NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 2186 OF 2013 (Against the order dated 03.01.2013 in Appeal No. 1316/2012 of the State Commission, Haryana, Panchkula) 1. 2. Sr. Supdt. Of Post Offices NIT, Faridabad Shri Babu Ram Postman C/o Sub Post Master Post Office Sector 16-A, Faridabad ....... Petitioners Versus 1. 2. Shri Mahabir Prasad R/o H. No.569, Sector-19, Faridabad At Present : R/o House No.37, Ward No.17 Panchham Mohalla Charkhi Dadri Distt.: Bhiwani, Haryana The Estate Officer HUDA, Sector – 14, Gurgaon …... Respondents BEFORE: HON'BLE MR. JUSTICE V.B. GUPTA, PRESIDING MEMBER HON'BLE MRS. REKHA GUPTA, MEMBER For the Petitioner : Mr. Roshan Lal Goel, Advocate Pronounced on : 4th July, 2013 ORDER REKHA GUPTA Revision Petition No.2186 of 2013 has been filed under section 21 (b) of the Consumer Protection Act, 1986 (short, ‘Act’) against the impugned order/judgment dated 3.1.2013, passed by Haryana State Consumer Disputes Redressal Commission, Panchkula (short, “State Commission”) in First Appeal No.1316/2012. Brief facts of the case are that respondent no.1/complainant had applied for allotment of a residential plot of 6 Marlas in Sector-57, Gurgaon to the Estate Officer, HUDA,Gurgaon, vide application No.11938 registered as G-57, 256681. For further correspondence the address in the application was given as H.No.569, Sector-19, Faridabad of respondent no.1’s son-in-law and he had authorized Shri Manoj Kumar to receive all letters on his behalf from postal authorities. On the draw of lots, the plot of land was not allotted to the respondent no.1. The respondent no.1 came to know that a registered letter containing refund of earnest money of Rs.51,030/- was sent by the respondent no.2 to the respondent no.1 at his given address i.e. H. No.569, Sector-19, Faridabad. However, neither the registered letter was delivered to the authorized person of the respondent no.1, by the postman of the office of the petitioner no.1, nor was it returned to the respondent no.2. The registered letter sent by the respondent no.2 containing refund of earnest money of Rs.51,030/- was marked to one Shri Babu Ram postman on 22.12.2004 who refused to deliver the same to Shri Manoj Kumar, the authorized representative of respondent no.1 and asked the respondent no.1 to collect it from the Post Office, Sector-16-A, Faridabad. It is also mention that even on production of authority letter, the registered letter in question was not delivered to authorized person of the respondent no.1 for some unknown reasons. Shri Manoj Kumar had addressed a complaint letter dated 28.12.2004 to respondent no.1 narrating the entire episode and even after the said complaint, the postman neither delivered the said registered letter to Manoj Kumar, Attorney of Shri Mahabir Parshad, respondent no.1 nor returned the said registered letter to the respondent no.2. The respondent no.1 also wrote a letter to respondent no.1 and the Secretary, Deptt. of Posts, Dak Bhawan, New Delhi. In response to this letter, the Asstt. Director General (PG), Ministry of Communication and I.T., Deptt. of Posts, Dak Bhawan, Sansad Marg, New Delhi vide their letter No.F-No.13-9/05 PG dated 2.9.2005 intimated that the Dealing Assistant of Speed Post Article is responsible for the loss of the said article and the Manager, SPC has been addressed to pay the compensation to the sender and amount of compensation will be recovered from the official at fault in addition to disciplinary action. Respondent no.1 sent an application by registered post on 1.3.2005 to the Estate Officer, HUDA, Gurgaon for refund of the earnest money subsequently reminders were sent on 27.4.2005 and 17.5.2005. The respondent no.2 i.e., Estate Officer, Gurgaon (HUDA) vide his office letter memo No. 13221 dated 18.7.2005 intimated that the refund order No.U-57-032588 for Rs.51,030/- and refund cheque No.32627 has been encashed on 18.1.2005 in the Hongkong and Shanghai Banking Corporation Ltd., Greater Kailash-I, New Delhi. The respondent no.1 had also got served a legal notice to the petitioner no.1 and respondent no.2 through his counsel on 9.7.2005 but yet till date of complaint the grievance of the respondent no.1 had not been redressed. The respondent no.1 wrote a letter to Sr. Supdt. of Police, Sector-12, Faridabad on 25.7.2005 and requested the Police authorities to lodge FIR against the erring person and investigate the case. The petitioners in their written statement before the District Consumer Disputes Redressal Forum, Faridabad (short, ‘District Forum’) took Preliminary Objections that : Under Section 6 of “The Indian Post Office Act, 1898”, the post office is exempted from liability for loss, misdelivery, delay or damage to any postal article in course of transmission by post. The Section 6 of IPO Act, 1898 is reproduced as under: “Exemption from liability for loss, misdelivery, delay or damage : Section-6 exempts Post Office from any liability for loss misdelivery or delay of, or damage to any postal article in course of transmission by post, except as the liability may be undertaken by the Government in express terms. This section is equally applicable to the articles sent by Speed Post for which provisions have been made under Indian Post Office Rules, 1933 by inserting Rule No.66B. These rules were further amended by notification GSR 40 (E) dated 21.1.1999 which inserted the following conditions under condition no.(5) of Rule 66-B -“In case of any delay of domestic speed post article beyond the norms determined by the Department of Posts from time to time, the compensation to be provided shall be equal to composite speed post charge paid. In the event of loss of speed post articles or loss of its contents or damage to the contents compensation shall be double the amount of composite speed post charges paid or Rs.1,000/- whichever is less”. However, the Government shall not incur any liability by reason of loss, misdelivery or delay of or damage to any postal article in course of transmission by post, except in so far as such liability may in express terms be undertaken by the Central Government as hereinafter provided ; and no officer of the Post Office shall incur any liability by reason of any such loss, mis-delivery, delay or damage, unless he has caused the same fraudulently or by his willful act or default. The respondent no.2 had not sent a registered letter but Speed Post article no.EE-907051664IN dated 21.12.2004 booked from Gurgaon and addressed to Shri Mahabir Prasad R/o H. No.569, Sector-19, Faridabad at present R/o H. No.37, Ward No.17, Panchham Mohalla, Charkhi Dadri, Bhiwani. The same was received for delivery on 22.12.2004 at Sector-16A, PO and was entrusted to postman, Shri Babu Ram for delivery on 22.12.2004 & 23.12.2004. Shri Babu Ram postman had doubts whether Shri Mahabir Prasad lived at the given address as Shri Mahabir Prasad did not meet him at the given address. Therefore, on 22.12.2004, the said postman did not deliver the article to Shri Manoj Kumar (other than the addressee) and returned it as undelivered to the concerned P.A. at Sector-16A, P.O. Faridabad. Shri Manoj Kumar visited the Sector-16-A, P.O. Faridabad on 23.12.2004 for taking delivery of the SPP article but he had no authority letter of Shri Mahabir Prasad, therefore, the SPP article 23.12.2004, Shri Babu Ram was postman not went delivered to the to Shri Manoj Kumar said address for on delivery but Shri Manoj Kumar failed to show the authority letter of the addressee as well as produce any witness. The speed post article was not entrusted by Sector-16A, P.O., Faridabad P.A. to the postman for delivery on 24.12.2005 and thereafter as the same was misplaced from the custody of P.A. On receipt of complaint, the said case was enquired into through inspecting officer concerned. The speed post article was lost in custody of the Dealing Assistant on 24.12.2004. The case was sent to SSPOs Gurgaon to pay the compensation to the sender. Letters were written to SSPOs Gurgaon on 17.3.2005, 15.4.2005 and 17.6.2005 vide which they were requested to settle the case by sanctioning the admissible claim to the sender of the article. SSPOs Gurgaon has also written to Administrator, HUDA, Gurgaon for completion of the claim application so that claim may be sanctioned. On receipt of legal notice, the matter was examined and as per the finding SSPOs, Gurgaon was addressed to pay the compensation amount to the sender of the article and intimate the amount of compensation to be recovered from official at fault. In addition, disciplinary action was taken against the official at fault vide SSPOs Faridabad Memo No.CR/DOPG/SP/ Sector-16A dated 30.9.2005/1.10.2005. District Forum vide their order dated 30.7.2012 came to the conclusion that ; “The argument of the counsel that the onus was on the complainant to show as to who got the cheque encashed from HSBC Bank is also untenable because where the speed post article containing the cheque was in custody of dealing assistant of speed post article, the onus was of the official of respondent no.1 to show as to how that cheque was misplaced and how it reached the person who got the cheque encashed. Since the complainant or his son-in-law Manoj Kumar never got possession of speed post article, how the onus can be shifted upon them to show as to how thecheque was encashed and who got it encashed from HSBC Bank. Therefore, respondent remains liable for nondelivery of speed post article to the complainant and it is the result of fraud or atleast default of the dealing assistant of speed post article because of which it reached the wrong hands who got it encashed from HSBC Bank. Respondent no.1 is, therefore, directed to pay the cheque amount of Rs.51,030/- (Rs. Fifty one thousand thirty only) to the complainant with interest @ 9% p.a. from the date of complaint i.e. 8.12.2006, till the date of actual payment and also to pay him Rs.5,000/- towards litigation expenses and mental harassment. A copy of this order be sent to the parties concerned free of costs. File be consigned to the record room.” Aggrieved by the order of the District Forum, petitioners filed an appeal before the State Commission. Vide their order dated 3.1.2013, State Commission observed that ; “In support of his arguments, learned counsel for the appellants-opposite parties referred to Section 6 read with Rule 66-B of the Post Office Act, 1898 which is reproduced as under :The Govt. shall not incur any liability by reasons of loss, misdelivery or delay of or damage to except in so far as such liability may in express terms the undertaken by the Central Govt. as hereinafter provided ; and no officer of the Post Office shall incur any liability by reasons of any such loss, misdelivery, delay or damage, unless he has caused the same fraudulently or by his willful act or default.” We do not find force in the contention raised by the learned counsel for the appellants-opposite parties because from the act and conduct of the opposite parties it is fully established that they were deficient and negligent in non-delivering of the postal article to the complainant. If nobody was available to receive the postal article the opposite parties were bound to send the same to its sender but they failed to perform their duty. In our view the act of the appellants-opposite parties for not delivering the speed post article at its proper destination, is willful act or default on the part of the officials of the appellants-opposite parties. It has to be kept in mind that in view of Section 106 of the Indian Evidence Act, 1872 the burden of proving deliberation about the delivery of the postal article was upon the opposite parties because after handing over the speed post envelope to the opposite party no.1 by the opposite party no.2, the opposite parties are the custodian of the same and by conducting an enquiry about the loss/missing of the postal article, the opposite parties could have submit their explanation but they failed to do so. It is evident on record that the appellants-opposite parties are deficient for the loss of speed post envelope which was containing cheque of Rs.51,030/-. Merely by stating that the liability of the opposite parties is limited to pay compensation as admissible under the rules for loss of article or Rs.1,000/- whichever is less, is not genuine excuse as the opposite parties have tried to absolve themselves from their liability by taking shelter of Section 6 of the Indian Post Office Act, 1989 and the provisions of the Indian Post Office Rules 1933 and Rule 66B of the Post Office Act and as such the deficiency of service of the opposite parties in the instant case is not to be over sighted. As a sequel to our aforesaid discussion, the instant case falls within the mischief of willful act or default on the part of the officials of appellants-opposite parties and as such the impugned order passed by the District Consumer Forum does require any interference. Hence, this appeal is dismissed being devoid of any merit.” Hence the revision petition. Revision petition has been filed with delay of 16 days. For the reasons mentioned in the application for condonation of delay, the delay is condoned. We have heard the learned counsel for the petitioner and gone through the record carefully. The grounds as given in the revision petition are that ; On the face of the record, it is proved that cheque in dispute sent by the respondent no.2 to respondent no.1 through Speed Post/Registered Post has been encashed by someMahabir Prasad R/o Gurgaon from HSBC Bank and a confirmation from the said Bank has been obtained by the petitioner attached with the present petition but surprisingly, respondent no.1 while filing the complaint before the District Forum did not array the HSBC Bank or a man known as Mahabir Prasad R/o Gurgaon in place of respondent no.1, in the absence of the array of HSBC Bank and the same person Mahabir Prasad R/o Gurgaon, the real controversy between the parties to the litigation could not have ben adjudicated upon and this important fact and plea has been ignored by the Courts below which is very much essential for imparting the justice to the parties. In view of the aforesaid submissions, the complaint of the complainant/respondent no.1 was not maintainable and the District Forum ought to have directed the respondent no.1 to array the HSBC Bank and another same person Mahabir Prasad R/o Gurgaon as respondent, neither the respondent no.1 nor the District Forum tried to do so, which is legally fatal itself. One important fact is established that the amount of the cheque in question has not been fraudulently or otherwise, used by the official of the petitioner no.1 or by the petitioner no.2, whereas, there are the possibilities that the cheque in question may have been encashed by the person of the same name respondent no.1 in collusion with the staff of the said Bank. Not only the above, before filing the complaint before the District Forum, it was also required for the respondent no.1 to get the verification from the respondent no.2, i.e., Haryana Urban Development Authority (HUDA) whether the amount in question has been got encashed of the cheque in question or not, this aspect was also not adhered to which clearly shows that gross negligence and nonadherence to the possible and expected measures by the respondent no.1, had the respondent no.1 taken this precaution and had done this exercise to this effect, then there were the firm possibility that the Bank referred to above and the person in the name of the respondent no.1 would have returned the amount in question to the respondent no.1 on being done so by the respondent no.1. Thus, both the impugned orders of Courts below are liable to be set aside. The District Forum correctly came to the following conclusion that there is no dispute that a speed post article No.EE-907051664IN dated 22.12.2004 addressed to MahabirPrasad, respondent no.1 was entrusted to the petitioner no.2, Babu Ram Postman (respondent no.3 before the District Forum) for delivery. But as the addressee did not live at the aforesaid address and no authority letter from the addressee was produced for taking delivery, Babu Ram, petitioner no.2 returned that letter to the dealing Assistant of Speed Post Article. It is clear from the letter dated 2.9.2005 written to the respondent no.1’s son-in-law Manoj Kumar by Asst. Director General, Post Offices. It was further mentioned in the letter that the dealing Assistant of Speed Post Article is responsible for the loss of the said articles and the Manager, SPC has been addressed to pay the compensation to the sender and recover the amount of compensation from the official at fault in addition to disciplinary action. So, it is clear from the letter of an officer of the Dept. of Posts of Government of India that the speed post article containing the cheque of Rs.51,030/- in favour of the respondent no.1 sent by respondent no.2 was not delivered to respondent no.1 or his authorized representative Manoj Kumar but was misplaced by the dealing Asst. of Speed Post Centre or was got encashed by him from HSBC Bank, Greater Kailash – I, New Delhi. Petitioner no.1 is, therefore, responsible for the loss caused to the respondent no.1 but there is no liability of petitioner no.2 Babu Ram because he had admittedly returned the speed post article to the dealing Assistant of Speed Post Article on the evening of 23rd December, 2005. When respondent no.2 had already issued the cheque in favour of the respondent no.1 and that already stands encashed on 18.1.2005 in HSBC Bank, New Delhi, either due to the fault or as a result a conspiracy of official of petitioner no.1, respondent no.2 is also not responsible for payment of any amount to the respondent no.1. The petitioner at this stage based on the advice of Shri Namit Kumar, Advocate dated 5.2.2013, with the view to prove that the person who has got the cheque encashed is the complainant, have obtained a statement dated 31.1.2005 from HSBC Bank, JMD, Gurgaon which indicates that a deposit of Rs.51,030/vide cheque no.032627 was made in the account of Mahabir Prasad, H.No.16, Gali no.4, Arjun Nagar, Gurgaon. With this statement they have sought to prove that the cheque in question had been encashed by Shri MahabirPrasad, respondent no.1 himself. To explain the same, they had pleaded before the District Forum that the article from the Post Office with the conspiracy of the official of respondent no.1 which in this case being the Sr.Superintendent of Post Offices, Faridabad had got the cheque encashed from HSBC Bank. It is noted that this plea was not raised in their reply before the District Forum. On the contrary, they had admitted in their reply that the SPP article had not been delivered and had been misplaced from the custody of PA. On receipt of complaint, the said case was enquired through inspecting officer concerned as the speed post article was lost in custody of the Dealing Assistant. It is indeed strange that after that they are taking a contrary stand that SPP article has been delivered to Shri Mahabir Prasad or as per their case “actually received the article from the post office with conspiracy of the officials of respondent no.1 and had got encashed the cheque” without giving any evidence to support this stand. The Bank statement dated 31.1.2005 was available in December, 2006, when the complaint was instituted with the District Forum and could have been introduced in their reply to the District Forum. It was neither introduced before the District Forum nor the State Commission. It has been relied upon for the revision petition without even making an application for filing of additional documents. As such we are of the opinion that this document cannot be introduced in this manner to adduce the main ground for their revision petition. Further, there is no evidence that the statement pertains to the account of respondent no.1 as the address of Shri Mahabir Prasad given in the Bank statement dated 31.1.2005 is not the same as that given in the complaint dated 8.12.2006. In the complaint, Shri Mahabir Prasad has been shown as at present - resident of House No.37, Ward No.17, Pachham Mohalla,Charkhi Dadri, Bhiwani and also his corresponding address has been shown House No.569, Sector-19, Faridabad and not the address given in the Bank statement which is H.No.16,Gali no.4, Arjun Nagar, Gurgaon. We also find that the respondent no.1 had continued to agitate his case with the Estate Officer, HUDA after 18.1.2005, the alleged date of encashment of the cheque, right upto17.5.2005. It is the Estate Officer, HUDA who vide his letter dated 18.7.2005 had intimated that the refund order No.U-57-032588 for Rs.51,030/- and refund cheque no.32627 has been encashed on 18.1.2005 in the Hongkong and Shanghai Banking Corporation Ltd., Greater Kailash-I, New Delhi. Inspite of the fact that this was mentioned in the complaint that petitioner took no action to verify whether indeed the cheque has been encashed and if so by whom at that stage. Respondent no.1 has also got served a legal notice upon HUDA and the Bank through its counsel on 9.7.2005 and lodged a complaint with Sr. Supdt. of Police on 25.7.2005 requesting the Police Authority to lodged FIR against the erring person and investigate the case. These actions of respondent no.1 do not support the stand of the petitioner that respondent no.1 had already encashed the cheque and deposited the amount in his account on 18.1.2005. 24. In view of the above facts, no jurisdictional or legal error has been shown to us to call for interference in the exercise of powers under Section 21 (b) of Act. Since, two Forabelow have given detailed and reasoned orders which does not call for any interference nor they suffer from any infirmity or erroneous exercise of jurisdiction or material irregularity. Therefore, present petition is hereby, dismissed with cost of Rs.10,000/- (Rupees Ten Thousand only). 25. Petitioners are directed to pay the cost of Rs.5,000/- by way of demand draft in the name of respondent no.1 and remaining cost of Rs.5,000/- by way of demand draft in the name of ‘Consumer Legal Aid Account’ of this Commission within four weeks from today. In case, petitioners fail to deposit the said cost within the prescribed period, then they shall also be liable to pay interest @ 9% p.a., till realization. 27. List on 23.8.2013 for compliance. …………………..………..J (V.B. GUPTA) PRESIDING MEMBER ………..…………..……….. (REKHA GUPTA) MEMBER Sonia/ NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION,NEW DELHI REVISION PETITION NO. 1894 OF 2013 (Against order dated 04.04.2013 in Complaint Case No. 10 of 2011 of the State Consumer Disputes Redressal Commission, Panaji-Goa) Mr. Mario Joseph, Flat S-4, ‘B’ Wing Sansha La Joy Bldg, Opp. Mahindra Cars H. No. 895/38, V Socorro Porvorim – Goa – 403521 Ph. 09820199134 … Petitioner. Versus Mrs. Mary Fernandes, R/o. Sushma Sadan, Parel, Mumbai 400012. ….Respondent BEFORE: HON’BLE MR. JUSTICE V. B. GUPTA, PRESIDING MEMBER HON’BLE MRS. REKHA GUPTA, MEMBER. For the Petitioner : Ms. Indu Malhotra Advocate with Mr. Kush Chaturvedi and Ms. Nishita, Advocates. PRONOUNCED ON: 4th JULY, 2013 ORDER PER MR. JUSTICE V. B. GUPTA, PRESIDING MEMBER In this revision petition there is challenge to order dated 4.4.2013 passed by Consumer Disputes Redressal Commission, Panaji-Goa (for short, ‘State Commission’). 2. Respondent/complainant had filed a complaint under Section 17 of the Consumer Protection Act, 1986(for short, ‘Act’) against Petitioner/O.P. on the ground that respondent has executed a registered sale deed dated 15.09.2008 in favour of the Petitioner in respect of property in question for a consideration of Rs.48 lacs. Since, respondent had incurred certain expenses for the improvement and development of the property for which petitioner has agreed to pay to the respondent a sum of Rs.27 lacs by way of reimbursement. As respondent failed to pay the same, a consumer complaint was filed before the State Commission. 3. Petitioner contested the complaint and filed its written statement. During the proceedings pending before the State Commission, petitioner also filed an application dated 9.11.2012 for cross examination of the respondent stating that at the time of preparing affidavit-in-evidence, petitioner noticed that there were certain facts which have not been stated by the respondent in its complaint. These facts are necessary to be brought on record by way of cross examination to prove the case of the petitioner. 4. That application was dismissed by the State Commission, vide order dated 08.01.2013 observing that “in case the complainant has not brought certain facts on record through his affidavit-in-evidence, the O.P. is always free to do so through their affidavit or their witnesses”. 5. Thereafter, petitioner filed an application dated 20.3.2013, for amendment of the written statement. The plea taken by the petitioner with regard to the amendment of the written statement is that, in view of the order dated 8.1.2013 passed by the State Commission, petitioner wants to bring certain facts on record as per the draft amendment. 6. The State Commission vide impugned order, dismissed the application for amendment. 7. It has been contended by learned counsel for the petitioner that since respondent has not brought on record certain facts, as such petitioner wants to bring those facts on record by way of amendment. It is also contended that amendment of written statement should be liberally allowed in view of the decision of Hon’ble Supreme Court in case Baldev Singh and others Vs. Manohar Singh and another (2006) 6 Supreme Court Cases 498, wherein the Court observed; “In the case of amendment of written statement, the courts are inclined to be more liberal in allowing amendment of the written statement than of plaint and question of prejudice is less likely to operate with same rigour in the former than in the latter case”. 8. Relevant portion of Impugned order passed by State Commission states; “ On perusal of the record and after hearing of the Ld. advocates on behalf of both the parties, we find that the O.P. had filed his written version wayback on 18.5.2012 and thereafter sought adjournments to file affidavit in evidence on 07/09/12, 12/10/2012, 09/11/12, 23/11/12, 14/12/12. The affidavit in evidence was filed on 20/12/12. In between an application for cross examination of the complainant filed on 23.11.2012 was disposed off by order dated 08/01/13. By proposed amendment to the written statement the O.P. seeks to explain as to how the sale deed dated 15.09.2008 between the parties came to be executed. Any explanation whether as regards the initial agreement dated 25.10.06 between the parties or the succession deed dated 29.07.08 or the sale deed dated 15.09.08 could have been given either in the written version filed by the O.P. on 18.5.2012 or the affidavit in evidence filed on 20.12.2012. In fact, even on 07.02.13 a statement was made on behalf of the O.P. that there were no additional documents to be filed. In case it is contended that the explanation sought to be given by virtue of the amendment application now filed has come about with the change of legal advice, it may be noted that there was also change in the advocate on 12.10.12. We find that we are already lagging behind the mandate of Section 13(3A) of C.P. Act. Written submissions have already been filed and the complaint is awaiting the final hearing of oral submissions on behalf of the respective parties. Allowing the amendment application at this stage will simply put the clock back. The application is filed at a very belated stage and will delay the complaint further. In the circumstances, we proceed to dismiss the application for amendment, and fix the complaint for final hearing of arguments on 22.4.2013. 9. There is no dispute about the principle of law laid down by the Apex Court in Baldev Singh (Supra). However, in the present case, petitioner has filed its written statement as far as back as on 18.5.2012 and thereafter its sought adjournments on five occasions to file its affidavit-in-evidence. The amendments which are being sought at this stage pertains to the initial agreement dated 25.10.2006 executed between the parties and sale deed dated 15.09.2008. All these documents were in existence at the time of filing of the written version and were in the knowledge of the petitioner. Petitioner could have easily mentioned about these documents in its written statement which filed in the year 2012. However, there is no explanation in the entire application for amendment as to why petitioner did not mention about these documents in the written statement. As apparent from the record, petitioner itself has been delaying the matter pending before the State Commission. Moreover, the application for amendment has been filed at a very belated stage, that is, when the matter is fixed for hearing of final arguments before the State Commission. 10. Under these circumstances, the State Commission was fully justified in not allowing the application for amendment of written statement at this very belated stage. Accordingly, we do not find any infirmity or illegality in the impugned order passed by the State Commission. There is no merit in the present revision petition and the same is hereby dismissed. 11. No order as to cost. ……..……………………J (V.B. GUPTA) ( PRESIDING MEMBER) ………………………… (REKHA GUPTA) MEMBER SSB/ NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 1291 OF 2013 (Against the order dated 06.03.2013 in FA No.700/2012 & FA No.128 of 2013 of the State Commission, Andhra Pradesh) M/s. Narne Estates Pvt. Ltd., Represented by its Managing Director, 1, Gunrock Enclave, Karakhana, Secunderabad- 500009 ……….Petitioner Versus Sri Dasari Janardhan, S/o Sri Rajaram, R/O:H.No.8-3-234/355, L.N. Nagar, Yasufguda Hyderabad- 500045 Andhra Pradesh .........Respondent BEFORE HON’BLE MR. VINAY KUMAR, PRESIDING MEMBER For the Petitioner : Mr. Bhagabati Prasad Padhy, Advocate PRONOUNCED ON: 4th July, 2013 ORDER PER MR.VINAY KUMAR, PRESIDING MEMBER Both parties to this revision petition had filed two cross appeals before the A P State Consumer Disputes Redressal Commission. complainant/Dasari Janardhan was allowed and the The appeal appeal filed of the by the OP/Narne Estates Pvt. Ltd was dismissed. Both appeals had arisen from an Execution Application filed by the complainant under Section 27 of the Consumer Protection Act before the District Forum, Hyderabad. The District Forum had passed the following order— “In view of the above, both the parties have to comply the orders of the District Forum dt. 12.09.2007, as it attained finality already. Further, the Forum provided adequate opportunity to both the parties. And the parties have now to be clear that to meet the ends of justice, they should adhere to this District Forum order dt. 12.09.2007 scrupulously. In the result, the order of this Forum dt. 12.09.2007 has become final. The complainant complied partly, so directed to comply fully by paying the balance of development charges with interest. Further, the opposite party is directed to comply fully (restoration of plot as directed above) within one month, failing which, punishable with a fine of Rs.10,000/- (Rupees Ten thousand) only.” 2. While considering the two appeals, the State Commission noted that the OP/present revision petitioner had apparently not preferred any appeal against the original order of the District Forum of 12.09.2007 in which the complaint had been allowed directing the OP to collect the developmental charges and restore the allotment of the plot. 3. The appeals filed by the two parties were disposed of by the State Commission with the following orders:“18. In the result, the appeal, F.A No.700 of 2012 is allowed modifying the order of the District Forum. The opposite party is sentenced to three months imprisonment or till it restores the allotment of plot bearing number 21 Sector V, Block Za, East City, Bibinagar in favour of the complainant whichever is earlier. Consequently, the appeal, F.A. No.128 of 2012 is dismissed. The costs of the proceedings quantified at Rs.2,000/-. Time for compliance four weeks.” 4. In view of the fact that the order of 24.7.2012 passed by the District Forum and the order of 6.3.2013 passed by the State Commission have both been passed in Execution Proceedings, the present revision, in effect, should have been filed as an appeal under Section 27 A (1) (b) of the Consumer Protection Act, 1986. The petitioner M/s. Narne Estates Private Ltd. has chosen to file the petition under Section 21 (b) of the Act which is not applicable to the present case. 5. I have carefully considered the records and heard Mr. B.P Padhy, Advocate at length on behalf of the petitioner. Learned counsel agreed during the course of the argument that the present petitioner had not challenged the original order of the District Forum passed on 12.09.2007. He therefore agreed that the same had acquired finality vis-a-vis the revision petition. 6. The petitioner has assailed the observation of the State Commission in para 16 of the impugned order. The contention of Shri Padhy is that it was wrong for the State Commission to observe that the OP had not adduced any evidence to show that the same plot had already been sold to a third party on 4.8.2007 i.e. prior to 12.9.2007, when the District Forum passed the relevant order. 7. In my view, for full appreciation, it is necessary to read para 16 mentioned by the petitioner’s counsel in conjunction with para 15 of the impugned order. These paras read as follows:“15. The opposite party contends that it could not restore allotment of plot since it has sold the plot to third party five years ago. The complainant submits that the opposite party cannot sell the plot during pendency of the complaint before the District Forum and in such case he seeks for refund of the amount paid by him and imposition of penalty to the opposite party to the tune of 10,00,000/- for gross violation of the order of the District Forum and for wasting the time of the District Forum and this Commission by suppressing the fact of sale of the plot to third party. 16. The opposite party has not adduced evidence to show that the plot was sold to third party. The opposite party has not stated the name of the person to whom the plot was sold and on which date as also through which registered sale deed the sale transaction was made in respect of the plot bearing number 21 at Sector V, Bloc Za, East City, Bibinagar. The scope of execution is limited and the District Forum or this Commission cannot go behind the order.” 8. Learned counsel also argued that the matter had been brought to the notice of the District Forum itself, when Execution Application No.88 of 2009 was under consideration. He sought to rely on the fact that in the order of 24.7.2012, the District Forum has mentioned that the OP had agreed to show an alternative plot to the Complainant on 23.3.2012. In my view, this does not amount to saying that the inability of the OP to hand over the original plot to the Complainant on account of the same having already been sold to another person, had been established before the District Forum. Secondly, if the sale of the same plot to another person on 4.8.2007 was actually the case of the OP before the District Forum and the OP felt that its evidence on this point had not been properly appreciated by the District Forum, the OP definitely would have appealed against the order of 12.9.2007. Admittedly, no such appeal was filed. Thirdly, learned counsel Shri B.P.Pardhy was specifically asked to point out what documentary evidence was placed before and rejected/ignored by the District Forum which would have established conclusion of sale in favour of a third party prior to the order of the District Forum. He expressed his inability to point to any such evidence. 9. In view of the details considered above, I find no ground to interfere with the impugned order passed by AP State Consumer Disputes RedressalCommission in Execution Appeal Nos. FA 700 of 2012 and FA 128 of 2013. The petition of M/s. Narne Estates Private Limited, listed as RP No.1291 of 2013, is consequently dismissed for want of merit. .………………Sd/-………… (VINAY KUMAR) PRESIDING MEMBER s./- NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI FIRST APPEAL NO. 88 OF 2013 (Against the order dated 13.12.2012 in Complaint Case No.CC/12/274 of the State Commission, Maharashtra) PDC Marketing Private Limited, A company incorporated under the Provisions of Companies Act, 1956, having its Head office at 12, Esteem Tower, Ambedkar Road, Nashik Road, Nasik 422101, Maharashtra Through its Director Mr. Vijaykumar Chaurasia ……….Appellant Versus Axis Bank Limited, A Company incorporated under the Companies Act 1956, carrying on Banking business under the Banking Regulation Act, 1949, and having its Concerned branch office at Thakkar Bazar, Nashik Maharashtra Through its Manager AND Having it registered office at “Thirshul”, Third Floor, Opp. Samartheshwar Temple, Near Law Garden, Ellisbridge, Ahmedabad 380006, Gujarat .........Respondent BEFORE HON’BLE MR. VINAY KUMAR, PRESIDING MEMBER For the Petitioner : Mr.Dilip Annasaheb Taur, Advocate PRONOUNCED ON: 04th July, 2013 ORDER PER MR.VINAY KUMAR, PRESIDING MEMBER In this appeal, PDC Marketing Ltd. has challenged the order of Maharashtra State Consumer Disputes Redressal Commission in Complaint Case No.CC/12/274. The State Commission has rejected the complaint filed by the appellant/PDC Marketing Limited, holding that the Complainant is not a ‘consumer’ within the meaning of Section 2(1) (d) of the Consumer Protection Act. 2. In paras 3 and 4 of the impugned order the State Commission has noted that the Complainant is a private limited company incorporated under the Companies Act. It is a multi-level marketing company operating from Nashik, marketing different types of goods through its Sales Commission Agents. In order to enable it to make payment of commission on sales to its agents, it had opened a bank account with OP/Axis Bank Ltd. The bank had issued ATM Cards in the name of the complainant company, which were distributed to the Sales Commission Agents. This arrangement enabled the SCAs to withdraw the amount of commission payable to them directly. The bank account and the ATM Cards stood in the name of the company. Under the arrangement, commissionpayment to the agents were towards commercial service rendered by them to the Complainant company. The State Commission, therefore observed that it is not a case of simple banking service but a camouflaged commercial activity was being carried out through this system in which 10060 ATM Cards had been activated by the bank. 3. While dismissing the complaint, the State Commissioner has held that: “5. What we find that the total activity of the complainant-Company is a commercial activity and therefore, though it may be a service, but it is hired for commercial activity of the complainant. Therefore, complainantCompany may have a remedy against the opponent-Bank, but the complainant-Company is not a consumer within definition of Section 2(1) (d) of Consumer Protection Act, 1986 and consumer complaint is not a remedy for the complainant-Company. 6. Learned Counsel appearing for the complainant tried to rely upon judgment of the Apex Court in the matter of Vimalchandra Grover V/s. Bank of India, AIR 2000 SC 2181. That is the case not involving a commercial transaction, but it was an individual account having overdraft facility and in that light banking is a service or not is considered by the Apex Court. There the complainant is a consumer and he was using the account for himself. In the present matter, such is not the position.” 4. Records submitted on behalf of the appellant/PDC Marketing Private Limited have been perused and Mr. D.A. Taur, Advocate has been heard on behalf of the appellant. 5. A copy of the Complaint filed before the State Commission is available on the records of the appeal. From a plain reading of the Complaint itself, the following facts emerge as part of the pleadings of the Complainant are significant and need a special mention. a) In para 1, the complainant claims to be ‘a company incorporated under Companies Act, 1956’. b) As per para 3, it is a ‘multi-level marketing company operating from Nashik’. c) Para 4 calls the account opened with the OP/Axis Bank a ‘current account in the name ‘PDC Marketing Private Ltd’. For operation of this account an agreement was executed between the two sides on 5.12.2008. d) Paras 5 & 6, show that under the agreement of 5.12.2008, 23,200 corporate cards were issued exclusively to allow withdrawal of commission charges of the Complainant’s individual clients. For this total of Rs.4463573/- was paid by the Complainant Company to the OP/bank. 6. The above facts, as seen from the complaint petition itself, clearly show that it is a case of a bank account opened by a business company in furtherance of its commercial business. The operation of the bank account was to be in terms of the agreement of 5.12.2008 between the two parties. 7. Evidently, the cause of action in this case would arise only subsequent to 2008 when the amendment of the relevant provision in the Consumer Protection Act, 1986 had already come into effect on 15.3.2003. The amended Section 2(1) (d) (ii) defines the term ‘consumer’ in the context of hiring of the service (banking service in the present case) in the following terms:“(ii) [hires or avails of] any services for a consideration which has been paid or promised or partly paid and partly promised, or under any system of deferred payment and includes any beneficiary of such services other than the person who [hires or avails of] the services for consideration paid or promised, or partly paid and partly promised, or under any system of deferred payment, when such services are availed of with the approval of the first mentioned person [but does not include a person who avails of such services for any commercial purpose]” 8. The above provision, applied to the facts of this case, clearly shows that the Complainant cannot be treated as ‘consumer’ under the Act. The decision of the State Commission is therefore, clearly based on correct appreciation of the facts and the law. 9. The revision petition, while challenging the order of the State Commission, has sought to rely upon certain decisions of the Hon’ble Supreme Court as well as the National Commission. However, no attempt is made to show how any of these decisions would be applicable to the facts of the present case. It is also noticed that the following decisions clearly belong to the period prior to the amendment of 15.3.2003 to the relevant provision discussed above:“1) Vimal Chandra Grover Vs. Bank of India reported in (2000) 5 SCC 122. 2) Lucknow Development Authority Vs. N.K.Gupta, reported in (1994) 1 SCC 243. 3. Amtrex Ambience Ltd. Vs. Alpha Radios and another, 1996, CPJ, 324 NC 4. Jindal Drilling & Industries Ltd. Vs. R.A.Aggarwal, in OP No.290 of 1997 (citation not given) ” 10. During the course of the arguments, learned counsel also could not throw any additional light on the matter. Therefore, no benefit can accrue to the case of the Complainant from these decisions. The revision is therefore held to be devoid of any merit and is dismissed as such. The order of the Maharashtra State Consumer Disputes Redressal Commission in Complaint Case No.CC/12/274 is confirmed. No orders as to costs. .……………Sd/-…………… (VINAY KUMAR) PRESIDING MEMBER s./- NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI CONSUMER COMPLAINT NO. 155 OF 2013 M/s. Shital Fibres Ltd. A-17, Focal Point Extension, Jalandhar, Punjab … Complainant Versus M/s Bharti Axa General Insurance Co. Ltd. Unit # SFS, 2nd floor, Eminent Mall 261, Lajpant Kunj, Guru Nanak Mission Chowk Jalandhar … Opposite Party BEFORE: HON’BLE MR. JUSTICE J. M. MALIK, PRESIDING MEMBER HON’BLE DR. S. M. KANTIKAR, MEMBER For the Complainant : Mr. K.L. Nandwani, Advocate PRONOUNCED ON 4TH July, 2013 ORDER JUSTICE J.M. MALIK 1. The key question involved Commission can travel outside the in Insurance this case Policy and is “Whether grant relief to this the complainant, without adhering to the parameters laid down in the policy itself?”. 2. The present complaint has been filed by M/s. Shital Fibres Ltd against M/s. Bharti Axa General Insurance Co.Ltd., wherein a sum of Rs.4,19,04,368/- towarcds loss & damage, Rs.25,00,000/- towards punitive losses, Rs.20,00,000/- towards compensation for loss of business and delay in settling the claim, interest @ 2% or at the bank rate prevalent as on 15.04.2012 as per Regulation No.9 of the Insurance Regulatory and Development Authority (Protection of Policyholders’ Interest) Regulations, 2002, because the amount was not paid within 30 days from the appointment of Surveyors and costs of the complaint, were claimed. 3. The facts germane to the present case are these. The complainant got constructed a building at Plot No.C-81, Focal Point, Jalandhar, Punjab, in December, 2007. The building was insured with different insurance companies, from time to time, but in the year 2011, the building was got insured from M/s. Bharati Axa General Insurance Co. Ltd, opposite party, which was issued seven policy schedules but did not issue the complete policies till date. The policies issued were Special Peril policies which also included the loss of the building due to subsidence and landslides. Unfortunately, on 15.04.2012, the building collapsed like a pack of cards when machines were running and work was going on as the factory used to run for 24 hours. 4. The loss was intimated to the opposite party, which appointed M/s.Puri Crawford Insurance Surveyors and Loss Assessors, which visited the site for the first time, on 17/18/12/2012. The surveyors called for documents in piece-meal, from time to time, w.e.f. 25.06.2012. All the furnished whenever the documents same were and drawings required. A was appointed by the Surveyor but he did not have complainant. No any joint meeting was held with the of the survey report, the complainant Associates. They supervised the again construction contacted were immediately Structural interaction Engineer, with the surveyor. On receipt M/s.Gossian of the building and had & issued completion certificate. The Structural Engineers vide their report reiterated that the sudden collapse of the entire structure suggested that it could not be a design/material defect and had to do more with the movement of soil. The opposite party did not pay heed and a legal notice was served on it to make the payment. The complainant approached Guru Nanak Dev Engineering Testing vide their and Consulting Cell, Ludhiana, which 15.03.2013, gave the opinion that structural design was report, College dated ‘OK’ and there was no defect in it. Another opinion from an Expert, namely M/s.ARO Tech Structural Consultants, Jalandhar City, Punjab, was obtained, which opinion that the collapse was due to faulty construction was of also sewer of the line by Punjab Sewerage Board, due to which soil underneath had become bad. The complainant also met Shri Kunwar Sunil his expert report and he opined that if the Kumar, Chartered total vibration Engineer of the for machine is taken together, it cannot cause the collapse of the building. 5. The Opposite party repudiated the claim made by the complainant vide its letter dated 04.02.2013, wherein it was mentioned : “…….We reiterate that the claim lodged is not admissible under the captioned policy due to non-operation of any insured peril as observed and recommended by surveyors. We thus repudiate our liability under the claim & close the claim file as “No Claim”. This report is accompanied by the report given by Er. Surjan Sindh Sidhu, BE (Civil) MIE India, FIV, Structural Engineer, Formerly Executive Engineer, PB.PWD (B & R), Associate Professor (Civil) RIET, Abohar. This is a detailed report which runs into five pages. The conclusion drawn by the Expert is reproduced, as follows:- “4. CONCLUSION Keeping in view the above facts and figures, it is reported that the main cause seems to be the failure at and near joints of R.C.C. Columns and R.C.C. beams due to shear stresses, as the work was done without following structural design and may have led to the collapse. Therefore, structural design defect is the main cause of collapse of building. Addition to it, there is no reliable information regarding construction procedure adopted, required quality control system applied, and qualified Civil Engineers deputed for construction etc. of building So, construction Codal and supervision, non-compliance Rules and Regulations, Byelaws, Technical Specifications, may have contributed to produce a weak structure, which could not resist the applied loads, continuous vibrations due to operating machinery and other forces causing ultimate failure of the building”. 6. We have heard the counsel for the complainant at the time of admission hearing of this case. The policy in question was produced before us which mentions about the Standard Fire and Special Perils and material damage. According to counsel for the complainant, this case falls within the ambit of Clause VIII of the policy in question, which reads, as under:“VIII. Subsidence and Landslide, including Rock slide: Loss, destruction or damage, directly caused by subsidence of part of the site on which the property stands or Landslide/Rock slideEXCLUDING : a) the normal cracking, settlement or bedding down of new structures b) the settlement or movement of made up ground c) coastal or river erosion d) defective design or workmanship or use of defective materials e) demolition, construction, structural alterations or repair of any property or ground works or excavations”. [EMPHASIS SUPPLIED] 7. He further submits that as his case falls within this clause, the case should not be dismissed in limine. He further contended that an enquiry should be made in the questions raised by him. In support of his case, he has cited the following authorities : (1) Consumer Education & Research Society & Ors., Vs. Ahmedabad Municipal Corporation & Ors., 2002 (10) SCC 542; (2) United India Insurance Co.Ltd. Vs. Kiran Combers & Spinners, (2007) 1 SCC 368; (3) New India Assurance Co. Ltd. Vs. Pradeep Kumar, (2009) 7 SCC 787; (4) Punj Lloyd Limited Vs. Corporate Risks India Private Ltd., (2009) 2 SCC 301; (5) V.N.Shrikhande (Dr.) Vs. Anita Sena Fernandes, (2011) 1 SCC 53; and (6) New India Assurance Co.Ltd., Vs. Avadh Wood Products (Cold Storage), II (2013) CPJ 10 (NC). 8. We are of the considered view that the case in hand does not fall within the above said clause. This is not a case of landslide/rock slide. It must be borne in mind that the policy does not include the normal cracking, settlement or bedding down of new structures or the settlement or movement of made-up ground. This case clearly falls within the exceptions (a), (b), (d) and (e), appended with Clause 8, already cited above. There is hardly any need to make an enquiry. The facts are crystal clear. The report given by the Expert carries enough value. It is well settled that it will get preponderance over the report Experts appointed by the private party. There made by the is no allegation against the Surveyor. He appears to be guileless and there is no reason to discard his statement/report. The Hon’ble Supreme Court of India has already held that a Surveyor’s report has significant evidentiary value unless it is proved otherwise, which the complainant has failed to do so in the instant case. This view was taken in United India Insurance Co. Ltd. Vs. Roshanlal Oil Mills & Ors., (2000) 10 SCC 19 and also by this Commission in D.N.Badoni Vs. Oriental Insurance Co.Ltd, 1 (2012) CPJ 272 (NC). 9. Otherwise, too, the reports submitted by the Experts, engaged by the Complainant have exiguous value. Their reports are vague, evasive and lead us nowhere. They harp on the same point that structure was quite alright. They have given different reasons. It is apparent that the complainant is trying to make bricks without straw. 10. The complainant has no bone to pluck with the opposite party. The case is meritless and, therefore, the same is dismissed at the admission stage. .…..………………………… (J. M. MALIK, J) PRESIDING MEMBER .…..………………………… (S. M. KANTIKAR) MEMBER dd/16 NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI CONSUMER COMPLAINT NO. 166 OF 2010 M/s K.K.Jewels Impex Z-25, Hauz Khas New Delhi Through its Partner Kailash Chand Jain ........ Complainant Vs. The Oriental Insurance Company Ltd. Through the Senior Divisional Manager Divisional Office No.9 1/28, 4th Floor, Asaf Ali Road Near Hamdard Circle, New Delhi-110002 ......... Opposite Party BEFORE: HON'BLE MR. JUSTICE AJIT BHARIHOKE, PRESIDING MEMBER HON’BLE MR.SURESH CHANDRA, MEMBER For the Complainant : For the Opposite Party : Mr.S.C.Dhanda and Ms.Sagari Dhanda, Advocates Mr.Kishore Rawat, Advocate PRONOUNCED ON : 05th JULY, 2013 ORDER PER HON’BLE JUSTICE AJIT BHARIHOKE, PRESIDING MEMBER The complainant – firm is engaged in the business of import and export of jewellery. The complainant carried jewellery worth US $ 632691.08 to USA for participating in exhibition and sale of jewellery organized at New York. Before leaving India with the jewellery, the complainant got the jewellery insured with the OP for Rs.2,96,09,942.67/- vide cover note number 945271. The insurance cover was for ‘all risks’. The complainant had carried said jewellery in packed steel containers to USA and the jewellery was declared to the custom authorities at New Delhi. The complainant participated in the exhibition at New York on 16 th & 17th June 2001. He sold some items of jewellery on both days. On the conclusion of exhibition, the jewellery was packed in suitcases and put in two cars. While on the way, the complainant decided to pick up some food at Taco Bell Restaurant. The car was stopped and Mr. Komal Jain who was driving one of the car came out of the car. In the meanwhile one person aged 25/30 year opened the driver side of the car which was driven by Mr.Komal. Mr.Komal yelled at him. However, said man managed to pull the internal liver to unlock the boot of the car and escaped with two suitcases containing jewellery in another car waiting for him. The matter was immediately reported to the police. It was even witnessed by a woman Ms. Keecha Patrick who had informed the police on phone no.911. The Nassau Country Police department registered a robbery case. The theft was also brought to the notice of Indian Consulate in USA. The jewellery could not be recovered. The complainant lodged a claim of US $ 315,445/with the OP for the loss of jewellery. The opposite party was supplied with all the information. It made inquiries directly from the police and Indian Consulate and even engaged M/s Webster & Co. USA who appointed M/s MRC Investigators. The investigator after making inquiry reported that incident of robbery was genuine. The OP not being satisfied engaged another surveyor M/s Omniscent Detectives (P) Ltd, who also opined that robbery could not be disputed. Thereafter M/s Alka Gupta & Associates were appointed to assess the loss who assessed the loss at Rs.1,47,62,838/-. 2. The OP failed to settle the claim. This prompted the complainant to serve the OP with a legal notice dated 16.03.2008. The OP vide letter dated 14.08.2009 offered to settle the claim at 50% of the claim amount i.e. Rs.73,81,419/- provided the discharge voucher was signed by the complainant. The complainant accepted the aforesaid amount and signed the discharge voucher. According to the complainant, the aforesaid discharge voucher has been signed by him under duress and because of the circumstances created by the OP in not settling the claim. It is alleged that the complainant is not a big jeweller and loss of capital of Rs.1,47,62,838/- has adversely affected the business of the complainant and as a result because of pressure of non settlement of the claim by the OP, he was compelled to accept the offer and signed the settlement voucher. Claim for the aforesaid settlement is not binding. The complainant has filed this complaint claiming Rs.2,83,79,458/- including the balance due from the surveryor assessment report plus interest. 3. The OP has contested the claim by filing the reply. The complaint is also resisted on the ground that after having settled the matter by receiving a sum of Rs.73,81,419/-, the complainant is estopped from reagitating the matter by filing a fresh complaint. 4. Undisputedly, the complainant has received a sum of Rs.73,81,419/- in full and final settlement of the claim by executing a discharge voucher which clearly records that the aforesaid amount has been received by the complainant in full and final settlement of all his claim. Now the question is after executing such a discharge voucher, whether the insured complainant could still pursue the claim for any further amount? 5. This question came up for the consideration of the Supreme Court in the case of United India InsuranceAjmer Singh Cotton & General Mills and Ors. II (1999) CPJ 10 (SC) = (1996) 6 SCC 400, wherein the Supreme Court observed as under: “The mere execution of discharge voucher would not always deprive the consumer from preferring claim with respect to the deficiency in service or consequential benefits arising out of the amount paid in default of the service rendered. Despite execution of the discharge voucher, the consumer may be in a position to satisfy the Tribunal or the Commission under the Act that such discharge voucher or receipt had been obtained from him under the circumstances which can be termed as fraudulent or exercise of undue influence or by misrepresentation or the like. If in a given case the consumer satisfies the authority under the Act that the discharge voucher was obtained by fraud, misrepresentation, undue influence or the like, coercive bargaining compelled by circumstances, the authority before whom the complaint is made would be justified in granting appropriate relief”. 6. The above position was reiterated by the Supreme Court in the later decisions in National Insurance Company Limited Vs. Sehtia Shoes (2008) 5 SCC 400 7. On reading of the above judgments, the legal position which emerges is that the mere execution of the discharge voucher would not always deprive the consumer for preferring the claim with respect to deficiency in service despite of execution of discharge voucher. The consumer can successfully press his claim provided the consumer is able to establish that the discharge voucher or receipt was obtained from him by fraud, misrepresentation, undue influence or coercive bargaining. 8. Shri S.C.Dhanda, Advocate, learned counsel for the complainant has submitted that ratio of the above noted judgments of the Supreme Court are squarely applicable to the facts of the case. He has contended that admittedly the claim for loss of jewellery due to robbery was submitted in June 2001. The matter was inquired into by the OP through M/s MRC Investigators as also M/s Omniscent Detectives (P) Ltd who confirmed the robbery incident. Even the surveyor assessed the loss suffered due to robbery at Rs.1,47,62,838/- and despite that OP delayed the settlement of claim which resulted in severe financial constraint on the complainant and because of this coercive approach of the OP, the complainant was compelled to accept the offer of 50% of the loss assessed by the surveyor. It is thus contended that complainant was coerced to sign discharge voucher and as such aforesaid discharge voucher cannot be taken as a circumstance to deprive the complainant from preferring the claim. Learned counsel further contended that the intention of the opposite party to pressurise and coerce the complainant to accept the offer is evident from the office noting dated 21.07.2009 wherein the Chief Manager of the Opposite Party while recommending settlement of the claim on compromise basis at 50% has noted that before releasing the payment a letter of compromise towards full and final payment be obtained by the Regional Office and placed on the file. 9. Learned counsel for the opposite party on the contrary has contended that this is a case of voluntarily full and final settlement of the claim. In support of this contention, learned counsel has drawn our attention to copy of letter dated 14.08.2009 addressed by the OP to the complainant wherein it is clearly mentioned that the cheque of Rs.73,81,419/- is being tendered in full and final settlement of the claim with a clear warning that if the offer is not acceptable, the complainant should return the cheque forthwith. Learned counsel contended that the complainant after having knowledge of the offer given in the letter has accepted the cheque which clearly indicate that the cheque has been accepted voluntarily without any demur or protest. Therefore, the complainant is estopped from filing the complaint. 10. We have considered the rival submissions and perused the material on record. The question for determination is whether or not the complainant has received the offered amount of Rs.73,81, 419/- and signed the full and final discharge voucher voluntarily under coercion, misrepresentation or fraud. To find answer to the question it would be useful to have a look on the content of the letter dated 14.08.2009 vide which the cheque for settlement was sent to the complainant: “Sir / Madam, We are enclosing herewith our cheque no.465772 dated 14.08.2009 for Rs.73,81,419/- (Rupees Seventy Three Lakh Eighty One Thousand Four Hundred Nineteen Only) in full and final settlement of your above claim. Please note in case the above offer is not acceptable to you, the cheque should be returned forthwith to this office, failing which it will be deemed that you have accepted the offer in full and final satisfaction of your claim. The retention of this cheque and / or encashment thereof will automatically amount to acceptance in full and final satisfaction of your above claim without reason and you will be estopped from claiming any further relief on the subject”. 11. On reading of this letter, it is clear that cheque was offered to the complainant in full and final settlement of his insurance claim with clear instructions that if the offer was not acceptable, the cheque should be returned failing which it shall be deemed that the cheque has been accepted in full and final settlement of claim. Despite that the complainant hasencashed the cheque without any demur or protest. If the complainant was coerced to sign the discharge voucher nothing prevented him to record his protest on the discharge voucher, which is not the case. Therefore, we are unable to accept the contention that discharge voucher has been obtained by adopting coercive means. 12. Undisputedly the cheque for full and final settlement was received by the complainant on 14.08.2009. The protest notice, however, was signed after six months on 30.03.2010. From this it can be safely inferred that the complainant accepted the cheque amount in full and final settlement of his claim voluntarily and signed the discharge voucher. If at all there was a pressure on the complainant to sign the discharge voucher, the complainant under ordinary course of circumstances instead of waiting for six months would have protested against the so called coercive measures adopted by the opposite party. From the conduct of the complainant also, it appears that the complaint after entering into the settlement has been filed on after-thought with a view to extract more money from the opposite party. As regards the office noting dated 21.07.2009, much importance cannot be attached to the same because the noting only indicate the anxiety of the Chief Manager of the Opposite Party to protect the rights of the opposite party and this noting by itself cannot be taken as a coercive protest. 13. In view of the discussion above, we find that the complainant received a sum of Rs.73,81,419/- voluntarily in full and final settlement of his claim and also executed a discharge voucher in this regard. Thus, the complainant having voluntarily entered into the full and final settlement is now estopped from re-agitating the claim by filing a complaint. As such, the complaint is liable to be dismissed as not maintainable. 14. The complaint is, hereby, dismissed as not maintainable. …..………………………Sd/-…. (AJIT BHARIHOKE, J) ( PRESIDING MEMBER) …..…………………Sd/-……… (SURESH CHANDRA) MEMBER NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 2945 OF 2012 (Against the order dated 17.05.2012 in First Appeal No. 1518/2009 of the State Commission Haryana, Panchkula) Rahul Electricals, Shop No.1379, Railway Road Rohtak-124001, Haryana Through its Proprietor Sh.Kulbhushan ........ Petitioner Vs. 1. State Bank of India Hissar Road Branch, Hissar Road, Rohtak Through its Manager 2. The Oriental Insurance Company Ltd. Through its Divisional Manager, Rohtak124001, Haryana ......... Respondents BEFORE: HON'BLE MR. JUSTICE AJIT BHARIHOKE, PRESIDING MEMBER HON’BLE MR.SURESH CHANDRA, MEMBER For the Petitioner : Mr.Shekhar Raj Sharma, Advocate For the Respondent No.1 : Mr.U.C.Mittal, Advocate For the Respondent No.2 : Mr.Manish Pratap, Advocate Alongwith Mr.Ajay Singh, Advocate PRONOUNCED ON : 05th JULY, 2013 ORDER PER JUSTICE AJIT BHARIHOKE, PRESIDING MEMBER This revision is directed against the order dated 17.05.2012 passed by State Consumer Disputes Redressal Commission Haryana ( in short, ‘the State Commission’) dismissing the appeal preferred by the petitioner / complainant against the order of the District Consumer Forum Rohtak dismissing the complaint. 2. Briefly put relevant facts for the disposal of this revision petition are that M/s Rahul Electricals filed a complaint under section 12 of the Consumer Protection Act against the respondents State Bank of India as also the Oriental Insurance Company Limited claiming that the complainant was engaged in the business of electrical goods. Complainant had obtained a cash credit limit of Rs.3 lakhs from the respondent / bank against the hypothecation of the stock. It is the case of the complainant that as per the agreement, the stock of the complainant was required to be insured and the opposite party / bank had agreed to get the stock insured on behalf of the complainant and debit the insurance premium to the cash credit account of the complainant. Pursuant to the agreement, the opposite party / bank had been getting the stock insured with the insurance company and the last insurance was for the period w.e.f. 25th May 2006 to 24th May, 2007. It is alleged in the complaint that after 24 th May, 2007, the opposite party / bank failed to renew the insurance. Unfortunately on 30.05.2007 the shop of the complainant caught fire due to electrical spark and the entire stock was destroyed. The complaint in this regard was lodged at PS Rohtak City vide DD No.46 dated 31.05.2007. The complainant approached the opposite party / bank to disclose the name of the insurance company with whom he had got the stock insured. The opposite party bank after evading the issue for sometime, ultimately replied that as per the agreement, the insurance was to be got done by the complainant himself. Claimant alleging the failure of the bank to renew the insurance of the stock as deficiency in service filed complaint before the District Forum claiming compensation of Rs.6,27, 870/- on account of loss suffered due to fire accident besides Rs.2,00,000/- on account of mental pain and agony. The complainant also sought direction to the opposite party bank to stop charging interest on the over draft w.e.f. 25.05.2007. 3. The opposite party bank contested the complaint and took the plea that stock hypothecated with the bank were to be insured comprehensively for the market value by the complainant in joint names of the bank and the complainant. It was alleged that the opposite party bank never got the goods insured and it was for the complainant to get the goods insured at his own responsibility. The bank also denied that stock worth Rs.6,27,870/- was destroyed. Thus, it was pleaded that there was no deficiency on the part of the bank. 4. OP No.2 took the plea that it was neither necessary nor proper party because on the date of fire accident, the stock of the complainant was not insured with the insurance company. 5. Sole controversy which needs determination in this revision petition is whether or not as per the terms of agreement between the parties, respondent / bank was under obligation to get the stock available at the shop of the complainant / petitioner insured?. If answer to this question is in the affirmative, then of-course, the respondent / bank has been deficient in providing service to the petitioner / complainant. 6. Shri Shekhar Raj Sharma, Advocate, learned counsel for the complainant/ petitioner has contended that impugned orders of the fora below are not sustainable as the orders are based upon incorrect appreciation of the evidence. It is argued that both the foras below have failed to appreciate that as per the agreement between the parties, opposite party no.1 / bank was under obligation to get the stock lying in the shop of the petitioner insured on behalf of the petitioner / complainant and debit the insurance premium amount to his cash credit account. It is contended that this obligation is admitted by the opposite party / bank in para 2 (c ) and ( e) of their written statement filed in response to the complaint in the District Forum. Learned counsel for the petitioner has also drawn our attention to the copies of the statement of accounts pertaining to cash credit account of the complainant for the periods 01.04.2006 to 31.12.2006 and 21.07.2006 to 31.05.2007 wherein there are debit entries pertaining to the insurance premium for the insurance of stock lying in the premises of the petitioner. It is contended that impugned orders have been passed ignoring the aforesaid evidence. Therefore, those are liable to be set aside. 7. On careful perusal of the record, we find both that both the District Forum as well as State Commission has based their finding on interpretation of Clause V of the hypothecation agreement which reads thus: “That the said goods shall be kept by the Borrower (s) in good condition at his / their risk and expense. Further, when required by the Bank all goods the subject of this agreement shall be insured against fire by the Borrower(s) at his / their expense in the joint names of the Borrower(s) and the Bank in some Insurance Office approved by the Bank to the extent of atleast 10 percent in excess of the amount advanced by the Bank against them and that the Insurance Policy (ies) shall be delivered to and held by the Bank, if the Borrower(s) fail(s) to effect such Insurance on being asked in writing to do so, the bank may insure the said goods against fire in such joint names and debit the premium and other charges to such account as aforesaid and in the event of the Bank being at any time apprehensive that the safety of the goods is likely to be endangered owing to not or strike, it shall on failure by the Borrower(s) to do so after request by the Bank at its discretion itself insure the same in such joint names against any damage arising therefrom the cost of such extra insurance being payable by the borrower(s) and being debited to such account as aforesaid, the Borrower(s) expressly agree(s) that the Bank shall be entitled to adjust, settle, compromise or refer to arbitration any dispute between the Company and the insured arising under or in connection with such policy or policies and such adjustment, settlement compromise and any award made on such arbitration shall be valid and binding on the Borrower(s) and also to receive all moneys payable under any such policy or under any claim made there under and to give a valid receipt thereof and that the amount so received shall be credited in the account having reference to the goods in respect of which such amount is received and that the Borrower(s) will not raise any question that a large sum might or ought to have been received or be entitled to dispute his / their liability for the balance remaining due on such account after such credit”. 8. On plain reading of the above said clause, it is evident that as per the agreement between the parties, the complainant borrower when required by the bank was under obligation to get the stock in his shop insured at his own expense in the joint names of borrower and the bank and if the complainant failed to get such insurance on being asked to do so in writing, the bank in its own discretion was entitled to get the goods insured against fire and debit premium and other charges to the account of the complainant. There is nothing in this clause which may suggest that the bank was under any obligation to get the hypothecated goods insured on behalf of the complainant. Further, the plea of the complainant that there is an admission of obligations to get the stock insured on the part of the respondent / bank, in para 2 (c) & ( e) of the written statement is against the record. On perusal of the copy of the written statement of the opposite party / bank, we find that in para 2 ( c ) & (e ), the bank has categorically denied that it had any obligation to get hypothecated goods insured on behalf of the complainant. On the contrary in the aforesaid paragraph, the bank has categorically stated that stock hypothecated with the bank as per the agreement was to be insured by the complainant at his own expense in the joint names of the bank and the borrower. Thus, we do not find any merit in the plea of the complainant. 9. In view of the discussion above, we are of the opinion that both the fora below have rightly dismissed the complaint in view of the written agreement between the parties. There is no material irregularity or infirmity in the impugned order which may call for any interference by this Commission in exercise of its revisional jurisdiction. Accordingly, the revision petition is dismissed. ………………………Sd/-………. (AJIT BHARIHOKE, J) ( PRESIDING MEMBER) ..…………………Sd/-…………… (SURESH CHANDRA) MEMBER Am/ NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI CONSUMER COMPLAINT NO. 99 OF 2013 WITH INTERIM APPLICATION NO. 2693 OF 2013 1. M/s Ashiana Inn Limited A body corporate, having its Registered Office at Village Dhakoli, Tehsil Dearabassi, District, Mohali through its Managing Director Shri Avtar Singh 2. Shri Avtar Singh s/o Shri Sarwan Singh r/o 1843, Sector 21, Panchkula, Haryana ........ Complainants Vs. Punjab & Sind Bank, IFB, Bank Square, Sector 17-B, Chandigarh Through its Branch Manager ......... Opposite Party BEFORE: HON'BLE MR. JUSTICE AJIT BHARIHOKE, PRESIDING MEMBER HON’BLE MR.SURESH CHANDRA, MEMBER For the Complainants : Mr. Madhurendra Kumar, Advocate Alongwith Mr.I.S.Ratta, Advocate PRONOUNCED ON : 05th JULY, 2013 ORDER PER JUSTICE AJIT BHARIHOKE, PRESIDING MEMBER M/s Ashiana Inn Ltd. through its Managing Director Shri Avtar Singh has preferred this complaint under section 21 r/w section 12 of the Consumer Protection Act, 1986 ( in short, ‘the Act’) against M/s Punjab & Sind Bank, IFB Bank Square, Sector 17-B, Chandigarh claiming deficiency on the part of the opposite party in relation to the release and sanction of the bank loan for the upcoming hotel project of the complainant with the following prayer: “i. To direct the bank to immediately release Rs. 25.00 crores. ii. to direct the bank to convert the overdue amount into FITL. iii. the opposite party to pay damages on account of mental agony etc. Rs.90.00 crores iv. the opposite party to pay costs of the complaint of Rs.2.00 lac. v. any other, additional or alternative relief as deemed fit and proper in the fact and circumstances of the case”. 2. The break-up of the damages of the Rs.90.00 crores claimed by the complainant given in para 50 of the complaint reads thus: (Amount in Rs.) Extra Interest liability on Bank borrowings for a period of last three years Extra interest liability on borrowings from other sources for a period of three years Loss of income from the Hotel for the period of last three years i.e. Rs.10.00crores each year Loss of reputation Mental torture and physical discomfort Total Rs. 3. 15.00 crores 10.00 crores 30.00 crores 30.00 crores 15.00 crores 90.00 crores Shri Madhurendra Kumar, learned counsel for the complainant in his written and oral submissions has contended that the respondent bank is engaged in the business of providing service to the general public for consideration. As such, it being the service provider, the bank is amenable to the jurisdiction of the consumer fora. In support of this contention, learned counsel has drawn our attention to the definition of ‘service’ as provided in section 2 (1) (O) of the Act. Learned counsel for the complainant has taken us through the definition of “consumer” as defined under section 2 (1) (d) of the Act and contended that since the complainant has hired the banking services of the opposite party, he squarely falls within the definition of “consumer”. He contended that amendment of definition of “consumer” which excludes the person who avails service for commercial purpose is not applicable in this case for the reason that although the loan transaction between the complainant and opposite party is a commercial transaction but the services availed are not for commercial purpose. Learned counsel contended that the building of the proposed hotel project is not yet complete or functional, therefore, at this stage, it cannot be said that the building in question would be used for commercial purpose because the user of the building is dependent upon various permissions and licences from the authorities. In support of his contention, learned counsel for the complainant has relied upon several judgments of the Apex Court and the National Commission particularly in the cases of Karnataka Power Transmission Vs. Ashok Iron Works Pvt. Ltd. AIR 2009 SC 1905 being Civil Appeal No. 1879 of 2003, Regional Provident Fund Commissioner Vs. Shiv Kumar Joshi (2000) 1 SCC 98, Chandigarh Housing Board Vs. Avtar Singh & Ors. AIR 2011 SC 130, Lucknow Development Authority Vs.M.K.Gupta (1994) 1 SCC 243, Harsolia Motors Vs. National Insurance Co. Ltd. 1 (2005) CPJ 27 (NC) and also the decision of this Commission dated 18.08.2011 in the matter of HUDA Vs. M/s Suneja & Sons in RP No. 2951 of 2009. 