Department of Game and Fish
Information Systems Division
Alternate Data Center and Upgrade
Program Initiation
June 24, 2015
Purpose/Approach

The purpose is to address our requirement to have our mission critical online and
vendor sales systems (used to sell all hunting/fishing/trapping licenses) and our
website to be available to our customers (e.g. vendors, public) at least 99.99% of
the time.

The overall approach is to develop an active – active cluster of the systems
between two geographically separated data sites and replace end of life
components
2
Project Goals

Reduce the number of single points of failure

Replace end of life servers and network components

Standardize on servers and network components

Replace physical servers with virtual servers to increase resources flexibility and
performance

Centralize data storage and eliminate use of local storage for increased redundancy and
performance

Minimize downtime during migration

Procure all components at the beginning of project
3
Schedule

Planning Phase: Completed

Phase 1 (DoIT): 30 days from Project Approval


Move existing redundant servers and load balancers from NMDGF Hqs Data Site to DoIT Data Site

Rack is leased to house the equipment at DoIT Data Site

Replace end of life McAfee firewall with Cisco ASA 5525 Firewall

Establishes an alternate data center with manual failover capabilities
Phase 1 (NMDGF HQS): 30 Days from Project Approval

Establish DoIT as the primary data site for operations

Replace end of life network switches with Cisco 3750 switches

Convert application physical servers to virtual servers on one physical server

Validate performance and functionality of virtual servers
4
Schedule
Phase 2: 60 Days from Project Approval


Replace the servers at NMDGF Hqs with Cisco Blade Servers using the virtual versions

Move the server with the virtual servers to the test domain

Connect the servers to a Storage Area Network device

Validate performance and functionality
Phase 3: 90 Days from Project Approval


Establish NMDGF Hqs as the primary site

Replace the servers at DoIT with Cisco Blade Servers using copies of the NMDGF virtual
versions

Connect the servers to a Storage Area Network device

Validate performance and functionality

Install Datto Sirius 2 device to establish active-active connectivity between the two
data sites
5
Schedule

Project Closeout: Completion of Phase 3 plus 30 days

Validate failover and performance
6
Project-Funding
Project Appropriation
$350,000
Professional Services
$20,000
$330,000
IT Maintenance for year 1
$30,000
$300,000
Exempt IT supplies
$50,000
$250,000
IT Equipment – Software
$50,000
$200,000
IT Equipment - Hardware
$200,000
$0
IT Maintenance after year 1 will be covered by
annual budgets.