Project : Ministry of Taxation Tower BAKU Office & Residental Tower Preliminary Design & Steel Deck Alternative Presentation General 3D Views General Architectural Design Concept Upper 2 Cubes Residental Usage Lower 3 Cubes Office Usage Podium & Auditorium General Overview • The site is located on Haydar Aliyev Avenue in Baku. General Section of MOT Tower General Schematic Designers General Overview of Schematic Structural Design From WSI Schematic Design Typical PT Slabs by WSI Lower Cube Structural System Lower Cube System Upper Cube Structural System Cantilever PT Slabs Central Core Lower Cube System Brief Structural Description of MOT Tower • Vertical Load Bearing System Brief Structural Description of MOT Tower • Lateral Load Bearing System Design Standards and Codes Structural Materials Structural Materials Loads Vertical Loads on Stories & Podium Loads Wind Loads From the rigid tunnel test results of Wacker Engineering Overall maximum forces and moments for the tower “Ministry of Taxation” – proximity model Loads Seismic Loads Loads Seismic Loads Loads Seismic Loads Loads Seismic Loads Main Structural Issues ETABS Model Main Structural Issues Outer Core Wall Thicknesses with initial stiffnes of tower Main Structural Issues Extruded View of the Core & Core Thicknesses Inner Core uniform thickness 40 cm Outer core thickness varying thickness 100cm from bottom to 40 cm at top Main Structural Issues Modal Analysis Results (According to WSI Design ) Main Structural Issues - Main challenging issue may be assumed as Wind Load. - In Baku Wind Load effects have very high values. Wacker Engineering Wind Tunnel Rigid Test Results Mean value of Wind Loads Main Structural Issues Wacker Engineering Wind Tunnel Rigid Test Results Total Story Shears Main Structural Issues With the initial stiffness of tower : T = 4.24 s f = 0.235 Hz Main Structural Issues Main recommendations from the first wind tunnel test (rigid) results : Main Structural Issues Main recommendations from the first wind tunnel test (rigid) results : Main Structural Issues Main recommendations from the first wind tunnel test (rigid) results : Main Structural Issues Top Story Acceleration Two arising problems after first rigid wind tunnel test result Vortex Resonance Effect of Wind Load Main Structural Issues Top Story Accelaration Criteria Check with initial tower stiffness Main Structural Issues Aeroelastic test results with increased stiffness of the tower. Increased Core Wall thicknesses for aeroelastic wind tunnel test Main Structural Issues Aeroelastic test results conclusions Main Structural Issues With stiffening the outer core wall of the tower ; Top Story Acceleration NOT OK. Acceleration at Cube 5 is still not acceptable for Vortex Resonance Effect of Wind Load residential criterias. OK, could be excluded for MOT Tower with frequency of 0.29 Hz. Main Structural Issues Alternative Solution of TMD adapted Tower with Composite Steel Deck Slabs; Advantages : - Major decrease in the tower total mass. - Seismic shear forces reduction. - Seismic