CERN LHC Project Document No. LHC-LJ-EC- CH-1211 Geneva 23 Switzerland EDMS Document No. the Engineering Change requested by ( Name & Div./Grp. ) : Large Hadron Collider A. L. Perrot / EN-MEF, R2E Project project Date: 3/12/2016 The 2Figures …a n Engineering Change Request – Class I Protection of equipment located in UJ56 Brief description of the proposed change(s) : The level of radiation expected from the collisions at the interaction point 5, and more precisely the flux of hadrons with energy in the multi MeV range, will induce Single Event Errors of the standard electronics present in many of the control equipment located in UJ56. Such events would perturb the LHC, possibly leading to critical situations for the machine elements. It is furthermore proposed to relocate part of the equipment installed in UJ56 (almost all first floor racks) into the UL557 bypass gallery, where the amount of radiation is reduced. The relocation of the SEE sensitive equipment identified by the RADWG is foreseen for the first LHC long shutdown. This ECR documents this implementation. Equipment concerned : Drawings concerned : Equipment installed in UJ56 Documents concerned : Reference Database PE in charge of the item : PE in charge of parent item in PBS : M. Brugger / A. L. Perrot Samy Chemli Decision of the Project Engineer : Decision of the PLO for Class I changes : Rejected. Accepted by Project Engineer, no impact on other items. Actions identified by Project Engineer Accepted by Project Engineer, Not requested. Rejected. Accepted by the Project Leader Office. Actions identified by Project Leader Office but impact on other items. Comments from other Project Engineers required Final decision & actions by Project Management Date of Approval : Date of Approval : Actions to be undertaken : Date of Completion : Visa of QA Officer : Note : when approved, an Engineering Change Request becomes an Engineering Change Order/Notification. LHC Project Document No. LHC-LJ-ECPage 2 of 20 1. DETAILED DESCRIPTION by A. L. Perrot The level of radiation expected from the collisions at the interaction point 5 has been simulated with the FLUKA code [1, 2] for the LHC design values. Critical radiation levels are found in the UJ56. Therefore, for 2011/2012, hadrons with E>20 MeV fluence between 3.5x107 and 1.1x108 cm-2 per year was predicted on average at relevant critical equipment locations in UJ56. This fluence will reach up to 5.3x108 cm-2 per year and 2.1x109 cm-2 per year, respectively, at LHC nominal and ultimate conditions. For comparison, at CNGS, before additional shielding implementation, SEE failures (leading to the stop of the facility) were observed for hadrons with E>20 MeV fluences of the order of 107 cm-2 per year. The relocation actions to be performed to reduce the SEE in the UJ56 electronics have been divided into 3 phases. The first two phases were performed during the 2010-2011 and the 2011-2012 Christmas breaks while the third and major phase is foreseen during the first long shutdown. The first phase consisted into moving the critical safety elements (ODH and fire detection central units) [3]. The second phase consisted into relocating the UPS units. The third phase will consist into relocating and protecting the remaining SEE sensitive equipment identified by the RADWG [4]. This document describes the second and third phases of the strategy proposed by the R2E Mitigation Project in terms of relocation to minimise radiation induced failures in electronics located in UJ56. 1.1 IRRADIATION TESTS RESULTS OF THE EQUIPMENT TO BE RELOCATED by M. Brugger and G. Spiezia The equipment installed in the UJ56 mostly consists of commercial electronics not specifically designed nor tested to be operated in a radiation environment. For example, previous test results on PLCs, Ethernet repeaters, QPS control, etc., as well as 2011 LHC operation have shown that the radiation tolerance of the existing equipment cannot be guaranteed and that LHC operation would be significantly impacted in case no mitigation measures are applied. In order to further evaluate the radiation sensitivity of the equipment exposed to the above mentioned radiation levels, some of the most affected devices/systems located in the UJ56 have been submitted to irradiation tests at the CNRAD test area [4]. During these tests not all UJ56 equipment could be tested (due to beam time limitation, complexity/size of the equipment to be tested) and it is furthermore important to note that testing commercial equipment/components does not guarantee that a similar type of equipment would lead to the same failure crosssections. This is due to the number of used components, possible different producers and component batches, where no control can be performed from the user side nor guarantee be given from the manufacturer. For the case of the power-converters, additional tests of full power-converter units were performed in a new R2E test-area, H4IRRAD [5]. This allowed for both, confirm the 2010/2011 LHC observation and study intermediate patch-solutions in order to minimize the impact during 2012 operation. Consistent with observations during LHC operation, the performed radiation tests confirmed clearly that various systems show soft failures (requiring reset) already at relatively low radiation levels of the order of 1x107 cm-2 (PLC control systems) and destructive failures (power-supplies) as from a few 1x108 cm-2 accumulated highenergy hadron fluence onwards. Even though some of the tested components showed a higher resistance during the radiation tests, it was decided between the equipment owners, the RadWG and the R2E mitigation project to relocate all concerned systems: where failures under radiation tests where observed; where the equipment type is known to be radiation sensitive (e.g. complex control or powering systems); LHC Project Document No. LHC-LJ-ECPage 3 of 20 where the relocation of other sensitive equipment makes it more efficient for the equipment to be relocated with (cabling/access/maintenance). The equipment remaining in critical areas exposed to radiation is thus only equipment which was tested under radiation (e.g. designed similarly for the LHC tunnel) or passive equipment not or less prone to SEE induced errors. 