ENERGY HVAC Impact Evaluation – WO32 Summary of the Report Draft For Comment WO32 Evaluation Team September 8, 2014 1 DNV GL © 2014 August 2014 SAFER, SMARTER, GREENER Webinar Agenda and Schedule Webinar Agenda for WO32 Commercial Quality Maintenance Impacts Residential Quality Installation Impacts Upstream Incentive Program Net to Gross Preliminary Laboratory Results Schedule 8/27/2014 Energy Division Released WO 32 report to WHPA 8/29/2014 IOU / CEC Comments due; Public Release (not modified to reflect CEC/IOU comments) 9/8/2014 Public Meeting and Webinar 9/12/2014 Public comments due on the Public Documents Area (PDA) 9/16/2014 Revised Report 2 DNV GL © 2014 August 2014 Project Timeline 3 Milestone Timeframe WO32 Research Plan April 2012 Weekly CQM calls with IOUs and implementers to coordinate pre-post monitoring and site observations (Varies by IOU) July 2012 – December 2013 QI Field Data Collection August – Dec. 2013 Memo and presentations on CQM interim findings August 2013 Presentations on QI interim findings March 2014 WO32 Draft Report August 2014 Comments and Webinar September 2014 2013-14 Research Plans September - October 2014 DNV GL © 2014 August 2014 Commercial Quality Maintenance 4 DNV GL © 2014 August 2014 Evaluation of Statewide CQM Measures The statewide programs were the focus of the evaluation research plan. The statewide programs generally assumed the same average energy savings per ton of cooling independent of which measures were installed. Evaluators coordinated with the statewide programs to sample and monitor units pre- and post-maintenance. This effort presented several logistical and technical challenges. – Recruitment to get pre-conditions – Maintenance observation(s) – Sensor placement and reliability – Unit replacement New - The sample size and representativeness of the sample have been questioned by the IOUs – Additional direct observations were made of top contractors Appendix information needs to be pulled into main report 5 DNV GL © 2014 August 2014 – Additional information on sampling and discussion being added Pre-Post Metering 6 DNV GL © 2014 August 2014 Results The evaluation team found that the realization rate was zero for the package of measures approach in the statewide program based on prepost monitoring. To confirm the results, the evaluation team performed bin analysis on the power consumption data for the same units included in the primary analysis and also found energy savings were negative. New - Since release of the draft report to IOUs and WHPA, additional analysis is being conducted on both unit performance estimation and power consumption analysis New – SDG&E ex ante savings for CQM need revision as records in tracking should total zero. Meaning SDG&E did not claim savings and we did not measure savings for that sample (Savings zero, RR – 100%) 7 DNV GL © 2014 August 2014 Site observations Conducted by Master Technicians under contract to DNV-GL Combination of pre/post and post-only Conducted across all pre/post metering sites in SW program Also conducted across third party programs Focus on contractors representing 75% of the savings claims Maintenance activities observed and cataloged Duplicate measurements taken using research grade instrumentation Maintenance activities and fault detection and diagnostic (FDD) protocols observed compared to program requirements Maintenance activities FDD protocols also compared manufacturer’s recommended service procedures specific to the unit observed 8 DNV GL © 2014 August 2014 Verification of Individual Measures – Economizer Repair Field observation found 25% of economizers worked after repair For economizers, the majority with reported repairs that we inspected were not found to be performing their primary function of changing damper position in response to temperature. In some cases, the technicians opened the position of the dampers, but did not complete working changes to sensors and linkages New – Additional information by IOU program based on Appendix being compiled 9 DNV GL © 2014 August 2014 Verification of Individual Measures – Refrigerant Charge Field observation found 60% of units met program refrigerant charge criteria. The evaluation found problems with the recommended refrigerant charge and airflow (RCA) fault detection procedures and with incorrect implementation of the procedure; this led to a large number of undiagnosed faults. New – Additional information by IOU program based on Appendix being compiled The RCA approach could not be guaranteed to determine correct refrigerant charge faults under ideal conditions (Braun and Yuill) and was more problematic when applied to commercial field conditions. Braun, Jim, David Yuill, and Howard Cheung. A Method for Evaluating Diagnostic Protocols for Packaged Air Conditioning Equipment. Purdue University and the California Energy Commission, 2012. Braun, Jim, and David Yuill. Evaluation of the Effectiveness of Currently Utilized Diagnostic Protocols. Purdue University. 