Contract Law Week 3 1. Termination (i) The meaning of termination/ discharge/ rescission for breach Johnson v Agnew 1980 Although a vendor has, at trial, to elect whether to go for damages or specific performance, if he chooses the latter and the order is not complied with, he can still apply to the court to terminate the contract and is then entitled to damages for its breach. The plaintiff vendors, being in arrears with mortgage repayments, entered into a written agreement for the sale of the properties. The purchasers failed to complete whereon the vendors obtained an order for specific performance. The purchasers failed to carry out the order, and the mortgagees duly enforced their securities by selling the properties. The proceeds of the sale were insufficient to discharge the mortgage in full, and the vendors moved for an order that the purchasers should pay the balance of the purchase price to the vendors. The judge made no order, and the Court of Appeal allowed the vendor's appeal. On appeal by the purchaser, held, dismissing the appeal that where specific performance was ordered but not complied with, damages was still available as an alternative remedy, and damages would be assessed on a common law basis as at the date when the remedy of specific performance was aborted. Photo Production Ltd v Securicor Transport Ltd 1980 The so-called doctrine of fundamental breach does not operate so as to prevent reliance upon an exclusion of liability clause upon the contract being brought to an end. The defendants contracted with the plaintiffs to provide a night- patrol service at the latter's factory premises. The contract excluded liability on the defendants' part for "any injurious act or default of any employee of the (defendants) unless such act or default could have been foreseen and avoided by the exercise of due diligence on the part of the employer; nor in any event shall the company be held responsible for any loss suffered through fire or any other cause except in so far as is solely attributable to the negligence of the company's employees acting within the cause of their employment." One of the defendants' employees who had been satisfactorily employed by them for some three months deliberately started a small fire in the factory, the fire getting out of control and burning down the factory. The Court of Appeal reversed the trial judge's ruling that the defendants could rely upon the contract as excluding their liability. Held, allowing the defendants' appeal, that whether an exclusion clause was apt to exclude or limit liability was a matter of construction of the contract; that the fact that a breach may be such as to justify the innocent party in terminating or treating as repudiated the contract did not mean that the terms of the contract in so far as they governed liability were not to be enforced; that, generally, parties to a contract, when they bargained on equal terms, should be at liberty to apportion liability in the contract as they saw fit; and that the wording of the exclusion clause in the instant case was adequate to exclude liability for what occurred. (ii) Conditions, warranties and innominate terms Bunge Corporation v Tradax Export SA 1981 In general, time is of the essence in a mercantile contract, and a term as to time of performance of an obligation by one party as a condition precedent to the performance of an obligation by the other party will generally be treated as a condition. By a contract dated January 30, 1974, buyers agreed to purchase 15,000 tons of soya bean meal, shipment to take place in consignments of 5,000 tons in May, June and July 1975. By cl.7 of the Grain and Feed Trade Association Ltd.'s standard form contract 119, which was incorporated, it was provided that "Period of delivery during May 1975 at buyers' call. Buyers shall give at least 15 days' notice of probable readiness of vessel." The buyers gave notice under cl.8 extending the period for delivery to one calendar month. The last day upon which the sellers could ship the goods therefore became June 30, 1975, and the last day for the buyers to give notice was June 12. The buyers did not give notice until June 17. The judge held that the term as to the time for giving notice was not a condition and that in any event there had been no breach. The Court of Appeal allowed the sellers' appeal. On appeal to the House of Lords, held, that, in general, time was of the essence in a mercantile contract; in such a contract, where a term had to be performed by one party as a condition precedent to the ability of the other party to perform another term, especially an essential term such as the nomination of a single loading port, the term as to time for performance of the former obligation would in general fall to be treated as a condition. cl.7 was a condition since until notice was given the sellers could not know which loading port to nominate. Hong Kong Fir Shipping Co Ltd v Kawasaki Kisen Kaisha Ltd 1962 By a time charterparty, charterers hired a ship ". . . she being in every way fitted for ordinary cargo service." The owners were to "maintain her in a thoroughly efficient state in hull