1.2 EQUIPMENT TO BE RELOCATED AND ASSOCIATED MODIFICATIONS by A. L. Perrot For complete information about the equipment and the reason inducing its relocation, please refer to the ‘Point 5 - equipment inventory document [3]. The current locations of the equipments to be relocated are presented in Figures 1 to 4 while their locations after relocation are presented in Figures 5 to 7. Relocating the equipment will not have any impact on the machine functionality. 1.2.1 POWER CONVERTERS EQUIPMENT This equipment is located in the UJ56 –level 1 and consists of 15 power converters used for the powering of the Inner Triplet (IT) quadrupoles circuits of Point 5 right and their correctors (see Table 1). The misbehaviour / failure of one of these devices will lead to the beam dump and possible access for reparation. All the equipment will be relocated in UL557 as close as possible to UJ56/UP56 (see Figure 6). Two amongst the four spare racks (RYSAxxx) will be relocated further away on the other side of the bypass. The two remaining spare racks today located in UJ56 will be removed. Two spare racks are already located in USC55 machine area. The integration of the power converters in the bypass takes into account the volume required for their installation (with connection) and their maintenance (1.4 m in front of the equipment to remove the power supply modules). The 2 calibration racks (RYCA01-02) have to be accessible from both sides and stay together. The only integration solution for these both racks leads to their partial interference with the transport volume. This implies their removal for the passage of the transport (see paragraph 1.4). To minimise the length of the watercooled cables from DFBX several ducts will be drilled in the wall between the machine and UJ56 and between UJ56 and UL557 bypass (see paragraph 1.3). In addition the bypass sector door (YCPS01=UJ561) will be displaced 10 meters away in UL56. This will allow relocating the power converters as close as possible to the cables arrival in the bypass. To ensure the functionality of the power converters in their new location the following constraints will have to be filled: - ensure the cooling of the equipment by chilled and demineralised water, - provide new links to WorldFip and PIC equipment, - provide Ethernet access in the bypass, - redefine the length/section of the DC cables in view to avoid getting over the maximum voltage delivered by the power converter (see paragraph 1.2.10), - group together the IT Quadrupoles racks and ensure a common grounding (via a common Copper plate installed below these racks). LHC Project Document No. LHC-LJ-ECPage 4 of 20 Table 1. Power converters Rack Reference RQX.R5 Converter/Rack Type LHC8kA-08V Power Converter Name RPHFC.UJ56.RQX.R5 [RYPFB, RYPFA01, RKHF, Circuit Name ‘RQX.R5’ (Cf LHC DataBase Layout) IT quadrupoles RYPFA02, RYHF01] RTQX2.R5 [RYPFA03, RKHG RYPFA04, RYHG01] LHC6kA-08V RPHGC.UJ56.RTQX2.R5 LHC600A-10V RPMBC.UJ56.RTQX1.R5 RYMCC01 RYCA01 DCCT Calibration RYCA02 DCCT - ADC Electronics RYMCB02 LHC600A-10V RYMCB03 LHC600A-10V RYMCB04 LHC600A-10V RYMCB05 LHC600A-10V RYLB01 LHC120A-10V RYLC01 LHC120A-10V RYSA01 Spare Parts RYSA02 Spare Parts RYSA03 RYSA04 Spare Parts Spare Parts RYSC01 Hot Spare Parts RPMBB.UJ56.RCBXH3.R5 RPMBB.UJ56.RCBXH2.R5 RPMBB.UJ56.RCBXV3.R5 RPMBB.UJ56.RCBXH1.R5 RPMBB.UJ56.RCBXV1.R5 RPMBB.UJ56.RCBXV2.R5 RPMBB.UJ56.RQSX3.R5 RPLB.UJ56.RCOX3.R5 RPLB.UJ56.RCOSX3.R5 RPLB.UJ56.RCSX3.R5 RPLB.UJ56.RCSSX3.R5 RPLB.UJ56.RCTX3.R5 RCBXH3.R5 RCBXH2.R5 RCBXV3.R5 RCBXH1.R5 RCBXV1.R5 RCBXV2.R5 RQSX3.R5 RCOX3.R5 RCOSX3.R5 RCSX3.R5 RCSSX3.R5 RCTX3.R5 1.2.2 SURVEY The electronics of the low beta magnet monitoring and repositioning system is located in three racks (GYPOS01-03) today installed in UJ56 level 1. The failure of the system would prevent for further adjustment of the inner triplets. GYPOS01 hosts the sensor data acquisition modules (SAS) for both triplets and electronics cards for temperature measurements while GYPOS02-03 host the motor electronics for remote positioning system of both triplets (one rack per triplet). The three racks will be relocated in UL557 bypass taking into account the maximum length of 270 m for the cables powering the motors and the sensors data acquisition. One of the GGPSO reference positions located in UL557 bypass will be hidden by one of the racks to be relocated in that area. To ensure the continuity between the different survey reference points, the survey group will install new reference points in UL557 bypass and in UL56. 1.2.3 ACCESS SYSTEM The five racks YYACS01-05 located in UJ56 level 1 are dedicated to the access system. Only one of them, the YYACS05 rack, contains sensitive electronics. It ensures the control and the management of all the underground doors. Its failure would lead to the misbehavior of the control of all the underground sector doors. This rack will be relocated in USC55 level 2 machine area (see Figure 7). 