2014. Similar results obtained in lab 10 DNV GL © 2014 August 2014 Conclusions The current program, and commercial unitary HVAC maintenance measures in general, face various inherent challenges, not addressed by current workpapers. The less-than-expected savings and installation rates from both the 2006-08 evaluation and this evaluation stem from trying to address individual faults or subsets of all faults without accounting for underlying system issues. FDD protocols in commercial units especially difficult to implement due to OA intakes and subsequent difficulty in getting an accurate mixed air temperature measurement 11 DNV GL © 2014 August 2014 Conclusions Multiple faults continue to be a source of incorrect or misleading results from program FDD protocols. Recovery and weigh-out of refrigerant charge implemented late this cycle to determine true state of charge; more research planned. Some issues, such as cabinet and economizer damper leakage were likely unknown until recent laboratory research. A comprehensive approach includes some components of maintenance, but also requires that retro-commissioning be completed prior to ongoing maintenance. Program changes since 2010-12 have taken place and additional changes are being considered 12 DNV GL © 2014 August 2014 Recommendations To address these findings, we recommend that IOU programs coordinate to clearly define the meaning of maintenance and retro-commissioning as related to measures and programs. For example: – Sealing economizer and unit leakage may be within the scope of maintenance, but is not part of current programs – The repair for basic functionality requires new parts beyond the scope of maintenance – Retro-commissioning involves setting integrated controls based on measuring unit operation We recommend piloting approaches that have demonstrated measurable savings. Measure recommendations relative to maintenance and repair include: – Seal Unit Leaks. – Reconsider Diagnostic-Based Refrigerant Charge Measures. – Use Manufacturer Maintenance and Diagnostic Protocols. – Develop Criteria to Replace Rather than Repair Economizers. 13 DNV GL © 2014 August 2014 Residential Quality Installation 14 DNV GL © 2014 August 2014 Residential Quality Installation The team conducted site visits at 50 program participants and 50 nonparticipant sites. Site staff followed identical data-collection protocols at participant and non-participant sites. Data collection for all tested units included spot measurement of unit airflow and duct leakage tests. Building envelope characteristics informed load-calculation models for each site. The evaluation team calculated energy savings for participants relative to non-participants based on system sizing, correct airflow, and reduced duct leakage. The team modified the DEER single-family residential prototype workpaper assumptions with measured values for the non-participants as the baseline and program participants as the efficient case. 15 DNV GL © 2014 August 2014 Residential Quality Installation The evaluation centers on the 2010-12 workpaper assumptions – The appropriate DEER calculation method was not used in the ex ante or ex post – Fan watt draw data was collected but was not incorporated into the savings estimates – Charge diagnostics collected, but only when weather permitted since it was not used in the analysis Clarification – Sizing ratio in the report is installed size relative to calculated size, we do not report sensible heat ratio (SHR) The sizing calculations use inputs based on data collected, not Manual J defaults – report revisions are needed to stipulate these are not “assumptions” when they are “averages” Window shading and overhangs observed during onsites were included in the sizing calculations 16 DNV GL © 2014 August 2014 Quality Installation Findings Statistic Total System Duct Leakage System Airflow (CFM per ton) System Oversizing 17 DNV GL © 2014 August 2014 NonParticipant Field Observations (mean) Baseline Assumptions Participant Field Observations (mean) QI Efficient Case Assumptions 17% 24% 12% 12% 300 350 338 400 13% 20% 10% 0% Duct Leakage 18 DNV GL © 2014 August 2014 Airflow 19 DNV GL © 2014 August 2014 Sizing 20 DNV GL © 2014 August 2014 Conclusions A note on our realization rate calculations: The team could not separate out free-ridership from presumed non-compliance in the gross (workpaper) baseline. Since the workpaper assumed non-compliance, it essentially presumes a standard practice baseline, not a code baseline. The evaluation team learned that installations in the programs exceeded Title 24 code on average and that installations outside the program do not perform as poorly as assumed in program workpapers. The evaluation findings showed that there was a continuous spectrum of installation efficiencies from good to bad outside the QI program. The team also discovered that the program workpaper does not fully capture all aspects of program participants. 21 DNV GL © 2014 August 2014 Recommendations Use a difference of differences approach for workpapers and evaluation to allow separate estimates of gross and net savings. This requires re-defining program workpaper assumptions where the baseline is code. Revise workpapers to consider that the baseline or net savings as defined above vary by code jurisdiction correlated to CZ and unit cost correlated to SEER level. Expand the non-participant sample to support QI programs and “to code” pilots. Ultimately the programs can influence savings for actions that exceed Title 24 requirements if they exist. A few areas where Title 24 can be exceeded: – Explore downsizing to reduce peak demand. – Explore duct sealing to reach a lower target leakage, such as the 6% threshold. – Explore air handlers/furnaces, filters, and duct modifications that reduce pressure drop and improve fan system efficiency. – Explore whether all ANSI/ACCA QI elements in programs impact energy use and align with workpapers. 