base moment reduction. - Economy for foundation & pile design - Decrease in the period of the building due to the dead mass decrease. - This causes increase of the tower’s frequency. - Required damper mass will be less than compared to PT RC slab design. - Total weight and the total cost of the damper will be less compared to required damper for initial PT RC slab design. Alternative Solution of TMD adapted Tower with Composite Steel Deck Slabs; Comparison Table : MoT Tower Comparison of 2 Systems ( Freysinet proposed PT System & Steel Composite Deck ) Parameter PT System Composite Steel Deck Decrease ( % ) Dead Mass (kN) 507500 392000 22.76 Seismic Mass (kN) 640000 525000 17.97 Seismic Base Shear (kN) 2840 2350 17.25 Seismic Overturning Moment (mN) 3400 2710 20.29 First period of the structure (s) 4.52 4.01 11.28 Frequency of the structure (Hz) 0.22 0.25 -13.64 Apprx. Required TMD Weight (kN) 5500 4500 18.18 Alternative Solution of TMD adapted Tower with Composite Steel Deck Slabs; Comparison of Core Reinforcement Ratios. Reinforcement Ratios of MOT Tower Inner & Outer Core Materials Concrete Reinforcement C50 fyk = 420 Mpa Inner Core Uniform Elevations Foundation ~ + 25.700 m 25.700 m +47.700 m 47.700 m ~ +77.400m 77.400 m ~ +107.10m 107.10m ~ +136.80 m 136.80m ~ +168.40 m Wall thickness (cm) 40 40 40 40 40 40 Reinforcement Ratio 0.01 0.01 0.01 0.008 0.008 0.008 Outer Core -1 Uniform Elevations Foundation ~ + 25.700 m 25.700 m +47.700 m 47.700 m ~ +77.400m 77.400 m ~ +107.10m 107.10m ~ +136.80 m 136.80m ~ +168.40 m Wall thickness (cm) 100 80 50 50 40 40 Reinforcement Ratio 0.035 0.035 0.035 0.025 0.02 0.015 Outer Core -2 Uniform Elevations Foundation ~ + 25.700 m 25.700 m +47.700 m 47.700 m ~ +77.400m 77.400 m ~ +107.10m 107.10m ~ +136.80 m 136.80m ~ +168.40 m Wall thickness (cm) 100 80 50 50 40 40 Reinforcement Ratio 0.025 0.02 0.02 0.015 0.015 0.01 Coefficient for Quantity splices, etc 78.5 78.5 78.5 62.8 62.8 62.8 1.3 1.3 1.3 1.3 1.3 1.3 Coefficient for Quantity splices, etc 274.75 274.75 274.75 196.25 157 117.75 1.3 1.3 1.3 1.3 1.3 1.3 Coefficient for Quantity splices, etc 196.25 157 157 117.75 117.75 78.5 1.3 1.3 1.3 1.3 1.3 1.3 Final Quantity 102.05 102.05 102.05 81.64 81.64 81.64 Final Quantity 357.175 357.175 357.175 255.125 204.1 153.075 Final Quantity 255.125 204.1 204.1 153.075 153.075 102.05 Overall Average 180.47 Typical Structural Solutions for Lower Cubes 3D View of the Lower 3 Cubes ROTATING FLOOR SLABS CUBE COLUMNS Φ508 mm STEEL TRANSFER TRUSSES Typical Structural Solutions for Lower Cubes 3D View of the Lower 3 Cubes STEEL TRANSFER TRUSSES FOR FIRST 3 CUBES Typical Structural Solutions for Lower Cubes Terrace Floor Plans PERIMETER BEAMS SECONDARY BEAMS COMPOSITE STEEL DECK Typical Structural Solutions for Lower Cubes Office Floor Plans PERIMETER BEAMS SECONDARY BEAMS COMPOSITE STEEL DECK DEFLECTION CHECK (G+Q) OFFICE FLOORS RELATIVE DISPLACEMENT OF CANTILEVER ARM ~ 48 mm LIMIT L/150 = 840 /150 = 5.6 cm DEFLECTION CHECK LOWER 3 CUBES RELATIVE DISPLACEMENT OF TRANSFER TRUSS ~ 