1.2.4 CRYOGENICS PROFIBUS EQUIPMENT Three racks QYC01-03 located in UJ56 level 1 are dedicated to the cryogenics instrumentation. The QYC01 and 03 racks contain ‘profibus crates’ which are sensitive to radiation field. A failure of these crates could severely degrade the cryogenic operation requiring a beam dump to provide access for reparation. The 2 racks will be relocated in UL557 bypass (see Figure 6). LHC Project Document No. LHC-LJ-ECPage 5 of 20 Figure 1: Point 5 general area layout. Figure 2: Point 5 general area view UJ56- UL557 bypass. Figure 3a: Equipment location in UJ56 – level 0 (in red equipment to be relocated). LHC Project Document No. LHC-LJ-ECPage 6 of 20 Figure 3b. Present location of the control cabinet UIA0-00560 in UJ56 – level 0. Figure 4:. Equipment to be removed from UJ56 – level 1 (inside blue thick borders). Figure 5: Overall view of UJ56-UJL557 bypass area after equipment relocation. LHC Project Document No. LHC-LJ-ECPage 7 of 20 Figure 6: UL557 bypass after equipment relocation. Figure 7: USC55 machine area after equipment relocation. 1.2.5 QUENCH PROTECTION SYSTEM (QPS) AND ENERGY EXTRACTION The racks DYPG01-02 located in UJ56 level 1 host the electronics dedicated to the protection of the inner triplets and correctors. Their failures may lead to the transmission of corrupted data, to the loss of communication and supervision of the LHC Project Document No. LHC-LJ-ECPage 8 of 20 QPS system. Even, if all the protection systems are fully redundant it has been decided to relocate these 2 racks. The QPS systems cannot be moved to the surface as their maximum distance to the corresponding DFB is restricted to about 100 m. The 2 racks will thus be relocated in UL557 bypass taking into account these 100 m (see Figure 6). With increasing length of the quench heater power cable from the DQHDS heater power supplies to the DFBX a larger part of the available energy (2.9 KJ per supply) will be deposited in the cable. That means less energy will be deposited in the triplet magnet heater. Calculations estimate that with the present configuration 33% of the energy is deposited in the cable and 67% in the magnet heaters. With the new length of cables, 43% of the energy will go in the cable and thus only 57 % in the magnet heaters. Taking these numbers into consideration the experts concluded that the functionality of the system will be ensured with the 2 racks in their new location. 1.2.6 FIRE AND ODH DETECTION EQUIPMENT The relocation of this equipment has been treated in a dedicated ECR [4]. In view of the amount of material that will be relocated in UL557 bypass, it has been decided to install new fire detection pipe to protect UP56, TU56 and UJL557 bypass areas. 1.2.7 CONTROL EQUIPMENT Collimators control: The racks TYCFL01 and TYCCR01 located in UJ56 level 1 are dedicated to the control of the collimators. Their failure will lead to the requirement of a beam dump. This control system is linked to the Beam Interlock System (BIS), to the remote reset rack and to the LHC timing. The system can be relocated up to 200 m from its present location due to cables length limitation for sensor and stepper motor driver. The two racks will be relocated in USC55 in the machine area (see Figure 7). The rack TYCFL01 will be renamed TYCFL02 while the TYCCR01 crates will be merged inside the already existing TYCCR01 rack. Power Interlock Controller (PIC): The complete protection system for the inner triplet R5 and the two PLCs controlling the remote I/Os for the matching section and the long arc cryostat (themselves installed in RR57) are currently installed in the rack CYCIP01 in level 1 of UJ56. The main clients connected to the system are the LHC quench protection system (QPS) and the power converters. In addition the system receives interlock signals from the cryogenics, the UPS and AUG and is sending beam dump requests to the Beam Interlock System (BIS). Any failure in the magnet powering infrastructure or the interlock system itself will lead to an interlock to the LHC power converters and for most circuits to a dump of both particle beams. The PLCs can be separated from the remote I/Os through a Profibus link up to ~ 1km, while the I/Os shall remain close to the QPS and power converters to keep the local controls cabling reasonably short. All systems currently installed in level 1 of UJ56 will be relocated into UL557 bypass, close to the QPS racks (DYPG01/02) and the power converters powering the inner triplet R5 (see Figure 6). Beam Interlock Controller (BIS): one Beam Interlock Controller (BIC) is located in the CYCIB01 rack in UJ56 level 1. The connected user systems are: Vacuum, Collimation, PIC, FMCM and both CMS and TOTEM experiences. Each user system delivers via a dedicated interface (CIBU) its own local permit for beam operation. Any failure of the system will lead to a beam dump and will block further beam operations. In addition to the BIC, the CYCIB01 rack contains another machine interlock system: the ‘Fast Magnet current Change Monitor’ (FMCM) unit attached to the RD1.LR5 circuit. The full rack will be relocated in USC55 machine area (see Figure 7). To ensure the functionality of the BIS in its new location the following constraints will have to be filled: - the extended cable length must stay below 1200 m, LHC Project Document No. LHC-LJ-ECPage 9 of 20 - the cables extension and optical fibers installations will have to be performed with a very special care as these cables transmit the beams ‘user permit’. A non high quality extension may lead to non requested beam dumps, - Ethernet connections available in the rack; - UPS network available in the rack. Current lead heaters: The rack DYXF01 located in UJ56 level 1 contains the control equipment of the current lead