and machinery during service." The ship was delivered to the charterers in February 1957 in reasonably good condition, but chiefly owing to an inadequate engine room staff, there were serious breakdowns on the first voyage, resulting in lengthy delays and considerable expense on repairs. In June 1957, the charterers, who had no reasonable grounds for thinking that the vessel could be made seaworthy before September 1957, repudiated the contract. The ship was in fact made thoroughly seaworthy by the middle of September, and the owners sued the charterers for wrongful repudiation of the charterparty. Salmon, J. held that the owners were entitled to damages. The charterers appealed. Held, although the owners were admittedly in breach of their obligation to deliver a seaworthy ship, seaworthiness was not a condition of the charterparty the breach of which entitled the charterers at once to repudiate; since, therefore, the delays caused by the breakdowns and repairs were not sufficient for the contract to be frustrated, the charterers' claim failed and the appeal must be dismissed. Per Diplock, L.J.: The shipowner's undertaking to deliver a seaworthy ship is neither a "condition" nor a "warranty" but one of that large class of contractual undertakings one breach of which may have the same effect as that ascribed to a breach of "condition" under the Sale of Goods Act 1893 and a different breach of which may have only the same effect as that ascribed to a breach of "warranty" under that Act. Maredelanto Compania Naviera SA v Bergbau – Handel GmbH (The Mihalis Angelos) 1971 A clause stipulating a date for expected readiness in a charterparty is a condition, and a charterer may terminate forthwith on discovering the falsity of the owner's assurance. On May 25, 1965, the owners let the vessel MA to charterers. Clause 1 contained an expected readiness clause for "about July 1, 1965." There was also a cancelling clause if the vessel was not ready to load by July 20, 1965. The owners had no reasonable grounds to expect the MA to be ready to load on July 1, or indeed until about July 14. Eventually the ship could not have been ready for trading until July 25. Meanwhile, however, the charterers discovered that they had no cargo for the vessel and they cancelled the contract on July 17 as a case of force majeure. The owners accepted this as a repudiation. They did not charter the vessel to anyone else, but sold her on July 29. The arbitrators found that the charterers would beyond doubt have cancelled when the ship missed her cancelling date, but the owners claimed damages for loss of the charter on July 17. Held, (1) that the expected readiness clause was a condition of the contract, the breach of which entitled the charterers to cancel on July 17; (2) that even had that not been the case, the charterer would have been entitled to cancel under the cancellation clause, and the owners would have been entitled to nominal damages only. L Schuler A-G v Wickman Machine Tool Sales Ltd 1974 The mere fact that a commercial contract describes one of its terms as a "condition" does not compel the court to hold that that term is a condition in the strict sense; the question will be decided by construing the contract as a whole. Per curiam: In construing a contract, the court could not take into account the conduct of the parties subsequent to the execution of the contract. S Co., a German company, entered into a contract with W Co., an English company, giving W Co. the sole rights to sell S Co.'s panel presses in England. Clause 7 (b) provided that "it shall be a condition of this agreement" that W Co.'s representatives should visit six named firms each week to solicit orders. W Co.'s representatives failed on a few occasions to do so. S Co. claimed to be entitled to repudiate the agreement, on the basis that a single failure was a breach of condition, giving them an absolute right to treat the contract as at an end. Held, that such a breach did not entitle S Co. to repudiate, since such a construction of the clause was so unreasonable that the parties could not have intended it. Sale of Goods Act 1979, ss 12-15 A (Other doc) (iii) Anticipatory Breach Hochster v De La Tour 1853 Hochster v De La Tour is a landmark English contract law case on anticipatory breach of contract. It held that if a contract is repudiated before the date of performance, damages may be claimed immediately. In April, De La Tour agreed to employ Hochster as his courier for three months from 1 June 1852, to go on a trip around the European continent. On 11 May, De La Tour wrote to say that Hochster was no longer needed. On 22 May, Hochster sued. De La Tour argued that Hochster was still under an obligation to stay ready and willing to perform till the day when performance was due, and therefore could commence no action before. 