4. We have considered the submissions made by learned counsel for the complainants and perused the record. The answer to the issue of maintainability of the instant complaint would depend upon the fact whether or not the complainants are covered within the definition of “complainants” given in section 2 (1) (b) of the Act which is reproduced thus: “complainant” means(i) a consumer; or (ii) any voluntary consumer association registered under the Companies Act, 1956 ( 1 of 1956) or under any other law for the time being in force; or (iii) the Central Government or any State Government ; or (iv) one or more consumers, where there are numerous consumers having the same interest; (v) in case of death of a consumer, his legal heir or representative; who or which makes a complaint”. 5. The complainants claim that they are covered under clause (i) of Section 2 (b) of the Act. Thus it is to be seen whether or not the complainants fall within the definition of “consumer”. The term “consumer” is defined under section 2 (1) (d) of the Act. Section 2 (1) (d) (i) deals with the definition of “consumer” in relation to the person who buys any good or consideration. Section 2 (1) (d) (ii) deals with the definition of “consumer” in relation to a person who hires or avails of services for consideration since this is a case relating to alleged deficiency in service. The definition of “consumer” as provided in section 2 (1) (d) (ii) is relevant which is reproduced thus: “consumer” means any person who (ii) hires or avails of any services for a consideration which has been paid or promised or partly paid and partly promised, or under any system of deferred payment and includes any beneficiary of such services other than the person who hires or avails of the services for consideration paid or promised, or partly paid and partly promised, or under any system of deferred payment, when such services are availed of with the approval of the first-mentioned person but does not include a person who avails of such services for any commercial purpose; Explanation.—For the purposes of sub-clause (i), ‘commercial purpose’ does not include use by a consumer of goods bought and used by him exclusively for the purpose of earning his livelihood, by means of self-employment. 6. Before dwelling upon the above noted definition of “consumer”, we may note that the definition of “consumer” was amended by Act 62 of 2002, Section 2 w.e.f. 15.03.2003. By this amendment, the legislature in its own wisdom restricted the scope of the definition of “consumer” by adding the words “but does not include a person who avails of such services for any commercial purpose”. This implies that a person who avails of services for consideration for any commercial purpose shall not be covered under the definition of “consumer” and as such, such persons would not be entitled to maintain a complaint under the Act in view of Section 2 (1) (b) of the Act. We are conscious of the fact that explanation to section 2 (1) (d) of the Act provides that for the purpose of section 2 (1) (d), “commercial purpose” does not include the services availed by the person exclusively for the purpose of earning his livelihood by means of selfemployment. Above-noted explanation restricting the scope of commercial purpose is of no avail to the complainant because complainant no.1 is a body corporate and not a natural person who needs to indulge in some activity to earn his livelihood. 7. In the light of the above analysis of the relevant provisions of the Act, we now proceed to analyse the complaint to find out whether or not the complainants fall within the definition of “consumer” reproduced above. On perusal of the complaint, it is evident that loan facility was availed of by the complainants to finance their commercial project to construct and run a three star hotel ‘Marc Royale’. Therefore, it is obvious that the so called services which are claimed to be deficient were availed by the complainant for commercial purpose i.e. running a hotel for earning profits. 8. Learned counsel for the complainant has made a valiant effort to make a distinction between the commercial transaction and commercial purpose referred to in the definition of consumer. He has contended that although the nature of loan transaction between the complainants and the opposite party is commercial but the loan sanctioned by the opposite party cannot be termed as loan for any commercial purpose. We do not find any merit in this contention in view of the allegations made in the complaint. Otherwise also, perusal of para 50 of the complaint would show that the complainants have sought compensation of Rs.30.00 crores for loss of income for three years because of deficiency in service by the opposite party and also Rs. 30.00 crores for loss of reputation. From the fact that the claimants are seeking compensation for loss of income for a period of three years because of non completion of project as a consequence of deficiency in service of the opposite party, it is clear that the loan in question was taken for commercial purpose. That being the case, the only conclusion which can be derived on reading of the complaint is that the complainants had availed the services of the opposite party bank for a commercial purpose i.e. construction of hotel for earning profit. Thus, in our view, the complainants are not covered under the definition of “consumer” as defined under section 2 (1) (d) (ii) of the Act. As such, the complaint is not maintainable before the consumer fora. 9. Judgments of the Supreme Court in the matters of Karnataka Power Transmission Vs. Ashok Iron Works Pvt. Ltd. (supra), Regional Provident Fund Commissioner Vs. Shiv Kumar Joshi (supra), Lucknow Development Authority Vs. M.K.Gupta (supra) are of no avail to the complainant because aforesaid judgments relate to the cases pertaining to the period prior to the amendment of definition of “consumer” which included the persons availing or hiring services for commercial purpose also. Even the other judgments relied upon by the complainants are of no avail to them for the reason that those judgments have been given in different context based upon the peculiar facts of said case. In the instant case, as discussed above, it is evident from the allegations in the complaint that the complainants have availed of the alleged services for purely commercial purpose. As such, complainants are not covered under the amended definition of “consumer”. 10. The result of above discussion is that the complainants herein are not covered under the definition of “consumer” as defined under section 2 (1) (d) (ii) of the Act. As such they are not entitled to maintain a consumer complaint in view of section 2 (1) (b) of the Act. Complaint is, therefore, rejected as not maintainable. Sd/…..…………………………. (AJIT BHARIHOKE, J) ( PRESIDING MEMBER) Sd/…………………………… (SURESH CHANDRA) MEMBER Am/ NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 4747 OF 2012 (Against order dated 03.10.2012 in First Appeal No. 827 of 2011 of the Andhra Pradesh State Consumer Disputes Redressal Commission,Hyderabad) 1. The Managing Director Cholamandalam MS. General Insurance Co. Ltd. Venkata Plaza-2, D.No. 6-3-698/3 Ist Floor, Panjagutta Cross Roads, Hyderabad 2. The Managing Director Cholamandalam MS. General Insurance Co. Ltd. Paramount Health Management, Elite House, Ist Floor, 55-A, Vasanji Road, Opp. Andheri Kurla Road Chakala, Andheri, Mumbai- 400093 …Petitioners Versus Ms. Borredy Pragahi W/o T. Bharat Reddy R/o D.No. 1/334-3, Opp. RTC Bus Stand, Maruthi Nagar Presently Resident At Flat No.-408, Victory Apartments, Yerramukkapalli Kadapa City, YSR District 526001 …Respondents BEFORE: HON’BLE MR.JUSTICE J.M.MALIK, PRESIDING MEMBER HON’BLE DR.S.M.KANTIKAR, MEMBER For the Petitioner(s) : For the Respondent(s) Mr.S.M. Tripathi, Advocate : Ms. Radha, Advocate Pronounced on 5th July, 2013 ORDER PER DR. S.M. KANTIKAR 1. The Revision Petition is filed against the Impugned Order of Andhra Pradesh State Commission Disputes Redressal Commission, Hyderabad (in short, State Commission, AP) in First Appeal Number 827 of 2011 against the Consumer Complaint No. 44/2011 of District Consumer Disputes Redressal Commission, Kadapa (in short District Consumer Forum). 2. The Facts In Brief are: The Complainant/Respondent herein was Ms. Borredy Pragahi a medical student of Nanjing Medical University,China took Overseas Student Travel Insurance Policy from the respondent for a sum of US $.1,00,000/- covering from 25.02.2007 to 24.02.2009. She got admitted in Jiang Hospital,Nanjing for treatment of iliac fossa pain, fever and nausea where she was diagnosed as Right Oopheritis, Menstrual Syndrome and Acute Appendicitis and treated accordingly. 3. She returned back to India on 16.01.2009 to visit her parents. Thereafter, she suffered similar attacks of pain as suffered in China for which she was operated on emergency basis at Pragathi Orthopaedic & General Hospital, Karapa on 10.02.2009. The said treatment incurred Rs.64,282/- as expenditure. The claim made with the Respondent, which was repudiated on the ground that said operation was not conducted in China. Therefore, she was not entitled for the claim amount. Against this repudiation the Complainant filed a Complaint before District Forum on 25/2/2011 claiming Rs.64,282/- together with interest 24 per cent per annum, Rs.50,000/- towards mental agony and cost. 4. The respondent resisted the case. While admitting the issuance of policy, it was alleged that the Complainant having taken treatment at Kadapa was not entitled to the amount covered under the policy. In fact, she was paid as amount of Rs.25,805/- towards treatment she underwent in China, which was paid towards full and final settlement of the claim. The surgeon, who conducted surgery, is none other than her own father. Therefore, it prayed for dismissal of the Complaint with costs. 5. The District Forum dismissed the Complaint. The Complainant preffered the Appeal in the State Commission. The State Commission set aside the order of District Forum and allowed the appeal. 6. Being aggrieved by impugned order of State Commission petitioner herein filed this revision petition on 14/12/2012. 7. We have heard the learned counsel for both the sides and perused the evidence on record before District forum and State Commission. 8. It is an undisputed fact that the Opposite party – the Insurance Company had issued an Overseas Student Travel Insurance Policy, Ex.B.1 for a sum of US $ 1,00,000/- covering the period from 25.02.2007 to 24.02.2009. It is not in dispute that during the above said period, she had taken treatment at China and the amount which she incurred towards treatment was paid. Her case was that after she returned to India, an emergency Appendicectomy operation was conducted on 10.02.2009,. This is evident on perusal of discharge summary that the diagnosis was “Acute Recurrent Appendicitis” and she incurred a sum of Rs.64,282/- towards medical expenses. When she requested for settlement of claim, the Insurance Company repudiated it by issuing letter, Ex.B.2 alleging that she would not be entitled to the said amount if the operation was performed in India. 9. On perusal of the policy condition under section B which is as follows: “Section B-Cover 1. Medical expenses1) Under Medical Evaculation/Transportation: 1) the transportation of the insured from that overseas country to India or the place of residence where necessary medical attention can be provided; the coverage for medical treatment will be up to the limit of indemnity for medical expenses for maximum period of 30 days from the date of return.” (emphasis supplied) 10. The Pragathi Hospital records like In-Patient Case Sheet, Discharge Summery where the Complainant underwent emergency operation on 10.02.2009 and it’s evident that operation was within 30 days of her return from China that is on 16.01.2009. Therefore, the Insurance Company is bound to reimbursement the amount paid by Complainant towards the hospitalization expenses. The repudiation was unfair and is unjustifiable. Therefore, we agree with the findings of State Commission in allowing the appeal filed by the Complainant. Therefore, we upheld the order of State Commission and pass the orderThe Revision Petition is dismissed with a punitive cost of Rs.25,000/- which is to be paid to Complainant within 45 days otherwise it will carry 9% interest per annum, till its realization. ..…………………..……… (J.M. MALIK J.) PRESIDING MEMBER ……………….…………… (S.M. KANTIKAR) MEMBER NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI ORIGINAL PETITION NO. 328 OF 2000 Indian Sugar Exim Corporation Limited Having its registered office at: Block-C, IInd Floor, Ansal Plaza, August Kranti Marg, New Delhi- 110049 Through Mr. V.K. Jain,its Manager (Commercial) …….Complainant Versus 1. M/s. United India Insurance Co. Ltd. Having its registered & head office at: 24, Whites Road Chennai- 600014 Through its Divisional Manager Divisional Office No.XXIII 607-608, Devika Tower 6, Nehru Place New Delhi- 110019 2. M/s. J.B. Boda Surveyors Pvt. Ltd. Having its registered office at: Maker Bhavan No.11, Sir Vithal Das Thackersey Marg Mumbai- 400020 Through its Managing Director ........Opposite parties BEFORE HON’BLE MR. JUSTICE J.M. MALIK, PRESIDING MEMBER HON’BLE MR. VINAY KUMAR, MEMBER For the Complainant : Mr. Buddy Ranganathan, Advocate Mr. Lokesh Bhola, Advocate, Ms. Pankhuri Jain, Advocate Ms. Mansha Anand, Advocate For the Opposite parties : Mr. A.K. De, Advocate Mr. Rajesh Dwivedi, Advocate Ms. Deepa Agarwal, Advocate PRONOUNCED ON: 5/7/13. ORDER PER MR.VINAY KUMAR, MEMBER M/s. Indian Sugar & General Industry Export Import Corporation has filed this complaint in the year 2000. In the course of the proceedings MA/1428/2009 was filed informing that the Complainant had changed its name to M/s Indian Sugar Exim Corporation Ltd. The application was allowed on 15.12.2009 and necessary amendment in the memo of parties permitted. In the proceeding of 19.11.2012, it was observed that negotiations for compromise between the parties were in progress. The matter was therefore adjourned to 2.1.2013 directing that in the event of no compromise being reached, the parties would file their written arguments. The matter was finally heard on day to day basis and reserved for order on 16.1.2013. BACKGROUND 2. The consumer dispute arises out of import of 13,800 MT of white sugar by the Complainant from Switzerland in 1994. The entire consignment was shipped to India and was received at Mangalore Port. The Complainant had obtained a marine insurance policy to cover the shipment. It was effective from 13.4.1994, initially for a period of 60 days. Subsequently, the terms of the policy got extended to 1.11.1994, with three extensions in between. CASE OF THE COMPLAINANT 3. The Cargo vessel MV Scotian Express left Eemshaven Port in Netherland on 28.4.1994 and arrived at Mangalore Port on 26.5.1994. Discharge of the entire Cargo of 13,785 (mts) of Sugar was completed by 3.7.1994. As per para 7 of the complaint petition, “substantial quantity of sugar bags were found progressively to be partly wet and stained in all hatches of the vessel apart from bursting of many bags. It would be also evident from perusal of date-wise summary of discharge as recorded in Annexures-A & B of Annexure-8 herein that; heavy rain was experienced right from first day of discharge upto the date of final discharge, namely, 3rd July 1994. A copy of Certificate issued by Indian Meteorological Department Station: Panambur dated 6th December 1994 certifying the recorded rain fall during the months of May, June, July & August 1994 is annexed herewith and marked as Annexure-9.” 4. In the above background of damaged conditions of the goods, the Complainant appointed M/s. Superintendence Company of India Pvt. Ltd. (hereinafter referred to SCPL) to inspect the condition of the Cargo in the vessel and to supervise its discharge therefrom. Simultaneously, OP-1/ insurance company appointed a Surveyor (OP-2) for the same purpose. The report of OP-2 (Annexure 12) gives full details of unloading of 13800 (mts) of sugar between 26.5.1994 and 3.7.1994. In this report OP-2 clearly mentions that:“During discharging we observed that lots of bags were wet stained/discoloured in-side the holds and the same were discharged alongwith the sound bags since it was difficult to segregate the wet stained/discoloured bags inside the hold.” The report of the Surveyor (OP-2) has also noted the details of the total discharge of 13800 MTs (Annexure 12) as follows:No. of sound bags 271,266 No. of cut/torn bags 1109 No of wet stained/ discoloured bags 3625 Total no. bags discharged 276,000 The complaint petition states that the Complainant is entitled to compensation on the basis of the facts contained in the above report of the Surveyor/OP-2. 5. The goods were stored in hired transit godowns of Mangalore Port Trust. The process of unloading and stacking was completed between 26.5.1994 to 3.7.1994. It is the case of the complainant that in this period Mangalore received very heavy rain fall. Despite coverage of the stocks, top and bottom, with tarpaulins sheets, further damage to the stocks occurred from leakage of the godown roofs. Also, excessive rains continued through the months of June and July. 6. The Complainant was advised by OP-2 to segregate the damaged cargo, but according to the Complainant it was not possible as the godowns were packed and there was no space to take up the segregation exercise of such a huge quantity. Moreover, with incessant rain any such exercise, involving movement of stocks from one godown to another would have exposed them to further damage by rain. Allegedly the Complainant also informed the OPs that due to heavy rain it was not possible to move the stocks to other regions in the country. He was advised to take action keeping in view Clauses of 16 and 18 of the Policy. The first dealt with reimbursement of expenditure incurred for averting or minimising loss and protecting the rights of the underwriter against third parties. The second required the Complainant to act with ‘reasonable despatch’ under all circumstances within its control. 7. The complaint petition states that by 22.10.1994, in all 77414 bags of sugar were segregated , with re-bagging to the extent necessary and 3870.70 MTs of sound sugar was despatched. Details of these deliveries made between 10.8.1994 and 22.10.1994 are shown in Annexure 42 to the complaint. Complaint petition also shows that joint survey of the remaining stocks—198353 bags-- was done and its report of 22.11.1994, signed by the representatives of both sides showed that it largely comprised either partly wet or fully wet bags. But, the total weight of these 198353 is accepted to be 9917.65 MTs in the complaint. This was based on analysis of 6000 bags as a joint exercise taken by both. 8. The complaint petition also seeks to make out a case that when sugar is damaged by rain it is not only moisture but also factors like loss of lustre and caking etc. that need to be taken into consideration. Allegedly, after 198353 bags of sugar were sold @ of Rs.9875 per MT, the picture of final loss became clear. Therefore on 16.9.1995 a claim under the policy was made for Rs.707.83 lakhs. In response, OP-1/ United India Insurance Company made an offer of Rs.44,24,963/- only on 8.5.1998, which was declined by the Complainant. The prayer of the Complainant is to award an amount of Rs.707.83 lakhs with 24 % interest from the date of the claim i.e. 16.9.1995. RESPONSE OF THE OPPOSITE PARTIES 9. Per contra, in the Written Statement filed on behalf of OP-1, it is stated that the entire unloading operation was personally supervised by the Surveyor/ OP-2 between 26.5.1994 to 3.7.1994. The WS accepts that the cargo has suffered water damage during the voyage and many bags were found to be wet/stained/discoloured at the time of unloading. Intermittent rains had continued during the entire period of unloading and the discharged cargo was stored in godowns with “roofs full of holes”. The written response strikes a note similar to that in the complaint petition when it comes to effect of continued heavy rain fall and repeated damage to the godown roofing on the sugar stocks stored therein. Allegedly, the Complainant failed to take prompt action to save goods from suffering further rain damage in the godowns. 10. It is the case of the Insurance company that while the Surveyor had repeatedly demanded segregation of sound stocks from the damaged ones in the godown, the Complainant was unwilling to take up the exercise, on the ground of high cost of the operation and offered to do the same at the time of delivery. However, the delivery operation itself came to a stop after 23.10.1994 with the despatch of 77414 bags of the sugar to various destinations. 11. As stated in the WS of the OP/United India Insurance Company Ltd., an attempt was made to settle the claim on non-standard basis, due to failure of the Complainant to segregate the damaged stocks from the sound ones and failure to take timely action to minimize the loss. The total loss was quantified by OP-2 to be of the order of 288.127 MTs, for which a total compensation Rs.44,24,963 was offered to the Complainant on 8.5.1998, against the claim of Rs.707,83,101.96. Apparently, the offer was declined. According to the OPs, there was no deficiency of service in rejection of a very large claim of Rs.707,83,101.96. ARGUMENTS ADVANCED BY THE TWO SIDES 12. Before the National Commission the case of the complainant has been argued by learned Advocates, Mr Buddy Ranganathan, Advocate and Mr A K De, Advocate has argued the case of the United India Insurance Co. They have been heard extensively, over several days, with reference to documents brought on record. We have also considered the written arguments filed on behalf of the two sides. 13. Coming to the core of their arguments, Mr Ranganathan argued that damage to the stocks and resultant loss suffered by the complainant are not denied by the insurer. But against a loss of Rs 707.8 lakhs, the insurance has assessed the loss as Rs 58.99 lakhs only. Even here, OP-1 has deducted 25% in the name of non-standard settlement of the claim. This was not acceptable to the complainant. Further, he referred to the joint exercise of November 1994 which segregated 6000 bags for analysis. Learned Counsel argued that the report of the Surveyor/OP-2 itself mentions that out of 6000 bags 5789 were found to be water stained externally, a fact that by itself would show that damage to the stocks was extensive. He referred to test results of the stocks (on parameters of polarisation, moisture, colour etc) at the time of loading for India and compared them to the results of analysis of samples drawn on 2.12.1994 and claimed that water had affected the quality (sale value) of the stocks. 14. Reacting sharply to the above, learned counsel for the OP/insurance coy, Mr. A.K.De, argued that a series of correspondence has taken place between the Surveyor appointed by the insurance and the insured on precisely the same concern i.e. need to protect the stored stocks against further damage from continued rain. But, the Complainant did not take action for speedy repair of the leaking godowns or for segregating damaged stocks from good ones. Nor was action taken for prompt disposal as a measure against further damaged in continued storage. The delivery of sugar stocks started only on 10.08.1994 and came to an abrupt stoppage since 23.10.1994. By then only 77414 bags, as against import arrival of 27,0000 bags, had been delivered to different destinations. It has been strongly argued on behalf of the respondent/Insurance Company that lab analyses of samples taken from 6000 bags segregated in November, 1994, showed that despite external damage to the packaging, moisture and sucrose content as well as colour of sugar were within the stipulated limits. The assessment of total loss being limited to 288.127 MT against the total quantity of 13800 MT was based on the above mentioned test results. Mr. A.K.De, argued that the complainant base his case only on the extent of external damage to the bags and not on actual condition of the sugar within. Therefore, the claim of the Complainant for Rs.707.83 lakhs is exaggerated, misconceived and untenable. The insurer cannot be held liable for loss caused by failure of the Complainant to take prompt action in protection and disposal of the stocks. THE EVIDENCE ON RECORD 15. Damage during storage at Mangalore Port, caused by continued rains and leaking godown roofs, is not denied. Para 19 of the affidavit evidence of Mr V K Jain, Manager (Commercial) of complainant coy accepts it. But it also goes on to add that the godowns were packed and there was no space to undertake the exercise of stock segregation. But, the claim that OPs had agreed that it could be done at the time of delivery, is denied by the OPs. 16. The two sides eventually undertook an exercise of segregating 6000 bags in November 1994 and analysed the contents with the help of SGS Goa. (Annexures 54 & 55). The content analysis of water affected bags showed their moisture content as follows— Partially stained bags 0.16% Fully stained bags 0.25% Further, in December 1994, while the complainant was in the process of moving 1700 MT (34000 bags) of sugar to Orissa, OP-2 got them analysed. As per his report of 23.5.1995, re-bagging resulted in 118 bags of water damaged sugar and 33,882 bags of sound quality cargo. Therefore, his report stated that the condition of sugar was not as bad as to require disposal on “as is where is” basis. The final assessment of loss was given by the Surveyor in June 1995, as follows:1. Amount of cargo lost due to cut/torn bags discharged from the vessel 2. 7.950 M.T. Based upon the %age of damages noticed on the 34,000 bags the loss in respect of the balance cargo of 1,98,427 bags (9921.350 M tons). 34.433 M.T. 3. Further depreciation allowed on analysis. 9,829,766 M.Ts at based on 245.755 M.T. 4. Total loss of cargo 17. 2.5% 288.127 M.T. While the OPs have relied on the report of the Insurance Surveyor, the complainant has relied upon the report of their expert agency, Superintendence Co. of India Pvt. Ltd (SCPL). It talks about delivery of stocks soon after recession of the monsoon and details segregation and despatch of 77414 (3870MT) between 17.8.1994 and 22.10.1994. SCPL report of 8.8.1995 states that on the basis of careful visual examination made on 3.10.1994 and excluding 7185.9 MT of stocks lying in two Port Sheds, “the entire remaining quantity of 2721.95 MT were completely damaged/wet/moistured conditioned and contents thereon not free flowing and therefore advised our client to dispose of the above stock immediately on as is where is condition to avoid to avoid further losses/damages.” Significantly, this opinion was based on visual examination of 2721.95 MT (corresponding to 54439 bags) stocks. SCPL also relies on segregation of 2000 bags on 23.10. 1994 and 6000 bags on 22.11.1994, jointly with OP-2. Its conclusion that over 99% of the remaining stock of 197667 bags (approximately 9883 MT) were damaged, is based on external appearance of stocks. On the other hand, the Insurance Surveyor has gone further and based its conclusions on content analyses of sucrose, moisture and polarisation percentages in the stock of sugar. SCPL report refers to these analyses reports and merely states that moisture content was above permissible limits. In the affidavit evidence of the complainant it is alleged that it was the result of selective sampling. 18. Affidavit evidence of Mr S K Sharma, Deputy Manager, has been produced on behalf of the insurer,OP-1. Its main thrust is on the contention that despite repeated requests and reminders from the Surveyor, the complainant did not segregate the stocks. Allegedly, this failure of the complainant “further aggravated the loss and had the soaked bags been separated from the sound one, the moisture would not have affected the sound bags/or the moisture content in cargo would have been minimal.” However, 6000 bags were segregated in November 1994, as part of content evaluation exercise. It also refers to analysis of samples drawn on 2.12.1994 and states that, “It was noticed that the moisture and sucrose contents were found to be within stipulated limits and colour of sugar was also within specification.” 19. OBSERVATIONS AND CONCLUSIONS a. It is not the case of the complainant that it was not aware that the cargo would arrive into Magalore Port during heavy monsoon season. But when the cargo arrived, the complainant did nothing more than storing it in unsafe conditions and waiting for the monsoon season to pass. b. Some damage had already occurred while in the ship hold itself. But it was only 4734 bags out of 276000 as reported by insurance surveyor and not questioned by the complainant. Admittedly, (para 9 of the complaint) these 4734 damaged bags were re-bagged into 3428 standard bags. Thus, the net loss before leaving the ship would come to 1203 standard bags out of 276000 i.e. 0.43%. c. Viewed only from external impact on packaging, the above report of the Insurance Surveyor (preliminary report of 6.10.94 and not followed by a final report) would show the loss of 65.20 MT out of 236.70 MT i.e. 27.54% of the wet or damaged bags, which was acceptable to complainant. d. Complainant has taken conflicting stands by first claiming that there was no space in the godowns to take up stock segregation and then arguing that its proposal of 25.7.1994 for stock segregation remained pending with OP-2 till 31.10.1994. e. The results of tests to bring out content analyses of sucrose, polarisation and moisture, has been dismissed by the complainant as outcome of selective sampling. As per the affidavit evidence of complainant, fresh sampling was done on 2.12.1994. But, its results are called ‘patently tainted’, without showing how does it become ‘tainted’, even if it is somewhat different from another analysis. f. In Aug-Oct 1994, segregation of 77414 bags with re-bagging, produced 77414 bags of 50 kg sugar. In all 3870.70MTs.Even a subsequent report of 13.12.1994 from the complainant to OP-2 shows that 33972 bags after rebaging produced 33882 bags of sugar. Both stocks were moved out for sale. These results would go against complainant’s claims of extensive damage to the content of externally damaged bags. g. Admittedly, the complainant wished to undertake stock segregation at the time of their despatch from Mangalore. But, till December 1994, only about 111,296 bags were attended to. Another 8000 bags were segregated as part of a joint evaluation exercise. There is nothing to show that the balance stock, about 170,704 bags, were also segregated. Clearly, it is a case of action by the complainant which was too little and too late. h. In the rejoinder filed on behalf of the Complainant in September, 2009, a reference is made to segregation and re-bagging of 34000 bags of sugar. Admittedly, re-bagging produced 33882 standard bags of 50 kg each. But, the stocks were not despatch to Orissa admittedly for want of a buyer. It is not the case of the Complainant that the responsibility for disposal of stocks rested with the OP. Therefore, the complainant has only itself to blame for its resultant predicament. i. Claim under the policy was lodged on 11.9.1995. The settlement offer from the OPs came only on 21.5.1998. Even if a reasonable processing time of three months is allowed, OP’s response was delayed by two years. j. Correspondence on record shows that high cost involved in segregation of stocks was one of the reasons why segregation was deferred by the complainant. This cost is admitted by OP-1 in the settlement offered, which raises a question as to why it was not agreed earlier. k. It needs to be observed that the claim of Rs 708.83 lakhs made by the complainant includes interest claimed at 24%. The interest amount itself comes to Rs 326.4 lakhs. 20. To conclude, details examined above establish that some damage had already been caused to the consignment before unloading at Mangalore Port. It is also evident that further damage was caused by improper storage after unloading. For the latter, major part of responsibility must lie at the door of the complainant itself. Further, the complainant has failed to establish its claim for a large settlement of Rs 708.83 lakhs. The attempt of the insured to make external condition of the sugar bags as the basis for determination of loss has rightly been rejected by the insurer. However, the failure of the insurer to consider reimbursement of the cost of segregation of stocks is held to be a deficiency of service. It was eventually accepted, though partly, in the proposed settlement, as re-bagging cost for 197739 bags. Secondly, inordinate delay in proposing the settlement itself is held to be another deficiency of service on the part of OP-1. We therefore deem it just and equitable to allow the following, in addition to the settlement of Rs 44,24,963 offered by OP-1 to the complainant on 8.5.1998-- i. Compensation for delay in proposing settlement of the claim Rs eight lakhs. ii. Compensation for delay in acceptance of the cost of segregation Rs five lakhs. iii. Litigation cost of Rs two lakhs. The entire amount of Rs 59,24,963 shall be paid by OP-1 within a period of three months, computed from 90 days after presentation of the claim to the insurer on 16th September 1995, with interest of 8% per annum. Period of delay, if any, shall carry additional interest of 3% per annum. .……………Sd/-…………… (J. M. MALIK, J.) PRESIDING MEMBER ……………Sd/-……………. (VINAY KUMAR) MEMBER s./- NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI CONSUMER COMPLAINT NO. 161 OF 2013 Anand Diamonds Pvt. Ltd. 1980, Ist floor Katra Khushal Rai, Kinari Bazar, Chandni Chowk, Delhi-110006 ……Complainant (s) Versus 1. National Insurance Co. Ltd. (A Govt. of India Undertaking), 808809, Kailash Building, VIIIth Floor, 26, K.G. Marg, New Delhi. 2. Bank of India New Delhi Mid Corporate Branch, 37, Shahid Bhagat Singh Marg, (Near Shivaji Stadium), New Delhi. …….Opp. Party (ies) BEFORE: HON’BLE MR. JUSTICE J. M. MALIK, PRESIDING MEMBER HON’BLE DR. S. M. KANTIKAR, MEMBER For the Complainant (s) : Mr. Rahul Sharma, Advocate PRONOUNCED ON : 5th JULY, 2013 ORDER JUSTICE J. M. MALIK, PRESIDING MEMBER 1. The complainant has made a vain attempt to make bricks without straw. Dacoity/robbery has to be proved not assumed. Can robbery of goods is a gooddefence to save yourself from the vigours of the Law under the SARFAESI Act. We have heard the counsel for the complainant at length. 2. The complainant, Anand Diamonds Pvt. Ltd. is owned by Mr. Rajesh Anand and his wife Mrs. Chandni Anand. The complainant company is a manufacturer and a wholesaler of jewellery dealing in both diamonds and gold. The business activities are transacted from their premises No. 1980, Ist FloorKatra Khushal Rai, Kinari Bazar, Chandni Chowk, Delhi-110006. 3. The complainant approached the Bank of Inida –OP No. 2, which granted credit limits for a credit amount of 4.5 crores. The complainant mortgaged two immovable properties in favour of the Bank in February 2008. As agreed and stipulated, hypothecated stocks of jewellery were got insured with the Respondent No. 1. The insurance amount went on increasing and on 23.03.2010, it was increased to Rs. 12 crores vide insurance policy. 4. On 26.03.2010, 4 unknown persons entered into the business premises of the complainant. They showed the visiting card of M/s Sri Ram Jewellers,Sadar Bazar, Gurgaon. When they were being shown the jewellery and other articles they committed the robbery on gun point after trying the staff present on the side and ensuring that none was able to raise alarm. They looted gold/gold jewellery & diamond jewellery lying in the premises which were worth Rs. 11.41crores and its value stands increased to Rs. 25 crores at the time of filing of this complaint. The police was informed immediately. FIR was lodged for offences under sections 392/397 read with Section 34 of IPC. The intimation was furnished to the National Insurance Company Limited-OP-1. The complainant filed claim in the sum of Rs. 11.41 crores with the OP-1. However, despite several reminders no claim was granted. 5. However, the OP continued paying the installment/interest to the OP-2 till 31.03.2011 in the hope of claim being paid. In the meantime Bank of India –OP2 delcared the account of the Complainant as N.P.A. on account of non-payment on 29.09.2011. OP-2 issued a noticed dated 21.10.2011 U/S-13(2) ofSecuritisation and Reconstruction of Financial Assets and Enforcement of Security Interest Act, 2002 (in short, ‘SARFAESI Act) thereby calling the complainant to pay the entire amount of Rs. 1,49,76,125.03/- alongwith the interest within 60 days. 6. The police filed a closure report as the police could not find any clue about the culprits on 26.02.2011. On 17.10.2011, OP-1 filed an application U/S 173(8) of Cr.P.C. raising doubts on the police investigation. The said application was dismissed by the learned M.M. 7. The request made by the complainant to the bank that under these circumstances he was unable in clearing the debts and its claim will be settled when the claim is granted by the Insurance Company was rejected. On 30.07.2012, the complainant filed a complaint against the OPs. Notice was issued in that complaint. Thereafter, the OP-1 illegally and arbitrarily vide letter dated 24.09.2012 repudiated the claim of the complainant, by falsely contended that no incident of robbery took place in the shop of the complainant. The complainant desired to withdraw the complaint so as to include the facts mentioned in the repudiation letter. The complaint was dismissed as withdrawn with the liberty to file another complaint on the same cause of action. Consequently, this fresh complaint has been filed. 8. We have heard the counsel for the complainant at the time of admission of this complaint. He contended that the police investigation clearly goes to show that the above said incident had taken place. He further explained that the investigator was an Ex-Delhi Police Officer, also supported that the incident had taken place. 9. As a matter of fact, the repudiation letter is very crucial. It is wee bit lengthy one but to understand this case completely it has become necessary to reproduce it fully. The letter of repudiation dated 24.09.2012 runs as follows:“Kindly refer to your claim under the Jewellers Block Policy No. 354301/46/09/3700000372 regarding the loss on account of alleged robbery on 26.03.2010. The claim has been examined and considered by the competent authority of the company in detail in terms of the Jewellers Block Insurance Policy terms, conditions and exceptions. Various observations have been made by Sh. Vinod Sharma, Surveyor. In his Survey Report indicating that there are many inconsistencies and contradictions in the alleged material event, as reported by you. To recap, based on the Surveyor’s observations as well as our own: 1. On enquiring from the other shopkeepers in the same building/ on the ground floor/neighbourhood, it was found that nobody noticed the said looting nor were aware of it, till the same was reported in a newspaper. Even the Police visit was taken as a routine matter. 2. The area in which the Insured location/ establishment is located is a highly and thickly populated area and to escape with the bags, is very difficult for any Robber/s. No four wheeler can enter the area from a long distance, and even for two wheelers also it is very difficult to drive in that locality/area. 3. You, as the Insured and your staff, instead of raising the alarm, went to the Police post located at some distance on foot. 4. Nearby/neighboring Shopkeepers came to know about the event and the quantum of loss of Rs. 8-10 Cr. from the Newspaper only, when news was published after 5 days. 5. There was no media reporting of the alleged event from 27 th March till 31st March 2010. It came only in a Hindi Newspaper, ‘Nav Bharat Times’. 6. During the Surveyor’s visit to your establishment on 31 st March, Mr. Rajesh Anand was not available and the staff and father of Mr.Rajesh Anand told that Mr. Rajesh Anand had gone to the Police Station as they wanted him for some identification. However, when the Surveyor immediately went to the Police Station and met the SHO and IO, they had to state that they never called Mr.Rajesh Anand, on that day. 7. There is an increase in the sum insured of Rs.7.5 cr. immediately before the alleged event and alleged loss. Throughout the year 200910, stocks as per stock statements to Bank was more than Rs.12 Cr. However, you had opted for a sum insured of only Rs.1.50 crores at inception, increased it by another Rs.3.00 crores on 24.02.2010, and another Rs.7.5 Cr. on 23.3.2010, which was suddenly increased to Rs.12 cr on 23.03.2010, just 3 days before loss. There is no convincing justification for the said increases, particularly of Rs.7.50 crores from your side. 8. The entire stocks from the shop were reportedly looted/taken away by the alleged miscreants. Reportedly, not even a single piece was left. As per your statement 4 persons took away the jewellery in 4 bags. The total weight of jewelleryreportedly stolen is approximately 50.00 Kgs. It does not appear to be convincing that nobody noticed the 4 persons carrying 4 bags of jewellery, weighing approx. 50.00 kg each. 9. There is a contradiction in the statement regarding masks used by the miscreants. At the time of looting, they used mask, in between. Definitely while escaping they must have taken out the masks. Why these were used in between the looting is inexplicable, particularly considering the fact that they had not used masks, while entering the shop. 10.Even in small jewellery shops, CCTV is installed. The CCTV installed by you was reportedly having no recording facilities. It is only used to have a watch on the entry from the staircase. At the time of incident, CCTV was not working. There is contradiction regarding CCTV. You did not reply/clarify/confirm properly that the CCTV in question, sans the recording facility was not working at the time of the alleged incident. 11. As per your statement, miscreants/robbers remained in shop for half-an-hour. However, surprisingly no customer came in between. And you claim to be one of the leading showrooms in that area? During the Surveyor’s visit, he was told that 12. due to firing from broken. Subsequently, pistol in all of miscreant, statements, police glass got report, this information was changed and it is mentioned that insured, Sh. Rajesh Anand threw the tray on one miscreant, which hit the glass and same got broken. 13. The Investigator appointed by us (Sh. L.D. Arora) failed to obtain information regarding stocks in possession of your employee, Shri Makkan Lal, who was on official duty, outside the office at the time of alleged incident. Sh. Makkan Lal was having 4 boxes of jewellery with him, which, he was carrying for Hall Marking. 14. You could not explain why Sh. Makkan Lal, who untied the rope/s of the person/s tied up, did not call the police from his Mobile. 15. As per the Surveyor, when he went to Police Station and met SHO and concerned IO, during Internal/Initial investigation, at that time, they, i.e. the Police were doubtful about the occurrence of event and quantum of loss. 16. There is a contradiction in your reply regarding how the police was informed. As per one statement of yours, your employee Sh. S.K. Aggarwal walked to the nearby PCO and informed the Police at 100 No. However, during the Surveyor’s visit, he was told that Sh. S.K. Aggarwal went on foot, to the Police Station which is at about 10 minutes walking distance. Further, as per the Surveyor, and to which we also agree, the employee concerned could have immediately gone down and informed the police from the ground floor shops. In fact, such employee or Mr. RajeshAnand himself could have raised an alarm, soon after being untied right from outside the shop, even which was not done. Why such alarm was not raised, and why the Police was not informed from the ground floor shop/s itself, is not clear. 17. The nearby shop keepers were not even aware of such an incident, till it was reported in a Hindi Daily, five days after. 18. Mr. Rajesh Anand did not clearly explain the number of mobile phones he is/was having. As per the Surveyor’s information, Mr. Rajesh Anand was having two mobile connections and mobiles. 19. You made a vague reply regarding intimation to the local Market/Traders’ Association. 20. You did not give proper reply regarding loans from Banks by the family members/close relatives of the Director (Mr.Rajesh Anand). The Police reportedly verbally informed the Surveyor that the Director and/or his family members have taken various loans from different Banks and are in default. The observations made by the Surveyor in his Survey Report, clearly show that there are many anomalies, inconsistencies and contradictions in the event ,as purportedly reported by you. Such an event or even attempt of threat is not remotely possible in a plea like where the Insured location/premises is located. There is a contradiction with regard to the incident of gunshot also. There is no mention of the incident of gun shot in the FIR & the final report. If there was a gunshot, the whole neighbourhood should have been upon the shop. Even a violent breakage of the glass, should also have brought the whole neighbourhood, down to your shop. The absence of a CCTV or it’s non-functioning, if installed, the statement that the glass/mirror got broken due to the throwing of a plate by an employee at one of the perpetrators, the role of the Peon, Mr. Makkan Lal, the story about some of the stocks having been taken for Hall Marking’, the ‘No objection’ statement given by you, for closure of the case by the P.S. and issuance of the Final Untrace/Closure Report, all clearly indicate that you were not keen for proper & further investigation of the case by the Police, even which further confirms our suspicions that the event of the alleged Robbery was stage-managed. It is obvious that you were keen to recover the insurance claim amount from the Insurance Company, as you were in financial distress. It is obvious that no such alleged robbery ever took place. The alleged event took place, within 3 days of the SI being enhanced. Incidentally, you were maintaining stocks of high value, as much as around, 15 crores even, but had insured only for 1.50 crores, in the previous year’s policy and also at the inception of the renewal of the policy, which is material to this claim. All facts considered, including the circumstantial evidence, the inconsistencies, the anomalies, the contradictions, we are of the considered opinion that this claim is based on fraud/fraudulent means. Neither such an event as alleged ever took place nor have you suffered any such loss, as claimed due to any alleged Robbery. Condition No. 9 of the Policy contract provides: “If the claim be fraudulent or if any fraudulent means or devices be used by the insured or any one, acting on his behalf to obtain any benefit under this policy, or if any destruction or damage be occasioned by the willful act or with the connivance of the insured, all benefits under this policy shall be forfeited.” Besides Condition No. 9, there is breach of Condition no. (ii) and condition no. 10 of the policy of insurance. The said two conditions i.e. no. (ii) and 10, deal with ‘the duty of the Insured to act, as if uninsured” and “due diligence and reasonable dispatch” respectively. We accordingly hereby regret our inability in unequivocal and categorical terms to admit any liability, whatsoever, in respect of this claim of yours, in terms of the terms and conditions of the governing Policy contract”. 10. It is surprising to note that the counsel for the Complainant could not explain all these reasons noted in the repudiation letter. He could not deny all these facts. He was asked to produce the Hindi Newspaper which was allegedly published five days after the incident. He admitted that he has not attached that Hindi Newspaper with the complaint. He however, argued that, that paper finds mention in the documents produced by him. 11. Secondly, the police also did not take any effective action. It is difficult to fathom why the case was sent as untraced. Why the police was not able todetect , even a single clue. The repudiation letter clearly shows that the case of the complainant is an inchoate mix of irreconcilable opposites. Such like stories can be created at any time. Arrest of the robbers or recovery of any article would have done the trick. No evidence was adduced, no proof, from where these ornaments were purchased, was produced. 12. Last but not the least, it is difficult to fathom as to why Bank of India was made a party in this case. Bank of India has nothing to do with the Insurance Policy. They have no privity of contract with the complainant or with the Insurance Policy. It appears that in order to save themselves from provisions of SARFAESI Act, this false case was instituted. Bank has to do nothing with the loss. No relief has been claimed against the bank. Attempt was made to punish them for proceedings against the complainant U/S13(2) of the SARFAESI Act. The Complaint has no merit and the same is dismissed in limine. .…..………………………… (J. M. MALIK, J) PRESIDING MEMBER .…..………………………… (S. M. KANTIKAR) MEMBER Jr/4 NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 1980 OF 2013 With (I.A. No. 3268 of 2013 for Stay) (From order dated 18.03.2013 in First Appeal No.1365 of 2012 of the State Consumer Disputes Redressal Commission, Haryana) Ansal Properties & Infrastructure Ltd. 115 Ansal Bhawan,16 Kasturba Gandhi Marg, New Delhi-110001 ...…Petitioner Versus Nidhi Jain w/o of Shri Parshant Kumar R/o A-171, Prashant Vihar, Delhi-110085. ……Respondent Nitin Jain S/o Ashok Jain, (R/o A-171, Prashant Vihar, Delhi-110085 ......(through Attorney Holder) Vijay Kumar Jain S/o Shri Nihal Chand Jain, R/o 3346, Bankeders Enclave, Sector-55 D, Chandigarh .....(through Attorney Holder) BEFORE: HON’BLE MR. JUSTICE V.B. GUPTA, PRESIDING MEMBER HON’BLE MRS. REKHA GUPTA, MEMBER For the Petitioner :Mr.Saurabh Taneja, Authorized Representative Pronounced on: 5th July, 2013 ORDER PER MR. JUSTICE V.B. GUPTA, PRESIDING MEMBER Being aggrieved by the impugned order dated 18.3.2013 passed by State Consumer Disputes Redressal Commission, Haryana, Panchkula (for short, ‘State Commission’), Petitioner/O.P. has filed the present revision petition. 2. Brief facts are that respondent/complainant booked a flat situated at the Europa Residency, Kundli, Sonepat which was provided by the petitioner. It is alleged that at the time of booking of the above said flat, respondent deposited an amount of Rs.90,000/- and thereafter she also deposited Rs.90,500/-, Rs.87,750/-, Rs.87,750/- and Rs.1,75,500/- i.e. total amount of Rs.5,31,500/- on different dates upto 21.5.2010 with the petitioner against proper receipts and petitioner also gave brochure of the flats scheme to her. 3. It is also alleged that at the time of booking of the flats, petitioner assured the respondent that they will construct/prepare above said flats within a period of 36 months as mentioned in para no. 10.1. a of the brochure and will construct the flats according to the norms of the brochure. However, it was surprising for the respondent that petitioner not only is unable to handover the possession but also it has not started the construction work of flats till today, which shows that the petitioner has not fulfilled the terms and conditions of the Government of Haryana and he was not fully authorized to construct the flats within a stipulated period. Thus, petitioner not only cheated the respondent by way of abstracting money from the respondent but also played fraud upon the respondent. 4. It is further alleged that when petitioner did not start the construction work on the site, the respondent wrote several letters and brought the deficiency/negligence to the knowledge of the petitioner. However, petitioner neither started the construction work of the flats nor replied the letters of the respondent. Hence, respondent filed consumer complaint seeking the following reliefs; i) To make the interest @24% per annum to the complainant from the date of booking the flat and thereafter i.e. 18.1.2010 to 25.11.2010 till the date of possession of the flat. ii) To provide compensation of Rs.10,000/- per month for not handing over the possession of the flat in time to the complainant till the date of delivery of the possession. iii) To complete the construction work within 6 months from filing the present complaint. iv) To make payment of Rs.50,000/- on account of deficiency in service on the part of the respondent and on account of sufferings, mental agony, transportation, humiliation etc. v) 5. To pay Rs.22,000/- as litigation expenses. Petitioner in its written statement has not denied the averments as made by the respondent in para nos. 2 and 3 of its complaint with regard to the booking of the flat as well as deposit of total amount of Rs.5,31,500/-. However, it is alleged that petitioner did not assure the respondent that the construction work will be completed within 36 months. It is pertinent to mention that respondent did not execute the Flat Buyer’s Agreement with the petitioner. As per terms and condition of the agreement, as per term No. 12 “the company shall endeavour to offer the possession of Apartment within 3 years from the date of sanction of building plans by the authorities subject to majeure circumstances and on receipt of all payments punctually as per agreed terms and on receipt of complete payment of the basic sale price.....” 6. Further as per term no.13 of the agreement “if the construction of the premises is delayed due to force majeure circumstances which interalia include delay on account of non availability of building materials, or water supply or electric power or slow down strike or due to a dispute with the construction agency, civil commotion, or by reason of war or enemy action or earth quake or any act of God, delay in certain decision/clearances from statutory body, or if non delivery of possession is as a result of any notice, order, rules or notification of the Government and/or any other public or any competent authority or for any other reason beyond the control of the company, then in any of the aforesaid event, the company shall be entitled to a reasonable corresponding extension of the time of delivery of the said premises on account of the force majeure circumstances. Further, in consequences of the company abandoning the scheme, the company’s liability shall be limited to refund the amount paid by the allottee without any interest. No compensation whatsoever shall be payable. 7. District Consumer Disputes Redressal Forum, Sonepat (for short, ‘District Forum’) vide order dated 23.10.2012, allowed the complaint. 8. Being aggrieved by the order of District Forum, petitioner filed appeal before the State Commission, which vide its impugned order dismissed the same. 9. Hence, this revision. 10. We have heard Mr. Saurabh Taneja, Authorized Representative of petitioner-company and have gone through the record. 11. It has been stated by A.R. of the petitioner that District Forum as well as the State Commission have ignored the fact that the project itself admittedly has not yet taken off and due to certain development at the level of the government the same may never come up. In the light of the above directions regarding handing over of a flat that is not and may never be constructed, is patently wrong and unsustainable. Another argument advanced on behalf of the petitioner is that respondent has not executed the Flat Buyer’s Agreement with the petitioner and in the absence of execution of such Agreement or any contractual obligation, both the fora erred in passing the impugned orders. 12. District Forum, while allowing the complaint in its order held; “4. After giving thoughtful consideration to each and every aspect of this complaint, reply, points argued by the learned counsel for the parties at length and after perusing the documents very carefully and minutely, this Forum is of the view that the ends of justice would be fully met if the directions are given to the respondents to pay interest to the complainant for not handing over the possession of the flat in time to the complainant and the respondents are utilizing the huge amount of the complainant without providing any services to the complainant and the respondents have no right to utilize the amount of the complainant without providing any services to her. Accordingly, we direct the respondents to pay interest to the complainant on the amount deposited by her during the period w.e.f. 18.1.2010 to 25.11.2010 at the rate of 9% per annum from the date 18.1.2010 to 25.11.2010 till the date of possession of the flat and further to compensate the complainant to the tune of Rs.1,000/-(Rs. One thousand) for rendering deficient services, for causing unnecessary mental agony & harassment and under the head of litigation expenses”. 13. State Commission while upholding the order of District Forum, in its impugned order observed; On behalf of the appellant it was argued that the complaint filed by the complainant was premature having been filed before the expiry of 36 months and thus was liable to be dismissed. During hearing, the appellant was asked to verify as to whether the construction work of the project was complete by now, when 36 months have already expired, to which the reply was in negative. Thus, it is established on the record that the opposite parties have failed to fulfil the terms of the agreement with respect of the allotment of the flat to the complainant and therefore no case for interference in the impugned order is made out. The complainant, who had deposited the huge amount with the opposite parties, is certainly entitled to interest on the same for the delayed period in delivery of possession to the complainant. In view of the above, this appeal is dismissed being devoid of any merit”. 14. This plea taken by the petitioner in its revision petition that due to certain development at the level of the government the project itself has not taken off and as such directions regarding handing over of a flat are patently wrong, are absolutely false on the face of it, in view of the Apartment Allottees Agreement which has been relied upon by the petitioner. As per Clause 2 A of this agreement, the petitioner had started the development of “THE EUROPA RESIDENCY” which was duly approved by the Government of Haryana and this Clause read as under; “WHEREAS the Company has been developing an integrated Group Housing Complex/Apartment over a piece and parcel of land admeasuring 5.85 acres approx. in the revenue estate of Village Badkhalsa, Tehsil and District Sonepat, Haryana, hereinafter referred to as the ‘Group Housing Project Land’ in the name and style of ‘THE EUROPA RESIDENCY’ which also situated within the colony, namely ‘SUSHANT CITY, KUNDLI’, being developed by the COMPANY and duly approved by the Govt. of Haryana”. 15. In view of petitioner’s own documents, now it does not lie in its mouth to take this plea, that the State Government has not approved the Scheme. With regard to the execution of the Buyer’s Agreement, there is nothing on record to show that petitioner ever asked or gave any notice to the respondent, to execute the Buyer Agreement or respondent had ever refused to execute that agreement. 16. Present revision petition has been filed under Section 21(b) of the Consumer Protection Act,1986 (for short, ‘Act’). It is well settled that the powers of this Commission as a Revisional Court are very limited and have to be exercised only, if there is some prima facie jurisdictional error in the impugned order. 17. Hon’ble Supreme Court in Mrs. Rubi (Chandra) Dutta Vs. M/s United India Insurance Co. Ltd. 2011 (3) Scale 654 has observed ; “Also, it is to be noted that the revisional powers of the National Commission are derived from Section 21 (b) of the Act, under which the said power can be exercised only if there is some prima facie jurisdictional error appearing in the impugned order, and only then, may the same be set aside. In our considered opinion there was no jurisdictional error or miscarriage of justice, which could have warranted the National Commission to have taken a different view than what was taken by the two Forums. The decision of the National Commission rests not on the basis of some legal principle that was ignored by the Courts below, but on a different (and in our opinion, an erroneous) interpretation of the same set of facts. This is not the manner in which revisional powers should be invoked. In this view of the matter, we are of the considered opinion that the jurisdiction conferred on the National Commission under Section 21 (b) of the Act has been transgressed. It was not a case where such a view could have been taken by setting aside the concurrent findings of two fora”. 18. Petitioner/builder in the present case “wants to have the cake and eat it too” as admittedly it has already received a sum of Rs.5,31,500/- towards the cost of the flat. Thus, petitioner being the builder is enjoying the huge amount deposited by the respondent without any hindrance. On the other hand, respondent having paid substantial amount of consideration is still without any roof. 19. Such type of unscrupulous act on the part of petitioner/builder should be dealt with heavy hands, who after grabbing the money from the purchaser, enjoy and utilize their money but does not hand over the flat, on one pretext or the other. Petitioner has made respondent run from one fora to other so that respondent cannot have any roof over her head and petitioner can go on enjoying respondent’s money without any hindrance. 20. Thus, no jurisdiction or legal error has been shown to us to call for interference in the exercise of power under section 21 (b) of the Act, since, two fora below have given cogent reasons in their orders, which does not call for any interference nor they suffer from any infirmity or revisional exercise of jurisdiction. 21. In Ravinder Kaur Vs. Ashok Kumar, AIR 2004 SC 904, Apex Court observed ; “Courts of law should be careful enough to see through such diabolical plans of the judgment debtor to deny the decree holders the fruits of the decree obtained by them. These type of errors on the part of the judicial forum only encourage frivolous and cantankerous litigations causing law’s delay and bringing bad name to the judicial system”. 22. It is well settled that no leniency should be shown to such type of litigants who in order to cover up their own fault and negligence, goes on filing meritless petitions in different foras. Time and again Courts have held that if any litigant approaches the Court of equity with unclean hands, suppress the material facts, make false averments in the written statement and tries to mislead and hoodwink the judicial Forums, then its defence should be thrown away at the threshold. Equity demands that such unscrupulous litigants whose only aim and object is to deprive the opposite party of the fruits of the decree must be dealt with heavy hands. Unscrupulous builders like petitioner who after taking entire cost of the flat do not perform its part of obligation, should not be spared. A strong message is required to be sent to such type of builders that this Commission is not helpless in such type of matters. 23. Now question arises for consideration is as to what should be the quantum of costs which should be imposed upon the petitioner for dragging the respondent upto this fora. It is not that every order passed by the judicial fora is to be challenged by the litigant even if the same is based on sound reasonings. 24. Apex Court in Ramrameshwari Devi and Ors. Vs. Nirmala Devi and Ors., Civil Appeal Nos.4912-4913 of 2011 decided on July 4, 2011 has observed ; “45. We are clearly of the view that unless we ensure that wrong–doers are denied profit or undue benefit from the frivolous litigation, it would be difficult to control frivolous and uncalled for litigations. In order to curb uncalled for and frivolous litigation, the Courts have to ensure that there is no incentive or motive for uncalled for litigation. It is a matter of common experience that court’s otherwise scarce and valuable time is consumed or more appropriately wasted in a large number of uncalled for cases”. Apex Court further held; “It is also a matter of common experience that to achieve clandestine objects, false pleas are often taken and forged documents are filed indiscriminately in our courts because they have hardly any apprehension of being prosecuted for perjury by the courts or even pay heavy costs. In Swaran Singh Vs. State of Punjab (2000) 5 SCC 668 this court was constrained to observe that perjury has become a way of life in our courts. It is a typical example how a litigation proceeds and continues and in the end there is a profit for the wrongdoers. Learned Amicus articulated common man’s general impression about litigation in following words : “Make any false averment, conceal any fact, raise any plea, produce any false document, deny any genuine document, it will successfully stall the litigation, and in any case, delay the matter endlessly. The other party will be coerced into a settlement which will be profitable for me and the probability of the court ordering prosecution for perjury is less than that of meeting with an accident while crossing the road”. 25. Thus, in our opinion, the present petition is nothing but a gross abuse of the process of law and the revision petition is totally meritless and frivolous, which is required to be dismissed with punitive costs of Rs.1,00,000/-(One lakh only). Accordingly, we dismiss the present petition with costs of Rs.1,00,000/- (Rupees One lakh only). 26. Out of the costs imposed upon the petitioner, Rs.50,000/-(Rupees Fifty Thousand only) be paid to respondent no.1–Nidhi Jain by way of demand draft in her name. Remaining costs of Rs.50,000/- (Rupees Fifty Thousand only) be deposited by way of demand draft in the name of “Consumer Legal Aid Account” of this Commission, within one month from today. 27. In case, petitioner fails to deposit the aforesaid costs within the prescribed period, then it shall also be liable to pay interest @ 9% p.a., till realization. 28. Costs awarded to respondent no. 1 shall be paid only after expiry of the period of appeal or revision preferred, if any. 29. Pending application also stands disposed of. 30. List on 23.08.2013 for compliance. ……..……………………J (V.B. GUPTA) ( PRESIDING MEMBER) ………………………… (REKHA GUPTA) MEMBER SSB NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO.3916 OF 2010 (From the order dated 25.02.2010 in F.A. No.749/2007 of the A.P. State Consumer Disputes Redressal Commission, Hyderabad) SMT. P. LAXMI W/O RAMULU R/O 5-1-87/M/C, SIDDARTHNAGAR, SANGAREDDY TOWN, MEDAK DISTRICT, A.P. .….. PETITIONER Versus THE BRANCH MANAGER, UNITED INDIAN INSURANCE COMPANY, SANGAREDDY BRANCH, MEDAK DISTRICT, A.P. ....... RESPONDENT BEFORE: HON'BLE MR.JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER HON’BLE MR.SURESH CHANDRA, MEMBER For the Petitioner For the Respondent PRONOUNCED ON: : Ms.Surekha Raman, Advocate : Mr.Maiban N. Singh, Advocate JULY, 2013 ORDER PER SURESH CHANDRA, MEMBER The petitioner who is the original complainant has filed this revision petition to challenge the order dated 25.02.2010 passed by the A.P. State Consumer Disputes Redressal Commission, Hyderabad in F.A. No.749/2007. The OP, which is an insurance company, is the respondent herein. 2. There is a delay of 118 days in filing this revision petition for which the petitioner has filed an application for condonation. For the reasons stated in the application and the submissions made by learned Amicus, the delay in filing the revision petition is condoned. 3. Briefly stated, the petitioner being the owner of the lorry bearing no. AP 31T 0599 insured it with the respondent company for the period from 17-11-1999 to 1611-2000. This lorry met with an accident on 28.08.2000 in the outskirts of Sadasivpet town of Medak. The incident of accident to the lorry was reported to the Police Station on 28.08.2000 and was also intimated to the respondent company on telephone followed by written communication. Immediately, the OP sent a surveyor to conduct spot inspection. The surveyor took photographs of the damaged vehicle and asked the complainant to submit her claim for settlement. The complainant submitted her claim and asked permission of the surveyor for shifting his damaged vehicle to the workshop, which was granted. It is alleged that while shifting the damaged lorry by towing it by another lorry on 02.09.2000, somewhere on the way the link chain between two Lorries got broken which allegedly resulted in the second accident. It is stated that the said fact about the second incident was also intimated to the respondent company on telephone and the complainant also lodged the complaint before the police. One more surveyor came to be appointed who also conducted survey by taking photographs of the damaged vehicle along with estimate and original bills for the repairs done to the tune of Rs.1,22,190/-. The grievance of the complainant is that in spite of submission of the claim and notice to the insurance company, her claim was repudiated, which made her to file a consumer complaint against the OP insurance company praying for a direction to pay compensation of Rs.2 Lakhs towards repairs of the damaged vehicle along with interest @18% p.a. and Rs.20,000/- towards compensation and costs. 4. On being noticed by the District Forum, Medak, the OP filed counter and while admitting the issuance of the insurance policy for the period in question to the vehicle and intimation about the accident on 28.08.2000, the insurance company denied the second accident or any intimation about it to the company or to their Divisional Office on 11.09.2000. The insurance company also submitted that the claim of the complainant for compensation was repudiated because she did not file copy of the police report and also when asked to submit the documents including the original bills, no such documents or the bills were sent by her. Denying any deficiency in service on its part, the OP insurance company prayed for dismissal of the complaint. On appraisal of the evidence placed before it by the parties, the District forum by its majority opinion held that there was no deficiency in service on the part of the OP insurance company and hence, dismissed the complaint. 5. Aggrieved by the aforesaid decision of the District Forum, the complainant filed an appeal before the State Commission, which was partially allowed by the State Commission by its impugned order in terms of the following directions:“In the result, the appeal is allowed partly, setting aside the order of the District Forum and as a consequence the complaint before the District Forum is allowed partly directing the opposite party insurance company to pay to the complainant an amount of Rs.7,425/- with interest at 9% p.a. from the date of claim i.e. 11-92000 till the date of realization and proportionate costs in a sum of Rs.1,000/- within six weeks from the date of receipt of this order.” 6. Not satisfied with the partial relief granted by the State Commission vide its impugned order, the petitioner has filed this revision petition praying for setting aside the impugned order and remanding the matter for afresh appraisal in view of raising the various points by her in the revision petition. 7. We have heard Ms.Surekha Raman, Amicus for the petitioner and Mr.Maiban N. Singh, Advocate for the respondent company. 8. Two issues have arisen for our consideration and decision. The first issue is as to whether the second accident took place while towing the lorry on 02.09.2000 as alleged by the petitioner and secondly in the given facts and circumstances of this case any interference is called for with the impugned order giving partial relief to the petitioner. 9. So far as the first issue is concerned, the State Commission has considered this aspect at great length in the impugned order based on the evidence before it and concluded that there was no second accident on 02.09.2000 as alleged by the petitioner. The State Commission has made following observations while rejecting the claim of the petitioner regarding occurrence of the second accident:“The opposite party however stated that it was informed only about the first accident. As a matter of fact, this discrepancy is not of much significance as ultimately the claim was made in writing by the complainant on 11-9-2000. In the said claim form which was obviously subsequent to even the so called second accident, did not make a mention about the second accident. On the other hand, it specifically gave, while giving a short description and other details of the first accident the following account: ‘While my vehicle was proceeding from Sangareddy to Tandur near at the accident spot while tried to overtaking a foregoing truck steered to right applied brakes. At that time in order to avoid a hit of opposite coming vehicle steered to left. Due to his my vehicle slipped and skidded and dashed the foregoing truck and again dashed a tree which was living on left of the road caused heavy damage. Estimate enclosed’. No where in Ex.B2 do we find reference to the second accident.” 10. We agree with the view taken by the State Commission. Incidentally, learned Amicus has admitted that there is no claim being pressed for the second accident to the vehicle. This leaves us with the second issue in respect of the adequacy or otherwise of the relief already granted by the State Commission through the impugned order. We may note that after going through the submissions and appreciating the evidence, the District Forum vide its majority opinion dismissed the complaint of the petitioner outright. The minority judgment however allowed compensation of Rs.73,000/- to be paid by the OP insurance company to the petitioner. After going through the preliminary report of the spot surveyor and the final report of the second surveyor which assessed the loss, the State Commission came to the conclusion that even though there was no cogent evidence to support the huge claim of the petitioner to the tune of Rs.2 Lakhs, the conclusion drawn by the second surveyor in his final report in respect of the entitlement of the petitioner to a net compensation of Rs.7,425/- should not have been ignored by the District Forum. In view of this, the State Commission has rightly set aside the order of the District Forum and given the aforesaid partial relief to the petitioner. Here again the State Commission has recorded reasons for its findings in respect of this partial relief and the same can be reproduced as under:“It is no where stated in the complaint that she got effected the repairs and for getting the repairs she had spent so much money. This is exactly what is decisive of the claim as claim cannot be adjudicated on the basis of estimates. Estimates were only for the purpose of arriving at a figure tentatively. As a matter of fact, the surveyor proceeded to assess the damages at the workshop at Vijayawada carrying with him the estimate, Ex.B10 furnished by the complainant and had come to a firm conclusion that the complainant was entitled to a net amount of Rs.7,425/-. This is rather an amount admitted by the opposite party. The complainant totally failed to adduce cogent evidence to support her huge claim of Rs.2,00,000/-by failing to produce the original bills but at the same time pretending that she so produced without any acknowledgement to that effect nor any reference to such production in the relevant documents especially the claim form marked as Ex.B2. The complainant contended in para 6 of her complaint that she had submitted the original bills to the surveyor, V.V.S.Ram Prasad of Vijayawada appointed by the Divisional Office for conducting the survey of damaged vehicle and it is simply absurd that she could have submitted the original repairs for the repair done amounting to Rs.1,22,190/- as contended by her in the said para for the simple reason that Ex.B12, dated 20-4-2001, the report of Mr.V.V.S.Ram Prasad, specifically referred to his time of survey as having been carried on 12th 14th, 18th and 25th September by which time the vehicle was not at all subjected to repairs as is obvious from the fact that the complainant did not tender any evidence to that effect. Apart from all this, if really the complainant had spent so much money nothing prevented her from filing the affidavit of the person who effected the repairs at Vijayawada workshop and also file if necessary duplicate copies of the bills if really she had ever taken the original bills. Thus the amount claimed is totally unsubstantiated. Nevertheless as per Ex.B12, damage did occur and the damage was translated into monitory terms fixing it at Rs.7,425/. The minority order of the District Forum rendered by the President quantified the relief at Rs.73,000/- comprising Rs.68,000/- plus Rs.5,000/- basing on his appraisal of the photographs. But this is very unscientific as the President himself stated that he worked it out by guess work. The total denial by the minority is also not acceptable. Thus the failure of the opposite party to offer relief in terms of Ex.B12 rather marks a certain amount of deficiency in service for which a suitable relief can be granted. In these circumstances, the complainant has to be granted a relief commensurate with the loss she sustained in the accident as established by the entirety of the evidence in the case. Going by such yardstick, the amount that she can be validly granted would boil down to an amount of Rs.7, 425/as drawn from the only reliable document in this regard. Of-course the complainant is also entitled to the concomitant interest and the proportionate costs as well. ” 11. On perusal of the record including the reports of the spot surveyor as well as the second surveyor, we are of the need to remand the matter. The impugned order having been passed on the evidence placed by the parties, the same is upheld. Consequently, the considered opinion that the State Commission has given a fair and just finding in respect of the entitlement of the petitioner for the damage suffered by her vehicle. We do not see any reason to interfere with this finding of the State Commission. 