75 Express Lanes Corridor-Wide Construction From NW 170 Street to I-595 Presentation to FDOT Materials Lab Tuesday, August 19, 2014 Project Team • Paul Lampley, P.E. – FDOT Construction Program Manager • Antonio Castro, P.E. – FDOT Construction Project Manager • Robert Bostian, P.E. – FDOT Design Program Manager • Vanita Saini, P.E. – FDOT Design Project Manager • Raj Rangaswamy, P.E. – CEI Senior Project Engineer, Target Engineering Group • Aurelio Matos, P.E. – CEI Senior Project Engineer, CH Perez & Associates • Scott Gombar, P.E. – CEI Senior Project Engineer, Eisman Russo • Jeremy Grady, P.E. – CEI Bridge Project Administrator, Corradino Group • Amanda Carballo – Construction Public Information Officer • Christopher Lewis, P.E. – Corridor-wide Geo-technical Engineer (FGE) I-75 Express – Corridor-wide Project Limits State Road (SR) 826 from W. Flagler Street to I-75 and I-75 from SR 826 to I-595 (Total 28 miles) D4 Segment : I-75 from NW 170 Street to I-595 (15 miles) D6 Segment: SR 826 from W Flagler Street to NW 154 Street and I-75 from SR 826 to NW 170 Street (13 miles) Regional Managed Lanes Network I-75 Express – Corridor-wide Project Overview Project Location • • • • Segment E – North of Griffin Road to I-595 (4.7 miles) Segment D - South of Sheridan Street to North of Griffin Road (3.7 miles) Segment C - South of Miramar Parkway to South of Sheridan Street (3.6 miles) Segments A & B – NW 170 Street to South of Miramar Parkway (3 miles) I-75 Express – Corridor-wide Scope of Work • Constructing Express Lanes in the existing I-75 median • Constructing ingress and egress points throughout the corridor • Constructing direct connections to 595 Express, Palmetto Express and Florida’s Turnpike (HEFT) • Reconstructing the interchanges at Sheridan Street, Miramar Parkway, Miami Gardens Drive and the HEFT • Constructing sound barrier walls at various locations • Installing additional traffic cameras, dynamic message signs and toll gantries • Adding new signals, signage, lighting and landscaping I-75 Express – Corridor-wide Construction Schedule Projected Express Lane Openings Partial Corridor Opening in Spring 2017 Full Corridor Opening in Summer 2017 Construction Completion in Late 2018 ITS Integration Completion in Summer 2019 I-75 Express – Corridor-wide 75 Express Lanes Typical Section • Express Lanes – Centered in existing I-75 median • Separated from the General Purpose Lanes – Two northbound and two southbound lanes • Separated by concrete barrier wall – Full width paved shoulders I-75 Express – Corridor-wide Ingress & Egress Ramps NOT TO SCALE I-75 Mainline Express Lanes I-75 Mainline Visit the Access Points page to view all of the Ingress and Egress ramps I-75 Express – Corridor-wide Segment E Overview From North of Griffin Road to I-595 Construction start date: March 2014 Estimated construction completion date: Summer 2017 Construction cost: $75 million CEI: Target Engineering Group, Inc. Design-Build Team: Dragados USA/Parsons Brinckerhoff I-75 Express – Corridor-wide Major Work Elements 2 2,300 650,000 29,000 31,000 Bridges Bridge Length Cubic Yards of Embankment Length of Drainage Tons of Asphalt Contractors Quality Control Firm: Terracon I-75 Express – Corridor-wide Proposed Plan View of R3 Ramp I-75 Express – Corridor-wide Proposed Connection Bridge to 595 Express Lanes • • Direct connect from 75 Express Lanes to 595 Express Lanes Temporary ramp closures and detours will be scheduled I-75 Express – Corridor-wide Segment D Overview From of South of Sheridan Street to North of Griffin Road Construction start date: September 2014 Estimated construction completion date: Summer 2018 Construction cost: $80 million CEI: Target Engineering Group, Inc. Design-Build Team: Ranger Construction/Wantman Group I-75 Express – Corridor-wide Major Work Elements 2 540 982,600 25,000 55,400 Bridges Bridge Length Cubic Yards of Embankment Length of Drainage Tons of Asphalt Contractors Quality Control Firm: Tierra South Florida I-75 Express – Corridor-wide C-11 Canal Bridge New Improvement Features Scope of Work: • New Express Lane bridge I-75 Express – Corridor-wide Sheridan Street Interchange I-75 Express – Corridor-wide Sheridan Street Interchange New Improvement Features Scope of Work: • Constructing ponds at the interchange • Widening the Sheridan Street bridge to the north and replacing the existing bridge deck • Installing additional signalized turn lanes • Installing new sidewalk on the bridge • Upgrading signage, lighting, landscaping and signals I-75 Express – Corridor-wide Segment C Overview From South of Miramar Parkway to South of Sheridan Street