50 mm LIMIT L/150 = 1100 /150 = 7.33 cm Typical Structural Solutions for 4th Cube 3D View of the 4th Cube ROTATING FLOOR SLABS CUBE COLUMNS Φ457 mm STEEL TRANSFER TRUSSES Typical Structural Solutions for 4th Cube 3D View of the 4th Cube STEEL TRANSFER TRUSSES FOR 4th CUBE Typical Structural Solutions for 4th Cube Terrace Floor Plans PERIMETER BEAMS SECONDARY BEAMS COMPOSITE STEEL DECK Typical Structural Solutions for 4th Cube Office Floor Plans PERIMETER BEAMS SECONDARY BEAMS COMPOSITE STEEL DECK DEFLECTION CHECK (G+Q) OFFICE FLOORS RELATIVE DISPLACEMENT OF CANTILEVER ARM ~ 25 mm LIMIT L/150 = 700 /150 = 4.67 cm DEFLECTION CHECK 4th CUBE RELATIVE DISPLACEMENT OF TRANSFER TRUSS ~ 51 mm LIMIT L/150 = 780 /150 = 5.2 cm Typical Structural Solutions for 5th Cube 3D View of the 5th Cube ROTATING FLOOR SLABS CUBE COLUMNS Φ323.9 mm STEEL TRUSSES Typical Structural Solutions for 5th Cube Terrace Floor Plans PERIMETER BEAMS SECONDARY BEAMS COMPOSITE STEEL DECK Typical Structural Solutions for 5th Cube Residential Floor Plans PERIMETER BEAMS SECONDARY BEAMS COMPOSITE STEEL DECK DEFLECTION CHECK (G+Q) RESIDENTIAL FLOORS RELATIVE DISPLACEMENT OF CANTILEVER ARM ~ 69 mm LIMIT L/150 = 1060 /150 = 7.1 cm DEFLECTION CHECK 5th CUBE RELATIVE DISPLACEMENT OF TRUSS ~ 62 mm LIMIT L/150 = 1060 /150 = 7.1 cm Typical Details for Composite Steel Deck Typical Details for Composite Steel Deck Material List for Preliminary Steel Design Cube by Cube MOT TOWER MATERIAL LIST Section Text IPE270 IPE330 IPE360 IPE400 IPE450 IPE500 T IPE600 HE200B O HE220B P HE240B HE260B HE280B C HE300B HE320B U HE400B B IPE500-600 IPE400-550 E TUBO-D114.3X3.6 PIPE323.9*12 NumPieces Unitless TotalLength TotalWeight m Tonf 41 124.17 4.47 33 216.96 10.66 48 324.82 18.54 88 722.82 47.94 8 96.06 7.45 16 121.29 11.04 48 101.50 12.43 16 36.35 2.23 4 8.92 0.64 16 26.79 2.23 4 19.79 1.83 24 64.88 6.67 4 10.36 1.21 12 74.94 9.47 26 71.01 11.04 4 6.60 0.70 8 13.20 1.13 100 226.66 2.23 24 105.82 9.77 The Total Weight of Profiles= 161.68 For connection elements, splices (0.25 coefficient is used)= 40.42 The Total Weight of top Cube= 202.09 The Total Composite Deck Area approximately 1950m², kg/m² 103.64 Material List for Preliminary Steel Design Cube by Cube MOT TOWER MATERIAL LIST Section Text IPE200 IPE220 IPE240 IPE270 C IPE300 U IPE600 HE220B B HE320B E HE360B HE400B PIPE457.2*16 4 NumPieces Unitless TotalLength TotalWeight m Tonf 44 17576.789 3.9319 64 37131.954 9.7344 80 52231.342 16.0297 40 28719.055 10.3467 12 8495.316 3.5874 136 122653.331 150.183 48 11456.214 8.1828 24 10055.726 12.7074 47 13141.751 18.6702 1 198.125 0.3079 40 17610.179 30.6539 The Total Weight of Profiles= 264.34 For connection elements, splices (0.25 coefficient is used)= 66.08 The Total Weight of Cube 4= 330.42 The Total Composite Deck Area approximately 3341m², kg/m² 98.90 Material List for Preliminary Steel Design Cube by Cube MOT TOWER MATERIAL LIST Section Text IPE300 IPE500 IPE600 IPE360 C IPE270 IPE450 U PIPE 508/10 B HE200A HE200A E HE300A HE600B HE360B 3 NumPieces TotalLength