12. In view of the discussion above, there is no revision petition stands dismissed with no order as to costs. ……………Sd-……..……….. (K.S. CHAUDHARI, J.) PRESIDING MEMBER ……………Sd-….…………… SURESH CHANDRA) bs MEMBER NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI FIRST APPEAL NO. 169 OF 2013 (Against the order dated 19.12.2012 in CC No.02/2009 of the State Commission, Haryana) M/s. Ravindra Spinners Ltd., Through its Director Sh. Anish Singla V.P.O. Kabri, Panipat (Haryana) ……….Appellant Versus 1. National Insurance Company Ltd. Through its Regional Manager SCO No.337-340, Sector 35-B, Chandigarh 2. National Insurance Company Ltd., Through its manager Near Kishore Theater, G.T.Road, Panipat .........Respondent BEFORE HON’BLE MR. VINAY KUMAR, PRESIDING MEMBER For the Appellant : Mr. Arvind Jain, Advocate PRONOUNCED ON: 08/7/2013. ORDER PER MR.VINAY KUMAR, PRESIDING MEMBER M/s. Ravindra Spinners Ltd. has filed this appeal against the order of Haryana State Consumer Disputes Redressal Commission in Consumer Complaint No.02 of 2009. The State Commission has dismissed the complaint on the ground that the claim of the Complainant under the policy had been settled by the respondent/National Insurance Co. with payment of Rs.51.89 lakhs on 14.3.2008, which had been accepted by the Complainant in full and final settlement of the claim. 2. The appeal has been filed with delay of 27 days. Explanation for it is contained in the application for condonation of delay. On perusal of the same the delay is condoned. 3. The records submitted on behalf of the appellant have been perused and Mr. Arvind Jain Advocate has been heard at length on behalf of the appellant. The case of the appellant/complainant, as seen from the complaint filed on 7.1.2009 before the State Commission, was that it had received the amount under coercion/compulsion due to financial constraints. The memorandum of appeal also states that the State Commission has failed to appreciate that the Complainant accepted the amount under pressure and due to financial problem. It is contended that the State Commission failed to appreciate that the ‘full and final’ acceptance cannot be held against the appellant/Complainant as it amounted to reduction of the claim to 75%. 4. Learned counsel for the appellant Mr. Arvind Jain argued that the allegation of coercion/pressure should have been appreciated by the State Commission in the light of the fact that the Complainant had lost everything in the accident of fire and was left with no option but to accept whatever was offered. However, learned counsel clarified that no specific evidence on the plea of coercion had been led before the State Commission. He accepted that no evidence was produced before the State Commission to show that the amount of Rs.51.89 lakhs was received under protest. He also accepted that the discharge slip acknowledging the payment in full and final settlement was signed on 14.3.2008, while the legal notice was issued by the appellant to the respondent/Insurance Company nearly four months thereafter, on 5.7.2008. 5. On consideration of the pleadings and evidence before it, the State Commission has arrived at the following categorical decision:“Having considered the facts and circumstances of the case and the ‘Discharge voucher’, we find force in the contention raised on behalf of the opposite parties. It is well settled law that once the claim has been accepted by the claimant without any objection by signing consent letter in full and final settlement of claim offered by the Insurance Company, thereafter, the claimant cannot be allowed to reopen his claim seeking any further relief. However, mere execution of discharge voucher in the form of letter of indemnity cannot deprive the claimant of consequential relief if discharge voucher was obtained by fraud, misrepresentation or under coercion. There is no evidence on behalf of the complainant that any fraud or misrepresentation or coercive method was adopted by the Insurance Company upon the complainant at the time of signing the discharge voucher and as such the complainant is not entitled for any further compensation.” 6. As seen from the impugned order, the State Commission has relied upon the law as laid down by Hon’ble Supreme Court of India in United India Insurance Vs. Ajmer Singh cotton and General Mills & Ors. Etc. 1999 (2) CPC 601 (S.C) as well as the decision of this Commission in National Insurance Company Ltd. Vs. Kuka Rice & General Mills, 2008 (1) CPC 28 (Haryana). 7. Considered objectively, the pleadings and the evidence led before the State Commission clearly established that:a) That the payment of Rs.51.89 lakhs was received without protest. b) The discharge slip admittedly signed on 14.3.2008 makes it a full and final settlement of the claim. c) It took the Complainant nearly four months to give the legal notice of 5.7.2008 on the ground of coercion/compulsion. d) The consumer complaint itself was filed before the State Commission on 7.1.2009, which makes it almost 10 months from the date of full and final discharge, 14.3.2008. 8. The above facts would by themselves indicate that it is a case of action as an afterthought. The arguments of learned counsel for the appellant would indicate that the Consumer Complaint was filed in the background of the information that the Surveyor had assessed the loss to be Rs.70.5 lakhs while the insured had accepted Rs.51.89 lakhs, in ‘full and final’ settlement. It is thus a case where, as rightly observed by the State Commission, the insured is seeking to reopen his claim for further relief. No evidence was led before the State Commission to show that the acceptance of the appellant/Complainant was obtained by any acts of fraud or misrepresentation or coercion on the part of the respondent/Insurance Company. 9. It is therefore, held that the decision of the State Commission is based on complete and correct appreciation of the evidence on record. There is no ground to interfere with the same. The appeal is therefore, dismissed at the stage of admission itself. No order as to costs. .……………Sd/-…………… (VINAY KUMAR) PRESIDING MEMBER s./- NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 1362 OF 2013 (Against the order dated 14.02.2013 in S.C.Case No.FA/223/2011 of the State Commission, West Bengal) Kotak Mahindra Bank Limited, 7th Floor, C Block, Apeejay House, 15 Park Street, Kolkatta West Bengal- 700016 Through its Authorised Representative ……….Petitioner Versus Partha Pratim Chatterjee S/o Bimal Chatterjee R/O A/1, Ramgarh Colony, Kolkata700047 .........Respondent BEFORE HON’BLE MR. VINAY KUMAR, PRESIDING MEMBER For the Petitioner : Mr. Sourabh Leekha, Advocate PRONOUNCED ON: 8/7/13. ORDER PER MR.VINAY KUMAR, PRESIDING MEMBER Revision petitioner/M/s. Kotak Mahindra Bank has challenged the order of West Bengal State Consumer Disputes Redressal Commission in FA No.223 of 2011. The State Commission has upheld the order of the Kolkata Consumer Disputes Redressal Forum, directing RP/OP to refund a sum of Rs.33,450/- to the respondent/Complainant. The order of the District Forum has been modified to the extent that the direction to pay compensation of Rs.5000/- has been set aside and the costs of Rs.2000/- awarded by the District Forum has been reduced to Rs.1000/. To this extent, the appeal of the RP/OP has been allowed partially by the State Commission. However, on the main issued of refund of Rs.33450/-, there is unanimity of view between the District Forum and the State Commission. Both have ordered its refund. 2. The matter arose out of loan of Rs.301205/- taken by the Complainant from the RP/OP Bank. It was to be paid in 36 instalments. After some default on repayment of the EMIs, the two parties negotiated the matter and research a settlement on 26.03.2009. Under the settlement, the complainant was required to pay Rs.140000/- in four instalments. As seen from the record, the agreed payment schedule was as follows:i) Rs.12,000/- within 30.03.2009 ii) Rs.20,000/- within 30.03.2009 iii) Rs.50,000/- within 30.05.2009 iv) Rs.58,000/- within 30.06.2009 3. The case of the Complainant was that the first three instalments were paid on time. Third instalments was paid with an additional sum of Rs.8000/-. Thus, the balance payable by 30.06.2009 was Rs.50,000/-, which was paid as per the following details:i) Rs.25,000/- on 01.07.2009 ii) Rs.10,000/- on 15.09.2009 and iii) 4. Rs.15,000/- on 26.10.2009. Accordingly, the entire agreed sum of Rs.140,000/- stood fully paid, though the last instalments of Rs.50,000/- was paid with some delay. Set back in business was explained as reason for this delay. In the meanwhile, the respondent/Complainant discovered from the bank statement of account that three monthly ECS payments of Rs.11,150/- each had also been deducted by the bank, without any prior intimation. This amounted to excess repayment to the extent of Rs.33450/-. This is the amount which has been ordered to be refunded by the fora below. While doing so, the District Forum has observed that:“That the petition of complaint is allowed ex parte with cost against the o.p. M/s. Kotak Mahindra Bank Ltd. O.p. is directed to refund the amount of Rs.33450/- (Rupees thirty three thousand four hundred fifty) only to the complainant along with interest @ 8% p.a within 45 days from the date of communication of this order and to pay compensation of Rs.5000/- (Rupees five thousand) and litigation cost of Rs.2000/- (Rupees two thousand) only positively within 45 days from the date of communication of this order, failing which it will carry further interest @ 10% p.a. till full realization.” Similarly, the State Commission has held that:“We have heard the submission made by both sides and perused the materials on record. From the materials on record it appears that the settled amount of Rs.1,40,000/was paid by the respondent/complainant. Vide cheque dated 29/06/09 the respondent paid Rs.25,000/- and thereafter the sum of Rs.10,000/- was paid vide cheque dated 05/09/09. There was the gap of two months and it is contended by the respondent that due to serious illness he could not pay the said insltament on time. Since the settled amount was paid by the respondent, we are of the considered view that the bank ought not to have deducted three instalments by way of ECS, in as much as, there was no intention on the part of the respondent to avoid payment.” 5. The records, as submitted by the revision petitioner, have been perused and Mr. Saurabh Leekha, Advocate has been heard at length on behalf of the petitioner/ Kotak Mahindra Bank. The main argument advanced in justification of the action taken by the bank is that the action of the fora below tantamounts to modifying the terms of the settlement reached between the parties. It is also contended that upon default in timely repayment as per the terms of the settlement, the terms and conditions of the original loan had automatically got revived. 6. The District forum has categorically observed that the RP/OP did not contest the case and therefore was treated ex-parte. In this background, a specific query was put to the counsel for the revision petitioner whether the contention raised in the revision petition was a ground before the District Forum. Learned counsel accepted that it was not raised as the petitioner was treated ex-parte. The contention was therefore raised before the State Commission. Learned counsel however, accepted that no specific justification was offered before the State Commission for deduction of three ECS instalments. It is thus, clear that the contention now raised is a mere attempt to improve the case of the OP at the stage of revision. 7. The fact remains that the petitioner/bank has received payment through the ECS arrangement under the original loan agreement as well as separate payments through cheques, under the settlement. Details as already examined show that the entire amount of Rs.140000/- has been received under the settlement, though the last 25,000/- with a delay of few months. Equally, there is nothing to show that the amount collected under the ECS arrangement, has been recredited to the account of the Complainant after 26.10.2009, when the entire agreed sum of Rs.140,000/- had already been received by the bank. 8. The revision petitioner has sought to rely upon the decision of Hon’ble Supreme Court in Export Credit Guarantee Corpn. of India Ltd. Vs. Garg Sons International, I (2013) SLT 614 in which it was observed that while construing the terms of a contract of a insurance, the words used therein must be given paramount importance, and it is not open for the court to add, delete or substitute any words. The above decision came in the context of a contract of insurance to cover default in payment by a foreign importer. Clause 8 (b) of the Insurance Agreement stipulated the period within which the insurer was to be informed about default, if any, committed by a foreign importer. The ECGC rejected the claim on the ground of non-compliance of this stipulation. It was held that the insured cannot claim anything more than what is covered under the policy. 9. The facts of the case of the revision petitioner stand on a very different footing. The bank has received payments under the subsequent settlement and at the same time granted to itself the ECS payment benefit under the original loan agreement. The fact of excess payment being received in the process is apparent from the record. Therefore, the revision petitioner cannot seek any protection under the terms of the decision of the Apex Court cited on his behalf. 10. In the result, the revision petition is held to be completely devoid of any merit and is dismissed as such. No order as to costs. .……………Sd/-…………… (VINAY KUMAR) PRESIDING MEMBER s./- NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 2248 OF 2013 (Against order dated 22.11.2013 in First Appeal No. 143 of 2012 of the Haryana State Consumer Disputes Redressal Commission, Panchkula) Today Homes Infrastructures Pvt. Ltd., Statesmen House, 8th Floor, New Delhi-110001 …Petitioner Versus 1. Mr. O.P. Ratra M-86 FF, Blossoms-II Sector-51, Gurgaon-122 018 2. Mrs. Harmeet Ratra W/o Mr. O.P. Ratra M-86 FF, Blossoms-II, Sector-51, Gurgaon-122 018 …Respondents BEFORE: HON’BLE MR.JUSTICE J.M.MALIK, PRESIDING MEMBER HON’BLE DR.S.M.KANTIKAR, MEMBER For the Petitioner(s) PRONOUNCED ON : Ms.Ruhi, Advocate JULY, 2013 ORDER PER DR. S.M. KANTIKAR 1. The Revision Petition is filed against the impugned order of Haryana State Commission Disputes Redressal Commission, Hyderabad (in short, State Commission, Haryana) in First Appeal Number 143 of 2012 against the Consumer Complaint No. 722/2009 of District Consumer Disputes Redressal Forum, Gurgaon(in short District Consumer Forum). The Facts in Brief are these. 2. The Respondents/Complainants One Mr. O.P. Ratra and Mrs. Harmeet Ratra had booked two floors in the project of Petitioner/Opposite Party units bearing No. 86 at Ground Floor and First Floor, Blossom-II at Sector-51, Gurgaon. The Complainants wrote a letter on 04.08.2005 to the Petitioner and sought concession of Rs.3,00,000/for the direct booking and deposited Rs.59,40,000/- as a down payment plan for the two floors in total. As per Agreement entered between the Complainants and Opposite Party the possession of unit was to be delivered within 21 Months but the OP offered possession along with final demand notice on 13/8/2007 for the same of Rs.8,28,094/of 29 months as detailed below:. 1. 2. 3. 4. 5. 6. Total Sale Consideration: Early Payment discounts (if applicable) Amount received till date Balance Payable Interest on delayed payment, if any Maintenance Security Rs. 65,07,000/Rs.60,000/Rs.59,40,000/Rs.5,07,000/Rs.2,96,094/Rs.25,000/- 3. The Complainants did not accept the above said offer because of delay of 29 months and by various reasons like the Units and Blossoms II, Complex were (i) not habitable (ii) nor in a capacity of ready to move in with no facilities/utilities, horticulture, water and power supply (iii) no motorable inside roads and proper entry of the complex from the main road. Complainants further alleged that the demand of the OP with respect to interest of Rs.2,96,094/- was wrong as per their letter dated 04.08.2005. OP stated that the delay in offering the possession was due to non-availability or sanction of power supply by the State electricity board. Subsequently on demand from builder the compliant cleared the final payment of Rs.5,32,000/-+ interest of Rs. 1,91,094/- in full and final settlement for Unit No. M 86 (GF & FF) in Blossoms_II, Gurgaon and requested for delivery of physical possession of their Units within one week after completing the leftover work. Thus, the Complainants paid a total sum of Rs.66,88,094/as on 07.06.2008/22.07.2008 including the additional Maintenance Charges (IFMS Charges) worth Rs.25,000/- and again prayer for delivery of physical possession was made. But the OPs further delayed and the physical possession of the Units was given after 41 months i.e. a delay of 20 months and the same was taken by the Complainants on 25-08-2008. As per agreement, the Complainants were entitled for compensation @ Rs.5/- per sq. ft per month for delay of 20 months of the Units which amount to Rs.3,00,000/-. Complainants further sought interest @12% per annum on the deposited amount from the date of each deposit on the total amount of Rs.66,88,094/-. Thus, alleging deficiency in service on the part of the OP, the Complainants filed complaint before the District Forum. 4. The District Forum dismissed the Complaint. 5. Aggrieved by the order of the District Forum the Complainants have preferred an Appeal before the State Commission. The State Commission heard both the parties wherein the Complainants restricted as arguments only with respect to charging of interest of Rs.1,91,094/- by the Respondent-Ops. The State Commission after the appraisal of pleadings and evidence of both parties on record allowed the appeal No.143/2012 with following findings as, “ keeping in view the facts and circumstances of the case and to bring the parties at an equal status, we hold the opposite parties deficient in service for not delivering the possession of the units to the complainant within 21 months and further hold them guilty indulging in unfair trade practice adopted by them for charging interest of Rs.1,91,094/- (Rs.91,094/- through cheque No.901953 dated 07.06.2008 and Rs.1,00,000/- through cheque No.349123 dated 07.06.2008), which could not be charged. The Complainant O.P. Ratra, who is Senior Citizen, has been put to great inconvenience by not delivering the possession of the flat in time and at time and at the old age of 74 years, he has to run from pillar to post to get justice. Keeping in view that the interest of Rs.1,91,094/- was charged by the opposite party, the same is to be refunded to the complainant” 6. Against the said impugned order of State Commission, this revision petition. 7. The learned counsel appearing for petitioner vehemently reiterated the submissions made before the State Commission. We have perused the entire material placed on record and the contentions of both the parties. 8. There is delay of 87 days in filing this revision petition. The petitioner moved an application for condonation of delay and the reasons sated therein are as follows: “a) It is stated that the legal officer of the Applicant Company, who was dealing with the matter, left the Applicants Company office in January 2013. b) It is further stated that after the said legal officer left the Applicant Company, the whole file of the matter along with the certified copy of the order of the State Commission was not traceable, due to shifting of some files for some renovations in the office. c) It is stated that, only when a new legal officer joined the office in May 2013, that the file was traced back and the matter could be revamped”. 9. The petitioner did not explain day-to-day delay. The reasons quoted in the application are not acceptable to us those appears to be vague and imaginary in nature. 10. Considering the merits of this petition; it is very clear from the documents on record that the petitioner had NOT given physical possession of the units to the Complainants after 21 months from the date agreement but the same was delivered after 41 months. Hence, the petitioner delayed the possession for 20 months. This is deficiency in service. The petitioner tried to cover up its deficiency by taking the plea that the delay was caused due to non-availability of the electricity by the Electricity Department and the possession could be taken without the electricity connection. In our view once the Complainants had paid the entire price of the Units the possession should be given with all amenities. The petitioner failed to do so, which is deficiency in service. 11. In our observation the petitioner claim his right to charge interest @ 15% which appears to be unjust and an exploitation of consumers. Hence, Petitioner is charging interest of Rs.1, 91,094/- which was not proper and is an unfair trade practice. As the Complainants are 72 and 68 years old, senior citizen suffered exploitation and inconvenience due to non-delivery of the flat within specified period of time and made him run from pillar to post. 12. In conclusion, we do not find any merit in this petition, as well there is unexplained delay of 87 days filing this revision petition. There is no illegality in the order of State Commission. Therefore, we dismiss this revision petition. No costs. .…..………………………… (J. M. MALIK, J) PRESIDING MEMBER .…..………………………… (S. M. KANTIKAR) MEMBER Mss NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI FIRST APPEAL NO. 327 to 379 OF 2012 (Against the Order dated 27/04/2012 in Complaint Case No. 13/2010 of the State Commission Andhra Pradesh) M/s. Maytas Properties Ltd. (Formerly Maytas Hill County Pvt. Ltd.) Regd. Office at Maytas Hills County Ltd. Through its authorized signatory, Sh. C. Nagaiah, Senior Manager, Bachupally, Miyanpur, Hyderabad Andhra Pradesh … Appellant Versus 1. Bharati Khurana D/o Ramesh Chander Khurana, R/o Pond Ave. Brokline, MA-02445, USA 2. Mrs. Asha Khurana, W/o Ramesh Chander Khurana, R/o 103, New Swastik Apartments, Sector-9, Rohini, New Delhi -110085 Both rep. by their GPA Holder Shri Sandeep Khurana, S/O Mr. Ramesh Chander Khurana, R/o 501, Block -2B, SMR Vinay Acropolis White Fields, Opp. Jayabheri Silicon Valley, Knodapur, Hyderabad PRONOUNCED ON 08.07.2013 ORDER ASHOK BHAN, J., PRESIDENT First Appeal Nos. 327 to 386 of 2012 have been filed by the Appellant/Developer, M/s. Maytas Properties Ltd. (formerly known as M/s. Maytas Hill County Pvt. Ltd.) against the judgments and orders dated 27.04.12 passed by the State Consumer Disputes Redressal Commission, Andhra Pradesh (in short, 'the State Commission') in 60 complaints filed by the Respondents/Complainants wherein the State Commission relying upon its own order passed in C.C. No.30/09 against the very same Developer which was modified by this Commission and upheld by the Hon’ble Supreme Court, allowed the complaints and directed the Developer to refund the amounts deposited by the Respondents/Complainants along with interest @ 12% p.a. from the respective dates of deposit till payment together with compensation of Rs. 1,00,000/- and costs of Rs. 10,000/-. First Appeal Nos. 387 to 400 of 2012 and First Appeal Nos. 14 to 25 of 2013 have been filed by the Appellants, State Bank of India and ICICI Bank Ltd. respectively against the judgments and orders dated 27.04.12 passed by the State Consumer Disputes Redressal Commission, Andhra Pradesh (in short, the “State Commission ”) in 26 complaints whereby the State Commission allowing the complaints has directed the Appellant Banks to recover the loan amount borrowed to the Respondents/complainants from the Developer and credit it to the loan accounts of the Respondnets/Complainants. First Appeal Nos. 717 to 720 of 2012 have been filed by the Appellant/Developer, M/s. Maytas Properties Ltd. against the judgment and order dated 25.09.12 passed by the State Consumer Disputes Redressal Commission, Andhra Pradesh (in short, ‘the State Commission’) in complaint case nos. 79 & 82/09 and 1 & 97/2010 wherein the State Commission allowing the complaints has directed the Developer to refund the amount deposited by the Respondents/Complainants along with interest @ 12% p.a. from the respective dates of deposit till payment together with compensation of Rs.1,00,000/and costs of Rs. 10,000/. First Appeal No.8 of 2013 and First Appeal No.29 of 2013 have been filed by the Maytas Properties Ltd. and the State Bank of Bank respectively challenging the order dated 19.10.12 passed by the State Consumer Disputes Redressal Commission, Andhra Pradesh in CC No.81/09 wherein also the State Commission allowing the complaint has given the same directions as above to the Developer and the Bank. First Appeal Nos. 781 & 783/12 have been filed by the Developer and the State Bank of India respectively against the common judgment and order dated 5.11.12 passed by the State Consumer Disputes Redressal Commission, Andhra Pradesh in CC No.75/10 wherein State Commission allowing the complaint has given the similar directions to them. State Commission dismissed the complaints against the land owner companies. Since the Developer had executed sales deeds in favour of some of the Respondents/Complainants, the State Commission has directed those Respondents/Complainants to re-convey the property to the Developer on receipt of refund of the amount. It is pertinent to mention that the State Commission has segregated the complaints into several categories and disposed of them by similar orders dated 27.04.12. The complaints in which the Bank was not a party and where loans were not availed of, were disposed of by 2 separate but similar orders. The complaints in which banks/financial institutions were made parties had been disposed of vide 5 separate but similar orders. The banks/financial institutions which were arrayed as parties in the complaints are, State Bank of India, ICICI Bank Ltd. IDBI Bank, Axis Bank Ltd. BHW Home Finance. All the orders passed by the State Commission are identical, in addition to the directions of refund to the Developer where the Banks are also made a party. Since the question of law and facts involved in all these Appeals are the same, we propose to decide all the Appeals by a common order. AVERMENTS MADE IN THE COMPLAINT:Appellant/Developer, M/s. Maytas Properties Ltd. (hereinafter to be referred to as “the Developer”) - entered into a Development Agreement cum General Power of Attorney bearing No. 102/206 dated 30.12.05 with the 14 land owner companies for development of Ac. 85.36 Guntas of land situated in Survey No. 192/P to 198/P, 201/P and 282/P at Bachupally Village, Qutubullapur Mandal, Rang Reddy District. Developer obtained layout permission from Hyderabad Urban Development Authority (HUDA) on 21.03.06 for development of a township known as “Maytas Hill County” consisting of 364 independent villas and multistoried residential apartments together with facilities like club apartments, parks, open spaces, gym, health clubs, playgrounds, shopping centre etc. Developer further entered into agreements of sale with the Respondents/Complainants (hereinafter to be referred to as the “Respondents”) for booking of flats/villas/apartment. As per agreements of sale, the sale consideration was agreed to be paid in installments, i.e., 10% of the sale consideration on the date of booking, another 10% within 15 days from the date of booking and remaining in phased manner and 5% at the time of handing over the possession of the flat. Some of the Respondents approached the Appellant Banks for grant of housing loan. The Appellant Banks agreed to grant the home loan as per tripartite agreements executed between the Bank, Developer and the Respondents. Developer executed registered sale deeds in favour of some of the Respondents in respect of undivided share of land together with unfinished structure. As per Agreements of Sale, construction of the flats/apartments was to be completed within one year with a grace period of three months. On 07.01.09, founder of M/s. Satyam Computer Services Ltd., Shri Ramalinga Raju confessed that he had diverted the funds from Developer to computer services and, therefore, there could be delay in completion of the project. Criminal proceedings were initiated against the Directors of the Developer. There was an award passed against the Developer for Rs.600 crores together with interest of Rs.221 crores. Respondents alleged that the Developer was deficient in rendering service by not completing the construction within the stipulated time and in diverting the funds; that they could not collect more than 20% towards advance as per Section 5 of the Andhra Pradesh Apartments (Promotion of Construction and Ownership) Act, 1987; that the Banks had disbursed the entire loan amount to the Developer without any physical verification or valuation by a valuer of the construction contrary to the agreement of sale and tripartite agreement. Complainants, being aggrieved, filed the complaints before the State Commission. STAND TAKEN BY THE DEVELOPER On being served, Developer entered appearance and filed its written statement contesting the complaints on the grounds; that the Developer commenced the project as per schedule but on a wholly incorrect understanding of Developer’s association with Mr. B. Ramalinga Raju, Founder of M/s. Satyam Computer Services Ltd. the various investigations and proceedings were instituted against the Developer; that the Banks/financial institutions which had committed funding withdrew from the project as a result of which the project could not be developed; that the delay in completion of the project was due to ‘force majeure’ which was beyond the control of the Developer; that the Developer constructed and delivered possession of 140 independent houses to some of the purchasers and 172 houses were in final stages; that pursuant to the enquiries initiated against M/s. Satyam Computers Ltd. the case of the Developer was referred to the Company Law Board (in short “CLB”) which appointed SBl Capital Markets Ltd. (in short “SBl Cap”) as transaction Advisor; that the CLB passed an order dated 13.01.11 inducting M/s. Infrastructure Leasing and Financial Services Ltd., M/s. IL&FS Financial Service Ltd. and M/s. IL & FS Engineering and Construction Company Ltd. into the company as shareholders by allotting preferential shares; that the Board of Directors of the Developer was re-constituted; that the new Board of Directors made efforts to arrange further funds to complete the project; that the complaints filed by the Respondents before the State Commission were not maintainable as in terms of Agreements of Sale in case of any dispute the matter was required to be referred to the Arbitrator for resolving the same; that by virtue of the orders passed by the CLB on 05.03.09 and 13.01.11, the complainants could not seek relief before the consumer fora and they were required to approach the CLB. STAND TAKEN BY THE APPELLANT BANK Appellant Banks, in the cases where the home loan was obtained by the Respondents/Complainants, contested the complaints on the grounds; that the Respondents, Developer and the Bank entered into a tripartite agreement and the Bank had disbursed the loan amount against the mortgaged property directly to the Developer on behalf of the Respondents as per agreed terms of the tripartite agreement; that the disbursement of loan to the Developer was not on the basis of different stages of construction of the flats but was on the basis of the due date fixed for payment as per agreement of sale; that as per tripartite agreement, the Developer and the Respondents were liable to indemnify the Bank against any risk which might arise on account of any defect in the title to the property; that the Respondents could not stop payment of EMIs on the ground that the Developer failed to complete the construction or hand over possession of the flats; that the Respondents were estopped from making any claims in the light of the terms of tripartite agreement. During the pendency of the complaints before the State Commission, the Developer moved Miscellaneous Applications seeking dismissal of the complaints on the ground that the complaints were not maintainable in view of the arbitration clause in the agreements of sale. That as per Arbitration Clause in case of dispute, the matter was required to be referred to the Arbitrator and the jurisdiction of the Civil Court/any other forum was ousted by the said Arbitration Clause. The said applications were dismissed by the State Commission holding that the Consumer Fora constituted under the Consumer Protection Act, 1986 had the jurisdiction to try, entertain and adjudicate upon the complaints as per law laid down by the Apex Court in catena of judgments. Feeling aggrieved, Developer filed Writ Petitions (27689/10 and batch) before the Andhra Pradesh High Court which were dismissed by observing as under:“ Having regard to the interpretation given by the Supreme Court in FAIR AIR ENGINEERS PVT. LTD ( supra) with regard to Section 3 of the 1986 Act and the ratio in LUCKNOW DEVELOPMENT AUTHORITY (supra), we are of the view that the 1986 Act, being a special enactment, created an additional remedy in favour of the consumers to raise consumer disputes before the Fora constituted under the said Act, and that Section 8 of the Arbitration Act does not have the effect of taking away such a remedy from the consumers as in the case of civil suits, which are in the nature of common law remedies. If a party chooses to avail a remedy other than the consumer dispute, he shall be free to do so because the remedy under the 1986 Act is not in derogation of the other remedies available to such a party and he cannot be denied such right on the ground of availability of an alternative remedy, such as Arbitration Act as Section 3 of the 1986 Act is intended to provide an additional remedy to a party and the same is not meant to deny such a remedy to him. Further, by virtue of Section 17 of the Consumer Protection Act the parties can undoubtedly resort to filing of the complaint as specified under section 17 of the Consumer Protection Act The restriction as to the inherent jurisdiction would not come in the way for the complainant to file the complaint, provided he fulfils the conditions mentioned in section 17 of the Consumer Protection Act. ” Developer, being aggrieved, filed SLP (C) No. 30367/11 which was dismissed as withdrawn by the Supreme Court vide order dated 18.11.11 with the following observations:“ If the petitioners file an appeal before the National Consumer Disputes Redressal Commission (for short, ‘the National Commission’) within 30 days and apply for condonation of delay then the prayer shall be considered by the National Commission on its own merits and decided keeping in view the fact that the petitioners had been pursing remedy before the High Court. It is needless to say that the National Commission shall decide the appeal uninfluenced by the observations made in the order passed by the High Court.” State Commission, after taking into consideration the facts, pleadings and the evidence led by the parties, came to the conclusion that the Developer was deficient in rendering service by not completing the construction of the flats/handing over the possession of flats within the stipulated time as per Agreements. State Commission relying upon its earlier judgment passed in Complaint Case No.30/09 against the same very Developer which was modified by this Commission and upheld by the Hon’ble Supreme Court, allowed the complaints and directed the Developer to refund the amounts deposited by the Respondents/Complainants along with interest @ 12% p.a. from the respective dates of deposit till payment together with compensation of Rs.1,00,000/- and costs of Rs.10,000/-. Since, in some of the cases the Sale Deeds were executed in favour of the Respondents, the State Commission directed the Respondents to re-convey the property to the Developer on receipt of the refund of the amount. Complaints against the land owner companies were dismissed. State Commission held the Developer deficient in rendering the service by observing as under:“26. Since the developer could not prove the stages of construction or that it would hand over possession within a reasonable period, and the period that was originally stipulated was already expired, and all through the complainants have been paying EMIs, we are of the opinion that it would be unjust that the complainants be directed to go on paying the amounts to the banks without there being any hope of getting the project completed. 27. The Complainant by issuing notice to the developer cancelled the above said agreement and directed the Developer to pay the consideration received so far, as no construction was taken up nor completed, and sought for refund of the amount with penalty @ Rs.5/- per sfts. as per clause 7 (a to d) of the agreement. However, we do not see any justification in impleading the original owners of property, who have no subsisting interest in the property. They have parted their title in favour of the Developer. Therefore, the claims against them do not sustain. The complaints are liable to be dismissed against them…. 29. In some of the cases, sales deeds were executed in favour of the complainants by the developer conveying the title. Obviously, the complainants cannot have title as well as refund of the amount, since the very sale has been frustrated, in such a case, when the developer has executed the sale deed and there is no prospect of either constructing flats or delivering the property to the complainants, the Hon’ble Supreme Court in somewhat similar case Vinod Kumar Thareja Vs. M/s. Alpha Construction reported in CPJII (2011) CPJ 3 SC while giving direction to refund the amount also directed to re-convey the property to the builder. Therefore, we direct the complainants to execute reconveyance deed on receipt of amount payable by the developer. The registration charges shall be borne by the developer. This is in conformity with the above said decision of the Hon’ble Supreme Court. 30. We may also state herein that the orders of this Commission against the same developer (vide C.C.No.30/2009) directing to refund the amount with interest @ 12% p.a has been upheld by the National Commission in F.A. No.189/2010 while reducing the compensation from Rs.5 lakhs to Rs.1 lakh. The SLP moved by the developer before the Hon’ble Supreme Court in Appeal (Civil) No. 26256/2010 was dismissed on 27.09.10. Therefore, these matters are covered by the above decisions and there is no need for any distinction to be made between these cases. These contentions do not sustain.” IL & FS which was inducted and permitted to complete the project by the CLB vide its order dated 13.01.11, raised an additional plea which was not raised earlier by the Developer in Complaint Case No.30/09 that by virtue of orders of the CLB dated 05.03.09 and 13.01.11 which were passed with the consent of Respondents, the Respondents could not seek the relief before the consumer fora and they ought to have approached the CLB for redressal of their grievances. The said contention was rejected by the State Commission on the grounds; that neither the Respondents were a party to the proceedings pending before the CLB nor were they issued any notice by the CLB; that the orders passed by the CLB were not binding upon the Respondents and did not bar the consumer fora to decide the complaints filed by them. In the complaints in which the Banks/Financial Institutions were made a Respondent Party, State Commission held that the Appellant Banks/Financial Institutions were deficient in rendering service in disbursing the loan amount to the Developer without verifying the stage and nature of the construction. State Commission also held that the Respondents were not liable to pay any further EMIs. State Commission directed the Banks/financial institutions to recover the loan amount plus whatever interest due from the Developer and credit it to the loan account of the Respondents. State Commission observed as under:“ The bank has undoubtedly violated the terms of the tripartite agreement and released the amount even without bothering to verify as to the stage and nature of construction. In other words, the bank financed to a non-existent project or incomplete project, duping its own customers. Now the complainants would be unnecessarily hard pressed to pay the amounts towards EMI without there being any hope of getting the apartments as the developer is under winding up proceedings. The bank cannot take advantage of its own indiscretion. This is unjust and unethical. If the bank released the amounts contrary to tripartite agreement it has to suffer for the consequential losses. Whatever loss caused thereby it could as well as approach appropriate forum for recovery of the amount from the developer, to which it has released the amount in one go. The bank under the terms entitled to recover from the developer to which it had paid the amounts. It cannot turn round and claim against the complainants. It is not under original stipulation that the bank had to pay the entire amount to the developer. The developer also agreed to refund the amount if there are cancellations of the agreement or failure to fulfill its commitments. The agreement that was arrived at earlier was fair and no party would benefit from the lapses or mistakes of the other. Therefore, the complainants are not liable to pay the EMIs. “ The Bank has to collect the loan amount plus whatever interest and other legally permissible charges from the developer and credit it to the complainant’s loan account. It shall not collect further EMI’s nor entitled to any more amount except the amount, if any, remained unpaid by the complainants towards loan granted to him. The Bank has no authority to complain to CIBIL. In fact if there is a provision, the CIBIL has to enter the name of the bank, as one of the violators of guidelines of the banks.” Feeling aggrieved, the Developer as well as the Banks have filed the present appeals. We have heard the Ld. Counsel for the parties at length. SUBMISSIONS MADE IN FIRST APPEAL NOS. 327 TO 386 OF 2012, 717 TO 720 OF 2912, 781/12 AND 8/13 FILED BY THE DEVELOPER Ld. Senior Counsel, Shri A.M. Singhvi, appearing for the Developer contends that the expiry date of construction was not the same for all the agreements of sale as the agreements of sale were executed on different dates till the end of the year 2009; that since the project was abandoned midway and construction activity came to a standstill for a period of two years after the Satyam scam; the purchasers under the misapprehension that the project will not be completed, stopped paying the installments and the various Investors/Banks/Financial Institutions which had committed funding of the project, also withdrew from the project; that due to acute shortage of funds the development of the project was jeopardized; that various attachments and court orders also delayed the project; that pursuant to the inquiries initiated against M/s. Satyam Computers Services Ltd., the case of the Developer was referred to the CLB; that CLB vide order dated 13.01.11 inducted IL & FS group as the new promoter of the Developer and consequently the Board of Directors of the Developer was re-constituted; that with the new arrangements made by the CLB, the Developer has completed 9 out of 11 Apartment Towers of the “Hill Country Project”; that the Developer is in a position to hand over the possession of the flats to the Respondents; that by virtue of order dated 13.01.11 passed by the CLB, the Respondents could not seek remedy of their grievances before the Consumer Fora; that the State Commission erred in holding that the order passed by the CLB was not binding upon the Respondents as they were not a party before the CLB; that no individual notices were required to be given to the Respondents as the Respondents were represented by the Hill County Home Owners Welfare Association, a body representing the interest of all the purchasers; that the Hill County Home Owners Welfare Association was impleaded as a party by the CLB and the arrangements were made by the CLB with the consent of the Association; that the State Commission has erroneously directed the refund of the deposited amounts to the Respondents on the presumption that the order of CLB had not been complied with and there was no progress in the construction; that in most of the complaints, Respondents had prayed for handing over of the possession of the finished flats and in the alternative for refund of deposited amount but the State Commission by a blanket order has directed the refund of amount to all the Respondents; that pursuant to the order dated 13.01.11 passed by the CLB, IL&FS Group had infused Rs.425 crores to meet the commitments of the Hill County Project and the Developer has no funds to pay the dues either to the Respondents or the Bank; that if the funds are diverted in making refunds to the Respondents or paying amounts to the Bank, it would be at the cost of the other customers of the “Hill County Project” as the project may not be completed due to lack of funds; that the State Commission erred in observing that there was no evidence on record to show as to what was the stage of construction when the additional affidavit of the Developer was on record giving all the details about progress in construction; that the application filed by the Developer for appointment of Commissioner to inspect the stage of construction was illegally rejected by the State Commission; that the delay in completion of the construction and handing over of the finished flats to the Respondents had occurred due to ‘force majeure’ events which were beyond the control of the Developer; that the project is near completion and the new Promoters will not charge any penal interest on the delayed payment and also not charge for any escalation in cost of construction. Ld. Senior Counsel appearing for the Developer further submitted that the State Commission wrongly proceeded to pass orders in favour of the Banks/Financial Institutions as if they were complainants before it; that after the Satyam Episode in 2009, Respondents started defaulting in making the payments of installments to the Banks/Financial Institutions; that the Developer has been meeting Banks/Financial Institutions periodically to help the Respondents to arrive at settlement and for restructuring of their loans; that there was no occasion or reason for the Respondents to apprehend about fate of the project or to stop making payment of their EMIs to the Bank and, therefore, there was no justification in shifting Respondents’ liability towards the Bank to the Developer; that the State Commission has held the Banks/Financial Institutions deficient in service and, therefore, the Banks/Financial Institutions should restructure the Respondents’ loan account. SUBMISSIONS MADE IN FIRST APPEAL NOS. 387 TO 400 OF 2012, 783/12, 29/13 AND 14 TO 25 OF 2013 FILED BY THE STATE BANK OF INDIA AND ICICI BANK LTD. Financial Institutions other than State Bank of India and ICICI Bank Ltd. have not challenged the orders passed by the State Commission. The orders passed against the Financial Institutions other than State Bank of India and ICICI Bank Ltd. have attained finality. Ld. Counsel appearing for the Appellant State Bank of India contends that the Appellant cannot be fastened with any liability to collect the loan amount from the Developer and the Respondents cannot be granted liberty not to pay the EMIs to the Appellant Bank; that it was agreed between the parties that the payment of the sale consideration of the flats would be made in installments on due dates fixed in the Agreements of Sale; that the disbursement of loan amount to the Developer directly was not linked to the stage of construction and, therefore, the bank was not liable to review the progress of construction; that as per clause 7 (a) of the tripartite agreement in the event of cancellation of allotment of schedule property by the Developer, the Developer was liable to pay all amounts received by it from the Bank on behalf of the Respondents and, therefore, in the present case as the allotment was not cancelled by the Developer, the Bank was not liable to recover the loan amount from the Developer; that there was no “Debtor – Creditor relationship” between the Developer and the Bank and the amounts were released to the Developer on the basis of duly signed disbursement request forms submitted by the Respondents and as such it is not open for the Bank to claim the recovery of the loan amount from the Developer. Ld. Counsel appearing for the Appellant Bank further contends that no complaint under the Consumer Protection Act, 1986 was maintainable against the Appellant Bank as they had acted under the agreed terms and conditions of the loan agreement; that the Respondents cannot escape the liability of making the payment of loan to the Banks and the Banks could not be made liable to collect the loan amount from the Developer; that if the construction of the project was not completed by the Developer, the Respondents were at liberty to take appropriate action against the Developer but that cannot be the ground for the Respondents to seek a declaratory relief or direction not to insist for repayment of the loan amount; that the State Commission erred in holding that the Appellant Bank did not try to recover the loan amount from the Developer by invoking clauses of tripartite agreement; that the home loan was granted to the Respondents for purchase of the residential property and the Appellant Bank is legally entitled to recover the dues from the Respondents. Ld. Counsel appearing for the Appellant, ICICI Bank Ltd. submits that the Appellant Bank in all the 12 appeals have disbursed the loan amount based only on the duly signed disbursement request forms submitted by the customers and there has been no direct disbursement; that the Appellant Bank has not disbursed the entire loan amount at one go. SUBMISSIONS MADE ON BEHALF OF COMPLAINANTS IN BOTH SET OF APPEALS THE RESPONDENTS/ Ld. Counsel appearing for the Respondents/Complainants contends that the direction to the IL&FS Group to complete the Maytas Hill County Residential Project Phase I within 18 months of its induction as Promoter by the CLB order dated 13.01.11 would not preclude the individual Respondents from agitating their rights in the complaints filed by them before the Consumer Fora; that the orders passed by the CLB were not binding upon the Respondents as they were not member of the Hill County Home Owners Association which participated in the proceedings before the CLB; that the Respondents were not issued any individual notice by the CLB; that the order dated 13.01.11 passed by the CLB was not in the nature of a scheme under the provisions of the Companies Act, 1956 and, therefore, the present batch of Appeals would have to be decided on its merit; that most of the Respondents had prayed only for refund of their amounts and the remaining Respondents who sought for alternative reliefs had categorically given up their claim for finished flats before the State Commission and restricted their claim for the refund of their amounts; that the State Commission taking into consideration the fact that the project was nowhere near completion, directed the Developer to refund the amounts paid by the Respondents; that in case the project is completed, the Developer can sell the flats in the open market at current market rates which will fetch more money for the Developer than the amounts at which they were agreed to be sold to the Respondents herein; that the Respondents are not interested in the allotment of the flats as they are facing litigations initiated by the Bank under the provisions of The Securitization and Reconstruction of Financial Assets and Enforcement of Security Interest Act, 2002, The Recovery of Debts due to Banks and the Financial Institution Act, 1993 and The Negotiable Instruments Act, 1881; Ld. Counsel for the Respondents vehemently argued that as per Clause 13 (c) of the Loan Sanction letter and as per clauses of the tripartite agreement the Appellant Banks were obligated to release the home loan amounts in phases to the Developer on the basis of progress of the construction; that the Appellant Banks in collusion with the Developer disbursed the entire home loan amount along with the contribution of the Respondents before the commencement of construction at the project site and even without verifying the existence of the approved building plans; that as per tripartite agreement executed between the parties, in the event of cancellation of allotment of flat the developer was liable to refund the entire loan amount to the Appellant within a period of 60 days but the Appellant Banks did not initiate any steps for recovery of the loan amount from the Developer; that if the Respondents take possession of their respective flats, the Appellants Bank would immediately initiate proceedings for attachment of the Flats towards recovery of the alleged dues; that the Appellant Banks cannot have any grievance against the order dated 27.04.12 passed by the State Commission as their interest has been adequately protected by granting liberty to recover the entire loan amount from the Developer; FINDINGS IN FIRST APPEAL NOS. 327 TO 386 OF 2012, 717 TO 720 OF 2912, 781/12 AND 8/13 FILED BY THE DEVELOPER M/s. Maytas Properties Ltd. – Developer – entered into individual agreements of sale/construction with each of the individual Respondents. The relevant clause from one of the agreements of sale is reproduced herein for ready reference:“3. Construction (a) Having received the consideration specified in Schedule 2, the first party agrees to complete the construction of the apartment in a timely manner by 31st December, 2008 subject to the availability of the steel or other construction material and other causes beyond the control of the first party. (b) months. The first party shall have a further grace period of three (c) The first party shall be entitled to further periods if the construction is delayed due to flooding, due to rain, war, earthquake, fire, stay of construction by any Court or authority or any other emergencies including riots and any terrorist activities, etc.; (d) In the event of any further delay beyond time stipulated in Clause 3 (a), 3(b), and 3(c), the first party shall pay the second party an amount of Rs.5 per sq. feet of contracted built-up area for every month or delay or part thereof upto a maximum of 8 months. After lapse of such extended period of 8 months, the second party can terminate this agreement and seek for immediate refund of total consideration amount paid to the first party i.e. the sale consideration amount and the construction agreement consideration amount alongwith the Corpus Fund as defined vide Clause 1 (c) above and the first party shall refund the amount within 30 days from the date of such termination. “ The individual sale agreements entered into by the Respondents specified a payment schedule to the Developer. Some of the Respondents paid the entire sale consideration from their own pocket. Since some of the Respondents after having paid the initial amount towards their contribution to the Developer, wanted to avail home loans, the Developer approached the various Banks/financial institutions to render financial assistance to them which is evident from the following clause of the tripartite agreement entered into between the Developer, the Banks/Financial Institutions and the Respondents:“AND WHEREAS the Developer has approached SBI to render financial assistance for the construction of dwelling units to such of its dwelling unit purchaser/members as may be in need thereof and in consideration of SBI doing so in accordance with its lending policies” Banks/Financial Institutions agreed to grant home loans to the Respondents in terms of the tripartite agreement executed between the Banks, Respondents and Developer. Some of the relevant clauses from one of the tripartite agreement wherein Bank/Financial Institution was a party, are reproduced herein for ready reference:“2. SBI shall make disbursement of the sanctioned loan by making payments to the Developer directly on behalf of the borrowers and payment(s) made to the Developer shall be deemed to be payment(s) made to the borrowers and the borrowers shall in each case be liable for the amount of the loan disbursed on his/her behalf to the Developer, as though the same has been disbursed directly to him/her. It is further agreed by the borrower that SBI shall not be responsible or liable to ensure or ascertain the progress of the construction and mere demands for disbursement would be sufficient for SBI to effect disbursement as aforesaid. However, SBI at its sole discretion, shall disburse the loan in suitable installments, at the request of borrower/Developer or in suitable installments to be decided by SBI with reference to need or progress of construction, which decision shall be final and binding on the borrower(s)/Developer. The borrower shall be responsible to follow up with SBI to make disbursement on his/her behalf as per any agreement, payment schedule he/she may have with the Developer. Notwithstanding anything to the contrary contained herein, SBI may in its sole discretion refuse to disburse the loan until; (a) Borrower(s) has/have paid his/her own contribution in full to the Developer (the cost of the dwelling unit less the loan) and the progress and need of the construction justifies the disbursement requested. 6. That in the event of cancellation of allotment to the borrower by the Developer for any reason whatsoever the Developer shall refund to SBI only forthwith the entire amounts received from SBI within 60 days subject to clause No. 7 below. The balance if any after adjusting the dues, interest, costs and other amounts recoverable by the SBI, shall be returned to the borrower by SBI. The Developer herein undertakes not to refund any amount, on any account, under any circumstances to the borrower without the written consent of SBI. 7(a) Upon cancellation of the allotment of the schedule property to the borrower for any reason, the Developer shall immediately intimate about the same in writing to SBI. Upon receipt of such intimation, SBI shall notify the Developer all amounts due to it from the borrower. In such an event, the Developer shall forthwith pay SBI all amounts received by it from SBI on behalf of the borrower within 60 days of receipt of such statement during which period, the Developer shall pay interest to SBI, at the rate of interest on such amount shall be the same as agreed between the SBI and borrower in the loan agreement. (b) Further, the Developer hereby agrees that it shall also pay all the remaining amounts due and payable to SBI from the borrower such as defaulted payments, additional interest etc. after deducting reasonable expenses (as agreed by both Developer and SBI) incurred by the Developer from the sale proceeds of the property” After entering into tripartite agreements, the Banks/Financial Institutions sanctioned the home loans to the Respondents. The loan agreements were executed between the Banks/Financial Institutions and the Respondents. As per loan agreements, in case of any delay in the payment of EMI, the borrower was liable to pay an additional interest and other penal charges. Relevant clause of one of the sample loan agreements, entered into by one of the Respondents with the BHW Home Finance Ltd. reads as under:“2.6 Delay in payment of EMIs/PEMIIs/Interest/ other dues, etc. (b) the delay in payment of EMIs/PEMIIs/Interest or any other dues shall render the borrower liable to pay additional interest at the rate of 24 per cent p.a. or at such higher rate as per the rules of BHW Home Finance Ltd. in that behalf as in force from time to tie. In such event, the borrower shall also be liable to pay incidental charges and costs of BHW Home Finance Ltd. “ After the sanction of the loans, both the Banks and the Financial Institutions disbursed the entire and/or substantial loan amount to the Developer contrary to the terms of the tripartite agreement which have been extracted hereinabove. Developer after making some initial construction completely abandoned the project in 2008. One of the purchasers of the flat filed complaint No.30/09 before the State Commission which was allowed by it directing the Developer/Opposite Party to refund the deposited amount with interest @ 12% p.a. from 4.08.08, i.e., the date of payment of the last installment by the complainant together with compensation of Rs.5 lakh and costs of Rs.5,000/-. Developer, being aggrieved, filed First Appeal No.189/10 which was disposed of by this Commission vide order dated 12.08.10. This Commission modified the order of the State Commission to the extent that the amount of compensation was reduced from Rs.5,00,000/- to Rs.1,00,000/-. Developer challenging the order passed by this Commission filed SLP (C) No. 26256/10 which was dismissed by the Supreme Court by its order dated 27.09.10. During the pendency of the present proceedings before the State Commission, the Central Government filed an application before the CLB under the provisions of the Companies Act, 1956 seeking change of management of the Maytas Properties Ltd. During the course of proceedings before the CLB, competitive bidding took place wherein 28 companies evinced expression of interest to take over the project and the assets and liabilities of the Developer. Out of 28 companies which had evinced expression of interest, 9 responded and out of 9, IL&FS and GVK Group submitted their concrete proposals. SBI Capital Market was the Advisor for transaction. M/s. Maytas Properties Ltd. submitted Company Application No.24/11 before the CLB On 13.01.11 wherein a prayer was made to induct IL&FS as promoter. The application was unopposed and was allowed by accepting the entire proposal made in the application, on the same date. CLB vide its order dated 13.01.11 permitted IL&FS group to be the new promoter of the Developer wherein it would acquire 80% in equity share capital by investing Rs.20 lakhs. IL&FS Group was permitted to take over the management control of the Developer and reconstitute the Board of Directors whereby it would have 4 nominees as Directors including the Chairman. IL&FS Group was to mobilize the fund of Rs.150 crores within a period of three months from the date of order. IL&FS Group was to complete the Maytas Hill County Residential Project Phase I within 18 months of its induction. It was required to arrange the finances to complete the project. It was also ordered by the CLB that the IL&FS Group shall settle all disputes, tax liability and the contractual dues and other creditors of the Developer. During the course of final arguments on 16.05.13 and 22.05.13 in the present batch of Appeals, the Ld. Senior Counsel, Shri A.M. Singhvi, appearing for the Appellant/Developer fairly conceded that the CLB proceedings/orders did not bind this Commission in any manner whatsoever inasmuch as the order of 13.01.11 was not in the nature of a scheme under the provisions of the Companies Act, 1956. That this Commission would have jurisdiction to decide the appeals on their merit by taking into consideration the overall facts and circumstances. Ld. Senior Counsel appearing for the Developer sought to contend that the order dated 13.01.11 passed by the CLB was a consent order and the Respondents herein were allegedly bound by it as they were represented by the Hill County Owners Welfare Association. Similar contention raised by the Appellant/Developer before the State Commission was rejected by it by observing that there was no proof that the Respondents were members of the said Association or that any notice was served upon the Respondents individually in order to bind them. The Respondents had categorically stated that the Hill County Owners Welfare Association did not represent their interests. That till date the Developer had not even bothered to implead the Respondents before the CLB. According to the Respondents, the Hill County Owners Welfare Association was acting in connivance with the Developer as it was present before the CLB on the first day itself on 13.01.11 when the period of 18 months was given to the Developer to complete the project. During the pendency of the Appeals, the period to complete the project has been extended by the CLB till 30.06.13. The project is not complete as yet. It may be mentioned here that the Hill County Owners Welfare Association filed an Interim Application No.3141/13 before this Commission seeking impleadment which was later on got dismissed as withdrawn reserving liberty with the Association or members other than the Respondents herein to start independent proceedings. We do not find any substance in the contention raised by the Ld. Senior Counsel for the Developer that the order dated 13.01.11 passed by the CLB could be termed as a consent order on behalf of the Respondents in the present Appeals. The presence of some advocates on behalf of the Hill County Owners Welfare Association who did not oppose the prayer made in the C.A.No.24/11 filed by the Developer would have no impact on the complaints filed before the State Commission. There is nothing on record to show that the said Association represented the interests of the Respondents herein. Any consent given by an advocate on behalf of that Association for the completion of the project would not tantamount to waiver of the rights of the Respondents. As per averments made by the Respondents, the said Association has been acting in connivance and behest of the Developer and does not represent the interest of the Respondents who had filed their complaints much prior to the passing of the order by the CLB. It may be mentioned here that a majority of the Respondents have formed their own Association which is duly registered in the name and style of M/s. Maytas Hill County Apartment Buyers Association. For the reasons stated above, it is held that the order dated 13.01.11 passed by the CLB cannot be taken as a consent order on behalf of the Respondents herein. Ld. Senior Counsel appearing for the Developer strenuously contended that the State Commission erred in directing the Developer to refund the amount contrary to the prayer made in the complaints. That majority of the Respondents had asked for possession of the finished flats as the main relief and had sought the relief for refund of the amount in the alternative. We do not find any substance in this submission as well. Out of the 66 Appeals, 39 Respondents had prayed for possession of the finished flat as the main relief and the relief for refund of the amount in the alternative. 27 Respondents herein had prayed for refund of their amounts only. 39 Respondents who had sought the possession of the flat as the main relief had categorically given up their claim for finished flats before the State Commission and confined their relief for the refund of the amount only. State Commission taking into consideration the fact that the project was nowhere near completion, directed the Developer to refund the amounts deposited by the Respondents. We do not find any infirmity in this finding. The project is still not complete. At the time of admission hearing of the appeals on 10.07.12, the Ld. Counsel appearing for the Developer had stated before us that out of 11 towers, 9 were near completion; that the Respondents/ Complainants will be handed over the flats as per agreement between the parties within a reasonable time at the old rates subject to the Respondents paying the balance amount; that the Appellant shall suitably compensate the Respondents for delayed handing over of the possession. On the basis of his submissions, this Commission passed the following order on 10.07.12. “ Counsel for the appellant states that out of the 11 towers, 9 are near completion; that the complainants/respondents will be handed over the flats as per agreement between the parties within a reasonable time which shall be submitted before the Commission at the old rates subject to the Respondents paying the balance amount; that the appellant shall suitably compensate the respondents for delayed handing over of the possession. Seek time to get firm instructions and put the same on affidavit. Undertakes to file the affidavit before the next date of hearing with an advance copy to the Respondents.” Subsequently, on a statement made by the Ld. Counsel for the parties that certain developments had taken place after passing of order by this Commission on 10.07.12, the following order was passed on 15.01.13:“ Ms.lndu Malhotra, learned senior counsel appearing on behalf of the respondents in majority of the cases has brought to our notice that a similar order passed by the State Commission has been upheld by this Commission in F.A. No.189/2010 against which SLP was filed which has been dismissed. Learned counsel appearing for the appellant submits that certain developments have taken place after the passing of the order by this Commission; that IL&FS, a new promoter, has stepped in and has taken over the assets and liabilities of the previous promoter; that Company Law Board (CLB) by its order dated 13.1.2011 permitted the IL&FS to step in and take over as a new promoter and develop the property within the time frame of 18 months. Buildings have not been completed in spite of the lapse of 18 months. New promoter has neither applied for nor got extension of time from CLB. Learned counsel for the appellant submits that in view of the subsequent developments, the decision rendered by this Commission in the earlier case is not binding. On 10.7.2012, counsel for the appellant had made a statement before us that out of 11 towers, 9 are near completion; that the complainant/ respondents will be handed over the flats as per agreement between the parties within a reasonable time which shall be submitted before this Commission at the old rates subject to the respondents paying the balance amount; that the appellant shall suitably compensate the respondents for delayed handing over of the possession. Appellant had taken time to file the affidavit before the next date of hearing with an advance copy to the respondents. Pursuant to the undertaking given, appellants have filed the affidavit. Ms.lndu Malhotra, senior counsel appearing for the respondents submits that offer made by the appellant is not acceptable to her clients; that since the property has been put under attachment by the Income Tax Department as per the statement made in the affidavit filed by the appellant themselves, complainants would not be able to get a clear title to the property; that the complainants are not paying the EMIs as possession has not been given. Complainants had given postdated cheques to the bank. Bank has initiated proceedings under Section 138 of the Negotiable Instruments Act for recovery and under the Securitization Act. Learned counsel appearing for the appellant submits that the High Court of Andhra Pradesh in Writ Petitions No.9227/2010 and other connected cases, by a common order dated 5.12.2012, in order to protect the interest of the purchasers and revenue, has issued certain instructions, one of which reads as under:“In respect of units (villas/ apartments/ plots) where full consideration was received by MPL, sale deeds executed in favour of purchasers and registered and possession of the plots and villas/ apartments (along with undivided) share of land) mentioned in the respective sale deeds has been delivered, we declare that such units and the undivided share in land transferred along with villas/apartments, covered by such registered sale deeds would be free from attachment and the attachment orders passed by the I.T. Department would have no application to them. This position in law is also accepted by the Revenue.”……………………… According to him, said instructions will protect the interest of the respondents as the property would be transferred to them free from any attachment. Counsel for the appellant is directed to supply a copy of the order passed by the CLB, High Court of Andhra Pradesh in Civil Writ Petition No.9227/2010 and other connected cases to the counsel for the respondent. Counsel for the respondent is directed to supply a copy of the proceedings initiated by the banks against the complainants to the counsel for the appellant. Adjourned to 19th March 2013 to enable the counsel for the parties to address their arguments regarding the effect and impact of the order passed by the CLB. Respective counsel appearing for respective banks are also directed to seek instructions. Counsel for the respondent is also directed to supply a copy of the order passed by this Commission referred to above and the order passed by the Supreme Court in SLP No.26256/2010.” On 20.03.13, Developer filed an application seeking permission to file some additional documents which was declined on the ground that the additional documents by way of additional evidence could not be taken at this belated stage. However, the order passed by the High Court of Andhra Pradesh in W.P.No.9227/10 will be taken note of while deciding these appeals. This Commission on 16.05.13 has passed the following order:“ Counsel for the appellant states that Company Law Board had extended the time for completion of the project by 30.6.2013. Adjourned to 22nd May 2013 to enable the appellant to file an affidavit as to within how much time the project would be completed in all respects including the facilities like water, road, sewerage, electricity, elevators and other such facilities to make the units livable. According to the learned counsel for the respondent, respondents had purchased the flats after taking loan from the banks; that the project was to be completed by 2008; that the bank would charge penal interest @ 24% for the delayed EMIs. Further states that the bank has also started proceedings under Section 138 of the Negotiable Instruments Act and Securitization and Reconstruction of Financial Assets & Enforcement of Security Interest Act, 2002. Counsel for the appellant is directed to state as to what compensation the appellant shall pay to the respondents for the delay caused in completion of the project which would take care of the interest which the bank will charge from the complainants for the delay in making the payments. Interim Application No.3141/2013 seeking impleadment is dismissed as withdrawn reserving liberty with the Association or members other than the complainants in these cases to start independent proceedings. Adjourned to 22nd May 2013. Affidavit be filed on or before 20.5.2013 with an advance copy to the counsel for the respondents. In compliance of our order dated 16.05.13, Developer has filed a detailed affidavit with regard to the status of construction, delivery of the apartments to the Respondents, interest to be charged by the Bank in cases where the Respondents have taken bank loans, Access Roads, Sewerage, Power, water, elevators etc. It is stated in the affidavit that the 4 towers, i.e. Darjeeling, Khandala, Mussoorie and Nainital have been completed and notices have been issued from November, 2012 onward to the purchasers for handing over possession. 