Fermilab FY07 ILC R&D Robert Kephart Fermilab Introduction ILC Americas • Fermilab will play a special role in the ILC – In the ILC era it will be the only remaining U.S. laboratory dedicated to High Energy Physics – It is also the designated host site for the ILC if it is hosted in the United States • EPP2010: Strongly endorsed the ILC – Recommended a “strong and vital Fermilab” – And said “ Fermilab must play a major role in advancing the priorities identified in this report” – Pier Oddone: ILC is our # 1 long term priority • The vast majority of the proposed FY07 R&D effort at FNAL is focused on crucial R1, R2 R&D issues (namely cavities & cryomodules) • In FY06 FNAL engaged in the ILC in a major way. Fermilab Apr 4-6, 2006 ILC ART Review 2 Introduction ILC Americas • FNAL’s FY06 effort: – – – – ILC (funded via the GDE) is ~ $ 12.0 M. SCRF infrastructure ~ $ 9.1 M ILC detector ~ $ 1.9 M 3.9 GHz effort ~ $ 3.9 M $ 26.9 M • The support to build SCRF infrastructure, for 3.9 GHz, and for ILC detector R&D was from laboratory core funds. ( OK but we are not allowed to do things that are explicitly ILC with these funds… wrong B&R category ) • The Presidents budget is such that FNAL cannot supply these funds in FY07. ( in fact the Tevatron running schedule will be cut back to save $$$) Fermilab Apr 4-6, 2006 ILC ART Review 3 Introduction ILC Americas • The GDE funded only 30 FTE ( ~ $ 4.5 M SWF) in FY06 at FNAL only a small fraction of the effort in progress • The overall effort has grown to over 120 FTE ( April) • A “bottoms up” request from task leaders resulted in FY07 requests for > 230 FTE. • This was reduced to 186 FTE (limit personnel to existing staff or approved openings, focus on highest priority work) • 186 FTE represents 8% of the FNAL staff. (eg SLAC has 5%) • Not unreasonable in FY07 if FNAL is to be the host site • M&S was cut back – No purchase of an EB welder – No start of a big refrigerator for ILCTA_NM • Working towards a fully resource loaded schedule for the FNAL work… As you will see we have names for nearly all the people assumed in FY07, most are already working Fermilab Apr 4-6, 2006 ILC ART Review 4 ILC Americas Summary of FY07 FNAL Request Detector & TB are not in this talk FNAL’s request is focused on developing cavities & cryomodules and on the RDR,TDR, and cost estimate effort Details follow: Fermilab Apr 4-6, 2006 ILC ART Review 5 ILC Americas Program Management (WBS 1.2) • Scope: Organize & direct the ILC Program @ Fermilab • FY06 Status: – Manage Fermilab ILC effort => direct technical efforts, organize work packages, set up and track expenditures – Task Leaders for work packages are in place – Cost tracking and reports to ART are operational – M&S is largely travel and small amount of computing – Travel: $200K budget but RDR expect larger actuals ~$365K – Paid for WebEx licenses for this year • FY06 Resources Fermilab Apr 4-6, 2006 ILC ART Review 6 ILC Americas Program Management (WBS 1.2) • Scope: Organize & direct the ILC Program @ Fermilab FY07 goals: – Continue to manage Fermilab ILC effort – Hire Webmaster to develop and maintain the FNAL ILC web site – Increase travel expenditures as overall FNAL effort grows and international collaboration effort increases ($501K budgeted) – Emphasis shifts from RDR to TDR – Software license fees for cost and schedule software • FY07 Resources Fermilab Apr 4-6, 2006 ILC ART Review 7 FY07 Personnel (WBS 1.2) ILC Americas • Personnel: – – – – – – – Bob Kephart 1.0 FTE Shekhar Mishra 1.0 FTE Sergei Nagaitsev 1.0 FTE Rich Stanek 1.0 FTE John Konc 0.5 FTE Monica Sasse 0.5 FTE Webmaster (new hire) 1.0 FTE Total 6.0 FTE Fermilab Apr 4-6, 2006 ILC ART Review 8 Public Relations (WBS 1.4) ILC Americas • Scope: Communication at local, state, national, and international FY06 Status: – Hired consultant (Perspectives Group) • Identified community stakeholders • Drafted ILC Community Communication Plan • Received input from Community Task Force on criteria for ILC site and on community outreach – – – – – Begun ILC brochure design Scheduled Congressional briefing May 9 (R&D Caucus) Scheduled launch of “Discovering the Quantum Universe” (May 9) Organized ILC speakers’ bureau, envoy program, with LCSCA Formed ILC2 (First meeting June 1) • FY06 Resources Fermilab Apr 4-6, 2006 ILC ART Review 9 ILC Americas Public Relations (WBS 1.4) • Scope: ILC communication activities • FY07 Goals: • Strengthen ILC communication at local, state, and national level – Produce print and electronic materials – Communication at many levels • Envoys to policy makers and opinion leaders • Media campaign (national and international) – Use symmetry magazine, Fermilab Web site, press releases and other media to communicate to a national and international audience • FY07 Resources Fermilab Apr 4-6, 2006 ILC ART Review 10 ILC Americas Public Outreach (WBS 7.3.1.4) • Scope: Build support for bid-to host @ Fermilab • FY07 Goals:Communication at local, state, national level – ILC Community Advisory Board • Consultant (Perspectives Group) • Engage Local Community Task Force on criteria for ILC site • Build local support for ILC at FNAL – Produce print and electronic materials – Community outreach at many levels including use of envoys, speakers bureau, community organizations and media campaign • FY07 Resources Fermilab Apr 4-6, 2006 ILC ART Review 11 ILC Americas FY07 Personnel (WBS 1.4 and 7.3.1.4) • Personnel: – Judy Jackson – Public Affairs Staff* Total 0.5 FTE 1.5 FTE 2.0 FTE * Matched to specific task Fermilab Apr 4-6, 2006 ILC ART Review 12 ILC Americas RDR & TDR ( WBS 2.1.2) • Scope: Develop the Reference Design Report • FY06 Status: – Baseline configuration document finishes Dec 05 – Fermilab is working on the following sections of RDR • Main Linac – – – – Accelerator Physics Cavity and Cryomodule Cryogenics Magnet • Cost and Schedule • Conventional Facility • Damping Ring, BDS, Instrumentation and Controls • FY06 Resources Fermilab Apr 4-6, 2006 ILC ART Review 13 ILC Americas RDR and TDR ( WBS 2.1.2) • FY07 Scope: – Develop the Reference and Technical Design Reports • FY07 goals: – This is continuation of FY06 goals for RDR – The Reference Design Report will be the key document defining the scope of the ILC project, the R&D program, and the project cost and schedule. – Fermilab scientific and engineering staff will work with the ILC GDE for the next 12 months in development of the Reference Design Report and subsequently on TDR. – The portion of the TDR design and cost estimate which is U.S. site specific should be funded as part of the U.S. bid-to-host (WBS 7.X) Fermilab Apr 4-6, 2006 ILC ART Review 14 FY07 Request ( WBS 2.1.2) ILC Americas • Personnel: – – – – – P. Garbincius H. Carter T. Peterson J. Tompkins Request from P. Garbincius 1.0 FTE 0.5 FTE 0.5 FTE 0.5 FTE (Primavera expert, WBS person, data entry) Total Fermilab Apr 4-6, 2006 ILC ART Review 3.0 FTE 5.5 FTE 15 ILC Americas DRing physics ( WBS 2.5.2 and WBS 7.3.2.1) • Scope: Provide modeling infrastructure (hardware & software) ; perform simulations including 3D multi-particle effects. • FY06 Status: – Order 20 dual CPU boxes to utilize existing parallel switch for dedicated DR multi-particle simulations – Begun study of baseline lattice with 3D space-charge • FY06 Resources Fermilab Apr 4-6, 2006 ILC ART Review 16 ILC Americas DRing physics (WBS 2.5.2 and WBS 7.3.2.1) • Scope: DR accelerator physics studies, including multi-particle effects. • FY07 goals: – Dynamic aperture/acceptance