbls w/no show of oil or gas. Cleanup run behind swab down recovered 50’ of dirty wtr. Secured well & SDFN @ 6:30 p.m. Daily cost - $10,840. September 20, 2012 (Thursday) SITP 120 psi. Blew tbg down & RU swab. 1st swab run FL @ 3650’. Recovered .62 BTF w/3000’ of gas w/80% oil cut. RD swab & RU Quasar Energy Service. Acidized perfs 3986-92’ w/300 gals 15% NEFE acid as follows: pressured backside to 500 psi. Pumped acid & loaded tbg w/3% KCL wtr. Tbg loaded & formation broke @ 1950 psi. Established rate of .5 BPM @ 1800 psi. Pressure breaking back. Brought rate to .75 BPM @ 1700 psi. Established final rate of 1 BPM @ 1300 psi w/ending injection pressure of 1140 psi. ISIP – 950 psi, 5 min. SI 460 psi, 10 min. SI 280 psi, 15 min. SI 190 psi. SWI. RD Quasar & RU swab. 1st swab run FL @ surface. LTR 25 bbls. Swabbed 21.08 bbls w/30% oil cut & acid gas. Started 1 hr. swab tests recovering as follows: 1st 2nd 3rd 4th 5th 6th hr. hr. hr. hr. hr. hr. 4.96 BTF, FL 2350’, 25% oil cut, GTS 1.86 BTF, FL 3300’, 35% oil cut, GTS 4.34 BTF, FL 3500’, 40% oil cut, GTS 2.48 BTF, FL 3800’, 45% oil cut, GTS .62 BTF, FL 3850’, 35% oil cut, GTS .62 BTF, FL 3850’, 45% oil cut, GTS Secured well & SDFN @ 5:00 p.m. Will take pressure reading in a.m. & swab down. TLR after acid job 35.96 bbls. Estimated wtr recovery 26.43 bbls. Chlorides – 88,889 ppm. Daily cost - $6559. September 21, 2012 (Friday) SITP 900 psi. Blew tbg down w/no flow. RU swab. 1st swab run FL 3400’ FS. Pulled swab from SN recovering 1.86 BF w/GTS & 55% oil cut. 1st hr. swab test recovered 1.86 BF w/GTS & 40% oil cut. 2nd hr. swab test recovered .62 BF w/GTS & 50% oil cut. RU Texas Tank Trucks. Pumped 15 bbls 3% KCL wtr down tbg. Tbg on vacuum. TRIO CONSULTING & MANAGEMENT, LLC DYSINGER NO. 1 DAILY REPORT Released pkr. Pumped 30 bbls 3% KCL down csg. TOOH w/tbg & pkr keeping hole full w/3% KCL wtr. RU Express Energy Service. Perforated Caddo with 3 3/8” tag gun as follows: 3940-48’ (OHGR), 4 SPF, 60° phase, 26 gram charge for a total of 33 .41 EH. TOOH w/gun. All shots fired. TIH with 5½” CIBP & set @ 3959’. RD Express Energy. TIH w/Arrowset 1X pkr, SN, 120 jts & 12’ tbg sub. ND BOP & installed stripper rubber on Larkin “R” tbg head. Set pkr w/10k tension @ 3894’ KBM. Packed wellhead off & tested pkr to 600 psi. Held OK. RD Texas Tank Trucks. RU swab. 1st swab run FL @ surface. Swabbed down 15 bbls w/no gas & no oil. 2nd run from SN had 500’ of gas w/no oil show. FL 3550’ FS. Waited 30 mins. & ran swab. FL 3700’ FS & recovered 150’ of muddy wtr w/15% oil cut & 2500’ gas. Waited 30 mins. FL 3700’ FS. Recovered 150’ of muddy wtr w/GTS & 30% oil cut. Waited 30 mins., FL 3750’ FS. Recovered 100’ of muddy wtr w/GTS & 45% oil cut. Recovered 16.5 BF including swab down. Secured well & SDFWKE @ 6:00 p.m. Daily cost - $ 10,722. September 24, 2012 (Monday) SITP 310 psi. Blew tbg down & RU swab. 1st swab run FL 300’ FS. Swabbed down in 3 runs recovering 9.3 BO. 2nd swab run from SN recovered .31 BO. Good blow of gas @ surface. Waited 30 mins. & ran