5 towers, namely, Dalhousie, Shimla, Ooty, Munnar and Manali are to be completed within the extended time schedule of end of June, 2013. With regard to remaining 2 towers, namely, Kodai and Coonoor, it was decided not to commence the construction as the number of bookings in these two towers were under 57 out of a total of 132 apartments. It is further stated that the work of access roads had been completed for the stages 1 to 4 and the similar work for stage 5 is under progress and expected to be completed by Ist week of July, 2013. The tar road connectivity to the areas leading to the apartment towers is under construction and would be completed by end of July, 2013. Permanent Sewage Treatment Plant works have been commissioned. External drainage, sewerage and water line works are in progress and will be completed by end of June, 2013. The application for power connection was submitted with APCPDCL in April, 2012 and final orders were issued by the department on May 10, 2013 for laying the cable to the sub-station of the Appellant for energizing as well as awarding the contract to M/s. Mamtha Constructions vide their letter dated Lr. NO.CGM(O&M)/ SE(O&M)/F.Tender/D.N. 384/13 dated 10.05.13. The cable laying work is expected to commence before end of May, 2012. At present, Hyderbad Metropolitan Water Supply and Sewerage Board is supplying Manjeera water to the residents of Hill Country. The Developer has made application for supply of additional quantum of water in February, 2013. The gas piping infrastructure work will be completed by June 30, 2013. It is further stated in the affidavit that the provisional club house is operational with indoor facilities and the permanent club house will be completed by end of July, 2013. With regard to the home loans taken by the Respondents from the Appellant Banks/Financial Institutions, it is averred in the affidavit that the Developer has been meeting the Banks/Financial Institutions periodically to help the Respondents to arrive at settlement and restricting the payment of loan amount. The Developer filed an application before this Commission on 19.03.13 offering a compensation package to all the apartment owners in Hill Country based on fair rental value. However, It has been submitted in the affidavit that the Developer is not in a financial position and cannot undertake to meet the financial bank interest commitments of the respondents or make refunds. The IL&FS Group has infused Rs.425 crores to complete the project and the has paid substantial income tax dues for the past period in order to negotiate with the Income Tax Department to lift the ban on registration of conveyance deeds in the Hill County Project. It is further submitted that if the funds are diverted in making refunds and making interest payments on behalf of the apartment owners, it would be at the cost of other customers of the Hill County Project as the project may not be completed due to lack of funds. Under these circumstances, the Respondents be granted compensation at the rate of Rs.5/- per sq. ft. per month in proportion to the amounts paid by them for the entire period of delay till the date of handing over possession except the 18 months period granted by the CLB to the Developer to complete the project. As per Agreements of Sale, the construction of the flats/apartments was to be completed by the Developer in all the cases on or before 31st December 2008. Due to Satyam Computer’s scam in 2009, the development of the project remained at standstill. The matter was referred to the CLB which by order dated 13.01.11 induced the IL & FS Group to complete the project. IL&FS infused Rs.425 crores to complete the project. As per statement made in the Affidavit filed by the Developer on 20.05.13 in compliance of our order dated 16.05.13 only four towers out of the 11 towers have been completed. 5 towers, namely, Dalhousie, Shimla, Ooty, Munnar and Manali which were to be completed by the end of June, 2013 are likely to be completed in the end of July, 2013. It has been decided by the Developer not to construct the remaining 2 towers, namely, Kodai and Coonoor. The work of providing basic amenities such as water, electricity, drainage, elevator, gas pipeline, club etc. has yet to be completed by the Developer. Under these circumstances, the Respondents/Complainants are not interested to take possession of the flats/apartments. This apart, most of the Respondents by issuing legal notices to the Developer cancelled the Agreements of Sale as they were not willing to take possession of the flats. Since there was nothing on record to show the stage of construction and when the project would be completed, the State Commission rightly directed the Developer to refund the deposited amount along with interest @ 12% p.a. from the respective dates of deposit till payment together with compensation of Rs.1,00,000/- and costs of Rs.10,000/-. As per affidavit filed by the Developer, the Developer could not complete the project within the period of 18 months granted by the CLB. Developer has got the period to complete the project extended by the CLB upto 30.06.13. Since the contradictory statements being made by the Ld. Counsel appearing for the Developer, we asked the Developer to file a fresh affidavit were showing the stage of construction. On perusal of the Affidavit, we are satisfied that the project cannot be completed till 30.06.13. As per Affidavit filed by the Developer, the Developer is not in a position to complete the project upto 30.06.13. Developer has sought further time upto 31.07.13 to complete the project as the basic amenities such as water, electricity, drainage, elevator, gas pipeline etc. have yet to be provided by them. Since the project is not complete as on the date, we cannot direct the Respondents to take the possession of the flats. For the reasons stated above, we endorse the finding as well as direction given to the Developer by the State Commission to refund the amount to the Respondents. The Developer’s primary contention made before us is that the order of refund passed by the State Commission is unsustainable and more so in the present circumstances when the construction is already completed. The affidavit filed by the Developer on 20.05.13 reveals that a substantial part of the work, even according to the Developer, is still going on. The affidavit, on the face of it, does not inspire any confidence and rather makes it abundantly clear that the apartments are not habitable. Section 455 of the Hyderabad Municipal Corporation Act, 1955 mandates that after completion of the work in a building, the builder should intimate the Municipal Corporation in writing about such completion in the prescribed form. The Authority after inspection, if it deems fit, would grant a completion certificate and no person shall be allowed to occupy a building until a completion certificate is issued. This would be possible only if the entire work is complete. It is pertinent to mention here that Section 4 (4) of the Andhra Pradesh Apartments (Promotion of Construction and Ownership) Act, 1987 mandates that an apartment can be transferred by the Developer only after obtaining a Completion Certificate and Certificate of fitness for occupation from the local authorities. In view of the mandatory provisions of law, the claim of the Developer that the flats are ready and would be handed over to the Respondents by June, 2013 is factually incorrect. Respondents are not interested in allotment of flats as the Banks/Financial Institutions are to recover the loans on the terms and conditions of the original agreement with interest for the period of six years when there was no construction. If the Respondent are compelled to take the flats, they would be in a state of debt to the Banks/Financial Institutions and would be required to pay interest/penal interest etc. Further, Respondents are facing litigations initiated by the Banks under the provisions of the Securitization and Reconstruction of Financial Assets and Enforcement of Security Interest Act, 2002; The Recovery of Debts due to the Banks and Financial Institutions Act, 1993 and The Negotiable Instruments Act, 1881. Assuming that the Respondents take possession of their respective flats, the Banks would immediately initiate proceedings for attachment of the flats towards recovery of the alleged dues. It is evident that in the event of the Respondent’s taking over the possession of the flats, they would have to pay huge amounts to the Banks as per the penal provisions for default in the loan agreements, which cannot be repaid by them even after selling the flat. If the Respondents take possession of the flats, they would be left with huge debts to the Banks and continue to litigate in various other Courts for no fault of theirs. The 66 Respondents in the present batch of Appeals comprise less than 10% of the total flat purchasers in the Developer’s project. It would not make any difference to the Developer, if the Respondents are refunded the amount paid by them. The Developer can sell the finished flats in the open market at current rates and fetch more money than the amounts at which they agreed to sell the flats to the Respondents herein. This apart, the earlier judgment on the same/similar facts in Complaint Case No.30/09 based on which the State Commission has allowed the present complaints, was upheld by this Commission with slight modification. SLP filed by the Developer against the said order was dismissed by the Supreme Court. The earlier judgment is a binding precedent which has been upheld upto Supreme Court. We respectfully follow the same. Complaint No.30/09 was filed against the Developer on the same facts. The only intervening factor is the order dated 13.01.11 passed by the CLB which according to us makes no difference as the Developer remains the same. By order dated 13.01.11, CLB had allotted the preferential shares to the IL&FS by virtue of which it has controlling interest in the company. The liability of the Developer to the Respondents remains the same. The judgment rendered by this Commission in First Appeal No. 189/10 in complaint No.30/09 which had been upheld by the Supreme Court, is a binding precedent and as stated above we are bound by the same. Even as on today, the flats are not complete. Developer has not obtained the Completion Certificate or Certificate of fitness for Occupation. Under these circumstances, Respondents cannot be ordered to take possession of the unfinished flats without Completion Certificate and Certificate of fitness for Occupation issued by the local authorities. For the reasons stated above, we do not find any merit in the Appeals filed by the Developer and dismiss the same with no order as to costs. FINDINGS IN FIRST APPEAL NOS. 387 TO 400 OF 2012, 783/12, 29/13 AND 14 TO 25 OF 2013 FILED BY THE STATE BANK OF INDIA AND ICICI BANK LTD. We need not recapitulate the facts again. Relevant clauses of the tripartite agreements wherein the Appellant, State Bank of India/ ICICI Bank Ltd. was a party, are reproduced as under:-. “2. SBI shall make disbursement of the sanctioned loan by making payments to the Developer directly on behalf of the borrowers and payment(s) made to the Developer shall be deemed to be payment(s) made to the borrowers and the borrowers shall in each case be liable for the amount of the loan disbursed on his/her behalf to the Developer, as though the same has been disbursed directly to him/her. It is further agreed by the borrower that SBI shall not be responsible or liable to ensure or ascertain the progress of the construction and mere demands for disbursement would be sufficient for SBI to effect disbursement as aforesaid. However, SBI at its sole discretion, shall disburse the loan in suitable installments, at the request of borrower/Developer or in suitable installments to be decided by SBI with reference to need or progress of construction, which decision shall be final and binding on the borrower(s)/Developer. The borrower shall be responsible to follow up with SBI to make disbursement on his/her behalf as per any agreement, payment schedule he/she may have with the Developer. Notwithstanding anything to the contrary contained herein, SBI may in its sole discretion refuse to disburse the loan until; (a) Borrower(s) has/have paid his/her own contribution in full to the Developer (the cost of the dwelling unit less the loan) and the progress and need of the construction justifies the disbursement requested. 6. That in the event of cancellation of allotment to the borrower by the Developer for any reason whatsoever the Developer shall refund to SBI only forthwith the entire amounts received from SBI within 60 days subject to clause No. 7 below. The balance if any after adjusting the dues, interest, costs and other amounts recoverable by the SBI, shall be returned to the borrower by SBI. The Developer herein undertakes not to refund any amount, on any account, under any circumstances to the borrower without the written consent of SBI. 7(a) Upon cancellation of the allotment of the schedule property to the borrower for any reason, the Developer shall immediately intimate about the same in writing to SBI. Upon receipt of such intimation, SBI shall notify the Developer all amounts due to it from the borrower. In such an event, the Developer shall forthwith pay SBI all amounts received by it from SBI on behalf of the borrower within 60 days of receipt of such statement during which period, the Developer shall pay interest to SBI, at the rate of interest on such amount shall be the same as agreed between the SBI and borrower in the loan agreement. (b) Further, the Developer hereby agrees that it shall also pay all the remaining amounts due and payable to SBI from the borrower such as defaulted payments, additional interest etc. after deducting reasonable expenses (as agreed by both Developer and SBI) incurred by the Developer from the sale proceeds of the property” Pursuant to the tripartite agreements, the Appellant Bank entered into the loan agreements with the Respondents herein and sanctioned the home loans. Thereafter, the Appellant Bank issued sanction letters. As per clause 13 (c) of the Loan Sanction Letter, the Appellant Bank was obligated to release the loan amount to the Developer directly on the basis of verification of the stage and nature of the construction. In terms of Section 5 of the Andhra Pradesh Apartments (Promotion of Construction and Ownership) Act, 1987, the Appellant Bank was under an obligation not to release more than 20% of the sale consideration amount as advance to the Developer before commencement of the construction. The relevant Section 5 reads as under:“ A promoter who intends to transfer any apartment shall before, accepting any sum of money as advance payment or deposit, which shall not exceed twenty percent of the price, enter into a written agreement of sale with the intending transferee and the same shall be registered as a document compulsorily registerable under clause (b) of sub-section (1) of Section 17 of the Registration Act, 1908.” The Appellant Bank disbursed the entire loan amount to the Developer even before the commencement project site contrary to the provisions of construction of the at the Tripartite Agreement. The Appellant Bank could not have disbursed the loan a mount without taking proper care and caution to find out about the existence/start which loans were sanctioned. part of the Appellant Bank, of construction of the flats for Due to the lack of supervision on the Developer diverted the funds of the project to the Satyam Computers. The Appellant Banks having acted contrary to the terms of the tripartite agreement, its own sanctioned terms and provisions of Section 5 of the Andhra Pradesh Apartments (Promotion of Construction and Ownership) Act, 1987 by disbursing the entire loan amount without any construction being made, cannot be absolved of their responsibility. The tripartite agreements executed between the Bank, Developer and the Respondents contemplate that in the event of cancellation of allotment of flat, the Developer was liable to refund the entire loan amount to the Appellant Banks within 60 days. Respondents terminated the contracts by filing the complaints. The Appellant Banks in spite of having notice of termination of the contracts did not take any steps for recovery of the loan amount from the Developer. The contention of the Bank that as per tripartite agreements the Bank was bound to review the progress of the construction only to protect its own interest otherwise no duty was cast upon it does not hold water and appears to be a fallacious argument and a lame excuse. The progress of construction and the manner in which the loan amount was to be disbursed by the Bank were inter-connected issues and the Appellant Bank being the home loan banker who has lien over the flats should have acted cautiously and taken reasonable care to ensure that its money is safe and secure. Moreover, the Appellant Bank cannot have any grievance against the order passed by the State Commission directing it to recover the loan amount from the Developer as the interest of the Bank has been adequately protected by the State Commission. For the reasons stated above, we do not find any merit in the Appeals filed by the Banks and dismiss the same with no order as to costs. The developer is directed to comply with the orders passed by the State Commission within a period of six weeks from today failing which the Respondents would be at liberty to execute the decree. Registry is directed to refund the sum of Rs.35,000/- deposited by the Developer as statutory deposit in each case along with accrued interest. …………….. . . . . . (ASHOK BHAN J.) PRESIDENT ................ (VINEETA RAI) MEMBER YD/* NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 2120 OF 2013 (From the order dated 04-07-2011 in F.A. No. 293/2009 of the State Consumer Disputes Redressal Commission, Andhra Pradesh) With IA/3478/2013(For stay) IA/3479/2013(For condonation of delay) M/s DDF (Davood Fruit Merchant), Rep. by S. Davood, S/o Mastan, No. 17, Municipal Shop, Near Old Bus Stand, Behind Ponnaimman Koil Street, Chittoor, Andhra Pradesh … Petitioner/Complainant Versus M/s Murugan Cold Storage Pvt. Ltd., Ramasamudram Road, near Degree College, Punganoor, Chittoor District, Andhra Pradesh rep. by its Managing Director … Respondent/Opposite Party BEFORE: HON’BLE MR. JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER HON’BLE DR. B.C. GUPTA, MEMBER For the Petitioner : Mr. V. Sridhar Reddy, Advocate PRONOUNCED ON 8th JULY, 2013 ORDER PER JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER This revision petition has been filed by the petitioner against impugned order dated 04-07-2011 passed by the learned State Consumer Disputes Redressal Commission, Andhra Pradesh (in short, ‘the State Commission’) in Appeal No.293 of 2009 – M/s DDF (Davood Fruit Merchant) Vs. M/s MuruganCold Storage Pvt. Ltd. by which, while allowing the appeal, order of the District Forum allowing complaint partly, was set aside and complaint was dismissed. 2. Brief facts of the case are that complainant/petitioner purchased apples worth Rs.26,08,907/- and same were stored in cold storage of opposite party/respondent. When complainant was lifting the stock, he was informed that apples worth Rs. 20 lakhs have been damaged. Complainant alleged that apples were damaged due to mismanagement of opposite party and alleging deficiency on the part of the opposite party filed complaint before the District Forum. Opposite party contested the complaint. Learned District Forum after hearing both the parties partly allowed the complaint and directed opposite party to pay an amount of Rs. 4 lakhs along with 9% p.a. interest. Appeal filed by the respondent was allowed by learned State Commission vide impugned order, against which this revision petition has been filed along with application for condonation of delay. 3. Heard learned Counsel for the petitioner at admission stage and perused the record. 4. Petitioner, along with revision petition, has filed application for condonation of delay of 57 days whereas as per office report there is delay of 592 days in filing the revision petition. Perusal of application reveals that learned State Commission passed impugned order on 04-07-2011 and issued free copy on 12-07-2011. Petitioner contacted his advocate in the month of August, 2011 but as his file was missing from the advocate’s office, he could not get opinion from the advocate. In the third week of December, 2012 file was traced and petitioner applied for certified copy of the impugned order on 21-12-2012 and received on 27-12-2012. It was further mentioned that his counsel asked him to approach another advocate appearing in the National Commission and petitioner’s present counsel was approached in March, 2013 and revision petition has been filed on 24th May, 2013. 5. It becomes clear that instead of delay of only 57 days, there is delay of 592 days in preferring revision petition. No satisfactory explanation has been given for condonation of inordinate delay of 592 days. As per application, when he received another certified copy on 27-12-2012, he should have preferred revision petition immediately. When petitioner’s counsel was also approached in March, 2013, he should have filed revision petition immediately but revision petition has been filed on 24th May, 2013. 6. As per law, revision petition is to be filed within 90 days and after excluding period of limitation, this revision petition has been filed with inordinate delay of 592 days, which cannot be condoned. 7. In R.B. Ramlingam Vs. R.B. Bhavaneshwari 2009 (2) Scale 108, it has been observed: “We hold that in each and every case the Court has to examine whether delay in filing the special appeal leave petitions stands properly explained. This is the basic test which needs to be applied. The true guide is whether the petitioner has acted with reasonable diligence in the prosecution of his appeal/petition.” 8. In Ram Lal and Ors. Vs. Rewa Coalfields Ltd., AIR 1962 Supreme Court 361, it has been observed; “It is, however, necessary to emphasize that even after sufficient cause has been shown a party is not entitled to the condonation of delay in question as a matter of right. The proof of a sufficient cause is a discretionary jurisdiction vested in the Court by S.5. If sufficient cause is not proved nothing further has to be done; the application for condonation has to be dismissed on that ground alone. If sufficient cause is shown then the Court has to enquire whether in its discretion it should condone the delay. This aspect of the matter naturally introduces the consideration of all relevant facts and it is at this stage that diligence of the party or its bona fides may fall for consideration; but the scope of the enquiry while exercising the discretionary power after sufficient cause is shown would naturally be limited only to such facts as the Court may regard as relevant.” 9. Hon’ble Supreme Court after exhaustively considering the case law on the aspect of condonation of delay observed in Oriental Aroma Chemical Industries Ltd. Vs. Gujarat Industrial Development Corporation reported in (2010) 5 SCC 459 as under; “We have considered the respective submissions. The law of limitation is founded on public policy. The legislature does not prescribe limitation with the object of destroying the rights of the parties but to ensure that they do not resort to dilatory tactics and seek remedy without delay. The idea is that every legal remedy must be kept alive for a period fixed by the legislature. To put it differently, the law of limitation prescribes a period within which legal remedy can be availed for redress of the legal injury. At the same time, the courts are bestowed with the power to condone the delay, if sufficient cause is shown for not availing the remedy within the stipulated time.” 10. Hon’ble Apex Court in (2012) 3 SCC 563 – Post Master General & Ors. Vs. Living Media India Ltd. and Anr. has not condoned delay in filing appeal even by Government department and further observed that condonation of delay is an exception and should not be used as an anticipated benefit for the Government departments. 11. Hon’ble Apex Court in 2012 (2) CPC 3 (SC) – Ansul Aggarwal Vs. New Okhla Industrial Development Authority observed as under: “It is also apposite to observe that while deciding an application filed in such cases for condonation of delay, the Court has to keep in mind that the special period of limitation has been prescribed under the Consumer Protection Act, 1986, for filing appeals and revisions in Consumer matters and the object of expeditious adjudication of the Consumer disputes will get defeated, if this Court was to entertain highly belated petitions filed against the orders of the Consumer Foras”. Thus, it becomes clear that there is no reasonable explanation at all for condonation of inordinate delay of 592 days. 12. As revision petition has been filed after 592 days, application for condonation of days is liable to be dismissed and as revision petition is barred by limitation, revision petition is dismissed at admission stage. 13. Consequently, revision petition filed by the petitioner is dismissed as barred by limitation at admission stage with no order as to costs. .……………….……………… ( K.S. CHAUDHARI, J) PRESIDING MEMBER .……………….…………… ( DR. B.C. GUPTA) MEMBER aj NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI FIRST APPEAL NO. 164 OF 2013 (Against the order dated 28.01.2013 in Complaint No.09/2010 of the State Commission, Rajasthan) Jet Airways (India) Ltd. Siroya Centre Sahar Airport Road Andheri (East), Mumbai400099 City Office: Umed Nagar House Corporate Office Ganapati Plaza, M.I. Road Jaipur (Rajasthan) ……….Appellant Versus 1. Smt. Vandana Jain W/o Sh. Subhash Bhatnagar R/o 11, Gangwal Park Jaipur302004 (Rajasthan) 2. Sh. Subhash Bhatnagar S/o Late Shri Avinash Chand Bhatnagar R/o 11, Gangwal Park Jaipur- 302004 (Rajasthan) 3. B.C.B. Tours & Travels Pvt. Ltd. 214 11th floor, Vardhman Complex, Johari Bazar, Jaipur (Rajasthan) .........Respondents BEFORE HON’BLE MR. VINAY KUMAR, PRESIDING MEMBER For the Appellant : Mr.Randhir Jain, Advocate Mr. Dhananjai Jain, Advocate PRONOUNCED ON: 9 July 2013. ORDER PER MR.VINAY KUMAR, PRESIDING MEMBER 1. This appeal has been filed by M/s. Jet Airways (India) Ltd. against the order of Rajasthan State Consumer Disputes Redressal Commission in Complaint No.9 of 2010. The State Commission has allowed the complaint of the respondent/Complainant against OP-1, the present appellant. The appellant has been directed to reimburse to the Complainant the cost of Cathay Pacific Airline Tickets for Hong-Kong and pay compensation of Rs.50,000/-, together with cost of Rs.25,000/-. No orders have been passed against OP-2/B.C.S. Tours and Travel Pvt. Limited. 2. Facts, as seen from the record, relate to the journey of the two Complainants from Jaipur to Hong-Kong via Mumbai. Both sectors of the journey were to be performed with Jet Airways. The Jet flight from Jaipur to Mumbai arrived at 11:40 p.m. instead of its scheduled arrival of 10:20 p.m. As a consequence of this delay of one hour twenty minutes, they could not take the connecting Jet Flight to Hong-Kong, despite having boarding cards for Mumbai Hong-Kong flight issued to them at Jaipur itself. According to the Complainants, this was due to delay in operation of the Airport shuttle and long immigration and security queues for boarding. The Airline staff allegedly failed to make arrangement for putting them in the next flight to Hong-Kong and advised the Complainants to buy fresh tickets for the next day. The Complainants therefore, were forced to take 5:30 a.m. flight of another Airline, the next morning. 3. The State Commission has held that the problem of delay in immigration and security checks was caused only by delayed arrival of Jaipur-Mumbai Jet Flight. The Airline staff failed to give the necessary help and assistance even when boarding passes has already been issued to the Complainants for the Jet flight to HongKong. Staff of Jet Airline knew that the Complainants had short time due to delayed arrival of their flight and they would need to be transported to the international terminal. But, no such assistance was provided. There was also no material to prove that the Complainants were offered seats in the next flight to Hong-Kong. Therefore, the State Commission held it to be a case of deficiency of service on the part of OP1/Jet Airline. 4. The records submitted by the appellant have been perused and the counsel for the appellant has been heard at length. In the appeal memorandum, it is stated that two other passengers coming from Jaipur on the same flight had successfully boarded the connecting flight from Mumbai to Hong-Kong. It is therefore, alleged that the Complainants themselves were to blame for missing the flight. However, this argument is contradicted by the appellant’s own averment that the delay, if any was caused due to non-co-operation and delay on the part of immigration and security personnel. This bland claim, in the absence of any evidence of assistance provided by the Jet Airways staff, is at best a very feeble attempt to pass on the blame to others for their own lapse. Having issued tickets for both sectors of the journey on two flights of their own Airline, the appellants/OP had a clear obligation to ensure that the passengers boarding at Jaipur are able to board the connecting flight at Mumbai. This obligation becomes more direct and inescapable due to delayed arrival of the Jaipur-Mumbai flight. Learned counsel for the appellant has referred to their written response before the State Commission and claimed that the delay in arrival of this flight due to air traffic congestion at Mumbai Airport resulting in delay in landing of the flight. This again cannot be accepted, if Jet Airways schedules a flight to land at Mumbai Airport at a particular time and another connecting flight to take off at a particular time, it must provide for time required in all services/functions including security, immigration and air traffic management, which are necessarily concerned with or mandated for such landing and departure. The travelling public is in no way responsible for delay caused by any of them. 5. In view of the above, it is held that the decision of the State Commission is based on correct appreciation of evidence on record and does not call for any interference. The appeal is held to be devoid of any merit and is dismissed as such. .……………Sd/-…………… (VINAY KUMAR) PRESIDING MEMBER S./-12 NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 2127 OF 2013 (From the order dated 09-10-2012 in First Appeal No. 1844 of 2008 of the State Consumer Disputes Redressal Commission, Haryana) WITH I.A./3563/2013 (FOR CONDONATION OF DELAY) Kapil Sharma S/o Late Shri Satbir Singh Sharma R/o Village Durjan Pur, Tehsil Narwana, District – Jind (Haryana) … Petitioner/Complainant Versus Life Insurance Corporation of India Jeevan Parkash Building, Sector-17, Chandigarh (U.T.) Through its Divisional Manager/ Manager(Legal) … Respondent /Opposite Party BEFORE: HON’BLE MR. JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER HON’BLE DR. B.C. GUPTA, MEMBER For the Petitioner PRONOUNCED ON : Dr. Sukhdev Sharma, Advocate 10th JULY, 2013 ORDER PER JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER 1. This revision petition has been filed by the petitioner against impugned order dated 09-10-2012 passed by the learned State Consumer Disputes Redressal Commission, Haryana (in short, ‘the State Commission’) in Appeal No. 1844 of 2008 – Life Insurance Corporation of India Vs. Kapil Sharma, by which while allowing the appeal, order of the District Forum allowing the complaint was set aside. 2. Brief facts of the case are that Satbir Sharma, father of the complainant/petitioner obtained policy for Rs. 1.00 lakh from opposite party/respondent on 22-022006. Insured died on 24-04-2006. Complainant submitted claim, which was repudiated by the opposite party on the ground that life assured was chronic alcoholic and suffered from Cirrhosis and this fact was not disclosed by the deceased in the proposal form. Complainant alleging deficiency on the part of opposite party, filed complaint before District Forum. Opposite party resisted claim on the ground mentioned in repudiation letter and prayed for dismissal of complaint. Learned District Forum after hearing both the parties, allowed complaint and directed opposite party to pay Rs. 1 lakh along with 9% p.a. interest and Rs.1,000/- as costs. Respondent filed appeal against the order and learned State Commission vide impugned order allowed the appeal and dismissed complaint, against which this revision petition has been filed along with application for condonation of delay. 3. Heard learned Counsel for the petitioner on application for condonation of delay as well as on merits, at admission stage and perused record. 4. Petitioner moved an application for condonation of delay of 107 days and alleged that copy of the order was received on 15-11-2012 and approached his counsel in December, 2012, who demanded records. Petitioner contacted his counsel at Panchkula, who provided photostat copies of record on 20 th April, 2013 and this revision petition was filed on 24th May, 2013. As per application for condonation of delay, there was delay of 107 days whereas, as per report of the office, there is delay of 100 days in filing not given any cogent reason revision petition. Apparently for condonation of delay. When petitioner on has 20-01-2013 counsel for the petitioner at Panchkula shown his inability to provide record, he should have applied for certified copies of the record. Not only this, when photostat copies of record were made available by advocate at Panchkula on 20-04-2013, revision petition should have been filed immediately but it was filed after 34 days of receipt of record. Revision petition is liable to be dismissed on the ground of limitation alone. 5. As far as merits of the case are concerned, certificate dated 24-02-2007 issued by Maharaja Aggarsain Medical College, Agroha shows that deceased assured was admitted in the hospital on 2006 and again on years and with 23-04-2006 with history Cirrhosis for last one of alcohol for 02-04last 15 to 20 year. Insured also remained on leave on medical grounds from 02-05-2005 to 30-06-2005 and 01-12-2005 to 1001-2006 from his employer’s office. 6. The contract of insurance is based on the doctrine of utmost good faith and life assured was under an obligation to disclose each and every aspect with respect to his health at the time of submitting proposal form. Insured had not disclosed fact of being alcoholic for last 15 to 20 years and suffering from Cirrhosis for last one year and had not disclosed fact of remaining on leave on medical grounds for about 3½ months and in such circumstances, on account of suppression of material facts regarding health, respondent has not committed any error in repudiating claim filed by the petitioner. 7. Learned State Commission dealt with suppression of material facts at length and had arrived at correct conclusion that life assured concealed true and material facts with respect to his health at the time of taking of the policy and has rightly allowed the appeal. We do not find any illegality, irregularity or jurisdictional error in the impugned order, which calls for any interference and revision petition is liable to be dismissed. 8. Consequently, revision petition filed by the petitioner is dismissed at admission stage, being barred by limitation as well as on merits, with no order as to costs. .……………….……………… (K.S. CHAUDHARI, J) PRESIDING MEMBER .……………….……………… (DR. B.C. GUPTA) MEMBER aj NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 2126 OF 2013 (From the order dated 28-06-2012 in First Appeal No. 1840 of 2008 of the State Consumer Disputes Redressal Commission, Haryana) WITH I.A./3562/2013 (FOR CONDONATION OF DELAY) Rajesh Sharma S/o Late Shri Satbir Singh Sharma R/o Village Durjan Pur, Tehsil Narwana, District – Jind (Haryana) … Petitioner/Complainant Versus Life Insurance Corporation of India Through Manager (Legal & HPF), Divisional Office, Sector 17-B, Chandigarh (U.T.) … Respondent /Opposite Party BEFORE: HON’BLE MR. JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER HON’BLE DR. B.C. GUPTA, MEMBER For the Petitioner PRONOUNCED ON : Dr. Sukhdev Sharma, Advocate 10th JULY, 2013 ORDER PER JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER This revision petition has been filed by the petitioner against impugned order dated 28-06-2012 passed by the learned State Consumer Disputes Redressal Commission, Haryana (in short, ‘the State Commission’) in Appeal No. 1840 of 2008 – Life Insurance Corporation of India Vs. Rajesh Sharma, by which while allowing the appeal, order of the District Forum allowing the complaint was set aside. 2. Brief facts of the case are that Satbir Sharma, father of the complainant/petitioner obtained policy for Rs. 1 lakh from opposite party/respondent on 28-08-2002, which lapsed due to non-payment of premium for the period from February, 2005 to August, 2005. Policy was got revived on 20-09-2002. Insured died on 24-04-2006 due to Cirrhosis. Complainant submitted claim, which was repudiated by the opposite party on the ground that life assured was chronic alcoholic and suffered from Cirrhosis and this fact was not disclosed by the deceased in the proposal form. Complainant alleging deficiency on the part of opposite party, filed complaint before District Forum. Opposite party resisted claim on the ground mentioned in repudiation letter and prayed for dismissal of complaint. Learned District Forum after hearing both the parties, allowed complaint and directed opposite party to pay Rs. 1 lakh along with 9% p.a. interest and Rs.1,000/- as costs. Respondent filed appeal against the order and learned State Commission vide impugned order allowed the appeal and dismissed complaint, against which this revision petition has been filed along with application for condonation of delay. 3. Heard learned Counsel for the petitioner on application for condonation of delay as well as on merits, at admission stage and perused record. 4. Petitioner moved an application for condonation of delay and alleged that he received copy of the order on 15-11-2012 and approached his counsel in December, 2012, who demanded records. Petitioner contacted his counsel at Panchkula, who provided photostat copies of record on 20th April, 2013 and this revision petition was filed on 24th May, 2013. As per application for condonation of delay, there was delay of 174 days whereas, as per report of the office, there is delay of 100 days in filing revision petition. Apparently petitioner has not given any cogent reason for condonation of delay. When on 20-01-2013 counsel for the petitioner at Panchkula shown his inability to provide record, he should have applied for certified copies of the record. Not only this, when photostat copies of record were made available by advocate at Panchkula on 2004-2013, revision petition should have been filed immediately but it was filed after 34 days of receipt of record. Revision petition is liable to be dismissed on the ground of limitation alone. 5. As far as merits of the case are concerned, certificate dated 13-04-2007 issued by Maharaja Aggarsain Medical College, Agroha shows that deceased assured was admitted in the hospital on 02-04-2006 and again on 23-04-2006 with history of alcohol for last 15 to 20 years and with Cirrhosis for last one year. Insured also remained on leave on medical grounds from 02-05-2005 to 30-06-2005 and 01-12-2005 to 1001-2006 from his employer’s office. 6. The contract of insurance is based on the doctrine of utmost good faith and life assured was under an obligation to disclose each and every aspect with respect to his health at the time of submitting proposal form as well at the time of revival of lapsed policy, as revival amounts to new contract of policy. Insured had not disclosed fact of being alcoholic for last 15 to 20 years and suffering from Cirrhosis for last one year at the time of revival and had not disclosed fact of remaining on leave on medical grounds for about 3½ months and in such circumstances, on account of suppression of material facts regarding health, respondent has not committed any error in repudiating claim filed by the petitioner. 7. Learned State Commission dealt with suppression of material facts at length and had arrived at correct conclusion that life assured concealed true and material facts with respect to his health at the time of taking of the policy as well as at the time of revival of the insurance policy and has rightly allowed the appeal. We do not find any illegality, irregularity or jurisdictional error in the impugned order, which calls for any interference and revision petition is liable to be dismissed. 8. Consequently, revision petition filed by the petitioner is dismissed at admission stage, being barred by limitation as well as on merits, with no order as to costs. .……………….……………… (K.S. CHAUDHARI, J) PRESIDING MEMBER .……………….……………… (DR. B.C. GUPTA) MEMBER aj NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 1322 OF 2012 (From the order dated 01-12-2011 in First Appeal No. 190 of 2010 of the State Consumer Disputes Redressal Commission, Madhya Pradesh) Smt. Satyavati Sharma R/o Village-Lohadwar, Post Office Padra Police Station, Tehsil Raipur Karvelyun, District – Rewa (M.P.) … Petitioner/Complainant Versus Life Insurance Corporation Through Branch Manager, Krishna Complex, Krishna Nagar District, Satna (M.P.) … Respondent /Opposite Party BEFORE: HON’BLE MR. JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER HON’BLE DR. B.C. GUPTA, MEMBER For the Petitioner : Mr. Vikas Upadhyay, Advocate For the Respondent : Mr. Kamal Gupta, Proxy Counsel for Mr. Neeraj Gupta, Advocate PRONOUNCED ON 10th JULY, 2013 ORDER PER JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER This revision petition has been filed by the petitioner against impugned order dated 01-12-2011 passed by the learned State Consumer Disputes Redressal Commission, Madhya Pradesh (in short, ‘the State Commission’) in Appeal No. 190 of 2010 – Smt. Satyavati Sharma Vs. Life Insurance Corporation, by which while allowing the appeal, order of the District Forum allowing the complaint was set aside. 2. Brief facts of the case are that deceased Shyamlal Sharma, husband of the complainant/petitioner obtained policy for Rs. 1 lakh from opposite party/respondent on 30-03-2007 and suddenly insured Shyamlal died on 13-06-2008. Complainant filed claim for payment of sum assured to the opposite party but claim was repudiated. Alleging deficiency on the part of opposite party, complainant filed complaint before District Forum. Opposite party resisted claim and submitted that after investigation it was noticed that insured was suffering from heart ailment and prior to filling proposal form he had taken leave for 289 days on the ground of said illness. Deceased had suppressed all these facts in proposal form and therefore prayed for dismissal of complaint. Learned District Forum, after hearing both the parties, allowed complaint and directed opposite party to pay Rs. 1 lakh with 8% p.a. interest and Rs.5,000/- as compensation and Rs.1,000/- as cost of the complaint. Appeal filed by the respondent was allowed by learned State Commission vide impugned order, against which this revision petition has been filed. 3. Heard learned Counsel for the parties at admission stage and perused record. 4. Learned Counsel for the petitioner submitted that as there was no nexus between the cause of death and alleged illness, learned District Forum rightly allowed the complaint but learned State Commission has committed error in dismissing the complaint, hence revision petition be allowed and impugned order be set aside. On the other hand, learned counsel for respondent submitted that order passed by learned State Commission is in accordance with law, which does not call for any interference, hence revision petition be dismissed. 5. Perusal of record clearly reveals that in the proposal form, insured replied in negative to Clause 11 (a) & (c) as under:-“Did you ever consult a Medical Practitioner for any Ailment requiring treatment for more than a week? No Ever remained absent from place of work on grounds Of health during the last 5 years? 6. No” On the other hand, record clearly reveals that insured took 289 days leave from the office and he was suffering from various diseases of the nature and kind which he ought to have disclosed before issuance of policy. Learned State Commission rightly observed as under:“We are of the view that in none of these cases the deceased had proceeded on long leave of 289 days for his treatment and the documentsEx.P/6 to P/18 clearly certify that he was suffering from hyper tension and diabetes. Thus, there is sufficient evidence on record to show that the deceased was suffering from the diseases and he had suppressed it, indeed he had not disclosed that he had taken leave on medical ground. All these circumstances lead to irresistible conclusion that the deceased had deliberately suppressed the pre-existing disease thus, relieving the Insurance Company of its obligation to pay amount of the insurance. The counsel for the Insurance Company has relied upon the decision of the Supreme Court of India in Satwant Kaur Sandhu vs. New India Assurance Co. Ltd., Civil Appeal No. 2776 of 2002 in support of his contention that the IRDA regulation 2(1) (d) (Protection of Policyholders’ interest) defines ‘material’ to mean and include all important, essential and relevant information to decide whether to undertake the risk or not. If the deceased had disclosed the multiple diseases from which he was suffering, the Insurance Company would have taken decision whether to undertake the risk or not.” 7. The contract of insurance is a contract of trust and it was obligatory on the part of the insured to disclose previous disease, treatment, etc. but as deceased not only suppressed all these material facts, but also answered in negative and in such circumstances, respondent has not committed deficiency in repudiating the claim. We do not find any illegality, irregularity or jurisdictional error in the impugned order and revision petition is liable to be dismissed. 8. Consequently, revision petition filed by the petitioner is dismissed at admission stage with no order as to costs. .……………….……………… ( K.S. CHAUDHARI, J) PRESIDING MEMBER .……………….……………… ( DR. B.C. GUPTA) MEMBER aj NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 4018 OF 2006 (From the order dated 26-10-2006 in Appeal No. 2106 of 2005 of the State Consumer Disputes Redressal Commission, Karnataka) M/s Monto Motors Ltd. Through its Director D-33, Okhla Industrial Area Phase – I, New Delhi-110020 … Petitioner/O.P. No.1 Versus 1. M/s Sri Sai Motors Through Sh. G. Venkatesulu R/o SBI Colony, Gandhi Nagar, Bellary Town, Karnataka … Respondent No. 1/Complainant 2. M/s Taj Motors 407, Brigade Tower, Brigade Road, Bangalore – 560025. … Respondent No. 2/O.P. No. 2 BEFORE: HON’BLE MR. JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER HON’BLE DR. B.C. GUPTA, MEMBER For the Petitioner For Respondent No. 1 For Respondent No. 2 PRONOUNCED ON : Mr. Rakesh Kakar, Advocate :NEMO :NEMO 10th JULY, 2013 ORDER PER JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER This revision petition has been filed by the petitioner against impugned order dated 26-10-2006 passed by the learned State Consumer Disputes Redressal Commission, Karnataka (in short, ‘the State Commission’) in Appeal No.2106 of 2005 – M/s Monto Motors Ltd. Vs. M/s Sri Sai Motors & Ors. bywhich while dismissing the appeal, order of the District Forum allowing the complaint was upheld. 2. Brief facts of the case are that complainant/respondent no. 1, proprietor of Respondent No. 1, being an unemployed person wanted to start his own business for earning his livelihood. As per advertisement of petitioner/O.P. No. 1, respondent no. 1 was appointed authorised dealer of the petitioner on 17-09-2002 and in pursuance to agreement, respondent no. 1 deposited Rs. 2 lakhs as security amount with the petitioner/O.P. No. 1 and respondent no. 1 opened his showroom in Bellary. Opposite party no. 2/respondent no. 2 being authorised distributor of opposite party no. 1 supplied 24 vehicles to the complainant/respondent no. 1. Complainant cleared all dues payable to opposite party no. 2 but opposite party no. 2 had not given the sales commission and discount to the complainant as agreed between the parties. Complainant requested for refund of security amount, but amount was not refunded. Alleging deficiency on the part of the opposite parties, complainant filed complaint before District Forum with a prayer for refund of security deposit of Rs. 2 lakhs along with interest and other expenses. Opposite party no. 1 submitted written statement and alleged that complainant does not fall within the ambit of consumer under Consumer Protection Act as dispute is of commercial nature. It was further alleged that District Forum has no jurisdiction to entertain the matter and denied any deficiency on the part of the opposite party and prayed that complaint be dismissed. Opposite party no. 2 did not appear before District Forum and was proceeded ex-parte. Learned District Forum after hearing both the parties allowed complaint and directed opposite party no. 1 to refund Rs. 2 lakhs with 10% p.a. interest from the date of filing complaint till realisation and Rs.5,000/- as compensation for mental agony and Rs.2,000/- as litigation cost. Appeal filed by the petitioner was dismissed by learned State Commission vide impugned order against which this revision petition has been filed. 3. Respondents did not appear; hence they were proceeded ex-parte. 4. Heard learned Counsel for the petitioner and perused record. 5. Learned Counsel for the petitioner submitted that as dealership was for the purpose of purchase and sale of vehicles and spare parts, complainant does not fall within purview of consumer. As per letter of authority, disputes were subjected to jurisdiction of Delhi Court and District Forum, Bellary had no jurisdiction to entertain the complaint, even then District Forum committed error in allowing the complaint and learned State Commission further committed error in dismissing the appeal. It was further argued that complainant has not come with clean hands, as per authority letter, complainant was partner of firm Sri SaiMotors whereas complaint has been filed by the complainant showing himself to be proprietor of the firm, hence revision petition be allowed and impugned order be set aside. 6. Perusal of record reveals that complainant has signed authority letter dated 17-09- 2002, letter of intent dated 17-09-2002, and commitment letter dated 26-09-2002 pretending himself as partner of the firm Sri Sai Motors. On the other hand complainant has filed complaint depicting himself as proprietor of the firm. Complaint could have been filed only by the firm through its partners and as complaint filed by the complainant, as sole proprietor of the firm, complaint was not maintainable and learned District Forum has committed error in allowing complaint and learned State Commission has committed error in dismissing the appeal. 7. Learned counsel for the petitioner submitted that as dealership was for the purpose of purchase and sale of the vehicles and spare parts, complaint does not fall within purview of consumer under Section 2(d)(i) of the Consumer Protection Act. Admittedly, Sri Sai Motors, when appointed authorised dealer for Bellary for selling and servicing motorcycles, Moped, fun bikes and spare parts by opposite party no. 1, deposited Rs. 2 lakhs as security with the opposite party. Section 2(d)(i) of Consumer Protection Act reads as under:-“(i) buys any goods for a consideration which has been paid or promised of partly paid and partly promised, or under any system of deferred payment and includes any user of such goods other than the persons who buys such goods for consideration paid or promised or partly paid or partly promised, or under any system of deferred payment, when such use is made with the approval of such person, but does not include a person who obtains such goods for resale or for any commercial purpose.” 8. Learned State Commission while dealing with this aspect observed as under:-“The case of OP-1 is that since the contract between the parties is commercial in nature, the complainant is not a consumer as defined under the Consumer Protection Act. It is true that the complainant was appointed as a Dealer to sell the vehicles manufactured by OP-1. The dispute between the complainant and OP-1 relates to the refund of the security deposit and it has nothing to do with the vehicles supplied by OP-1 through OP-2 to the complainant and re-sale of the said vehicles by the complainant to third parties. Hence, the complaint filed by the complainant is maintainable, as the complainant is a consumer as there is “Deficiency in service” by OP-1 in not refunding the security deposit as per the terms of the contract.” 9. We do not agree with the interpretation arrived at by learned State Commission. As security amount was deposited for obtaining dealership for the purpose of purchase and sale of vehicles, dispute regarding refund of security amount does not fall within the purview of consumer disputes under the Act and in such circumstances complaint (i) has been added w.e.f. was not maintainable. Explanation 15-03-2003 whereas dealership to Section 2(d) has been granted vide letter dated 17-09-2002 and explanation excluding commercial purpose for purpose of earning livelihood by self-employment is not applicable to the present case and in such circumstances, District Consumer Forum had no jurisdiction to entertain the complaint and has committed error in allowing complaint and learned State Commission further committed error in confirming order of District Forum. 10. Learned counsel for the petitioner further submitted that District Forum, Bellary had no jurisdiction to entertain the complaint as disputes were subjected to jurisdiction of Delhi Courts as per letter of intent dated 17-09-2002. We do not agree with this submission as dealership was granted for Bellary and showroom was also opened at Bellary and security amount was also given for running dealership at Bellary. In such circumstances, cause of action also arose at Bellary and as per Section 11 of Consumer Protection Act; complaint can be filed within the local limits of District Forum in whose jurisdiction cause of action arises. Merely by mentioning that all disputes are subjected to jurisdiction of Delhi Courts in the letter of intent, jurisdiction of Court at Bellary is not ousted. 12. From the above discussion it becomes clear that complainant has not come with clean hands and complaint filed by the complainant, as sole proprietor of Sri Sai Motors was not maintainable and as dispute does not fall within the purview of consumer dispute. Revision petition is to be allowed and order of learned State Commission is liable to be set aside. 12. During course of arguments, learned counsel for the petitioner submitted that petitioner is ready to refund the security amount to Sri Sai Motors subject to returning of the documents, inventory and indemnifying loss caused to the petitioner. We hope complainant will submit requisite documents along with inventory to the petitioner and petitioner will refund security amount to the complainant. 13. Consequently, revision petition filed by the petitioner is allowed and impugned order dated 26-10-2006 passed by learned State Commission in appeal no. 2106/2005 – M/s Monto Motors Ltd. Vs. M/s Sri Sai Motors & Anr. is set aside and complaint is dismissed. .……………….……………… ( K.S. CHAUDHARI, J) PRESIDING MEMBER .……………….……………… ( DR. B.C. GUPTA) MEMBER aj NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION No. 857 of 2010 (From the order dated 20.11.2009 of the Haryana State Consumer Disputes Redressal Commission, Panchkula in Appeal no. 609 of 2006) Haryana Urban Development Authority Through its Estate Office, Gurgaon Haryana Petitioner Versus Pawan Kumar Gupta Son of Shri C P Gupta 43 Sarojini Park Shastri Nagar New Delhi – 110031 Respondent BEFORE: HON’BLE MRS REKHA GUPTA For the Petitioner For the Respondent , PRESIDING MEMBER Mr R S Badhran, Advocate IN PERSON Pronounced on 10th July 2013 ORDER REKHA GUPTA Revision petition no. 857 of 2010 has been filed under section 21 (b) of the Consumer Protection Act, 1986 against the order dated 20 th November 2009 passed by the Haryana State Consumer Disputes Redressal Commission, Panchkula in First Appeal no. 609 of 2006. The brief facts of the case as per the respondent/complainant are as follows: The respondent had applied for allotment of 10 Marla Plot in Sector 9, Gurgaon to the Petitioner/ Opposite Party vide application no. 014712 dated 20.08.1992 and has deposited earnest money of 10% amounting to Rs.22,836/- in cash on 20.08.1992. Respondent was allotted a plot bearing no. 1184 ad-measuring 10 marlas, i.e., 220 sq mtrs, in Sector – 9, Gurgaon vide memo no. E O (G)/ ALT – 9/ 961 dated 09.07.1993 issued by the petitioner and a sum of Rs.34,924/-, i.e., 15% of the total tentative price was deposited with the petitioner vide Bank draft no. 283813 dated 24.07.1993 drawn on SBI, Laxmi Nagar, Delhi and thus 25% of the total price was paid at the time of allotment and the balance 75% sale price was payable in 6 yearly instalments. The respondent has also deposited Rs.1,51,031/- towards the cost of additional price i.e., 574/- sq. yds, as desired in notification no. 7904 dated 03.05.1999. Thus full and final payment has been received by HUDA in 1998 and escalated price also on 23.03.2002. The respondent has paid Rs.3,80,031/- as per the above list enclosed and the petitioner had received full and final payment but they unduly delayed the possession of plot for no fault of the respondent causing undue harassment, mental agony and irreparable loss. The above said plot was allotted to the respondent with a provision to offer possession of the same after completion of its full development in the area at the earnest and not later than two years. But now more than 12 years have passed since the date of allotment of the said plot and the petitioner has not bothered to offer. The possession of the said plot to the respondent till this date after completion of full development work in the area, inspite of repeated requests and personal visits to the office of the petitioner. Time and again, the respondent has visited the site. During long spell of 12 years, the petitioner neither developed his site well nor supply of sewage system, water supply and other amenities. Facilities like community centre, school, health centre required for the residential colony as declared by the petitioner, has yet to be provided. Furthermore as the possession was not given even after 12 years it has another impact, i.e., the cost of construction, cost of steel, cement, building material and labour charges etc., has increased approximately by 300%. Thereby what could have been done at a cheaper rate, will now, be done with more. The petitioner/ opposite party in their reply have stated that paragraph no. 4 of the complaint is wrong, baseless and hence denied. The area of this plot is fully developed and only thereafter physical possession was offered to the allottee vide this office memo no. 2749 dated 29.06.2001. As per the terms and conditions of the allotment the respondent/ allottee was given an offer of possession, but the allottee failed to even start the construction work and hence he is bound to pay the extension fee as per HUDA policy. Paragraph no. 7 of the complaint was also denied by stating that the area is fully developed and physical possession had already been offered to theallottee on 29.06.2001. The allottee failed to start the constructions and complete the building within two years from the date of offer of possession. The District Consumer Disputes Redressal Forum, Gurgaon (in short, ‘the District Forum) came to the following conclusions after going through the file and hearing the parties: “Possession has been admitted to have been delivered during the proceedings. As per application dated 16.12.2005 conveyance deed is not being executed. It is ordered that the same be executed on furnishing papers by the complainant, if any, besides the complainant is awarded interest @ 18% per annum on deposits from the dates of deposits till the delivery of possession of his plot on the spot by demarcation and this interest is being awarded keeping in view the rise in construction cost so as to compensate him as he has been waiting for the plot since, 1993. During the arguments counsel for the complainant contended that another illegal demands have been raised vide memo no. 17260 dated 15.09.2005. We have perused the said letter Rs.8,246/- have been demanded as instalments due to on 15.10.2005 and Rs.88,335/- towards enhancement which could be recovered as per terms of the allotment. However, Rs.14,565/- demanded as extension fee could not be demanded as physical possession was delivered only on 24.10.2005. This last demand is struck down and this amount is ordered to be refunded to the complainant with interest as per HUDA policy from the date of deposit till the date of refund. As regards the plea that the complainant had already paid amount of instalment and enhancement in 10/99 and March 02 respectively, he has not mentioned any receipt number or date. He can agitate the matter again with the HUDA and in case the complainant paid amount of instalment and enhancement double, respondent is liable to refund the said amount to the complainant along with interest from the date of deposit till the date of refund as per HUDA policy. There will be no other orders as to costs. Compliance of the above order be made within one month from the receipt of the copy of this order”. Aggrieved by the order of the District Forum, the petitioner/ opposite party filed an appeal before the State Commission. The State Commission in their order has recorded that “none has put in appearance on behalf of the appellant. Perusal of the file shows that this appeal is old one and relates to the year 2006. No one has taken care to appear on behalf of the appellant before this Commission from the last four consecutive hearings, i.e., 11.06.2007, 29.08.2007, 17.01.2008 and 27.01.2009. Even today none has appeared on behalf of the appellant. Since this appeal is old, therefore, we do not find any justification to adjourn the case time and again. Hence we proceed to decide this appeal after going through the case file”. The State Commission thereafter came to the following conclusion: “We have gone through the impugned order and taken into consideration the facts and circumstances of the case and are of the view that it is a case where the plot no. 1184, Sector – 9, Gurgaon was allotted to the complainant on 09.07.1993 whereas the physical possession of the same was handed over to the complainant on 24.10.2005 during the pendency of the proceedings before the District Forum, i.e., after a period of more than 11 years, which itself shows deficiency in service on the part of the opposite party. Therefore, we do not find any ambiguity or illegality in the impugned order passed by the District Forum. No case for interference in the impugned order is made out. No merit. Dismissed”. Hence, this present revision petition. The main grounds for the revision petition are as follows: - Forums below erred in facts and law, and have misread, misconstrued and misinterpreted the documentary evidence available on record and also the mandatory provisions of law applicable on that fact while passing the orders dated 20.11.2009. In fact the counsel for the petitioner was not present at the time of deciding the matter which devoid the petitioner herein being heard and explain the position of the matter before the State Commission. The petitioner thus lost the opportunity to bring the true facts before the Commission. - The Forums below failed to appreciate that the respondent herein is bound by the terms and condition of the allotment letter as well as provisions of Act, Rules and Regulation, policies instructions framed and issued in this regard from time to time. The respondent herein is bound by the aforementioned rules, instructions and policies of the petitioner herein and to pay the outstanding amount as demanded by the petitioner herein. - The Forums below have not taken into consideration that the offer of possession of the plot was made after completion of all the developments works on 29.06.2001. However, it was the respondent herein who instead of taking the possession filed the complaint with ulterior motives. The complaint was thus not maintainable. The District Forum has travelled beyond its jurisdiction in entertaining the complaint under the Act, which ought to have been dismissed. - The Forums below failed to appreciate that vide Memo no. 17260 dated 15.09.2005 demand of Rs.14,564/- as extension fees was rightly raised as the respondent herein has failed to construct the building as per the terms and conditions of the allotment and as per HUDA Policy. The Forums below erred in striking down the said demand even though the same was demanded as per rule and regulations of HUDA policy and as per the terms and conditions of the allotment letter. - The Forums below erred in awarding interest @ 18% per annum on deposits from the date of deposits till the delivery of possession of plot on the spot by demarcation. As already submitted the possession of the plot was offered on 29.06.2001 and it was the respondent who failed to take the possession of the plot, as such there is no deficiency in the service. Moreover the interest so awarded is too high. I have heard the counsel for the petitioner and respondent in person and have gone through the record. Nowhere in the revision petition has it been mentioned as to why no one had put in appearance on behalf of the petitioner/ appellant on the last four consecutive dates in the State Commission on 11.06.2007, 29.08.2007, 17.01.2008 and 27.01.2009. Thereafter the petitioner cannot complain that they were not given opportunity to bring the true facts before the State Commission. The counsel for the petitioner drew my attention to the offer of possession dated 29.06.2001 and stated that it is the fault of the respondent that he did not take immediate possession. However, the respondent denied having received this communication. Counsel for the petitioner could not provide any evidence that the said communication had been received by the respondent. Counsel for the petitioner then stated that the petitioner was objecting to pay 18% interest because as per the terms and condition of the allotment letter it was not due. He drew my attention to paragraph 7 of the allotment which states that “possession of the site will be offered to you on completion of the development works in the area, where situated”. It is however, patently unfair that this clause is open ended with absolutely no time limit. The petitioner had taken full payment from the respondent by March 2002 with the first payment being taken in August 1992. It is an undisputed fact that plot bearing no. 1184, Sector -9, Gurgaon was allotted by the petitioner to the respondent vide memo no. E O (G) /ALT – 9/ 961 dated 09.07.1993 at a tentative base price of Rs.22,836/-. Full and final payment including the escalated price was paid by 23.03.2002. However, the physical possession of the plot was given only on 24.10.2005. The respondent has now received both physical possession of the plot as also the conveyance deed. The petitioner is objecting to pay interest @ 18% per annum for the period upto 29.06.2001. The respondent has stated however, that since interest has not been paid till date, he should get the same even for the period beyond 2005. In view of the above, we find that there is no jurisdictional error, illegality or infirmity in the order passed by the State Commission warranting our interference. However, as per the terms and conditions of the allotment letter, the interest payable by allottee in case of default is 15%. In all fairness and in the interest of equity and justice, the order of the District Forum is partially modified by reducing the rate of interest from 18% to 15% per annum. Rest of the order stands as it is. In view of the foregoing, the revision petition stands disposed of. Sd/……………………………….. [Rekha Gupta] Satish NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 2569 OF 2012 (From the order dated 18-05-2012 in First Appeal No. 1147 of 2008 of the State Consumer Disputes Redressal Commission, Punjab) 1. MALKIAT SINGH S/o Shri Karam Singh R/o Flat No. 521, 6th Floor, Housefed Flats Complex, Shaheed Bhagat Singh Nagar, Block-E, Ludhiana - 141013 Punjab .... Petitioner/Complainant Versus 1. SHAHEED BHAGAT SINGH NAGAR, HOUSEFED COMPLEX, CO-OPERATIVE HOUSR BUILDING SOCIETY LTD. Through President, Block-E, Ludhiana Punjab 2. The Managing Director, Housefed Punjab, SCO No. 150-152, Sector 34-A, Chandigarh Punjab 3. The Registrar, Co-Operative Societies, Chandigarh Punjab ... Respondents BEFORE: HON’BLE MR. JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER HON’BLE DR. B.C. GUPTA, MEMBER For the Petitioner PRONOUNCED ON : In person 11th JULY, 2013 ORDER PER JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER 1. This revision petition has been filed by the petitioner against impugned order dated 18-05-2012 passed by the learned State Consumer Disputes Redressal Commission, Punjab (in short, ‘the State Commission’) in Appeal No. 1147 of 2008 – Malkiat Singh Vs. The Shaheed Bhagat Singh Nagar,Housefed Complex, Co-operative House Building Society Ltd. & Ors., by which appeal filed by the petitioner was dismissed and order of the District Forum dismissing the complaint, was upheld. 2. Brief facts of the case are that complainant/petitioner was allotted flat no. 521 on 6th floor by opposite party no. 1/respondent no. 1 and possession was delivered to the petitioner on 30-04-2002 after receiving entire amount of Rs.11.90 lakhs. Respondent no. 1 charged additional amount of Rs.1,000/- for creation of common fund which was to be used or maintenance of common services/area. It was also mentioned in the Brochure that monthly instalments as decided by opposite part no. 1 shall be payable by the members of this society for maintaining, regulating common areas and services. Petitioner was under impression that respondent no. 1 shall provide all amenities. It was further alleged that there was seepage of water in the lintel roof, which was brought to the notice of opposite parties. Many cracks developed in the walls. It was further alleged that respondent no. 1 was to provide two lifts and generator set for the use of allottee members. Complainant never withheld monthly payment of maintenance but resolution was passed by opposite party no. 1 that in case flatownerfailed to pay monthly water supply charges, his connection would be disconnected and complainant’s water connection would be discontinued. It was further alleged that only one lift was provided against provision of two lifts. Alleging deficiency on the part of respondents, complainant filed complaint before District Forum. Complaint was not admitted against respondents’ no. 2 & 3. Opposite party no. 1/respondent no. 1contested complaint before District Forum denied allegations of deficiency and further submitted that complaint is time barred and complainant himself is in arrears of maintenance charges, hence complaint be dismissed. Learned District Forum after hearing both the parties, dismissed complaint against which appeal filed by the petitioner was dismissed by learned State Commission vide impugned order against which this revision petition has been filed. 3. Heard petitioner in person at admission stage and perused record. 4. Learned petitioner submitted that as per Brochure, two lifts, generator set has not been provided and as there are many defects in the construction, which have not been removed by opposite parties; even then learned District Forum has committed error in dismissing the complaint and learned State Commission further committed error in dismissing the appeal, hence revision petition be admitted. 5. Admittedly, possession was delivered to the petitioner on 30-04- 2002 whereas complaint was filed before District Forum on 08-09-2005. Complaint should have been filed within a period of two years from getting possession of the flat regarding any defect in the construction or deficiency in the services. As complaint has been filed after almost three years and four months and no application has been moved for condonation of delay, complaint being time barred is not maintainable and learned District Forum has not committed error in dismissing the complaint and learned State Commission has not committed any error in passing the impugned order. 6. was As far as defects in the flats are concerned, as per delivery possession receipt, flat in good condition. In that construction of flat such circumstances, was defective. and generator set, petitioner could As far it as cannot providing not place be inferred two lifts any document to substantiate that respondent was to provide two lifts and generator set for inhabitants of the building. Learned Commission and District Forum rightly observed that as State petitioner himself was defaulter in making payment of maintenance charges, petitioner cannot claim benefit of service of lift, etc. to be provided by the respondent. It cannot be expected from the respondent to maintain all the services without contribution towards maintenance charges being made by flat owners and in such circumstances, petitioner is not entitled to any relief. 7. We do not find any illegality, irregularity or jurisdictional error in the impugned order, which calls for any interference and revision petition, is liable to be dismissed at admission state. 8. Consequently, revision petition filed by the petitioner is dismissed at admission stage with no order as to costs. .……………….……………… (K.S. CHAUDHARI, J) PRESIDING MEMBER .……………….……………… (DR. B.C. GUPTA) MEMBER aj NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 3345 OF 2012 (Against the order dated 10.01.2012 in Appeal No. 176/2009 of the State Consumer Disputes Redressal Commission, Rajasthan, CIRCUIT BENCH NO.2, Jaipur) M/s Sterlite Industries (India) Ltd. a Company incorporated under the Companies Act, having its Registered Office at SIPCOT Industrial Complex, TV Puram, Tuticorin 628002 (Represented By its Company Secretary) ........ Petitioner Versus Ganapati Finsec Pvt. Ltd. Registered Office : 37 K Block, Sriganganagar, Rajasthan Through its Director, Shri Devendra Kumar Mittal …….Respondent BEFORE: HON'BLE MR. JUSTICE J.M. MALIK, PRESIDING MEMBER HON’BLE DR.S.M.KANTIKAR, MEMBER For the Petitioner : Mr. Manish Garg, Advocate For the Respondent : Mr. Vijay K. Jain, Advocate Pronounced on : 12th July, 2013 ORDER JUSTICE J. M. MALIK, PRESIDING MEMBER 1. Ganapati Finsec is a private limited company. It had purchased 116 shares from the Sterlite Industries Limited. The above said 116 shares were deposited in the complainant’s Demat Account. 2. It is alleged that the respondent company, without the permission of the complainant, sent the cheque of Rs.11,600/- to the complainant company, drawn at Standard Chartered Bank Branch, M.G. Road, Mumbai, under Buyback Scheme for 116 shares @ Rs. 100/- per share, in the year 2002, along with 580 NonConvertible Debentures. The complainant company refused to accept the same and informed the respondent, through e-mail, on 04.02.2003, 17.02.2003 and 20.02.2003 and the above said cheque was returned by the complainant company to the respondent company. The complainant company sent a letter/Notice dated 22.02.2003 to the respondent company for depositing back the 116 Demat Start Lite Industries Ltd.’s shares in the CDLL Demat Account of the complainant company. Complainant Company also stated that it may deposit the above said debentures in the account of the respondent. The respondent company neither gave the reply nor returned the 116 shares to the complainant. Thereafter, a legal notice was sent on 16.10.2003, but the respondent company did not respond. It is alleged that the respondent has committed deficiency in service by not returning the 116 shares of Demat to the complainant and by not replying to the letter dated 22.02.2003 and notice dated 16.10.2003, and this act of respondent caused unnecessary mental harassment and financial losses to the complainant company. 3. The petitioner accordingly filed the complaint under Section 12 of the Consumer Protection Act, with the prayer that respondent be directed to give 116 shares of Sterlite Industries Limited of Demat account of the complainant company so that the complainant company may deposit the debentures in the account of the respondent. It was further prayed that compensation in the sum of Rs. 10,000/- and costs amounting to Rs. 2,200/-, be also awarded. 4. The District Forum dismissed the complaint. It was held: “Complainant has not stated anything in his complaint with regard to Option Form nor has stated in the affidavit that Option Form was not received by him. Despite filing of reply to the affidavit on behalf of the non-applicant, complainant has neither filed affidavit in rebuttal nor denied the above averments of the non-applicant that he had received the Option Form, as desired under the approved Scheme. Therefore, there is no reason to discard this averment mentioned in the reply of the non-applicant that the Option Form was received by the complainant, under the Scheme. In such circumstances, when according to the Scheme, non- applicant had the right to buy back the share under the Scheme, in case option form of the complainant was not received and in exercise of the above right, chequeof Rs. 11,600/- at the rate of Rs.100/- per share, towards 116 shares held by the complainant was sent to him and 580 Non-Convertible Debentures were deposited in his De-mat Account. Thus, complainant is not entitled to any relief, as sought in the complaint”. 5. Aggrieved by this order, the complainant filed First Appeal before the State Commission. The State Commission allowed the complaint. It was held: “In our opinion, respondent, without sending the Option Forum, cannot convert the shares into debentures. Thus, complaint of the complainant is liable to be allowed against the respondent. Thus, after allowing the appeal and complaint, respondent is directed to deposit 116 shares of the complainant again and provideDemat account to him and also pay the dividend and bonus accrued on it, from time to time. He is further directed to pay Rs. 5000/- as compensation and Rs. 1000/- towards costs of proceedings. Accordingly, appeal and complaint are allowed”. 6. In this revision petition, we have heard the counsel for the parties. The main question which falls for consideration ‘Consumer’?”