studies, employing multiphysics simulation • Include higher-order optics, field errors & misalignment – Incorporate e-cloud module from QuickPIC in simulations (SciDAC leveraged) – Incorporate wakefield effects – Support FNAL site-specific simulation studies Fermilab Apr 4-6, 2006 ILC ART Review 17 ILC Americas FY07 Personnel (WBS 2.5.2 and WBS 7.3.2.1) • Personnel: – – – – – – – – – Jim Amundson Francois Ostiguy Mike Church John Johnston Bill Ng Panagiotis Spentzouris Eric Stern Valentin Ivanov Leo Michelotti 0.30 FTE 0.30 FTE 0.25 FTE 0.25 FTE 0.25 FTE 0.30 FTE 0.20 FTE 0.20 FTE 0.45 FTE Total Fermilab Apr 4-6, 2006 ILC ART Review 2.50 FTE 18 ILC Americas FY07 Request (WBS 2.5.2 and WBS 7.3.2.1) 7.3.2 is place holder. Need to make a better guess of how much DR work is site specific… Actually really should be RTML… Fermilab Apr 4-6, 2006 ILC ART Review 19 ILC Americas ML Accel. Physics ( WBS 2.7.3 & WBS 7.3.2) • Scope: Simulations to support RDR • FY06 Status: – – – – Designed of realistic Lattice Failure models and analysis started Static tuning studies started Upgraded computing capabilities • FY06 GDE Resources (+ Fermilab Apr 4-6, 2006 ~ 3 FTE paid from core funds) ILC ART Review 20 ILC Americas FY07 Personnel WBS 2.7.3 and WBS 7.3.2 • Personnel: – – – – – – – – – – – – – M. Church F. Ostiguy J. Johnstone A.Valishev V.Lebedev K.Ranjan N.Solyak P.Lebrune L.Michelotti V.Ivanov P.McBride P.Spentzouris 1 posted opening Total Fermilab Apr 4-6, 2006 0.7 FTE 0.65 FTE 0.5 FTE 0.8 FTE 0.15 FTE 1.0 FTE 0.5 FTE 0.9 FTE 0.5 FTE 0.8 FTE 0.55 FTE 0.15 FTE 1.0 FTE 8.2 FTE ILC ART Review 21 ILC Americas ML Accel. Physics ( WBS 2.7.3 & WBS 7.3.2) • Scope: RDR and site-specific ML design • FY07 goals: – – – – – – – Continue Developing computing capabilities Continue Dynamic tuning studies Integrated Simulation MPS design and studies Study dark current in ML (generation and dynamics) Beam instrumentation issues Cold BPM design (0.3 um resolution, clean technology) Fermilab Apr 4-6, 2006 ILC ART Review 22 ILC Americas Alignment and Vibration ( WBS 2.7.4) • Scope: Develop alignment procedures and study vibration of RF cavities at all frequencies • FY06 Status: – Slow ground motion studies in MINOS hall and Conco Western Mine in Aurora (100 meter depth) – Start vibration studies on capture cavity in Meson lab • FY06 Resources Fermilab Apr 4-6, 2006 ILC ART Review 23 ILC Americas Alignment and Vibration ( WBS 2.7.4) • Scope: Alignment and Vibration • FY07 goals: – Continue monitoring of slow ground motion in MINOS hall and Conco Western mine North Aurora – Understand sources of slow ground motion – Develop fiducialization process for RF cavities and quadrupole magnets – Develop network for test areas in Meson lab and New Muon – Develop fast motion monitoring of RF cavities – Understand sources and causes of vibration in RF cavities Fermilab Apr 4-6, 2006 ILC ART Review 24 ILC Americas FY07 Personnel ( WBS 2.7.4) • Personnel: – Jim Volk 0.2 FTE – Shavkat Singatulin 0.2 FTE – Summer student 0.1 FTE Total 0.5 FTE Fermilab Apr 4-6, 2006 ILC ART Review 25 ILC Americas FY07 Request (WBS 2.7.4) Fermilab Apr 4-6, 2006 ILC ART Review 26 ILC Americas Conventional Facilities (WBS 2.11.2) • Scope: Prepare Conventional Facilities scope, criteria and cost estimating documents in support of RDR • FY06 Status: – Developed requirements for each of the machine areas – Conceptual drawings of machine and facility layout to form the basis of estimates – Developing unit prices for various elements of work – Placed various contracts with A&E consultants • FY06 Resources Fermilab Apr 4-6, 2006 ILC ART Review 27 Conventional Facilities (WBS 2.11.2) ILC Americas • Scope: Refine details of the conceptual requirements • FY07 Goals: – – – – Perform options studies in conjunction with Value Management Continue to develop drawings of machine and facility layouts Refine & optimize cost estimate in conjunction with A&E firms FES Labor appears as M&S because of charge back system except for 0.6 FTE of Vic Kuchler (FES management) • FY07 Resources Fermilab Apr 4-6, 2006 ILC ART Review 28 ILC Americas Controls (WBS 3.2.9,4.7.2, 5.9.11) • Scope: Global Controls Design, Develop control system(s) for test facilities(ILCTA) • FY06 Status: – Controls systems for Horizontal/Vertical test stands under development – Developed baseline conceptual design for ILC controls in context of the “Global” ILC Controls Collaboration – Work on BCD complete; working on RDR/Costing – Investigate hardware for High Availability implementation • FY06 Resources (FNAL Core funds) – 1 FTE on Global Design; $75k M&S for HA studies and software licenses, etc. – 3.5 FTE (personnel from 4 divisions) Test stand controls infrastructure and software Fermilab Apr 4-6, 2006 ILC ART Review 29 ILC Americas Controls (WBS 3.2.9, 4.7.2, 5.9.11) • Scope: Control system design, Controls R&D and Controls System Support for ILC test stands • FY07 goals: – R&D (3.2.9) • High Stability RF Phase Distribution Modulator development; prototypes to be installed at ILCTA in FY08. • Control System Framework: Identify and evaluate candidate systems. • R&D on High Availability Hardware/software (de-scoped) • Collaboration Tools and Remote operations (de-scoped)] – Global Control system design (4.7.2) • Requirements document for Global Controls System – ILCTA Control System(s) Design, implementation and support (5.9.11) • Support for test stands and test facilities. Concentrate on ILCTA_NML. Fermilab Apr 4-6, 2006 ILC ART Review 30 ILC FY07 Personnel (WBS 3.2.9, 4.7.2, 5.9.11) Americas • Controls R&D (3.2.9) – – – – – ILCTA Support (5.9.11) – – – – – – – – – – – – – – – Vince Pavlicek 0.25 Bill Haynes 0.25 Margaret Votava Jim Patrick Other Resources • • • • Charlie Briegel Erik Gottschalk Control System Design (4.7.2) – – – – – – – – – – Erik Gottschalk Patricia McBride Jim Patrick Vince Pavlicek Margaret Votava Steve Wolbers Rob Kutschke Manfred Wendt (Instr) Brian Chase (LLRF) others Fermilab Apr 4-6, 2006 Paul Joireman 0.1 Mike Kucera 0.5 Paul Kasley 0.5 Sharon Lackey 0.5 Dan MacArthur 0.5 Rich Neswold 0.5 Dennis Nicklaus 0.5 Jerzy Nogiec 0.5 Luciano Piccoli 0.5 Ron Rechenmacher 1.0 Geoff Savage 0.25 Dennis Shpakov 0.5 Vladimir Sirotenko 0.25 Margaret Votava 0.5 Other Available Resources • • • ILC ART Review AD Controls CD AMR (New) AD Sysadmin 2.25 1.0 0.5 31 ILC Americas FY07 Request (WBS 3.2.9,4.7.2,5.9.11) Description: Controls System FTE years Labor K$ M&S K$ Indirect Cost Total Cost HA Control System 0 $0 $0 $0 $0 HA Std Instruments 0 $0 $0 $0 $0 0.5 $58 $40 $24 $121 0.25 $29 $10 $10 $49 0 $0 $0 $0 $0 1.25 $144 $80 $56 $280 8.4 $966 $340 $348 $1,654 Grand total 10.4 $1,196 $470 $438 $2,104 Fermilab Apr 4-6, 2006 ILC ART Review High Precision RF Phase Distribution Controls Framework Collaboration Tools/Remote Operations Control System Design Control System for ILCTA 32 ILC Americas Instrumentation R&D ( WBS 3.2.10) • Scope: Collaborating R&D activities • FY06 Status: – Collaboration started with SLAC and DESY – Funded with FNAL core funds • FY06 Resources – No resources in FY06 • FY07 Scope: – Continue R&D activities • FY07 goals: – KEK ATF BPM digital signal processing system R&D – SLAC ESA cavity-BPM R&D – DESY TTF HOM coupler signal processing R&D Fermilab Apr 4-6, 2006 ILC ART Review 33 ILC Americas FY07 Personnel ( WBS 3.2.10) • Personnel: – – – – – Jim Crisp Nathan Eddy Peter Prieto Manfed Wendt Duane Voy Total Fermilab Apr 4-6, 2006 0.1 FTE 0.1 FTE 0.1 FTE 0.1 FTE 0.1 FTE 0.5 FTE ILC ART