Prepared for: Mr. Michael Bolch Shaw Group Project Scope and Client Goals Florida Institute of Technology Design and construction of a 12,600 s.f. commercial office building to be used as a financial institute SW corner of Babcock St. and Palm Bay Blvd. in Palm Bay, Fl Create a construction schedule using MS Project Generate an estimated probable cost Develop construction contracts and terms Project Management Plan Divided into 3 parts Project Controls Project Scope Project Schedule Structural Design Layout Structural analysis / Member design Connections Hurricane damage mitigation Legal Aspects Contract development & terms Preparation for negotiations Regulatory Agencies Project Size and Cost Steel structure 2 stories 12,600 s.f. Parking lot Transportation Level of service analysis Water and sewer system design Geotechnical Foundation design Total Estimated Cost: $1,895,000.00 ($150.00/s.f.) Project Design Schedule Structural Design Key Elements Layout Structural analysis / Member design Connections Hurricane damage mitigation Anticipated Final Design Second Floor Layout Roof Layout Structural Analysis / Member Design Two Dimensional Dr. Frame Analysis Determining Maximum Shear, Moment, and Axial Loads being less than the Design Load Structural Elevation Drawing (Transverse View) Structural Elevation Drawing (Longitudinal View) Final Member Selection Roof Beam A2 - A3 Beam B1 - B2 Beam B2 - B3 Beam C1 - C2 Beam D1 - D2 Beam D2 - D3 Beam E2 - E3 Girder A1 - B1 Girder A2 - B2 Girder A3 - B3 Girder B2 - D2 Girder D1 - E1 Girder D2 - E2 Girder D3 - E3 Designed Member Sizes W14 x 68 W16 x 50 W16 x 50 W16 x 50 W16 x 50 W16 x 50 W14 x 68 W14 x 68 W14 x 68 W14 x 68 W12 x 35 W14 x 68 W14 x 68 W14 x 68 Second Floor Beam A2 - A3 Beam B1 - B2 Beam B2 - B3 Beam C1 - C2 Beam D1 - D2 Beam D2 - D3 Beam E2 - E3 Beam B4 - D4 Girder A1 - B1 Girder A2 - B2 Girder A3 - B3 Girder B2 - D2 Girder D1 - E1 Girder D2 - E2 Girder D3 - E3 Girder B3 - B4 Girder D3 - D4 Designed Member Sizes W16 x 45 W18 x 65 W18 x 65 W18 x 65 W18 x 65 W18 x 65 W16 x 45 W12 x 53 W16 x 77 W16 x 77 W16 x 77 W12 x 53 W16 x 77 W16 x 77 W16 x 77 W14 x 38 W14 x 38 Frames (Roof) Beam B1 - D1 Beam B3 - D3 Girder A1 - A2 Girder E1 - E2 Columns Frames (2nd Floor) Beam B1 - D1 Beam B3 - D3 Girder A1 - A2 Girder E1 - E2 Stair Column Stair Beam Columns A3 B2 D2 E3 B4 D4 Designed Member Sizes W12 x 35 W12 x 35 W14 x 38 W14 x 38 W12 x 120 Designed Member Sizes W12 x 53 W12 x 53 W16 x 45 W16 x 45 W8 x 31 W8 x 58 Designed Member Sizes W8 x 31 W8 x 31 W8 x 31 W8 x 31 W8 x 31 W8 x 31 Connections / Drawings Shear Connections are bolted Moment Connections are shop-welded and bolted Connection Bolted Connection Welded Connection A3 Web Shear Connection 6 - 1/2" A325 Bolts - L2 1/2 x 2 1/2 x 1/2 Angle Min Edge Distance: 0.632" Min Spacing: 1.33" --------- A3 Flange Shear 6 - 1/2" A325 Bolts - L2 1/2 x 2 1/2 x 1/2 Angle Connection Min Edge Distance: 0.632" Min Spacing: 1.33" --------- 4 - 1" A325 Bolts - L6 x 6x 3/8 Angle Min Edge Distance: 0.95" Min Spacing: 2.667" --------- B1 