. Learned counsel for the is, “Whether the complainant complainant/respondent is a vehemently argued that the revisional jurisdiction is limited. The National Commission can decide the legal question, if any, but should interfere into facts, which have already been adjudicated not by the Fora below. It was also submitted that this issue was never raised. The OP did not raise any objection on this point. This is explained that there is no dispute between the parties. He submitted that shares are goods and there is deficiency on the part of the petitioner/OP. 7. Counsel for the respondent has cited few authorities reported in the cases of “Lakshmi Engineering Works V. P.S.G. Industrial Institute” [AIR 1995 Supreme 1428], “Kalpavruksha Charitable Court Trust versus Toshniwal Brothers (Bombay) Pvt. Ltd.” [(2000) 1 Supreme Court Cases 512], “Saurashtra Oil Mills Association, Gujarat versus State of Gujarat & Another” [AIR 2002 Supreme Court PalChoudhary versus Sheirly Weigal Nain Court 3011]”. 1130] & “Subhadra Rani and others [AIR 2005 Supreme In the first two authorities, it was held that whether purpose for which person has bought goods is a commercial purpose within the meaning of the definition of expression consumer in Section 2 (d) of the Act is always a question of fact to be decided in the facts and circumstances of each case. In the last two authorities, it was held that dismissal of Special Leave Petition is a nonspeaking order, what remains a dismissal simplicitor, in which permission to file the appeal to this court is not granted, it would not mean to be the declaration of Law by the Apex Court. 8. The above said authorities are not of much help to the respondent. We have perused the reply and affidavit filed before the District Consumer Disputes Redressal Forum, Shriganganagar. In para No. 6, the petitioner/OP clearly, specifically and unequivocally, made the following averments: “Non-applicant again submits in reference to paras 1 to 6 of the complaint and saves its above averments and whichever is contrary and irrelevant, they are denied. No comments in regard to Para 1. As per the definition given under CP Act, in reply to para 2, it is not admitted that the complaint is a ‘consumer complaint’ ……..”. 9. It is clear that the objection was raised by the respondent at the earliest possible opportunity. It must be borne in mind that the Complainant is a Private Limited Company, which is registered under the Companies Act 1986. The shares were purchased by the Complainant Company and not by any individual. It was not established that these shares were not purchased for any commercial purpose. It must be borne in mind that the disputes between the parties relating to commercial purposes are excluded under the Act. This view stands fortified by a recent judgment of this Commission, reported in “Vijay Kumar Vs. Indusind Bank, II 2012 CPJ 181 (NC)”, wherein it was held: “10. Again, such like question arose for consideration before National Commission in case of Som Nath Jain Vs. R.C. Goenka &Anr, reported in 1 (1994) CPJ 27 (NC). In that case, dealing with sale-purchase of shares, National Commission expressed serious doubt, whether the complaint, qua, it would be maintainable under the Consumer Protection Act. Because, qua such transactions, elaborate evidence need to be taken regarding purchase and sale of shares, their prevalent price in the market and evidence regarding passing of instructions by client to the broker. Resultantly, the complainants were relegated to get the dispute decided through civil court. 10. West Bengal State Consumer Disputes Redressal Commission, Kolkata, in case Ramendra Nath Basu Vs. Sanjeev Kapoor & Anr., reported in 1 (2009) CPJ 316 qua share trading has held that transactions between parties do not come under purview of Consumer Protection Act, 1986. 11. Similar view was taken Disputes Redressal Commission, New by the Delhi Delhi in State Consumer case Anand Prakash Vs. A.M. Johri & Ors., reported in III (2000) CPJ 291, by holding that “sale-purchase of shares are commercial transactions, so, the complainant is not a ‘consumer’, in such cases”. 12. The same view was “A. Asaithambi Vs. Company Secretary Satyam & Ors.” by this Bench. The Hon’bleSupreme also taken Computer Court, vide Services order in Ltd. dated 14.12.2012, in Special Leave to Appeal (Civil) No. 36840 of 2012 (A. Asithambi Vs. Company Secretary Satyam Computer Services Ltd. & Orts.), dismissed the case in limine. 13. This view is further supported by the case of Dr. V.K.Agarwal Vs. M/s Infosys Technologies Ltd. & Ors. in OP No. 287 of 2001, decided on 24.07.2012, by this Bench . 14. In Morgan Stanley Mutual Fund vs. Kartick Das (1994) 4 SCC 225, paras 26, 27, 33, 34 & 35, are relevant. However, paras 33, 34 and 35, are reproduced, as under : “33. Certainly, clauses (iii) and (iv) of Section 2(1) ( c) of the Act do not arise in this case. Therefore, what requires to be examined is, whether any unfair trade practice has been adopted. The expression ‘unfair trade practice’ as per rules shall have the same meaning as defined under Section 36-A of Monopolies and Restrictive Trade Practices Act, 1969.That again cannot apply because the company is not trading in shares. The share means a share in the capital. The object of issuing the same is for building up capital. To raise capital, means making arrangements for carrying on the trade. It is not a practice relating to the carrying of any trade. Creation of share capital without allotment of shares does not bring shares into existence. Therefore, our answer is that a prospective investor like the respondent or the association is not a consumer under the Act. 34. From the above discussion, it is clear that the question of the appellant company trading in shares does not arise. 35. In view of our answers to questions 1 and 2, it follows that the Consumer Disputes Redressal Forum has no jurisdiction, whatsoever”. 15. In a recent authority in the case of Ganapati Parmeshwar Kashi & Anr. Vs. Bank of India & Anr. First Appeal No. 362 of 2011, the National Commission, headed by Hon’ble Justice Ashok Bhan, was pleased to hold : “Apart from this, State Commission also held that since the appellants had alleged that they had suffered loss as they could not trade due to suspension of accounts, were not consumers as the dispute related to loss and profit from the share business of the appellants. We agree with the view taken by the State Commission. Bank could not continue the Demat Account, in violation of the terms and conditions laid down by the NDSL and RBI. Appellants had admittedly failed to furnish the identity proof by submitting copies of PAN cards, etc., as per directions of NDSL and RBI. For Demat Accounts, Respondent Bank is bound by the directions issued by NDSL and RBI. Dismissed”. 16. The aggrieved party went to the Supreme Court. The Apex Court dismissed the Special Leave Petition on 14.01.2013 and held, as under : “ii) The concurrent finding recorded by the State Consumer Disputes Redressal Commission, Maharashtra and the National Consumer Disputes Redressal Commission that the petitioners cannot be treated as ‘consumer’ within the meaning of Section 2(d) of the Consumer Protection Act, 1986, is based on analysis of the pleadings filed by the parties. The DMAT Account was opened by the petitioners purely for commercial transactions. Therefore, they were rightly not treated as ‘consumer’ so as to entitle them to claim compensation by filing complaint under the 1986 Act”. 17. Consequently , we accept the revision petition and dismiss the complaint. However, there shall be no order as to costs. ..………………………… (J. M. MALIK,J.) PRES IDING MEMBER …………….…………… (DR.S.M. KANTIKAR) MEMBER Jr/2 NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 2862 OF 2008 (From the order dated 13.5.2008 in Appeal No. 541/2007 of the State Consumer Disputes Redressal Commission, UT, Chandigarh) M/s. Tata AIG General Insurance Co. Ltd. A Company incorporated under the Companies Act, having its Registered Office at Peninsula Corporate Park, Nicholas Piramal Tower, 9th Floor, Ganpathrao Kadam Marg, Lower Parel, Mumbai – 400 013 and Zonal Office at 1st Floor, Barjeye Towers, Community Centre, New Friends Colony, New Delhi – 110065 …Petitioner/Opp. Party (OP) Versus M/s. Balaji Medicos, SCO No. 355, Sector – 32, Chandigarh, through its Proprietor Shri Kewal Krishan …Respondent/Complainant BEFORE HON’BLE MR. JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER HON’BLE DR. B.C. GUPTA, MEMBER For the Petitioner : Mr. Anjalli Bansall, Advocate For the Respondent : Mr. Vijay Kr. Mangla, Advocate PRONOUNCED ON 12th July, 2013 ORDER PER JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER This revision petition has been filed by the petitioner/opposite party against the order dated 13.5.2008 passed by the State Consumer Disputes RedressalCommission, UT Chandigarh (in short, ‘the State Commission’) in Appeal No. 541/2007 – M/s. Balaji Medicos Vs. Tata AIG General Insurance Co. Ltd. by which, while allowing appeal, order of District Forum dismissing complaint was set aside. 2. Brief facts of the case are that complainant/respondent was doing business of sale of drugs and pharmaceuticals as a wholesaler and retailer at shop Nos. 2 & 3, Iron Market, Sector 29, Chandigarh and was also running retail business at Sector 32, Chandigarh under the name and style of M/s. Balaji Medicos. Complainant took insurance policy for the goods lying at its godown in Sector 29 for Rs.10 lakhs from OP No. 1/petitioner which was valid from 18.10.2003 to 17.10.2004. On account of heavy rains on the intervening night of 2/3-8-2004, drugs and medicines stored in the godown were damaged, as water had entered into godown. Complainant informed to the OP and submitted claim of Rs.10,08,126.20. OP appointed assessor to assess the loss and at the instance of surveyor, complainant revised claim and lodged claim of Rs.9,08,846/-. OP sent cheque of Rs.6,00,533/- on 26.10.2004 towards full and final settlement, which was received by the complainant under protest. After legal notice, OP did not release payment of Rs.3,08,313/- and in such circumstances, alleging deficiency on the part of OP, complainant filed complaint before District Forum. OP contested complaint and submitted that stocks of Sector 29 as well as Sector 32 were damaged. Due to rains, surveyor assessed loss of Rs.6,00,533/- for the stocks lying in Sector 32 and this amount was paid to the complainant as full and final settlement and prayed dismissal of complaint. Learned District Forum after hearing both the parties dismissed complaint against which, appeal filed by the complainant was allowed by the impugned order against which, this revision petition has been filed. 3. Heard learned Counsel for the parties and perused record. 4. Learned Counsel for the petitioner submitted that, as the amount was accepted by the complainant in full and final satisfaction of the claim, learned District Forum rightly dismissed complaint. It was further submitted that stocks of godown of Sector 29 were only insured and as per survey report, payment of assessed loss had been made; even then learned State Commission had committed error in allowing appeal for rest of the amount; hence, revision petition be allowed and impugned order be set aside. On the other hand, learned Counsel for the respondent submitted that learned State Commission after elaborate discussion has rightly allowed complaint and order passed by the learned State Commission is in accordance with law, which does not call for any interference; hence, revision petition be dismissed. 5. First question to be decided by this Commission is; whether complainant accepted cheque of Rs.6,00,533/- towards full and final settlement of the claim, or not. Complainant in para 10 of the complaint has clearly stated that cheque of Rs.6,00,533/- has been received by the complainant towards full and final settlement of the claim on 26.10.04. It appears that later on by hand “and was received under protest” has been inserted. Affidavit in support of this complaint has also been filed by the complainant and para 10 of the affidavit does not depict receipt of payment under protest. In such circumstances, it can very well be held that cheque of Rs.6,00,533/was received by complainant towards full and final settlement to the claim. OP/petitioner has clearly mentioned in paragraph 10 of its reply before District Forum that complainant has received aforesaid amount as full and final settlement of the claim. Thus, it becomes clear that complainant after receiving Rs.6,00,533/- on 26.10.2004 towards full and final settlement of the claim issued legal notice to the OP for release of rest of the amount and filed Complainant No.274/05. Ld. Counsel for the respondent could not apprise the date, when legal notice was given for release of rest of amount and on which date complaint was filed. Perusal of complaint case number reveals that complaint might have been filed in mid of year 2005, whereas complainant received cheque of Rs.6,00,533/- on 26.10.04. Filing complaint after many months and that too without pleading, coercion, fraud, undue influence, etc., it cannot be believed that amount was received under protest. Once the amount is received towards full and final settlement of the claim, complaint for rest of the amount is not maintainable, as held by Hon’ble Apex Court in JT 1999 (6) SC 23 – United India Insurance V. Ajmer Singh Cotton & Gen. Mills & Ors. etc. and (2000) SCC 334 – New India Ass. Co. Ltd. Vs. Sri Venkata Padmavathi R&B Rice Mill. Ld. State Commission has committed error in allowing complaint, though, complainant received amount towards full and final satisfaction of the claim. 6. As far value of stocks lying in the godown in Sector 29 are concerned, surveyor has clearly mentioned in its survey report that goods worth Rs.7,39,230/- was lying in Sector 29 and goods worth Rs.3,14,270/- was lying in shop situated in Sector 32. Cross-examination of Mr. Shiv Kumar, Chartered Accountant of complainant clearly reveals that Annexure P-8 was the consolidated statement of Sector 32 and Sector 29, which was signed by him as well as by proprietor of complainant firm. Closing stock of both the places was of Rs.10,53,500/-. In such circumstances, learned State Commission has committed error in holding that closing stock of Sector 29 was worth Rs.10,61,150/- and allowing appeal of the complainant. 7. In the light of aforesaid discussion, it becomes clear that, as complainant had accepted payment towards full and final settlement of the claim and failed to prove stock worth Rs.10,61,150/- in godown of Sector 29, learned District Forum rightly dismissed complaint and learned State Commission has committed error in allowing appeal and impugned order is liable to set aside. 8. Consequently, revision petition filed by the petitioner against the respondent is allowed and impugned order dated 13.5.08 passed by Ld. State Commission in Appeal No. 541/07 – M/s. Balaji Medicos Vs. Tata AIG Gen. Ins. Co. Ltd. & Ors. is set aside and order of District Forum dismissing complaint is affirmed. There shall be no order as to costs. ..……………Sd/-……………… ( K.S. CHAUDHARI, J) PRESIDING MEMBER ..…………Sd/-………………… ( DR. B.C. GUPTA ) MEMBER k NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 1895 OF 2013 (Against order dated 30.11.2006 in First Appeal No. A/38/2007 of the Maharashtra State Consumer Disputes Redressal Commission, Mumbai) Circuit Bench at Aurangabad Shailendra S/o Madanlal Malara, Proprietor of M/S Vardhman Computers, Plot No. 9, Shriram Colony, Samarth Nagar, Aurangabad -431001 (Maharashtra State) …Petitioner Versus 1. M/S Kulkar Corporation, 4, Gazi Industrial Shed, Hare Ram Industrial Estate, I.V. Patel Road, Cross lane Goregaon (East), Mumbai- 400063 2. M/S Kulkar Corporation, 6, Akruti, 76-A, J.P. Nagar Road No. 5, Goregaon (East), Mumbai- 400063 3. Shri M.D. Shirodkar, One of the Partner of M/S Kulkar Corporation, 4, Gazi Industrial Shed, Hare Ram Industrial Estate, I.V. Patel Road, Cross lane Goregaon (East), Mumbai- 400063 4. Shri M.D. Shirodkar, One of the Partner of M/S Kulkar Corporation, 6, Akruti, 76-A, J.P. Nagar Road No. 5, Goregaon (East), Mumbai- 400063 …Respondent(s) BEFORE: HON’BLE MR.JUSTICE J.M.MALIK, PRESIDING MEMBER HON’BLE DR.S.M.KANTIKAR, MEMBER For the Petitioner(s) : Ms. Meenakshi Midha, Advocate PRONOUNCED ON 15th JULY, 2013 ORDER PER DR. S.M. KANTIKAR Brief Facts: 1. The Petitioner / Complainant had filed the complaint against the Opposite Parties/Respondents for providing the defective offset printing machine to him. The case of the Complainant in brief is that, he had placed a confirmed order on 17.08.1998 for “Pack to Pack Offset Printing Machine” from M/S Kulkar Corporation, Mumbai by paying necessary advance. That, although the respondent had promised to deliver the machine by 31.12.1998, it had actually delivered on 12.01.2000 i.e. after the delay of about one year. At the time of delivery the entire amount was paid to the respondent. It was contended that, the respondents had assured that, if any defect is occurred, it would be rectified from their end and would also help the installation and final trial of the said machine would be taken at Aurangabad. However, the respondents did not arrange for sending their engineers for the installation of the said machine and it was installed by the complainant himself. It was further contended that, after its installation and trial, it was found that the machine was not giving proper result. The respondent was informed but the defects were not removed. Therefore, complainant filed a complaint before District Forum on 19.04.2001 for total compensation of Rs.3,55,540/-. 2. The respondents (OP) appeared before the District forum contended that as per the contract the Complainant was to pay 40% cost of the machine at the time of placing of the order. However the Complainant paid only Rs.50,000/-. It was further contended that after placing of the order for the machine the Complainant suggested so many changes in the machine. Therefore it was necessary for the OPs to take trial again and again as per the suggestion of the Complainant. It was contended that after having rigorous five trials of the machine Complainant had accepted delivery of the said machine. The said machine was installed by the Complainant himself and had not followed the instructions as per the manual about the installation. It was contended that the District Forum Aurangabad had no jurisdiction to entertain the complaint as cause of action arose in Mumbai. It was also averred that the said machine was purchased for commercial purpose to earn profit. As the Complainant himself has admitted in his compliant that he had employed labours, workers etc. and he had to pay their salary and wages from his own pocket and hence as per definition given under the Consumer Protection Act, he was not a “consumer” and the complaint filed by him was not maintainable before Forum. It was thus requested to dismiss the complaint. 3. The District Forum heard the parties. District Forum appointed a Commissioner for verification of the performance of the said machine. On the basis of Commissioner’s Report and the available records the District Forum allowed the Complaint and directed the OPs to refund cost of machine of Rs.4,05,000/- along with other reliefs. 4. Aggrieved by this order of District Forum the Respondents preferred an Appeal before the State Commission. The learned Counsel for Respondent therein contended that machine was purchased for commercial purpose with the motive of getting profits and hence the Complainant was not covered under the definition of Consumer as per Consumer Protection Act. He also contended that the Complainant has not proved the manufacturing defects, the Commissioner was not an expert and the machine was installed by the Complainant on his own. Therefore, the OPs are not liable. The OPs further relied upon the judgments of Hon’ble Supreme Court: 1) Laxmi Engineering Works Vs. PSG Industrial Institute, reported in AIR 1995 S.C. 1428. 2) Poly Products Factory, Jalgaon and another, Vs. Shri. Girish Vs. Shah and Anr. in F.A. No. 1781/2005. 5. The Learned Counsel for the Complainant vehemently argued the matter before the State Commission and relied upon few authorities of this Commission. 6. The State Commission allowed the appeal considering the machine was purchased for commercial use and not for earning livelihood by the Complainant. 7. Against this order of the State Commission the Petitioner/Complainant preferred this Revision Petition. 8. We have heard the Learned Counsel for the Petitioner who stressed her arguments that the Complainant was consumer. She contended that since the machine was lying with respondent company from 2004 for last 9 years, the same has now become total scrap. 9. The counsel for petitioner relied upon the judgments of this Commission. The case of Hindustan Power Plus Ltd. vs. Santosh Drillers & Ors., IV (2007) CPJ 161 (NC) and several other judgments of this Commission. But, we do not find any relevance of those judgments in this petition. 10. 11. We have perused the documents available on the file which clearly raises the question that whether the Complainant is a consumer as per Section 2 (1) (d) of the CPA. The respondent’s objection was that the machine purchase by the Complainant for commercial purposes to earn profit, hence, he was not a consumer. The livelihood is depending upon the earnings by the way of profits. The explanation reduces the question, what is a “commercial purpose”, to a question of fact to be decided in the facts of each case. It is not the value of the goods that matters but the purpose to which the goods bought are put to. The several words employed in the explanation, viz., “uses them by him”, “exclusively for the purpose of earning his livelihood” and “by means of self-employment” make the intention of Parliament abundantly clear, that the goods bought must be used by the buyer himself, by employing himself for earning his livelihood. A few more illustrations would serve to emphasize what we say. A person who purchases an auto-rickshaw to ply it himself on hire for earning his livelihood would be a consumer. 12. On perusal of the Complaint and affidavit in support of the Complaint was filed by the Complainant before the District Forum it is revealed that the Complainant has nowhere mentioned that the said machine is purchased for earning livelihood by means of self-employment. As per explanation given under section 2 (1) (d) (ii) of C.P. Act “commercial purpose” does not include use by a person of goods bought and used by him and services availed by him exclusively for the purposes of earning his livelihood by means of self-employment. In fact, as pointed out by the appellant while claiming the compensation the complaint has sought compensation in respect of expenses incurred by him towards salaries, wages, of the employees etc. He has also mentioned in his complaint that due to defective machine he had to sustain loss in his business. The very nature of the complaint reveals that Complainant had purchased the machine not only to earn profit out of it. Hence the Complainant does not fall within the explanation given under section 2 (1) (d) (ii) C.P. Act. 13. Therefore, the District Forum erred in allowing the complaint. We agree with the view of the State Commission. Therefore, no need to interfere in the order of State Commission. Accordingly, we pass the order that this Revision Petition, stands dismissed. No order as to costs. 14. The Petitioner/Complainant is given opportunity to file the complaint before the appropriate Forum except Consumer Fora for Redressal of his grievance, if any. He can seek help from Laxmi Engineering Works Vs. PSG Industrial Institute, A.I.R. 1995 S.C. 1428. …..………………………… (J. M. MALIK, J.) PRESIDING MEMBER .…..………………………… (S. M. KANTIKAR) MEMBER MSS NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 4493 OF 2012 (From the order dated 07.08.2012 in First Appeal No. 617/2008 of the Haryana State Consumer Disputes Redressal Commission,Panchkula) Alka Narwal W/o Sh. Balinder Singh House No. 194, Shastri Colony, Yamunanagar, Tehsil Jagadhri District Yamunanagar Haryana 15-A/1, Model Town, Patiala …Petitioner Versus 1. Haryana Urban Development Authority Through its Chief Administrator, HUDA, Haryana 2. The Estate Officer, HUDA, HUDA Office Jagadhri, Harayana …Respondents BEFORE: HON'BLE MR. JUSTICE J.M. MALIK, PRESIDING MEMBER HON’BLE DR. S.M. KANTIKAR, MEMBER For the Petitioner : Mr. Keshav Kaushik, Advocate with Mr. Balinder Singh, Petitioner’s Husband PRONOUNCED ON 16th JULY, 2013 ORDER PER DR. S.M. KANTIKAR 1. That the present Revision Petition is directed against the Impugned Order dated 07.08.2012, whereby the Hon’ble State Commission had been pleased to allow the First Appeal No. 617 of 2008 filed by the Respondents herein and set aside the order dated 11.12.2007 passed by the Ld. District Forum in Consumer Complaint. The Hon’ble State Commission had also dismissed the complaint filed by the Petitioners before the Ld. District Forum. 2. The brief facts : The Complainant was allotted plot No. 146 located in Sector-15, HUDA, Jagadhri in the lot of draw held on 30.07.1991. The possession of the plot was offered to the Complainant vide letter No. 691 dated 28.01.1999. The Complainant neither deposited the balance amount with respect to the price of the plot including the enhancement price nor came forward to take possession. Complainant filed complaint No. 343/2000 which was accepted by the District Consumer Disputes Redressal Forum, Yamunanagar at Jagadhri vide order dated 23.11.2000 with the direction to the Opposite Parties to refund the amount deposited along with 10% interest and other relief. 3. Thereafter, the Complainant did not want to implement the said order of the District Consumer Forum, she filed an affidavit on 28.01.2002. But, the higher authorities of HUDA, Jagadhri decided to implement the order of the District Forum subject to the decision of the State Commission. Accordingly, as per the direction and in pursuance of the letter issued by the Chief Administrator, HUDA, Panchkula, the Opposite Parties sent a cheque to the complainant bearing No. 466017 dated 14.10.2005 for an amount of Rs.8,53,491/- through speed post on 29.11.2005 but the same was received back by the Opposite Parties with the report as “not met” dated 29.11.2005, 30.11.2005 02.12.2005, 05.12.2005, 06.12.2005 and 08.12.2005. 4. Further in 2007 the complainant filed another compliant No. 813 of 2007 before the District Forum seeking direction to the Opposite Parties to hand over the actual and physical possession of the plot and to grant other relief as prayed for in the prayer clause of the Complaint. The subject matter of complaint was that the HUDA authorities instead of complying with the order dated 23.11.2000 had asked the Complainant to take back the plot in question. Accordingly, she had submitted her affidavit dated 29.04.2002 to retain the plot and not to execute the order dated 23.11.2000. She was ready to pay the entire price of the plot along with interest and extension fee as well as the enhanced price of the plot but the OPs did not accede to her request. For that reason she filed in the instant complaint before the District Forum. 5. On the other hand, the OPs resisted the complaint’s averments, also contended that an appeal No 2766/2004 filed by HUDA against the order of District Forum was dismissed by the State Commission vide order dated 22.03.2007. Therefore, in compliance of the order of the District Forum as well as of the State Commission, the OPs again sent a cheque bearing No. 541011 dated 06.04.2007 for an amount of Rs.8,53,491/- through registered post on 26.04.2007 which was received back with the report “not met” on 3/5/2007. Thereafter, the cheque duly was sent to the Complainant twice on 28/8/2007 and 7/9/2007 through Charanjit Singh, Field Chowkidar, HUDA but the Complainant refused to accept the said cheque which was reported by the said Chowkidar. Thus, OPs prayed for dismissal of complaint. 6. On appraisal of the pleadings of the parties and the evidence adduced on the record, District Forum accepted complaint and passed an order as “the respondents to handover the actual physical possession of the plot no. 146 in Sector-15 HUDA to the complainant and till the actual physical possession is delivered not to demand any extension fees from the complainant and pay Rs. 50,000/- as cost of escalation charges on account of mental agony, harassment and unfair trade practice and pay Rs. 5500/- as litigation expenses.” 7. Aggrieved by the order of the District Forum, the Opposite Parties filed an Appeal No.813/2007 before State Commission. The state commission accepted the appeal and passed an order on 7/8/2012 with following observations:Before parting with the order it is material to mention here that the Complainant has been able to manage for allotment of the plot from the office of Estate officer HUDA, Jagadhri/Chief Administrator, HUDA, Panchkula which is totally against the spirit of the order dated 23.11.2000 of the District Forum as well as the State Commission order dated 22.03.2007 (qua judicial order). During the pendency of this appeal, three applications were moved by the Complainant with the prayer to decide this Appeal at earlier possible time to enable her to raise the construction on her plot, which shows the collusion of the Complainant with the official of HUDA to bypass the order of the District Forum with respect to refund of the amount, instead the authorities have allotted the plot of their own against the spirit of the order dated 23.11.2000, maintained by State Commission vide order dated 22.03.2007. This act of Complainant and the erring officials of HUDA has caused huge financial loss to the state Exchequer. Under the facts and circumstances of the case, it is ordered that Chairman/Chief Secretary to Government of Haryana HUDA will hold a discrete enquiry in the matter to punish the erring officials of HUDA for acting against the spirit of the order of the District Forum dated 23.11.2000 which was maintained vide order dated 22.03.2007 by State Commission. This is one of the numerous cases which have come to our notice after the consumer lost his/her case before the Consumer For a. The erring officials of HUDA who are involved in this illegal act, are burdened with Rs.50,000/- as cost, which on recovery will be deposited with the Legal Service Authority, Haryana. Copy of this order be sent to the Chief Secretary to Government of Haryana for doing needful. 8. Against the said order of State Commission this revision petition filed before us. 9. We have heard the counsels and perused the material on record. It is clear that after dismissal of appeal No 2766/2004 filed by HUDA the HUDA authorities have complied with the order of District Forum. OPs have sent cheque for amount of Rs.8,53,491/- by post and as well through Chowkidar several times to the complainant but the complainant refused it. The act and conduct of complainant shows that she doesn’t want refund amount but, wants to get the plot from HUDA as the prices increased drastically. 10. The complainant filed another complaint which is barred by the principles of Res Judicata as the present complaint No.813/2007 and previous complaint No. 343/200 based on same cause of action despite matter has been decided in favor of complainant. We uphold the observations and order of Sate Commission. 11. Hence, we dismiss this revision petition. No order as to costs. ..…………………..……… (J.M. MALIK J.) PRESIDING MEMBER ……………….…………… (S.M. KANTIKAR) MEMBER Mss NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 342 OF 2013 (From the Order dated 10.10.2012 in Appeal No. 441/2008 of Haryana State Consumer Disputes Redressal Commission, Panchkula) New India Assurance Co. Ltd. Yamuna Nagag Through its Manager Regional Office, S.C.O. No.36-37 Sector 17-A, Chandigarh Petitioner Versus M/s Uni Ply Industries Village Jorian Yamuna Nagar Through Sh. Rajiv Gupta S/o Shri H.R. Gupta R/o House No.523-L Model Town, Yamuna Nagar Haryana Respondent BEFORE: HON’BLE MR. JUSTICE AJIT BHARIHOKE, PRESIDING MEMBER HON’BLE MR. SURESH CHANDRA, MEMBER For the Petitioner : Shri Mohan Babu Aggarwal, Advocate Pronounced on : 16th July, 2013 ORDER PER SURESH CHANDA, MEMBER The petitioner Insurance Co. which was OP before the District Forum has filed this revision petition against the concurrent finding of both the Fora below holding the petitioner company liable for deficiency in service in terms of the impugned order passed on 10.10.2012 by the State Consumer Disputes Redressal Commission, Haryana, Panchkula in FA No.441/2008. By its order, the State Commission dismissed the appeal of the petitioner Co. and upheld the order dated 3.1.2008 passed by the District Forum, Yamuna Nagar in consumer complaint No.1115 of 2007. The District Forum had allowed the complaint of the respondent / complainant by granting the following reliefs:“Resultantly we allow the complaint of the complainant and direct the respondent to pay the balance amount of Rs.10,86,592/- along with interest at the rate of 12% per annum after three months of the causing of fire till realization and to pay Rs.11,000/as litigation expense. Order be complied within one month.” 2. Briefly stated, the respondent/complainant had insured stock of its factory for a sum of Rs.30 lakhs vide cover note valid from 10.4.2005 to 9.4.2006 issued by the petitioner Co. The insurance cover was renewed for next year also by the respondents and was valid upto 9.4.2007. According to the respondent/complainant, the petitioner Insurance Co. issued one page cover note only of the said policy and never issued the terms and conditions with this policy to the complainant. On the intervening night of 56th April 2006, a fire broke out in factory premises resulting into huge loss of stock. The complainant lodged the DDR on 6.4.2006 with the local police followed by intimation to the petitioner Co. which deputed spot surveyor who verified the fact of fire along with Branch Manager of the petitioner Co. The petitioner Co. appointed another surveyor for assessing the loss. The complainant lodged a claim with the petitioner Co. for Rs.19,46,800/- along with necessary documents for settling the claim. The petitioner Co. informed the complainant about the settlement of the claim at Rs.8,60,208/- for which a cheque dated 1.12.2006 was issued by the petitioner Co. to the complainant after making certain deductions from the sum of Rs.10,86,592/- which had been assessed as loss by the surveyor. The respondent / complainant received the said amount and signed the discharge voucher indicating it to be only a partial settlement and thereafter the respondent continued to represent against the deduction made from the sum of Rs.10,86,592/-. Since the differential amount which had been deducted from the figure of loss assessed by the surveyor was not allowed by the petitioner Co., the respondent / complainant filed a consumer complaint alleging it a case of deficiency in service on the part of the petitioner Co. On being noticed, the petitioner Co. contested the complaint and raised the plea that it had already settled the case of the complainant within a reasonable time and paid a sum of Rs.8,60,208/- as full and final settlement and nothing remained due to the complainant by the OP Co. It was further submitted by the OP Co. that the claim was settled as per the report of an IRDA approved independent surveyor and loss assessor who had arrived at a net loss figure of Rs.8,60,208/ subject to terms and conditions as well as limitations and exceptions provided in the insurance policy. Since certain amount was deducted as per excess clause and the net amount had been disbursed as per full and final settlement, the OP Co. denied any kind of deficiency in service on its part and prayed for dismissal of the complaint. 3. The District Forum after hearing the parties and appraising the evidence placed before it, allowed the complaint in terms of the aforesaid order which after challenge by the OP insurance co. before the State Commission came to be confirmed in appeal. 4. We have heard arguments of learned counsel Sh. Mohan Babu Aggarwal, Advocate for the petitioner. Learned counsel submitted that petitioner had appointed IRDA approved surveyor and loss assessor to give his preliminary surveyor report and it had also appointed another surveyor to certify and assess the final loss in the premises of the insured. He submitted that based on the surveyor’s report which assessed the loss to the tune of Rs.8,60,208/- after making necessary deductions on account of excess clause, the amount was immediately disbursed to the complainant and the complainant accepted it. He contended that the surveyor is the best person to assess and ascertaining the loss and its recommendations should have been accepted as provided in the Insurance Act. Another contention raised by learned counsel was that the payment made by the insurance co. was by way of full and final settlement of the claim lodged by the complainant and since he accepted the amount sent by cheque and signed the discharge voucher, the complainant is not entitled for any further relief. In view of this, learned counsel submitted that the Fora below erred in ignoring these aspects while awarding further compensation over and above that recommended by the surveyor and already accepted by the complainant towards full and final settlement of its claim. In the circumstances learned counsel prayed for setting aside of the impugned order and acceptance of the revision petition. 5. We have considered the arguments of learned counsel and perused the reports of the surveyors as well as the orders of the Fora below. The points raised by learned counsel have been considered at length by the District Forum in its order which has been upheld by the State Commission by the impugned order. The submission of the learned counsel regarding settlement of claim by way of full and final settlement is obviously not correct since it was submitted by the complainant and upheld by the Fora below that the respondent / complainant had accepted the cheque of Rs.8,60,208/- as partial relief and that too under protest. Nothing has been placed before us to rebut this fact. Besides this, it is settled law that surveyor’s report cannot be treated as last word and a gospel truth. The District Forum after considering the report has given its cogent reasons to disagree with the final figure of loss while giving the desired relief to the complainant. The State Commission has agreed with the finding. The State Commission while dismissing the appeal of the petitioner has made the following observations in its impugned order:“After gone through the file as well as arguments of counsel for both the parties, we are of the considered view that it is admitted fact the factory of the complainant namely Unit Ply Factor was insured with the OP for amounting to Rs.30,00,000/- and the said factory was enjoying CC limit against the stock statement with Oriental Bank of Commerce, Yamuna Nagar. It is also admitted that on intervening night of 5/6.4.2006 the fire broke out in the said factory and intimation in this regard was given to the OP and the complainant also lodged DDR with the police. It is also admitted that on intimation the OP appointed two surveyors, one for spot survey and second for conduct the final survey. It reveals from the final survey report that maximum quantity of insured stock of material was burnt and mixed up beyond recognition and it was not possible to prepare inventory of the damage stock. The surveyor after inspect the stock statement which are issued by the bank, the surveyor observed that on an average the insured is having stock worth Rs.29 lacs comprising of finishing raw material and made clear that the statement of account dated 31.3.2006 is shown the stock of Rs.29,29,067/- vide which this is clear that after deducting the said stock which was not damaged the insured suffered a loss to the tune of Rs.19,46,800/- lying in the factory premises due to fire. The surveyor after using the excess clause deduct the 20% as is clear from the surveyor report. But in our view if the ambiguity in terms and surveyor apply the excess clause of the policy which were not supplied the OP cannot claim benefit of the said clause. Moreover, the full and final settlement was not matured because the complainant accepted the amount under protest and endorsement to this effect was made on the voucher that it is part payment. Thus, deficiency in service on the part of appellant/opposite party stands proved. District Consumer Forum after considering each and every aspect of the case, rightly allowed the complaint of complainant.” 6. The powers of National Commission flows from section 21(b) of the Consumer Protection Act, 1986 which reads thus:“(b)to call for the records and pass appropriate orders in any consumer dispute which is pending before or has been decided by any District Forum within the State, where it appears to the State Commission that such District Forum has exercised a jurisdiction not vested in it by law, or has failed to exercise a jurisdiction so vested or has acted in exercise of its jurisdiction illegally or with material irregularity.” 7. On reading of the above, it is obvious that the National Commission under its revisional jurisdiction have very limited powers in exercise of revisional jurisdiction. The National Commission can interfere with the orders of the Fora below if they have exceeded their jurisdiction under law or failed to exercise their jurisdiction or have acted in exercise of its jurisdiction with illegality or material irregularity. In the instant case on perusal of the record, we find that both the Fora below have returned their concurrent finding of fact. On perusal of the impugned order, we find that the State Commission has based its finding on analysis of the evidence produced. Counsel for the petitioner has failed to point out any material evidence ignored by the State Commission. Therefore, it cannot be said that the State Commission while passing the impugned order has committed any material irregularity, illegality or jurisdictional error which may call for interference by this Commission, in exercise of its revisional jurisdiction under section 21(b) of the Act. We, therefore dismiss the revision petition in limine with no order as to costs. ……………Sd/-……..……….. (AJIT BHARIHOKE, J.) PRESIDING MEMBER ……………Sd/-….…………… (SURESH CHANDRA) MEMBER SS/ NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO.1137 OF 2011 (From the order dated 19.05.2010 in First Appeal No.156/2010 of the Delhi State Consumer Disputes Redressal Commission) Mr. Ved Prakash Juneja GD-176, Pitam Pura Delhi-34 ..…. PETITIONER Versus 1. Director, CGHS Nirman Bhawan New Delhi 2. Additional Director, CGHS New Rajender Nagar Shankar Road New Delhi .... RESPONDENTS BEFORE: HON’BLE MR.SURESH CHANDRA, PRESIDING MEMBER For the Petitioner For the Respondents : : In person Mr. Rajat Gaur, Advocate PRONOUNCED ON: 16th July, 2013 ORDER PER SURESH CHANDRA, MEMBER There is a delay of 180 days in filing this revision petition for which the petitioner has filed an application for condonation. We have considered the submissions made by the petitioner and for the reasons given in the application, we condone the delay in filing this revision petition. 2. This revision petition has been filed by Sh. Ved Prakash Juneja who is the original complainant in this case against the respondents – Director, CGHS and Additional Director CGHS who were the opposite parties No.1 & 2 respectively before the District Forum. 3. The factual matrix of this case are that the petitioner who retired on superannuation from Government’s service under the Delhi Police on 30.6.1988 was drawing Rs.2000/- p.m. as basic pay and Rs.40/- per month as special pay. Based on his pay, he was entitled for nursing home facilities in accordance with the circular of Ministry of Health No.S-50/1974-CGHS(P) dated 30.10.1974. On his superannuation, his pension was fixed at Rs.988/- per month w.e.f. 1.7.1988 but he was denied CGHS ICard with nursing home facility. Besides this, he had also submitted a claim for reimbursement of medical expenses amounting to Rs.12,832/- incurred by him for treatment. This claim, however, was rejected by the OPs on the ground that the claim was regarding purchase of medicines as an OPD patient and hence it was not admissible because the medicines are to be procured by the concerned patient from the CGHS dispensary where the beneficiary is registered. Aggrieved by the decision of the respondents/opposite parties, he filed a consumer complaint bearing No.339/2008 before the District Forum (Central), Kashmere Gate, Delhi with two-fold grievance, namely, denial of CGHS I-Card with nursing home facilities and non-reimbursement of his medical claim bills amounting to Rs.12,832/. It was pleaded by him before the District Forum that since he retired w.e.f. 1.7.1988 and was drawing pension of more than Rs.750/- per month (his actual pension being fixed at Rs.988/- per month), he was entitled to nursing home facilities under Ministry of Health order dated 30.10.1974 (supra). Regarding the reimbursement of his claim on account of purchase of medicines etc, it was his submission that CGHS dispensary normally kept medicines for general use and procurement of a number of medicines prescribed by the specialist would take 4-8 days which would also require several visits to the dispensary. Since his treatment was in respect of injuries sustained by him in an accident, he had purchased the medicines from the market and hence there was no reason that his claim should have been disallowed. The OP department resisted the complaint. In respect of his claim for nursing home facilities, it was submitted that the order dated 30.10.1974 (supra) was superseded by a later government order No.S-11011/9/86-CGHS (P) dtd. 1.2.1989 and as per the new government order after the implementation of 4th Pay Commission recommendations, the pensioners who were drawing less than basic pay of Rs.2501/- could not get nursing home facility. This had been duly communicated to the complainant / petitioner vide letter dated 12.3.2011 issued by the OPs. The claim in respect of the reimbursement of medical bill, as stated above, was rejected because the OPD patients could not be reimbursed for purchase of the medicines. 4. On appraisal of the evidence adduced by the parties before it, the District Forum vide its order dated 14.7.2009 partially allowed the complaint in terms of the following directions:“A) To pay the sum of Rs.12,832/- with interest @ 9% per annum. The interest shall be payable from the date of filing of the complaint i.e. 23.5.2008 till the realization of the amount. It is so because in the complaint, the date of purchase of the medicines or submitting the bills for reimbursement has not been mentioned. B) Compensation for harassment and agony, amounting to Rs.3,000/- and litigation charges amounting to Rs.2,000/- shall also be paid to the complainant.” 5. Not satisfied with the aforesaid order of the District Forum, the petitioner filed an appeal bearing No.10/156 before the Delhi State Consumer Disputes Redressal Commission against this order praying for direction to the OPs to provide the petitioner with a CGHS I-Card allowing nursing home facility since this request was turned down by the District Forum. The OPs did not challenge the order of the District Forum. The State Commission vide its order dated 19.5.2010 held that the petitioner as a pensioner could not be regarded as a consumer within the meaning of section 2(1)(d) of the Consumer Protection Act, 1986 and as such dismissed his appeal in limine by observing that the facility provided to a Government servant cannot be provided to a pensioner even on contribution since he cannot be held to be a consumer within the meaning of section 2(1)(d) of the C.P. Act. However, keeping in view the fact that the OPs did not challenge the order of the District Forum, the State Commission did not disturb the partial relief already granted by the District Forum. It is against this order of the State Commission that the present revision petition has been filed by the petitioner. 6. We have heard the petitioner who has pleaded his case himself and learned counsel Mr. Rajat Guar, Advocate for the respondents. Learned counsel pointed out that since the respondents have already paid the medical bill in accordance with the order of the District Forum, the grievance of the petitioner in regard to payment of his bills has been satisfied. The petitioner submitted that in view of the impugned order, the revision petition now is for direction to treat the petitioner as a consumer within the meaning of the provisions of the C.P. Act and for issuance of a CGHS I-Card with nursing home facilities. In respect of the first prayer, petitioner submitted the State Commission gravely erred in ignoring the settled law which recognises a pensioner and beneficiary of the CGHS as a consumer under the provisions of the C.P. Act, 1986. In this context, he drew our attention to the order dated 20.10.2005 in the case of Jagdish Kumar Bajpai Vs. Union of India which has been delivered by 6-Member Bench of this Commission holding that a pensioner and beneficiary of the CGHS would be a consumer under the provisions of the C.P. Act, 1986 for the alleged deficiency in service by the CGHS officials. A copy of this order has been placed by the petitioner on the paper-book. This 6-Member Bench order is in line with the law settled by the Apex Court. 7. Referring to the view taken by the Apex Court in V.P. Shantha’s case [(1995) 6 SCC 651], this Commission has observed as under:“This aspect is considered in para 49 of the V.P.Shantha’s case (Supra). The Court dealing with a similar situation illustrates that where a person has taken an insurance policy for medicare whereunder all charges, consultation, diagnosis and medical treatment are borne by the Insurance Company. In such a case the person receiving treatment is a beneficiary of services and the payment for such services would be made by the Insurance Company to the medical practitioner. The rendering of such service by the medical practitioner cannot be said to be free charge. Similarly, where as part of conditions of service the employer bears the expense of medical treatment of the employee and his family members dependant upon him, the service rendered to him by the medical practitioner would not be free of charge and would, therefore, constitute service under Section 2(1)(o). The same analogy would apply in case of retired employee. As stated above, past service would be consideration for providing such medical facility or other facilities.” 8. In view of above position, we are convinced that the State Commission gravely erred in holding that the petitioner is not a consumer. Its impugned order in this regard, therefore, cannot be sustained in the eye of law and must be set aside. 9. So far as the second issue in this revision petition regarding issuance of a CGHS I-Card with nursing home facility to the petitioner is concerned, the petitioner has submitted that he retiredw.e.f. 1.7.1988 and as on that the Government order dated 30.10.1974 (supra) was applicable which entitled him to nursing home facilities in terms of para 1(c) since his pay as well as pension both were more than Rs.750/- per month. His contention was that the Government order dated 1.2.1989 (supra) which has been heavily relied by the respondents to reject his representations and denying him the issuance of CGHS I-Card with nursing home facility has become effective from the date of its issue, i.e., 1.2.1989. He submitted that keeping in view his date of retirement which was prior to this Government order and his eligibility to the nursing home facilities as on that date under the then existing instructions vide OM dated 30.10.1974, denial of the nursing home facility was absolutely wrong on the part of the respondent authorities. To support his understanding in this regard, the petitioner referred to the clarificatory OM No.S-11011/9/86-CGHS(P) dated 11.10.1989 issued by the Ministry of Health which lays down that “contribution can be made by the pensioner and pensioner family on the basis of the last pay drawn and they are entitled to avail the treatment at the same level as on the date of retirement / date of death of the employee.” The petitioner submitted that this clarificatory OM which was issued after issuance of the OM dated 1.2.1989 clearly supports his plea that the government cannot deny him the facility which was already available to him on the date of his retirement and much before the issuance of the OM dated 1.2.1989 which obviously came into effect only from 1.2.1989 and not before. The petitioner has also referred to the two instant cases of S/Shri P.R. Sethi, retired Inspector of Delhi Police to whom CGHS I-Card No.407942 was issued on 11.8.1988 and B.D. Relan who retired as SubPostmaster on 1.10.1988 and whose pension was fixed at Rs.985/- per month and yet he was issued CGHS Card No.416692 on 12.10.1988 with nursing home facility. He submitted that besides the specific instructions of the government in the government orders referred to by him, he had been pleading time and again with the respondent authorities to give him the same treatment as was given to the other retired offers in similar circumstances but the respondents persistently rejected his representations and when he asked for information under the RTI Act which would disclose the basis and authority of the government for such rejection, the information was not furnished to him on the ground that the same being part of their old record, it was not available. He, therefore, submitted that the District Forum order which is based on the wrong interpretation of the applicability of OM dated 1.2.1989 and which ignores the later clarifications issued on 11.10.1989, is liable to be set aside. He clarified that so far as the contribution for availing the CGHS facility for his entitlement is concerned, he has never refused to contribute as per the instructions in force and in fact, he placed on record (page 45 of the paper-book) copy of a document which indicates that a higher contribution of Rs.15 was taken from him by the department. 10. Per contra, learned counsel for the respondents submitted that even though the petitioner was eligible for nursing home facility I-Card as on the date of his retirement, admittedly he did not get the pensioner’s card issued soon after his retirement and applied for the card only on 13.9.1989 by which time the revised instructions as per OM dated 1.2.1989 had been issued. He further submitted that even though the petitioner has sent representations to the respondent authorities from time to time, he had been given suitable reply indicating that after the implementation of the 4 th Pay Commission’s recommendations, the pensioners who were drawing a basic pay of Rs.2501/- and above are alone entitled for nursing home facilities. He, therefore, submitted that the order of the District Forum which turned down the plea of the petitioner regarding his eligibility to the nursing home facility is in accordance with the revised instructions of the Ministry of Health and the same deserves to be upheld and confirmed. He further submitted that the respondents have already sent a cheque dated 26.11.2009 for Rs.19,372/- in compliance of the District Forum order in respect of the other prayer of the petitioner/complainant. Hence the revision petition should be dismissed. 11. We have given our anxious thoughts to the rival contentions and have also perused the record. There is no dispute that the petitioner was eligible for nursing home facility in terms of the instructions of the government contained in OM dated 30.10.1974, a copy of which is placed at pages 23-24 of the paper-book. It is also not in dispute that the instructions of this OM which came into effect on 1.11.1974 were in force till 31.1.1989 when they came to be superseded/revised by another OM issued on 1.2.1989 which admittedly became effective only from the date of its issue, i.e., 1.2.1989. It appears that the whole confusion arose because of the fact that the petitioner did not get the CGHS I-Card issued as a pensioner immediately after the retirement and by the time he applied for it on 13.9.1989, the situation, as interpreted by the respondents, had changed because of the OM of 1.2.1989. A plea was also taken by the learned counsel for the respondents that the petitioner himself had chosen to contribute differently to the CGHS kitty which rendered him ineligible to avail all the benefits of the earlier OM at a belated stage after issuance of OM of 1.2.1989. We are not impressed by the plea taken by the counsel for the respondents. If we go by his submission in this regard, it would be contradictory to the instructions issued by the government vide OM dated 11.10.1989 (supra) which clarifies that contribution can be made by a pensioner and pensioner family on the basis of last pay drawn and they are entitled to avail the treatment at the same level as on the date of retirement/date of death of the employee. Learned counsel has not been able to convince us as to how this clarification which clearly entitles the pensioner to avail the treatment at the same level as on the date of retirement can be ignored because this has been issued consciously by the government keeping in view the contents of both the earlier orders dated 30.10.1974 and 1.2.1989. We are, therefore, of considered view that learned District Forum erred in wrongly interpreting the instructions contained in OM dated 11.10.1989 by holding that the petitioner lost his eligibility to the nursing home facilities by opting for medical facilities on the basis of last pay drawn pension and not on the basis of last pay drawn. In spite of opportunities given, nothing has been produced before us by the respondents which would establish that the petitioner had either given such an option consciously at the time of the retirement or even if assuming that he had given such option, the petitioner would stand to lose the eligibility to nursing home facilities in terms of the later clarification issued on 11.10.1989 which restores the same facility to every pensioner / family pensioner if he/she was prepared to contribute according to his/her last pay/pension. In this context, we reproduce below the extracts from the later OM dated 11.10.1989 which contains the aforesaid clarification:“All Central Government pensioners including CPF retirees (except those of Railway and Armed Forces) are eligible for availing CGHS facilities if they were eligible to avail the same while in service irrespective of whether they actually availed of such facilities or not prior to their retirement”. 12. Learned counsel for the respondents has not filed any instructions of the government contrary to the clarification contained in the OM of 11.10.1989 which clearly makes the petitioner eligible for the nursing home facility on payment of the required contribution as per rules. In this context, we may also note that on superannuation, every pensioner can either contribute on a monthly basis to the CGHS or make a payment of 10 times of the annual contribution as may be applicable in his case. If we go by the contribution of Rs.4 per month as on the date of retirement, the petitioner would be entitled for availing the treatment of his level as on the date of his retirement by making a lump sum payment of Rs.480/- which is equivalent of 10 years contribution in lump-sum. Unfortunately, what learned counsel for the respondents has filed before us on 18.7.2012 is copy of OM in respect of reimbursement of medical expenses when pensioners take the treatment immediately after retirement but before getting CGHS card and condonation of delay for reimbursement of such expenses. The claim regarding reimbursement of medical bill preferred by the petitioner having already been settled by the respondents in accordance with the District Forum order, the OM dated 5.11.1993 filed by the counsel for the respondents has no relevance to the issue which remains to be decided by us. We may also note that in spite of repeated representations the respondents have miserably failed to give any explanation regarding issuing different CGHS I-Cards in two other cases of retired employees referred to by the petitioner. 13. In view of the above discussion, we hold that the petitioner is eligible to issuance of CGHS pensioner’s I-Card with nursing home facility in terms of instructions contained in para 1 (c) of the Department of Health OM dated 30.10.1974 (supra) read with clarificatory instructions contained in the later Om dated 11.10.1989 (supra). We, therefore, direct respondent No.1 Director, CGHS, Ministry of Health and Family Welfare, Govt. of India to issue Pensioner’s I-Card with nursing home facilities to the petitioner within a period of 6 weeks from the date of receipt of this order subject to the petitioner making payment of lump sum amount of contribution to the CGHS for issuance of such a card in accordance with the instructions of the government based on the contribution applicable to the petitioner under the OMs dated 30.10.1974 read with clarificatory OM dated 11.10.1989. 14. Impugned order of 19.5.2010 passed by the State Commission is accordingly set aside and the revision petition stands allowed in terms of the aforesaid directions with the parties bearing their own costs. ……………Sd/-….…………… (SURESH CHANDRA) PRESIDING MEMBER SS/ NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 1240 OF 2008 (From the order dated 10.12.2007 in First Appeal No. 247/A/2007 of West Bengal State Consumer Disputes Redressal Commission) Amarendra Kumar Roy Thikana Apartments 38, Girish Ghosh Sarani Hakimpara P.O. and PS Siliguri District – Darjeeling ... Petitioner Versus 1. Branch Manager Life Insurance Corporation of India Siliguri Branch – II, Station Feeder Road, Silliguri 2. Administrative Officer Life Insurance Corporation of India J.P. Building, J.S. Department 16, C R Avenue Kolkata – 700072 3. Branch Manager Life Insurance Corporation of India Balurghat Branch, Chakbhabani P.O. Balurghat – 733101 Through its Branch Manager …. Respondent(s) BEFORE HON’BLE MR. JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER HON’BLE DR. B.C. GUPTA, MEMBER APPEARED AT THE TIME OF ARGUMENTS For the Petitioner(s) Mr. Niranjan Saha, Advocate For the Respondent(s) Mr. Mohan Babu Aggarwal, Advocate PRONOUNCED ON : 16th JULY 2013 ORDER PER DR. B.C. GUPTA, MEMBER This revision petition has been filed under section 21(b) of the Consumer Protection Act, 1986 against the impugned order dated 10.12.2007 passed by the West Bengal State Consumer Disputes Redressal Commission (for short ‘the State Commission’) in FA No.247/A/2007, “Branch Manager, LIC versus Amarendra Kumar Roy”, vide which, while allowing appeal, the order passed by the District Forum dated 25.5.2007 in consumer complaint case number 9/S/2007 was set aside and the complaint was ordered to be dismissed. 2. Brief facts of the case are that the complainant/petitioner Amarendra Kumary Roy obtained one Life Insurance Corporation of India (LIC) policy named “Jeevan Suraksha (Endowment Funding)” bearing no. 452384400 from Balurghat Branch of the LIC on 13.07.2001. This was a policy for five years with yearly instalment of Rs.55,299/- and the date of last payment was 13.07.2006. LIC issued the policy showing monthly pension at Rs.3,366/- and from 13.08.2006 and the capital sum with guaranteed addition was Rs.3,43,750/-. The complainant gave his option under option ‘F’ for life pension under which the pension fund was to be returned to the nominee/legal heirs on the death of the annuitant. After completion of five years, LIC sent 13 cheques to the complainant, out of which one cheque was for Rs.1,787/- for the period 13.08.2006 to 31.08.2006 and 12 cheques were for Rs.2,916/- for the period September 2006 to August 2007. The complainant took the plea that he was entitled to get pension of Rs.3,366/- per month as stated on the policy. The case of the LIC, however, is that a sum of Rs.3,366/- per month is payable under option ‘D’ and not under option ‘F’. Moreover, under option ‘D’, the capital sum amounting to Rs.3,43,750/- is not payable to the nominee / legal heirs after the death of the annuitant. This sum is payable under option ‘F’ only and consequently the payment being made per month was less than that allowed under option ‘D’. The complainant approached the District Forum, which allowed his complaint and ordered that he was entitled to get pension @Rs.3,366/- per month and also the capital sum of Rs.3,43,750/- for his nominee / legal heirs after his death. The District Forum ordered the LIC to make payment for the shortfall in the cheques already issued. An appeal was filed by the LIC against this order which was allowed, holding that there was printing error on the policy by which an amount of Rs.3,366/- had been written. In fact, this amount is allowed under option ‘D’, whereas the complainant had exercised option ‘F’ for getting the pension. It is against this order that the complainant has filed the present revision petition. 3. While arguing the case, the learned counsel for the petitioner vehemently argued that under the “Jeevan Suraksha (Endowment)” type plan and the tables released by the LIC, the petitioner was entitled to get a sum of Rs.3,366/- per month as pension and this sum has been mentioned on the body of the policy as well. The LIC had, therefore, made grave injustice with the petitioner by allowing pension @Rs.2,916/- per month. He admitted that while exercising option, he had opted for type ‘F’ for getting pension and this factor was mentioned on the ‘cover note’ as well. 4. Learned counsel for the LIC, however, stated the amount, Rs.3,366/- had been wrongly written on the policy. In fact, this was the amount under option ‘D’ and not under option ‘F’. They could not give him pension under option ‘D’ and also allow him the benefit of capital sum after the death. 5. We have examined the entire material on record and given a thoughtful consideration to the arguments advanced before us. 6. The factum of obtaining the Jeevan Suraksha policy by the complainant and the amount of premium and capital sum with guaranteed addition at Rs.3,43,750/- are admitted by both the parties. It is also an admitted fact that the complainant had given option for getting life pension under option ‘F’ with return of pension fund to the nominee / legal heirs on the death of the annuitant. However, simply because of the fact that the LIC committed a mistake by printing Rs.3,366/- as amount payable per month on the policy, does not entitle the complainant to get the best under both the options ‘D’ & ‘F’. The complainant can only be eligible to get the benefit under option ‘D’ or option ‘F’ and the LIC is agreeable to allow him to choose any of the two options. It is quite obvious that the amount payable under option ‘D’, i.e., Rs.3,366/- is higher than the amount payable under option ‘F’, i.e., Rs.2,916/- because the persons opting to get pension under option ‘D’ are not eligible to get the payment of the capital sum with guaranteed addition whereas the same is payable to their nominees / legal heirs under option ‘F’. 7. We, therefore, hold that the petitioner cannot be given pension under option ‘D’ and the benefit of return of capital sum under option ‘F’. He has to choose between one of the two options. We, therefore, do not find any infirmity, illegality or irregularity in the order passed by the State Commission and the same is upheld. The revision petition is ordered to be dismissed with no order as to costs. ..…………………………… (K.S. CHAUDHARI J.) PRESIDING MEMBER ..…………………………… (DR. B.C. GUPTA) MEMBER RS/ NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 4020 OF 2012 (Against order dated 11.04.2012 in First Appeal No. 2674/2007 of the M.P. State Consumer Disputes Redressal Commission, Bhopal) Shri Shyam Lal Ladia S/O Khuman Singh Ladia, R/O Near Shyam Diary, Beejasen Ward, Gadarwara, Tehsil, Gadarwara, District Narsinghpur (M.P.) …Petitioner Versus 1. Dr. O.P. Nayak Ophthalmologists Near Aamgaon Naka, Gadarwara District Narsinghpur (M.P.) 2. Dr. S.P. Kurchania Savitri Nursing Home, Gadarwara, Tehsil, Gadarwara, District Narsinghpur (M.P.) …Respondents BEFORE: HON’BLE MR.JUSTICE J.M.MALIK, PRESIDING MEMBER HON’BLE DR.S.M.KANTIKAR, MEMBER For the Petitioner : Md.Izhar Alam, Advocate with Shyam Lal, In-person PRONOUNCED ON 17th JULY, 2013 ORDER PER DR. S.M. KANTIKAR 1. This Revision Petition filed under Section 21 (b) of the Consumer Protection Act, 1986 directed against the Impugned Judgment and order dated 11.04.2012 passed by the State Consumer Disputes Commission, Bhopal (in short ‘ State Commission’) in F.A. No. 2674 of 2007 whereby the State Commission had dismissed the F.A. aforesaid preferred by the Petitioner against the Judgment and order dated 20.09.2007 passed by the District Consumer Disputes Redressal Forum Narsinghpur, M.P. (in short ‘District Forum’) in C.C. No. 42 of 2005 whereby the District Forum allowed the entire claim of the Respondents of Rs.2,00,000/-. 2. Brief Facts: For cataract of Right eye of the Complainant was advised by the OP No 1, Dr. O.P. Nayak for an operation. He got admitted in the Government Eye Camp at Gadarwara, but the doctor told him that he would treat him personally at OP No 2- Savitri Nursing Home. He was admitted at Savitri Nursing Home and operated there by OP 1. He was admitted for 5 days. He could not see properly after the surgery, so he consulted Dr. O.P. Nayak who again treated by giving an injection. As his sight still did not improve, OP 1 referred him to Dr. Gurdeep Singh at Hamidia Hospital, Bhopal. Dr. Gurdeep Singh demanded Rs.5,000/- towards the operation. As he could not afford it, he went back to OP 1 who also demanded Rs.20,000/-. The Complainant then consulted Dr. R.K. Mishra at Jabalpur who told him that his vision would not come back. His Right eye was ultimately removed. Alleging negligence in the cataract operation and infection in the eye due to poor quality of lens, he has sought a relief of Rs.5, 50,000/-. 3. The OP No.-1, Dr. O.P. Nayak, stated that he is an experienced and qualified ophthalmologist who examined complainant at the eye camp on 07.10.1996. He had cataract in both his eyes. As the cataract in his right eye had matured, he was advised surgery, but he did not get admitted in the camp. He came again later and was told that 7 lens had been donated by the Lions Club. Two were still left and one of them would be implanted in his eye free of cost. As Savitri Nursing Home had equipments like operating microscope etc., which were not available in the Civil Hospital at Gadarwara, the lens was implanted at Savitri Nursing Home. The surgery was successful and the Complainant was advised to stay away from the sun and avoid smoking. Since he was a mason, he was also advised to avoid dust. However, he did not heed the instructions and started working which caused infection in the eye. He was given medication and watched for 2 days. When his condition did not improve he was referred to Dr. Gurdeep Singh at Hamidia Hospital, Bhopal. He was admitted at Hamidia Hospital at Bhopal but got discharged against medical advice. The Complainant consulted him again on 27.11.1996, and he prescribed some medicines. He also referred him to Dr. R.K. Mishra at Jabalpur. 4. Opposite Party No.2, Dr. S.P. Khurchania of Savitri Nursing Home states that in 1996, Lion’s club organized an eye camp and donated 7 lenses. One of these lenses was used in the cataract surgery of the Complainant. No charges were taken for the lens. The Complainant was admitted for 5 days and had no complaints till his discharge. 5. The District Forum allowed the complaint on three grounds (i) the tests required prior to cataract surgery was done one month back. (ii) It was a case of Res ipsa loquitor as the OPs admitted that the Complainant was suffering from endopthalmitis and (iii) referral letters did not mention the type of endopthalmitis. 6. Against the order of District Forum, two cross appeals were filed in State Commission as Appeal No.2325/07 by OPs and Appeal No 2674/07 by the Complainant. 7. The State Commission heard both the counsels and perused documents filed on record. The State Commissions allowed Appeal No.2325/07 filed by OPs and dismissed Appeal No 2674/07 filed by the Complainant. 8. Aggrieved by the order of state commission the complainant preferred this revision petition. 9. The advocate for petitioner and complainant were present. The application for condonation of delay heard, the justification was satisfactory and accordingly delay is condoned. 10. Complainant’s main grievance was negligence in the operation and implantation of poor quality of lens which led to infection resulting in removal of his right eye. The State Commissions order clearly pointed out that the affidavit filed by Dr. Akhilesh Gumastra of Lions Club mentioned that the lenses were from Aurolab, Madurai, one of the best qualities. Those seven lenses were donated in the memory of his mother. The six other patients who have received the lenses did not show any infection. Therefore, infection was not due to quality of the lens. The Complainant has not filed any evidence to prove that the lens were of low quality. 11. Even the pre-operative laboratory tests and medical check- up which were conducted one month prior to the surgery were normal. Hence, there was no necessity to repeat the test again unless the patient had any signs or symptoms which is not negligence. 12. There were no hospital case papers or treatment records for the period the Complainant was in Savitri Nursing Home. There was no discharge card. The Opposite Party has handed over all medical records to the Complainant. The post-operative prescription dated 17.11.1996 clearly mentions that the Complainant had vision of 6/24. OP referred the complaint to Dr. Gurdeep Singh at Hamidia Hospital, Bhopal and Dr. R.K. Mishra, Emeratus Professor in Medical College, at Jabalpur for management of infection like endopthalmites; but it could not be controlled and ultimately the Right eye was removed. Therefore, referring a patient to higher centre is not a negligent act. 13. We have gone through several medical texts, literature and reported articles in the journals which revealed that the endophthalmitis is a known complication of cataract surgery. As per medical literature on various EVS studies the Postoperative endophthalmitis is defined as severe inflammation involving both the anterior and posterior segments of the eye after intraocular surgery. Typically, postoperative endophthalmitis is caused by the perioperative introduction of microbial organisms into the eye either from endogenous source like the patient's normal conjunctiva and skin flora or from contaminated instruments. Once organisms gain access to the vitreous cavity, overwhelming inflammation is likely to occur, making rapid recognition, diagnosis, and treatment critical in optimizing final outcomes. Although most cases of postoperative endophthalmitis occur within 6 weeks of surgery, infections seen in high-risk patients or infections caused by slow-growing organisms may occur months or years after the procedure. The other referred journal articles are: i) Review Article-ISRN Orthalmology Volume 2011 titled as “PostOperative Endophthalmitis following cataract Surgery in Asia” by authors Jin A Choi and Sung Kun Chung. ii) “Post-Operative Endophthalmitis” Author: William Lloyd Clark, MD; Chief Editor: Hampton Roy, Sr. MD. fromhttp://emedicine.medscape.com/article/1210260-clinical#a0218 14. In this case the OP was a qualified and experienced ophthalmic surgeon. Also there was no iota of evidence that other six patients have any signs of endophthalmitis who were undergone cataract surgery and lens implantation. Hence, there was no evidence of cluster of infection. 15. Intra-ocular infection has always brought disrepute to the ophthalmologist and this problem is not only rampant at eye-camps but also in hospitals, which include the five star ones. Only surgeon who does not have endophthalmitis is the one who does not operate. The problem is general and it is not the surgeon who is to be blamed although he is responsible for surgery. Despite the best possible care, mishaps cannot always be avoided. 16. In view of aforesaid findings and discussions we are of considered view that OPs acted as per standards of practice and there was no negligence or deficiency in service. 17. Therefore, the revision petition is dismissed. No order as to costs. …..………………………… (J. M. MALIK, J.) PRESIDING MEMBER .…..………………………… (S. M. KANTIKAR) MEMBER MSS/21 NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 2108 OF 2013 With IA/3467/2013, IA/3468/2013 and IA/3675/2013 (Stay, Exemption from filing the certified copy, Modification of Order) (From the order dated 21.05.2013 in Appeal No. 838/2012 of the State Consumer Disputes Redressal Commission, Delhi) Castrol India Ltd. Through its: General Manager-Legal & Secretary 5th Floor, NBCC Place East Tower, Pragati Vihar Bhisham Pitamah Marg, New Delhi -110003 …Petitioner/Opp. Party (OP) Versus 1. Neerja D/o Prof. Ram Prakash R/o 212, Sukhdev Vihar New Delhi – 110025 2. MCS Ltd. Office No.21/22, Ground Floor Kashi Ram Jamnadas Building 5, PD Mello Road, (Ghadiyal Godi) Masjid Mumbai – 400009 (Maharashtra) Also at: F-65, 1st Floor Okhla Industrial Area Phase 1, New Delhi – 110020 3. IM Morgan Stanley Pvt. Ltd. 141, Makers Chambers III Nariman Point Mumbai 400021. Also at: 114, Himalaya House, 11th Floor 23, Kasturba Gandhi Marg, New Delhi – 110001 …Respondents/Complainants BEFORE HON’BLE MR. JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER HON’BLE DR. B.C. GUPTA, MEMBER For the Petitioner : Mr. Sukumar Pattjoshi, Sr. Advocate and Ms. Divya Jain, Mr. S.K. Dubey and Mr. Vikas Nautiyal Advocates with him. For the Respondent-1 : Mr. Ram Parkash, Auth. Rep. For the Respondent-2 : Ms. Vandana Sharma, Advocate For the Respondent-3 : Mr. Kishore M. Gajaria, Advocate PRONOUNCED ON 18th July, 2013 ORDER PER JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER This revision petition has been filed by the petitioner/opposite party against the order dated 21.5.2013 passed by the Delhi State Consumer Disputes RedressalCommission, (in short, ‘the State Commission’) in Appeal No. 838/2012 – Castrol India Ltd. Vs. Ms. Neerja & Ors. by which, the stay order passed in favour of the petitioner was not extended. 