22 DNV GL © 2014 August 2014 Commercial Upstream Equipment 23 DNV GL © 2014 August 2014 Commercial Upstream Net to Gross The evaluation efforts for the upstream component of the study focused on the level of free-ridership in the Upstream HVAC program. Gross ex ante savings claims are based on DEER estimates and were not evaluated. A participant self-report method was used for the free-ridership/net-togross (NTG) work, and the analysis was based on in-depth telephone interviews with 19 out of 22 participating HVAC distributors that were conducted by DNV GL in 2013. The approach took into account the program’s effect on both the stocking practices and sales practices of the distributors. 24 DNV GL © 2014 August 2014 Methods 2. Program Influence on Sales Q3. Did rebate influence Distributor's equipment sales? Yes Program credit 5% for cited as a influences on sales. No Program credit reduce to 2.5% from 5% when not cited initially as a influence on sales. Probe: Confirm rebate was not a factor in equipment sales. )No program Yes influential credit for equipment sales (-70%) Not influential Q4. Rated influence of rebates' influence on equipment sales on (0-10) Program credit for influence on sales [70%* score (0-10)] Survey Question Quetio Consistency Check: Rebate was rated highly influential >8 in equipment sales? Sum of sales score= Q3 + Q4 = (+/-) 70% Customer Decision Scoring Methods Probe/Consistency Checks _ _ _ Dash Line = Score Flow Logic __ Solid Line = Question Flow Logic 3. Sum of Program Influence on Stocking and Sales Sum of score= [Q1 + Q2 (30%)] + [Q3 + Q4 (70%)] =100% 25 DNV GL © 2014 August 2014 Results Overall, the program is achieving a savings-weighted NTG score of 0.80, versus an un-weighted NTG score of 0.61. The final net to gross ratio was applied to gross energy and demand savings for 2010-12 programs. Stocking Score Sales Score Overall Score Proportion of Program Savings 16.2% 37.5% 53.7% 56.1% Manufacturer-owned or franchise distributor 4.1% 21.3% 25.4% 39.2% Independent manufacturers’ representative 0.0% 0.6% 0.6% 4.7% 20.3% (30%) 59.4% (70%) 79.7% (100%) 100% Type of Distributor Independent HVAC equipment distributor Total (Maximum Potential Total) 26 DNV GL © 2014 August 2014 Commercial Upstream Net to Gross For upstream distributor incentives, the evaluation team learned that the provided incentives influence stocking and sales for the highest volume distributors, but have less influence on lower volume distributors. Some distributors supply units directly from manufacturers, and stocking incentives have no influence there. The team identified some opportunities beyond the efficiency incentives: – The program does not focus on permitting and compliance – The program does not provide additional incentives for climateappropriate systems. 27 DNV GL © 2014 August 2014 Recommendations The program should consider increasing rebate levels for higher efficiency equipment to encourage more sales in the highest efficiency tiers. Program-provided support on how to market high efficiency equipment systems may be helpful to distributors, particularly those who are less successful at selling the concept of high efficiency. Providing a reservation system or rebate guarantee would encourage more participation, and increased high-efficiency sales from distributors who have long sales cycles or custom build equipment. 28 DNV GL © 2014 August 2014 WO 32 Laboratory Results 29 DNV GL © 2014 August 2014 Laboratory Results Testing conducted at AHRI-certified laboratory Master technicians oversaw laboratory technicians who tested packaged HVAC units Additional laboratory tests are continuing and include packaged units from a variety manufacturers. The laboratory tests with actual cabinet leakage and functioning economizers provided critical new findings on the diagnosis of system faults and the efficiency impacts of repairs. Critical findings from laboratory testing with an economizer include: – All tests show that even optimally adjusted systems with an economizer perform significantly lower than their rated efficiency. – The diagnosis and adjustment of charge is difficult, if not impossible, to achieve in the field since the airflow and economizer affect unit performance. 30 DNV GL © 2014 August 2014 Affect of Outside Air and Charge 31 DNV GL © 2014 August 2014 Affect of Outside Air and Airflow 32 DNV GL © 2014 August 2014 Laboratory Results The following laboratory results are available based on tests of the 7.5ton dual-compressor packaged RTU: – The test results demonstrate that reducing minimum damper position can be a reliable measure to improve cooling efficiency – Understanding the efficiency impacts of faults presents several challenges. We found that the efficiency effects of outdoor conditions, indoor conditions and faults exhibit non-linear trends and become more complex when combined, requiring empirical testing to derive efficiency impacts. – Tests with the economizer open from 10% to 30% indicate that loads and energy consumption increase 5% to 62% compared to closed dampers that deliver 15% outdoor air through leakage. 33 DNV GL © 2014 August 2014 Laboratory Results – Outdoor airflow is 15% with closed dampers, 20% with 1-finger open, 23% with 2-fingers open, 30% with 3-fingers open, and 62% with dampers fully open. Designers, technicians, and program implementers assume 2% outdoor airflow with closed dampers and 100% outdoor airflow with fully open dampers. – Program and manufacturer’s FDD protocols could not accurately diagnose faults induced in the laboratory – Manufacturer EER ratings were replicated when using AHRI-specified test conditions – Imposition of test conditions better representing field conditions produced much lower unit efficiency 34 DNV GL © 2014 August 2014 Thank you. Questions? Jarred Metoyer Jarred.metoyer@dnvgl.com 510-891-0446 www.dnvgl.com SAFER, SMARTER, GREENER 35 DNV GL © 2014 August 2014