Department of Game and Fish
Information Systems Division
Alternate Data Center and Upgrade
Program Initiation
June 24, 2015
Purpose/Approach
The purpose is to address our requirement to have our mission critical online and
vendor sales systems (used to sell all hunting/fishing/trapping licenses) and our
website to be available to our customers (e.g. vendors, public) at least 99.99% of
the time.
The overall approach is to develop an active – active cluster of the systems
between two geographically separated data sites and replace end of life
components
2
Project Goals
Reduce the number of single points of failure
Replace end of life servers and network components
Standardize on servers and network components
Replace physical servers with virtual servers to increase resources flexibility and
performance
Centralize data storage and eliminate use of local storage for increased redundancy and
performance
Minimize downtime during migration
Procure all components at the beginning of project
3
Schedule
Planning Phase: Completed
Phase 1 (DoIT): 30 days from Project Approval
Move existing redundant servers and load balancers from NMDGF Hqs Data Site to DoIT Data Site
Rack is leased to house the equipment at DoIT Data Site
Replace end of life McAfee firewall with Cisco ASA 5525 Firewall
Establishes an alternate data center with manual failover capabilities
Phase 1 (NMDGF HQS): 30 Days from Project Approval
Establish DoIT as the primary data site for operations
Replace end of life network switches with Cisco 3750 switches
Convert application physical servers to virtual servers on one physical server
Validate performance and functionality of virtual servers
4
Schedule
Phase 2: 60 Days from Project Approval
Replace the servers at NMDGF Hqs with Cisco Blade Servers using the virtual versions
Move the server with the virtual servers to the test domain
Connect the servers to a Storage Area Network device
Validate performance and functionality
Phase 3: 90 Days from Project Approval
Establish NMDGF Hqs as the primary site
Replace the servers at DoIT with Cisco Blade Servers using copies of the NMDGF virtual
versions
Connect the servers to a Storage Area Network device
Validate performance and functionality
Install Datto Sirius 2 device to establish active-active connectivity between the two
data sites
5
Schedule
Project Closeout: Completion of Phase 3 plus 30 days
Validate failover and performance
6
Project-Funding
Project Appropriation
$350,000
Professional Services
$20,000
$330,000
IT Maintenance for year 1
$30,000
$300,000
Exempt IT supplies
$50,000
$250,000
IT Equipment – Software
$50,000
$200,000
IT Equipment - Hardware
$200,000
$0
IT Maintenance after year 1 will be covered by
annual budgets.