2. Brief facts of the case are that complainant/respondent no.1 filed complaint before District Forum and alleged that complainant was holding 3476 equity shares of OP-1/Petitioner. As per offer letter for purchase of shares by OP-1, complainant submitted the form of acceptance duly filled along with duly signed transfer form and share certificates, but complainant’s offer was rejected. Alleging deficiency on the part of OPs, complainant filed complaint before District Forum for grant of difference of share price @ 150/- per share on 1745 equity shares. OPs resisted complaint. Learned District Forum after hearing both the parties, allowed complaint and directed OPs to pay a sum of Rs.3,80,218/- along with 12% p.a. interest and Rs.50,000/- as compensation and Rs.10,000/- as litigation charges. Petitioner filed appeal along with stay application before learned State Commission and learned State Commission after hearing petitioner on stay application, vide order dated 10.10.2012, stayed operation of order of District Forum dated 24.5.2012 till next date and case was adjourned to 21.1.2013. On 21.1.2013, none appeared for the petitioner, but respondent-1 appeared in person and State Commission directed petitioner to furnish correct latest address of Respondent-2 within 7 days and thereafter to issue notice to Respondent-2. Service on Respondent-3 was presumed and matter was adjourned to 22.7.2013. It appears that learned District Forum in the light of orders dated 10.10.2012 and 21.1.2013 passed by the learned State Commission, stayed execution proceedings and adjourned execution proceedings to 29.7.2013. It appears that in the meantime, warrant of attachment was issued for recovery and in such circumstances, petitioner moved an application before learned State Commission and learned State Commission passed following impugned order: “A prayer is made by the Counsel for the appellant to extend stay order dated 10.10.2012, but we do not find any force in the prayer of the Counsel for the appellant in as much as the direction of the State Commission as per order dated 21.3.2013 (21.01.2013) has not been followed by which the appellant was directed to file correct address of the respondent no.2. Prayer rejected. Now the correct address of respondent no. 2 has been filed. Issue notice on the fresh address furnished by the appellant, under the registered cover with AD, for the date already fixed in this case for filing reply and for further orders” against which, this revision petition has been filed. 3. Heard learned Counsel for the petitioner, Auth. Rep. of Respondent No.1 and the Counsel for the Respondents No.2 & 3. 4. Learned Counsel for the petitioner submitted that even after furnishing correct and latest address of Respondent-2; though, not in time, learned State Commission has committed error in not extending stay order dated 10.10.2012; though, it was impliedly extended upto 22.7.2013 by order dated 21.1.2013; hence, revision petition be allowed and impugned order be set aside and stay order may be extended upto 22.7.2013, the date already fixed for hearing the matter before the State Commission. On the other hand, learned Authorized Representative of Respondent no. 1 submitted that revision petition be dismissed, as it is not maintainable as well as time barred and Courts should not grant ex-parte interim stay. Learned Counsel for the Respondents no. 2&3 submitted that they have no objection in allowing revision petition. 5. Perusal of record reveals that petitioner filed appeal before learned State Commission along with stay application and learned State Commission vide order dated 10.10.2012 stayed operation of order of District Forum till next date i.e. 21.1.2013. On 21.1.2013, as notice issued to Respondent-2 was received back unserved, learned State Commission directed petitioner to furnish correct and latest address within 7 days and thereafter to issue notice to Respondent-2. On that date, Respondent-1 filed reply against the stay order. Matter was adjourned to 22.7.2013. It is true that order of 10.10.2012 was not extended by learned State Commission expressly, but at the same time, stay was not vacated and it appears that inadvertently, the extension of stay order was not recorded in order sheet dated 21.1.2013, but it can be inferred that impliedly stay order was extended upto 22.7.2013 and it was withdrawn on 21.5.2013. Order sheet dated 22.4.2013 in execution application filed before District Forum runs as under: “JD has filed an application along with the copy of the orders dated 10.10.2012 and 21.01.2013 and which disclosed the operation of the order under execution was stayed by Hon’ble State Commission and next date of hearing is fixed as 22.07.2013. Therefore, the proceeding of this execution application stands stayed. Now, for awaiting of the further order therefrom, it is adjourned to 29.07.2013”. 6. According to this order sheet, which was drawn in presence of both the parties, it was inferred by District Forum that stay order has been extended upto22.7.2013 and proceedings of the execution application was stayed and matter was adjourned to 29.7.2013. It appears that on the request of complainant/Respondent-1, warrant of attachment was issued. On the application of petitioner for extension of stay order, stay was not extended on account of non-filing of correct address of Respondent-2 within 7 days; though, that had been filed before State Commission, before the date of impugned order. Only on account of non-filing of fresh address of Respondent-2 within time, it was not appropriate on the part of learned State Commission to not extend stay order, which was granted on 10.10.2012 and impliedly extend on 21.1.2013. 7. Authorized Representative of Respondent-1 submitted that revision petition is not maintainable against interlocutory order. This submission is devoid of force. In the light of Section 21 (b) of the Consumer Protection Act, 1986, National Commission can pass appropriate orders in any consumer dispute, which is pending before or has been decided by any State Commission, which makes it clear that revision petition is maintainable before this Commission against any order passed by the State Commission in the matter pending before that. 8. Authorized representative of Respondent-1 further submitted that revision petition is barred by limitation. This argument is also devoid of force, as this revision petition has been filed on 23.5.2013 against the impugned order dated 21.5.2013 meaning thereby, within two days from the date of passing order. This revision petition is not against the order dated 21.1.2013; hence, revision petition is well within limitation. 9. Authorized Representative of Respondent-1 further submitted that in the light of judgment of Hon’ble Apex Court reported in 2011 (6) SCALE - RamrameshwariDevi & Ors. Vs. Nirmala Devi & Ors., Courts should be cautious while granting ex-parte ad interim injunctions or stay orders. We agree with the proposition of law laid down by the Hon’ble Apex Court in the aforesaid judgment, but this aspect is to be considered by learned State Commission, who has granted stay on 10.10.2012 and we are not to comment on grant of stay at this stage. 10. In the light of aforesaid discussion, impugned order passed by learned State Commission is liable to be set aside and stay order dated 10.10.2012 is to be extended till 22.7.2013, the date on which, the matter has already been fixed for hearing before State Commission. 11. Consequently, the revision petition filed by the petitioner against the respondent in Appeal No. 838/2012 – Castrol India Ltd. Vs. Ms. Neerja & Ors. is allowed and impugned order dated 21.5.2013 to the extent of non-extension of stay order dated 10.10.2012 is set aside and order dated 10.10.2012 passed by learned State Commission is extended till 22.7.2013, the date on which the matter has already been fixed for hearing. There shall be no order as to costs. ..…………………Sd/-………… ( K.S. CHAUDHARI, J) PRESIDING MEMBER ..………………Sd/-…………… ( DR. B.C. GUPTA ) MEMBER k NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 3560 OF 2012 (Against order dated 01.06.2012 in First Appeal No. 372/2008 of the Haryana State Consumer Disputes Redressal Commission, Panchkula) M/S Ayurvet Ltd. 6th Floor, Sagar Plaza District Centre, Vikas Marg Laxmi Nagar, Delhi110092 Through its Authorized Representative Petitioner Versus Shri Gopal Krishan Gaushala Gurukul, Kurukshetra Haryana Through its Authorized Representative …Respondent BEFORE: HON’BLE MR.JUSTICE J.M.MALIK, PRESIDING MEMBER HON’BLE DR.S.M.KANTIKAR, MEMBER For the Petitioner For the Respondent : Mr. Rajeev Shukla, Advocate with Mr. Rajesh Srivastava, Advocate : Nemo PRONOUNCED ON 19th JULY, 2013 ORDER PER DR. S.M. KANTIKAR 1. The present Revision Petition is filed under Section 21(b) of the Consumer Protection Act, 1986, challenging the order of the State Consumer Disputes Redressal Commission, Haryana, Panchkula (in short, ‘State Commission’) dated 01.06.2012 passed in First Appeal No. 372/2008 titled as “Ayurvet Ltd. Vs. Shri Gupal Krishan Gaushala”’ which dismissed the Appeal by non-interference in the order passed by the Ld. District Consumer Disputes Redressal Commission (in short, ‘District Forum’), Kurukshetra in Complaint No. 357/2006 decided dated 24.12.2007. 2. Brief Facts of this case as: That the Complainant purchased 100 bags of Uttam Super Gold Diary Special feed manufactured by Dabour Ayurvet Pvt Ltd. (OP No 2) and Uttam Super Gold Diary Special, Ayurvet Ltd (OP No. 3) from OP No.1 i.e. P.K. Traders. It is alleged that the Complainant is Gaushala and had 25 numbers of Hostern Fridgian Category cows. It was further alleged that above said feed was given to cows as suggested by representative of Co. by mixing the said feed with Banola Khal. Thereafter, on 03.02.2006, the cows started feeling unwell and some of the cows felt weakness and milk was decreased. One of the cows died due to this reason and the same was buried by the Complainant without any post-mortem taking the death as natural death. It was further alleged that all the cows were treated by the doctors of NDRI, Karnal, HAU, Hissar and the local veterinary surgeon inspite of treatment 11 cows have died from 03.06.2006 to 16/07/2006 and postmortems of all cows were performed by veterinary surgeon, Kurukshetra. On F.I.R. police sent visra to FSL Madhuban, Karnal. The FSL report dated 17.07.2006 stated that organo phosphorous pesticide was detected in Exhibits sent to FSL for testing. In this way feed was found poisonous feed and due to this reason the cows have died and suffered a loss of Rs.1335773/-. Therefore, there was deficiency in service on the part of the Opposite Parties. 3. Notice being issued, Opposite Parties appeared and contested the complaint, raising plea that OP No.2 and 3 are dealing in the manufacturing of best quality feed and the same is supplied in the market after proper checking through OP No.1. There is no complaint whatsoever from any corner except the Complainant. It was submitted that sample of feed has neither been sent in presence of OPs nor necessary measures have been adopted for sending the sample and as such the alleged report of FSL, Madhuban the analysis is not sustainable. It was further submitted that the cows of Complainant might have died due to some other factor. As per blood report dated 26.06.2006 the cows have died due to Theilerisis which was an outcome of stress and existing environment of Gaushala. Thus, there was no deficiency in service on their part. 4. On appraisal of the pleadings of the parties and evidence brought on record, the District Forum allowed the complaint and directed the OPs to pay Rs.2,74,000/cost of ten dead cows, medicines charges of Rs.1,03,273/-, cost of feed Rs.32,500/- and Rs.50,000/- as compensation for harassment . 5. Aggrieved by the order of District Forum respondent filed an appeal No.372/2008. The State Commission heard the parties and dismissed the appeal with observation as “Undisputedly, the Complainant purchased 100 bags of Uttam Super Gold, Diary Special Dabaur Ayurvet Ltd. feed on 24.05.2006 at the rate of Rs.325/- per bag from OP No.1, which was manufactured by OP No.2 and OP No.3. It is also not disputed that on 03.06.2006 the cows started feeling unwell and 11 cows have died from 03.06.2006 to 16.07.2006. It is also disputed that F.I.R. was registered. The Counsel for Respondent has placed on record of FSL report and as per report of FSL an organophosphorous pesticide was detected by the FSL while testing. Since, the FSL report clearly mentioned that cows of the Complainant taking poisonous feed, thus the Appellant/Opposite Party is held liable for compensation.” 6. Against the said dismissal order of State Commission the petitioner preferred this Revision Petition. 7. The Respondent/Complainant, Sh. Gopal Kishen Gaushala, was served in this case. Mr. Ravi Kumar, clerk for Mr. Ajay Pal Nookala Sumanth, Advocate for Respondent appeared in this case on 18.02.2013. Counsel for the Respondent was given time to file Vakalatnama and counter affidavit on 18.02.2013. However, on 15.07.2013, none appeared on behalf of the Respondent. Therefore, final arguments were heard in the absence of the Respondent or his Counsel. It may be mentioned here that the record reveals that the memo of appearance was filed on behalf of Respondent, which was taken on record. Proof of receipt of costs of Rs.10,000/- is placed on record, which was received by the Respondent, as per the postal receipt. 8. We have heard the counsel for petitioner who argued vehemently and have perused the documents on record like Post mortem and FSL Repot. It is noted that the FSL reported “cause of death of cow only”. The FSL report did not comment upon quality and contents of the feed supplied/manufactured by the Petitioner was poisonous and due to which the death of cows was occurred. We do not find any proximity on the death of the cow with the cattle feed. Petitioner further contention that the Complainant/Respondent is not a consumer as it is being a body corporate involved in the commercial activities and earning profits. It is not an individual, who is earning for his livelihood. 9. The document on record i.e. report of cattle feed sample from Director General, Dairy Development, Haryana, Panchkula which was addressed to Dy. Director Animal Husbandry, Kurukshetra mentioned that after analysis of approved lab regarding sample (KKR-17, KKR-18) found as per Bureau of Indian Standard. 10. The veterinary doctor who has conducted the post mortem and issued a report did not specify anything about the feed which was taken by the cows and no toxic level mentioned about the quantity of organophosphorous pesticide. No samples of feed were referred to the FSL laboratory to establish that it contains organ phosphorous poison. Even otherwise the post-mortem done by the veterinary doctor did not say anything about the lethal dose. 11. Therefore, firmly we cannot say that the cows which died only by such feed. The grazing animal can eat many substances and therefore it is not possible to locate the source of poison. There is evidence on record that those cows were suffering from Theilerisis a tick borne disease, which was confirmed by blood smear examination. Therefore, the death of cows attributed to the disease Theilerisis. 12. Therefore, we are of considered view that both the Fora below erred in appreciation of evidence and records on file. Accordingly the orders passed by the Fora below are set aside and we allow this revision petition. No order as to costs. …..………………………… (J. M. MALIK, J.) PRESIDING MEMBER .…..………………………… (Dr. S. M. KANTIKAR) MEMBER MSS/5 NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 267 OF 2012 (From order dated 01.08.2011 in First Appeal No. 1697/2009 of the State Consumer Disputes Redressal Commission, Haryana, Panchkula) WITH IA/2/2012 (FOR CONDONATION OF DELAY) & IA/3/2012 (FOR IMPLEADMENT OF PARTIES) 1. Haryana Urban Development Authority Through its Chief Administrator, Sector-6, Panchkula 2. Estate Officer Haryana Urban Development Authority Panchkula … Petitioners Versus Jitender Nath Sharma S/o Late Janardhan Sharma R/o H.No. 1125, Sector-7, Panchkula … Respondent BEFORE: HON'BLE MR. JUSTICE J.M. MALIK, PRESIDING MEMBER HON’BLE DR. S.M. KANTIKAR, MEMBER For the Petitioners : Ms. Anubha Agrawal, Advocate For the Respondent : Mr. Himanshu Gupta, Advocate For the Applicants : Mr. Mahurendra Kumar, Advocate PRONOUNCED ON_19.07.2013 ORDER JUSTICE J.M. MALIK 1. This case revolves around the question “Whether the oustees, complainant or the other Co-sharers are entitled to a plot under the Oustees Policy?”. The petitioners/Opp.parties acquired the land of Sh.Jitender Nath Sharma, the complainant and 39 other Co-sharers, on 09.10.2003. As per the Oustees Policy, Harayana Urban Development Authority (HUDA) invited applications for allotment of 1 (one) Kanal plot in Sector-6, MDC, Panchkula. Sh. Jitender Nath Sharma, the complainant applied for the same and deposited the earnest money in the sum of Rs.2,10,000/- with the petitioners/opp.parties. HUDA allotted plot No. 18-P in Sector 6, MDC, Panchkula, vide allotment letter, in favour of the complainant along with 69 other co-sharers, whereas, there are only 39 co-sharers in the acquired land. The other oustees did not apply for the allotment of plot. The complainant further deposited 15% of Rs.36,78,500/-, on 31.01.2007. The complainant made an enquiry and the officials of HUDA replied that they cannot allot plot in the sole name of the complainant as per HUDA Policy unless and until No Objection affidavits were furnished by the remaining Co-sharers. Aggrieved by that decision, the complainant filed a complaint before the District Forum. 2. The District Forum allowed the complaint and directed the OPs to issue allotment letter dated 04.01.2007 in the sole name of the complainant in respect of the same plot after deleting the names of other co-sharers or in the alternative, allot any other plot as per his entitlement, according to the Policy of HUDA, in the same Sector or adjoining Sector at the same price and the same conditions. Liberty was granted to HUDA to recover the dues in respect of the plot in question, if any, from the complainant alone. 3. HUDA preferred an appeal before the State Commission. The State Commission dismissed the appeal vide its order dated 01.08.2011. Thereafter, the present revision petition was filed. There is delay of 34 days in filing this revision petition. Counsel for the respondent/complainant argued that the petitioner has failed to establish “sufficient ground” for condonation of delay. He alleged that it has taken lame excuse and the application should be dismissed. 4. We have perused the application for condonation of delay in filing this revision petition. The delay is explained in para No.2 of the said application, which is reproduced, as under:- “That after receipt of the copy of the impugned order from the counsel of the petitioner, the same was analysed by the petitioner in view of the financial implications and policy issues involved therein. Considering the importance of the matter, it was thereafter decided by the petitioner that revision petition may be filed challenging the orders passed by the Forums below. Hence, necessary approvals were taken for filing the said revision petition. The Governmental procedures in respect of seeking sanctions, collecting relevant documents from concerned departments and preparing and filing the present revision petition has resulted in unavoidable delay of 34 days, which is unintentional, unavoidable and highly regretted”. 5. In the said application reference was also made to the authorities, State of Nagaland Vs. Lipok Ao (2005) 3 SCC 752, Bhag Singh & Ors. Vs. Major Daljit Singh & Ors., 1987 Supp SCC 685. Counsel for the petitioner has also invited our attention towards the affidavit of Sh.Ashwani Sharma, Estate Officer, HUDA, Panchkula, wherein an effort has been made to explain the day-to-day delay. 6. Learned counsel for the respondent vehemently argued that it is only administrative and procedural delay and the petitioners do not deserve any leniency from this Commission. 7. There is delay of 34 days only. This cannot be said to be ‘inordinate delay’. The procedural and administrative steps take negligence on the part of the some petitioners, time. Even the same if there is can be some met by payment of costs. Last but not the least, we also see some merit in the case of the respondent. The application for condonation of delay is allowed subject to deposit of Rs.25,000/- with Prime Minister Relief Fund, towards Uttarakhand Tragedy, within 90 days, otherwise, the application shall be deemed to have been dismissed along with the revision petition. The Registrar is directed to see the compliance of the order and shall submit the report, within 30 days’, thereafter. 8. Now, we turn to the merits of the case. Learned counsel for the petitioner/complainant vehemently argued that this case is different from the other cases. In this case, the allotment letter was issued and as such, the petitioner is to be considered as a “consumer”. He has also invited our attention towards allotment letter dated 18.03.1992, wherein, para III of the said letter reads, as under :“III. The above policy shall also apply in case there are a number of co-sharers of the land which has been acquired. If the acquired land measures more than one acre. Then, for the purpose of granting benefits under this policy, the determining factor should the area owned by each co-sharer, respectively, as per his/her share in the joint-holding. In case the acquired land of the cosharer is less than one acre, only one plot of 250 sq.yd., would be allotted in the joint name of the co-sharers”. 9. However, counsel for the petitioners has pointed out that the said Policy has been amended and has invited our attention towards letter dated 12.03.1993, the relevant para of which, reads as follows:- “I am directed to address you on the subject cited above and to inform that pursuit to the review of the oustees policy by the Authority in its meeting held on 20.02.1992, revised instructions were circulated on the subject vide memo No.S-292/2071, dated 18.03.1992. While the said policy laid the guidelines to determine the eligibility of claimant oustees for allotment of residential commercial sites, the procedure to examine such claims remained open-ended”. 10. All the arguments advanced by the counsel for the respondent are bereft of merit. As a matter of fact, the case of oustees does not come within the domain of consumer fora. In a judgment of this Commission, titled HUDA Vs. Uday Singh, (RP No.3456 of 2009), it was held : “Learned counsel for the petitioner would also place reliance on a decision of this Commission in the matter of Premkanta & Ors., Vs. HUDA & Anr., for unsuiting respondents, they being not consumers, as defined under Section 2(1)(d) (ii) of the Act. We can take notice of the fact that since owners of land had received compensation for land acquired by HUDA, allotment of residential plot under the Scheme was only a gesture of goodwill and there being no element of ‘hiring’ service for consideration of petitioner authority from respondents. The ratio of decision of the case in Premkanta (Supra) applies with all force with the case under consideration before us with identical factual backgrounds”. 11. A Special Leave Petition (Civil Appeal No. 10379/2010, titled Udai Singh Vs. HUDA & Anr.) was filed before the Hon’ble Supreme Court against the above said order and the same was dismissed by the Hon’ble Apex court, vide order dated 16.04.2010. 12. This Bench consisting of Justice J.M.Malik and Mr.Vinay Kumar, Member, took the same view in Prem Singh Vs. Chief Administrator, HUDA, III (2012) CPJ 320 (NC) and also followed the judgment of Premkanta & Ors., Vs. HUDA, III (2008) CPJ 146 (NC). 13. LRs., We also decided another case, titled as Om Prakash (deceased), Through Vs. HUDA & Ors., (RP No. 2007 of 2011, decided on 03.09.2012), and took the same view, wherein a number of other authorities were also cited. It, therefore, appears that the District Forum as well as the State Commission arrogated to themselves those powers with which they were not armed with. The consumer fora has no jurisdiction. 14. An application has been moved by Co-sharers through Sh.Madhurendra Kumar, Advocate. That application has become infructuous. We set aside the orders passed by the fora below and dismiss the complaint. There shall be no order as to costs. However, the complainant is given liberty to file this case before the appropriate forum for redressal of his grievances. He can seek help from Laxmi Engineering Works vs.PSG Industrial Institute – (1995) 3 SCC 583, on the point of limitation. ..…………………..………J (J.M. MALIK) PRESIDING MEMBER ……………….…………… (DR.S.M. KANTIKAR) MEMBER dd/1 NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 485 OF 2013 (From the order dated 19.10.2012 in Appeal No. 525 of 2010 of the Kerala State Consumer Disputes Redressal Commission, Thiruvananthapuram) Sasi P.K., S/o Kochukutty Thadikal House, Padiyoor, P.O. Padiyoor, Kannur Distt. …Petitioner/Complainant Versus 1. The Director H & J Infomark Industrial Estate, Ettumanoor, Kottayam 686631 2. H & P Estate Pvt. Ltd. 43/1495 Benedict Road, Ernakulam North Cochin 682018 3. Malanad Agencies Nediyodichal, Padiyoor Post PIN 670703 …Respondents/Opp. Parties (OP) BEFORE HON’BLE MR. JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER HON’BLE DR. B.C. GUPTA, MEMBER For the Petitioner : PRONOUNCED ON Mr. Rajan P. Kaliyath, Advocate 19th July, 2013 ORDER PER JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER This revision petition has been filed by the petitioner/Complainant against the order dated 19.10.2012 passed by the Kerala State Consumer Disputes RedressalCommission, Thiruvananthapuram (in short, ‘the State Commission’) in Appeal No. 525 of 2010 – Sasi P.K. Vs. Director, H & J Infomark & Ors. by which, while dismissing appeal, order of District Forum dismissing complaint was upheld. 2. Brief facts of the case are that complainant/petitioner planted 227 rubber plants in 1 acre of land. Complainant purchased 8 Kg. Well Coat @ 55% from OP3/Respondent-3, which was manufactured by OP-1/Respondent-1 and marketed by OP2/Respondent-2. Complainant applied Well Coat to the plants, but after a week, all plants dried up and perished. Matter was reported to the OPs and authorities of Rubber Board collected sample from the remaining portion of Well Coat and reported that plants dried up and perished on account of application of the Well Coat which is defective and harmful Well Coat. Alleging deficiency on the part of OP, complainant filed complaint. OPs resisted complaint and submitted that OPs had not given any promise or issued printed plan tips to the complainant regarding the application of Well Coat to the entire trees. OPs further denied supply of injurious or defective pesticides. It was further alleged that, as complainant is an inexperienced and incompetent rubber planter, plants dried and prayed for dismissal of complaint. Learned District Forum after hearing both the parties dismissed complaint against which, appeal filed by the petitioner was dismissed by learned State Commission vide impugned order against which, this revision petition has been filed. 3. Heard learned Counsel for the petitioner at admission stage and perused record. 4. Learned Counsel for the petitioner submitted that even after proving the fact that on account of defective Well Coat, petitioner’s plants dried, learned District Forum committed error in dismissing complainant and learned State Commission further committed error in dismissing appeal; hence, revision petition be admitted. 5. Perusal of record reveals that as per complaint, complainant purchased 8 Kg. Well Coat bottles of 1 Kg. each, whereas he has filed Bill No.757 only for 3 bottles of 1 Kg. each. Complainant has not produced Bill of another 5 Kg. Well Coat for the reasons best known to him. Complainant has also not placed any expert opinion to show that Rubber plants perished due to application of Well Coat though sample was collected by Rubber Board from remaining portion of Well Coat. As per report of PW2, all 217 Rubber Plants were found completely dried and recommended replanting. It was further observed that chemical contamination has to be confirmed pertaining to dried plants. During cross-examination, he admitted that if 10 gms Rubber kot is applied, it will not dry meaning thereby, 1 Kg. Well Coat was to be applied to 100 plants, whereas complainant purchased 8 Kg Well Coat and applied to the plants. In such circumstances, it can very well be presumed that on account of excess application of Well Coat plants dried up. He has further admitted that approx. 12 Kg of Rubber kot has been applied in the plantation of complainant. It appears that only due to excess application of Well Coat, petitioner has not filed Bill of purchase of rest of 5 Kg. Well Coat. He further admitted that he cannot say whether drying of the plantation was not due to application of Rubber Kot, but due to some other thing. He has simply expressed possibility of drying due to application of Well Coat. He is even not aware; whether any other product is added to Well Coat or not, whereas 100 gms. tyroid was purchased only for the purpose of mixing with the Well Coat. He has further admitted that for confirmation of drying up of plantation due to application of Well Coat, chemical analysis is required. 6. Complainant has not placed any laboratory report and in the absence of laboratory report, it cannot be inferred that on account of application of injurious Well Coat Rubber plants dried. Learned Counsel for the petitioner submitted that as sample of Well Coat could not be sent to laboratory for test, as whole the quantity purchased was used and in the light of judgment passé by Apex Court in I (2012) CPJ 1 (SC) – National Seeds Corporation Ltd. Vs. M. Madhusudhan Reddy &Anr., laboratory test is not required where whole quantity of purchased article has been used. We agree with the law propounded by Hon’ble Apex Court, but in the present case, witness of the petitioner has admitted in his cross-examination test, there was sufficient quantity of sample in the tin and complaint reveals that sample was collected by Rubber Board. In such circumstances, it was obligatory on the part of complainant to get sample tested by laboratory to prove that Well Coat purchased from OP-1 and manufactured by OP-3 was injurious. 7. Learned State Commission has not committed any error in upholding order of learned District Forum dismissing complaint. We do not find any illegality, irregularity or jurisdictional error in the impugned order, which calls for any interference. 8. Consequently, revision petition filed by the petitioner is dismissed at admission stage with no order as to costs. ..……………Sd/-……………… ( K.S. CHAUDHARI, J) PRESIDING MEMBER ..…………Sd/-………………… ( DR. B.C. GUPTA ) MEMBER k NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION No. 891 of 2013 (From the order dated 30.01.2013 of the West Bengal State Consumer Disputes Redressal Commission, Kolkata in SC Case no. FA/446 of 2012) Sujit Roy 2/44 Udaynagar, P O Amroi Durgapur – 713203 Formerly A /2 Akbar Road Durgapur – 713204 Petitioner Versus 1. In-charge Standard Chartered Bank SN/10 Ambedkar Sarani City Centre, Durgapur – 713216 2. Branch Manager Standard Chartered Bank 19, Netaji Subhash Road Kolkata – 700001 3. Head of Customer Care Unit Standard Chartered Bank 19 Rajaji Salai, Chennai – 600001 Respondents BEFORE: HON’BLE MR JUSTICE V B GUPTA PRESIDING MEMBER HON’BLE MRS REKHA GUPTA MEMBER For the Petitioner IN PERSON Pronounced on 19th July 2013 ORDER REKHA GUPTA Revision petition no. 891 of 2012 has been filed against the impugned order dated 30th January 2013 passed by the West Bengal State Consumer Disputes RedressalCommission, Kolkata (‘the State Commission’). The brief facts of the case as per the petitioner/complainant are that the petitioner opened an account with ANZ Grindlays Bank at Kolkata long back, for share tradingbusiness vide ID no. 11871890. Subsequently, Standard Chartered Bank has entered into the Banking business with the said ANZ Grindlays Bank in the title of Standard CharteredGrindlays Banks. Thereafter, the name of the Bank has been renamed as Standard Chartered Bank. The petitioner had made payments as per bill of the Bank as under: S No. DD no. Date In favour of Issued by (i) 210377 26/08/2000 ANZ Bank DSP Bank (ii) 216855 14/06/2011 Standard Allahabad Amount Coop. 965/- 655/- (iii) 652335 (iv) 186267 11/05/2003 Chartered Grindlays Bank Std. Ch. Bank HDFC Bank 400/- -do- -do- 700/- Rs. 700/- was paid against their billing instruction dated 06.10.2002 for Rs.320/i.e., an extra amount of Rs.380/- was paid as advance for next billing instruction, which was lying in my account as credit balance. On the other hand, the bill as outstanding in petitioner’s account dated 05.01.2005 states that on 04.10.2002 the pending amount was Rs.17/- only for which the respondent/ opposite party charged Rs.8/- as interest, whereas in the statement of transaction dated 06.10.2002 exhibits that a total due amount is Rs.320/-. It reveals that respondent does not maintain their records and accounts correctly having no authenticity and as such the complainant has been suffering financial losses. On 10/12/2003 the respondent intimated that there was an outstanding bill of Rs.969/- as on 10.12.2003 which the petitioner should pay within 7 days, failing which the respondent would suspend the account. The demand of the respondent had no authenticity and the petitioner felt that this claim had no basis since he had already deposited all the legitimate amounts and hence, he did not make further payment resulting, he his account being suspended without giving him any information by the respondent and till then no transaction, whatever was made. And thus the petitioner had to incur loss in share transaction. In February 2004, he had given a written notice to the Bank about the suspension of my account under their acknowledgement. But no reply was given by them. The petitioner has not filed the copy of the written statement of the respondent before this Commission. However, the District Consumer Disputes Redressal Forum,Muchipara, Burdwan (‘the District Forum’) vide their order dated 11th July 2011 have stated that “the respondent bank has contested the case by filing written statement denying inter alia all the material allegations in the complaint. It is specifically stated in the written version that subject matter of the petitioner pertains to the years 2000 to 2003 and the latest whisper on the same was made, as alleged, in the year 2004-2005 and even thereafter more than four years have elapsed for which the case is barred by limitation under section 24 A of the C P Act. It is further contended that simply by letter dated 05.11.2009 as submitted by the petitioner where the reference of the letter dated 24.06.2008 of the respondent denying the allegations of the petitioner, the cause of action for the case cannot be extended and for the reasons that the case is definitely barred by limitation”. The District Forum then gave the following order: “Both the points are taken up together for a compact discussion in this case. During the argument learned lawyer of the respondent has referred to the order no. 15 as passed by this Forum on 14.09.2010 and submitted that the Forum has allowed opportunity to the petitioner to incorporate the fact of its letter dated 05.11.2009 with reference to respondent’s letter dated 24.06.2008 by way of amendment of the complaint. The order was very clear and explicit. But the same was not done by the petitioner. If in a particular allegation is not incorporated in the pleading the same cannot be relied on for getting any benefit out of it. The complaint as it is without amendment is definitely barred by limitation. As such the case is not maintainable. That apart the allegation of the petitioner regarding the fact that the respondent Bank never intimated regarding suspension of his account is baseless in view of the letters of intimation as sent by the respondent on 15.03.2004 and 05.02.2005, as it appears from the Xerox copies filed under Annexure A. Admittedly the petitioner took no step as it appears from his averments in paragraphs 7 & 8 of the complaint. In such view of the fact the case of the petitioner fails as it is time barred and not maintainable. Hence, that the case be dismissed without cost”. Aggrieved by the order of the District Forum, the petitioner filed an appeal before the State Commission. Along with the appeal an application for condonation of delay was filed. In the application for condonation of delay nowhere has the period of delay has been mentioned. The reasons given are as follows: Before the order is passed the petitioner shifted his residence from 1a/2 Akbar Road Durgapur to 2/44 Udainagar PO Amroi Durgapur – 713 204. For this reasons he was not in touch with his authorised representative who was handling the case before the District Consumer Forum on his behalf. He was thus not aware of the order so passed. The petitioner is earning for his bread and butter by giving private tuition to the school and college students. For that he cannot take frequent leave from his students. He got the certified copy of the order of the Hon’ble District Consumer Forum only on 30.01.2012. After receipt of the order the appellant handed over all the papers to Sri Banerjee an Advocate of High Court at Calcutta. It is difficult to follow up the matter regularly with the Advocate at Calcutta from Durgapuri. As a result the appeal was not filed in time. When information regarding progress of the appeal was not received he met the Advocate. After meeting him at Calcutta in the month of July 2012 he came to know that no appeal since then was filed. On the same date the papers were taken back and handed to the present lawyer to file the Appeal. Meanwhile the petitioner’s wife became sick due to rheumatic Arthritis for which the petitioner could not move of Durgapur. He is having a daughter who is aged about 3 years. The delay was totally unintentional and beyond the control of the petitioner and for that the petitioner is begging pardon for the delay. The State Commission vide their order dated 30.01.2013 heard the submissions of the Counsel for the Appellant and on perusal of the material on record for condonationof delay of 353 days in filing the appeal and dismissed the application for condonation of delay as also the appeal being time barred stating that “we have heard the submission made by the learned and perused the papers on record. It appears that the judgment was delivered on 11.07.2011 and the certified copy was applied for on 30.01.2012. In the petitioner for condonation of delay and also in the MA 18 of 2013 there is no mention as to the reasons for delay in filing the application for certified copy. The certified copy was delivered on the very same day i.e., 30.01.2012. The appeal was filed on 30.07.2012. The medical certificate was issued on 31.12.2011. Having heard the submission made by the learned Counsel for the appellant and on perusal of the materials on record we find that the delay in filing the appeal has not been sufficiently explained”. Dissatisfied by the order of the State Commission, the petitioner – Mr Sujit Roy has filed this present revision petition before us. The main ground for the revision petition is that the State Commission has not considered the merit of the case and “instead wanted an explanation for each and every day delay”. We have heard the petitioner in person and have gone through the records. With regard to the application for condonation of delay before the State Commission, the State Commission vide impugned order dated 30.01.2013 have correctly came to the conclusion that the delay in filing the appeal has not been sufficiently explained in spite of every opportunity being given. The petitioner could not give any cogent reasons or ‘sufficient cause’ for condonation of delay of 353 days in filing the appeal before the State Commission. The petitioner has failed to prove sufficient cause for condonation of delay. It is well settled that ‘sufficient cause’ for condoning the delay in each case is a question of fact. The apex court in the case of In Anshul Aggarwal v. New Okhla Industrial Development Authority, IV (2011) CPJ 63 (SC), has held that: “It is also apposite to observe that while deciding an application filed in such cases for condonation of delay, the Court has to keep in mind that the special period of limitation has been prescribed under the Consumer Protection Act, 1986 for filing appeals and revisions in consumer matters and the object of expeditious adjudication of the consumer disputes will get defeated if this Court was to entertain highly belated petitions filed against the orders of the Consumer Foras”. In Balwant Singh Vs. Jagdish Singh & Ors., (Civil Appeal no. 1166 of 2006), decided by the Apex Court on 08.07.2010 it was held: “The party should show that besides acting bona fide, it had taken all possible steps within its power and control and had approached the Court without any unnecessary delay. The test is whether or not a cause is sufficient to see whether it could have been avoided by the party by the exercise of due care and attention. [Advanced Law Lexicon, P. Ramanatha Aiyar, 3rd Edition, 2005]”. In view of the above, we find that there is no jurisdictional error, illegality or infirmity in the order passed by the State Commission warranting our interference. The revision petition is accordingly dismissed with no order as to cost. Sd/..……………………………… [ V B Gupta, J.] Sd/……………………………….. [Rekha Gupta] Satish NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI FIRST APPEAL NO. 397 OF 2007 (Against the order dated 17.02.2007 in Complaint Case No. 240/1998 of the Maharashtra State Consumer Disputes Redressal Commission) 1. Narsimha Kamath 2. Ms. Kanchan N. Kamath 3. Ms. Aditi N. Kamath (Through Mr. Narsimha Kamath) A8/4, ‘Dahivali’, Laxman Mhatre Road Kandarpada, Dahisar (West) Mumbai-400068 … Appellants Versus 1. M/s Ghai Gas Service Sayadri Building, Aarey Road Goregaon (East) Mumbai400063 2. M/s Bharat Petroleum Corporation Ltd. (LPG Division), Bharat Bhawan Ballard Estate Mumbai-400038 … Respondents BEFORE: HON'BLE MRS. VINEETA RAI, PRESIDING MEMBER HON’BLE MR. VINAY KUMAR, MEMBER For Appellant : Ms.Garima Parshad, Advocate For Respondents : Mr. Ashok Mathur, Advocate for R-1 Mr. Sanjay K. Shandilya, Advocate for R-2 Pronounced : 19th July, 2013 ORDER PER VINEETA RAI, PRESIDING MEMBER 1. This first appeal has been filed by Narsimha Kamat, Complainant No.1 before the Maharashtra State Consumer Disputes Redressal Commission (hereinafter referred to as the State Commission) and Appellant No.1 herein (other 2 Appellants being his minor daughters) being aggrieved by the order of that Commission which had dismissed their complaint filed against M/s Ghai Gas Service and Bharat Petroleum Corporation Limited, Opposite Parties before the State Commission and Respondents No.1 and 2 respectively herein. 2. In his complaint before the State Commission, Appellant stated that on 02.07.1996 his wife Anushri Kamath (hereinafter referred to as the Deceased) suspected gas leakage from the cylinder used in the kitchen and complained about the same to Respondent No.1. The complaint was attended to only after 2 days i.e. on 04.07.1996 and that too after she had personally visited the office of Respondent No.1. The mechanic who attended to the complaint changed some parts and thereafter made out a bill for Rs.340/- as also Rs.10/- as service charges. As the said amount was considered high, Deceased paid only Rs.150/- to the mechanic and told him that she would settle the remaining payment after visiting the office of Respondent No.1 next day. At about 3.45 a.m. on the night intervening 4-5.07.1996 Deceased experienced a strong smell emanating from the kitchen and she went there and immediately put off the gas regulator. Thereafter to ensure that there was no further gas leakage she triggered the gas lighter near the burner since she had seen the mechanic also test for leakage by lighting a match during his visit and thereafter there was a loud explosion in which she sustained burn injuries on her face, hands and feet. She was admitted to KEM Hospital with 37% burn injuries and succumbed to the same following Septicemia 4 days later. According to the Appellant, although the news of the incident and the death of the Deceased was conveyed to Respondent No.1, no one visited the site to make any enquiries, including reporting of the incident to the Controller of Explosives as required under the law. Appellant alleged that the accident and the unfortunate death of the Appellant’s wife occurred because the mechanic of Respondent No.1 had rendered deficient service in not attending properly to the complaint and the parts that were replaced appeared to be defective. He also left the place without completing the repairs as he himself admitted to a neighbor of the Appellant one Shri Mehta. Appellant further stated that because of the trauma suffered by him he could not follow up the case after the letter that he had written on 14.10.1996 until 05.05.1998 when he asked the Respondent No.1 to pay a compensation of Rs.20 Lakhs for causing the premature death of his wife due to deficiency in service and negligence. Since he did not receive a satisfactory response to this communication, he filed a complaint before the State Commission against Respondents No. 1 and 2 and requested that they be directed to jointly and severally pay Rs.5 Lakhs for loss of company and deprivation of marital life; Rs.5 Lakhs to his children for deprivation of maternal care; Rs.5 Lakhs on account of future loss of income earned by the Deceased; Rs.4.50 Lakhs as compensation and Rs.10,000/- as litigation costs. 3. Respondents on being served filed a written rejoinder denying the allegations pertaining to any deficiency in service. Respondent No.1 stated that the complaint regarding gas leakage was lodged on 04.07.1996 by the Deceased and on the same day itself a mechanic was deputed to attend the complaint. It was further stated that thereafter the Deceased paid a sum of Rs.340/- to the mechanic and denied that only a part payment was made inter alia on the ground that some repairs were still pending. Respondent No.1 further denied that it had been informed about the incident immediately after the incident and stated that they were informed about it vide letter dated 05.05.1998 i.e. almost two years after the incident, after which Respondent No.2 was also informed. It was further stated that it was well established by investigations conducted by the police as also the dying declaration of the Deceased herself that the unfortunate incident occurred due to the negligence on the part of the Deceased since she failed to switch off the gas regulator and tested for gas leakage by using a lighter, a practice which had been widely publicized as being very hazardous. It was also contended that the LPG cylinders are manufactured from special steel and due care is taken regarding its safety. In case of any mishap like leakage, the safety precautions have to be taken by the customers themselves, including switching off the regulator. In the instant case the Deceased herself had admitted in the dying declaration that the gas was not properly put off by her which was likely to result in the leakage of the gas. Thus, the negligence, if any, lay on the part of the Deceased and the Respondents cannot be blamed for the same. Therefore, the question of deficiency in service or settling the insurance claim with the insurance company (which has not been impleaded as a party) did not arise. 4. The State Commission after hearing the parties and on the basis of evidence produced before it dismissed the complaint by observing as follows: “7. There is no proof placed on record to show that O.P.no.1 was deficient in service or negligent in rendering service to the customer. The dying declaration of Anushri Kamath was recorded by the Investigating officer. Police agency also recorded statements of close relatives of Anushri Kamath, including husband and father of deceased Anushri. They have not attributed any negligence to O.P.no.2. The dying declaration and police statements are part of the record and proceeding of this complaint. 8. Ld.Advocate Mr.Shirish Deshpande submitted that dying declaration of Anushri Kamath cannot be considered on the ground that there is nothing on record to show that Anushri was conscious at the time of recording of dying declaration. He also submitted that dying declaration cannot be considered as a piece of evidence. 9. Dying declaration, which is properly recorded is a best piece of evidence. In criminal trials the dying declaration is regarded as a legal proof, provided all the legal requirements are complied with before recording of Dying declaration. Dying declaration can be the basis for conviction. A statement made by a person who is on the deathbed under expectation of death, is called a dying declaration. If the person is mentally conscious, then statement of a person who is on the deathbed, can be recorded in presence of doctor. It is said that a person on the deathbed and who is likely to embrace death within short time, is reluctant to speak a falsehood. Such a person does not want to meet the God with a falsehood on the tongue. Therefore dying declaration is regarded as a best kind of proof. 10. In the case in hand, Dr.A.K.Deodhar attached to KEM Hospital examined Anushri Kamath and found that she was fully conscious and was in a condition to give statement. Doctor Deodhar accordingly made endorsement about mental condition of injured in the margin of the dying declaration. Sub-Inspector of Police attached to Dindoshi police station thereafter recorded dying declaration of Anushri Kamath. Anushri Kamath has given full account of the mishap. After narrating the entire of the incident, she concluded at the fag end of the dying declaration that she did not properly switched off the gas stove and because of that there was explosion of gas cylinder. The husband and father of deceased have also given similar kind of version before the police. All the necessary precautions, which were required by law were taken before dying declaration of injured was recorded. Dr.Deodhar examined the physical and mental condition of the injured. He found that injured was mentally alert and was in a position to give statement. Thereafter the police officer recorded the dying declaration. No fault can be found in the dying declaration of deceased Anushri Kamath. 11. Complainants have miserably failed to prove that O.P.no.1 was negligent in any manner. There was no deficiency in service.” 5. Being aggrieved by the order of the State Commission, the present appeal has been filed. 6. Learned Counsels for both parties made detailed oral submissions. 7. Counsel for the Appellant contended that the State Commission erred in concluding that there was no deficiency in service on the part of Respondents by relying primarily on the dying declaration of the Deceased and without taking into account other important evidence, which clearly confirmed that Respondent No.1 was negligent, resulting in the gas explosion and death of the Deceased. Counsel for the Appellant reiterated that while the complaint regarding leakage of gas from the gas cylinder supplied by Respondent No.1 was made on 02.07.1996 no action was taken by Respondent No.1 till two days later and that also after the Deceased had personally visited the office. Since the leakage of gas can prove to be very hazardous and dangerous, the delay in attending to this serious complaint by Respondent No.1 itself indicates deficiency in service. Thereafter an inexperienced mechanic was sent to repair the same and on the first day i.e. on 04.07.1996 he only changed some parts of the cylinder leaving some repairs for the next day. This is evident from the fact that against a total payment of Rs.340/-, only sum of Rs.150/- was paid the first day and the remaining amount was to be paid after the major work was done. Counsel for the Appellant contended that these facts had been submitted before the State Commission and in support the names of the mechanic as also a neighbor Shri Mehta to whom the mechanic informed that the work was incomplete were stated before the State Commission. The very fact that Respondent No.1 did not produce the mechanic to support their case confirms the Appellant’s version of the matter. Further, that there was a complaint of leakage of gas was accepted by Respondent No.1 in the written rejoinder filed by it before the State Commission (Annexure P-8). Counsel for the Appellant further stated that the contention of Respondent No.1 that the Deceased herself was responsible for the accident since she did not take due care in switching off the knob of the gas cylinder from the regular is also not correct and in fact she had turned off both the gas cylinder knobs and the regulator. Regarding the dying declaration of the Deceased, Counsel for the Appellant contended that this statement was made by her because Deceased wanted to convey that there was no foul play relating to dowry or marital issues which led to the incident and the State Commission erred in misinterpreting the dying declaration. Counsel for the Appellant also stated that the State Commission erred in concluding that the Respondents were not informed about the incident. In fact, they were informed about the same vide letter dated 14.10.1996 i.e. soon after the incident and the death of the Deceased and the delay in filing the complaint before the State Commission was because the Appellant was hoping for a favourable response from the Respondents and also because he was in a traumatized state and was busy in the repairs of his house, which was damaged in the gas explosion. 8. Counsel for Respondent No.1 stated that the above contentions made by the Counsel for the Appellant are not borne out by the evidence on record, including the documentary evidence. Regarding the dying declaration of the Deceased, it was clearly stated by her as follows : “The said incident has occurred as gas was not properly put out by me and I have therefore no complaint or any suspicion on anybody.” This statement clearly indicates that the Deceased admitted that she had not properly switched off the gas cylinder and had turned off the gas to prevent leakage only after she had detected the smell on the early morning of 05.07.1996. Further the action of the Deceased in using the gas lighter to check that there was no leakage was highly hazardous and dangerous and it was, therefore, because of this action on her part that the very unfortunate incident occurred. Counsel for Respondent No.1 denied that there was any delay in attending to the complaint which was made on 04.07.1996 and within hours a mechanic was dispatched to attend to the complaint. As per the bill filed in evidence, he had completed the repairs and in acknowledgment the total amount due i.e. Rs.340/- was paid. Appellant’s contention that the mechanic had come back the next day to complete the repairs and had also informed a neighbor about the same is not supported by any credible and independent evidence by the Appellant. No affidavit was for example filed by Shri Mehta, the neighbor, to support this contention. Counsel for Respondent No.1 further stated that there is nothing on record to support Appellant’s contention that he immediately informed Respondent No.1 about the incident and in fact Respondent No.1 only came to know about the same on 05.05.1998 and it had also informed the Appellant vide letter dated 29.05.1998 that it never received the letter purported to have been sent by the Appellant in 1996. Police investigations conducted into the matter also confirmed that the Respondents were not guilty of any deficiency in service and negligence in this case. The State Commission, which is a first court of fact, had gone into the entire facts of this case and had rightly concluded that there was no negligence or deficiency in service on the part of Respondents. 9. Counsel for Respondent No.2 stated that Respondent No.2 are the manufacturers of the gas cylinders and they had not been informed about the incident. Further, the relationship between Respondent No.1 and Respondent No.2 was on principal-to-principal basis and, therefore, Respondent No.1 was not their agent. Under the circumstances, the State Commission had rightly concluded that they could not be held guilty in rendering deficient service or being responsible for the incident. 10. We have heard learned Counsels for the parties and have also carefully gone through the evidence on record. The facts pertaining to the gas explosion in which Deceased received 37% burn injuries for which she was admitted to KEM Hospital on 05.07.1996 and her subsequent death on 08.07.1996 is not in dispute. It is further a fact that in her dying declaration Deceased had clearly stated that the gas was not properly put off by her and, therefore, she had no complaint against anyone else. In the same dying declaration she had also stated that at about 3.45 a.m. on 05.07.1996 when she detected a smell emanating from her kitchen, she went to the kitchen and turned off the gas to prevent leakage of gas, which further indicates that the gas was not properly turned off by her. Apart from this, she further confirmed that to make sure that there was no further leakage she triggered the gas lighter causing the explosion. At the time she made the dying declaration, it was certified by Dr. A.K. Deodhar at KEM Hospital that she was fully conscious and in a condition to make her statement. The contention, therefore, of Counsel for the Appellant that the dying declaration was made by her only to rule out any foul play or involvement of any third party is not borne out by the evidence on record. Regarding the allegation of negligence against Respondent No.1 that they failed to respond to the complaint immediately and that the mechanic did not complete the work, we are unable to accept the contention of Counsel for the Appellant since again there is no independent evidence in support of the same. From the records on file, the mechanic did the entire repairs on 04.07.1996 itself and in acknowledgment he was paid the total amount as clearly indicated in the receipt. The contention of Counsel for the Appellant that the mechanic came the next day to complete the remaining repairs and that he had informed the same to a neighbor (Shri Mehta) is not confirmed by any evidence in respect of the same except the verbal contention of the Appellant. Appellant in support of the case could have produced the affidavit of Shri Mehta before the State Commission, which he failed to do. It is also a fact that the complaint was made before the State Commission almost two years after the incident. The reasons given for the same do not adequately explain the delay. Undoubtedly, the Appellant suffered a great trauma in losing his wife in such a tragic manner and a delay of few months in filing the complaint could have been well explained but not such a long period of almost two years. Because of this delay, it was not possible for any meaningful enquiry to have been conducted by Respondent No.2 i.e. the manufacturer when it was informed about the incident. The State Commission after considering all these facts has rightly concluded that the Appellant has failed to prove that there was any deficiency in service or negligence on the part of Respondents. 11. In view of the above facts, we see no reason to disagree with the order of the State Commission and uphold the same. The first appeal is dismissed. No costs. Sd/(VINEETA RAI) PRESIDING MEMBER Sd/(VINAY KUMAR) MEMBER Mukesh NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 1975 OF 2013 (From the order dated 16.11.2012 in First Appeal No. 662/2011 of Kerala State Consumer Disputes Redressal Commission) 1. SKARIAH MATHAI S/O THOMAS SKARIAH, 2. P.M JOHNYKUTTY, S/O SKARIAH MATHAI, 3. MATHEW VARGHESE, S/O SKARIAH MATHAI, 4. P.M. SAJIMON , S/O SKARIAH MATHAI, 5. ANNAMMAS MATHEW, D/O THOMAS SKARIAH, REP BY MATHEW VARGHESE BROTHER, all r/o PUTHENCHIRAYIL HOUSE, MEKOZHOOR P.O, PATHENAMTHITTA KERALA ...........Petitioner(s) Versus 1. MAR GREGORIOUS MEMORIAL MUTHOOT MEDICAL CENTRE REP BY ITS CHIEF MEDICAL OFFICER/ MANAGING DIRECTOR, COLLEGE ROAD, KOZHENCHEERY – 689641 KERALA 2. DR. JOLLY V. MATHEW, MGM MUTHOOT MEDICAL CENTRE, COLLEGE ROAD, KOZHENCHEERY – 689641 KERALA 3. DR. SUSAN THARIAN, MGM MUTHOOT MEDICAL CENTRE, COLLEGE ROAD, KOZHENCHEERY – 689641 KERALA 4. D. DEVARAJAN, CARDIOLOGIST, MGM MUTHOOT MEDICAL CENTRE, COLLEGE ROAD, KOZHENCHEERY – 689641 KERALA 5. ICICI LOMBARD GENERAL INSURENCE, ICICI BANK TOWERS, BANDRA KURLA COMPLEX, MUMBAI – 400051 MAHARASHTRA ...........Respondent(s) BEFORE HON’BLE MR. JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER HON’BLE DR. B.C. GUPTA, MEMBER APPEARED AT THE TIME OF ARGUMENTS For the Petitioner(s) Mr. K.P. Toms, Advocate PRONOUNCED ON : 19th JULY 2013 ORDER PER DR. B.C. GUPTA, MEMBER This revision petition has been filed under section 21(b) of the Consumer Protection Act, 1986 against impugned order dated 16.11.2012 passed by the Kerala State Consumer Disputes Redressal Commission (for short ‘the State Commission’) in FA No. 662/2011 “Mar Gregorious Memorial Muthoot Medical Centre Vs. Skariah Mathai,” vide which, while allowing appeal against the order dated 16.08.2011, passed by District Forum, Pathenamthitta, the consumer complaint no. 121 of 2007 was ordered to be dismissed. 2. Brief facts of the case are that Mrs. Sosamma Mathew, who was the wife of petitioner/complainant no. 1 and mother of petitioners/complainant nos. 2 to 5 was admitted at respondent/OP No. 1 Medical Centre on 1.2.2007 with complaints of pain in the neck and pleuritic pain on the right side of the chest for two weeks before admission. She was diagnosed as a patient of Type II Diabetic Mellitus / Hypertension, Bronchogenic Carcinoma with pleural metastasis, malignant mesothelioma and Coronary Artery Heart Disease. She was admitted in the Intensive Care Unit (ICU) under the direct supervision of respondent nos. 1 to 4. It has been stated that the condition of the patient worsened on 3.2.2007 when she had chest pain followed by cardio-respiratory arrest. She was intubated and put on ventilator by respondent no. 3 who was anaesthetist on duty. It has been alleged that the relatives and family members of the patient were not allowed to see her when she was in the ICU, neither they were given any information about the condition of the patient and her treatment. It has also been alleged that the patient was put on ventilator by the OPs without the consent of the relatives. The complainants have stated that the condition of the patient worsened due to wrong medication, medical negligence, improper management and care, due to which she developed oedema and other respiratory heart complications and she had to be put on ventilator. The OPs also served huge medical bills upon the complainants which was not bearable for them. They were asked to pay a sum of Rs.43,000/- which included Rs.27,000/- as hospital charges and Rs.16,000/- for medicines. They had to pay that money by borrowing from others. The complainants, therefore, requested the OPs to discharge the patient so that she could be taken to some other hospital for treatment. The patient was discharged on 08.02.2007 and admitted to Fellowship Mission Hospital at Kumbanad on the same day. In the said hospital, she was never put on ventilator and given treatment and medication of a mild nature and she remained their till 15.02.2007. The patient, Mrs. Sosamma Mathew, issued a notice to the respondent hospital on 5.03.2007 and also made a complaint before the Chief Minister who asked the District Medical Officer to enquire into the matter and submit report. Mrs. S. Mathew, however, died on 31.07.2007 due to lung cancer. The present complaint has been filed by her husband and children. The District Forum allowed the complaint on 16.08.2011 and directed the first OP to return 50% of the treatment expenses along with compensation of Rs.25,000/- and cost of Rs.10,000/-. The District Forum also allowed interest @10% p.a. from the date of the order till realisation. It was also stated that the OP Hospital could realise the decreed amount from OP No. 5, Insurance Company, if there was a valid insurance policy. An appeal was filed against this order before the State Commission which was allowed by the Commission and the order of the District Forum was set aside and the complaint was dismissed. It is against this order that the complainants have filed the present revision petition. 3. Heard the learned counsel for the petitioners and examined the entire material on record. 4. Learned counsel for the petitioner invited our attention to copies of discharge summary made by two hospitals where the patient was admitted for treatment. He vehemently argued that at the first hospital, i.e., OP No. 1, the patient was constantly kept on ventilator, which was not required. The moment the patient was discharged by the first hospital, she walked away on her own and was taken to the Fellowship Mission Hospital where no life-saving support was given. The patient was fit to be discharged on 06.02.2007 but the OPs, with an intention to make money, kept the patient with them in the ICU. The discharge summary given by the first hospital indicates that the patient was being discharged against medical advice on the written consent given by the relatives. The discharge summary made by Fellowship Mission Hospital, however, shows that the patient was admitted for palliative care and was given normal treatment. On the date of discharge, the oedema had improved as compared to the time of admission. Learned Counsel also invited our attention to the complaint dated 06.12.2007 in which it has been alleged that the complainants had to pay through their nose for hospitalisation and follow-up treatment and medicines, due to wrong medication, medical negligence and improper management and care of a critical and terminally-ill patient. 5. An examination of the facts of the case make it very clear that as stated by the petitioners/complainants themselves, the patient Mrs. Sosamma Mathew was a critical and terminally-ill patient, who was admitted in the OP No. 1 Hospital with multiple problems. As stated earlier, the complainants had made a complaint to the Chief Minister against OP No. 1 Hospital and the matter was enquired into by the District Medical Officer (Health), Pathenamthitta. The DMO (Health) submitted a detailed report after recording the statements of the complainants and the concerned doctors. The report of the DMO shows clearly that the patient was brought to OP No. 1 Hospital on 1.02.2007 with fluid accumulation in the right side of the chest. After check-up, it was detected that the accumulation of fluid in chest was Misothilioma, a type of cancer. In order to confirm the same, CT scan of the chest was done and it was found that she was suffering from bronchogenic cancer that had spread to pleura, and it was confirmed that the disease was Misothilioma. The relatives of the patient were informed that for expert treatment and diagnosis, the patient had to be taken to Regional Cancer Centre, Thiruvananthapuram. The report of the DMO makes it very clear that on 3.2.2007, after midnight, the functioning of heart and lungs of Mrs. Sosamma Mathew had suddenly stopped and in order to save her life, she was put on ventilator with the consent of relatives. Her life was saved due to the emergency treatment given to her. The report has further highlighted that the complainants had financial difficulties and was unable to bear the expenses. The complainant no. 3, Mathew Varghese is the clerk of an Advocate. 6. It is also made out from the facts on record that on 07.02.2007, the hospitals doctors tried to remove the ventilator from the patient, but the same had to be reconnected after three hours. On 08.02.2007, the ventilator was disconnected on the insistence of the complainants. The patient was discharged and taken to other hospital where she remained in treatment for another one week. From the material on record, especially the report of the DMO, it becomes clear that OP No. 1 Hospital tried their best to take care of the patient, who was in a critical and terminally ill stage. She was put to examination by doctors belonging to all concerned specialists and in fact, they were able to save her life when her heart and lungs stopped functioning on 3.02.2007. We, therefore, tend to agree with the findings of the State Commission that the allegation of medical negligence against the respondents does not stand proved. The complaint has been made for the reason that the complainants had difficulty in meeting the expenditure of the Hospital and they even approached the Chief Minister for getting a relief from the Distress Relief Fund. We, therefore, find no reason to interfere with the well-reasoned order passed by the State Commission which does not suffer from any irregularity, illegality or jurisdictional error. The revision petition is, therefore, ordered to be dismissed and the order of the State Commission upheld with no order as to costs. SD/(K.S. CHAUDHARI J.) PRESIDING MEMBER SD/(DR. B.C. GUPTA) MEMBER RS/ NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 1449 OF 2012 (From the order dated 28.02.2012 in First Appeal No. 1622/2010 of Gujarat State Consumer Disputes Redressal Commission) Proprietor of Zuber Transport Sohaibbhai Unusbhai Vohra Res. at: Paramount Society, Bungalow No. 62, Polson Dairy Road Anand, Gujarat State ... Petitioner Versus Reliance General Insurance Co. First Floor, P.N. Square, Opp. Cafe Coffee Day, Opp. Petrol Pump, Anand, District Anand Gujarat State … Respondent BEFORE HON’BLE MR. JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER HON’BLE DR. B.C. GUPTA, MEMBER APPEARED AT THE TIME OF ARGUMENTS For the Petitioner(s) Ms. Girija Wadhwa, Advocate For the Respondent(s) Mr. Navneet Kumar, Advocate PRONOUNCED ON : 22nd JULY 2013 ORDER PER DR. B.C. GUPTA, MEMBER This revision petition has been filed under Section 21 of the Consumer Protection Act, 1986 against the order dated 21.02.2012 passed by the Gujarat State Consumer Disputes Redressal Commission (hereinafter referred as ‘State Commission’) in appeal no. 1622 of 2010, ‘Proprietor of Zuber Transport Vs. Reliance General Insurance Company’ and appeal no. 1778 of 2010, ‘Reliance General Insurance Company Vs. Proprietor of Zuber Transport’ vide which appeal no. 1622 of 2010 filed by the complainant/petitioner as per Consumer Complaint No. 46 of 2009 before the District Forum was dismissed, while appeal of the opposite party, Reliance General Insurance Company was accepted and the order passed by the District Forum dated 30.09.2010 was set aside. The District Forum vide said order had directed the opponent, the Insurance Company to pay Rs. 1 lakh with 9% interest from 01.03.2009 to the complainant and also ordered to pay Rs. 5,000/- for mental agony and cost of litigation. 2. Briefly stated, the facts of the case are that the petitioner/complainant carried on business under the name of Zuber Transport in District Anand, Gujarat having truck no. GJ 9Y6891 since 22.02.2008. The said truck was insured with the opposite party, Reliance General Insurance Company vide policy no. 1611782334002087 and premium amount of Rs. 25,777/- was paid by the complainants. The policy was valid from 16.01.2008 to 15.01.2009. It is stated that the said truck was parked outside the office of Zuber Transport in common plot, when it was stolen early morning and FIR No. 2/09 dated 01.01.2009 was filed with the police, and the insurance company was also informed. The aforesaid truck was later recovered from the area of Bodeli Police Station, District Vadodara, Gujarat State. As per the Panchnama prepared by the police, 11 tyres and plates, nuts were stolen which valued at Rs. 1,75,000/-. The complainant sent the requisite documents and original bills of Rs. 2,53,908/- to the Insurance Company, but the company sent a cheque of Rs. 45,441.50/- as full and final settlement. The complainant returned the said cheque to the Insurance Company and filed Consumer Complaint in the District Consumer Forum. The stand taken by Insurance Company was that under the terms and conditions of the policy, the tyres of the truck were not covered, and hence the complainant could not be given compensation for the loss of tyres. The District Forum vide their order dated 30.09.2010, allowed the complaint and directed the Insurance Company to pay a sum of Rs. 1 lakh with 9% interest with effect from 01.03.2009 and also to pay Rs. 5,000/- for mental agony and cost of litigation. Against this order, two cross appeals were filed before the State Commission. The State Commission dismissed the appeal filed by the complainant for enhancement of the award as given by the District Forum. On the other hand, the State Commission accepted the appeal filed by the opposite party and set aside the order passed by the District Forum. It is against this order that the present petition has come up. 3. Heard the learned counsel for the parties and examined the record. 4. It has been contended by the learned counsel for the petitioner/complainant that the claim should have been allowed, at least on non-standard basis by the Insurance Company. The learned counsel invited our attention to the order passed by Hon’ble Supreme Court of India in Amalendu Sahu Vs. Oriental Insurance Company as reported in 2010 (2) CACC 103 (SC) in which it has been stated that in case of violation of conditions of policy, the claim ought to be settled on non-standard basis. Further, in another judgment given by the Hon’ble Apex Court in National Insurance Company Vs. Nitin Khandelwal, as reported in IV (2008) CPJ 1(SC), it has been stated that in the case of theft of vehicle, breach of condition is not germane. The Insurance Company is liable to indemnify the owner of the vehicle when the insurer has obtained comprehensive policy for the loss caused to the insurer. The claim should be settled on a non-standard basis. The learned counsel argued that the factum of truck being stolen is an admitted fact and the District Forum has rightly allowed the complaint, though partly. 5. In response, the learned counsel for the respondent vehemently argued that in the instant case, the truck in question had been recovered, and hence the Insurance Company is liable to pay for “own damage” only. Had the truck not been recovered, the Insurance Company was liable to pay compensation as per the total loss, but in this case, the position was different, as the truck had been recovered. There was no deficiency on the part of the Insurance Company, because they had sent a cheque of Rs. 45,441.50/- to the complainant in accordance with the reports submitted by the surveyor. The learned counsel invited our attention to a number of rulings of the Hon’ble Supreme Court of India in ‘Export Credit Guarantee Corporation of India Ltd. Vs. Garg Sons International’, as reported in 2013 (1) SCALE 410, Suraj Mal Ram Niwas Oil Mills (P.) Ltd. Vs. United India Insurance Co. Ltd. and Anr. as reported in (2010) 10 SCC 567 and Oriental Insurance Company Ltd. Vs. Sony Cheriyan as reported in AIR 1999 SC 3252. The learned counsel argued that the insured can not claim anything more than what is covered by the insurance policy and that the insurance policy between the insurer and the insured represents a contract concluded between the parties. 6. We have examined the entire matter on record and given a thoughtful consideration to the arguments advanced before us. A perusal of the record indicates that the terms and conditions of the insurance policy in question state as follows:“The company shall not be liable to make any payment in respect of: (B) Damages to tyres and tubes unless the vehicle insured is damaged at the same time in which case the liability of the company shall be limited to 50% of the cost of replacement and as per the clause (a) of paragraph TMT 21 special exclusions and compulsory deductible of policy. (A) Except in the case of total loss of the vehicle insured the insured shall not be liable under section of the policy for loss or the damages to lumps, tyres, tubes, mudguards, bonnet side parts, bumpers and paint work ….” 