swab. FL 3550’ FS w/GTS recovering .93 bbl w/45% oil cut. Checked chlorides – 8300 ppm – filtrate wtr. RD swab & RU Quasar Energy Service. Acidized perfs 3940-48’ as follows: 300 gals 15% NEFE acid (7 bbls). Loaded tbg w/3% KCL wtr (8 bbls). Brought pressure to 1550 psi @ .1 BPM. SD for leak off. Brought pressure to 1650 psi @ .1 BPM. SD for pressure leak off. Brought pressure to 1700 psi @ .2 BPM. Formation broke & established rate of .5 BPM @ 400 psi w/total of 16.5 bbls into job. Tbg on vacuum @ 19 bbls total fluid into job. SD w/2 bbls acid in pipe. RD Quasar. LTR 21.5 bbls. RU swab. 1st swab run FL 700’ FS. Made 3 swab runs & well kicked off. Last swab run from 2200’ FS. Opened flowed tbg for 30 mins. 40% oil cut. Estimated acid load recovered 18 bbls. SWI & installed adjustable choke on wellhead. Opened choke & set on 22/64” for 30 mins. FTP 170 psi. Recovered 7.28 BO. SWI & installed 10/64” choke. Flow tested for 30 mins. (11:30 – 12:00 p.m.) FTP 180 psi. Recovered 2.64 BO (24 hr. 126.7 BO). Flow tested rest of day as follows: 12:00-12:30 12:30-1:30 1:30-2:30 2:30-3:30 3:30-4:30 4:30-5:30 FTP 170 150 160 160 165 165 Choke 10/64 7/64 10/64 10/64 10/64 10/64 LR 1.24 1.24 2.48 1.86 1.86 1.86 Oil Cut 100% 100% 100% 100% 100% 100% BOPD 59.52 29.76 59.52 44.64 44.64 44.64 Left well flowing to frac tank on 10/64” choke for night. Released rig crew @ 2:00 p.m. If well still flowing in a.m., will RD WO unit. Daily cost - $5700. September 25, 2012 (Tuesday) 7:30 a.m. FTP 165 psi on 10/64” choke. Made 37.20 BO, no wtr in 14 hrs. (63.84 BOPD). Flow tested 2 hrs. recovering 2.75 & 2.79 BO w/no wtr. FTP 165 psi. RD WO unit. SWI & NU wellhead to frac tank. SI 30 mins. SITP 155 psi. Opened tbg to frac tank. TP blew down to 95 psi before fluid surfaced. Released rig & flow tested well rest of day as follows: 10:00-11:00 11:00-12:00 12:00-1:00 1:00-2:00 2:00-3:00 3:00-4:00 4:00-5:00 FTP 120 120 120 120 120 120 120 Choke 10/64 10/64 10/64 10/64 10/64 10/64 10/64 BPH 2.52 2.48 2.48 2.47 2.46 2.50 2.50 BOPD 60.48 59.52 59.52 59.28 59.04 60.00 60.00 LR in 7 hr. test period 17.41 BO w/no wtr. Avg. rate 2.48 BPH or 59.69 BOPD. Left well flowing to frac tank. Will check pressures & volume in a.m. Daily cost- $5546. September 26, 2012 (Wednesday) 7:30 a.m. FTP 100 psi on 10/64” coke. 24 hr. production 39.44 BO, no wtr. Flow tested well rest of day as follows: TRIO CONSULTING & MANAGEMENT, LLC DYSINGER NO. 1 DAILY REPORT 7:30-8:30 8:30-9:30 9:30-10:30 10:30-11:30 11:30-12:30 12:30-1:30 1:30-2:30 2:30-3:30 3:30-4:30 FTP 100 95 105 105 90 95 100 100 100 Choke 10/64 10/64 14/64 14/64 14/64 14/64 14/64 14/64 14/64 BPH 2.28 2.00 4.86 4.00 3.71 4.57 4.00 4.29 4.76 BOPD 54.72 48.00 116.64 96.00 89.04 109.68 96.00 102.96 114.24 Tubing set as follows: Length(ft) Depth(ft) 8.00 8.00 12.10 20.10 3865.86 3885.96 1.10 3887.06 7.40 3894.46 Set below KB 1 new 2 3/8”, J-55, 4.7#/ft tbg sub 120 jts new 2 3/8”, J-55, 4.7#/ft tbg SN Arrowset 1X Pkr SWI & installed 10/64” choke for night. Opened well back to frac tank @ 4:30 p.m. FTP 110 psi. Will check well in a.m. Daily cost - $1252. September 27, 2012 (Thursday) 8:30 from 7:30 Flow a.m. FTP 70 psi on 10/64” choke. Produced 28.52 BO & no wtr 4:30 p.m. 9/26 to 8:30 a.m. 9/27. Produced 62.99 BO from a.m. 9/26 to 8:30 a.m. 9/27. SWI & installed 14/64” choke. tested well as follows: 8:30-9:30 9:30-10:30 10:30-11:30 11:30-12:30 12:30-1:30 1:30-2:30 2:30-3:30 3:30-4:30 4:30-5:30 FTP 75 65 55 45 50 60 65 65 65 Choke 14/64 14/64 12/64 12/64 12/64 12/64 12/64 12/64 12/64 BPH 4.34 2.79 3.41 2.17 1.55 1.86 2.48 2.48 2.48 SWI @ 5:30 p.m. for pressure buildup. & run static pressure gradient & BHP. October 2, 2012 (Tuesday) BOPD 104.16 66.96 81.84 52.08 37.20 44.64 59.52 59.52 59.52 Will MI GW Wireline in a.m. Daily cost - $1246. SITP 132 psi. Removed 12/64” choke & installed adj. choke. Opened tbg to frac tank on open choke. Pressure blew down to 0 psi before fluid surfaced. Unloading oil & pressure building. Set adj. choke on 28/64”. 30 mins. into flow, started unloading wtr. Flowed on adj. choke from 28-12/64” for 1 hr. Wtr percentage slowly dropping to no wtr @ end of 1 hr. flow period. SWI & installed 12/64” choke. Color cut frac tank. Estimated 2.28 BW recovered. Flow tested well as follows: 8:00-9:00 9:00-10:00 10:00-11:00 11:00-12:00 12:00-1:00 1:00-2:00 2:00-3:00 3:00-4:00 4:00-5:00 5:00-6:00 FTP 60 120 115 118 115 110 105 100 90 85 Choke 48-28 adj. 28-12 adj. 12/64 12/64 12/64 12/64 12/64 12/64 11/64 11/64 BPH 22.32 9.30 3.72 4.34 3.72 3.72 4.34 3.10 2.79 2.17 Oil Cut 45-90% 90-100% 100% 100% 100% 100% 100% 100% 100% 100% BOPD 535.68 223.20 89.28 104.16 89.28 89.28 104.16 74.40 66.96 52.08 Total fluid recovered for day 59.52 bbls (57.24 BO, 2.28 BW). Left well flowing to frac tank for night. Will check in a.m. Total flow time 10 hrs. Daily cost - $1478. October 3, 2012 (Wednesday) 8:00 a.m. FTP 50 psi on 11/64” choke. Produced 27.28 BO from 6:00 p.m. 10/2 to 8:00 a.m. 10/3. Avg. rate 1.95 BPH. No water in sample @ bleeder on wellhead. Color cut tank – no water produced overnight. Called out Texas Tank Trucks. Pulled wtr off of frac TRIO CONSULTING & MANAGEMENT, LLC DYSINGER NO. 1 DAILY REPORT tank. Total of 12.5 bbls. Called Sentinel to haul load of oil. Will PU oil in a.m. Set up roustabout crew & trucks to MI tank battery on Monday 10/8. Left well flowing to frac tank. October 4, 2012 (Thursday) 7:30 a.m. FTP 20 psi on 11/64” choke. Produced 19.22 BO from 1:30 p.m. 10/3 to 7:30 a.m. 10/4. 18 hr. flow time avg. 1.07 BPH. Produced total of 25.42 BO from 8:00 a.m. 10/3 to 7:30 a.m. 10/4. Sentinel hauled 176.3 BO. 1:30 p.m. FTP 8 psi. Flow rate down to less than ½ BPH. SWI. Installed adj. choke & opened tbg to frac tank on 48/64”. After 1½ hrs. light blow of gas on tbg w/no flow. SWI. Called GW Wireline to run static pressure gradient & BHP in a.m. October 5, 2012 (Friday) SITP 80 psi. RU GW Wireline & ran static pressure gradient & BHP. Top of oil 894’. Top of SW 2322’. BHP 1343.45. RD GW Wireline. Opened tbg to frac tank on 48/64” choke. TP blew