heaters providing the temperature regulation of the top part of the current lead. Their failure will stop their heating function and possibly lead to a non start of the power converters at the restarting of the LHC machine. It has been decided to relocate the rack in USC55 machine area (see Figure 7). Timing and remote reset: there are two racks located in UJ56 level 1 hosting, respectively, the timing (rack CYTIM01) and the remote reset (rack CYFRE01) systems. Each system consists into a 3 units crate and manages the timing and remote reset distribution for the front-end controls. A failure of the timing system would induce a beam dump due to the lack of timing distribution for the equipment related to the beam control. The two racks will be relocated in UL557 bypass where their user agents will be relocated (see Figure 6). The distance between their present and future locations should be as short as possible. Network: The racks CYNET01 and CYNET02 located in UJ56 level 1 are the network star-points for UJ56. They provide the Technical Network (TN) and Global Purpose Network (GPN) to the equipment installed in UJ56. Their failure will affect all the users in the area. As a consequence it has been suggested to relocate these two racks. It has been decided to merge them into one rack. The maximum distance between the ‘star-point’ (i.e. the rack) and the Ethernet plugs installed all around (i.e. the users) is 90 m. This drives the location at which the new rack CYNET01 can be displaced. It will be installed in UL557 bypass where the major part of the users will be relocated (see Figure 6). Optical fibers: the rack CYFIB01 installed in UJ56 level 1 is the star-point for the UJ56. It will not suffer from SEE as it consists of passive elements. However, new racks CYFIB01 will have to be installed in UL557 bypass and UCS55 machine area to ensure the dispatch towards the users that will be relocated in these areas. WorldFip repeaters: Cryogenics and power converters are the only users of the worldfip repeaters located in UJ56. The ten corresponding units are hosted in the CYFRE01 rack in UJ56 level 1. A failure of one repeater unit implies that the associated equipment cannot respond anymore. The four units dedicated to the cryogenics are optical fibers /Cu type while the six units dedicated to power converters are Cu/Cu type. Following the irradiation test results for both types of repeaters it has been decided to relocate in UL557 bypass in the rack CYFRE01 only the worldfip repeaters units dedicated to cryogenics (see Figure 6). 1.2.8 ELECTRICAL EQUIPMENT Uninterruptible Power Supply (UPS): there are two UPS systems (cabinets EBS1/56, EBS11/56 and ESS12/56) located in UJ56 level 0. They power machine equipment via the associated racks/switchboards installed in UJ56, USC55 (machine area) and RR53/57. The UPS modules are purchased as complete units. They contain electronics to control voltage and current, and switches between battery powered units and the main supply. The two UPS with their associated distribution switchboards (EOD) may suffer from SEU. A failure of the UPS could lead to a total loss of electrical power delivered to the users (see Table 2). In particular it could lead to the loss of the vacuum system, the quench detection, the radiofrequency equipment, the beam monitoring and the supervision system. It has thus been decided to relocate the UPS modules in UL557 bypass (see Figure 6, units EBS11/56, EJG11/56, EBS12/56, EJG12/56, EOD1/56, EOD3/56). LHC Project Document No. LHC-LJ-ECPage 10 of 20 Electrical services dedicated to the personal safety for Point 5: they are installed in the safe room located in UJ56 level 0 (see Figure 3). - General emergency stop ‘AUG’ system (EYU01 rack): its misbehaviour could generate false safety alarms and power-off the electrical network. It will be relocated in UL557 bypass in a ‘mini safe-room’. - The Electrical Network Monitoring system (EYC01/02/03 racks): the three racks host PLCs and industrial data acquisition units that are sensitive to SEE. Their misbehaviour would corrupt the information on the status of the network and could generate false alarms. They will be relocated in the UL557 bypass. Following discussion with the Safety, they will be relocated outside the mini safe room. - 48 V dc system (ECD, ECG, ESU): it contains electronics that may be sensitive to SEE. Its misbehaviour would lead to the power-off of EL safety equipment, 18 KV loop, EYC and AUG racks. In particular the ambient and Safety lightning in UJ and the tunnel will be lost. To reduce the amount of equipment to be relocated in the UL557 mini safe room, it was decided to feed directly the Safety lightning system with 230 Vac through an UPS system located in surface. The 48V dc chargers will be moved into UL557 bypass mini safe room in order to simplify the cabling and to be able to replace them (if needed) by new ones (estimated more sensible to radiation effects). These relocations have been validated by Safety. The new electrical layout is available in [6]. Table 3 presents the electrical equipment to be installed in UL557 after the relocation process. Table 2. UPS users. Distribution switch board User EOD103/56 EOK103/56 distribution busbar EOD104/56 EOK104/56 distribution busbar EOD105/56 EOK105/56 distribution busbar EOD106/56 EOK106/56 distribution busbar EOD107/56 EOD1/53 distribution busbar EOD108/56 EOD1/57 power supply EOD109/56 Power supply 1 FORCE F3 R561-R562-R571-R572-R58 EOD110/56 Power supply 2 FORCE F3 R561-R562-R571-R572-R58 EOD111/56 Power supply 1 FORCE F3 R531-R52 EOD112/56 Supply 2 FORCE F3 R52 EOD113/56 RESERVE EOD114/56 Power supply EOJ9/55 