Review 34 Magnet R&D (3.2.11) ILC Americas • Scope: Design/prototype magnets for various ILC applications • FY07 Goals: – – – – – – – Main Linac Low Gradient Quadrupole ($40K) Main Linac Dipole Corrector ($25K) Superconductor Material ($40K) Iron Dominated Quadrupole ($25K) Stretch wire test stand ($20K) Low Fringe Field measurement test stand ($10K) M&S support for contract designer ($60K) • FY07 Resources Fermilab Apr 4-6, 2006 ILC ART Review 35 ILC Americas FY07 Personnel (WBS 4.3.1 & 3.2.11) • Personnel: – – – – – – – – – – – – – John Tompkins 0.5 FTE Vladimir Kashikhin 0.5 FTE Vadim Kashikhin 0.25 FTE Mike Tertullian 0.35 FTE Joe Dim Arco 0.4 FTE Tom Woks 0.5 FTE Tom Nicola 0.2 FTE Kerry Weald 0.8 FTE Guest Engineer 0.85 FTE Mechanical Tech (tbd) 0.75 FTE HFM Group* 0.65 FTE Test & Inst Group* 0.65 FTE Process Engineering Group* 0.35 FTE Total 6.75 FTE * Assignments depend on tasks (usually small % of a few people) Fermilab Apr 4-6, 2006 ILC ART Review 36 ILC Americas Cryogenic System Design ( WBS 3.2.12) • Scope: Design of overall ILC cryogenic system • FY06 Status: – Layout & cost information in progress for RDR • FY06 Resources – Only 2.0 FTE funded by GDE for all FY06 RDR work – Exception: Magnet work was funded late in the year • FY07 Goals – Finish RDR cryogenic design and begin TDR design • Personnel: Fermilab Apr 4-6, 2006 - Tom Peterson 0.25 FTE ILC ART Review 37 ILC Americas LLRF Controls ( WBS 3.8.3) • Scope: Work towards an ILC LLRF system • FY06 Status: – Transferred DESY’s Simcon 2.1 and Simcon 3.1 LLRF technology to FNAL – Adapted an SNS LLRF system to 1.3 GHz operation – Used both systems to operate 1.3 GHz Capture Cavity 1 at A0 and 1.3 GHz Capture Cavity 2 at Meson Area – Established an MOU with University of Pennsylvania for the development of an ILC RF unit simulator • FY06 Resources (shared with WBS 5.8.4) Description LLRF ILCTA_MDB, LLRF ILCTA_IB1_VTS, and LLRF Controls Fermilab Apr 4-6, 2006 FTE Labor M&S Indirect years K$ K$ Cost 2 230 ILC ART Review 150 94 Total Cost 474 38 ILC Americas LLRF Controls ( WBS 3.8.3) • Scope: Develop LLRF systems for FNAL ILCTA • FY07 goals: – Short-term (< 18 months): Improvements to Simcon 3.1 system • Board hardware modifications to improve noise performance • Develop FNAL capability to manufacture Simcon 3.1 boards • Board firmware modifications to improve functionality • Board control interface to EPICS • Develop high intermediate frequency (IF) capability (better performance) • Design and fabricate high quality downconverter to high IF • Start work on automation, exception handling, fast tuner integration, etc • Evaluation of commercial alternatives (e.g., Lyrtech board) – Long-term (> 18 months): development of a new generation 24-Ch LLRF board for an ILC RF unit • In collaboration with DESY, SNS, LBNL, UPenn, and industry Fermilab Apr 4-6, 2006 ILC ART Review 39 ILC Americas LLRF Controls ( WBS 3.8.3) • FY07 Personnel: – Accelerator Division: 1 FTE • (B. Chase, J. Branlard, E. Cullerton, T. Koeth, M. Kucera, D. Nicklaus) – Computing Division: 2 FTE • (G. Cancelo, K. Treptow, R. Kwarcyany, B. Haynes, T. Zmuda, S. Rapisarda, G. Duerling, Other (Tech)) – Technical Division: 1 FTE • (R. Carcagno, D. Orris, A. Makulski, R. Nehring, Y. Pischalnikov, J. Nogiec, D. Shpakov, Other (Tech)) FY07 resources Description Development Software Development Hardware Grand total Fermilab Apr 4-6, 2006 Total FTE years Labor K$ 2 2 230 4 ILC ART Review M&S K$ 4 FTE Indirect Cost Total Cost 80 372 230 62 73 82 385 460 135 161 756 40 ILC Americas Cavity EM simulation ( WBS 3.9.2.1) • Scope: cavity simulations • FY06 Status: – Developed computing capabilities for AP Studies (M&S) – 20 new nodes of Grid computer farm in CD • Goal: Acc.Phys, Omega3P/Tau3P(SLAC) for wakefield simulation • FY06 Resources – None: this is a new task for FY07 • FY07 Scope: Cavity HOM trapped modes and wakefields study • FY07 goals: – Simulate HOM trapped modes – Study wakefield effects Fermilab Apr 4-6, 2006 ILC ART Review 41 ILC Americas FY07 Personnel ( WBS 3.9.2.1) • Personnel: – G. Romanov – A. Lunin – T.Khabibulin Total Fermilab Apr 4-6, 2006 0.25 FTE 0.30 FTE 0.25 FTE 0.8 FTE ILC ART Review 42 ILC Americas Cavity Fabrication ( WBS 3.9.2) • Scope: Fabricate ILC Cavities • FY06 Status: – Type III+: 4 at AES, 2 at TJNL + (4 ACCEL are done) – 2 R&D cavities at TJNL (Large Grain, Type IV, new HOM) – Developed tooling for the cavity fabrication at TJNL with a plan to share them with US industry and train them – Bid package under preparation for 8-10 Type IV Cavities • FY06 Resources Fermilab Apr 4-6, 2006 ILC ART Review 43 ILC Americas Cavity Fabrication ( WBS 3.9.2) • FY07 Scope: Fabricate ~20 Type IV ILC Cavities • FY07 goals: – Build enough cavities to establish the processing technology to reliably achieve an accelerating gradient of 35 MV/m in US. – Develop 2nd US vendor for cavity fabrication – TTC/SMTF technical board recommends we divide these cavities 50/50 fine grain & large/single crystal Niobium. – It is expected that the fine grain material will go through the Electro-polishing while the large/single crystal would be processed by BCP only. – Successful cavities from this and FY06 production will be incorporated into the 1st Type IV cryomodule built at FNAL in FY08 Fermilab Apr 4-6, 2006 ILC ART Review 44 ILC Americas Cavity Fabrication ( WBS 3.9.2) • Personnel: – – – – Mike Foley Scott Reeves AD Engineer* AD Technician* Total 1.0 FTE 1.0 FTE 1.0 FTE 1.0 FTE 4.0 FTE * Agreement to assign these people after shutdown Fermilab Apr 4-6, 2006 ILC ART Review 45 SRF Cavity Cost Reduction R&D ILC ( WBS 3.9.2.2) Americas • • • FY06 Scope: FNAL is sending $ 40 K to MSU to investigate TIG welding of single cell Nb cavities, MSU funded hydroforming studies with NSF funds FY07 Scope: Study Hydro-forming and high purity TIG welding as methods for cavity cost reduction FY07 goals: – Hydro-forming • Work with commercial bellows manufacturers • Fabricate niobium and copper clad niobium tubes via extrusion, welding and/or flow forming • Form multi-cell prototypes using swaging and hydro- forming techniques • Process and test prototype cavities • Work with DESY hydro form experts (now@FNAL) – High purity TIG Welding • Design single-cell cavity with TIG welds • Fabricate prototype niobium single-cell cavities • Process and test prototype cavities Fermilab Apr 4-6, 2006 ILC ART Review 46 ILC Americas Cost Reduction ( WBS 3.9.2.2) • FY07 MSU Personnel: – – – – – – – – Terry Grimm Jon Bierwagen Steve Bricker Chris Compton Walter Hartung Dan Pendell John Popielarski Laura Saxton FY07 Resources Total 0.1 FTE 0.1 FTE 0.1 FTE 0.2 FTE 0.1 FTE 0.2 FTE 0.1 FTE 0.1 FTE 1.0 FTE MSU labor is in M&S Fermilab Apr 4-6, 2006 ILC ART Review 47 ILC Americas BCP ( WBS 3.9.3.1 & 5.9.X) • Scope: Develop BCP Facility and Testing at Cornell and ANL/FNAL ( Move ANL BCP effort to WBS 3.9.3.4 ?) • FY06 Status: – Cornell upgraded BCP, HPR, and vertical test for 9-cell ILC cavities. – Cornell has two 9-cell ACCEL cavities from Fermilab. One of was processed & first RF test is done ( 17 MV/m… will re-etch) – The BCP Facility was installed at ANL – Commissioned with water and awaits safety approval. – Upgrades in progress to handle and transport ILC Cavities. • FY06 Resources Fermilab Apr 4-6, 2006 ILC ART Review 48 ILC Americas BCP ( WBS 3.9.3.1 & 5.9.X) • FY07 Scope: BCP Facility & Test at Cornell and ANL/FNAL • FY07 goals: – Develop BCP in US to achieve 25 MV/m – Ramp up U.S. capacity – Cornell will