down to 0 psi. Left tbg open to frac tank for 2 hrs & unloaded 2.85 BO in 1st hr. Last hr. light blow gas w/no fluid. SWI. Daily cost - $1246. October 8, 2012 (Monday) SITP 110 psi. Opened tbg to frac tank on 20/64” adj. choke. Pressure blew down to 0 psi. Fluid surfaced. Flowed 4.57 BO & died. SWI. Light blow of gas @ end of 1 hr. MI Lear Dozer Service & constructed pad for tank battery. Will start setting tanks in a.m. Daily cost - $817. October 9, 2012 (Tuesday) Hurd Roustabout Service removed fence from around tank battery. Backhoe removed part of dyke west, east and past of north side for tank removal. Shortes Roustabout Services started breaking out tank battery. Daily cost - $890. October 10, 2012 (Wednesday) SITP 125 psi. Opened tbg to frac tank on 28/64” choke. Pressure blew down to 0 psi & fluid surfaced. Unloaded 4.57 BO w/no wtr. Flowed 45 mins & died. SWI. MI Shortes, Inc. backhoe. Hauled in 3 bobtail loads of rock. Leveled & spread rock on battery pad. Set 300 bbl fiberglass tank on pad. Unloaded all connections, staircase & walkway for tanks. SDFN. Will set oil tanks & NU in a.m. Daily cost - $1344. October 11, 2012 (Thursday) Hauled in 30” x 10’ horizontal 3 phase lo pressure separator from Beakley Reed lease. Washed & cleaned out separator. Hauled in 2 steel 300 bbl oil tanks from Ferguson Cummins lease & set on pad. Installed walkway & staircase. Started NU tanks. SITP 130 psi. Opened tbg to frac tank. Tbg blew down to 0 psi & fluid surfaced. Flowed back 4.62 BO & died. SWI for night. SD roustabout crew FN @ 4:30 p.m. Daily cost $8,342. October 12, 2012 (Friday) PU connections & meter run in WF. Hauled to location. Set separator & meter run. Started NU. Built pad for pumping unit out of base material. SITP 100 psi. SDFWKE @ 4:30 p.m. Will MI WO unit on Monday to place well on pump. Daily cost - $3,888. October 14, 2012 (Sunday) PU Total gas flow meter in Bowie. Drove to location & checked after rain for work in a.m. Daily cost - $541. October 15, 2012 (Monday) SITP 120 psi. Opened tbg to frac tank & blew down for WO unit. Flowed back 5.58 BO & died. MIRU Reliable Well Service WO unit. Released pkr & flowed tbg down. NU 7 1/16” 3K manual BOP. TOOH w/tbg & pkr. LD pkr & TIH w/1 jt BPMA 2’ PS, 2’ tbg sub, 2’ PS, SN, 121 jts tbg & 8’ tbg sub. ND BOP. Landed tbg in Larkin head & packed off. Depth EOT 3954’ KBM. Depth SN 3915’ KBM. RU for rods & TIH w/1”x12’ GAC, 1½”x14’ RWBC pump, (155) ¾” rods, (1) 6’ rod sub & 1¼”x21’ PR. Spaced pump out & checked pump action. OK. Secured well & SDFN. Tank battery NU complete. Will lay flowline to separator & NU wellhead in A.M. Tubing set as follows: Set below KB (1) 2 3/8” J-55, 4.7#/ft tbg sub 121 jts new 2 3/8” J-55, 4.7#/ft tbg 2 3/8” SN (1) 2’ J-55 PS (1) 2’ J-55 tbg sub Length(ft) Depth(ft) 9.00 9.00 8.10 17.10 3898.01 3915.11 1.10 3916.21 2.10 3918.31 2.10 3920.41 TRIO CONSULTING & MANAGEMENT, LLC DYSINGER NO. 1 DAILY REPORT (1) 2’ J-55 PS 1 jt BPMA 2.10 32.30 3922.51 3954.81 Daily cost - $12,605. October 16, 2012 (Tuesday) RD WO unit & MOL. NU Wellhead. Laid flowline, ditched to separator. NU to wellhead, separator & backfilled. Set gate at walkover. Finished out containment dike. Started prepping production facility for paint. Will set pumping unit Thursday & start well pumping w/generator until Ft. Belknap constructs power line. Daily cost - $4779. October 17, 2012 (Wednesday) Loaded fence panels & “T” posts in Wichita Falls. PU 5 gallons of paint & hauled to location. Constructed fence around tank battery. Started painting tank battery. Will set pumping unit in a.m. Daily cost - $3435. October 18, 2012 (Thursday) Loaded out Lufkin 160 pumping unit & fence panels in Wichita Falls & hauled to location. Set unit & hung on rods. Installed fence panels around unit. Completed all painting of production facility. Will hookup electrical control panel to unit, set generator, tie into panel and start well producing in a.m. Daily cost - $2427. October 19, 2012 (Friday) Set 45 KW generator. Kamay Electric set stub pole & new control panel. Made all electrical hookup’s to 20HP motor & Murphy OPLCA-600 Hi-Lo pressure switch. Started unit. Checked balance. Rebalanced unit. Started well producing @ 1:00 p.m. @ 7.6 SPM. Set back pressure regulator on tbg to 150 psi. Opened csg w/0 psi. Transferred oil from frac tank to production tank. Both load line valves leaking on tank. Replaced 3 load line valves w/3” Balon 750 ball valves. Released frac tank. Transferred 192.88 BO from frac tank. Well pumping ok. 14% oil cut. Turned well over to pumper. Daily cost- $6,354. October 20, 2012 (Saturday) Made 5 BO & 70 BW (LW to recover was 71 bbls). Checked well. Oil cut 30%. Checked water. Chlorides 39,111 ppm. 8.8 #/gal. 11:00 a.m. tbg kicked off flowing oil. Set high pressure kill @ 200 psi to shut unit down, w/low pressure kill @ 50 psi to start unit. Set choke on separator at 16/64”. Daily cost - $1196. October 21, 2012 (Sunday) Made 24.98 BO & 3.74 BW. October 22, 2012 (Monday) Made 87.8 BO & 5 BW. Reduced choke at separator to 14/64” and increased back pressure on tbg. Set timer in control panel to 3 hrs. run time & 3 hrs. off time. Turned unit on automatic. Will check well in a.m. Trying to maintain 40-50 bbls production per day. Daily cost - $1651. October 23, 2012 (Tuesday) Made 40.07 BO, 5.85 BW. MI Holland Dozer Service. Cleared rightof-way for Fort Belknap Electric line. Production Meter & Testing hooked up & calibrated Total Flow gas meter. Targa representative took gas sample & tested volume. Estimated flow rate @ time 10.4 MCFD. Daily cost - $705. October 24, 2012 (Wednesday) Made 38.41 BO, 10.02 BW. Pumper called in reporting dump valve on water leg hung open unloading all production into water tank. Drove to location and found water side of separator empty. SWI & pulled float on separator. Found trunnion assembly on water leg sticking. Also found debris hung in dump valve. Left well SI. Will try to find new trunnion assembly for separator. October 25, 2012 (Thursday) PU parts for separator. MI Texas