USC55 EOD115/56 RESERVE EOD116/56 Power supply RACK RYCA01-02 EOD117/56 RESERVE EOD118/56 Power supply RACK CYNET01=UJ56 EOD119/56 Power supply RACK CYNET02=UJ56 EOD302/56 Power supply COFFRETS F3 NEW QPS R52 EOD303/56 Power supply COFFRETS F3 NEW QPS USC55-RR53 EOD304/56 Power supply COFFRETS F4 NEW QPS R58 EOD305/56 Power supply COFFRETS F4 NEW QPS RR57 EOD306/56 Power supply RACK DYPG01 EOD307/56 Power supply RACK DYPG02 EOD308/56 RESERVE EOD309/56 Power supply CYCIB01=UJ56 LHC Project Document No. LHC-LJ-ECPage 11 of 20 Table 3. Electrical equipment in UL557 after its relocation from UJ56. Equipment reference in UL557 (after relocation) EBD10/56 (new) EBS11-12/56 ECD1-2/56 ECG1-2/56 EJG11-12/56 EOD3/56 ERD1/56 ESD4/56 (new) ESU1-2/56 EYC04-07/56 EYU02/56 (new) Equipment reference in UJ56 (before relocation) EBS11-12/56 ECD1-2/56 ECG101-201/56 EJG11-12/56 EOD3/56 ERD1/56 ESU304 EYC01-03/56 Function Low voltage switchboard UPS cabinet 48 V dc commutation 48 V dc batteries UPS batteries UPS distribution switchboard Power converters switchboard Diesel switchboard 48 V dc chargers EL monitoring controllers AUG system Relocation in UL557 outside mini safe room outside mini safe room in mini safe room in mini safe room outside mini safe room outside mini safe room outside mini safe room in mini safe room in mini safe room outside mini safe room in mini safe room Location in UJ56 (present) UJ56- level 0 UJ56- level 0- safe room UJ56- level 0- safe room UJ56- level 0 UJ56- level 0 UJ56- level 0 UJ56- level 0- safe room UJ56- level 0 -safe room 1.2.9 CV EQUIPMENT The control cubicle UIA0-00560 manages the air ventilation units of UJ56 and will manage in the future those of UL557 bypass. It consists of one process PLC and one PLC concentrator. The process PLC collects the information, the measurements, the status of the ventilation in UJ56, RR53, RR57 and delivers alarm to CCC. The PLC concentrator linked to Ethernet is connected by profibus to the process PLC. A failure of the PLCs may lead to the loss of the ventilation alarm in the CCC, to the absence of ventilation supervision in the UJ56, RR53 and RR57. The ventilation may be in an indefinite state with possibly the overheating of one of the supervised areas. It was decided to displace the PLCs from their present location in UJ56 level 0 to UJL557 bypass (see Figures 3b and 6). 1.2.10 DC CABLING by J.C. Guillaume, H. Thiessen Due to the relocation of the power converters, the DC cables between the converters and the DFBX must be changed with new lengths and sometime new cross sections, mainly for the main quadrupole circuit of the Inner Triplet of LSS5R. The Table 4 gives the new characteristics of the DC circuits with the updated power dissipations of the DC cables. To facilitate their integration the water cooled DC cables of the main quadrupole circuit will be split in two. The 2000 mm 2 water cooled DC cables of the RQX power converter will be realized with two 1000 mm 2 water cooled DC cables in parallel and the 1600 mm2 water cooled DC cables of the RTQX2 power converter will be realized with two 800 mm2 water cooled DC cables in parallel. With this configuration, adapters must be inserted between the water cooled DC cables and the electrical terminals of the DFBX and the power converters. Although the main quadrupole circuit of the Inner Triplet of LSS5L is not concerned by the R2E project, the water cooled DC cables of this circuit will be changed at the same time to increase their cross sections at 2000 mm 2 and 1600 mm2 instead of 1300 mm2 and 1000 mm2. With the present cables, the nominal parameters (nominal currents and nominal didts) of the main quadrupole circuit of the Inner Triplet left of 5 cannot be reached. To avoid this important constraint for the LHC, it is strongly recommended to replace these DC cables. The Table 5 gives the new characteristics of the DC circuits of the main quadrupoles of the Inner Triplet left of 5. As for the Inner Triplet right of 5, the water cooled DC cables of the main quadrupole circuit of the Inner Triplet Left of 5 will be split in two. LHC Project Document No. LHC-LJ-ECPage 12 of 20 Table 4. DC circuit characteristics of the IT.R5. Section rau 40oC Resistance Vcable_ult Vmagnet Vtotal_ult Pcables_ult Pcables_ult [H] [A/s] [V] [A] [A] [m] [mm2] [Ohm.mm2/m] [Ohm] [V] [V] [V] [Wair] [Ww ater] RCOX3.R5 0.004 1 0.1 100 110 150 35 0.019 0.081 8.91 0.004 9.12 981 0 RCOSX3.R5 0.003 1 0.1 100 110 150 35 0.019 0.081 8.91 0.003 9.12 981 0 RCSX3.R5 0.005 0.5 0.1 100 100 150 35 0.019 0.081 8.10 0.003 8.31 810 0 RCSSX3.R5 0.008 1 0.1 100 110 150 35 0.019 0.081 8.91 0.008 9.12 981 0 RCTX3.R5 0.029 1 0.1 80 86 150 35 0.019 0.081 6.97 0.029 7.20 599 0 RTQX1.R5 0.09 19.333 0.12 550 600 150 240 0.019 0.012 7.09 1.740 9.07 4255 0 RCBXH3.R5 0.287 5 0.12 550 600 150 240 0.019 0.012 7.09 1.435 8.77 4255 0 RCBXH2.R5 0.287 5 0.12 550 600 150 240 0.019 0.012 7.09 1.435 8.77 4255 0 RCBXV3.R5 0.175 5 0.12 550 600 150 240 0.019 0.012 7.09 0.875 8.21 4255 0 RCBXH1.R5 0.287 10 0.12 550 600 150 400 0.019 0.007 4.25 2.870 7.36 2553 0 RCBXV1.R5 0.175 10 0.12 550 600 150 240 0.019 0.012 7.09 1.750 9.08 4255 0 RCBXV2.R5 0.175 5 0.12 550 600 150 240 0.019 0.012 7.09 0.875 8.21 4255 0 RQSX3.R5 0.014 5 0.12 550 600 150 240 0.019 0.012 7.09 0.070 7.40 4255 0 RQX.R5 0.218 6 0.12 6800 7180 75 2000 0.019 0.001 5.09 1.642 6.97 0 36557 RTQX2.R5 0.038 8.777 0.12 4600 4780 80 1600 0.019 0.001 4.52 0.562 5.32 0 21603 CIRCUIT NAME L TOT MAX DI DT U LEADS I NOMINAL I ULTIMATE Long cables Table 5. DC circuit characteristics of the main quadrupole IT.L5. CIRCUIT NAME L TOT MAX DI DT U LEADS I NOMINAL I ULTIMATE Long cables Section [H] [A/s] [V] [A] [A] [m] RQX.L5 0.218 6 0.12 6800 7180 RTQX2.L5 0.038 8.777 0.12 4600 4780 rau 40oC Rcable Vcable_ult Vmagnet Vtotal_ult Pcables_ult Pcables_ult [mm2] [Ohm.mm2/m] [Ohm] [V] [V] [V] [Wair] [Ww ater] 75.00 2000 0.019 0.001 5.09 1.642 6.97 0 56242 75.00 1600 0.019 0.001 4.24 0.562 5.04 0 32405 1.2.11 OVERVIEW OF THE EQUIPMENT TODAY IN UJ56 Tables 6a and 7b present the equipments today installed, respectively, in UJ56 level 0 and UJ56 level 1. They indicate in red the equipment that will remain in its present location, in green the equipment to be relocated in UL557 or USC55 and in purple the equipment to be removed / dismantled as it will not be used anymore after LS1. LHC Project Document No. LHC-LJ-ECPage 13 of 20 Table 6a. Equipment today located in UJ56 level 0. Equipment UIAN -00503 UIAO-00560 water pumps BRAN area - gaz control anti-panic lightning unit ODH detectors, sirens fire detectors mobile shielding control RAMSES detector LACS control boxe (YJBC01=UJ56-0) SAREP -0026 (previously CAR101UJ56) SAREP-0025 (previously CBR101UJ56) CTRIO1UJ56 CTER-00540 CYRR01 EAD1-2/56 EBD1-2/56 EBS1/56 * EBS11-12/56 ECD1-2/56 ECG101-201/56 EJG11-12/56 EMD1/56 EMT103/56 EOD1/56 EOD3/56 EOX01/56 ERD1/56 ESD1-3/56* ESU303-304*/56 EYP01/56 EYC01-02-03/56 EYB01/56 Function To be relocated within R2E Equipment owner Contact person raw water pumps control air ventilation control no yes no no no no no yes no no yes no no no no no no no to be removed (no more used) yes yes yes yes no no no yes yes yes to be removed (no more used) no/yes no yes no EN/CV EN/CV EN/CV BE/BI EN/EL GS/ASE GS/ASE GS/ASE EN/HE DGS/RP GS/ASE GS/ASE/AS GS/ASE/AS IT/CS GS/ASE/AS IT/CS EN/EL EN/EL EN/EL EN/EL EN/EL EN/EL EN/EL EN/EL EN/EL EN/EL EN/EL EN/EL EN/EL EN/EL EN/EL EN/EL EN/EL EN/EL P. Valente P. Valente P. Valente E. Bravin N. Dos Santos S. Grau S. Grau S. Grau J. P. Granchelli A. Day R. Nunes S. Grau S. Grau F. Chapron S. Grau F. Chapron J.C. Guillaume/N. Dos Santos J.C. Guillaume/N. Dos Santos J.C. Guillaume/N. Dos Santos J.C. Guillaume/N. Dos Santos J.C. Guillaume/N. Dos Santos J.C. Guillaume/N. Dos Santos J.C. Guillaume/N. Dos Santos J.C. Guillaume/N. Dos Santos J.C. Guillaume/N. Dos Santos J.C. Guillaume/N. Dos Santos J.C. Guillaume/N. Dos Santos J.C. Guillaume/N. Dos Santos J.C. Guillaume/N. Dos Santos J.C. Guillaume/N. Dos Santos J.C. Guillaume/N. Dos Santos J.C. Guillaume/N. Dos Santos J.C. Guillaume/N. Dos Santos J.C. Guillaume/N. Dos Santos safety safety safety safety safety access transmission alarms levels 2 & 3 transmission alarms levels 2 & 3 phone red phone GSM probe emergency lightning GS switch board UPS cabinets UPS cabinets 48 V dc commutation 48 V batteries UPS batteries HV switchboard HT transformer UPS distribution switch board UPS distribution switch board PIC alarm box power converters switchboard Diesel switchboard 48 V dc chargers emergency lightning EL monitoring controllers LV switchboard protections (*) Equipment to be removed / dismounted. Table 6b. Equipment today located in UJ56 level 1. Equipment ODH detectors siren AUG anti-panic lightning UTA WorldFIP boxes BY01 CYCIP01 CYCIB01 GYPOS01-02-03 YYASC01-02-03-04-05 QYC01-02-03 CYFIB01 CYNET01-02 CYTIM01 CYFRE01 DYPG01-02 DYXF01 TYCFL01 TYCCR01 RQX.R5 RTQX2.R5 RYMCB02-03-04-05 RYMCC01 RYCA01-02 RYLC01 RYLB01 RYSC01 RYSA01-02 RYSA03-04 Function To be relocated within R2E Equipment owner Contact person safety safety safety safety ventilation no no no no no no no yes yes yes only YYASC05 QYC01 and QYC03 yes yes yes yes yes yes yes yes yes yes yes yes yes yes yes yes yes to be removed (no more used) GS/ASE GS/ASE EN/EL EN/EL EN/CV BE/CO BE/BI TE/MPE TE/MPE BE/ABP GS/ASE TE/CRG EN/EL IT/CS TE/MPE TE/MPE TE/MPE TE/MPE EN/STI EN/STI TE/EPC TE/EPC TE/EPC TE/EPC TE/EPC TE/EPC TE/EPC TE/EPC TE/EPC TE/EPC S. Grau S. Grau N. Dos Santos N. Dos Santos P. Valente J. Palluel B. Dehning, E. Effinger B.Puccio, I. Romera Ramirez B. Puccio, C. Martin, I. Romera ramirez A. Marin R. Nunes J. F. Bel, B. Ivens A. Gonzalez Puertas J. Shade, M. Da Costa R. Chery R. Chery R. Denz, M. Zerlauth, K. Dahlerup-Petersen R. Mompo A. Masi A. Masi V. Montabonnet, C. Coupat V. Montabonnet, C. Coupat V. Montabonnet, C. Coupat V. Montabonnet, C. Coupat V. Montabonnet, C. Coupat V. Montabonnet, C. Coupat V. Montabonnet, C. Coupat V. Montabonnet, C. Coupat V. Montabonnet, C. Coupat V. Montabonnet, C. Coupat BPM PIC BIC/ FMCM Survey Access/ Safety Cryogenics Fibres Ethernet Timing Remote reset QPS Current leads heaters Collimation Collimation power converters power converters power converters power converters power converters calibration system power converters power converters power converters hot spare power converters spare power converters spare (*) equipment to be removed / dismounted. LHC Project Document No. LHC-LJ-ECPage 14 of 20 1.3 CIVIL ENGINEERING ACTIVITIES To minimise cables length and to provide passageways for new cables and pipe work into UL557 bypass, several ducts will have to be drilled (see Figures 8): - through the UJ56 separating wall between machine (LHC tunnel) and services area: 5 ducts 2 m long with 350 mm diameter; - between UL557 and UL558 (‘mur tympan’): 4 ducts 350 mm diameter for cables and 4 ducts 350 mm diameter for cooling pipes (2 for the ‘mini’ safe room); - between the UJ56 cavern (services area) and the UL557 bypass tunnel: 4 ducts 14 m long with 400 mm diameter. Before the start of these works surrounding equipment (especially those located in UJ56 levels 0 and 1 including the ‘safe room’) will have to be protected. The protection will need to be water-proof as the drilling method will use water. The removal of the