TotalWeight Unitless m Tonf 172 1212.71 51.22 8 73.24 6.67 72 720.00 88.17 44 372.10 21.24 72 326.75 11.75 28 263.18 20.41 32 140.89 17.03 16 70.40 2.97 8 35.22 1.49 4 17.60 1.56 88 240.02 49.75 64 250.35 35.57 The Total Weight of Profiles= 307.82 For connection elements, splices (0.25 coefficient is used)= 76.96 The Total Weight of Cube 3= 384.78 The Total Composite Deck Area approximately 3825m², kg/m² 100.60 Material List for Preliminary Steel Design Cube by Cube MOT TOWER MATERIAL LIST Section Text IPE300 IPE500 IPE600 IPE360 C IPE270 IPE450 U PIPE 508/10 B HE200A HE200A E HE300A HE600B HE360B 2 NumPieces TotalLength TotalWeight Unitless m Tonf 172 1384.55 58.47 8 83.62 7.61 72 822.02 100.66 44 424.83 24.25 72 373.05 13.42 28 300.47 23.30 32 160.86 19.44 16 80.38 3.39 8 40.21 1.70 4 20.09 1.78 88 274.04 56.80 64 285.82 40.61 The Total Weight of Profiles= 351.44 For connection elements, splices (0.25 coefficient is used)= 87.86 The Total Weight of Cube 2= 439.30 The Total Composite Deck Area approximately 4367m², kg/m² 100.60 Material List for Preliminary Steel Design Cube by Cube MOT TOWER MATERIAL LIST Section Text IPE300 IPE500 IPE600 IPE360 C IPE270 IPE450 U PIPE 508/10 B HE200A HE200A E HE300A HE600B HE360B 1 NumPieces TotalLength TotalWeight Unitless m Tonf 172 1536.85 64.91 8 92.82 8.45 72 912.45 111.74 44 471.56 26.91 72 414.08 14.89 28 333.52 25.87 32 178.55 21.58 16 89.22 3.77 8 44.64 1.89 4 22.30 1.98 88 304.18 63.04 64 317.26 45.08 The Total Weight of Profiles= 390.10 For connection elements, splices (0.25 coefficient is used)= 96.32 The Total Weight of Cube 1= 481.61 The Total Composite Deck Area approximately 4841m², kg/m² 99.50 Material List for Preliminary Steel Design Total Weight Total weight of the steel = 1840 t For connection elements, splices (0.25 coefficient is used) Steel deck weight is not included in the total weight. Primary Details & Critical Points for Composite Steel Deck System ; - Vibration Check for Composite Slabs Primary Details & Critical Points for Composite Steel Deck System ; - Vibration Check for Composite Slabs Damping ratio is accepted as 0.03 To take the effect of walls into account. Primary Details & Critical Points for Composite Steel Deck System ; - Vibration Check for Composite Slabs Acceptance Criteria for Human Walking Excitation Primary Details & Critical Points for Composite Steel Deck System ; - Vibration Check for Composite Slabs SLAB CHECK 1 SLAB CHECK 2 Primary Details & Critical Points for Composite Steel Deck System ; - Slab Check 1 Vibration Check Joist / Beam Mode Maximum moment at beam due to dead loads M= 115kNm Linear Load from dead loads wjb = 16.355556kN/m Additional deflections Deflection due to dead loads Δjb = 0.0855366mm Frequency of the composite slab fjb 2.1145423 Total weight of the composite slab wj 122.66667 Support Deflection Column Deflection 85.53659849m 15mm 56mm Primary Details & Critical Points for Composite Steel Deck System ; - Slab Check 1 Floor occupancy OfficeAcceleration limit Constant Force 0.29kN Damping Ratio 