7. A plain reading of the above terms and conditions indicates that the Insurance Company is not liable to pay compensation for the loss of tyres and tubes, unless it is a case of total loss of the vehicle. It is an admitted fact that in this case, the stolen truck was recovered later, but the tyres etc. were missing. There is no force in the contention of the complainant that the claim could at least be settled on a non-standard basis. The citations submitted by the complainant do not provide him any benefit, as this is not a case where there has been a violation of terms and conditions. It is clearly one of the conditions of the insurance policy that damage of tyres and tubes is not covered under the policy. The Insurance Company has, therefore, not committed any deficiency in disallowing the claim of the complainant for the loss of tyres etc. It is clear, therefore, that the State Commission has made a correct appreciation of the facts and circumstances of the case, and came to the conclusion that the Insurance Company had not committed any deficiency in service and provided compensation in accordance with the report of the surveyor. We do not find any illegality, irregularity or jurisdictional error in the order passed by the State Commission and hence, the same is ordered to be upheld. The petition is ordered to be dismissed, with no order as to costs. ..…………………………… (K.S. CHAUDHARI J.) PRESIDING MEMBER ..…………………………… (DR. B.C. GUPTA) MEMBER PSM NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 1051 OF 2013 (From the order dated 04.01.2013 in MA/11/76 in Appeal No. A/11/169 of the Maharashtra State Consumer Disputes Redressal Commission, Circuit Bench, Nagpur) Nirmal Land Developers & Builders Through its Proprietor Shri Mahendra Jayram Borkar Aged about 49 years Occ – Business R/o Nirmal Colony, Nara Road, Nagpur Maharashtra …Petitioner/Opp. Party (OP) Versus Rameshchandra Gopalrao Pande R/o Block No. AG-1 Rahate Colony, Nagpur, Maharashtra …Respondent/Complainant BEFORE HON’BLE MR. JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER HON’BLE DR. B.C. GUPTA, MEMBER For the Petitioner : Mr. Arvind S. Waghmare, Advocate PRONOUNCED ON 22nd July, 2013 ORDER PER JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER This revision petition has been filed by the petitioner/opposite party against the order dated 04.01.2013 passed DisputesRedressal Commission, Commission’) in Appeal by the Circuit No. Bench, A/11/169 Maharashtra State Nagpur short, (in – Nirmal Land Consumer ‘the State Developers & Builders Vs. RameshchandraGopalrao Pande by which, appeal filed by the petitioner was dismissed as barred by limitation. 2. Complainant/respondent filed complaint before District Forum with a prayer to direct OP/petitioner to execute sale deed of plot Nos. 57 & 68 in favour of the complainant and pay Rs.55,000/- as compensation towards harassment. Learned District Forum after hearing both the parties allowed complaint vide order dated 24.11.2009 and directed OP to execute sale deed and pay Rs.5,000/- as compensation and Rs.1,000/- as litigation expenses. Appeal filed by the petitioner was dismissed by learned State Commission, as it was barred by 15 months. 3. Heard learned Counsel for the parties at admission stage and perused record. 4. Petitioner filed appeal along with application for condonation of delay before the learned State Commission and submitted that as soon as the impugned order dated 24.11.2009 was passed by District Forum, petitioner approached to the concerned Clerk of the Forum and asked about the copy of the order and petitioner was asked by the Clerk that the copy will be served at his registered address and asked him to wait. Petitioner waited for two months, but copy was not received. Again in March 2010, petitioner approached to the Clerk and Clerk shown him dispatch entry about the copy of the order. It was further alleged by the petitioner that he waited till October, but did not receive copy of the order. After that, he suffered typhoid and remained bed ridden for two months and later on applied for certified copy on 16.3.2011 and received it on 18.3.2011 and appeal was filed on 25.3.2011. 5. Perusal of application clearly reveals that petitioner was aware of the order dated 24.11.2009, but he waited for two months for copy of the order and apparently after four months in March 2010, he again contacted Clerk of the Forum, who had shown him dispatch of the copy of the order, but even then he waited till October, 2010 and did not apply for certified copy of the order as free copy was not received by him. He has not filed any document pertaining to suffering by typhoid. As per his application, he remained bed ridden for two months on account of typhoid meaning thereby from November to December, 2010, but he did not apply for certified copy in January, 2011, but applied on 16.3.2011 and there is no explanation for delay in applying certified copy of the order of District Forum. No satisfactory explanation has been given by the petitioner for condonation of delay and learned State Commission has not committed any error in dismissing appeal as barred by 15 months. 6. As there is inordinate delay of 15 months, this delay cannot be condoned in the light of the judgment passed by the Hon’ble Apex Court and the National Commission in (1) (2010) 5 SCC 459 – Oriental Aroma Chemical Industries Ltd. Vs. Gujarat Industrial Development Corporation and Anr.; (2) (2012) 3 SCC 563 – Office of The Chief Post Master and Anr. and (3) 2012 General (2) and Ors. Vs. CPC 3 Living (State Media India Ltd. Commission) – Anshul AggarwalVs. New Okhla Industrial Development Authority. 7. We do not find any illegality, irregularity or jurisdictional error in the impugned order and revision petition is liable to be dismissed. 8. Consequently, revision petition filed by the petitioner in Appeal No. A/11/169 – Nirmal Land Developers & Builders Vs. Rameshchandra Gopalrao Pande is dismissed at admission stage. There shall be no order as to costs. ..………………Sd/-…………… ( K.S. CHAUDHARI, J) PRESIDING MEMBER ..……………Sd/-……………… ( DR. B.C. GUPTA ) MEMBER k NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 863 OF 2013 (From the order dated 09.01.2013 in Appeal No. 243 of 2011 of the Rajasthan State Consumer Disputes Redressal Commission, Circuit Bench, Jodhpur) With IA/1549/2013 (Stay) Trio Elevators Company (India) Ltd. Having its Office at –404, Shivam Complex, Bhuyangdev Cross Road, Sola Road, Ahmedabad, Gujarat …Petitioner/Opp. Party (OP) Versus Tansingh Chauhan S/o Sh. Sujansingh Chauhan Resident of –Gandhinagar, Badmer, Jodhpur …Respondent/Complainant BEFORE HON’BLE MR. JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER HON’BLE DR. B.C. GUPTA, MEMBER For the Petitioner : Ms. Anushree Kapadia, Advocate For the Respondent : Ms. Vidushi, Advocate Mr. R.S. Rana, Advocate PRONOUNCED ON 22nd July, 2013 ORDER PER JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER This revision petition has been filed by the petitioner/opposite party against the order dated 09.01.2013 passed by the Rajasthan State Consumer DisputesRedressal Commission, Circuit Bench at Jodhpur (in short, ‘the State Commission’) in Appeal No. 243 of 2011 – Manager, Trio Elevators Co. (India) Ltd. Vs. Tan SinghChauhan by which, while allowing appeal, order of District Forum allowing complaint was set aside and matter was remanded back to learned District Forum to decide after taking evidence. 2. Brief facts of the case are that complainant/respondent is possessing Hotel Kalinga Palace at Barmer. As per agreement with OP/petitioner, petitioner was to install 3 elevators of the capacity of 8 persons, whereas OP installed elevators of the capacity of 5 persons, which too are not working properly. It was further alleged that on account of delay in completion of work, complainant has suffered loss of Rs.10 lakhs. Alleging deficiency on the part of OP, complainant filed complaint before District Forum and prayed for grant of Rs.10 lakhs as compensation for mental agony and direction to OP to install elevators of the capacity of 8 persons. OP resisted claim and submitted that proper elevators were installed of the capacity of 8 persons and further submitted that agreement between the parties was of commercial nature and District Forum has no jurisdiction and prayed for dismissal of complaint. Learned District Forum after hearing both the parties allowed complaint and directed OP to replace 3 elevators of the capacity of 8 persons instead of 5 persons. Appeal filed by the petitioner was allowed by learned State Commission vide impugned order, but as learned State Commission remanded for disposing the matter after recording evidence; this revision petition has been filed by the petitioner. 3. Heard learned Counsel for the parties at admission stage and perused record. 4. Learned Counsel for the petitioner submitted that, as transaction was of commercial nature and complainant did not fall within the purview of consumer under the C.P. Act, District Forum had no jurisdiction to deal with the complaint. It was further argued that there was no occasion for remand of the matter by learned State Commission, as parties had already placed evidence on record, revision petition be allowed and impugned order be set aside and complaint be dismissed. On the other hand, learned Counsel for the respondent submitted that order passed by learned State Commission is in accordance with law; hence, revision petition be dismissed. 5. Perusal of complaint reveals that as per agreement, petitioner/OP was required to install 3 elevators in the hotel of complainant/respondent. Complainant has nowhere mentioned in his complaint that this hotel was for the purpose of earning of his livelihood by means to self-employment. OP has taken plea in the written statement that, as agreement was for commercial purposes, complainant does not fall within the purview of consumer. Admittedly, 3 elevators were to be installed in the hotel, which is run for commercial purposes and certainly not for the purposes of earning livelihood by complainant by means of self-employment. Learned Counsel for the petitioner has placed reliance on AIR 1999 SC 3356 – Kalpavruksha Charitable Trust Vs. Toshniwal Brothers (Bombay) Pvt. Ltd. & Anr. “9. In the instant case, what is to be considered is whether the appellant was a “consumer” within the meaning of the Consumer Protection Act, 1986 and whether the goods in question were obtained by him for “resale” or for any “commercial purpose.” It is the case of the appellant that every patient who is referred to the Diagnostic Centre of the appellant and who takes advantage of the CT Scan etc. has to pay for it and the service rendered by the appellant is not free. It is also the case of the appellant that only ten per cent of the patients are provided free service. That being so, the “goods” (machinery) which were obtained by the appellant were being used for “commercial purpose”. 6. In the light of above judgment, it becomes clear that complainant does not fall within the purview of consumer under the C.P. Act, as the elevators were to be installed in the hotel run for commercial purposes. In such circumstances, District Forum had no jurisdiction to entertain the complaint and complaint was liable to be dismissed. Learned State Commission has not considered this aspect and remanded the matter and directed District Forum to record expert evidence to be led by both the parties. 7. Learned Counsel for the petitioner submitted that there was no occasion to remand the matter as the parties had already led evidence before District Forum. In support of her contention she has relied on AIR 2002 SC 771 – P. Purushottam Reddy and Anr. Vs. M/s. Pratap Steels Ltd. in which it was held that matter should not be remanded when trial court has recorded finding on all these issues and parties are not pleading prejudice at trial for want of any issue or specific issue or recording of evidence. In the matter in hand, parties filed their evidence before District Forum as they liked and in such circumstances, without any request on the part of any party, learned State Commission should not have remanded the matter for disposal after recording evidence of experts. 7. fall In the light of aforesaid discussion, it becomes clear that, as complainant did not within the purview of consumer under the C.P. Act, complaint was notentertainable before District Forum and complaint was liable to be dismissed. 8. Consequently, revision petition filed by the petitioner is allowed and impugned order dated 09.01.2013 passed by learned State Commission in Appeal No. 243 of 2011 – Manager, Trio Elevators Co. (India) Ltd. Vs. Tan Singh Chauhan is set aside and complaint filed by the complainant/respondent is dismissed. There shall be no order as to costs. ..………………Sd/-…………… ( K.S. CHAUDHARI, J) PRESIDING MEMBER ..……………Sd/-……………… ( DR. B.C. GUPTA ) MEMBER k NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 2370 OF 2010 (From the order dated 28.4.2010 in Appeal No. FA-10/129 of the State Consumer Disputes Redressal Commission, Delhi) M/s. Religare Securities Ltd., Having its registered office at: D-3, P3B, District Center, Saket, New Delhi 110019 …Petitioner/Opp. Party (OP) Versus Mr. Om Singh Deswal 14, Green Avenue Behind Sector D-3, Vasant Kunj New Delhi …Respondent/Complainant BEFORE HON’BLE MR. JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER HON’BLE DR. B.C. GUPTA, MEMBER For the Petitioner : Mr. Rohit Puri, Advocate For the Respondent : Mr. Sanjeev Nirwani, Advocate PRONOUNCED ON 22nd July, 2013 ORDER PER JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER This revision petition has been filed by the petitioner/opposite party against the order dated 28.4.2010 passed by the State Consumer Disputes Redressal Commission, Delhi (in short, ‘the State Commission’) in Appeal No. FA/10/129 – M/s. Religare Securities Ltd. Vs. Om Singh Deswal by which, appeal was dismissed as barred by limitation. 2. Brief facts of the case are that complainant/respondent filed complaint before District Forum for directing OP to compensate loss of Rs.6,07,539/- with interest and Rs.3,00,000/- as mental compensation and Rs.30,000/- as litigation charges. OP was proceeded ex-parte by the District Forum and after hearing complainant, learned District Forum allowed the complaint. Appeal filed by the petitioner before the State Commission was dismissed as barred by limitation. 3. Heard learned Counsel for the parties at admission stage and perused record. 4. Learned Counsel for the petitioner submitted that after restoration of the complaint by District Forum, in absence of petitioner, no fresh notice to the petitioner was given for further proceedings and learned District Forum committed error in proceeding ex-parte and in allowing complaint. It was further submitted that learned State Commission has committed error in dismissing appeal as barred by limitation; hence, revision petition be allowed and impugned order be set aside. On the other hand, learned Counsel for the respondent submitted that order passed by learned State Commission is in accordance with law, which does not call for any interference; hence, revision petition be dismissed. 5. Perusal of record of District Forum reveals that on 19.3.2009, complaint was dismissed in default of the complainant and complainant filed restoration application before the District Forum. Notices were issued to OP/petitioner for 21.5.2009 and on that date, as OP did not appear, restoration application was allowed and simultaneously, OP was proceeded ex-parte and after recording ex-parte evidence, the order allowing complaint was passed by learned District Forum. Petitioner challenged the order dated 21.5.2009 and final order dated 10.7.2009 before Hon’ble Delhi High Court and on 9.12.2009 petitioner did not press prayer with regard to quashing the order dated 10.7.2009 and sought liberty to take appropriate remedy under the law and vide order dated 16.12.2009, writ petition was dismissed being infructuous. 6. By the order dated 21.5.2009, complaint was restored by learned District Forum, which order was upheld by the Hon’ble Delhi High Court; though, as per judgment of the Hon’ble Apex Court in IV (2011) CPJ 35 (SC) – Rajeev Hitendra Pathak & Ors. Vs. Achyut Kashinath Karekar & Anr. , District Forum and State Commission have no power to review its order. 7. Prayer for quashing the final order dated 10.7.2009 was withdrawn by petitioner and Hon’ble High Court allowed that prayer and in pursuance to the order dated 9.12.2009, petitioner filed appeal before the learned State Commission on 10.2.2010 and learned State Commission dismissed the appeal as barred by 30 days. 8. No doubt, appeal should have been filed by the petitioner before the learned State Commission within time and appeal has been filed after 30 days with application under Sections 5 and 14 of the Limitation Act and submitted that after passing of the order by Hon’ble High Court, on account of winter vacations, Counsel of the petitioner went out of station and by the time his counsel returned back, the case slipped out of petitioner’s mind, which caused delay in filing appeal. No doubt, it is not a reasonable ground for condonation of delay, but as ex-parte judgment has been pronounced by learned District Forum against the principles of natural justice without notice to the petitioner, learned State Commission should have condoned delay of 30 days in filing appeal and decided appeal on merits. 9. Notices for 21.5.2009 were issued by learned District Forum only regarding restoration of the complaint and in the absence of OP/petitioner when District Forum allowed restoration application and restored complaint, apparently, District Forum should have issued notices for further proceedings to the OP. Apparently, learned District Forum has committed error and should not have proceeded ex-parte simultaneously with restoration of complaint. 10. In the light of aforesaid discussion, we deem it proper to condone the delay of 30 days in filing appeal before learned State Commission subject to payment of cost of Rs.2000/- to be paid by the petitioner to the respondent and remand the matter back to the State Commission for disposal of appeal on merits. 11. Consequently, revision petition filed by the petitioner against the respondent is allowed and impugned order dated 28.4.2010 passed by learned State Commission in Appeal No. FA/10/129 – M/s. Religare Securities Ltd. Vs. Om Singh Deswal is set aside subject to payment of cost of Rs.2000/- to be paid by the petitioner to the respondent and remand the matter back to the State Commission for deciding appeal on merits after giving opportunity of being heard to both the parties. 11. Parties are directed to appear before the Learned State Commission, Delhi on 12.8.2013. ..………………Sd/-…………… ( K.S. CHAUDHARI, J) PRESIDING MEMBER ..……………Sd/-……………… ( DR. B.C. GUPTA ) MEMBER k NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 2555 OF 2012 (From the order dated 10.04.2012 in Appeal No.1227 of 2010 of the A.P. State Consumer Disputes Redressal Commission, Hyderabad) M/s. Bajaj Alliaz General Insurance Co. Ltd. Through Shri Ashutosh Singh, Dty Manager 2nd Floor, 1, DLF Industrial Estate, Moti Nagar, New Delhi – 110015 …Petitioner/Opp. Party (OP) Versus Mr. K. Eswara Prasad S/o K. Durgaiah Car Driver R/o H. No. 1-86-33, Near CMR Model High School, Sitarampuram, Bowenpally, Hyderabad …Respondent/Complainant BEFORE HON’BLE MR. JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER HON’BLE DR. B.C. GUPTA, MEMBER For the Petitioner : Ms. Manjusha Wadhwa, Advocate For the Respondent : Mr. D. Abhinav Rao, Advocate PRONOUNCED ON 22nd July, 2013 ORDER PER JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER This revision petition has been filed by the petitioner/opposite party against the order dated 10.04.2012 passed by the A.P. State Consumer Disputes Redressal Commission, Hyderabad (in short, ‘the State Commission’) in Appeal No. 1227 of 2010 – Mr. K. Eswara Prasad Vs. M/s. Bajaj Allianz General Insurance Co. by which, while allowing appeal, order of District Forum dismissing complaint was set aside and complaint was allowed. 2. Brief facts of the case are that complainant filed complaint before District Forum and alleged that his car AP-9-TV2927, which was insured by OP/petitioner for a period of one year commencing from 14.10.2007 to 13.10.2008 for a sum of Rs.2,60,000/- was parked by him on 22.6.2008 in front of his house. Complainant locked the car and handed over the keys to the complainant’s neighbour and left for Bangalore due to personal reasons. He had to stay in Bangalore for a longer period and when he returned on 4.10.2008, car was found missing. Complainant immediately lodged FIR, but car could not be traced. Complainant filed claim with the OP, but OP vide letter dated 18.3.2009 closed the claim alleging deficiency on the part of OP. Complainant filed complaint before District Forum. OP resisted claim and alleged that complainant failed to take reasonable steps to safeguard the vehicle and violated Clause IV of the policy and prayed for dismissal of the complaint. District Forum after hearing both the parties dismissed the complaint. Appeal filed by the complainant was allowed by learned State Commission vide impugned order against which, this revision petition has been filed. 3. Heard learned Counsel for the parties at admission stage and perused record. 4. Learned Counsel for the petitioner submitted that since the complainant failed to take reasonable steps to safeguard the vehicle and there was delay of more than 3 months in lodging FIR and intimation to Insurance Company, learned District Forum rightly dismissed complaint and learned State Commission has committed error in allowing appeal; hence, revision petition be allowed and impugned order be set aside. On the other hand, learned Counsel for the respondent submitted that order passed by learned State Commission is in accordance with law, as all reasonable care was taken by the complainant while parking car; hence, revision petition be dismissed. 5. Perusal of record clearly reveals that car was parked by complainant in front of his house on 22.6.2008 and keys and documents of the car were handed over by the complainant to his neighbour. On 4.10.2008 when complainant returned back, he did not find his car and lodged report with the police and intimated to the Insurance Company. This is not clear when the car was actually stolen. Complainant filed his own affidavit before District Forum in which, he admitted that he enquired from his wife, who remained in the house itself and neighbours and then lodged complaint at police station. From this statement it becomes clear that during the period complainant was out of station for more than 3½ months, complainant’s wife was at home. Complainant also filed affidavit of Alkesh Kumar who has stated in his statement that complainant was residing in upper portion of his house and complainant parked his car on 22.6.2008 in front of his house and returned on 4.10.2008 and found that car was missing from that place. He has also not revealed when car was stolen. It appears that purposely no date has been given that when the car was stolen. In such circumstances, it can be presumed that car must have been stolen long back and complainant’s wife and his neighbour Alkesh Kumar must be aware about theft of the car. No report was lodged immediately after theft and report has been lodged by the complainant only after returning back on 4.10.2008. It is also not clear when information to OP regarding theft of car was given by the complainant. Only copy of reminder dated 21.1.2009 issued by OP to petitioner has been placed on record by which, reply was sought from complainant regarding reasonable steps to safeguard the vehicle. It appears that OP was also not intimated immediately. In F.A. No. 321 of 2005 – New India Insurance Co. Ltd. Vs. Trilochan Jane, National Commission dismissed the claim of the complainant on the ground of delay as theft took place on 8.4.2000, but FIR was lodged on 10.4.2000 and intimation to Insurance Co. was given on 17.4.2000. Hon’ble Apex Court in JT 2004 (8) SC 8 – United India Insurance Co. Ltd. Vs. M/s. Harchand Rai Chandan Lal observed that delay in intimation to Insurance Company is fatal. In the case in hand, apparently there is long delay in lodging FIR and intimation to Insurance Company about theft of insured car and in such circumstances, complaint is liable to be dismissed. 6. Complainant’s statement is not believable. When his wife was staying at home, why keys of the car will be given to neighbour instead of his wife. He has not approached District Forum with clean hands and has purposely suppressed date of theft. 7. Consequently, revision petition is allowed and impugned order dated 10.4.2012 passed by learned State Commission in Appeal No. 1227 of 2010 – Mr. K. Eswara Prasad Vs. M/s. Bajaj Allianz General Insurance Co. is set aside and complaint filed by the complainant is dismissed at admission stage with no order as to cost. ..………………Sd/-…………… ( K.S. CHAUDHARI, J) PRESIDING MEMBER ..……………Sd/-……………… ( DR. B.C. GUPTA ) MEMBER k NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 602 OF 2013 (From the Order dated 09.11.2012 in Appeal No. 1460/2011 of U.P. State Consumer Disputes Redressal Commission, Lucknow) With IA/1062/2013 (Stay) Union of India Through its General Manage North Eastern Railway Gorakhpur Petitioner Versus Dr. (Smt.) Shobha Agarwal W/o Dr. M.C. Head of the Department T.B. & Chest B.R.D. Medical College Gorakhpur Respondent BEFORE: HON’BLE MR. JUSTICE AJIT BHARIHOKE, PRESIDING MEMBER HON’BLE MR. SURESH CHANDRA, MEMBER For the Petitioner : Mr. Rajeshwar Singh, Advocate For the Respondent : Mr. Ajit Sharam, Advocate Pronounced on : 22nd July, 2013 ORDER PER SURESH CHANDA, MEMBER This revision petition is directed against the order dated 9.11.2012 passed by the U.P. State Consumer Disputes Redressal Commission, Lucknow in appeal No.1460 of 2011 by which the State Commission upheld the order dated 14.7.2011 passed by the District Forum, Gorakhpur in complaint case No.612 of 1997 and dismissed the appeal filed by the petitioner. The petitioner was the OP before the District Forum and the respondent was the original complainant. 2. The factual matrix of this case are that on 10.10.1996 the complainant/respondent along with her daughter was travelling in a AC second class sleeper with reserved berth Nos.35 & 36 from Gorakhpur to Beena by 1016 UP Kushinagar Express. It is alleged that there was lot of disarrangement in the reserved AC coach and some suspected person was seen snooping here and there about which a complaint was made to the ticket checker but no action was taken by him. The same suspected person was again seen in reserved coach at about 2’O clock in the night. When the complainant woke up at 7’O clock in the morning, she found that her grey colour suitcase which had been tied under the berth with the help of chain and lock, was missing from there. As per the allegation in the complaint, the said suitcase had been stolen by cutting the chain and lock. Information about the said incident was given to the ticket checker who after some initial reluctance received the same after being forced to do so by certain co-passengers but the ticket checker refused to receive the list of the articles. The complainant brought the incident to the notice of the Railway Department and Railway Minister by writing letters to the authorities and it appears that after about one year, the railways lodged an FIR in regard to this incident sometime in the year 1987. Alleging negligence on the part of the OP, the complainant lodged a consumer complaint before the District Forum praying for compensation of Rs.1.5 lakhs along with interest @ 12% w.e.f. 10.10.1996, i.e., the date of loss of the valuables along with Rs.30,000/- by way of compensation on account of mental agony. On notice, the complaint was resisted by the OP and in the written statement filed by the OP, it denied any negligence on its part and also submitted that railway administration is not liable for the goods which were not booked with them. It also raised the question of jurisdiction of the District Forum in the matter. 3. On hearing the parties and appreciating the evidence placed before it, the District Forum allowed the complaint vide its order dated 14.7.2011 in terms of the following directions:“The present of the complainant is accepted against the opposite party. It has been directed to the respondent to pay Rs.1,50,000/- along with interest to the complainant from the date of filing of the application / complaint from the date of filing of the application/complaint till its realization. Besides this, the opposite party to pay Rs.50,000/- towards the compensation account of mental and physical agony and Rs.1000/- towards the costs of the litigation and the said amount is to be given in the shape of demand draft before this forum which could be given to the complainant within one month from the date of passing of the said order. In case the opposite party failed to pay the same within stipulated period of one month, then the same will be recovered from the opposite party as per the law.” 4. Aggrieved by the aforesaid order of the District Forum, the petitioner carried the same before the State Commission by filing an appeal against it but the same was dismissed by the State Commission vide its impugned order which is now under challenge through the present revision petition. 5. We have heard learned counsel Mr. Rajeshwar Singh, Advocate for the petitioner and learned Mr. Ajit Sharma, Advocate for the respondent. Learned counsel for the petitioner has submitted that there was no negligence on the part of the railway administration and unless the goods in question are booked with the railways, the railway administration under the provisions of Railway Act are not liable to pay the compensation. He further submitted that the luggage in question being carried on by the complainant along with her daughter, it was under her custody and it was for her to take care of that. The onus of proof regarding negligence on the part of the railway staff lies on the complainant which she has failed to discharge. 6. Learned counsel has also relied on the provisions of sections 97 and 100 of the Railways Act, 1989 under which the railways cannot be held liable for compensation in this case and the State Commission erred in wrongly appreciating these provisions. Another contention raised by learned counsel was that section 15 of the Railway Claims Tribunal Act, 1987 bars the jurisdiction of the consumer Fora to deal with this case. In view of these aspects, learned counsel submitted that orders of the Fora below cannot be sustained in the eye of law and are liable to be set aside. On the other hand, learned counsel for the respondent submitted that the impugned order is a well-reasoned order passed in accordance with the provisions of law and the same deserved to be maintained and the revision petition be dismissed. 7. We have given our anxious thought to the submissions made by the parties. We may note that the broad facts of this case not being under dispute, the two Fora below have returned their concurrent finding in respect of the allegation of negligence on the part of the petitioner based on the facts placed before them. The order of the State Commission is in line with the judgements of this Commission in similar cases including those of Union of India & Ors. Vs. J.S. Kunwar [1 2010 CPJ 90 (NC)] and Union of India & Ors. Vs. Sanjiv Dilsukhraj Dave & Anr. [2003 CTJ 196 (CP) (NCDRC) and Mrs. Kanthimathi & Anr. Vs. Govt. of India where the liability of the railways in such cases has already been examined established in such cases in the light of the provisions of sections 97 and 100 of the Railways Act. We do not wish to reiterate here the details of these cases except to refer to the observations of this Commission in the case of Sanjiv Dilsukhraj Dave & Anr. (supra) and the same are reproduced thus:“A major responsibility cast on the TTE in addition to examining the tickets is that of ensuring that no intruders enter the reserved compartments…………..This is certainly a gross dereliction of duty which resulted in deficiency in service to the Respondents. The price difference between the unreserved ticket and a reserved ticket is quite high and the traveling public who buy a reserved ticket would expect that they can enjoy the train journey with a certain minimum amount of security and safety. ………. …… One has to presume that passenger would take reasonable care of his luggage. But, he cannot be expected to take measures against intruders getting easily into reserved compartments and running away with goods, when the railway administration is charged with the responsibility to prevent such unauthorized entry. We have entered the 21st century and we cannot carry on our daily life in the same age old fashion with bearing brunt of indifferent service provided by public authorities like Railways. People expect in the 21st century a modicum of efficient and reliable service, which provides at least safety of person and property while traveling in reserved compartments”. 8. Undisputedly, the complainant and her daughter were travelling in a reserved coach and it was the duty of the TTE to ensure that no intruders entered the reserved compartment. Since apparently there was a failure on the part of the TTE to prevent entry of unauthorized person in the coach during the night, the Fora below were right in holding the petitioner liable for deficiency in service to the respondent in this regard. So far as the applicability of section 15 of the Railway Claims Tribunal Act, 1987 is concerned, we cannot agree with the contention of learned counsel because this section bars jurisdiction of the other courts only “in relation to the matters referred to in sub-sections (1) and (1A) of section 13”. Section 13 is reproduced thus:“13. Jurisdiction, powers and authority of Claims Tribunal - (1) The Claims Tribunal shall exercise, on and from the appointed day, all such jurisdiction, powers and authority as were exercisable immediately before that day by any Civil Court or a Claims Commissioner appointed under the provisions of Railway Act,(a) relating to the responsibility of the railway administrations as carriers under Chapter VII of the Railways Act in respect of claims for(i) compensation for loss, destruction, damages, deterioration or nondelivery of animals or good entrusted to a railway administration for carriage by railway ; (ii) compensation payable under Sec. 82-A of the Railways Act or the rules made thereunder; and (b) in respect of the claims for refund of fares or part thereof or for refund of any freight paid in respect of animals or goods entrusted to a railway administration to be carried by railway. [(1-A) The Claims Tribunal shall also exercise, on and from the date of commencement of the provisions of Sec.124-A of the Railways Act, 1989 (24 of 1989), all such jurisdiction, powers and authority as were exercisable immediately before that date by any Civil Court in respect of claims for compensation now payable by the Railway Administration under Sec. 124-A of the said Act or the Rules made thereunder.] (2) The provision of the [Railways Act, 1989] and the rules made thereunder shall, so far as may be, be applicable for inquiring into or determining any claims by the Claims Tribunal under this Act.” 9. Plain reading of section 13 indicates that the case of the respondent does not fall under any of the categories mentioned in the section. In view of this, the jurisdiction of the Consumer Fora cannot be barred by virtue of the provisions of section 15. 10. In view of the foregoing discussion, we do not find any infirmity or jurisdictional error with the concurrent finding of the Fora below which could justify our intervention under section 21(b) of the Consumer Protection Act, 1986. The scope of powers of this Commission while exercising its revisional jurisdiction under section 21(b) of the Consumer Protection Act, 1986 being very limited, we do not find any justification to interfere with the impugned order. We, therefore, dismiss the revision petition in limine with no order as to costs. ……………Sd/-……..……….. (AJIT BHARIHOKE, J.) PRESIDING MEMBER ……………Sd/-….…………… (SURESH CHANDRA) MEMBER SS/ NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 2061 OF 2008 (From the order dated 10.03.2008 in First Appeal No. 1084 / 2007 of Rajasthan State Consumer Disputes Redressal Commission) Examination Controller Maharshi Dayanand Saraswati University Ajmer ... Petitioner Versus 1. Kumari Atia Rasheed d/o Shri Rasheed Ahmed r/o Mehandi Bagh, Patel Circle, Tonk Rajasthan 2.Principal, Government College Tonk Rajasthan … Respondent(s) BEFORE HON’BLE MR. JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER HON’BLE DR. B.C. GUPTA, MEMBER APPEARED AT THE TIME OF ARGUMENTS For the Petitioner(s) Mr. S.K. Bhattacharya, Advocate For the Respondent-1 Mr. Bhopal Singh Gahlani, A.R. For Respondent – 2 NEMO PRONOUNCED ON : 22nd JULY 2013 ORDER PER DR. B.C. GUPTA, MEMBER This revision petition has been filed under section 21(b) of the Consumer Protection Act, 1986 against the impugned order dated 10.03.2008 passed by the Rajasthan State Consumer Disputes Redressal Commission (for short ‘the State Commission’) in Appeal No. 1084/2007 “Examination Controller, Maharishi Dayanand Saraswati University versus Kumari Atia Rashid & Anr.”, vide which, appeal against the order dated 10.04.2007 passed by District Forum, Tonk in consumer complaint no. 33/2007 was ordered to be dismissed. 2. Briefly stated, the facts of the case are that the complainant/respondent no. 1 Atia Rashid had appeared in M.Com. final year examination in 2006, conducted by the petitioner/OP No. 1 against roll number 70771 and deposited the necessary fee etc. When the result of the examination was declared by the petitioner, it was found that in the paper, “Direct and Indirect Taxes”, she had obtained 61 marks, whereas she was expecting 85% to 90% marks in that paper. The complainant requested for revaluation of marks by depositing the necessary fee. However, on revaluation, the marks obtained by her were reduced from “61 to 41”. The petitioner took into account 41 marks in that paper for the purpose of preparing the final result for the complainant. However, the case of the complainant is that since the difference between the marks obtained earlier, i.e., 61, and the marks obtained after revaluation, i.e., 41, was more than 20%, the University should have taken into account the marks obtained earlier, while preparing the final result. The complainant has based her assertion upon Rule 6 B of Ordinance 157 ‘A’ of the University, in support of her arguments. The District Forum vide their order dated 10.04.2007 allowed the complaint and directed the University to pay a sum of Rs.2,000/- to the complainant for mental torture and litigation expenses. The appeal against this order was dismissed by the State Commission vide order dated 10.03.2008. It is against this order that the present revision petition has been filed before us. 3. At the time of hearing before us, the petitioner moved an application for deletion of the name of respondent no. 2, the Principal, Government College, Tonk, and the same was allowed. 4. Learned counsel for the petitioner while arguing the matter, stated that in the instant case, the complainant does not fall under the definition of ‘Consumer’, and hence the proceedings under the Consumer Protection Act are bad in the eyes of law. He invited our attention to judgement of the Hon’ble Apex Court in ‘Bihar School Examination Board versus Suresh Prasad Sinha’ [(2009) 8 SCC 483], in which it has been held that the Board does not provide any service to the examinee and the examination fee paid by an examinee is also not a consideration for providing any service. Any dispute relating to fault in holding of examination or non-declaration of results of an examinee, does not fall within the purview of the Consumer Protection Act. Learned counsel further invited our attention to Rule 6 B of Ordinance 157 ‘A’ of the University saying that if the difference of marks obtained earlier and those obtained after revaluation, is upto 20% of the totalmaximum marks, this rule is applicable and the marks obtained after revaluation are to be counted for preparing the final result. In the instant case, the difference between the marks obtained earlier and those obtained after revaluation is exactly 20% of the total maximum marks and hence the University had rightly taken into account 41 marks for the purpose of preparing the final result. The complaint should, therefore, have been dismissed by the courts below. 5. Learned counsel for the respondent no. 1, however, stated that the Universities are covered under the provisions of the Consumer Protection Act and hence in this case also, she had right to file consumer complaint against the OP. Learned counsel further argued that the change of marks on revaluation from 61 to 41, makes it clear that the difference was more than 20% and hence based on Rule 6 (B), original marks obtained, i.e., 61 should have been taking into consideration for preparing the final result. The orders passed by lower courts were, therefore, as per law and the petition deserves to be dismissed. 6. We have examined the material on record and given a thoughtful consideration to the arguments advanced before us. As mentioned in the revision petition, the rules regarding revaluation are given under Ordinance 157(A) Rule 6(B), which are reproduced as follows:“Ordinance 157 (A) Rule 6(B) (i) In case the marks are increased or decreased upto 20% consequent upon revaluation, full marks secured shall be counted for working out the result. But marks can be decreased to the extent that the result of the candidate will not be affected adversely, the division of the candidate will also not be changed adversely and the candidate will not be declared from pass to fail / supplementary. In such cases the original marks will remain unchanged. (ii) In cases a candidate applies for revaluation in subject(s) in which he had been declared pass, the marks worked out after revaluation will be taking into for working out the result. (iii) In cases a candidate who applies for revaluation in subject in which he was declared supplementary or fail, if after the revaluation the result remains fail or supplementary to supplementary, the result will be declared as no change. (iv) If the difference of the awards of the re-valuator and the original examiner is more than 20% of the maximum marks, the answer books shall be referred to third examiner and average of two nearest awards shall be taking into account and the result will be worked out and declared accordingly.” 7. An examination of the above provisions indicate that there is a mention of 20% of maximum marks in clause (iv), whereas clause (i) mentions only about the increase or decrease upto 20%. Since the words ‘maximum marks’ have not been incorporated in clause (i), the implication is that the percentage mentioned relates to marks obtained only and not the maximum marks. 8. In the instant case, the marks of the candidate upon revaluation have been reduced from 61 to 41 indicating that there was change of more than 20% upon revaluation. Clause (i) talks about the increase or decrease upto 20% only and hence it is not applicable to the present case because the decrease in marks is more than 20% marks. 9. Clause (iii) is also not applicable in the present case because the candidate was not declared fail or was not given supplementary. 10. Clause (iv) is applicable only if the difference of award of revaluator and original examiner is more than 20% of the maximum marks. In the present case the difference is exactly 20% of the maximum marks; hence clause (iv) is also not applicable in the present case. 11. Clause (ii) shows it clearly that if a candidate applies for revaluation in the subject in which he had been declared pass, the marks worked out after revaluation will be taken into account for working out result. It is clear that the clause (ii) is applicable to the facts of the present case and the marks obtained by the candidate after revaluation, i.e., 41 marks are to be taken into account for the purpose of preparing the result. 12. In the light of above discussion, the above petition succeeds and the action taken by the petitioner University is held to be in accordance with the rules and regulations. The revision petition is, therefore, accepted and the orders passed by the State Commission and District Forum are set aside and the action taken by the University is held to be in order. There shall be no order as to costs looking into the facts and circumstances of the case. Sd/(K.S. CHAUDHARI J.) PRESIDING MEMBER Sd/(DR. B.C. GUPTA) MEMBER RS/ NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 3775 OF 2012 (Against order dated 01.06.2012 in First Appeal No. 378/2010 of the H.P. State Consumer Disputes Redressal Commission, Shimla) Suresh Kumar S/o. Sh. Manohar Lal Sharma, R/o. Village & Post Office Rajgarh, Tehsil Sadar, District Mandi, Himachal Pradesh …Petitioner Versus National Insurance Company Ltd. Divisional Office, Himland Hotel Circular Road, Shimla, Himachal Pradesh Through Its Deputy Manager …Respondent AND REVISION PETITION NO. 3776 OF 2012 (Against order dated 01.06.2012 in First Appeal No. 378/2010 of the H.P. State Consumer Disputes Redressal Commission, Shimla) Suresh Kumar S/o. Sh. Manohar Lal Sharma, R/o. Village & Post Office Rajgarh, Tehsil Sadar, District Mandi, Himachal Pradesh …Petitioner Versus National Insurance Company Ltd. Divisional Office, Himland Hotel Circular Road, Shimla, Himachal Pradesh Through Its Deputy Manager …Respondent BEFORE: HON’BLE MR.JUSTICE J.M.MALIK, PRESIDING MEMBER HON’BLE DR.S.M.KANTIKAR, MEMBER For the Petitioner in both cases For the Respondent in both cases : Mr. Kunwar Singh, Advocate : Mr. Abhishek Kumar, Advocate PRONOUNCED ON 23rd JULY, 2013 ORDER PER DR. S.M. KANTIKAR 1. By this order we are disposing of two Revision Petitions No. RP/3775/2012 and RP/3776/2012 filed by Mr. Suresh Kumar, Complainant against the impugned order dated 01.06.2012 passed by State Consumer Disputes Redressal Commission, Shimla, H.P. (in short, ‘State Commission’) in FA/393/2010 filed by National Insurance Company, OP, was allowed in FA/378/2010 filed by the Complainant for increase in the awarded amount, was dismissed. As per order passed in FA/393/2010, Appeal was allowed, which resulted in dismissal of Complaint No.299/2009, dated 07.09.2009 before District Consumer Disputes Redressal Forum, Mandi, Himachal Pradesh (in short, ‘District Forum’). 2. The Complainant is owner of a Swaraj Mazda Tipper Vehicle with registration No.HP33 7445 for carriage of goods. It was insured with the respondent for the sum of Rs.2,00,000/-, for one year during period from 21.04.2008 to 20.04.2009. Said vehicle met with an accident on 06.02.2009, and was extensively damaged. Intimation of the accident was given to the Respondent who assessed the loss through his deputed surveyor. Claim was repudiated by the Respondent on the ground that the person, who was driving the vehicle at the time of the accident, did not possess a valid and effective driving license, in as much as his license was endorsed for driving a ‘light transport vehicle’, whereas, the vehicle, in question, was a ‘medium goods vehicle’, as its gross weight was more than 7500 kilograms. 3. Complainant then filed a complaint before District Forum seeking a direction to the Opposite Party to pay the insurance claim and also to pay damages to the tune of Rs.2,00,000/-. Opposite Party contested the complaint and took the same plea, on which it had repudiated the claim. 4. The District Forum allowed the complaint and directed the Opposite Party to pay 75% of 1,98,000/-, the amount assessed by the surveyor, on total loss basis, i.e. Rs.1,48,500/-, subject to return of salvage and transfer of the registration certificate by the Complainant in favour of the Opposite Party. 5. Aggrieved by the order of District Forum two appeals were filed in State Commission. Complainant filed an appeal No.378/2010 as aggrieved by quantum of insurance claim was filed and the OP filed an appeal No 393/2010 on the grounds that reason for repudiation of claim had been established hence seeking of dismissal of complaint. 6. The State Commission heard counsels of both parties and perused the evidence on record like Registration Certificate of vehicle in question , the driving license. Also referred the Section 2(21) and Section 10(2) of Motor Vehicle Act. According to section 2(21) of the Motor Vehicles Act, “light motor vehicle” means, a transport vehicle or omni bus, the gross vehicle weight of either of which does not exceed 7500.00 kilograms. In the present case, as per registration certificate, the gross weight of the vehicle, in question was 8000.00 kilograms. That means, it was not a ‘light motor vehicle’. Person, who was driving it, was authorized to drive only a light motor vehicle (transport), and therefore, apparently, he did not have the license to drive the vehicle, in question. The State Commission relied upon judgments of this commission Oriental Insurance Company Ltd. v. Ashok Verghese, III (2009) CPJ 73 (NC) and allowed the appeal filed by OP i.e.(FA 393/2010) and dismissed appeal FA 378/2010 filed by complainant. 7. Against the order of State Commission the complainant filed this revision petition. 8. We heard the counsels for both parties. The counsel for petitioner argued that an amendment in the Motor Vehicle Act has been carried out in 1994 and therefore the Section 10(2) has only defined single category of vehicles like Transport Vehicle as per clause (E) of sub- section (2) of Section 10 and therefore, there will not be any differentiation with a person to have a license to drive transport vehicle can drive any type of transport vehicle that is Light Motor Vehicle and Medium or Heavy Motor Vehicle. Therefore, the Section 10(2) which classifies the vehicles for the purpose of grant of license does not clarify about Heavy or Medium Motor Vehicle. 9. The Ld. Counsel for the Complainant brought our attention to the decision of his own State Commission in FA No. 108/2010 Mubarak Singh Vs. The Oriental Insurance Company decided on 11.08.2010; as per order the Complainant was entitled to least 75% of the amount as assessed by the Surveyor. We relied upon another judgment of Hon’ble Apex Court in the case titled Amalendu Sahoo Vs. Oriental Insurance Co. Ltd. II (2010) CPJ-9 (SC) and held that if a driver holding a driving license to drive a light transport vehicle but driving a medium goods vehicle, it would be a case of breach of the terms/conditions and warranties including “limitation as to use” and the insured will be entitled to 75% of the Amount assessed by the Surveyor. The relevant portion of the aforesaid portion judgment reads as under: “4. Now coming to the alternate submission urged on behalf of the appellant. Suffice it to say in this behalf that this question need not detain us in the light of the decision of the Hon’ble Supreme Court in the case of Amalendu Sahoo Vs. Oriental Insurance Co. ltd. (supra), relied upon by Mr. Thakur in support of his Alternate submission. As according to us, driver holding the driving license whereby he was licensed to drive a L.T.V., whereas he was driving a Medium Goods Vehicle, would be a case of breach of any of the terms/conditions and warranties including limitation as to use. Therefore, we are of the view that the appellant is entitled to Rs. 4,20,750/- being 75% of the amount assessed by the surveyor who is an independent expert appointed by the appropriate authority for assessing the loss. Once this conclusion is arrived at, then there us no escape but for allowing this appeal. Order accordingly.” 10. We put more reliance upon the judgment of Hon’ble Apex Court Amalendu Sahoo Vs. Oriental Insurance Co. Ltd. II (2010) CPJ-9 (SC) which prevails over the judgment of this commission in case Oriental Insurance Company Ltd. v. Ashok Verghese, III (2009) CPJ 73 (NC). Hence, the State Commission is not justified to give preference to the judgment passed by this Hon’ble Commission by surpassing the judgment delivered by the Hon’ble Apex Court. It was held that a breach of driving clause in the basis of guidance/notification issued by the Insurance Company while dealing with own damage matter has directed to settle the claim of the insured on non-standard claim basis which means the 75% of the insured amount. 11. On perusal of Surveyor report placed by OP on record clarify that he has assessed the loss on repair basis at Rs.1,97,268/- on total loss basis at Rs.1,98,000/- and on the net of salvage basis Rs.1,23,000/-. Since the Insured Declared Value of the vehicle is Rs.2,00,000/-. In the interest of justice we are of considered view that claim should be settled on total loss basis at Rs.1,98,000/- as assessed by the Surveyor; accordingly the complainant is entitled to 75% of this amount. 12. With reference to aforesaid discussion, we set aside the order passed by State Commission in F.A.393/2010 and F.A.373/2010 and restore the order of District forum. We allow these revision petitions. No order as to costs. …..………………………… (J. M. MALIK, J.) PRESIDING MEMBER .…..…………… …………… (Dr. S. M. KANTIKAR) MEMBER MSS/5-6 NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 2251 OF 2008 (From the order dated 29.02.2008 in FA No. 1042/07 @ MA 1389/07 of Maharashtra State Consumer Disputes Redressal Commission) Chandrakant S. Kothari Ruby Apartment, Mahavir Nagar, Dahanukar Wadi, Kandivali (West) ... Petitioner Versus 1. Dean, Sir Hurkirondas Norrotumdas Hospital & Research Centre Padamshir Gordhanbega Chowk, Raja Rammohan Roy Marg, Mumbai 2. Dr. Nitul Parikh Hospital & Research Centre Padamshir Gordhanbega Chowk, Raja Rammohan Roy Marg, Mumbai … Respondent(s) BEFORE HON’BLE MR. JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER HON’BLE DR. B.C. GUPTA, MEMBER APPEARED AT THE TIME OF ARGUMENTS For the Petitioner(s) Mr. A.K. Panigrahi, Advocate For the Respondent(s) Mrs. Pankaj Bala Varma, Advocate PRONOUNCED ON : 23rd JULY 2013 ORDER PER DR. B.C. GUPTA, MEMBER This revision petition has been filed under section 21(b) of the Consumer Protection Act, 1986 by the petitioner against the impugned order dated 29.02.2008 passed by the Maharashtra State Consumer Disputes Redressal Commission (for short ‘the State Commission’) in FA No.1042/2007, “Sir Hurkisondas Narrotumdas Hospital & Research Centre versus Chandrkant S. Kothari” vide which the order dated 26.06.2007 passed by District Consumer Disputes Redressal Forum, Mumbai in complaint no. SMF/MUM/98/2003 was set aside. The District Forum vide that order had allowed the complaint filed by the petitioner / complainant and ordered the respondents / OPs 1 & 2 to pay a sum of Rs.5 lakh severally and jointly to the complainant within one month along with interest @9% p.a. till final payment with effect from 4.4.2003 and also pay a sum of Rs.5,000/- to the complainant for mental harassment and cost of the litigation. 2. Briefly stated, the facts of the case are that Ms. Chandrakant Vora, who was daughter of present complainant was admitted in OP hospital on 10.04.2001 for the treatment and surgery of “Infertility Chocolate Cyst of the Ovary”. She was operated upon by Dr. S.S. Sheth in the hospital on 11.4.2001. It has been stated that the patient was alright after the surgery, but she developed post-operative complications with effect from 12.04.2001. She had complaints of vomiting along with diarrhoea and breathlessness. She had patches and swelling on the body and darkness on face and legs. She was unable to pass urine. The complainants have alleged that on 12.04.2001, no doctor examined the patient from 11:00 AM to 5:30 PM and no medical treatment was given to her during this period. It has been alleged that because of the negligence of the hospital and the doctors, the patient died because of septicaemia on 20.04.2001. The complainant, father of the deceased, filed a consumer complaint before the District Forum which was allowed by the said fora on 26.06.2007 as stated in the preceding paragraph. The OPs filed an appeal against this order before the State Commission, which was allowed vide impugned order and the order of the District Forum was set aside and the complaint was dismissed. It is against this order that the present revision petition has been filed. 3. Heard the learned counsel for the parties and examined the record. 4. Learned counsel for the petitioner narrated the facts of the case and stated that the hospital has shown grave negligence by not attending to the patient from 11:00 AM to 5:30PM on 12.04.2001. No doctor attended to the patient during this period, because of which the condition of the patient deteriorated and she developed septicaemia which is a highly infectious disease, resulting in blood poisoning. Learned counsel has drawn our attention to the synopsis attached with the revision petition in which it has been stated that as per medical literature, the probable causes for developing septicaemia could be as follows:- i) ii) Invasive Procedures or devices Indwelling urinary catheter iii) Diverticutitis, perforated viscus 5. Learned counsel maintained that it was a case of sheer medical negligence at the post-operative stage which led to the death of the patient. 6. Learned counsel for the respondent, however, denied that the patient was not properly attended to by the hospital on 12.04.2001. She stated that the patient was properly attended and medications / injections were also given to her. She was examined by all senior doctors and even taken to the Intensive Care Unit (ICU). She stated that in cases of surgery, septicaemia may develop in the patients and it was wrong to state that this condition developed due to any negligence by the doctors or hospital. She further stated that if the attending doctors performed their duties as per the normal procedures, no medical negligence can be attributed to them. 7. A perusal of the record of the case indicates that the impugned order has been passed by the State Commission after careful examining the relevant papers of the hospital. It has been observed by the State Commission that these case-papers had come from the custody of the complainant. The entries in the case-papers show that the opposite party examined patient at 7:00 AM on 12.04.2001 and oral medicines / injections were also administered. The patient was seen by Dr. Priya, Gynaecologist on 12.04.2001 and she had no complaints. Another injection was given for fever at 12:00PM on 12.04.2001. The patient was seen by gynaecologist house surgeon at 5:30PM on 12.04.2001 and at that time they noticed breathlessness and side shoulder pain. The case was also discussed with operating surgeon Dr. S.S. Sheth and the patient was also referred to other medical specialists. The patient was sent to ICU where the treatment was monitored by Dr. Rajesh Sharma, MD (Medicine) who is a critical care specialist. The State Commission has observed that all possible care was taken by the Hospital to save the life of the deceased. 8. The State Commission have also referred to Bolam test as stated in the case of “Bolam versus Friern Hospital Management Committee [(1957) 2 AII.E.R. 118 McNair J.] The following are the important features in the said case:“(i) A doctor is not negligent, if he has acted in accordance with a practice accepted as proper by a responsible body of medical men skilled that particular art…. Putting it the other way round, doctor is not negligent, if he is acting in accordance with such a practice, merely because there is a body of opinion that takes a contrary view. At the same time, that does not mean that a medical man can obstinately and pig-headedly carry on with some old technique contrary to what is really substantially the whole of informed medical opinion. (ii) When a doctor dealing with a sick man strongly believed that the only hope of cure was submission to a particular therapy, he could not be criticised if, believing the danger involved in the treatment to be minimal, did not stress them to the patient. (iii) In order to recover damages for failure to give warning the plaintiff must show not only that the failure was negligent but also that if he had been warned he would not have consented to the treatment.” 9. Further the Hon’ble Supreme Court in the case of “Indian Medical Association versus V.P. Shantha” [III (1995) CPJ 1 (SC) = 1995 (6) SCC 651] has observed as under: “The approach of the Courts is to require that professional men should possess a certain minimum degree of competence and that they should exercise reasonable care in the discharge of their duties. In general, a professional man owes to his client a duty in tort as well as in contract to exercise reasonable care in giving advice or performing services.” 10. From the entire factual matrix of the case, it becomes clear that there is no doubt that the patient developed post-operative complications in the Hospital which led to septicaemia resulting in her death after few days, but the charge of medical negligence on the part of Doctors or the hospital is not established on any account. The patient has been handled and treated by the concerned specialists and they did their best to save her life. 11. In view of these facts, it is held that the State Commission have committed no illegality, irregularity or jurisdictional error in passing the impugned order. The said order is upheld and the present revision petition is dismissed with no order as to costs. Sd/(K.S. CHAUDHARI J.) PRESIDING MEMBER Sd/(DR. B.C. GUPTA) MEMBER RS/ NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 3265 OF 2011 (Against the order dated 22.07.2011 in Appeals No.5000/2010, 534/2011 & 1156/2011 of the Karnataka State Consumer Disputes Redressal Commission, Bangalore) B.T. Shivaprasad S/o Shri B.S. Thippeswamy Residing at No.407, 14th Cross 2nd Stage, 2nd Phase, West of Chord Road Mahalakshmipuram Bangalore-560086 … Petitioner Versus President/Vice President/Secretary Vyalikaval House Building Cooperative Society Ltd. No.100, 11th Cross, Malleswaram Bangalore-560003 … Respondent BEFORE: HON'BLE MRS. VINEETA RAI, PRESIDING MEMBER HON’BLE MR. VINAY KUMAR, MEMBER For the Petitioner : Mr. B.T. Shivaprasad, Petitioner-in-person For the Respondent : NEMO Pronounced : 23rd July, 2013 ORDER PER VINEETA RAI, PRESIDING MEMBER 1. Petitioner-in-person was present on 18.07.2013 when the orders were reserved in this matter. Counsel for Respondent, who was present on the last date of hearing i.e. on 02.05.2013 and was aware that the case was to come up on 18.07.2013, was not present. 2. Briefly stated, the facts of the case are that the Petitioner/Complainant had become a member of the Opposite Party/Society, Respondent herein, with a view to own a residential site and had paid a sum of Rs.21,050/- on various dates from 21.04.1985 to 23.01.1999. The total value of the site was Rs.54,000/-. There was no progress in the allotment of the site and also despite contacting the Opposite Party/Respondent through letters there was no response. Being aggrieved Petitioner/Complainant filed a complaint before the District Forum. District Forum directed the Opposite Party/Respondent to pay Rs.20,900/- to the Petitioner/Complainant with interest at the rate of 12% per annum from the respective dates of payment till actual payment as also compensation of Rs.2,00,000/- towards sufferings and deprivation of the site in Bangalore alongwith Rs.5000/- as costs. In the cross-appeals filed before the State Commission by both the Petitioner/Complainant and the Opposite Party/Respondent, the State Commission modified the order of the District Forum by setting aside the direction as to compensation of Rs.2,00,000/- by observing as follows :“10. This Commission in the earlier cases has taken a decision following the decision of the Hon’ble Supreme Court and the National Commission that the complainants are not entitled for both compensation and interest. The District Forum while allowing the complaint of the complainant has directed to refund the amount of Rs.20,900/- with 12% (interest) pa from the date of respective dates of payment till actual payment. But the complainant in his appeal No.5000/10 sought for enhancement of both compensation and interest.” The State Commission further directed that interest be enhanced from 12% to 18% per annum on the refunded amount of Rs.20,900/- alongwith payment of costs of Rs.5000/-. 3. The present appeal has been filed by the Petitioner seeking restoration of compensation of Rs.2,00,000/- awarded by the District Forum. 4. We have heard the submissions made by the Petitioner-in-person and have also gone through the evidence on record. We agree with the order of the State Commission that the Petitioner/Complainant is not entitled to both compensation and interest. This view has been taken by us in Mohit Bindal V. Haryana Urban Development Authority (First Appeal No. 173 of 2008) and New India Assurance Co. Ltd. V. Tauseful Hassan & Anr. (Revision Petition No. 91 of 2009). In the latter case, this Commission had observed as follows :“The complainant cannot be given double benefit of compensation as well as interest on the insured amount. Interest be taken as by way of compensation.” Therefore, the order of the State Commission is in accordance with our own orders on the subject. 5. In view of the above, we see no reason to interfere with the order of the State Commission, which is upheld. The revision petition is dismissed. Opposite Party/Respondent is directed to refund the sum of Rs.20,900/- with interest at the rate of 18% per annum from the respective dates of payment till actual payment with Rs.5000/as costs within a period of four weeks from the date of receipt of copy of this order. Registry is directed to send a copy of this order to the Opposite Party/Respondent immediately. Sd/(VINEETA RAI) PRESIDING MEMBER Sd/(VINAY KUMAR) MEMBER Mukesh NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO.2273 OF 2012 (From the order dated 03.04.2012 in First Appeal No.A/09/1082 of the Maharashtra State Consumer Disputes Redressal Commission, Mumbai) DR. CHANDRAKANT VITTHAL SAWANT, PATEL RESIDING AT: 6, SHRI MATRUCHAYA, SANT MUKTABAI MARG, VILE PARLE (EAST), MUMBAI-400 057, MAHARASHTRA STATE ..…. PETITIONER Versus 1. SHRI L.R. PILANKAR INSPECTOR OF LAND RECORDS, DEPARTMENT OF LAND RECORD OF MAHARASHTRA STATE, TALUKA/MALVAN, AT & POST MALVAN, DISTRICT: SINDHUDURG-416 606. 2. SHRI R.S. MALANKAR SURVEY OFFICER, DEPARTMENT OF LAND RECORDS OF MAHARASHTRA STATE, TALUKA/MALVAN, AT & POST MALVAN, DISTRICT: SINDUDURG 416606 ..... RESPONDENTS BEFORE: HON'BLE MR.JUSTICE AJIT BHARIHOKE, PRESIDING MEMBER HON’BLE MR.SURESH CHANDRA, MEMBER For the Petitioner : In person PRONOUNCED ON: 23rd JULY, 2013 ORDER PER SURESH CHANDRA, MEMBER This revision petition is directed against the order dated 03.04.2012 passed by the State Consumer Disputes Redressal Commission, Maharashtra, Mumbai in F.A. No.A/09/1082 by which the State Commission disposed of the appeal filed by the petitioner challenging the order dated 07.08.2009 of the Sindhudurg District Consumer Forum in Complaint no.24/2009 dismissing the complaint of the petitioner asking him to approach Civil Court or other suitable Appellate Court within the prescribed time. 2. The facts of this case leading to filing of the present revision petition are that the petitioner who is the original complainant approached the respondents on 19.04.2007 requesting for urgent measurement of his land (S.No.234/P.H. No. 1A & 1B) and paid a fee of Rs.2,000/- for the purpose. The first measurement was arranged on 18.07.2007 but when the petitioner reached the place, he found that the procedure had been cancelled because of the rains. It was rescheduled for 15.02.2008 and when the procedure was completed, the petitioner was advised to collect the map in 15 days. It is alleged that thereafter in spite of repeated attempts the petitioner failed to get the map and hence he sent an application to the respondent authority on 11.05.2008. On 16.07.2008, the complainant was informed that re-measurement of the land was done on 15.07.2008. Thereafter, on 20.07.2008, the petitioner/complainant made complaint to the Superintendent of Land Records and measurement of land was rescheduled for the fourth time on 20.08.2008 and again got cancelled. He was also informed that the land will not be divided for the time being and the application of the complainant was cancelled. He also thereafter applied under the RTI Act on 15.09.2008 but was denied the required data. Feeling harassed on account of repeated cancellation of the measurement and the delay involved as also the refusal of the respondents to give the map, the complainant filed a consumer complaint before the District Forum asking for compensation. 3. The complainant filed affidavit in support of his allegations. The respondents/OPs contested the complaint and filed their affidavits refuting the allegations of the complainant. The District Forum after considering the evidence and hearing the parties, dismissed the complaint holding that even though fees has been paid by the complainant for the job requested to be done by the respondents, the land measurement to be done by the respondents as per the request of the complainant is a sovereign function and hence, the complaint is not maintainable. The District Forum, therefore, dismissed the complaint in terms of the aforesaid order which was challenged through an appeal before the State Commission which disposed it of as stated above. 4. We have heard the petitioner who has argued his case himself and perused the record. 5. We may note that the appeal of the complainant against the dismissal of the complaint on the ground of maintainability under the Consumer Protection Act has been disposed of by the State Commission by a brief order, which may be reproduced as under:“Adv. Rajendra Pai is present on behalf of the Appellant. Adv. Dipak Atmaram Andhari is present on behalf of the Respondents. Respondent No.1 namely – Mr. L. R. Pilankar, in person is present. In view of the fact that the Respondent no.1 has ultimately measured the land and the report has been submitted a copy of which is already given to the Appellant pursuant to the direction given by this Commission we now think that purpose of filing of this appeal is over and we record statement of the Respondent No.1 that henceforth he will be helping all the consumers in like fashion we dispose of the appeal. No order as to costs. Inform the parties accordingly.” 6. Since the State Commission has simply disposed of the appeal without touching upon the question of maintainability of the complaint against the respondents who have claimed to be government servants discharging sovereign function, two issues have arisen for our consideration in the present revision petition, namely, whether the District Forum was right in holding the function of the respondent authority in carrying out measurement on paying of fees and supplying a map after the measurement as a sovereign function and hence, rejecting the complaint as not maintainable under the Consumer Protection Act and if not, whether the complainant is entitled for any compensation as prayed for by him in the given facts and circumstances of this case. 7. So far as the issue regarding the claim of the respondents discharging sovereign function as government servants is concerned, we do not agree with the view taken by the District Forum while rejecting the complaint. No doubt both the respondents are government servants and were carrying out their functions in their official capacity. However, carrying out of measurement of land for payment of prescribed fees as per the application made by the petitioner before the respondents cannot be regarded as a sovereign function. This is part of their administrative functions which they were required to perform for a prescribed fee. This function, therefore, cannot be called a ‘sovereign function’. This view is in line with the judgment of this Commission dated 08.07.2002 in the case ofShri Prabhakar Vyankoba Aadone v. Superintendent Civil Court [R.P. No.2135 of 2000/19862004 Consumer 7211 (NS)] on which reliance has been placed by the petitioner. It was held in this case that while judicial officers may be protected from being arrayed in legal proceedings for their judicial function, they do not enjoy immunity for the administrative functions performed by them or by their staff and as such the grant of certified copies of orders of courts is not a sovereign function but is an administrative function. It was also held that since this is not a judicial function, it does not partake the character of a ‘sovereign function’. It was also held by this Commission in that case that an applicant for certified copy of a judicial order, who deposits a fee for obtaining such copy is a “Consumer” within the meaning of the Consumer Protection Act, 1986 and the processing of such application and the preparation and delivery of the copy in consideration of the copying charges/fee by the concerned staff attached to the court would be a service within the meaning of the Act. We find that the ratio of this case is squarely applicable to the present case where the petitioner had approached the respondent authority for carrying the measurement of the land in question and for which purpose the applicant had paid the requisite fees to the respondents. In this circumstances, the petitioner is a consumer within the meaning of the Consumer Protection Act qua the functions discharged by the respondents since these functions of the respondents while dealing with the application of the petitioner for measurement of the land would constitute service. 8. In view of the above position, we have to examine whether the State Commission was right in simply disposing of the appeal after noting that the measurement had been carried out and report thereof had already been submitted or whether the petitioner is entitled for any compensation for the alleged harassment and delays suffered by him. In this context, we have perused the affidavits of both the respondents no.1 and 2. The respondent no.2 being Junior Officer Incharge of Survey under the control of respondent no.1, who is Inspector of Land Records, the submissions made by the respondent no.1 in his affidavit before the District Forum, are more relevant. He has stated on oath the circumstances in which the delay took place and the measurement dates had to be changed for reasons beyond their control. The following points brought out by respondent no.1 in his affidavit before the District Forum explain the situation appropriately and hence the same are reproduced thus:“1. In the matter of land measurement, until the final decision is reached, the map cannot be given to the applicant. In the current problem due to objection raised, the decision was delayed. For this reason Shri Sawant could not be given the map. 2. In measuring pothissa, all co-farmers have to show their share of land under occupation and the old boundaries. During the measurement done on 15/02/2008, only Shri Sawant was present. His co-farmers were absent to show their share of land. Unless their share was confirmed, the decision could not be made. This delayed the final outcome. 3. Shri V.V.Rane is heir to the property of late V.S. Rane. On objection raised by Shri V.V.Rane on 09/06/2008 the higher office ordered enquiry on 20/08/2008. During inquiry unlike shown on 15/02/2008, Shri Sawant seems to have his share of land in two separate pieces. Therefore measurements done on 15/02/2008 were cancelled. Hence complaint by Shri Sawant is false, mischievous and misleading. 4. On 20/08/2008, Shri Sawant & co-farmer Shri Rane settled the matter and requested to keep land temporarily in “ status qua’’ and signed the agreement in presence of witnesses. Therefore complaint by Shri Sawant is false, mischievous and misleading. 5. The complainant has intentionally given false information and addresses of his co-farmers. Shri V.S. Rane was dead and his heir Shri V.V. Rane raised objection. Thus map could not be given to complainant. 6. The objection to land measurement was sent by Shri Rane to Supdt Land Records at Sindhudurg. Hence Shri Sawant could not be given its copy under R.T.I. (2005). Since Shri Sawant is insisting that there was no objection, the copy of Rane’s objection was obtained from office of Supdt Land Records on 29/11/2008 and Shri Sawant was asked to collect it from me on 05/03/2009. 7. Shri Rane’s objection was lying in the office of Supdt Land Records, Sindhudrg. My report of inquiry of that no objection was sent to the office of Superintendent on 28/08/2008. 8. The reply given to Shri Rane and Shri Sawant and list of witnesses is kept on record.” 9. The petitioner has not denied any of the aforesaid averments made by respondent no.1 in his affidavit. It is also not under dispute that the measurement in question has already been carried out and report to that effect has been given to the petitioner in pursuance of the directions given by the State Commission. In the circumstances, we cannot hold the respondents liable for deficiency in service which would justify any compensation as such. No doubt the dates of the measurement were postponed and delay took place but apparently there were reasons for the same which could not be helped. The petitioner needs to keep in mind that although he is a consumer and the respondents have rendered a service to him while processing and dealing with his application for measurement of land, his being consumer does not necessarily entitle him to get compensation unless the delays involved could be regarded as deficiency in service. In this view of the matter, while we set aside the order of the District Forum and hold the petitioner as a ‘Consumer’ within the meaning of the Consumer Protection Act, 1986, there is no case for compensation as prayed for by him in his complaint. The revision petition is, accordingly, disposed of with these observations with no order as to costs. 