excavated material will be via PM56 lift. The base of the UL557 vault will be cut on the external wall (opposite to ‘mur tympan’) along 30 m. Three to five centimeters of concrete will be removed. In order to carry out the drilling activities the Civil Engineering contractor will require a free space of 2 m clearance from the tunnel wall and 1 m additional diameter around each duct to be drilled. The overall time of the drilling/excavation activities is estimated to 15 weeks: - 5 ducts through the UJ56 separating wall: 2 weeks; - 4 ducts between UJ56 and UL557 bypass: 10 weeks; - 8 ducts through the UL557/UL558 separating wall: 2 weeks; - cut the base of the UL557 vault: 1 week. 3D models showing the ducts to be performed are stored in SmarTeam under the reference ST0307981_01 for UJ56, ST0307980_01 for UL557 and ST0057895_01 for UP56. The mini safe room structure construction and fire resistant doors installation will be, respectively, performed under the GS/SE and EN/HE responsibilities. These 2 tasks are estimated to be, respectively, 3 and 2 weeks. Figure 8a: 4 ducts 14 m long to be drilled between UJ56 and UL557 bypass LHC Project Document No. LHC-LJ-ECPage 15 of 20 Figure 8b: 5 ducts to be drilled through UJ56 wall Figure 8c: 8 ducts to be drilled through the UL557/UL558 separating wall (‘mur tympan’). 1.4 SAFETY CONSIDERATIONS IN UJ561 BYPASS Sealing: following the CMS, Safety and Radioprotection requests all openings for cables and pipes performed between UL557 and UL558 will be properly sealed such that they are leak tight, withstand a fire for at least 90 minutes and a blast of 120 mbar overpressure. In order to preserve the current fire and ventilation compartmentalisations, both extremities of each hole will be sealed with 80 mm thick plates made of mineral wool and with external faces covered by a layer of fire-resistant paint. In addition, the cables will be painted with the fire-resistant paint at the position where they exit of the plates. Relocation of ‘tablotins’: the relocation of equipment in the UL557 bypass will interfere with two ‘tablotins- safety organs’ today installed in the bypass (see Figure 2). The ‘tablotin T1’ consists of AUG push button, siren, emergency lightning and fire extinguisher. The ‘tablotin T2’ consists of AUG push button, siren (with ‘bris de glace’), emergency lightning and fire extinguisher. For T2 the siren will not have to be moved as it will not interfere with equipment. The Safety (DGS/SEE) agreed to relocate the 2 ‘tablotins’ T1 and T2. These relocations are technically feasible (studies performed by GS/ASE and EN/EL). T1 will be relocated on the other side of the bypass while T2 will be translated 2 meters away from its current position (see Figure 5). LHC Project Document No. LHC-LJ-ECPage 16 of 20 UL557 – bypass framework load resistance: it is proposed to install on the UL557 framework the cooling pipes and part of the cables for the equipment to be relocated in the UL557 bypass (see Photo 1 and Figure 9). They correspond to an additional weight on the framework of 1t/m. GS/SE studied the impact of this additional load on the framework and concluded that the framework will support it [7]. Mini ‘safe room’: Racks today located in the UJ56 ‘safe room’ will be relocated in UL557. After discussion with Safety colleagues, the equipment owners decided for safety reasons to relocate part of these racks in a 2 hours fire resistant structure called ‘mini safe room’ (see Tables 6). A dedicated ‘mini safe room’ will thus be built in UL557 (see Figure 6). The height of the racks to be installed inside the ‘mini safe room’ will be limited to 1.80m (instead of the usual 2.20m) due to the presence of cable trays already installed along the UL557/UL558 separating wall. Fire detection: see paragraph 1.2.6. Photo 1. Framework along UL557 bypass- present situation Figure 9. Cross section of UL557 bypass after equipement relocation LHC Project Document No. LHC-LJ-ECPage 17 of 20 Sector door: to minimize the length of the water cooled cables, the power converters will be relocated at the present location of the YCPS01=UJ561 sector door. As a consequence this door will be displaced 10 m away into UL56 behind the ventilation/blast door. In its new location the sector door will allow the full aperture of the blast door and will be compatible with the passage of the TIM. GS/ASE and the machine DSO agreed with this displacement taking into account that R2E will ensure the arrival of the cables to the new sector door location. Transport volume: in their new location in UL557, the power converters calibration racks (RYCA01/02) will interfere with the transport volume by 30 cm. It is agreed between EN/HE and TE/EPC colleagues that EN/HE will inform TE/EPC about each heavy transport requiring the 2 racks to be pivoted to free the transport volume. The rotation of the calibration racks will be performed by TE/EPC. It will take half a day. If heavy transport convoy breaks down in UL557 (between the mini safe room and the power converters areas), EN/HE foresees a non standard recovery method with a mechanical jack with cradle (device called ‘recovery’) [8]. Once all equipment will be relocated in UL557, a transport test (with a wooden mock-up) will be carried out by EN/HE in the UL557 bypass. 