Tank Trucks & Stew’s Roustabout Service. Cleaned out separator and installed new parts. Pulled SW off oil tank #2. Started unit & set levels on separator. Everything working OK. Turned well over to pumper. Started unit @ 4:00 p.m. October 26, 2012 (Friday) Made 11.7 BO, 4.17 BW in 17½ hrs. TRIO CONSULTING & MANAGEMENT, LLC DYSINGER NO. 1 DAILY REPORT October 27, 2012 (Saturday) Made 38.41 BO, 10.02 BW. October 28, 2012 (Sunday) Made 34.23 BO, 13.36 BW. October 29, 2012 (Monday) Made 28.39 BO, 15.87 BW. October 30, 2012 (Tuesday) Made 31.73 BO, 15.86 BW. October 31, 2012 (Wednesday) Made 30.06 BO, 16.7 BW. November 1, 2012 (Thursday) Made 31.73 BO, 18.37 BW. November 2, 2012 (Friday) Made 28.39 BO, 20.04 BW. November 3, 2012 (Saturday) Made 26.72 BO, 20.04 BW. November 4 2012 (Sunday) Made 28.39 BO, 25.05 BW. Sentinel turned down oil w/1’4” high bottom. Called out bobtail to pull bottoms on both tanks. BS too heavy to pull. Called L&S Hot Oil Service to treat tanks. Hot oiled both tanks. Will pull bottoms on Monday 11/5. Took sample of bottoms & wellhead sample to Champion for analysis for chemical injection. Well SI. November 5, 2012 (Monday) SD, will turn well back on when load of oil hauled. November 6, 2012 (Tuesday) Well SI. November 7, 2012 (Wednesday) Well SI. WO chemical hookup. PU LMl-150 110 volt chemical pump & connections. Installed pump on chemical tank & NU pump to tank. Hauled to location & set. NU discharge line off chemical pump to flowline. WO Kamay Electric to wire in 110 volt plug for pump. Call Champion Technologies to delivery chemical. Daily cost $1836. November 8, 2012 (Thursday) In 17 hrs. made 18.37 BO, 18.37 BW. November 9, 2012 (Friday) Made 28.39 BO, 21.71 BW, 4.6 MCF. November 10, 2012 (Saturday) Made 26.72 BO, 20.04 BW, 4 MCF. November 11, 2012 (Sunday) Made 21.71 BO, 26.76 BW, 4 MCF. November 12, 2012 (Monday) Made 28.39 BO, 23.38 BW, 3.9 MCF. November 13, 2012 (Tuesday) Made 21.71 BO, 23.38 BW, 3.6 MCF. November 14, 2012 (Wednesday) Made 21.71 BO, 26.72 BW. 3.4 MCF. November 15, 2012 (Thursday) Made 21.71 BO, 25.05 BW, 3.4 MCF. November 16, 2012 (Friday) Made 20.04 BO, 21.71 BW, 3.5 MCF. TRIO CONSULTING & MANAGEMENT, LLC DYSINGER NO. 1 DAILY REPORT November 17, 2012 (Saturday) Made 20.04 BO, 23.38 BW, 3.1 MCF. November 18, 2012 (Sunday) Made 20.04 BO, 26.72 BW, 3.1 MCF. November 19, 2012 (Monday) Made 20.04 BO, 28.39 BW, 3.1 MCF. November 20, 2012 (Tuesday) Made 18.37 BO, 28.39 BW, 3.0 MCF. November 21, 2012 (Wednesday) Made 16.70 BO, 28.39 BW, 3.1 MCF. November 22, 2012 (Thursday) Made 18.37 BO, 25.05 BW, 2.8 MCF. November 23, 2012 (Friday) Made 16.7 BO, 28.38 BW, 2.8 MCF. November 24, 2012 (Saturday) Made 16.7 BO, 26.72 BW, 2.0 MCF. November 25, 2012 (Sunday) Made 16.7 BO, 26.72 BW, 2.1 MCF. November 26, 2012 (Monday) Made 18.37 BO, 33.40 BW, 2.6 MCF. November 27, 2012 (Tuesday) Made 13.36 BO, 31.37 BW, 2.6 MCF. Turned off pumping unit. Blew well down to tank battery @ 11:00 a.m. MIRU SDT Silverado Well Service. Hung off unit & unseated pump. TOOH