Feasibility: Endurance

advertisement

Project Customer

Prof. Eric Frew

Project Advisors

Prof. Bill Emery

Prof. Kurt Maute

Spring Final Review

Leah Crumbaker

Jason Farmer

James Gordon

Matt Lenda

Jeffrey Mullen

Scott Tatum

Travis Schafhausen

Kristina Wang

Spring Final Review 1

Briefing Overview & Content

Purpose

This presentation will showcase the MADS senior design project.

System Architecture Design Elements

Mechanical

Model Validation,

Verification &

Testing

Mechanical

Objectives

Concept of Operations

Requirements

System Design

Electrical

Software

Electrical

Software

2

Spring Final Review

System Architecture

Fabrication and Integration

Experimental Test Results

Project Management

Project Summary

Spring Final Review 3

Project Objectives and Purpose

Objective:

Integrate a mechanism into an existing

RECUV vehicle that can store and deploy four small sub-vehicles on demand during flight.

Purpose:

• Provide a test platform for cooperative control protocols

• Provide a proof of concept that in-flight deployment of air vehicles and the overall dynamics associated with such an action can be managed, predictable, and reliable.

System

Architecture

4

Interim Review #1

Concept of Operations

System

Architecture

Spring Final Review

5

Requirements Overview

System

Architecture

Definition of Success (Qualitative and Quantitative):

• Functionality

• Repeatability

• Verification of theoretical models with experimental data

Definitions

PV = Primary Vehicle

SV = Sub Vehicle

DM = Deployment Mechanism

Project Requirements

• The PV is the SIG Rascal 110

• The system shall carry and deploy 4 SVs in flight

• At least 1 flight-capable SV shall be delivered

System Requirements

Sub-Vehicle

• Minimum 15 minute endurance

• Minimum speed of 5 m/s

• Shall be controlled by the CUPIC autopilot

• Deployed on-demand (between 50 and 100 meters AGL)

DM Impact on PV

• Minimum 15 minute PV endurance with deployment system

• PV remains stable with deployment system in any configuration

6

Interim Review #1

System Design

1. Primary Vehicle (PV)

• On-board electronics controls deployment through wireless commands from a ground station

• Flown by an RC Pilot

2. Deployment Mechanism (DM)

• Consists of mounting point for the SV and linear actuator for pin-movement release

• Attached to the PV with bracketing system

3. Sub-Vehicle (SV)

• CUPIC Autopilot commands the control surfaces and motor settings autonomously from mission commands given from the ground station

Interim Review #1

System

Architecture

7

Major Design Changes from CDR

Mechanical Elements

• Linear actuator mount (2 revisions)

• Top beam attached to PV (angled to bent)

• Bracket reinforcements (large to small)

Electrical Elements

• Linear actuator custom control board (digital switches to transister-based logic)

Software Elements

Creation of software

System

Architecture

8

Interim Review #1

Requirement Verifications

System

Architecture

Definitions

PV = Primary Vehicle

SV = Sub Vehicle

DM = Deployment Mechanism

Project Requirements

• The PV is the SIG Rascal 110

• The system shall carry and deploy 4 SVs in flight

• At least 1 flight-capable SV shall be delivered

System Requirements

Sub-Vehicle

• Minimum 15 minute endurance

• Minimum speed of 5 m/s

• Shall be controlled by the CUPIC autopilot

• Deployed on-demand (between 50 and 100 meters AGL)

DM Impact on PV

• Minimum 15 minute PV endurance with deployment system

• PV remains stable with deployment system in any configuration

9

Spring Final Review

Verification Items

Primary Vehicle

 SIG Rascal 110

 Deploy Altitude (50-

100m)

 V = 15m/s at deployment

 E = 15min

 Max Payload = 4.71kg

 Max Mass = 12.67kg

 Controlled by RC Pilot

 Stability

Sub-Vehicle

 Flight Capable

 Min V = 5m/s

 E = 15min

 Max Mass = 485g

 Max Payload = 0.1 kg

 Stability

Deployment

Mechanism

 Carry 4 SVs for 15 minutes

 Deploy SV on Demand within 3 seconds

 Max Mass = 0.013kg

System

Architecture

CDH

 Stream data at 10 Hz

 Control SV elevons

 Control SV throttle

 Stream potentiometer data from PV at 10 Hz

 Interpret data

System

 Full-System Fit and Functionality

 PV – DM interface

 The system shall not alter from [43 cm, 0 cm, -5 cm] more than of +/- 2 cm in the X, or Z direction

 DM in flight shall not exceed the material limits of the PV structure

 Mount within specified area

 DM – SV interface

 DM shall not decrease the structural integrity of the SV

 Flight environment

 Operate in the temperature range of 0-40 degrees Celsius.