Moment Connection 2 - 1/4" A36 Steel Plates - 2L6 x 3 1/2 x 3/8 Double Angle - 3/4" diameter A325 (X) Bolts Min Edge Spacing: 1 1/4" Web 1/8" Fillet Weld 2L6 x 3 1/2 x 3/8 Double Angle Length: 6" Location: All Around B3 Web Shear Connection 4 - 1 1/4" A325 Bolts - L3 1/2 x 3 x 5/16 Angle Min Edge Distance: 3/4" - Min Spacing: 3.33" --------- A2 Web Shear Connectin B3 Flange Shear 4 - 1 1/4" A325 Bolts - L3 1/2 x 3 x 5/16 Angle Connection Min Edge Distance: 3/4" Min Spacing: 3.33" --------- A3 Web-Shear Connection 6 – A325 ½” bolts based on Slip Critical Strength L2½” x 2½” x 1/2 Double Angles based on Areas Column Base Plate Drawings Work Breakdown Structure DURATION GENERAL WORK BREAKDOWN START END HOURS RESPONSIBLE PLANNED ACTUAL ENGINEER SALARY BUDGET $/HR PLANNED $ $ $ $ $ $ $ $ $ $ 170.00 510.00 510.00 510.00 510.00 $ 85.00 $ $ 85.00 $ 850.00 850.00 ACTUAL DONE % COMPLETE PRELIMINARY DESIGN (50% SUBMITTAL) STRUCTURAL ANALYSIS STAIRS COLUMNS BEAM FRAMES GIRDER STRUCTURAL DESIGN CONNECTIONS BRACING DESIGN 17-Oct 17-Oct 17-Oct 17-Oct 17-Oct 17-Oct 17-Oct 17-Oct 17-Oct 24-Oct 24-Oct 24-Oct 24-Oct 24-Oct 24-Oct 24-Oct 24-Oct 24-Oct CRAIG CRAIG CRAIG CRAIG CRAIG CRAIG CRAIG 26 2 6 6 6 6 20 10 10 26 2 5 6 8 5 12 10 2 85.00 85.00 85.00 85.00 85.00 $ $ $ $ $ $ $ $ $ 170.00 425.00 510.00 680.00 425.00 850.00 170.00 YES YES YES YES YES YES YES YES YES 100% 100% 100% 100% 100% 100% 100% 100% 100% FINAL DESIGN (95-100%) PROPOSAL STRUCTURAL DRAWINGS PLANS SECTIONS DETAILS/CONNECTIONS 31-Oct 31-Oct 31-Oct 31-Oct 5-Dec 5-Dec 5-Dec 5-Dec CRAIG CRAIG CRAIG 12 4 4 4 15 6 4 5 $ $ 85.00 $ 85.00 $ 85.00 $ $ $ 340.00 340.00 340.00 $ $ 340.00 425.00 YES YES YES YES 100% 100% 100% 100% Hurricane Damage Mitigation Constructed on raised foundations above sea level Built upon steel, concrete, or wooden pilings or anchored to solid rock All concrete is reinforced with steel Specialized doors and windows Using shutters over doors and windows during hurricanes Legal Aspects Contract Development Preparations for Negotiations Permits, Licenses, Agencies Contract Development-1 Contract Development for Panther Financial Description of lands/site Contractors Responsibilities Labor Schedule Permits Owners Responsibilities Communication Payments Insurance Contract Development-2 Change Orders Claims Tests and Inspections Dispute Resolution Good Faith Negotiations Mediation Arbitration Litigation Liquidated Damages Negotiations Preparation for Negotiations Gather outside information Establish points of leverage Set a goal BATNA Shoot for a Win - Win conclusion Permits, Licenses, Agencies Follow codes and regulations Acquire permits and licenses Keep in good standing with agencies and the public Project Summary Scope Schedule Estimated Cost Structural Design Contract Development Negotiation Tactics Codes, Permits, and Licenses Thank you for choosing The Shaw Group, Inc. Project plan will meet client’s goals We will produce a quality project We appreciate your business Your Project Manager Stephen M. Craig StephenCraig11@gmail.com (412) 657-6263