BCP more Fermilab provided ILC cavities to populate the first US-built ILC cryomodule. – Activities at Cornell will be a good training ground for Fermilab personnel to learn BCP, HPR and cavity testing. Industrial personnel can also join in. – Finish Commissioning of BCP facility at ANL and process 1.3 GHz ILC Cavities. – We believe additional AD people will be assigned to help operate the ANL facility. Asked ANL to help also. Fermilab Apr 4-6, 2006 ILC ART Review 49 ILC Americas BCP ( WBS 3.9.3.1 & 5.9.X) • FY07 Personnel: – Allan Rowe, Mike Frett, Debbie Bonifas, Mike Heinz, Ryan Montiel, Wade Muranya, Michael Rauchmiller, Brad Tennis, Dan Assel, Todd Thode, Cristian Boffo, Luciano Elementi, Jamie Blowers, Jan Szal, 7.4 FTE – Need to hire Contract techs 2.0 FTE – Need to identify Engineer (AD) 2.0 FTE – Need to identify Drafter (AD) 1.0 FTE Total 11.4 FTE FY07 Resources Fermilab Apr 4-6, 2006 ILC ART Review 50 ILC Americas EP ( WBS 3.9.3.2 & 5.9.x) • Scope: Develop R&D EP Facility and Testing infrastructure at Cornell, Jlab and ANL/FNAL • FY06 Status: – Jlab EP, HPR and Vertical testing Facilities were upgraded to handle 1.3 GHz ILC cavities – Jlab has exercised the system with cavities from DESY and is waiting for US ILC Cavities. – The TTC, SMTF and STF collaboration has been discussing the ILC EP Facility design specification. A documents has been prepared and being discussed. – Fermilab has hired Tsuyoshi Tajima (LANL) and Antoine Claier (SACLAY) as guest scientist to work on EP. – Preliminary design of an EP R&D facility to be build at ANL/FNAL facility has been developed. Engineering design and schedule needed. – Cornell has successfully used the vertical EP set up to etch single cell 1.3 GHz cavities. Gradients between 35 - 47 MV/m have been reached in several single cells. Fermilab Apr 4-6, 2006 ILC ART Review 51 ILC Americas FY06 Resources ( WBS 3.9.3.2 & 5.9.x) • FY06 Resources • NSF Funds were used to develop Vertical EP at Cornell Fermilab Apr 4-6, 2006 ILC ART Review 52 ILC Americas EP ( WBS 3.9.3.2 & 5.9.x) • Scope: Develop R&D EP Facility and Testing infrastructure at Cornell, Jlab and ANL/FNAL • FY07 goals: – Extend the Vertical EP to ILC 9-cell cavities, and carry out the procedure for 1 -2 cavities. – Assemble and commission EP system at ANL/FNAL – Small sample, tumbling and single cell EP R&D at FNAL – Simulation of 9 Cell Cavity EP process – Design study of an ILC pre-production EP Facility with industrial vendors Fermilab Apr 4-6, 2006 ILC ART Review 53 ILC FY07 Personnel ( WBS 3.9.3.2 & 5.9.x) Americas • Personnel: – – – EP R&D at Fermilab • C. Boffo • D. Hicks • Designer • C. Antoine • Associate Scientist opening • C. Cooper • Tech ANL EP: • L. Elementi • K. Ewald • Engineering opening • Tech • ANL Staff Pre-Production EP Facility Design • L Elementi • K. Ewald • T. Tajima • C. Antone • Engineering opening • Unidentified TD Staff 0.25 FTE 0.25 FTE 0.5 FTE 0.25 FTE 0.25 FTE 0.25 FTE 0.5 FTE 0.25 FTE 0.5 FTE 0.5 FTE 1.5 FTE 3.0 FTE count as M&S 0.25 FTE 0.5 FTE 1.0 FTE 0.5 FTE 0.5 FTE 1.0 FTE Total Fermilab Apr 4-6, 2006 ILC ART Review 8.8 FTE 54 ILC Americas EP (WBS 3.9.3.2 & 5.9.x) FY07 Request: Fermilab Apr 4-6, 2006 ILC ART Review 55 ILC Americas Type IV Cryomodule Design ( WBS 3.9.4) • FY06 Scope: FNAL part of the international effort to design the Type IV Cryomodule for ILC • FY06 Status: – – – – DESY type III+ drawings imported to FNAL 3D model created in IDEAS using this information Dimensions “Americanized” Developed Specifications • including cavity-to-cavity dimensions so they can be ordered – Working on cavity to cavity interconnects ( proto-types) • FY06 Resources Fermilab Apr 4-6, 2006 ILC ART Review 56 ILC Americas Type IV Cryomodule Design ( WBS 3.9.4) FY07 goals: • Create a complete documentation package for type IV module fabrication (so parts can be ordered) – 3-D model – 2-D drawings for fabrication of parts and assembly – Include real magnet and BPM design • Start with module without magnet – We have no magnet design yet – We need module design without a magnet, anyway – Nevertheless, the quad/corrector/BPM design is at the heart of the module and is needed soon • Resources – Labor is FNAL engineers and designers – M&S includes funds for Contract Designers and for prototypes of cavity interconnects and other parts Fermilab Apr 4-6, 2006 ILC ART Review 57 ILC Americas Type IV Cryomodule Design ( WBS 3.9.4) • Personnel: Total is 9 FTE’s • FNAL Staff: – – – – – – – Don Mitchell Youri Orlov Mike McGee Harry Carter Tom Peterson Salman Tariq Chuck Grimm Total 0.75 FTE 1.00 FTE 1.00 FTE 0.25 FTE 0.25 FTE 0.25 FTE 0.50 FTE 4.00 FTE Engineers • Plus Five Full time designers ( 5.0 FTE) – Contract designers are all on board. Show up as M&S – Also M&S for prototypes of cavity interconnects & other parts • International Effort – Participants: CERN, DESY, Fermilab, INFN, KEK, SLAC – Some specific plans for dividing the work are in place Fermilab Apr 4-6, 2006 ILC ART Review 58 ILC Americas FY07 Request ( WBS 3.9.4) M&S Details: $ 600 K for 5 contract designers @ 125 K/yr $ 100 K for prototype parts Fermilab Apr 4-6, 2006 ILC ART Review 59 ILC Americas SCRF Materials Research ( WBS 3.9.14) • Develop an intellectual understanding that relates SCRF cavity performance to materials characteristics measurable in the lab… Goals include: – a) reliable & predictable cavity performance – b) significant cost reduction • FY06 Program: – Develop Facilities: • IB3 SCRF Lab (Nb Eddy current scanning, RRR measurements, IB3 chemistry hood, upgrade Instron stress-strain measurement machine ) • TD MDL (small scale BCP and EP chemistry) • TD conventional and electron microscope – Activities: • Materials Characterization in Support of Cavity Fabrication ( 250 sheets Nb) • Eddy Current Scans, RRR, mechanical & thermal analysis at MSU, chemical analysis at FNAL Materials Development Lab • University Program (Northwestern 3D Atomic Probe, UW - Vortex Penetration) • Studies include role of grain boundaries in SCRF surface performance, role of impurities, theoretical work at U. Wisconsin Applied Superconductivity Center • Bauer: Coordinates a world wide materials effort (Cornell, TJNL, DESY, etc.) Fermilab Apr 4-6, 2006 ILC ART Review 60 ILC Americas SCRF Materials Research ( WBS 3.9.14) • FY06 Resources • This entire effort, including characterizing material (eddy current scans of Nb) for cavity fabrication was supported in FY06 by FNAL core funds. We can not do this in FY07. FY07 goals: – All FY06 activities continue, efforts need to increase – Ramp up program on cavity cost reduction with MSU – Cavity TIG welding, hydro-forming, mechanical material removal Fermilab Apr 4-6, 2006 ILC ART Review 61 ILC Americas SCRF Materials Research ( WBS 3.9.14) • Desire to grow this program: Request was 8 FTE • We limited the request to: existing staff + posted openings – – – – – – – – – P Bauer Scientist opening C Antoine C Boffo C Cooper F McConologue Dave Burke TD tech Laurea Student Total 1.00 FTE 1.00 FTE 0.35 FTE 0.30 FTE 0.25 FTE 1.00 FTE 0.10 FTE 1.00 FTE 1.00 FTE 6.00 FTE Scientists Engineer Chemist Designer • M&S request was $ 700K, but only $ 525 K request to GDE – – – – $100 K for materials characterization for cavity fabrication $200 K of this is for the university program at NU,UW,& MSU $200 K SCRF materials infrastructure $200K Single cell program fund $ 175 K from FNAL core funds Fermilab Apr 4-6, 2006 ILC ART Review 62 ILC Americas FY07 Request ( WBS 3.9.14) • FY07 Resources * Not included in these totals: We hope to attract an “out standing” engineer (FNAL Bardeen Fellow) to SCRF single cell program as part of the “tight loop” effort at FNAL. They get SWF and M&S support from lab core funds. Will request $ 175 K M&S. Reuse the A0 3.9 GHz cryostat. Fermilab Apr 4-6, 2006 ILC ART Review 63 ILC Cryomodule Type-IV Components ILC Americas ( WBS 3.9.15) • Scope: Cryomodule components (except Cavities) for the 2nd ILC Cryomodule for ILCTA_NM • FY06 Status: – DESY Drawings were transferred to Fermilab – Fermilab converted these drawings for US vendors – These drawings are the base for the Type-IV cryomodule design (WBS 3.9.4). – We are preparing bid package to purchase Helium Vessel, Coupler, Tuners, Cold Mass etc. using TTC design from US and International Vendors in FY06 – The 2nd Cryomodule is expected to be assembled in late FY07 • FY06 Resources (Fermilab core funds) • Fermilab Apr 4-6, 2006 ILC ART Review 64 ILC ILC Cryomodule Type-IV Components Americas ( WBS 3.9.15) • FY07 Scope: Cryomodule components (except Cavities) for the 3rd ILC Cryomodule for ILCTA_NM. This will be of Type-IV ILC design • FY07 goals: – Finish the design of the ILC Type-IV Cryomodule as described in WBS 3.9.4 – Coupler, Tuners, Helium Vessel etc. are not expected to change from Type-III+ to Type-IV. – Purchase long lead time items as the design of components are finalized. Fermilab Apr 4-6, 2006 ILC ART Review 65 ILC Americas FY07 Request ( WBS 3.9.15) • Personnel: – Fabrication Specialist from Materials Control Group and a small part of Tom Peterson (1.0) Total 1.0 FTE FY07 Resources Additional SWF and M&S resources will be needed in FY08 to finish this Cryomodule. Fermilab Apr 4-6, 2006 ILC ART Review 66 ILC Americas 3.9 GHz Cryomodule ( WBS 3.9.16) • Scope: Fabricate One 3.9 GHz 3rd harmonic Cryomodule for DESY • FY06 Status: – Cavities under fabrication: • Half Cells for six 9-Cell Cavities formed at Fermilab, 1 has been ebeam Welded at Jlab – Coupler design was finished and it is being fabricated at CPI – Design of other cryomodule components are in progress. It is expected to finish June 06. – Design and fabrication of tooling for the cryomodule fabrication at Fermilab Cryomodule Assembly Facility is in progress. – 3.9 GHz cavity testing and dressing will share the 1.3 GHz infrastructure • FY06 Resources (Fermilab core funds) Fermilab Apr 4-6, 2006 ILC ART Review 67 ILC Americas 3.9 GHz Cryomodule ( WBS 3.9.16) • Scope: finish 06 scope… • FY07 goals: – – – – – Vertical testing of the 3.9 GHz cavity 3.9 GHz Coupler conditioning Horizontal test of the 3.9 GHz cavities at ILCTA_MDB Complete assembly of 4 cavities in a cryomodule Deliver to and assemble at DESY • FY07 resources Fermilab Apr 4-6, 2006 ILC ART Review 68 ILC Americas 3.9 GHz cryomodule ( WBS 3.9.16) • FY07 Personnel: (This Project is expected to finish in the 2nd quarter of FY07) – Don Mitchell, Dan Olis 0.25 FTE – Mike Foley, Mark Steinke, John Zweibohmer 0.1 FTE – Tug Arkan, Mike Heinz, Ryan Montiel, Wade Muranyi, Michael Rauchmiller, Allan Rowe, Brad Tennis, Timergali Khabibulline, Andy Hocker, Brian Smith, Glenn Smith 2.0 FTE – Leo Bellantoni, Harry Carter, Helen Edwards, Elvin Harms, Phil Pfund 1.5 FTE Total Fermilab Apr 4-6, 2006 ILC ART Review 3.85 FTE 69 ILC Americas 3.9 GHz Crab Cavity ( WBS 3.9.17) • FY06 Status: – ILC crab cavity is needed to achieve the design luminosity – Fermilab has a design of a transverse mode 3.9 GHz cavity that it developed for the CKM experiment. – Several single cell and four 3 cell prototypes exist – Nb and half cells exist for 13 cell prototype • FY06 Resources – No ILC resources allocated in FY06 • FY07 Scope: Fabricate and test a 13 cell 3.9 GHz Crab Cavity using existing FNAL design • FY07 goals: – Fermilab is building 3.9 GHz 3rd harmonic cavities for DESY, this is a modest incremental effort – The crab cavity will be processed and tested at Fermilab using the existing 3.9 GHz facilities. Fermilab Apr 4-6, 2006 ILC ART Review 70 ILC Americas FY07 Personnel ( WBS 3.9.17) • Personnel: – Leo Bellontoni – Engineer * – Drafter * 1.0 FTE 0.5 FTE 0.5 FTE Total 2.0 FTE * Thought to be AD personnel but no agreement in place. Fermilab Apr 4-6, 2006 ILC ART Review 71 ILC Americas Beam Delivery System-Collimators ( WBS 3.10.6) • Scope: Feasibility study of beam loss, energy deposition and radiation in beam delivery system (BDS) and extraction beam-lines, detector backgrounds and mitigation measures • FY06 Status: – Front-end STRUCT-MARS15-GEANT4 model of BDS, IP and extraction lines developed – BDS vs IP backgrounds done 6/06 – Radiation loads in collimation region, IP and 20-mrad extraction line and beam loss in 2 and 14-mrad extraction lines done 9/06 • FY06 Resources: 1.0 FTE, $50k M&S paid by GDE 0.5 FTE paid with core funds Fermilab Apr 4-6, 2006 ILC ART Review 72 ILC Americas BDS-Collimators ( WBS 3.10.6) • Scope: Feasibility study of beam loss, energy deposition and radiation in beam delivery system (BDS) and extraction beam-lines, detector backgrounds and mitigation measures • FY07 goals: – Refine front-end STRUCT-MARS15-GEANT4 model of BDS, IP and extraction lines and extend to realistic detector, experimental halls and beam dumps – Optimization studies of BDS apertures, collimators, synchrotron masks, muon spoilers, machine-detector interface (tunnel plugs, two-hall separation, masks, quads at IP, detector), extraction beam-lines with their collimators and beam dumps at the end for 2, 14 and 20-mrad crossings. – Radiation loads, prompt and residual radiation levels in BDS, IP and extraction components; impact on environment and second experiment. Fermilab Apr 4-6, 2006 ILC ART Review 73 ILC Americas BDS-Collimators ( WBS 3.10.6) • FY07 Personnel: – – – – Nikolai Mokhov Alexander Drozhdin Sergei Striganov Noriaki Nakao Total 0.5 FTE 0.5 FTE 0.5 FTE 1.0 FTE 2.5 FTE FY07 Resources Fermilab Apr 4-6, 2006 ILC ART Review 74 ILC Americas Magnets for RDR (WBS 4.3.1) • Scope: Conceptual design and cost estimation of magnet systems in support of the RDR • FY06 Status: – Effort was organized and funded half way through FY06 – Gathered information from Area System leaders as to the type and number of magnets required – Preparing parametric cost estimates for magnets • FY06 Resources Fermilab Apr 4-6, 2006 ILC ART Review 75 ILC Americas Magnets for RDR (WBS 4.3.1) • Scope: Conceptual design and cost estimation of magnet systems in support of the RDR • FY07 Goals: – Continue to provide conceptual design and cost estimation for magnets in support of the RDR – Work on detailed designs for magnets to better understand parameter space and physical dimensions • FY07 Resources Fermilab Apr 4-6, 2006 ILC ART Review 76 ILC Americas Magnets for RDR (WBS 4.3.1) • FY07 Personnel: – – – – John Tompkins Vladimir Kashikhin Vadim Kashikhin Mike Tartaglia Total Fermilab Apr 4-6, 2006 0.5 FTE 0.5 FTE 0.25 FTE 0.25 FTE 1.5 FTE ILC ART Review 77 ILC Americas Cryomodule Cost Est. (WBS 4.4.1) • Scope: Initial cryomodule cost estimate in support of RDR • FY06 Status: – Working Group formed with TJNL and SLAC to estimate cost of RF Unit production • Parallel effort to Industrial Cost Study • Will include cost estimate of required infrastructure – Follow through on order for Industrial Cost Study of RF Unit • FY06 Resources Fermilab Apr 4-6, 2006 ILC ART Review 78 ILC Americas Cryomodule Cost Est. (WBS 4.4.1) • Scope: Develop cryomodule cost estimate • FY07 Goals: – Continue effort to estimate cryomodule cost