 Shall not operate if winds exceeds 7 m/s

Spring Final Review

10

System Architecture

Fabrication and Integration

Experimental Test Results

Project Management

Project Summary

Spring Final Review 11

Mechanical Design Updates

• Firgelli PQ-12 attachment method required several design cycles

Initial Design Final Design

Fabrication

And Integration

1 st Design:

• Contour matching bracket

• Set screws restrain and position PQ-12

• PQ-12 not mounted according to manufacturer’s specifications

• Time consuming to manufacture

Final Design:

• Bracket tightened around PQ-12

• PQ-12 mounted at manufacturer’s specifications

• Set screws restrain and position PQ-12

• Easy to manufacture

12

Spring Final Review

Mechanical Design Updates

• Minor Reinforcement System changes

• Interior brackets – light weight design created

• Angled beams – bent instead of angled cuts and mounting brackets

Fabrication

And Integration

Spring Final Review

13

Fabrication Summary

1) Deployment Mechanisms– finalized 2/3/09 ………….. 20 hours

• 4 SV Brackets

• 4 PV Brackets

• 8 Restraint plates

• 4 Pins

2) Reinforcement Assembly (2 Sets) – finalized 2/6/09… 20 hours

• 4 Interior Brackets

• 4 Exterior Plates

• 2 Threaded Interior Connectors

3) Struts and Connectors – finalized 3/7/09 ………………. 10 hours

• 2 Angled Struts

• 2 Straight Struts

4) PQ-12 Attachment Brackets – finalized 4/3/09 ………. 60 hours

• 4 Brackets

Total Time: 110 Hours

Fabrication

And Integration

14

Spring Final Review

Fabrication (cont’d)

Lessons Learned

Fabrication

And Integration

Spring Final Review

15

System Integration Diagram

SV Assembly

Battery, CUPIC, Motor,

Propeller, Servos, Receiver,

Comparator circuit

DM Assembly

Top of DM body, Sleeves,

Screws, Pin

PV Assembly

CUPIC, Engine, Fuel, Aluminum reinforcements

Fabrication

And Integration

Ground Station

Laptop, RC Transmitter, Xbee

Pro GS

DM-Bracket System

• Attach linear actuators to beams

• Attach DM pin to linear actuator

• Fasten DMs onto end of beams

SV-DM Integration

• Screw bottom DM piece to SV Canopy

• Align and glue SV canopy onto SV

Sensors

• Integrate verification sensors into PV

DM-PV Integration

• Screw beams through PV fuselage and hold in with joints and set screws

Power ON

• Connect all batteries

• Initialize GUI

• Zero/Calibrate Sensors

SV-DM-PV Integration

• Activate linear actuators to push pins through DM mechanism

Full System

• PV, SV, DM, GS

Spring Final Review

16

Integration Testing

• Linear Actuators (Test ##.#)

• Measured retract force of each PQ-12 and verified results against manufacturers specifications

• Reinforcement System (Test ##.#)

• Measured structural deflection from estimated flight loading and verified results against a FEM model

• Vibration Testing

• Evaluated deployment mechanism functionality in vibration environment and verified results with flight tests

• Static Deployment (Test ##.#)

• Evaluated full system functionality on ground and verified results against predicted performance models

• Ground Station Test (Test ##.#)

• MICHAEL AND MATT SAY SOMETHING!

Spring Final Review

Fabrication

And Integration

17

System Integration

Fabrication

And Integration

Spring Final Review

18

System Integration (cont’d)

Lessons Learned

Fabrication

And Integration

Spring Final Review

19

System Architecture

Fabrication and Integration

Experimental Test Results

Project Management

Project Summary

Spring Final Review 20

MADS Test Schedule

• Ground testing performed first

• Flight tests occurred only after successful ground tests

Flight Testing

Ground Testing

Experimental

Testing Results

= Test Completed

JAN

17 25

FEB MAR

1 13 16 18

APR

5 11

MAY

21

Spring Final Review

MADS Test Schedule

• Ground testing performed first

• Flight tests occurred only after successful ground tests

Flight Testing

Ground Testing

Experimental

Testing Results

= Test Completed

JAN

17 25

FEB MAR

1 13 16 18

APR

5 11

MAY

22

Spring Final Review

SV Battery Endurance Test

Experimental

Testing Results

Requirement to Verify:

The SV shall have a minimum 15 minute, +/- 1 minute, post-deployment flight endurance.