with (1) 6’ x ¾” sub & (155) ¾” rods. Removed 2 x 1½ x 14’ BHD pump w/12’ strainer. Throckmorton Pump PU pump for repairs. ND Larkin wellhead. TOOH with TS & 58 jts tbg. . NU Larkin wellhead. Plumbed in flowline. TIH w/redressed pump, (81) ¾” rods, & (1) 6’ & (1) 2’ x ¾” subs. Respaced well. Checked pump action – good. Hung unit on. Unit out of balance. SWI & SDFN @ 5:30 p.m. Will balance unit in a.m. Changed 2 ball & seats on pump. Seats were cracked. Tbg setting now as follows: Length(ft) Depth(ft) Set below KB 7.00 7.00 (1) 8’ x 2 3/8” sub 8.10 15.10 63 jts 2 3/8” tbg 2028.60 2043.70 SN 1.10 2044.80 PS 2.10 2046.90 TS 2.10 2049.00 PS 2.10 2051.10 BPMA 32.30 2083.40 Rods as follows: (1) 2’ x ¾” sub (1) 6’ x ¾” sub (81) ¾” rods 2 x 1½ x 14’ BHD pump Daily cost - $3433. November 28, 2012 (Wednesday) 8:30 a.m. RDMO SDT Silverado Well Service. 9:30 a.m. Shortes Roustabout Service rebalanced unit. Loaded 59 jts 2 3/8” tbg & (108) ¾” rods on trailer. Took rods and tbg to Cactus. Unloaded tbg on racks, put on thread protectors, unloaded rods onto sills. Put well on line @ 11:00 a.m. & turned to pumper. Daily cost $3607. November 29, 2012 (Thursday) Made 35.07 BO, 3.08 BW, 4.1 MCF. TRIO CONSULTING & MANAGEMENT, LLC DYSINGER NO. 1 DAILY REPORT November 30, 2012 (Friday) Made 40.58 BO, 8.35 BW, 4.9 MCF. December 1, 2012 (Saturday) Made 16.7 BO, 31.73 BW, 2 MCF. December 2, 2012 (Sunday) Made 16.7 BO, 35.07 BW, 2 MCF. Changed time clock to 2 hrs. run time, 4 hrs. off time @ 4:00 p.m. December 3, 2012 (Monday) Made 13.36 BO, 38.41 BW, 2.9 MCF. December 4, 2012 (Tuesday) Made 11.69 BO, 23.38 BW, 1.4 MCF. December 5, 2012 (Wednesday) Made 8.35 BO, 23.38 BW, 1.4 MCF. December 6, 2012 (Thursday) Made 10.02 BO, 23.38 BW, 1.4 MCF. December 7, 2012 (Friday) Made 10.02 BO, 23.38 BW, 1.4 MCF. December 8, 2012 (Saturday) Made 10.02 BO, 23.38 BW, 0 MCF. December 9, 2012 (Sunday) Made 10.02 BO, 23.38 BW, 0 MCF. December 10, 2012 (Monday) Made 10.02 BO, 25.05 BW, 1 MCF. December 11, 2012 (Tuesday) Made 8.35 BO, 23.38 BW, 1 MCF. December 12, 2012 (Wednesday) Made 1.67 BO, 1.67 BW, 0 MCF. Electricians wired unit into Fort Belknap power line & left unit down. Released generator effective 12/11. December 13, 2012 (Thursday) Made 8.35 BO, 25.05 BW, 1.8 MCF. December 14, 2012 (Friday) Made 8.35 BO, 23.38 BW, 1.3 MCF. December 15, 2012 (Saturday) Made 10.02 BO, 23.38 BW, 0 MCF. December 16, 2012 (Sunday) Made 8.35 BO, 25.05 BW, 0 MCF. December 17, 2012 (Monday) Made 11.69 BO, 26.72 BW, 1.2 MCF. December 18, 2012 (Tuesday) Made 6.68 BO, 23.38 BW, 1.2 MCF. December 19, 2012 (Wednesday) Made 10.02 BO, 26.72 BW, 1.1 MCF. December 31, 2012 (Monday) Repaired chemical pump and took production report to pumper. January 30, 2013 (Wednesday) MI Lear Dozer Service & Stew’s Roustabout Service. Took down fence around reserve pit. Backfilled reserve pit. Dozer cut electrical supply by wellhead. Will repair line in a.m. & start well back up. Daily cost - $3625. TRIO CONSULTING & MANAGEMENT, LLC DYSINGER NO. 1 DAILY REPORT