0.03 0.005g Panel acceleration value Ap Target 0.03759527m/s^2 0.0490500m/s^2 OK Primary Details & Critical Points for Composite Steel Deck System ; - Slab Check 1 Vibration Check wg = Combined Mode 55.757576kN/m Support Deflection Column Deflection Girder Length 15m Wg Δgb = 418.18182kN 30 fgb 3.2549654Hz fgb (combined) W ( with effective panel weight ) mm 2.005827Hz 417.09518 kN 49mm mm Primary Details & Critical Points for Composite Steel Deck System ; - Slab Check 1 Floor occupancy OfficeAcceleration limit Constant Force 0.29kN Damping Ratio 0.03 Panel acceleration value Ap 0.0114855m/s^2 Target 0.0490500 0.005g Primary Details & Critical Points for Composite Steel Deck System ; - Slab Check 2 Vibration Check Maximum moment at beam due to dead loads M= 80kNm Linear Load from dead loads wjb = 12.51895kN/m Deflection due to dead loads Δjb = 0.0932349m Frequency of the composite slab fjb 1.8463655 Total weight of the composite slab wj 89.51049 Support Deflection Column Deflection 93.23493295mm 84mm 0mm Primary Details & Critical Points for Composite Steel Deck System ; - Slab Check 2 Floor occupancy OfficeAcceleration limit Constant Force 0.29kN Damping Ratio 0.04 0.005g Panel acceleration value Ap Target 0.04244347m/s^2 0.0490500m/s^2 OK Should be filled manually Primary Details & Critical Points for Composite Steel Deck System ; - Vibration Check for Composite Slabs SLAB CHECK 3 Primary Details & Critical Points for Composite Steel Deck System ; - Slab Check 3 Vibration Check Joist / Beam Mode Maximum moment at beam due to dead loads M= 137kNm Linear Load from dead loads wjb = 7.0144kN/m Additional deflections Deflection due to dead loads Δjb = Support Deflection Column Deflection 0.0755501mm Frequency of the composite slab fjb 2.4945975 Total weight of the composite slab wj 87.68 75.55006748m 51mm 0mm Primary Details & Critical Points for Composite Steel Deck System ; - Slab Check 3 Floor occupancy OfficeAcceleration limit Constant Force 0.29kN Damping Ratio 0.03 Panel acceleration value Ap Target 0.04604577m/s^2 0.0490500m/s^2 0.005g Project : Ministry of Taxation Tower BAKU Office & Residental Tower Upper&Lower Cubes – Truss & Core Connection Typical Details Typical Structural Solutions for 5th Cube 3D View of the 5th Cube Transfer Truss 3d View of The 4th Cube Transfer Truss 3d View of The 3th Cube ( Similar to 1st and 2nd Cube ) Transfer Truss Plan View of The Transfer Story at the 5th Cube Transfer Trusses Plan View of The Transfer Story at the 4th Cube Transfer Trusses Plan View of The Transfer Story at the 3rd Cube Transfer Trusses 3d View of The 3th Cube Truss (Similar to 1st and 2nd Cube) 3d View of The 3th Cube Truss (Similar to 1st and 2nd Cube) 3D View of the Transfer Truss at 4th Cube 3D View of the Transfer Truss at 5th Cube Axial Load Diagram of Truss Elements (Most Unfavorable Combination) P(tension) = 1670 kN P(compression) = 3410 kN Punching Check of The Core Wall 5th Cube (Governing action at bottom chord connection) Punching Check of The Core Wall P1 = 1670 kN P2 = - 2380 kN P3 = -3410 kN Equivalent Horizontal Force : Phor = P3*cos7+P2*sin47= 5150 kN Vd = 5150 kN Vrc = ϒ . Up. fctd . d ϒ = 0.90 fctd = 1650 kN/m2 (C50) Up = ( 1.20 + 0.225) x 2 + ( 0.70 + 0.225 ) x 2 = 4.7m d = 0.45 m Vrc = 0.90 x 4.7 x 1650 x 0.45 = 3140 kN Vr = Vrc + Vrs Vrs = 5150 – 3140 = 2010 kN 8 x φ 20 / 150 selected transverse reinforcement Asw / sw = 167.55 cm2 /m Rsw = 30 kN/cm2 Vrs = Asw / sw x d x Rsw = 2261 kN > Vrs = 2010 kN OK. Concrete Bearing Check σ = ( Phor / Aplate ) = 5150 / ( 1.20 * 0.70 ) = 6130 kN/cm2 σlim = fcd*/2 = 16667 kN/cm2 > 6130 kN/cm2 OK. Uniform Core Wall Thickness t = 500 mm Plate dimensions 0.70 m * 1.20 m Vertical Shear Force will be transferred by bolts Equivalent Vertical Force : Pver = P3.sin7+P2*cos47 = 2040 kN Vertical Shear Force will be transferred by bolts 1 bolt shear strength (8.8) M36 Vrs = 0.75*0.45*Fu = 0.45*8 * 10.17 =27.45t n = 204 / 27.45= 8 bolts for connection Top Chord Brace Connection to Core Check of Anchor Bolts at tension Ptmax = 2000 kN Top Chord Connection to Truss Check of Anchor Bolts (M36 – 8.8) Pr = 0.75 * 0.75 * 8 * 10.17 * 12 = 548 t > Pd = 200 t Top Chord Connection to Truss Punching Shear at Top Chord 12 M36 8.8 Vd = 2000 kN Vrc = ϒ . Up. fctd . d ϒ = 0.90 fctd = 1650 kN/m2 (C50) Up = ( 4*1.08) = 4.32 m d = 0.45 m Vrc = 0.90 x 4.32 x 1650 x 0.45 = 2880 kN > Vd = 2000 kN Concrete Bearing Check σ = ( Phor / Aplate ) = 2000 / ( 0.6*0.6 ) = 5555 kN/cm2 σlim = fcd*/2 = 16667 kN/cm2 > 5555kN/cm2 OK. Uniform Core Wall Thickness t = 500 mm Plate dimension 600 mm* 600 mm Punching Check of The Core Wall 4th Cube (Governing action at bottom chord connection) P1 P2 P3 Punching Check of The Core Wall P1 = 2000 kN P2 = -2380 kN P3 = -3000 kN Equivalent Horizontal Force : Phor =P3 = 3000 kN Vd = 3000 kN Vrc = ϒ . Up. fctd . d ϒ = 0.90 fctd = 1650 kN/m2 (C50) Up = ( 0.60 + 0.225) x 2 + ( 0.60 + 0.225 ) x 2 = 3.3 m d = 0.45 m Vrc = 0.90 x 3.3 x 1650 x 0.45 = 2205 kN Vr = Vrc + Vrs Vrs = 3000 – 2205 = 795 kN 5 x φ 16 / 150 selected transverse reinforcement Asw / sw = 67.03 cm2 /m Rsw = 30 kN/cm2 Vrs = Asw / sw x d x Rsw = 904 kN > Vrs = 3000 - 2205 = 795 kN Concrete Bearing Check σ = ( Phor / Aplate ) = 3000 / ( 0.60 * 0.60 ) = 8333 kN/cm2 σlim = fcd*/2 = 16667 kN/cm2 > 8333 kN/cm2 OK. Uniform Core Wall Thickness t = 500 mm Plate dimensions 0.60 m * 0.60 m OK. Top Chord Connection to Core Check of Anchor Bolts at tension Ptmax = 2000 kN + 2400 kN * cos45 = 3697 kN Top Chord Connection to Truss Check of Anchor Bolts (M36 – 8.8) Pr = 0.75 * 075 * 8 * 10.17 * 12 = 549 t > Pd = 369 t Top Chord Connection to Truss Punching Shear at Top Chord Vd = 3697 kN Vrc = ϒ . Up. fctd . d ϒ = 0.90 fctd = 1650 kN/m2 (C50) Up = ( 0.82*4) = 3.28m d = 0.45 m Vrc = 0.90 x 3.28 x 1650 x 0.45 = 2191 kN > Vd = 2000 kN Concrete Bearing Check σ = ( Phor / Aplate ) = 3697 / ( 0.60 * 4) = 1540 kN/cm2 σlim = fcd*/2 = 16667 kN/cm2 > 1127kN/cm2 OK. Uniform Core Wall Thickness t = 500 mm Plate dimension 600 mm* 600 mm Vertical Shear Force will be transferred by bolts Equivalent Vertical Force : Pver = P3.sin7 + P2.sin50 = 2240 kN Vertical Shear Force will be transferred by bolts 1 bolt shear strength (8.8) M36 Vrs = 0.75*0.45*Fu = 80 * 0.45 * 10.17 = 275.0 kN n = 2240 / 275.0 = 9 bolts for connection 12 M36 Vr = 3300 kN > 2240 kN Punching Check of The Core Wall 3th Cube ( Governing action at bottom plate connection ) P1= Total tensile force P2= Total compressive force Punching Check of The Core Wall P1 = 12400 kN P2 = -12060 kN Vd = 12400 kN Vrc = ϒ . Up. fctd . d ϒ = 0.90 fctd = 1650 kN/m2 (C50) Up = ( 5.25 + 0.225) x 2 + ( 1.06 + 0.225 ) x 2 = 13.52 m d = 0.45 m Vrc = 0.90 x 13.52 x 1650 x 0.45 = 9034 kN Vr = Vrc + Vrs Vrs = 12400 –9034 = 3366 kN Asw / sw = 250 cm2 /m OK. Concrete Bearing Check σ = ( Phor / Aplate ) = 12400 / ( 5.25 * 1.06 ) = 2228 kN/cm2 σlim = fcd*/2 = 16667 kN/cm2 > 2228 kN/cm2 OK. Uniform Core Wall Thickness t = 500 mm Plate dimensions 5.25 m * 1.06 m Top Chord Connection to Core Check of Anchor Bolts at tension Ptmax = 12400 kN 42 M36 (8.8) Top Chord Connection to Truss Check of Anchor Bolts (M36 – 8.8) Pr = 0.75 * 075 * 8 * 10.17 * 42 = 1922 t > Pd = 1240 t Vertical Shear Force will be transferred by bolts Equivalent Vertical Force : Pver= 5650kN Vertical Shear Force will be transferred by bolts 1 bolt shear strength (8.8) M36 Vrs = 0.75*0.45*Fu = 80 * 0.45 * 10.17 = 275.0 kN n = 5650 / 275 = 21 bolts for connection 42 M36 Vr = 11550 kN > 5650 kN Out of Plane Bending Moments of Core Wall at Transfer Truss Surface M22 ( Vertical direction ) -250 kN.m 350 kN m Out of Plane Bending Moments at Core Wall at Transfer Truss Surface SECTION/ СЕЧЕНИЯ h' M am e z As Арматура 1 Арматура 2 A As Asmin (mm2) (mm2) (mm2) (mm2) (mm2) (mm2) b h (mm) (mm) (mm) ( kN.m ) 1000 700 50 250.0 0.039 0.039 0.980 902.0 Ø 16 / 200 + Ø 0 / 200 1005.31 > 1000 700 50 320.0 0.050 0.051 0.975 1161.2 Ø 20 / 200 + Ø 0 / 150 1570.80 > 1161.23 Additionally φ20/200 reinforcement will be added vertically to resist the out of plane moment at core wall. 901.97 Out of Plane Bending Moments of Core Wall at Transfer Truss Surface M11 ( Horizontal direction ) -300 kN.m 600 kN m Out of Plane Bending Moments at Core Wall at Transfer Truss Surface SECTION/ СЕЧЕНИЯ h' M am e z As Арматура 1 Арматура 2 A As Asmin (mm2) (mm2) (mm2) (mm2) (mm2) (mm2) b h (mm) (mm) (mm) ( kN.m ) 1000 700 50 300.0 0.046 0.048 0.976 1086.8 Ø 20 / 200 + Ø 0 / 200 1570.80 > 1086.84 1000 700 50 600.0 0.093 0.098 0.951 2230.9 Ø 25 / 200 + Ø 0 / 150 2454.37 > 2230.86 Additionally φ20/200 outer surface reinforcement will be added horizontally to resist the out of plane moment at core wall. Additionally φ25/200 inner surface reinforcement will be added horizontally to resist the out of plane moment at core wall. TYPICAL DETAILS FOR TRANSFER TRUSS & CORE CONNECTION 4th & 5th Cube TYPICAL DETAILS FOR TRANSFER TRUSS & CORE CONNECTION Lower 3 Cubes TYPICAL DETAILS FOR TRANSFER TRUSS & CORE CONNECTION Lower 3 Cubes TYPICAL DETAILS FOR TRANSFER TRUSS & CORE CONNECTION Lower 3 Cubes TYPICAL DETAILS FOR TRANSFER TRUSS & CORE CONNECTION Lower 3 Cubes