• Power model of SV created to estimate flight time

• Power resistor was used to measure real-time current

• Comparison between data and model prepared

Spring Final Review

23

SV Battery Endurance Test

Experimental

Testing Results

AES Aircraft Stability Wind Tunnel was used to cool the battery, electronic speed controller, and various power resistors, ensuring that no component will overheat.

3 trials for 3 current draw levels (4A, 6A, 10A)

*Error of voltage reading from 14-bit ADC = ± .0006 V

*Error of current draw reading from .37 Ω resistor with 5% tolerance

Spring Final Review

24

SV Battery Endurance Test

Sub-Vehicle Post-Deployment Endurance

V

B

= 7.4V, C

B

= 2.1Ah

70

60

50

40

30

20

10

2 3 4 5 6 7

Motor Current [A]

8 9 10

Current Draw Theoretical Endurance Actual Endurance

4A 31.18 min 47.52 min

6A

10A

20.79 min

12.57 min

29.75 min

15.41 min

Spring Final Review

Experimental

Testing Results

Conclusion

The SV should fly for at least 15 minutes.

25

MADS Test Schedule

• Ground testing performed first

• Flight tests occurred only after successful ground tests

Flight Testing

Ground Testing

Experimental

Testing Results

= Test Completed

JAN

17 25

FEB MAR

1 13 16 18

APR

5 11

MAY

26

Spring Final Review

Structural Integrity Test

Experimental

Testing Results

Requirement to Verify:

The deployment mechanism shall be able to carry and deploy four SVs in flight.

• Non-destructive load testing on the bracket structure

• Estimated the maximum applied loads

• Power available

• CFD data

• Simulated maximum loading cases

• Compared results to FEM model

27

Spring Final Review

Structural Integrity Test

Experimental

Testing Results

Load Approximation

• ASSUME: No gusts or vibrations P excess

Power Required to Fly for Various Conditions

P max

1

Excess Power [W]

2

1000

S

C

D

V

2

10

Infeasible Flight Condition

8

500

6

0

4

-500

2

Feasible Flight Condition

0

-1000

-2

-1500

-4

-2000

-6

-2500 -8

-10

5 10 15

Velocity [m/s]

20 25 30

• Calculating maximum lift along feasible/infeasible intersection from SuperFLY CFD data, maximum lift occurs at AoA = 10 o and V

= 19m/s

• Corresponds to 23.8 N (~5.4lbf) per SV. A total of 95.2N (~21lbf) applied to the structure of the PV

28

Spring Final Review

Structural Integrity Test

• Restrained tips of deployment mechanisms

• Applied load (to the fuselage of the aircraft

• Displacement from the bottom of the fuselage measured

• Comparison to COSMOSWorks FEM model was used to verify the results

5

4

3

2

7

6

8

Deflection of Plane Fuselage for Varying Applied Loads

Trial 3

1

0

0 1 2 3 4 5

Experimental Data

Theoretical (Fixed BCs)

Theoretical (Immovable BCs)

6

Applied Load [kg]

7 8 9 10

Spring Final Review

Experimental

Testing Results

29

MADS Test Schedule

• Ground testing performed first

• Flight tests occurred only after successful ground tests

Flight Testing

Ground Testing

Experimental

Testing Results

= Test Completed

JAN

17 25

FEB MAR

1 13 16 18

APR

5 11

MAY

30

Spring Final Review

CUPIC Autopilot Flight Test

Requirement to Verify:

The SV shall utilize the CUPIC autopilot

Add SV Velocity Req

• The SVs must be able to autonomously track commanded loiter waypoints

• Flight Control Gains trimmed:

• Roll Angle Rate, Roll Angle

• Throttle to Altitude, Vertical Velocity to Elevon

• Commanding:

• Multiple loiter centers, radii, altitudes

• Autonomous landing mode

• “Safe Fall” deployment sequence

Experimental

Testing Results

31

Spring Final Review

CUPIC Autopilot Flight Test

Test Results

Speed Plot

Altitude/Altitude CMD plot

Experimental

Testing Results

Predicted Flight Speed: 10.1 m/s

Average Flight Speed: X +/- X m/s

Spring Final Review

32

CUPIC Autopilot Flight Test

Test Results

39.8445

39.844

39.8435

SV CUPIC GPS Position

CLC,

= +/- 2.0m = +/-2.34e-5 o

RC Invalid

39.843

39.8425

39.842

-105.2145 -105.214 -105.2135 -105.213 -105.2125 -105.212 -105.2115 -105.211

Longitude [deg]