including cost of required infrastructure – Develop simulation model for fabrication process to allow optimization and what-if scenarios • FY07 Resources Fermilab Apr 4-6, 2006 ILC ART Review 79 ILC Americas Cryomodule Cost Est (WBS 4.41) • FY07 Personnel: – – – – – – – – – – Rich Stanek Harry Carter Tom Peterson Phil Pfund Gregg Kobliska Tom Nicol Tug Arkan Bob Bernstein Bill Borowski Don Mitchell Total Fermilab Apr 4-6, 2006 0.1 FTE 0.1 FTE 0.15 FTE 0.1 FTE 0.15 FTE 0.1 FTE 0.1 FTE 0.1 FTE 0.1 FTE 1.1 FTE ILC ART Review 80 ILC Americas Instrumentation RDR ( WBS 4.7.1) • Scope: System layout, RDR cost estimation, technical details for the TDR • FY06 Status: – Specifications of most subsystems completed – Main Linac layout almost complete • FY06 Resources: No GDE support for this task • FY07 Scope: Same • FY07 goals: – System layout for Injector, DR, RTM & BDS instrumentation (in collaboration) – Completing the cost estimation of all instrumentation subsystems (in collaboration) – Detailed technical description of all major instrumentation subsystems (in collaboration) – Details on related systems (timing & trigger, clock distribution, DAQ, control system, etc.) Fermilab Apr 4-6, 2006 ILC ART Review 81 ILC Americas Instrumentation RDR ( WBS 4.7.1) • Personnel: – – – – Jim Crisp Peter Prieto Alexei Semenov Manfed Wendt Total Fermilab Apr 4-6, 2006 0.15 FTE 0.15 FTE 0.10 FTE 0.35 FTE 0.75 FTE ILC ART Review 82 ILC Americas RF Power ( WBS 5.8.3) • Scope: Provide RF power to FNAL test stands • FY06 Status: – Two large modulators under construction – PD (4.5 ms) done 6/06, ILC ( 1.5 ms) complete 12/06 • FY06 Resources Fermilab Apr 4-6, 2006 ILC ART Review 83 ILC Americas RF Power ( WBS 5.8.3) • Scope: Provide RF power to FNAL test stands • FY07 goals: – Complete ILC modulator for ILCTA_NM ($20 K, .5 FTE) – Modulator will be used to supply RF to 1st Type III cryomodule in Fall of 07 – Build a new 10 MW modulator for FNPL RF gun ( $ 400k, 1.5 FTE) – Buy a set of spare parts for 10MW modulator ($150k) – Build two 200 KW RF systems for HTS systems – Order a 10-MW klystron ($1000k) – Procure rf distribution for 1st cryomodule – Procure 1.3Ghz driver Fermilab Apr 4-6, 2006 ILC ART Review 84 RF Power ( WBS 5.8.3) ILC Americas • FY07 Personnel: – – – – – – J. Reid 1 new eng (accepted) C. Jensen D. Sun R. Pasquinelli 2 AD RF techs Total Fermilab Apr 4-6, 2006 ILC ART Review 0.50 FTE 1.00 FTE 0.50 FTE 1.00 FTE 0.25 FTE 2.00 FTE 5.25 FTE 85 ILC Americas Test Facility LLRF ( WBS 5.8.4) • Scope: Develop LLRF systems for FNAL ILCTA • FY06 Status: – ILCTA_MDB_HTS • 1.3 GHz system based on DESY’s Simcon 3.1 LLRF system is available (tested at both A0 CC1 and MDB CC2) • A 3.9 GHz up/down converter box is being fabricated to support 3.9 GHz coupler conditioning and 3.9 GHz cavity testing at ILCTA_MDB – ILCTA_IB1_VTS • Design based on Jlab VTS LLRF system, buy in FY06 • FY06 Resources (shared with WBS 3.8.3) Description LLRF ILCTA_MDB, LLRF ILCTA_IB1_VTS, and LLRF Controls Fermilab Apr 4-6, 2006 FTE years 2 Labor K$ 230 ILC ART Review M&S K$ 150 Indirect Cost 94 Total Cost 474 86 ILC Americas Test Facility LLRF ( WBS 5.8.4) • Scope: Develop LLRF systems for FNAL ILCTA • FY07 goals: – ILCTA_NML • Photoinjector: LLRF upgrade of A0 photoinjector based on improved Simcon 3.1 system (RF Gun, CC1, CC2) • First ILC cryomodule: LLRF system based on improved 8Ch Simcon 3.1 system • Beyond FY07: ILC RF unit (three cryomodules): LLRF system based on a new generation 24-Ch LLRF module – ILCTA_IB1_HTS • LLRF system for a two-cavity HTS facility based on improved Simcon 3.1 system Fermilab Apr 4-6, 2006 ILC ART Review 87 ILC Americas Test Facility LLRF ( WBS 5.8.4) • Personnel: – Accelerator Division: 2 FTE • (B. Chase, J. Branlard, E. Cullerton, T. Koeth, M. Kucera, D. Nicklaus) – Computing Division: 2 FTE • (G. Cancelo, K. Treptow, R. Kwarcyany, B. Haynes, T. Zmuda, S. Rapisarda, G. Duerling, Other (Tech)) – Technical Division: 2 FTE • (R. Carcagno, D. Orris, J. Ozelis, A. Makulski, R. Nehring, Y. Pischalnikov, J. Nogiec, D. Shpakov, F. Lewis, D. Eddy, S. Helis, New Engineer) Total Fermilab Apr 4-6, 2006 6 FTE ILC ART Review 88 ILC Americas Test Facility LLRF (WBS 5.8.4) FTE Labor M&S Indirect years K$ K$ Cost Description ILCTA_MDB Upgrades ILCTA_NML LLRF Photoinjector LLRF ILC Cryomodule Tuner Controllers RF Phase Ref. Line ILCTA_IB1 LLRF HTS Tuner Controllers RF Test Equipment Grand total Fermilab Apr 4-6, 2006 Total Cost 0.5 58 30 22 110 2 230 90 84 404 1 115 30 40 185 1 115 50 43 208 0.5 58 30 22 110 0.5 58 30 22 110 0.5 58 5 18 81 100 16 116 365 268 1323 6 ILC ART Review 690 89 Horizontal Test Stand (WBS 5.9.1) ILC Americas • Scope: ILCTA_MDB HTS • Cryostat: – Accepts single “dressed” cavities, 1.3 GHz or 3.9 GHz – Similar to the DESY HTS but has access at both ends. • Cryogenics: – – – – • MDB has an existing 1800 W @ 4 K cryogenic system New distribution system built to supply cavity test areas Large vacuum pump has been added to achieve 60 W at 1.8 K Cryogenic costs for this are in WBS 5.9.3 RF System: – 300 KW klystron & modulator provides pulsed RF power – Costs associated with RF system are in 5.8.3 ILCTA_IB1 HTS • A second HTS will be built for IB1 – Improved throughput (HTS is bottleneck @ DESY) – Design improvements – Accepts two 1.3GHz cavities simultaneously. Fermilab Apr 4-6, 2006 ILC ART Review 90 ILC Americas Horizontal Test Stand (WBS 5.9.1) • FY06 Status: ILCTA_MDB HTS – Cryostat delivery: mid May-2006 – Cryo lines to cave installed, feed can under construction – Working 1.3 GHz RF system in MDB ( tested with CC II) ILCTA_IB1 HTS – Working on ( two cavity) cryostat design • FY06 Resources Fermilab Apr 4-6, 2006 ILC ART Review 91 ILC Horizontal Test Stand (WBS 5.9.1) Americas • FY07 Goals: – – – – Operate ILCTA_MDB for 3.9 Ghz Convert ILCTA_MDB to 1.3 GHz and begin operation ( $ 50 K M&S) Cryo ops:2 FTE, testing/analysis:2 FTE, mechanical/RF tech:2 FTE ILCTA_IB1 HTS: Eng/Design:2FTE, cryo & electrical techs:2 FTE RF Eng:0.5 FTE, instrumentation:0.5 FTE – M&S: IB1 cryostat $ 250 K, electrical & infra 85 K – M&S: build mezzanine, shielding cave & interlocks $ 200 K • FY07 Resources Fermilab Apr 4-6, 2006 ILC ART Review 92 ILC Americas Horizontal Test Stand ( WBS 5.9.1) • FY07 Personnel: – – – – – Andy Hocker TD IB1 tech grp Valeriy Poloubotko Clark Reid New Physicist Total Fermilab Apr 4-6, 2006 1.00 FTE 1.75 FTE 0.25 FTE 0.25 FTE 1.00 FTE 4.25 FTE ILC ART Review 93 ILC Americas ILCTA_MDB Cryogenics (WBS 5.9.3) • FY07 Goals: – Complete Cryogenics construction at ILCTA_MDB for HTS – MDB Refrigerator and vacuum pump improvements – Additional instrumentation • FY07 Resources – O.25 engineer, 0.75 tech assigned from AD cryo group Fermilab Apr 4-6, 2006 ILC ART Review 94 ILC Americas Vertical Test Stand (WBS 5.9.2) • Our goal is to rapidly advance the intellectual understanding of SCRF surface physics and establish process controls to reliably achieve high gradient ( 35 MV/M) SCRF cavity operation • Approach: Establish a “tight loop” processing and test infrastructure in the U.S. • Tight loop elements: – – – – – Cavity fabrication improvements ( e.g. single crystal) BCP & Electro-polish facilities High purity water and High pressure rinse Vertical test facilities SCRF experts & materials program to interpret results • Vertical test facilities exist at Cornell and TJNL (bare cavities) • These are being modified for near-term use by ILC R&D • On a longer term ( 2007) new Vertical Test Stand (designed for 35 