2. DAMAGES (i) The general principle Jeancharm Ltd (t/a Beaver International) v Barnet Football Club Ltd Abstract: A football club, B, appealed against a ruling that it was liable in damages to a clothing manufacturer, J. B had previously entered into an agreement with J pursuant to which J agreed to supply free training kit to the team and replica kits at an agreed price for sale to the public. Under the terms of the agreement, if the items in question were supplied late J would be obliged to pay a penalty of 20 pence per garment per day. Conversely, if B were late in making payment for the items supplied, interest would accrue at the rate of 5 per cent per week. Following various difficulties over payment, J invoked the penalty clause. At first instance the judge upheld the penalty clause which took B's liability under the contract from approximately GBP 5,000 to GBP 20,000. B contended that the clause was a penalty clause at common law as well as being defined as such by contract, with the result that it was unlawful. Held, allowing the appeal, that the leading authority in relation to the determination of whether a clause was a penalty clause at common law was still the case of Dunlop Pneumatic Tyre Co Ltd v New Garage & Motor Co Ltd [1915] A.C. 79. The courts had continued to apply the principles therein but had also warned that caution was required before categorising a clause as such when the parties were of equal bargaining power. In order to be upheld such a clause had to contain a genuine pre estimate of the damage likely to result from breach, Dunlop and Robophone Facilities Ltd v Blank [1966] 1 W.L.R. 1428 applied and Philips Hong Kong Ltd v Attorney General of Hong Kong 61 B.L.R. 41 considered. An increased rate of interest might constitute a valid clause in certain circumstances where such an increase still represented a genuine pre estimate of the damage suffered; however 5 per cent per week represented a yearly interest rate of 260 per cent. Such a sum did not amount to a genuine pre estimate but was a penalty clause in the Dunlop sense and consequently unenforceable, Lordsvale Finance Plc v Bank of Zambia [1996] Q.B. 752 considered. Alfred McAlpine Capital Projects Ltd v Tilebox Ltd Summary: Pre-estimated damages calculated for the purposes of a liquidated damages clause in a contract did not have to be reasonable to be enforceable, and the court would be predisposed, where possible, to uphold contractual terms that fixed the level of damages for breach, particularly in the case of commercial contracts freely entered into between companies of comparable bargaining power. Abstract: The applicant (M) applied for a declaration that a liquidated and ascertained damages clause contained in a construction contract between M and the respondent (T) was in fact a penalty clause and unenforceable. T had engaged M as the main contractor on a commercial development and clause 24.2 of the contract provided for a fixed weekly sum of GBP 45,000 in damages in the event of any delay. T had also entered into a development funding agreement (DFA) with a third party (S), which was to fund the development up to an agreed maximum figure in return for T's leasehold interest. T argued that the DFA required it either to ensure completion by the date stipulated in the DFA or by the date for completion in the JCT contract with M, failing which it would be liable to S. T submitted that its potential liability was therefore a foreseeable loss, included in the liquidated damages clause to provide a genuine estimate of its losses. M maintained that there was no obligation on T to complete the works by the date specified, but only to do so within a reasonable time. It fell to be determined whether the liquidated damages clause was valid and enforceable. Application refused. Pre-estimated damages did not have to be right to be reasonable. There had to be a substantial discrepancy between the level of damages stipulated in the contract and the level of damages that was likely to be suffered before it could be said that the agreed pre-estimate was unreasonable. The test for a genuine pre-estimate did not turn on the honesty or genuine nature of a party: it was primarily an objective one, even though the court would have regard to the thought processes of the parties at the time of contracting. Because the rule about penalties was an anomaly within the law of contract, the courts would be predisposed, where possible, to uphold contractual terms that fixed the level of damages for breach. That predisposition would be even stronger in the case of commercial contracts freely entered into between parties of comparable bargaining power, Law v Redditch Local Board [1892] 1 Q.B. 127, Clydebank Engineering & Shipbuilding Co Ltd v Don Jose Ramos Yzquierdo y Castaneda [1905] A.C. 6, Dunlop Pneumatic Tyre Co Ltd v New Garage & Motor Co Ltd [1915] A.C. 79, Bridge v Campbell Discount Co Ltd [1962] A.C. 600, Philips Hong Kong Ltd v Attorney General of Hong Kong 61 B.L.R. 41 applied. In the instant case, under the DFA, T had been required to secure completion by the date required under the building contract, and at the time the contract was made, losses flowing from a delay in completion at the level specified in the liquidated damages clause were foreseeable. In those circumstances, cl.24.2 of the building contract was not unenforceable as a penalty. It was clearly an enforceable provision for liquidated damages and not a penalty clause.