Construction start date: June 2014 Estimated construction completion date: Summer 2018 Construction cost: $85 million CEI: A&P Consulting Transportation Engineers Design-Build Team: Ranger Construction/Wantman Group I-75 Express – Corridor-wide Major Work Elements 2 910 858,900 39,000 55,000 Bridges Bridge Length Cubic Yards of Embankment Length of Drainage Tons of Asphalt Contractors Quality Control Firm: Tierra South Florida I-75 Express – Corridor-wide Miramar Parkway Interchange I-75 Express – Corridor-wide Miramar Parkway Interchange New Improvement Features Scope of Work: • Reconstructing a new bridge to accommodate the new I-75 Express Lanes (60 feet longer and 36 feet wider) • Reconstructing the interchange ramps at Miramar Parkway • Installing additional signalized turn lanes • Installing new sidewalk on the south side of the bridge • Signage, lighting and signal upgrades I-75 Express – Corridor-wide Miramar Parkway Interchange Existing Interchange Features Dual-left Sidewalk turn onleft north lanes (EB side to only NB) Dual-left turn lanes to SB) Existing turn(WB lanes New Improvement Features signalized ramps New sidewalk on sides Extended Triple-left Dual-left leftNew turn turn turn lanes lanes lanes forboth maximum (EB (WBto toNB) SB)capacity Option forsidewalk future triple-left turn lanes New on both sides I-75 Express – Corridor-wide Pembroke Road Bridge I-75 Express – Corridor-wide Pembroke Road Bridge Scope of Work & Schedule • Collaborative effort between Broward County & FDOT – Broward County will construct bridge approaches – FDOT will construct the bridge over I-75 • Broward County began bridge approaches – June 2014 • FDOT to start bridge construction – September 2014 • Broward County to complete overpass – Final paving, signing, striping, and lighting • Anticipated opening by Broward County – late 2016 I-75 Express – Corridor-wide Pembroke Road Bridge Bridge Features • Four-lane divided bridge with inside and outside shoulders • Bike lanes and sidewalks on both sides • Lighting on the south side of the bridge I-75 Express – Corridor-wide Segments A & B Overview From NW 170 Street (Miami-Dade County) to South of Miramar Parkway Estimated construction start date: Late 2014 Estimated construction completion date: Spring 2019 Construction cost: $234 million CEI: The Corradino Group Design-Build Team: Community Asphalt/Wantman Group I-75 Express – Corridor-wide Major Work Elements 14 6,880 2.0million 60,000 Bridges Bridge Length Cubic Yards of Embankment Tons of Asphalt Contractors Quality Control Firm: Construction Testing Inspection (CTI) I-75 Express – Corridor-wide Proposed I-75/HEFT Interchange I-75 Express – Corridor-wide Proposed I-75/HEFT Interchange Miami Gardens Drive Ramp H-12 HEFT Ramp H-13 Ramp H-5 I-75 Express – Corridor-wide Proposed I-75/HEFT Interchange Ramp H-4 Snake Creek Road Bass Creek Road I-75 Express – Corridor-wide Miami Gardens Drive Interchange New Improvement Features Scope of Work: • Modifying the existing bridges to accommodate the new I-75 Express Lanes and the new ramps • Reconstructing the interchange ramps • Signage, lighting and signal upgrades I-75 Express – Corridor-wide Sound Barrier Walls • Ground Mounted Sound Barrier Walls • To be completed within the first half of the Segment contract • Direct coordination with affected communities • Hours of operation – Daytime work only – No weekend work I-75 Express – Corridor-wide Sound Barrier Wall Location Segment E • Benefited communities • Highland Ranch Estates • New River Estates • Woodgate Condos • Vista Filare • Royal Palm • Forest Oak I-75 Express – Corridor-wide Sound Barrier Wall Location Segment D • Benefited communities • Sheridan Glen • The Crossbow • Waverly Hundred • Falcon’s Lea • Waterford • Hawkes Bluff • Ivanhoe Estates • Chelsea I-75 Express – Corridor-wide Sound Barrier Wall Location Segment C • Benefited communities • Windsor at Miramar • Villas at Nautica • Cobblestone Townhomes • Towngate I-75 Express – Corridor-wide Sound Barrier Wall Location Segments A & B • Benefited communities • Royal Landings • West Lakes Estates • Century Gardens • Lakes on the Green • Marbella Park West • Riviera Isles • Huntington • Courtyards at Nautica I-75 Express – Corridor-wide Stay Informed Sign up for Construction Updates and Lane Closure Information: Project Public Information Officer Amanda Carballo (954) 548-2754 amanda@iscprgroup.com For more information on lane closures and other project details, log onto the FDOT Construction website at www.75-express.com I-75 Express – Corridor-wide We welcome your comments and questions. I-75 Express – Corridor-wide