MV/M) cavity testing is being built at FNAL Fermilab Apr 4-6, 2006 ILC ART Review 95 ILCTA_VTS ILC Americas • A Vertical Test Stand VTS is sited in IB1 because this building currently houses the Magnet Test Facility large refrigerator capable of 60 W at 1.8 K • Bare 1.3 GHz 9-cell Tesla-style cavities LHe & vacuum lines Measure Q vs. T and Q vs. Eacc • 250 W (CW) RF power required at maximum gradient (Q=5x109, Eacc=35 MV/m) • Installed in a vertical pit in the Floor • Shielding against X-rays and Neutrons is an important issue for 35 MV/M cavities • Maintain “Controlled Area” status in IB1 Industrial Building 1 Cornell <5 mrem/hr immediately outside shielding <0.25 mrem/hr in normal working areas Fermilab Apr 4-6, 2006 ILC ART Review 96 ILC Vertical Test Stand (WBS 5.9.2) Americas • FY06 Status – – – – – – – Civil Design done, Radiation review ~done Civil work done in ~ 2 months Dewar design is advanced order soon Instrumentation, rack layout, etc. has begun Refrigerator modifications in the fall Input coupler design will start soon RF Power, LLRF, controls are elsewhere • FY06 Resources Fermilab Apr 4-6, 2006 ILC ART Review 97 ILC Americas Vertical Test Stand (WBS 5.9.2) FY07 Personnel Name Camille Ginsburg Cosmore Sylvester Ruben Carcagno Joe Ozelis Andrei Lounine Oleg Prokofiev Tom Peterson Valeri Poloubotko Clark Reid Charlie Hess William Mumper Dean Validis Danny Massengill George Kirschbaum Mark Thompson Craig Lerette Fred Wilson Randy Ward Fred Lewis Steve Helis Dan Eddy Yuri Pischalnikov Darryl Orris Mike Herr RF engineer Chuck Worel AD/ES&H tech Primary Task Project Physicist Project Engineer LLRF RF and test instrumentation, operation RF coupler design test instrumentation and operation cryogenic infrastructure mods, cryostat installation, reviews cryogenic infrastructure mods, cryostat installation cryogenics infrastructure mods, cryostat installation, drawings top plate assembly, installation: shielding (rad+mag), instrum, top plate assembly, installation: shielding (rad+mag), instrum, top plate assembly, installation: shielding (rad+mag), instrum, top plate assembly, installation: shielding (rad+mag), instrum, top plate assembly, installation: shielding (rad+mag), instrum, test instrumentation installation and operation test instrumentation installation and operation top plate assembly, installation: shielding (rad+mag), instrum, top plate assembly, installation: shielding (rad+mag), instrum, top plate assembly, installation: shielding (rad+mag), instrum, test instrumentation and operation test instrumentation installation test instrumentation and operation test instrumentation and operation safety reviews ILCTA RF liaison Design and install safety interlocks Design and install safety interlocks Estimated Effort (%) for ILCTA_IB1_VTS FY07 Q1 FY07 Q2 FY07 Q3 FY07 Q4 70 70 70 70 70 70 50 50 10 10 10 10 70 70 70 70 40 40 40 40 10 40 40 40 20 10 0 0 50 10 0 0 30 30 30 30 cavities 20 20 20 0 cavities 20 20 20 0 cavities 20 20 20 0 cavities 20 20 20 0 cavities 20 20 20 0 20 20 30 40 20 20 30 40 cavities 20 20 20 20 cavities 20 20 20 20 cavities 20 20 20 20 20 20 20 20 20 20 20 20 20 40 20 20 20 40 20 20 40 20 0 0 30 30 0 0 10 0 0 0 10 0 0 0 sum (%) 740.00 720.00 610.00 530.00 sum (FTE's) 7.4 7.2 6.1 5.3 6.5 FTE on average Fermilab Apr 4-6, 2006 ILC ART Review 98 ILC Vertical Test Stand (WBS 5.9.2) Americas • FY07 Goals: – – – – – – – Detailed plan exists Design and fabricate Dewar top Develop and build coupler Modify IB1 cryogenics Install RF, controls, instrumentation, etc Put all together Make it all work • FY07 Resources Fermilab Apr 4-6, 2006 ILC ART Review 99 ILC Cryomodule Assembly Facility (CAF) Americas ( WBS 5.9.5) • Scope: Build a CAF to – Dress a single cavity for Horizontal Testing – Prepare a 8 cavities string – Build a Cryomodule • FY06 Status: – – – – The MP9 building was improved to house the CAF . Clean Room has been constructed Equipment & Components for the clean room All the fixture for string assembly and cryomodule fabrication purchased – Ready to Assemble Cryomodule June 2006 – Training of Fermilab staff and Procedure development at DESY • FY06 Resources (Fermilab core Funds) Fermilab Apr 4-6, 2006 ILC ART Review 100 CAF ( WBS 5.9.5) ILC Americas • Scope: Dress cavities for Horizontal testing and Assemble ILC Cryomodule. • FY07 goals: – Build and commission a High Pressure Rinse system for ILC Cavities ( may ship these M&S funds to MSU) – Upgrade Ultra Pure Water System – Dress ILC Cavities for Horizontal testing at ILCTA-MDB – Assemble 1st ILC Cryomodule using Kit provided by DESY and INFN. • FY07 Resources: M&S includes 4 contract techs Fermilab Apr 4-6, 2006 ILC ART Review 101 CAF ( WBS 5.9.5) ILC Americas • FY07 Personnel: – – – – – – – – – – – – – Tug Arkan Brian Smith Marco Battistoni Jeff Eliott Glen Smith Jeff Wittenkeller Mark Clebek Euvgene Borissov Mark Steinke John Zweibohmer QC Process Eng Technician 0.6 FTE 1.0 1.0 1.0 (Contract) 1.0 1.0 1.0 (Contract) 0.4 0.5 0.2 0.2 1.0 3.0 (2 Contract) Total 8.0 FTE Note: Move the contract Techs to M&S and do not count them as FTE. Fermilab Apr 4-6, 2006 ILC ART Review 102 ILC ILCTA_NM Facility Infrastructure Americas ( WBS 5.9.6) • Scope: Infrastructure to install and operate one ILC RF unit with beam in New Muon Lab at FNAL • FY06 Status: – Cleaned the NML Building, Removing the CCM – General infrastructure improvement including computing, network, electrical and water. – Funded with FNAL core funds in FY06 • FY06 Resources Fermilab Apr 4-6, 2006 ILC ART Review 103 ILCTA_NM ( WBS 5.9.6) ILC Americas • Scope: Improve infrastructure to install and commission Photo-injector and one Cryomodule • FY07 goals: – – – – Build cave for the test of ILC RF unit with photo-injector Interlocks and electrical infrastructure Move loading dock and build a beam dump Temporary Beam-line extension from the end of the Cryomodule to Beam Dump • FY07 Resources: Fermilab Apr 4-6, 2006 ILC ART Review 104 ILCTA_NM ( WBS 5.9.6) ILC Americas • FY07 Personnel: – – – – – – – – Paul Czarapata Tom Sperry Margaret Crayton John Bell Bocean Virgil James Catalanello James Kilmer Misc AD & PPD Eng/Techs Total 0.5 FTE 0.5 FTE 0.7 FTE 0.5 FTE 0.3 FTE 0.4 FTE 0.25 FTE 2.05 FTE 5.0 FTE This crew exists and is working in FY06 Fermilab Apr 4-6, 2006 ILC ART Review 105 ILC ILCTA_NM Cryo Construction (WBS 5.9.7) Americas • Scope: Construction of ILCTA_NML cryogenic system • FY07 Goals: – Engineering and technical support for cryogenic system construction – FY06 SWF + M&S support to start on the NML cryogenics was provided by AD cryo using Fermilab core funds ($1050K) – Effort moving from cryo in MDB to ILCTA_NM – M&S Support includes • • • • • • • Compressor and vacuum pump installation ($207K) Gas storage components ($30K) Coldbox installation ($100K) Cryogenic storage and distribution system ($467K) Controls and spares ($250K) Cryomodule interface equipment (end cans) ($1120K) M&S support for 5 contract engineers, designers, and techs (as required - $600K) Fermilab Apr 4-6, 2006 ILC ART Review 106 ILC Americas ILCTA_NM cryo construction ( WBS 5.9.7) • FY07 Resources • FY07 Personnel: – Crew worked in FY06 on MDB cryogenics NM cryo – 15 FTE are a combination of AD Cryogenic Department and PPD Mechanical Department personnel (presently working on the project) and represents the baseline of support that can be counted on in FY07. Additional support will be required (using either contract or temporary help) in order to maintain the schedule. Fermilab Apr 