Tracking Error Plot

Experimental

Testing Results

33

Spring Final Review

CUPIC Autopilot Flight Test

Test Results

Safe Fall Plot

- altitude comparison

- speed comparison

Spring Final Review

Experimental

Testing Results

34

MADS Test Schedule

• Ground testing performed first

• Flight tests occurred only after successful ground tests

Flight Testing

Ground Testing

Experimental

Testing Results

= Test Completed

JAN

17 25

FEB MAR

1 13 16 18

APR

5 11

MAY

35

Spring Final Review

Ground Station Functionality Test

Requirements to Verify:

The SV shall utilize the CUPIC autopilot

The CUPIC shall stream data at 10Hz

The SVs shall be deployed on-demand

Add PV potentiometer 10Hz req

• Telemetry and Commanding Verification

• Deploy – Deploys SV on-demand and shuts off current flow

• Force Retract/Extend – Retracts/Extends DM pin on demand without current flow control

• Post-processing determines incoming packing rate

Experimental

Testing Results

36

Spring Final Review

Ground Station Functionality Test

Test Results

1.6

1.4

1.2

1

0.8

0.6

0.4

0.2

0

640

PV-DMPIC Pin Deploy and Control Status

Pot 1 [cm],

= 0.05cm

Crit [cm]

Low [cm]

Deploy [DN]

Current [DN]

641 642 643

Time [s]

644 645 646

Spring Final Review

Experimental

Testing Results

37

Ground Station Functionality Test

Test Results

SV Debug Packets

25

20

15

10

5

0 500 1000

Time [s]

PV Debug Packets

1500

30

20

10

0

0 200 400

Expected SV/PV Packet Rate: 10Hz

Average SV Packet Rate: 8.55 Hz

Average PV Packet Rate: 8.23 Hz

600 800

Time [s]

1000 1200 1400 1600

Attributed to lack of processing power on ground station

Spring Final Review

Experimental

Testing Results

38

DM Release On-Demand Static Test

Requirement to Verify:

The SV shall be deployed on-demand from the PV

• Autonomous Sequence

• PV samples potentiometer data and waits for “critical” value

• PV notifies SV of deployment

• SV begins autonomous sequence to stabilize in roll and pitch

• Fault Protection and Deployment Conditionals:

• Deployment Order

• GPS Lock (PV and SV)

• Altitude and Speed of Deployment

Experimental

Testing Results

39

Spring Final Review

DM Release On-Demand Static Test

Test Results

Pin Position, Current Control, and Deploy Status - Flight Test

2

Throttle [DN]

1.8

1.6

SV Deploy [DN]

Pot 4 [cm],

= 0.05cm

Crit [cm]

1.4

Low [cm]

Current [DN]

1.2

1

0.8

0.6

0.4

0.2

0

645 650 655 660

Time [s]

665 670

Experimental

Testing Results

40

Spring Final Review

MADS Test Schedule

• Ground testing performed first

• Flight tests occurred only after successful ground tests

Flight Testing

Ground Testing

Experimental

Testing Results

= Test Completed

JAN

17 25

FEB MAR

1 13 16 18

APR

5 11

MAY

41

Spring Final Review

Full System Mass

Experimental

Testing Results

Requirement to Verify:

The DS shall not move the CG from [43 cm, 0 cm, -5 cm] with a margin of +/- 2 cm with respect to the nose of the PV Location

• Weigh full system and components to determine CG

• Weigh each possible deployment configuration

• Weigh system at landing gear locations

• Sum moments to determine CG location

Full System Mass

Test Results

X Center of Gravity Locations (cm from nose) Model

Loading

Case

Initial Adjusted Adjusted w/ Fuel

Predicted

CG

Brackets 48.1

45.2

44.4

56.5

SV 4

SV 3,4

SV 2,3,4

SV 1,2,3,4

48.6

49.0

50.6

50.7

47.2

48.2

48.5

48.9

46.1

47.6

47.9

48.3

56.9

57.3

58.8

60.1

Experimental

Testing Results

Total Mass (kg)

