Infrastructure Division

advertisement
Galliford Try Plc
Group Structure
Galliford Try Plc
INFRASTRUCTURE DIVISION
David Bevan
Managing Director
Infrastructure Division
Civil Engineering
Scotland & International
Divisional Projects
Civil Engineering
England & Wales
Water
Specialist Services
Galliford Try Plc
DIVISIONAL PROJECTS
Divisional Projects
M40/J15
(Long Bridge)
Bypass
Forth Replacement
Crossing
A45/A46
Toll Bar End
M74 Extension
South Devon Link Road
(A380 Kingskerswell Bypass)
Galliford Try Plc
South Devon Link Road (A380 Kingskerswell Bypass)
Galliford Try Plc
Detailed Design
May – June:
Designer mobilisation (currently 60nr within design team)
June - July (Aug):
Design Workshops : Prepare Options : Optimisation Decisions
July 2012 - Apr 2013:
Completion of the Detailed Design :
 Technical Approval Process (DCC / TC / Third Party Approvals)
 Third Party Approvals : Utility companies / NR / EA / NE /
planning depts. / etc.
Galliford Try Plc
Construction Planning/Programming
• Mobilising the Construction Team (key positions from within and
external recruitment)
• Developing the Construction Programme (in conjunction with the
developing detailed design and consultations with third parties)
• Engage with Key Specialist Suppliers (who are integrated in the
design process) eg. PC Concrete Beams / PC Conrete Culverts /
Reinforced Earth Retaining Walls / Structural Steel / Specialist SubContractors – piling - / etc
Galliford Try Plc
Construction
Intention is to harness local supply chain where appropriate
To date:
Staff: 50% recruited locally (expected to recruit
70/80%
of remaining staff locally)
Engineering surveyors:
4D CES, Plymouth
Site Clearance:
KJ Thornburn Paignton / Newton Abbot
Future Opportunities
Earthworks & Drainage
Galliford Try Plc
Programme
October 2012 – March 2013
•
Complete the detailed design and approvals
•
Continue with mobilising the construction
team
•
Complete demolitions and site clearance
(trees, hedges, scrub)
•
Commence utility diversion works at Penn
Inn / Addison Road (detailed surveys and
planning currently ongoing)
•
Commence culvert works at Sainsbury, inc
service diversions (mid Jan 2013)
Galliford Try Plc
Programme
Spring / Summer / into Autumn 2013
•
Complete ecological mitigation (reptiles at Edginswell)
•
Commence earthworks :–
- establish haul route through site from the south (cut at Hamlin Way)
- establish working platform at Aller Junction
- commence retaining walls at north end east and west side of existing carriageway
•
Install Culverts and drainage infrastructure (inc temp surface water control measures)
•
Continue / complete retaining walls at north end
•
Establish temp diversion of Yon St
•
Complete Elmcroft Link Road, Churchway Lane Diversion and Access into land opposite
Edginswell Lane
•
Commence Structures :- Penn Inn Ramps (north & south)
- Aller Tunnel
- Aller Road Overbridge
- Aller Cross Underbridge
- Cattle Creep Extension and Extension of Edginswell Overbridge at Hamlin Way
Galliford Try Plc
Programme
2013 - 2014
•
Complete north end (Penn Inn to Barn Owl) by summer 2014 with main flyover complete by
winter 2014
•
Continue with all earthworks, drainage, pavement activities between Aller Junction and Hamlin
Way
2014 - 2015
•
Pending completion of detailed design, approvals and construction planning it is anticipated that
completion will be in advance of December 2015
Download