1.5 INSTALLATION PHASES The equipment relocation is scheduled for LS1. The activities sequences with the coactivities are today defined. The overall implementation to be carried-out during LS1 is estimated to 57 weeks (14 months) [9]. Table 7 gives a summary of the teams involved with their estimations of the duration of their respective activities. During the 2011-2012 winter shutdown, UPS and PIC were relocated. Preparatory work for BIC relocation and part of the civil engineering activities were also anticipated. All remaining preparatory work than can be anticipated will be performed during the 2012 technical stops (e.g., cables trays installation). The integration layouts changes linked to the R2E relocations were discussed within the ICL. They are today approved throughout the ICL by the equipment owners and the services (see Table 8). All the installation drawings will be verified by the corresponding CERN services, in particular by EN/CV, EN/EL and GS/SE to ensure their conformity with the 3D LHC integration models. They will be circulated amongst the services teams and the LHC integration team (EN/MEF-INT). During LS1, survey scans of the areas will be performed at the end of each major service installation/intervention. A follow-up of the installation non-conformities will be performed by the EN/MEF-INT team. In case of a critical non conformity, the equipment not installed in its nominal location will be removed and then reinstalled following the installation drawings. LHC Project Document No. LHC-LJ-ECPage 18 of 20 Table 7: Teams involved into the R2E relocations activities in Point 5 with the estimated duration of their respective activities (as provided by the responsible groups). Group BE/ABP BE/CO EN/CV EN/EL EN/HE EN/STI GS/ASE GS/SE-CE IT/CS TE/CRG TE/EPC TE/MPE Equipment / activity survey equipment timing & remote reset WorldFip pipes/ducts UTAs equipment relocation, cabling & optical fibers equipment transport collimator control equipment fire/ODH detection access drill/dig activities mini safe room Ethernet cryogenics equipment power converters QPS* PIC* current leads heaters BIS Duration [weeks] 3 <1 1 19 6 27 (2 shifts/day) 2 5 5 6 9 (2 shifts/day) 4 3 4 7 1 <1 3 <1 *activities performed outside the LHC hardware commissioning Table 8: EDMS references of the LHC integration models taking into account the relocations to be carried out within the R2E Mitigation Project. Location EDMS reference UJ53 UJ56 UJ57 UP56/UL557/UL558 UL54 UL56 USC55 (machine side) RR53 RR57 1143900 1102744 / 1145767 1143908 1143676 1143902 1143904 1143911 1143898 1143910 LHC Project Document No. LHC-LJ-ECPage 19 of 20 2. REASONS FOR CHANGE by AL Perrot Reduce the risk of misbehaviour due to SEE of the equipment located in UJ56 that may lead to stop of the LHC machine or jeopardize its correct operation. 3. IMPACT ON COST, SCHEDULE & PERFORMANCE by AL Perrot The total cost for the relocation activities is estimated to 3175 KCHF (see Table 9). These relocations are discussed with the LHC integration team (EN/MEF-LE), the services and the equipment owners. The new integration layouts are approved through LHC Integration Committee (ICL). The relocation activities are scheduled by the LHC planning officers (EN/MEF-OSS). The present estimate of the hadron flux in UJ56 indicates that SEE may be a limitation for LHC operation. The modifications proposed would allow for a safer operation and a decrease of the machine down-time. Table 9: Cost estimate corresponding to the R2E relocation activities in Point 5 (as provided by the responsible group, rounded up to 5 KCHF). Equipment /service EL Cooling / Ventilation Civil engineering Fire detection Sector doors YCPS01=UJ561 Access rack Transport Network Survey Activity control cabling for electrical distribution low voltage optical fibers DC and control cables installation UTAs, cooling pipes installation drilling activities safe room UJ56/RR53/RR57 smoke detectors relocation UJ561 new smoke detectors displacement displacement relocation of equipment structure cabling, wifi 1 rack VDSL cabling GGPSO installation reference marks Cryogenics Collimation control QPS False floor on the bypass framework Metallic structure for UPS Power converters ('gerbeur') Group Contact Total cost [KCHF] EN/EL EN/EL EN/EL EN/EL EN/CV GS/SE J C Guillaume N. dos Santos A. Gonzalez Puertas J C Guillaume, N. dos Santos P Valente J Osborne GS/ASE S Grau 75 410 100 1420 420 265 85 100 10 45 50 20 40 5 GS/ASE, EN/HE GS/ASE EN/HE IT/CS R Nunes, A. Foreste R Nunes C. Bertone M. Da Costa EN/EL BE/ABP J. C. Guillaume A. Marin TE/CRG EN/STI TE/MPE GS/SE B.Ivens, J. F. Bel A. Massi, J. Lendaro R. Denz D. Parchet TE/EPC C. Coupat 5 5 50 35 10 15 5 5 TOTAL [KCHF] 4. IMPACT ON OTHER ITEMS 3175 by A L Perrot See paragraph 1.2. 5. CHANGE CLASS by Project Engineer 6. COMMENTS (COMPULSORY) by Project Engineer 7. COMMENTS (IF REQUIRED) by other Project Engineers LHC Project Document No. LHC-LJ-ECPage 20 of 20 8. COMMENTS (IF ANY) by PLO appropriate Committees 9. REFERENCES [1] [2] [3] [4] [5] [6] [7] [8] [9] ‘R2E FLUKA studies for Point 1 and Point 5’, R. Versaci & al, ATS/Note/2010-046, October 2010; ‘Residual dose maps, air activation and prompt dose in the adjacent tunnel at IR5’, M. Fuerstner &al, CERN-DG-2009-057-RP-TN, edms: 1006918; ‘Strategy against SEE for Fire and Oxygen deficiency detection systems’, S. Grau & A. L. Perrot, Feb. 2011, edms: 1126688, LHC-LJ-EC-0023 v.0.1; https://edms.cern.ch/nav/P:CERN-0000083951:V0/P:CERN-0000091190:V0/TAB3 www.cern.ch/h4irrad ‘Proposition d'implantation et distribution des équipements EN-EL en UL55 et TZ76, dans le cadre des déplacements des équipements liés au projet R2E’, N. Dos Santos, April 2012, edms: 1210200 v.1, ELG-LVNET-EN-0179 v.1; Private discussions and calculations performed by D. Parchet (GS/SE), January 2011. Discussion in ICL no. 2011-324, 9th March 2011. Work by M. Barberan and K. Foraz (EN/MEF-OSS), November 2011: https://espace.cern.ch/MEFactivitiesforR2E/Planning_Documents/Forms/AllItems.aspx