Initial Adjusted Adjusted w/ Fuel

7.901

8.94

9.221

8.304

8.608

9.051

9.454

9.409

9.787

10.192

10.624

9.672

10.04

10.452

10.864

• Adjusted CG forward

• Adjusted the placements of sensor batteries

• Added 588g lead weights to the nose of the PV

• Final CG of the PV with brackets met the CG requirement

• Full system CG does not meet CG requirements

• Total empty mass location too far forward to make additional adjustments

MADS Test Schedule

• Ground testing performed first

• Flight tests occurred only after successful ground tests

Flight Testing

Ground Testing

Experimental

Testing Results

= Test Completed

JAN

17 25

FEB MAR

1 13 16 18

APR

5 11

MAY

44

Spring Final Review

SV Endurance

Experimental

Testing Results

Requirement to Verify:

The SV shall have a minimum 15 minute, +/- 1 minute, post-deployment flight endurance.

• CUPIC Autopilot samples battery voltage

• Max current draw is limited by internal battery resistance and voltage

• Internal battery resistance and voltage are functions of:

• Temperature: dR/dT < 0, dV/dT > 0

• Charge: dR/dQ < 0, dV/dQ > 0

45

Spring Final Review

SV Endurance

Test Results

Plot of:

Battery Voltage

Relation of battery internal resistance, voltage as a function of temperature/charge

Experimental

Testing Results

Requirement is not met due to cold weather on initial flight days and crashes on the others

Spring Final Review

46

MADS Test Schedule

• Ground testing performed first

• Flight tests occurred only after successful ground tests

Flight Testing

Experimental

Testing Results

= Test Completed

Ground Testing

JAN

17 25

FEB MAR

1 13 16 18

APR

5 11

MAY

47

Spring Final Review

System Endurance

Experimental

Testing Results

Requirement to Verify:

The PV shall have a minimum flight endurance of 15 minutes, +/- 1 minute, with the full deployment system attached.

• Flow meter on system measures fuel volume consumed

• Data is extrapolated to calculate maximum endurance

Spring Final Review

48

System Endurance

Experimental

Testing Results

Test Results

PV-DMPIC Flow Meter Data: Remaining Fuel (Engine On Only)

450

400

350

300

250

-100

1.5

0 100 200 300 400

Time [s]

500 600

PV-DMPIC Measured Flow Rate

700

COMPARE TO MODEL!!!!

800

TSFC and Endurance!

1

0.5

0

-100 0 100 200 300 400

Time [s]

500 600 700 800

Average flow rate: 0.4 mL/s +/- 0.012 mL/s

Thrust-Specific Fuel Consumption: ???

Projected endurance: 18.33 minutes +/- 34 seconds

Spring Final Review

49

System Stability Test

Requirement to Verify:

PV remains stable with deployment system in any configuration

• Stable aircraft reduces risk of flight-related damages to the system

• Stability derivatives derived through CFD

• EagleTree records comparable parameters to validate model

Experimental

Testing Results

Spring Final Review

50

System Stability Test

Model

• Hundreds of several forced oscillation simulations using PowerFLOW (powered by the Lattice Boltzmann Method)

• Iterative process in order to ensure simulations were set-up properly

• From this process, all the cross-coupled and linear stability derivatives estimated

• EG: N

Θ,

X r

, etc…

• Each flight case takes roughly 2 weeks to run

• Due to time constraints, only the full system stability could be simulated

0.4

0.2

0

-0.2

-0.4

-80

4

2

0

-2

-4

-4.5

-4 -3.5

-3

Experimental

Testing Results

Poles of Longitudinal Modes

Short-Period

Phugoid

-70 -60 -50 -40 -30

Real Axis

-20

Poles of Lateral Modes

-10

Roll Subsidence

Spiral Divergence

Dutch Roll

-1

0

-0.5

10

0 -2.5

-2

Real Axis

-1.5

51

Spring Final Review

System Stability Test

• A 6 DOF aircraft flight model created

• Limitations: Model does not take into account throttle and non-trim conditions

• Comparisons when the throttle was constant and plane at trim were performed

20

Aileron Command* Angular Velocity Comparison Near  = 0**

2

Experimental

Testing Results

0

-20

0 0.5

1 1.5

Time [s]

Elevator Command

2 2.5

0

-2

0 0.5

1 1.5

Time [s]

2 2.5

10

5

0.2

0

0

0 0.5

1 1.5

Time [s]

Rudder Command

2 2.5

-0.2

0 0.5

1 1.5

Time [s]

-0.5

0.5

-1 0

-1.5

0 0.5

1 1.5

Time [s]

2 2.5

-0.5

0 0.5

1 1.5

Time [s]

Experimental Data

Model

* Accuracy of EagleTree logger for the control surfaces unknown.