4-6, 2006 ILC ART Review 107 ILC Americas Electron Source ILCTA_NM ( WBS 5.9.8) • Scope: N/A • FY06 Status: N/A • FY06 Resources – Was not funded in FY06 • Scope: Provide a new rf photo-gun (DESY type) • FY07 goals: – – – – Laser upgrade 200K Laser table upgrade 140K new rf gun 760K Miscellaneous 100K • Collaboration with Budker INP on the gun design, production and testing Fermilab Apr 4-6, 2006 ILC ART Review 108 ILC Americas Electron Source ILCTA_NM ( WBS 5.9.8) • FY07 Personnel: – – – – R. Fliller J. Santucci New laser phys (offer accepted) R. Andrews Total Fermilab Apr 4-6, 2006 ILC ART Review 0.5 FTE 0.25 FTE 0.75 FTE 0.5 FTE 2.0 FTE 109 ILC Americas Test Facility Ops ( WBS 5.9.10) • Scope: Operations support for all three ILCTA test areas (MDB HTS, IB1 VTS, NML cryomodules) • FY07 Goals: – In FY07 each of the areas will need support for operations. It is planned to share personnel between areas for cryo and RF operations and while we grow expertise in cavity handling – Engineering and technical support: • • • • • Operation of cryogenic system Handling of cavities and cryomodules Operational support for RF power, LLRF and controls Minor modifications and upgrades to existing systems Repairs and maintenance – M&S costs estimates are based on costs to operate other cryogenic and RF systems at FNAL Fermilab Apr 4-6, 2006 ILC ART Review 110 ILC Americas Test Facility Operations ( WBS 5.9.10) • FY07 Resources *M&S includes cost for cryogens and other operating expenses Fermilab Apr 4-6, 2006 ILC ART Review 111 ILC Americas Test Facility Operations ( WBS 5.9.10) • FY07 Personnel: – ILCTA_NML • Paul Czarapata (0.25), John Reid (0.25), AD Electrical Techs (0.5), AD Cryogenics Engineer (0.5), PPD Mechanical Techs (1) – ILCTA_MDB • Paul Czarapata (0.25), John Reid (0.25), AD Electrical Techs (0.5), AD Cryogenics Engineer (0.5), AD Mechanical Techs (2) – ILCTA_IB1: • Joe Ozelis (0.6), Yuenian Huang (0.5), Cosmore Sylvester (0.3), Darryl Orris (0.3), New Engineer II (0.3), Yuriy Pischalnikov (0.2), Ruben Carcagno (0.2), Dennis Shpakov (0.2), Andrzej Makulski (0.2), Roger Nehring (0.2), Electrical & Mechanical Tech Support (1) Fermilab Apr 4-6, 2006 ILC ART Review 112 Test Facility Instr. ( WBS 5.9.12) ILC Americas • Scope: Beam Instrumentation for FNAL ILCTA • FY06 Status: – RF interlock system design and prototyping completed – Cold cavity-BPM EM simulations and design underway • FY06 Resources: None, new task for FY07 • FY07 Scope: same • FY07 goals: – – – – Completion of the RF interlock system Prototyping of a cold cavity-BPM for the cryostat Establishment of a cavity-BPM test-stand Development, prototyping and production of a general purpose digitizer board (ATCA-based) – Design of an analog signal pre-processing interface for button BPM’s of the photo-injector – Design of bunch phase monitor electronics – Design of a cavity-BPM signal down-converter Fermilab Apr 4-6, 2006 ILC ART Review 113 Test Facility Instr ( WBS 5.9.12) ILC Americas • Personnel: – – – – – – – – – – – – – – John Van Bogaert Charlie Briegel Jim Crisp Bob Dysert Nathan Eddy Brian Fellenz Jim Fitzgerald Marv Olson Peter Prieto Andrea Saewert John Seraphin Randy Thurman-Keup Manfred Wendt Duane Voy Total Fermilab Apr 4-6, 2006 0.25 FTE 0.25 FTE 0.50 FTE 0.25 FTE 0.50 FTE 0.25 FTE 0.25 FTE 0.25 FTE 0.75 FTE 0.25 FTE 0.25 FTE 0.25 FTE 0.25 FTE 0.25 FTE 4.50 FTE ILC ART Review 114 ILC Americas Test Facility Instr (WBS 5.9.12) FY07 Resources: Fermilab Apr 4-6, 2006 ILC ART Review 115 ILC Americas Bid to Host: Conventional Facilities (WBS 7.1.1) • Scope: Fermilab ILC site planning • FY07 Goals: – FNAL site specific technical drawings and machine layouts – Characterize local surface and geotechnical site – Optimize design and perform site specific cost estimate in conjunction with A&E consultants • FY07 Resources FESS labor on charge system so M&S Fermilab Apr 4-6, 2006 ILC ART Review 116 ILC Industrial Cost Study and RF Unit Fabrication (WBS 4.10.1, 7.2.1) Americas • Scope: Initiate the RF Unit Costs Study • FY06 Status: – Provide necessary back up documentation and justifications to move the RF Unit Cost Study contract through the signature authorization process – Provide interface with industrial vendors to transmit required designs and specifications to allow accurate cost estimation and monitor progress of contract – *Conventional Facilities Cost Study is also planned in FY06 • FY06 Resources Fermilab Apr 4-6, 2006 ILC ART Review 117 ILC Industrial Cost Study and RF Unit Fabrication (WBS 4.10.1, 7.2.1) Americas • Scope: Complete the RF Unit Cost Study and initiate industrial order to fabricate an RF Unit as part of bid-to-host • FY07 Goals: – 4.10.1: Continue to provide interface with industrial vendors to transmit required designs and specifications to allow accurate cost estimation and monitor progress of contract – 7.2.1:Begin a multi-year bid-to-host effort to qualify U.S. industry for ILC components (first step: fabricate a complete RF Unit using U.S. industry and lab infrastructure) • FY07 Resources Fermilab Apr 4-6, 2006 ILC ART Review 118 ILC Americas FY07 Personnel (WBS 4.10.1, 7.2.1) • Personnel: – Phil Pfund – Gregg Kobliska – Mark Steinke Total Fermilab Apr 4-6, 2006 0.45 FTE 0.1 FTE 0.2 FTE 0.75 FTE ILC ART Review 119 ILC U.S. Site Specific Prog Mgmt (WBS 7.3.1) Americas • Scope: U.S. Site Specific accelerator design effort • FY07 Goals: – – – – – Lead effort on U.S. Site Specific accelerator design ( for TDR) Accelerator design optimized for FNAL site Central Damping Rings, cryogenic facilities, etc. Minimize impact on surrounding community, etc. Candidate chosen by international search but must reside @ FNAL • FY07 Resources Fermilab Apr 4-6, 2006 ILC ART Review 120 Conclusions ILC Americas • FNAL’s ILC effort is growing rapidly • Our request for FY07 is large $ 55 M (remove GDE, detector) – 186 FTE – $ 26 M M&S (direct) but several M of this goes to other labs – Not included: $ 3.2 M for Detector R&D + $ 1.2 M for test beam • The vast majority of this proposed effort is focused on R1, R2 R&D (cavities and cryomodules) and on the RDRTDR machine design effort • More people wish to join… we should not have to send them away because the ILC B&R category won’t support them right now • Most have their salaries paid with HEP funds now • However, there still needs to be enough overall funding in the labs and universities to support the desired level of effort Fermilab Apr 4-6, 2006 ILC ART Review 121 END ILC Americas • GDE common fund is below Fermilab Apr 4-6, 2006 ILC ART Review 122 ILC Americas GDE Common Fund (WBS 1.7) • Scope: Support the GDE Office and Staff • FY06 Status: – GDE Office was established with staff support person and ILC Americas communicator – Coordinate activities associated with GDE meetings – Developed (in conjunction with all three regions) the “ILC Newsline” web based communication tool • FY06 Resources Fermilab Apr 4-6, 2006 ILC ART Review 123 ILC Americas GDE Common Fund (WBS 1.7) • Scope: Support the GDE Office and Staff • FY07 Goals: – Continue to support the GDE Office and coordinate associated GDE meetings – Upkeep of the ILC web page and develop additional communication tools (incl. brochure) – Implement EDMS solution for ILC • FY07 Resources Fermilab Apr 4-6, 2006 ILC ART Review 124 ILC Americas GDE Common Fund (WBS 1.7) • Personnel: – Max Hronek – Elizabeth Clements – Web Specialist* Total 1.0 FTE 1.0 FTE 1.0 FTE 3.0 FTE * Posted opening Fermilab Apr 4-6, 2006 ILC ART Review 125