** http://www.analog.com/static/imported-files/data_sheets/ADXRS150.pdf

. Sensitivity Nonlinearity of 0.1% of FS

2

2

2.5

2.5

52

Spring Final Review

System Stability Test

17.5

17

16.5

16

15.5

15

14.5

0

Airspeed Comparison Near  = 0*

Experimental Data

Model

0.5

1

Time [s]

1.5

2 2.5

Conclusion

• From CFD modeling, the system is slightly unstable in the longitudinal mode

• The CFD-method of modeling was validated!

* Accuracy of EagleTree logger for the airspeed unknown.

Spring Final Review

Experimental

Testing Results

53

DM Release On-Demand Flight Test

Requirement to Verify:

The SV shall be deployed on-demand from the PV

• Autonomous Sequence (In Flight)

• PV samples potentiometer data and waits for “critical” value

• PV notifies SV of deployment

• SV begins autonomous sequence in flight to stabilize in roll and pitch

Experimental

Testing Results

54

Spring Final Review

DM Release On-Demand Flight Test

Test Results

Plot of:

Pot 4 w/ crits

SV deploy/idle bits

Throttle

Experimental

Testing Results

55

Spring Final Review

DM Release On-Demand Flight Test

Test Results

Plot of:

Pot 4 w/ crits

SV deploy/idle bits

Throttle

Experimental

Testing Results

56

Spring Final Review

DM Release On-Demand Flight Test

Test Results

Altitude/Altitude CMD plot

Tracking Error Plot

Experimental

Testing Results

57

Spring Final Review

MADS Test Schedule

• Ground testing performed first

• Flight tests occurred only after successful ground tests

Flight Testing

Ground Testing

Experimental

Testing Results

= Test Completed

JAN

17 25

FEB MAR

1 13 16 18

APR

5 11

MAY

58

Spring Final Review

System Architecture

Fabrication and Integration

Experimental Test Results

Project Management

Project Summary

Spring Final Review 59

PMP Summary

Project

Management

MADS

Kurt Maute

William Emery

PAB Advisors

Eric Frew

Customer

Travis Schafhausen

Project Manager

Leah Crumbaker

Safety Engineer

Kristina Wang

Webmaster

Scott Tatum

Chief Financial Officer

Leah Crumbaker

Systems Engineer

Aerodynamics

Jeff Mullen

Kristina Wang

Leah

Crumbaker

Avionics/

Electronics

Matthew

Lenda

Jeff Mullen

Travis

Schafhausen

SV Design

Kristina Wang

Matthew

Lenda

Travis

Schafhausen

Mechanics/

Deployment

Scott Tatum

Jason Farmer

Leah

Crumbaker

Structures

Jason Farmer

Scott Tatum

James Gordon

Software

James Gordon

Matthew

Lenda

Jeff Mullen

Fabrication

Jason Farmer

Test

Jeff Mullen

Travis

Schafhausen

60

Spring Final Review

Budget Breakdown

Project

Management

Remaining

Project Management

Sub Vehicle

32%

System Expense Breakdown

Shipping

Ground Station

Primary Vehicle

Misc Items

Deployment Mechanism

6% 3% 6%

22%

6%

5%

20%

Budget Issues

• Remaining Budget: $140

• Why we spent more than expected

• Shipping Costs: $285

• Used 30% margin on many misc items

• Unexpected items that were not budgeted: $ 1300

Unexpected Charges

Compact Flash Card

DM Servos

Carbon Fiber Beams

Cost

$50.00

$87.47

$92.30

3 additional Fully outfitted SVs

Li-Po Charger

USB 2 Serial Cable

Micro Servo Cables

DM Battery

DP3T Switch

DM & PIC Boards

Total

$571.68

$130.00

$36.99

$103.62

$36.99

$66.01

$142.59

$1,317.65

Project

Management

Use

For high speed camera

Possible DM (not used)

Original beam idea(not used)

All extra equipment for 3 additional SVs

For charging Li-Po batteries

For DEV board programming

PV DM Electronics

PV DM Electronics

PV DM Electronics

PV DM Electronics

Industry Equivalent

Labor

• ~25 hrs/person/week = ~3000 hrs/semester

• ~$30.00/hr = ~$62,400/year

• ~$180,000 in salaries

Materials

• $4000.00 Course Budget

• $2200.00 Customer Input

• $ Travel Allowance

Overhead

• 200%

• ~$400,000.00

Spring Final Review

Project

Management

63

Scheduling

Project

Management

Spring Final Review

64

Lessons Learned

Project

Management

Budget

• Watch closely

• Multiple people

• Submission and approval system

• Beware shipping and miscellaneous expenses

Team Dynamics

• Design by committee is difficult

• Quickly break into subsystem teams

• Review by committee

• Keep the design and the feedback impersonal

• Juggling 8 different personalities

Scheduling

• Aggressive test schedule left room for schedule slips later in the semester

• Pilots with flexible schedules

• Plan for weather delays

• Take advantage of schedule slips in one subsystem to advance another.

Outside Resources

• AAM

65

Spring Final Review

System Architecture

Fabrication and Integration

Experimental Test Results

Project Management

Project Summary

Spring Final Review 66

Accomplishments

• SIG Rascal 110

• Altitude recorded at SV deployment

• Velocity recorded at SV deployment

• Endurance derived from data

• Stability model verified

Primary

Vehicle

• Flight capable

• Velocity requirement met

• Endurance derived from data

• Stability requirement met through autopilot flight

• Carry 4 SVs

• Deploy 4 SVs

• Release on demand

Sub-Vehicle

Deployment

Mechanism

Project

Summary

• Sample data

• Stream data from the SV to GS and PV to GS

• Interpret data

• PV – DM interface

• DM – SV interface

• Full system fit and functional

CDH System

Interim Review #1

67

Lessons Learned

Major Issues

Linear Actuators

Real term in MATLAB

Monetary Budget

Project

Summary

Lessons Learned

Do not trust components from venders. Take the risk, take apart and understand the component before interfacing it with the rest of the system. Or reverse engineer the mechanism and make a more reliable one.

Use C-Sharp. MATLAB is not fast enough.

Apply for any funding regardless of the large margin in the original budget. Avoid rush ordering all COTS pieces because any margin will diminish quickly.

68

Interim Review #1

Future Applications

Project

Summary

MADS provides a proof of concept that in-flight deployment of air vehicles and the overall dynamics associated with such an action can be managed, predictable, and reliable. This technology can be further developed and used for different applications:

• Test cooperative communication protocols

• Adapt revised deployment systems for more advanced PVs and SVs for the following:

• Longer data collection times

• Larger areas to cover and characterize

• Dangerous/Difficult situations that require data-collection (i.e. severe weather, wildfire observation)

MADS 2.0: potential Masters project (Fall 2009)

69

Interim Review #1

Project

Summary

Spring Final Review

70

Conclusions

• MADS is complete!

Project

Summary

Spring Final Review

71

Acknowledgements

Prof. Bill Emery and Prof. Kurt Maute – Our faculty advisors have given useful feedback throughout the design process.

Prof. Dale Lawrence – Dr. Lawrence supervised our wind tunnel testing and allowed us to use his equipment for data collection.

Frank Dilatush – Frank has provided an abundance of useful information regarding RC planes and suggested our final SV choice. He has also offered additional time and resources to our team during the critical design and testing phases of the project.

Eric Frew – Our customer has offered many hours in helping us develop our project goal and requirements.

Georg Pingen – Georg assisted with CFD analysis by offering help with PowerFlow.

David Halko– The designer and manufacturer of SuperFly RC planes has provided additional specifications and information about his products and offered future help with the project.

Trudy Schwartz – Trudy has been a great help in our consideration of electromagnetic deployment during preliminary design. She has guided us in our calculations and component search.

Bill Pisano – Bill has helped a great deal in aiding our understanding of the CUPIC.

Tom Aune - Tom has helped with the selection of PV flight components

PAB – The members of the PAB have provided constructive criticism, feedback, and guidance throughout project definition, development, and design.

72

Spring Final Review

Back-Up Slides

Spring Final Review

73

Linear Actuator Improvement

Experimental

Testing Results

First deployment flight test resulted in failed deployments, and potentiometers damaged.

Problem: Plastic sleeve slipped off metal screw during retraction

Solution: Adhere plastic sleeve to metal using CA glue

Problem: Bent metal contact points for potentiometer, causing no potentiometer reading

Solution: Bend contact points back to original form, avoid applying pressure to parts of the linear actuator

74

Interim Review #1

Linear Actuator Improvement

Test of the pre- and post-repaired linear actuators within and outside of the brackets showed which were pulling to manufacturer’s specified 18 N.

Experimental

Testing Results

Linear Actuator Unrepaired, Old

DM Bracket

1

2 (successful deployment)

3

4 (successful deployment)

6 N

18 N

8 N

18 N

Unrepaired

10 N

18 N

8 N

18 N

Repaired

18 N

18 N

18 N

18 N

Conclusion: Damaged from compression. Problems were repaired, and actuators are able to sustain greater loads.

Repaired, New

DM Bracket

18 N

18 N

16 N

18 N

Full System Mass

Requirement to Verify:

The DS shall not move the CG from [XXX] Location

• Mass of the full system and components to determine CG

• Mass with each possible deployment configuration

• Take mass at landing gear locations

• Sum moments to determine CG location

Experimental

Testing Results

Full System Mass

Test Results

Tables of CG location and total masses

Experimental

Testing Results

Full System Mass

Comparison to Model

Model CG locations and Actual locations and required adjustments

Experimental

Testing Results

Full Configuration Flight Test

February 8, 2009

Experimental

Testing Results

Spring Final Review

79

In-Flight Deployment

March 18, 2009

Experimental

Testing Results

Spring Final Review

80

In-Flight Deployment

March 18, 2009

Experimental

Testing Results

Spring Final Review

81

PV/SV Flight Capability

Experimental

Testing Results

Spring Final Review

82

PV Engine Characterization

Experimental

Testing Results

The PV and DM shall have a minimum flight endurance of 15 minutes.

Specific Fuel Consumption at different RPM values

4

3.5

Engine 1: Prop 16x8

Engine 2: Prop 15x8

Engine 2: Prop 16x8

• At ~ 4660rpm (~30% throttle)

• 1.6010 lb/(hp*hr)

• 0.3480 oz/min

•At ~ 6660rpm (~50% throttle)

• 1.6043 lb/(hp*hr)

• 0.4380 oz/min

•At ~ 7500rpm (~75% throttle)

• 2.3320 lb/(hp*hr)

• 1.5660 oz/min

3

2.5

2

1.5

1

0.5

4500 5000 5500 6000 6500 7000 7500

RPM

Error bars: derived from the accuracy of volume measurements, time and rpm values for horse power.

8000

83

Interim Review #1

PV Engine Characterization

Measured Thrust

10

Engine 1

Engine2

5

Experimental

Testing Results

0

-5

-20 0 20 40 60

Percent Throttle

80 100 120

Error bars: derived from standard deviation of load cell test data that was taken during the experiment.

84

Interim Review #1

PV Engine Characterization

Theoretical Thrust

12

10

Engine 1, Test 1

Engine 2, Test 1

Engine 2, Test 2

8

6

4

2

0

-20 0 20 40 60 80 100

Percent Throttle

Error bars: derived from the accuracy of being able to measure rpm values.

120

Interim Review #1

Experimental

Testing Results

85

Budget Breakdown

Product

Primary Vehicle

Aircraft

Servos/Electronics

Engines

Fuel System

Field Equipment

CUPIC

Subtotal

Deployment Mechanism

Cost ($)

0

0

0

0

0

290

Mountings

Linear Actuator

Electronic Circuits

Subtotal

Project Management

FFR Printing

Credit Card Overhead

Repay Frank for Superfly

Subtotal

#

1

1

1

1

1

1

$290.00

Cost Breakdown

Total ($)Notes Product

0

Sub Vehicle

Airframe

0

0

0

0 Provided Servo/Electonics by

RECUV

Additional/ Spare Parts

CUPIC

Subtotal

290 Ground Station

RC Transmitter

XBee Pro Ground Station

250 1

70 4

360 1

$890.00

250

280

360

62 1

37.04

1

116.95

1

$215.99

62

37.04

116.95

USB to Serial Cable

Subtotal

Misc Items

EagleTree

High Speed Camera Card

Li-Po Charger

Horizon Sensor

Misc Hardware/ Tools

Subtotal

Shipping

Total

Available

Balance/Additional Margin

Cost ($)

50

190

150

290

0

211

36.99

300

50

130

48

450

Project

Management

# Total ($)Notes

5 250

4 760

1 150

1 290

$1,450.00

RECUV 1

1

0

211

1 36.99

$247.99

1

1

1

300

50

130

1 48

1

$978.00

450

$285.00

$3,855.99

$4,000.00

$144.01 3.60%

Download