10. While on the subject, we wish to make it clear that since the respondents like any other government servants discharged their functions in their official capacity, no liability for deficiency in service could have been fastened on them by name and as such, the complaint would not be maintainable against them individually but only by their designation. However, this aspect loses its relevance at this belated stage when this complaint has already completed its journey upto the present revision petition, which is now disposed of as above. ……………sd/-……..……….. (AJIT BHARIHOKE, J.) PRESIDING MEMBER ……………sd/-….…………… SURESH CHANDRA) MEMBER bs NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 2910 OF 2008 (From the order dated 28.02.2007 in Appeal No.252 of 2006 of the Jharkhand State Consumer Disputes Redressal Commission, Ranchi) Sri Tapas Kumar Roy S/o Late Shankar Kr. Roy, R/o Quarter No. E-13, C.C.W.O. Colony P.O. & P.S. Saraidhela, Dhanbad, Jharkhand … Petitioner/Complainant Versus 1.The General Manager, BSNL, Dhanbad, Jharkhand 2.Accounts Officer, Telecom Department B.S.N.L. Dhanbad Jharkhand … Respondents/Opp. Parties (OP) BEFORE HON’BLE MR. JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER HON’BLE DR. B.C. GUPTA, MEMBER For the Petitioner : NEMO For the Respondents : Mr. Pavan Kumar, Advocate Mr. Prithivi Pal, Advocate PRONOUNCED ON 23rd July, 2013 ORDER PER JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER This revision petition has been filed by the petitioner/complainant party against the order dated 28.02.2007 passed by the Jharkhand State Consumer DisputesRedressal Commission, Ranchi (in short, ‘the State Commission’) in Appeal No. 252/2006 – General Manager, BSNL Vs. Sri Tapas Kumar Roy by which, while allowing appeal, order of District Forum allowing complaint was set aside. 2. Brief facts of the case are that petitioner/complainant filed complaint before District Forum in respect of telephone bills dated 11.4.2003, 11.6.2003, 11.8.2003, 11.10.2003, 11.12.2003 and 11.2.2004 in respect of landline telephone no. 03262201457 and alleged that bills were too excessive and inflated and telephone connection was disconnected in March, 2004 without rectifying those bills. OP/respondent contested the matter and submitted that there was no technical fault in the metering equipment during the relevant period; hence, complaint be dismissed. District Forum after hearing the parties, allowed complaint and directed OP to issue revised telephone bills on the basis of average 5 previous bills. Appeal filed by the OP was allowed by learned State Commission vide impugned order against which, this revision petition has been filed. 3. None appeared for the petitioner even in second round. Heard learned Counsel for the respondents and perused record. 4. Petitioner filed complaint regarding excessive and inflated 6 telephone bills pertaining to his landline telephone. Learned Counsel for the respondent submitted that Consumer Forum has no jurisdiction in the matter in the light of judgment of Hon’ble Apex Court in – 2009 (12) SCALE – General Manager, Telecom Vs. M. Krishnan & Anr.; hence, revision petition be dismissed. 5. It is admitted case of the complainant that he filed complaint on the basis of inflated telephone bills. In the aforesaid judgment, Hon’ble Apex Court held that when there is a special remedy provided in Section 7-B of the Indian Telegraph Act regarding disputes in respect of telephone bills, then the remedy under the Consumer Protection Act is by implication barred. In the light of aforesaid pronouncement of Hon’ble Apex Court, District Forum had no jurisdiction to entertain complaint and learned State Commission has not committed any error in allowing appeal and dismissing complaint, though, on other grounds. 6. Consequently, revision petition filed by the petitioner is dismissed with no order as to costs. ..……………Sd/-……………… ( K.S. CHAUDHARI, J) PRESIDING MEMBER ..…………Sd/-………………… ( DR. B.C. GUPTA ) MEMBER k NATIONAL CONSUMER DISPUTES REDRESAL COMMISSION NEW DELHI REVISION PETITION NO. 2509 OF 2013 (From the order dated 25.04.2013 in S.C. Case No.: FA/448/2012 of the West Bengal State Consumer Disputes Redressal Commission, Kolkata) Smt. Alaka Roy W/o Tapan Kumar Roy E-2, Tagore Park, Laskarhat P.O. – Tiljala P.S. – Kasba Kolkata – 700039 …Petitioner/Complainant Versus 1.Om Tara Maa Construction Block E-6, Tagore Park Main Road, P.O. – Tiljala, P.S. – Kasba, Kolkata – 700 039 2.Mr. Santanu Kanjilal S/o Gouranga Kanjilal, one of the Partner Representing M/s. Om Tara Maa Construction Residing at – 149F, Picnic Garden Road, P.O. & P.S. – Tiljala, Kolkata – 700 039 3.Mr. Sanjib Das S/o late Sankar Ch. Das, one of the Partner Representing M/s. Om Tara Maa Construction Residing at E-6, Tagore Park Main Road, P.O. – Tiljala, P.S. – Kasba Kolkata – 700 039 … Respondents/Opp. Parties (OP) BEFORE HON’BLE MR. JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER HON’BLE DR. B.C. GUPTA, MEMBER For the Petitioner : Mr. G. Ghoshal, Auth. Representative PRONOUNCED ON 23rd July, 2013 ORDER PER JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER This revision petition has been filed by the petitioner/complainant against the order dated 25.4.2013 passed by the West Bengal State Consumer Disputes Redressal Commission, Kolkata (in short, ‘the State Commission’) in S.C. Case No. FA/448/2012 – Om Tara Maa Construction & Ors. Vs. Mrs. Alaka Roy by which, while allowing appeal partly, order of District Forum allowing complaint was partly set aside. 2. Brief facts of the case are that complainant/petitioner filed complaint before learned District Forum and alleged that OP/respondent delayed delivery of possession of the flat by 4 months and failed to construct the flat with standard and good quality of materials. It was further alleged that OP is guilty of not paying electric charges amount Rs.1,120/- and have also failed to handover clearance certificate, fit certificate, soil test report and other documents. OP contested complaint and submitted that delay in delivery of possession was not intentional, but beyond control of OP and construction is as per standard and prayed for dismissal of complaint. Learned District Forum after hearing parties, allowed complaint and directed OP to pay Rs.5,000/- for delayed possession, Rs.9,000/- for rent for 3 months along with Rs.1,00,000/- as compensation and Rs.3,50,000/- towards cost and expenses for proposed construction and Rs.2,000/as cost, totalling Rs.4,66,000/-. OP filed appeal before learned State Commission and learned State Commission vide impugned order partly allowed appeal and set aside order of awarding compensation of Rs.3,50,000/- towards cost and expenses for proposed construction against which, this revision petition has been filed. 3. Heard Authorized Representative for the petitioner at admission stage and perused record. 4. Authorized Representative of the petitioner submitted that learned District Forum rightly allowed Rs.3,50,000/- as cost and expenses for plastic paints and learned State Commission vide impugned order has committed error in modifying order of District Forum; hence, revision petition be admitted. 5. Perusal of record reveals that complainant has claimed Rs.3,50,000/- as compensation for proposed cost and expenses for the plastic paint of the floor and for the grill and doors. 6. Perusal of agreement for joint venture reveals that plastic paint was to be provided inside the wall. This agreement nowhere depicts that plastic paint was to be provided on the floor, grill and doors. Learned State Commission rightly observed as under: “But so far as it relates to awarding of compensation in favour of the complainant in respect of the proposed construction, we are of the considered opinion that since there is no adequate and sufficient material on record in this regard in respect of the complainant’s case and regard being had to the fact that the complainant has not been able to produce cogent and reliable evidence in support of her case of failure on the part of the OPs to effect proposed construction, we think it was not just and proper on the part of the Ld. District Forum to award a sum of Rs.3,50,000/- in favour of the complainant”. 7. We do not find any illegality, irregularity or jurisdictional error in the impugned order and revision petition is liable to be dismissed at admission stage. 8. Consequently, revision petition filed by the petitioner is dismissed at admission stage with no order as to costs. ..………………Sd/-…………… ( K.S. CHAUDHARI, J) PRESIDING MEMBER ..…………Sd/-………………… ( DR. B.C. GUPTA ) MEMBER k NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 2788 OF 2012 From the order dated 17.4.2012 in M.A. No. 170/2011 in Appeal No. 91/2011 of the H.P. State Consumer Disputes Redressal Commission, Shimla) The Managing Director, H.P. State Cooperative Housing Federation, Shimla – 171009 … Petitioner/Complainant ` Versus 1.Shri Gian Chand S/o Sh. Sohnu Ram, Ward No. 1, Krishna Nagar,’ Hamirpur 2.The Hamirpur Cooperative House Building Society Ltd., Hamirpur, through its President … Respondents/Opp. Parties (OP) BEFORE HON’BLE MR. JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER HON’BLE DR. B.C. GUPTA, MEMBER For the Petitioner : Mr. H.S. Upadhyay, Advocate For the Respondent No. 1 : Mr. Santosh Kumar, Advocate Mr. Sunil Kumar, Advocate For the Respondent No. 2 PRONOUNCED ON : Ex-parte 23rd July, 2013 ORDER PER JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER This revision petition has been filed by the petitioner/complainant against the order dated 17.04.2012 passed by the H.P. State Consumer DisputesRedressal Commission, Shimla (in short, ‘the State Commission’) in M.A. No. 170/2011 in Appeal No. 91/2011 – The Managing Director, H.P. State Co-Op. Housing Federation Vs. Gian Chand & Anr. by which, appeal was dismissed as barred by limitation. 2. Brief facts of the case are that learned District Forum allowed complaint of the complainant/Respondent No. 1 vide order dated 2.8.2001 and directed OP-1 Society to handover possession of the house to the complainant after receiving balance amount. In Execution Proceeding 15/2007 on account of compromise between the parties, Execution Petition was disposed of as partly satisfied against which, appeal filed by the petitioner was dismissed by learned State Commission vide impugned order against which this revision petition has been filed. 3. None appeared for Respondent No. 2. Heard the petitioner and Respondent No. 1 and perused record. 4. Learned Counsel for the petitioner submitted that learned State Commission has committed error in dismissing appeal being barred by limitation, as delay occurred due to fault of Advocate; hence, impugned order be set aside and revision petition be allowed. On the other hand, learned Counsel for the Respondent No. 1 submitted that order passed by leaned State Commission is in accordance with law; hence, revision petition be dismissed. 5. In application for condonation of delay filed before the State Commission, petitioner submitted that appeal could not be filed in time, as their Counsel did not inform about the order. Further, it was submitted that petitioner came to know about the order only, when it received copy of the order dated 3.8.2010 on 3.9.2010. Then, petitioner issued letter to the Counsel on 19.10.2010 and called his explanation and Counsel assured that he will get the order modified, but as he had not taken any steps; hence, delay of 7 months was caused in filing appeal. 6. There appears to be no explanation at all for condonation of delay. When the petitioner came to know about the District Forum’s order on 3.9.2010, petitioner should have filed appeal immediately before the State Commission, but appeal has been filed after a delay of 7 months that too without any affidavit of the Counsel, who orally assured to get the order modified. This application has also not been supported by letter calling explanation of the Advocate. Law does not permit review of order by District forum or State Commission and in such circumstances instead of waiting for the Counsel to get the order modified from the District Forum; petitioner should have filed appeal immediately. As appeal has been filed after 7 months, learned State Commission has not committed any error in dismissing application for condonation of delay in turn dismissing appeal being barred by limitation. 7. As there is inordinate delay of 7 months, this delay cannot be condoned in the light of the following judgment passed by the Hon’ble Apex Court. 8. In R.B. Ramlingam Vs. R.B. Bhavaneshwari 2009 (2) Scale 108, it has been observed: “We hold that in each and every case the Court has to examine whether delay in filing the special appeal leave petitions stands properly explained. This is the basic test which needs to be applied. The true guide is whether the petitioner has acted with reasonable diligence in the prosecution of his appeal/petition.” 9. In Ram Lal and Ors. Vs. Rewa Coalfields Ltd., AIR 1962 Supreme Court 361, it has been observed; “It is, however, necessary to emphasize that even after sufficient cause has been shown a party is not entitled to the condonation of delay in question as a matter of right. The proof of a sufficient cause is a discretionary jurisdiction vested in the Court by S.5. If sufficient cause is not proved nothing further has to be done; the application for condonation has to be dismissed on that ground alone. If sufficient cause is shown then the Court has to enquire whether in its discretion it should condone the delay. This aspect of the matter naturally introduces the consideration of all relevant facts and it is at this stage that diligence of the party or its bona fides may fall for consideration; but the scope of the enquiry while exercising the discretionary power after sufficient cause is shown would naturally be limited only to such facts as the Court may regard as relevant.” 10. Hon’ble Supreme Court after exhaustively considering the case law on the aspect of condonation of delay observed in Oriental Aroma Chemical Industries Ltd. Vs. Gujarat Industrial Development Corporation reported in (2010) 5 SCC 459 as under; “We have considered the respective submissions. The law of limitation is founded on public policy. The legislature does not prescribe limitation with the object of destroying the rights of the parties but to ensure that they do not resort to dilatory tactics and seek remedy without delay. The idea is that every legal remedy must be kept alive for a period fixed by the legislature. To put it differently, the law of limitation prescribes a period within which legal remedy can be availed for redress of the legal injury. At the same time, the courts are bestowed with the power to condone the delay, if sufficient cause is shown for not availing the remedy within the stipulated time.” 11. Hon’ble Apex Court in (2012) 3 SCC 563 – Post Master General & Ors. Vs. Living Media India Ltd. and Anr. has not condoned delay in filing appeal even by Government department and further observed that condonation of delay is an exception and should not be used as an anticipated benefit for the Government departments. 12. Hon’ble Apex Court in 2012 (2) CPC 3 (SC) – Anshul Aggarwal Vs. New Okhla Industrial Development Authority observed as under: “It is also apposite to observe that while deciding an application filed in such cases for condonation of delay, the Court has to keep in mind that the special period of limitation has been prescribed under the Consumer Protection Act, 1986, for filing appeals and revisions in Consumer matters and the object of expeditious adjudication of the Consumer disputes will get defeated, if this Court was to entertain highly belated petitions filed against the orders of the Consumer Foras”. Thus, it becomes clear that there is no reasonable explanation at all for condonation of inordinate delay of 7 months. Revision petition is liable to be dismissed on the ground of delay alone. 13. In the light of aforesaid judgments, revision petition is liable to be dismissed, as we do not find any infirmity, illegality, irregularity or jurisdictional error in the impugned order. 14. Consequently, the revision petition filed by the petitioner is dismissed at admission stage with no order as to costs. ..……………Sd/-……………… ( K.S. CHAUDHARI, J) PRESIDING MEMBER ..…………Sd/-………………… ( DR. B.C. GUPTA ) MEMBER k NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 1660 OF 2013 (Against the order dated15.01.2013 in FA No.437 /2012 of the State Commission, UT Chandigarh) Ramesh Chandra Singh, CPL RC Singh, C.P.R.U., Air Force Station Palam, New Delhi 110010 …..Petitioner Versus 1. State Bank of India through its Chief Manager, Punjab University Branch, Sector 14, Chandigarh 2. Regional Zonal Office of the State Bank of India through its General Manager Sector 17B, Chandigarh .....Respondents BEFORE: HON’BLE MRS. VINEETA RAI, PRESIDING MEMBER HON’BLE MR. VINAY KUMAR, MEMBER For the Petitioner : Mr. Ramesh Chandra Singh, In Persom PRONOUNCED ON: 24-7-2013 ORDER PER MR. VINAY KUMAR, MEMBER Revision Petition No.1660 of 2013 has been filed against concurrent orders of the District Consumer Disputes Redressal Forum, Chandigarh and the State Consumer Disputes Redressal Commission UT of Chandigarh. Both have dismissed the complaint of the petitioner Mr. Ramesh Chandra Singh. 2. The matter pertains to an EMD loan of Rs.2,91,405/- taken by the Complainant from OP/State Bank of India, Chandigarh branch. Allegedly, OP/bank failed to inform the Complainant about progress of EMD loan and made changes in the chargeable rate of interest, from time to time. It also wrote to the Chandigarh Housing Board for cancellation of the allotment to the Complainant as well as to CIBIL to add the loan given to the Complainant in the list of non-performing assets. Even intimation through e-mail or mobile phone was not sent before taking such action. The Complainant being an officer of Indian Air Force, had to move from location to location as part of his duty and was therefore unable to keep track of his loan account on regular basis. 3. De hors, the case of OP/State Bank of India was that for the purposes of this EMD loan the Complainant had opened a saving bank account on 26.4.2008. The EMD loan was sanctioned as he had been allotted a flat under the relevant scheme of the Chandigarh Housing Board. Subsequently, a number of letters were sent to the Complainant at his local address furnished by him in the application form. But, he never informed the bank about his transfer and shifting from Chandigarh. Nor was any address given to the bank for further correspondence. In this background, the OP was left with no alternative but to write a letter to the office of the Complainant. The Complainant took no action to repay the EMD loan. Nor did he respond to the letters from the bank. In this background, the bank was forced to write to the Chandigarh Housing Board for cancellation of the allotment. While dismissing the complaint, the District Forum has categorically observed that:“9. However, otherwise also the facts speak for themselves, beyond any doubt about the dilly-dallying, irresponsible & careless attitude of the complainant, who himself failed to perform his agreed/legal duty to repay the said loan availed from the OP Ban, which is a public Financial Institution. 10. The Complainant had utilized the public money through OP Bank in the shape of loan, in order to get a Flat under CHB Scheme, but did not return it. By such illegal acts, the complainant has abused his office of serving in Essential Services, by not paying the instalments of loan on the pretext that he was transferred & shifted from the place where he was residing initially. 11. Though the onus to prove this fact was squarely lies upon the complainant, but he has not been able to prove it, by leading/adducing any certain documentary & convincing evidence that he ever informed the OP Bank about the change of his address or about his transferred locations, from time to time.” 4. Similarly, the State Commission has observed that from a perusal of the loan application form it was seen that the Complainant gave ‘No.543/C, Sector 46A, Chandigarh -160047’ as his present residential address as well as his permanent address. All correspondence between July, 2009 and March, 2011 was made on this address. However, the bank received no reply from him. Thereafter, the bank wrote letters to his official address in July and December, 2011, again with no response from the Complainant. In this background, the State Commission has observed that: “Undisputedly, the appellant/complainant defaulted in repaying the loan amount within the stipulated period, and thus, violated Clause No.3 of the Arrangement Letter (Annexure C-1) at Page 23 of District Forum’s file). In this view of the matter, in default of re-payment of loan amount, the Opposite Parties rightly declared the Loan Account of the appellant/complainant as Non-performing Asset (NPA). In our considered opinion, the District Forum, after taking all these facts into consideration, rightly dismissed the complaint of the appellant/complainant.” 5. We have heard the petitioner/Complainant Mr. Ramesh Chandra Singh, in person and perused the record submitted by him. He was also allowed to file his written argument. We find that the entire thrust of the revision petition and his written arguments is to show that the respondent/State Bank of India did not make enough effort to contact the petitioner/Complainant before declaring EMD loan as a nonperforming asset. It is also alleged that the respondent/bank should have informed the Complainant over mobile phone or through SMS or E-mail. But, nowhere in the revision petition or in the written arguments any attempt is made to explain what steps were taken by the petitioner himself either to repay the loan or even to acknowledge the letters written by the OP/Bank. 6. Documents placed on record by the revision petitioner himself show that the loan was sanctioned on 26.4.2008. The details terms of repayment of this loan are also contained therein. In the event of non-allotment, the entire refund of the earnest money was to be adjusted towards the EMD loan and in the event of successful allotment, the entire outstanding amounts including interest was to be repaid within 15 days from the allotment. In his case, it meant an obligation to repay within 15 days of allotment. In this background, the contention of the petitioner in his written arguments that he visited the office of the respondent in September, 2011 to get details and to repay the loan carries no conviction whatsoever. It also does not explain his long silence since sanction of the loan in 2008. 7. In view of the above, we find no substance in this revision petition. It fails to carry any conviction against categorical and concurrent findings of facts reached by the fora below. The revision petition is consequently dismissed for want of merit. No orders as to costs. …..…………….Sd/-…….…… (VINEETA RAI) PRESIDING MEMBER …..…………Sd/-….…….…… (VINAY KUMAR) MEMBER S./- NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION No. 2814 of 2011 (From the order dated 20.06.2011 of the Maharashtra State Consumer Disputes Redressal Commission, Mumbai in Appeal no. 771 of 2006) M/s SAS Motors Ltd., B 14-20 Industrial Estate Baramati District Pune Petitioner Versus Anant Haridas Choudhari Atahrdi Tal – Kalamb Osmanabad District Respondent BEFORE: HON’BLE MR JUSTICE V B GUPTA PRESIDING MEMBER HON’BLE MRS REKHA GUPTA MEMBER For the Petitioner Mr Manan Batra, Advocate For the Respondent Mr Amol V Deshmukh, Advocate with Mr Dilip A Taur, Advocate Pronounced on 24th July 2013 ORDER REKHA GUPTA Revision Petition no. 2814 of 2011 has been filed against the order dated 26.02.2011 passed by the Maharashtra State Consumer Disputes Redressal Commission, Mumbai (‘the State Commission’) in appeal no. 771 of 2006. Complaint of the respondent/ complainant in brief is as follows: Respondent no. 1 is a progressive farmer residing at Atahrdi Tal Kalamb District Osmanabad. Petitioner/ OP no. 2 manufactures and sells Angad tractors and is a sole distributor for Maharashtra and respondent no. 2/ OP 1 is the authorised dealer for selling this tractor. He paid Rs.1,09,500/- as a tractor cost and Rs.24,100/- as a cost of plough thus the total amount was Rs.1,33,600/- and he received a discount of Rs.2,600/-. Thus respondent no. 2 handed over this tractor by taking Rs.1,31,000/-. Respondent no. 2 had orally committed to one year free service and given free service card along with service manual. Respondent no. 1 observed so many defects after working in actual field and hence he took the tractor to the showroom of respondent no. 2 and on 16.02.2005. Respondent no. 1 requested respondent no. 2 to resolve all the defects in this tractor and to repair it. The residence of respondent no. 1 is at Athardi and distance from residence to showroom is 30 km thus the total to and fro is 60 km and respondent no. 1 has to travel 60 km every time for getting his tractor repaired and this leads to unnecessary expenses. After the purchase of tractor from respondent no. 2, from 23.02.2005 to 20.06.2005 for a total of 38 days, the tractor was lying idle at the show room of respondent no. 2 Learned counsel for the petitioner, who was opposite party no. 2 before the District Consumer Disputes Redressal Forum, Osmanabad (‘the District Forum’) confirmed that they had filed no reply before the District Forum and had chosen to go with the reply of OP 1. However, a reading of the District Forum order does not confirm this fact. The District Forum’s order dated 04.04.2006 only refers to the reply of respondent no. 1. The District Forum dismissed the complaint. Aggrieved by the order of the District Forum the respondent no. 1/ complainant filed an appeal before the State Commission. After perusing the records and hearing the counsels for the parties the State Commission considered the following points: (i) “Vehicle admittedly was taken to the respondent for repeated repairs immediately after purchase. (ii) Instead of free servicing complainant was required to get the repaired vehicle for many defects. (iii) It is admission of respondent that they tried to repair tractor by going to village of complainant. This itself shows that tractor was not of quality as advertised. (iv) Respondent did not produce any evidence of expert to show that vehicle is at par. Neither made application before Forum to get inspected the tractor from the expert. (v) Immediately after purchase of vehicle, complainant was compelled to take tractor to respondent many times for repairs. This fact shifts the burden on respondent to prove that though repairs were carried out they were not manufacturing defects. (vi) Appellant many times approached for repairs then issued legal notice which was also not replied by respondent. Appellant was constrained to leave the tractor with respondent as it was not in condition to use the same. Therefore, we are of the view that brand new tractor immediately after purchase was found to have manufacturing defects. This is unfair trade practice to supply the vehicle with defects. District Forum without appreciating the facts and circumstances, proceeded on the ground that tractor was used by unskilled person. IN the absence of any proof about it Forum decided complaint on assumptions and presumptions. We are therefore, quashing the said order. We are directing respondent to refund the price of tractor with 9% interest from the date of purchase”. The State Commission then passed the following order: “Hence, the appeal is allowed. Judgment and order passed by the District Forum is hereby quashed and set aside. Respondent is directed to pay Rs.1,31,000/with 9% interest from 09.02.2005 i.e., from the date of purchase. Respondent has to pay Rs.15,000/- towards compensation and cost”. Hence, the present revision petition. The main grounds of the revision petition are as follows: The State Consumer Disputes Redressal Commission had on its own without any satisfactory material on record, concluded that the said tractor was defective. It is pertinent to note here that the burden of proving any manufacturing defect in the said tractor was upon the respondent no. 1. It is reiterated that neither the complaint C R No. 217/ 2005 before the District Forum nor the appeal no. 771 of 2006 had placed on record any documentary evidence to show that the said tractor was suffering from any manufacturing defects as alleged or at all. The State Commission erred in taking note of the normal wear and tear of the said tractor and misinterpreted the same as the defects in the said tractor. We have heard the counsels and gone through the record. It is an undisputed fact that while the tractor was purchased on 05.02.2005 and it was taken for repairs within 12 days i.e., 17.02.2005. As mentioned in the complaint from 23.02.2005 to 20.06.2005 the tractor remained in the show room of the petitioner for 38 days for repairs. The defects listed in the complaint are corroborated by the job cards placed on file. Respondent no. 2/OP no.1 was situated at a distance of 30 km from the residence of the petitioner and hence, the journey to show room and back was around 60 km so the respondent no. 1 would hardly make frivolous and unwarranted trips unless required. A perusal of the job cards indicated that on 17.02.2005 itself the customer had a complaint regarding broken lower link pin, oil leakage, clutch setting. All these were attended to. Thereafter there were complaints relating to lower link pin, clutch and the fact that the tractor was not moving even in gear also. After 20.04.2005, the water pump had to be changed, dynamo belt had also broken. On 05.05.2005, the alternator failed and had to be changed. On 10.05.2005, there was hydraulic arm oil leakage and the battery failed. The tyre rim of the front left side tyre had also to be changed. Counsel for the petitioner stated that no expert opinion had been taken with regard to the manufacturing defects. When there were so many defects which started occurring within 12 days of purchase of the tractor and as the job cards confirmed that the same defects had to be rectified to by respondent no. 2, the facts speak for themselves. In the circumstances, we find that no expert advice is required to be obtained by Respondent no.1. If the petitioner felt it was imperative he could have pleaded for the same before the State Commission. In view of the foregoing reasons, we find that there is no jurisdictional error, illegality or infirmity in the order passed by the State Commission warranting our interference. The revision petition is accordingly dismissed with cost of Rs.10,000/(Rupees ten thousand only). Revision petitioner is directed to pay Rs.5,000/- to the respondent no. 1 directly by way of demand draft and the balance amount of Rs.5,000/- be deposited by way of demand draft in the name of ‘Consumer Legal Aid Account’ of this Commission, within four weeks from today. In case the revision petitioner fails to deposit the said amount within the prescribed period, then it shall be liable to pay interest @ 9% per annum till realisation. List on 30th August 2013 for compliance. Sd/..……………………………… [ V B Gupta, J.] Sd/……………………………….. [Rekha Gupta] Satish NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 1184 OF 2011 (From order dated 01.02.2011 in First Appeal No. 4571 of 2010 of the State Consumer Disputes Redressal Commission, Karnataka) New Holland Fiat (India) Pvt. Ltd. Formerly known as Fiat India Pvt. Ltd. 303, Central Plaza, 166, C. S. T. Road, Kalina, Mumbai-400098, Maharashtra ...…Petitioner Versus 1. Govindkar Vinod Krishnamurthy, S/o Late G. M. Krishnamurthy, No. 46, 3rd Cross, Aga Abbash Alli, Road, Halsur, Bangalore 2. Genesh G. K. S/o Late G. K. Krishnamurthy, No. 46, 3rd Cross, Aga Abbash Alli, Road, Halsur, Bangalore 3. Manx Auto Ltd. No. 16/A, KKMP Building,Miller Tank Bund Road, Vasnathnagar, Bangalore, Rep. By its MD Prabhakar. 4. Kotak Mahindra Prime Ltd. Formerly Kotak Mahindra Primus Ltd. No. 20, 3rd Floor, Uniworth Plaza Sankey Road, Palace Guttahalli, Bangalore 20, Rep. By its Authorized Signatory Mallikarjuna Jaliahal .... Respondents BEFORE: HON’BLE MR. JUSTICE V.B. GUPTA, PRESIDING MEMBER HON’BLE MRS. REKHA GUPTA, MEMBER For the Petitioner : Mr. Puneet Agrawal, Advocate For the Respondents : Mr. Shekhar G. Devasa Advocate for R-1 and R-2 Respondent no. 3 is already ex parte. Mr. Abhishek Dwivedi, Advocate for R-4 Pronounced on: 25th July, 2013 ORDER PER MR. JUSTICE V.B. GUPTA, PRESIDING MEMBER Petitioner/O.P. No.1 being aggrieved by impugned order dated 1.2.20121, passed by Karnataka State Consumer Disputes Redressal Commission, Bangalore(for short, ‘State Commission’) has filed the present revision petition. 2. Brief facts are that Complainant no. 2/respondent no.2 has paid Rs.1,50,000/- to respondent no.3/opposite party no. 2 on 11-1-1999 for purchase of FIAT UNO car and requested to get registered Fiat car in the name of his mother Smt. Tara Bai. The request was accepted by respondent no.3 who is the authorized dealer of petitioner, while respondent no. 4/opposite party No.3 is the financer. However, the car was not delivered to Smt. Tarabai. Respondent No.4 has financed Rs.2,86,000/- and the amount was paid to respondent no. 3. In spite of payment of full car amount i.e., Rs.4,38,000/which includes cash paid by respondent no.1 and loan released by the respondent no. 4, respondent no. 3 has not delivered the vehicle. Smt. Tara Bai died on 13-11-2007 and respondents no.1 and 2 are her legal heirs. It is alleged that petitioner and other respondents have allegedly misappropriated the payment made by respondents no.1 and 2, in collusion with respondent no.4 without giving delivery of vehicle. Therefore, there is deficiency of service.Respondents no.1 and 2 have came to know that respondent no.4 has initiated recovery of loan proceedings against them. Thus, petitioner and other respondents have played fraud. Hence, respondents no.1 and 2 have claimed that petitioner and other respondents be directed pay Rs.4,38,902/- with interest. 3. After admitting the complaint, notice were sent to the opposite parties by the District Forum. Petitioner was well as respondent no. 3 did not appear before District Forum despite service. Hence, they were proceeded ex parte. 4. Respondent no.4, in its written version has admitted that respondents no. 1,2 and Smt. Tara Bai have made request for sanction of loan of Rs.2,86,000/-. However, matter is pending before Civil Court, hence, the complaint is not maintainable. 5. District Consumer Disputes Redressal Forum, Seshadripuram, Bangalore(for short, ‘District Forum’) vide order dated, 13.07.2010 passed the following directions; “Opposite party No.1 Fiat India Pvt. Ltd., is directed to pay Rs.1,50,000/- to the complainants within 60 days from the date of this order. The complainants are entitled for 9% interest p.a. from the date complaint till payment / realization”. 6. Being aggrieved by the order of District Forum, petitioner filed an appeal before the State Commission, which was dismissed, vide impugned order. 7. Now petitioner has filed the present revision petition. Notice of this petition was issued to all the respondents. However, respondent no.3 has not appeared despite service by publication. Hence, respondent no. 3 has been proceeded ex parte in these proceedings. 8. We have heard the learned counsel for the parties and gone through the record. 9. It has been contended by learned counsel for the petitioner that petitioner was never served with notice of the complaint. However, petitioner had shifted to a new address but no notice was served upon the new address. 10. Other contention is that there was no relationship of Principal–Agent between the petitioner and respondent no.3, herein. 11. Lastly, the claim of respondents no.1 and 2 is hopelessly barred by limitation since cause of action arose in the year 1999, when respondents no.1 and 2 had allegedly paid a sum of Rs.1,50,000/- to respondent no.3. However, the complaint was filed only in the year 2009 and as such impugned order is liable to be set aside. 12. On the other hand, it has been contended by learned counsel for respondents no.1 and 2 that this plea of petitioner’s counsel at this stage, that no notice was served upon the petitioner as it has shifted to a new address, is patently false and mischievous one. The address of the petitioner as mentioned in the complaint filed before the District Forum as well as in the memo of appeal filed before the State Commission, are same. Secondly, as respondents no.1 and 2 have not been delivered the car in question till date, it is continuous cause of action. Hence, there is no ambiguity or illegality in the impugned order. 13. District Forum in its order held; “ Since, Rs.1,50,000/- is paid by the complainant to the opposite party No.2 by way of cheque this has not been denied by opposite party No.2. Therefore, the payment has to be believed and accepted. The complainants has produced a public Notice was issued in Times of India news paper, dated 14-10-2002, it is as under: FIAT NOTICE This is to inform all our clients and other concerned Members of the public that M/s. MANXAUTOLTD. 16-A, KKMP Building Miller Tank Road, Vasant Nagar, Bangalore-52. is no longer a Dealer of the Company w.e.f. 2-10-2002 Customers are therefore advised not to book orders Or deal in any manner with the said M/s. MANX AUTO LTD. Bangalore The Company shall owe no responsibility Whatsoever for any such dealings done by them or liability After the said date. Fiat India Private Ltd. Regd. Office LBS Marg, Kurla Mumbai- 400070 So, as per this public notice it is clear that the opposite party No.1 company has admitted that opposite party No.2 was their dealer and the company has owed the responsibility or liability of dealings done by the opposite party No.2 before 2-10-2002. The opposite party No.2 was dealer of the opposite party No.1 till 2-10-2002, and his dealership was removed after that date. In this case the complainants have paid Rs.1,50,000/- to the opposite party No.2 by cheque on 11-1-1999. Therefore, the opposite party No.1company has to owe the responsibility and liability of the opposite party No.2. Since, the booked car was not delivered to the complainants it is the duty and obligation of the opposite party No.1&2 to refund Rs.1,50,000/- to the complainants”. 14. The State Commission, while dismissing the appeal at admission stage observed; “8 At the out set, it is not in dispute that the complainant booked FIAT UNO Car manufactured by OP 1 through its dealer/agent OP 2 and paid a lump-sum amount of Rs.1,50,000/-.For the remaining amount the mother of the complainant Smt. Tarabir in whose name the car was booked, availed financial assistance from OP 3. Though OP 1 and 2 received the said amount they failed to deliver the said car. Ultimately Tarabai died on 13.11.2007. Thereafter, through complainants being the heirs made repeated requests and demands to OP, OP 1 and 2 failed to deliver the car. Hence they felt deficiency in service. 9. The evidence and the pleadings of the complainant has remained unchallenged which finds full corroboration with the contents of undisputed documents. There is nothing to discard the testimony of the complainant. Though OP 1 was duly served with notice as could be seen from the postal acknowledgement remained absent without any reason or cause. Though paper publication was issued against OP 2, he did not appear. So the absence of the Ops does not appears to be bonafide and reasonable. 10. The DF has rightly assessed both and documentary evidence and come to the conclusion that there is a deficiency in service. Of course by public notice, OP 1 terminated the agency or the dealership of OP 2 with effect from 02.10.2002, whereas the said car was booked on 11.1.1999 and the amount is paid. So on that date OP 2 was the agent-cum-dealer of OP 1. Naturally there is liability on the OP 1 in all aspects. The very fact of issuance of the notice that the said dealership comes to and with effect from 02.10.2002 speaks to the fact that OP 1 admits the status of OP 2 prior to 02.10.2002. When that is so, OP 1 is liable to refund the said cost. 11. Complainants through invested their hard earned money they are unable to reap the fruits of their investments. Neither they got back the money nor the vehicle. Under the circumstances, naturally they must have been put to greater hardship and prejudice. We don’t find any error in the findings recorded by the DF. On the other hand, appellant has failed to show before this Commission that the impugned order is erroneous, unjust and improper and that it suffers from any legal infirmity, unsustainable in law much less it suffers from any error apparent on the face of record requiring our interference. 12. There are no substantial grounds and reasons made out by the appellant so as to admit this appeal. In addition to that, there is an inordinate delay of 61 days in filing this appeal. There is no satisfactory explanation for the said delay. So on this score also the relief claimed by the appellant cannot be considered. Accordingly, we answer Point No.1 and proceed to pass the following: ORDER Appeal is dismissed at the stage of admission”. 15. This plea of the petitioner that no notice has been received by him from the District Forum since he has changed his address is patently wrong and false and the same has been taken only just to mislead this Commission as address of the petitioner as mentioned in the complaint filed before the District Forum as well as in the memo of appeal filed before the State Commission are same. There has been no change in the address of the petitioner. 16. Secondly, there was relationship of Principal-Agent between petitioner and respondent no.3, when respondent no. 3 took a sum of Rs.1,50,000/- from the respondents no.1 and 2. 17. With regard to question of limitation, District Forum in its order has held; “The complainants alleged that the opposite party No.1 & 2 have committed the deficiency in service in not delivering the vehicle booked, therefore, the cause of action being a running cause of action, it will continue till the delivery of vehicle.The Complainants several time approached the opposite party No.2 and requested for delivery of vehicle, but the opposite party No.2 did not deliver the vehicle for the reasons best known to him”. 18. Present revision petition has been filed under Section 21(b) of the Consumer Protection Act, 1986 (for short, ‘Act’). It is well settled that the powers of this Commission as aRevisional Court are very limited and have to be exercised only, if there is some prima facie jurisdictional error in the impugned order. 19. Hon’ble Supreme Court in Mrs. Rubi (Chandra) Dutta Vs. M/s United India Insurance Co. Ltd. 2011 (3) Scale 654 has observed; “Also, it is to be noted that the revisional powers of the National Commission are derived from Section 21 (b) of the Act, under which the said power can be exercised only if there is some prima facie jurisdictional error appearing in the impugned order, and only then, may the same be set aside. In our considered opinion there was no jurisdictional error or miscarriage of justice, which could have warranted the National Commission to have taken a different view than what was taken by the two Forums. The decision of the National Commission rests not on the basis of some legal principle that was ignored by the Courts below, but on a different (and in our opinion, an erroneous) interpretation of the same set of facts. This is not the manner in which revisional powers should be invoked. In this view of the matter, we are of the considered opinion that the jurisdiction conferred on the National Commission under Section 21 (b) of the Act has been transgressed. It was not a case where such a view could have been taken by setting aside the concurrent findings of two Fora”. 20. Thus, no jurisdiction or legal error has been shown to us to call for interference in the exercise of power under section 21 (b) of the Act, since two fora below have given cogent reasons in their order, which does not call for any interference nor they suffer from any infirmity or revisional exercise of jurisdiction. 21. It is not that every order passed by the fora below is to be challenged by a litigant even when the same is based on sound reasoning. 22. Under these circumstances, present petition is without any legal basis and having no merit is hereby dismissed with cost of Rs.10,000/-.(Rupees Ten Thousand only) to be paid to respondents no.1 and 2. 23. Petitioner is directed to pay the cost by way of draft to the respondents no.1 and 2, within four weeks from today. In case, petitioner fails to pay the aforesaid cost within the prescribed period, then it shall also be liable to pay interest @ 9% p.a., till realization. 24. List on 30.08.2013 for compliance. ……..……………………J (V.B. GUPTA) ( PRESIDING MEMBER) ………………………… (REKHA GUPTA) MEMBER SSB/ NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION No. 2479 of 2008 (From the order dated 01.02.2008 of the Delhi State Consumer Disputes Redressal Commission, Delhi in First Appeal no. 550 of 2007) UCO Bank (Through its Manager) Patiala House Court New Delhi – 110 001 Petitioner Versus Shri S D Wadhawa D – 3, G K Enclave - I New Delhi – 110 048 Respondent BEFORE: HON’BLE MR JUSTICE V B GUPTA PRESIDING MEMBER HON’BLE MRS REKHA GUPTA For the Petitioner MEMBER Mr Sarfaraz Khan, Advocate For the Respondent IN PERSON Pronounced on 24th July 2013 ORDER REKHA GUPTA Revision petition no. 2479 of 2008 is against the final order and judgment dated 1st February 2008 passed by the Delhi State Consumer Disputes Redressal Commission, Delhi (‘the State Commission’) in First Appeal no. 550 of 2007. The brief facts of the case as given by the respondent/complainant are as follows: The respondent is a practicing lawyer and has been availing the services of the petitioner/ OP Bank right from the inception of his practice/ profession vide his S B Account no. 1802. The service of the petitioner which is a nationalised institution, have been (in totality) reasonably up to the mark with the exception of 3 stray unfortunate incidents (out of respondent’s seven cheques) whereon his signatures were forged and were issued in three different names by some unknown culprit/ mischief monger with the aid and abetment of his court clerk Pooran Chandra Pant on the one side joined by some bank staff on the other side who actively connived, collaborated/ colluded in the matter of fraudulent withdrawal of total of Rs.40,000/- from the respondent’s aforesaid S B Account. Respondent’s first cheque bearing no. 557529 dated 05.08.2002 for Rs.10,000/purported to have been issued in fictitious/ imaginary name of one Rajesh Kumar with the forged signature of the respondent beneath it were got encashed the same day from the Bank vide its token no. 132. The respondent’s second cheque bearing no. 557532 dated 14.08.2002 for Rs.10,000/- was issued in the name of one Rajbir Singh, again with the forged signatures of the respondent beneath it, was got encashed the same day vide its token no. 192. The respondent’s third cheque bearing no. 618832 dated 23.07.2003 for Rs.20,000/- was issued in the name of one Gopal Singh against, with the forged signatures of the respondent beneath it, was got encashed the same day vide its token no. 1834. Intimation of the first stop payment advice for the remaining 2 uncashed cheques had been given on 26.08.2002 to the petitioner Bank. Whereas intimation of the second stop payment advice for the remaining two uncashed cheques was made on 24.07.2003 to the petitioner Bank. In the first incident a complaint was made only to the petitioner Bank with a written request to compensate the respondent for the loss of Rs.20,000/- suffered by him due to lack of its vigilance and carelessness in the matter of properly tallying and comparing the signatures appended beneath the said two forged cheques. The proceeds of these three cheques seemingly have been collected by one and the same individual on the respective dates as is amply evident from the style of the signing done by the bearer at the back of the three cheques. The noteworthy point in this context is that during this period the computer network system of the petitioner Bank was non-functional and thus the respondent’s routine of getting his passbook update on weekly basis with the debit-credit entries was disturbed and disrupted and as a consequences thereof the culprit/ offender took advantage of the situation and got all the three cheques encashed on different dates/ occasions. In essence, this kind of loss suffered by the respondent is attributable to ‘Glaring Deficiency in Service’ on the part of the petitioner Bank in the following manners inter alia others: Firstly, by not doing the posting job of the passbook due to the defects in the petitioner’s computer system. Secondly, the laches in the form of hastily, heedlessly and negligently verifying tallying/ comparing the forged signatures on the said three cheques. Thirdly, by not looking at the signatures made on the back of the first cheque dated 05.08.2002 where the bearer has signed as R Singh on the back thereof instead of Rajesh Kumar and the second cheque dated 14.08.2002 also carrying the signature in the handwriting of the same individual as R Singh on the back thereof while the cheque had been issued in the name of Rajiv Singh and in the third case even though the signatures were that of the bearer on the back of the cheque but the handwriting shows that the signatory had been one and the same individual as is apparent to the naked eye. In their reply, the petitioner/ OP 1 – Bank have denied the allegations made in the complaint. They have stated that the respondent nowhere in his FIR and other communication to the police made any allegation against the petitioner Bank and its staff members. His needle of suspicion centres around his own staff members, i.e., his clerk and driver. This itself amounts an admission by the respondent that there is no deficiency in service on the part of the petitioner Bank and the loss if any is because of vicarious liability for the negligence on the part of respondent himself. The complaint is hopelessly time barred and no plausible explanation has been given to account for inordinate delay in filing the complaint. The respondent has lodged a complaint with the police on 24.07.2003 whereas he has filed the present complaint as an after thought and on account of fall out of the FIR. The payment of all the cheques which are uncrossed and bearer were made in due course without negligence to the holder of the cheques in the circumstances which to the judgment of the official of the petitioner Bank did not reveal any reasonable doubt particularly about the genuiness of the cheque. There was not an iota of doubt that the holder of the cheque was not entitled to payment thereof. The loss if any is not because of the alleged deficiency in service but because of negligence on the part of the respondent in not keeping his cheque book in lock and key and or safe custody and over reliance/ dependence on his own driver and clerk. The District Consumer Disputes Redressal Forum – II, Udyog Sadan, New Delhi (‘the District Forum’) vide order dated 13.06.2007 has stated that “the opinion is based on the examination made from the Photostat of the documents and not from the original documents. The opinion is subjected to confirmation after the examination from the original documents. The complainant is also negligent is suffering loss. He suffered fraud in the year 2002. Instead of taking care and caution, he kept the pass book unlocked in his car and in possession of his clerk. The conduct of complainant is like maxim ‘volenti non fit injuria’. His careless attitude caused loss to him. A banker is not supposed to compare the signature of account holder on the cheque with the same technique is adopted by CFSL. The complainant did not care to be vigilant”. The District Forum did not find any deficiency in service on the part of the petitioner Bank. Consequently, the complaint was dismissed. Aggrieved by the order of the District Forum, the respondent/ complainant filed an appeal before the State Commission. State Commission differed with the findings of the District Forum and stated that “it is settled principle that every skilled person has to be trusted in his art and no court can replace the opinion by its own opinion even by comparing the admitted and disputed signatures. Unless and until the reports of the expert are so diametrically opposite and suffer from such irreconcilable contradictions no different opinion can be framed. Once the District Forum was equipped with two reports of handwriting expert it was not open to it to introduce its own opinion by stepping into the shoes of an expert. Another observation of the District Forum which also suffers from inherent infirmity is that the respondent who had suffered a fraud in the year 2002 should have kept the pass book and cheque book under lock and key and not in his car in the possession of his clerk and therefore his conduct is that of ‘volenti non fit injuria’ and the careless attitude caused loss to him. Such an observation was not at all apt in the given facts and circumstances of the case, particularly when the person who forged the signature is none but his own clerk. In ordinary course of business and transactions of the Bank the officials of the Bank sitting at the counter are not supposed to avail the service of handwriting expert in each and every case. But at the same time they are required to take sufficient precaution and exercise utmost care in encashing cheque which are bearer or self and since in the instant case the petitioner bank did not take care to exercise sufficient care the caution as is demonstrated from the two reports of the handwriting expert petitioner bank has to be held guilt for deficiency in service. Since there was no malafide intention nor was there only conspiracy of the bank officials, we hold the petitioner bank guilt for limited deficiency in service to the aforesaid extent and deem that compensation of Rs.20,000/- besides Rs.5,000/- as cost of litigation would meet the ends of justice. In the result, we allow the appeal, set aside the impugned order with the directions respondent/ appellant to pay Rs.20,000/- as compensation and Rs.5,000/- as cost of litigation”. Hence, this present revision petition. The main ground for the revision petition are that the State Commission has failed to appreciate the facts regarding day to day transaction of the bank is ordinary course of business and the official staff of the bank who are sitting at the bank counter are not handwriting expert to avail these type of service to check every stroke, turns, curvature, place of joining letter of the bearer cheque in normal course of day. It is pertinent to mention that all the signature of the cheques where duly tallied/ verified from the specimen of the record of the customers. For that the State Commission has failed to appreciate the facts that the negligence in the part of the respondent for loss of his blank cheque twice not once. He did not keep his cheque in a secured place. We have heard the learned counsel for the petitioner and respondent in person and gone through the records. Learned counsel for the petitioner - Bank drew our attention to the fact that the complaint before the District Forum ought to have been dismissed on limitation. He drew our attention to paragraph 2 of the complaint wherein three cheques had been encashed by some unknown culprit/ mischief monger with the aid and abetment of his court clerkPooran Chandra Pant. Cheque bearing no. 557529 dated 05.08.2002 for Rs.10,000/-, the second cheque bearing no. 557532 dated 14.08.2002 for Rs.10,000/and the third cheque bearing no. 618832 dated 23.07.2003 for Rs.20,000/-. Intimation of the first stop payment advice for the remaining two uncashed cheques had been given on 26.08.2002 to the petitioner, whereas intimation of second stop payment advice for the remaining two uncashed cheques was made on 24.07.2003. However, the complaint was filed after two years from 24.07.2003 on 17.08.2005, hence, it is time barred. Learned counsel for the petitioner also stated that respondent had also not filed thecondonation of delay application along with the complaint. He drew our attention to the Apex Court judgment in the case of Dr V N Shrikhande vs Mrs Anita Sena Fernandes – AIR 2011 Supreme Court 212, wherein the Apex Court considered whether the Consumer Forum established under the Act can refuse to admit the complaint on the ground that the same is barred by time. The decision of this question depends on the interpretation of sections 12(1), (3), (4), 18, 22 and 24 A of the Act. The Apex court held that “in other words, the Consumer Forums do not have jurisdiction to entertain a complaint if the same is not filed within 2 years from the date on which the cause of action has arisen. This power is required to be exercised after giving opportunity of hearing to the complainant, who can seek condonation of delay under section 24 A (2) by showing that there was sufficient cause for not filing the complaint within the period prescribed under section 24 A (I). If the complaint is per se barred by time and the complainant does not seekcondonation of delay under section 24 A (2). The Consumer Forums will have no option but to dismiss the same. Reference in this connection can usefully be made to the recent judgments in State Bank of India vs B S Agricultural Industries (I) (2009) 5 SCC 121 : (AIR 2009 SC 2210) and Kandimalla Raghavaiah and Company vs National Insurance Company and Another – (2009) 7 SCc 768 : (2010 AIR SCW 2528)”. Learned counsel for the petitioner has also argued that the respondent in his complaint has alleged that signatures were forged on the cheques and money was withdrawn from his account. Counsel for the petitioner have cited two cases of National Commission (Bright Transport Co. vs Sangli Sahakari Bank Ltd - II (2012) CPJ 151 (NC), decided on 12.01.2012 and Prempreet Textiles Industries Ltd., vs Bank of Baroda and Ors. – III (2006) CPJ 218 (NC) decided on 15.05.2006) and one case pertaining to Delhi State Commission (Srikrishan Dass vs Dena Bank – I (2003) CPJ 276 decided on 08.07.2002). In the case of Bright Transport Co. (Supra) the National Commission has held that “we must consider the question whether this Commission in exercise of its summary jurisdiction would be able to adjudicate all those issues arising on the complaint in an effective manner. If this Commission ventures to do it, it may have to record the evidence of all those persons whose evidence was collected by the CBI. It is only after detailed examination and cross examination of those witnesses and the documentary evidence i.e. voluminous record involved in the said bank transactions that the Commission may perhaps be able to adjudicate on the said question. We have, therefore no hesitation to hold that the complaint indeed raises very complicated question of facts and law which can only be answered by a regular Civil Court and the complainants should be relegated to the Civil Court to work out their remedy for the entire claim made by them in the present complaint or this Commission can decide upon the claim in regard to which there is no dispute between the parties. It also appears to us that filing of present complaints before this Commission are nothing but an attempt to misuse the jurisdiction of this Commission only with a view to save on the court fee payable in a suit before the Civil Court. Having considered the matter from different angles and having given our thoughtful consideration to the submissions made by the learned counsel for the complainants, we are of the view that these consumer complaints are not maintainable before this Commission. However, the complainants shall be free to work out its remedy in accordance with law before the appropriate court / Tribunal. With these observations, the consumer complaints are dismissed”. In the case of Srikrishan Das (Supra), the State Commission has held that “if the above criterion is applied to the present case, it is noticed by us that the complaint filed by the complainant before this Commission requires adjudication in respect of complicated and complex questions of fact, such as whether in fact on the basis of forged cheque the amount in question has been fraudulently withdrawn from the account of the complainant and whether there was any connivance/ conspiracy to cause wrongful loss to the complainant by the staff members of the Bank. The above complex and complicated questions, which require taking of elaborate evidence and adducing documentary/ expert evidence also and thereafter a detailed scrutiny and assessment of such evidence, decidedly cannot be adjudicated upon satisfactorily by a redressal agency, established under the Act. In view of the position explained above, the present complaint filed by the complainant is directed to be dismissed in limine. However, the complainant is given the liberty to approach the appropriate Civil Court for redressal of his grievances being raised by the complainant in the present complaint, as the complainant may be advised”. Counsel for the petitioner also argued that it was for the respondent to keep his cheque book under lock and key and it was indeed surprising that his staff could access his cheque book and allegedly forged the signature to withdraw Rs.40,000/- on no less than three occasions. Learned counsel for the petitioner also drew our attention to the case of Prempreet Textile Industries Ltd., (Supra) have stated that “it was the duty of the above Director to have ensured that the cheque book was kept under locked key at a safe place. In this backdrop, there was hardly any occasion for the respondent bank to have doubted the genuineness of the signatures on the cheque in question if any embezzlement was made by the employee of company the respondent Bank cannot be held responsible for it. Respondent Bank had, thus, been rightly exonerated of the liability arising out of the cheque in question by the State Commission in terms of the aforesaid order dated 01.02.2006 which does not call for any interference in revision jurisdiction under section 21 (b) of the C P Act, 1986. Dismissed”. Respondent who has appeared in person admitted that he used to keep his cheque book and other papers in his car or his office drawer and his staff had ready access to the cheque book at both the places. He further admitted that on the first occasion when the two cheques were encashed, he had not even lodged an FIR with the police, as he was not sure who on his own staff could have had access to his cheque book and encashed the cheques. It was only on the third occasion that he lodged an FIR with the police. Hence, it is an admitted fact that the respondent failed to keep the cheque book under lock and key. In view of the above circumstances all the citations cited above are applicable to the case on hand. It is clearly established that the respondent had failed to take due care of his cheque book due to which his own staff could access the same and withdraw the money fraudulently from the bank account. He came to know the same on updating his pass book. Bank cannot be held for deficiency in service in this regard. Secondly, complaint regarding fraudulent withdrawal from the respondent account on the basis of forged cheques, involve complicated and complex questions which require elaborate evidence and hence, the dispute is not adjudicable in summary jurisdiction. As such the complaint is not maintainable in the Consumer Form. The facts of the case also clearly indicate that the complaint was filed beyond the period of limitation of two years and hence, it should have been dismissed by the District Forum. In view of the foregoing, the revision petition is allowed and the order of the State Commission is set aside. Sd/..……………………………… [ V B Gupta, J.] Sd/……………………………….. [Rekha Gupta] Satish NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO.1834 OF 2012 (From the order dated 17.01.2012 in Appeal No.20/2012 of the Karnataka State Consumer Disputes Redressal Commission, Bangalore) The Manager, Bharti AXA General Insurance Co. Ltd. 1-Floor, Fems Icon, S.No.28, Doddanekkundi Village, K.R. Puram, Bangalore, Pin Code-560037 Through Its Area Manager, (Legal) Bharti AXA General Insurance Co. Ltd. 2nd Floor, Bigjos Tower,A-8, Netaji Subhash Place, Pitampura, New Delhi-110034 ..…. Petitioner Versus B.A. Lokesh Kumar S/o B. Aswatha Raju R/o Door .1532/2, Raghavendra Nilaya, Opp. To Venkatenhalli, Narasimhaih Choultry, B.B. Road, Chickballapur Town & District Pin Code-562 101 ..... Respondent BEFORE: HON'BLE MR.JUSTICE AJIT BHARIHOKE, PRESIDING MEMBER HON’BLE MR.SURESH CHANDRA, MEMBER For the Petitioners : Mr. Navneet Kumar, Advocate For the Respondent : Mrs. Vijayshanthi Girish, Advocate PRONOUNCED ON 25th JULY, 2013 ORDER PER SURESH CHANDRA, MEMBER This revision petition is directed against order dated 17.01.2012 passed by the Karnataka State Consumer Disputes Redressal Commission, Bangalore (“State Commission” in short) in appeal No.20/2012. Petitioner is the opposite party/Insurance Company and the respondent herein is the original complainant. By its impugned order the State Commission dismissed the appeal filed by the petitioner/Company and upheld the order dated 24.10.2011 passed by the Additional District Consumer Disputes Redressal Forum, Seshadripuram, Bangalore wherein the petitioner company was directed to pay to the respondent/complainant a lumpsum compensation of Rs.13,31,997/- alongwith interest @ 12% p.a. from 13.6.2011 till realization along with Rs.2,000/- as cost of litigation. 2. Briefly stated, the facts of this case, which are relevant for its decision, are that the respondent/complainant had purchased a new Innova vehicle with temporary registration No.KA-01/TR-MB-2979 and got it insured under a comprehensive package with insured declared value (I.D.V) of Rs.11,63,284/- from the petitioner/company for the period from 25.10.2010 to 24.10.2011. Admittedly the validity of the temporary registration certificate of the vehicle expired on 23.11.2010 after which the respondent/complainant did not obtain a registration number. On 9.6.2011, the complainant sent this vehicle to Dharamasthala on a pilgrimage trip for the conveyance of his family members and relatives and on the way toDharmsasthala when the vehicle was proceeding on NH-48, it met with an accident and in that it got toppled and fell into a road side ditch in a topsy turvey position. The respondent intimated about the accident and the damage to the vehicle on account of this accident to the petitioner/insurance company. It is alleged that after inspection of the damaged vehicle, damage to the tune of around Rs.13,16,997/- was assessed besides expenditure of about Rs.15,000/incurred by the respondent towards lifting and shifting charges. The petitioner-company after considering the survey report and other relevant documents repudiated the claim of the respondent vide its letter dated 30.6.2011 stating that the vehicle in question did not have a permanent registration number and thus there was blatant violation of Section 39 of the Motor Vehicles Act, 1988. It was also indicated in its letter that the temporary registration of the vehicle had already expired on 23.11.2010 and because of this at the time of the accident the vehicle did not have either a valid temporary registration or a permanent registration. Aggrieved by the repudiation of his claim, the respondent filed a consumer complaint bearing No.1303/2011 before the District Consumer Forum seeking compensation of Rs.13,16,997/- alongwith other reliefs. The District Forum vide its order dated 24.10.2011 allowed the complaint in terms of the aforesaid directions against which the petitioner filed an appeal before the State Commission which came to be dismissed by the impugned order. Thus the petitioner has approached this Commission challenging the concurrent orders of the fora below through the present revision petition. 3. We have heard learned Shri Navneet Kumar, counsel for the petitioner and learned Mrs.Vijayshanthi Girish, counsel for the respondent. While admitting the validity of the insurance policy under a comprehensive cover and the occurrence of the accident in question involving the vehicle in dispute, learned counsel for the petitioner submitted that the forabelow had failed to appreciate that the temporary registration of the vehicle had expired on 23.11.2010 itself and the respondent did not get the vehicle permanently registration and thus there was clear violation of the policy condition and the provisions of the Motor Vehicles Act, 1988. He submitted that it was made abundantly clear to the respondent by the petitioner company while repudiating his claim that since the vehicle did not have valid registration number on the date of the accident, it was violation of a mandatory requirement of law and also breach of contractual obligations by the respondent, the claim submitted by him could not be allowed. Later on, when the respondent filed the consumer complaint before the consumer forum, the petitioner-company took the same plea in addition to other submissions in the written version filed by it before the District Forum and reiterated the same before the State Commission while challenging the order of the District Forum. He submitted that in spite of this, both the fora below have rejected this plea while allowing the complaint by their concurrent finding as confirmed by the impugned order. Besides referring to the provisions of Section 39 of the Motor Vehicles Act, 1988, learned counsel has relied on two judgments of this Commission in the cases of Kaushalendra Kumar Mishra vs. The Oriental Insurance Co. Ltd. (Order dated 16.2.2012 in R.P. No.4043/2008) and NiranjanKumar Yadav vs. National Insurance Co. Ltd. (Order dated 29.3.2011 in R.P. No.2926/2010). He summed up his arguments by submitting that since the crucial point regarding the expiry of the temporary registration of the vehicle before the date of the accident and non-issuance of a permanent registration to the vehicle on the date of the accident are not under dispute, the impugned orders cannot be sustained and are liable to be set aside as being violative of the express provisions of law. Per contra, learned counsel for respondent/complainant has submitted that there is no merit in the revision petition and that there is no case for interference with the concurrent finding of the two Fora below under section 21(b) of the Consumer Protection Act, 1986 and hence the revision petition should be dismissed. 4. Having considered the submissions of the parties, the short point that has arisen for our decision is as to whether the two Fora below were right in returning their concurrent finding in favour of the respondent in spite of the undisputed fact that the vehicle in dispute did not have a valid registration number on the date of the accident and hence was being used in violation of the law and condition of the insurance policy. In this context, we may note that that registration of the vehicle is a mandatory requirement of the law and the relevant provisions as contained in Section 39 of the Motor Vehicles Act, 1988 may be reproduced as under: “39. Necessity for registration. – No person shall drive any motor vehicle and no owner of a motor vehicle shall cause or permit the vehicle to be driven in any public place or in any other place unless the vehicle is registered in accordance with this Chapter and the certificate of registration of the vehicle has not been suspended or cancelled and the vehicle carries a registration mark displayed in the prescribed manner: Provided that nothing in this section shall apply to a motor vehicle in possession of a dealer to such conditions as may be prescribed by the Central Government.” 5. In view of the aforesaid requirement of law, it is clear that both the fora below gravely erred in ignoring and rejecting the plea taken by the petitioner while returning their concurrent finding accepting the complaint. They should have appreciated that the use of the vehicle in question was in violation of the law itself and hence would take it beyond the protection of the insurance policy. We have therefore no hesitation in setting aside the impugned order and accepting the revision petition. The present case is squarely covered by the ratio of the two judgments relied upon by the counsel for the petitioner. We, therefore, allow the revision petition and set aside the impugned order leaving the parties to bear their own cost. ……………Sd/-……..……….. (AJIT BHARIHOKE, J.) PRESIDING MEMBER ……………Sd/-….…………… (SURESH CHANDRA) MEMBER Raj/ NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 4513 OF 2012 (Against the order dated 05.09.2012 in First Appeal No. A/12/630 of the Maharashtra State Consumer Disputes Redressal Commission, Mumbai) 1. M/s Raviraj Abhinandan Associates Millenium Star, 2nd Floor, Dhole Patil Road, Pune-01. 2. Ravindra Kumar Sakla Millenium Star, 2nd Floor, Dhole Patil Road, Pune-01. 3. Abhinandan R Sakla Millenium Star, 2nd Floor, Dhole Patil Road, Pune-01. Vs. Mrs. Surekha K Dang 505/B-2, Excel Corner, Guruwar Peth, Pune-411042 ......... Respondent BEFORE: HON'BLE MR. JUSTICE AJIT BHARIHOKE, PRESIDING MEMBER HON’BLE MR.SURESH CHANDRA, MEMBER For the Petitioner : Mr.Chetan Sharma, Sr. Advocate Alongwith Mr.Vaibhav Gaggar, Advocate And Ms. Aparna, Advocate For the Respondent : Mr.(Dr.) R.R.Deshpande, Advocate Alongwith respondent in person PRONOUNCED ON 26th JULY, 2013 ORDER PER HON’BLE MR. JUSTICE AJIT BHARIHOKE, PRESIDING MEMBER This revision is directed against the order of the State Consumer Disputes Redressal Commission Maharashtra, Mumbai dated 05.09.2012 whereby the State Commission dismissed the appeal preferred by the petitioner / opposite party passed against the order of the District Forum whereby the District Forum partly allowed the complaint in following terms: “1. The complaint of the complainant is partially allowed 2. As provided in the agreement, upon payment of the balance amount payable to the respondents, the respondents shall within six weeks of such payment, deliver possession of the said flat no.105, first floor, building no.A-4, ‘Raviraj Colorado’, Survey No.44, Kondwa Khurd, Pune 48, with all facilities and amenities to the complainant; 3. The respondents shall pay interest @ 12 % per annum on the said amount of Rs.6,57,000/- from May 2010 till the possession is delivered to the complainant and further a sum of Rs.1000/- towards costs of this complaint within six weeks from the receipt of copy of this order”. 2. Briefly put relevant facts for the disposal of the revision petition are that respondent Ms. Surekha K Dang filed a consumer complaint, against the petitioner (s) (builder), alleging deficiency in service on the part of the petitioner for their failure to hand over the possession of residential flat booked by her within the stipulated time. 3. The complaint was contested by the petitioners / opposite party, who in their reply admitted that that complainant / respondent had booked a flat in the scheme floated by them and made certain payments during the period 14.04.2009 to 13.11.2009 adding upto the extent of Rs.6,57,000/-. Petitioners in their written version claimed that the project could not be completed in time because of genuine reasons and it was not possible to give the exact time frame within which the possession of flat would be given to the complainant. The petitioners further claimed in the written version that because of the hurdles in the completion of project and the delay caused. They did not demand balance consideration of Rs.8,03,000/- from the complainant. The petitioners, however, admitted having received a sum of Rs.6,57,000/- from the complainant in terms of the construction linked schedule of payment. The petitioners, however, claimed that as per the agreement they could cancel the contract, however, they were ready to deliver possession of the flat to the complainant within next 18 to 24 months without asking for escalation of price provided the complainant was ready to wait. 4. The District Forum on consideration of the evidence led by the parties allowed the complaint and directed the petitioners / opposite parties to deliver the possession of the flat to the complainant after receiving the balance consideration amount agreed between the parties. The District Forum, also awarded 12% interest on the amount of Rs.6,57,000/- already paid to the opposite parties till the handing over of the possession alongwith litigation cost of Rs.1000/-. 5. Being aggrieved of the order of the District Forum, the petitioners preferred appeal before the State Commission. After service of notice of the appeal on respondent, the petitioners failed to put any appearance on hearing dated 05.09.2012 and the State Commission instead of dismissing the appeal for non-prosecution dismissed it on merits after considering the record. 6. Being aggrieved of the concurrent finding returned by the State Commission, the petitioners have preferred this revision. 7. Learned Shri Chetan Sharma, Senior Advocate appearing on behalf of the petitioners have firstly contended that the impugned order is not sustainable in law for the reason that it has been passed ex parte without giving an opportunity of being heard to the petitioners. In this regard, he has drawn our attention to the impugned order where it is mentioned that no one was present at the relevant date before the State Commission. We do not find any merit in this submission because the State Commission was compelled to decide the appeal exparte because of conduct of the petitioners / appellant who opted not to appear either in person or through counsel. The State Commission could have dismissed the appeal for non-prosecution but opted to adopt better course in going through the record and deciding the appeal as per grounds taken in Memorandum of Appeal. Thus the procedure adopted by the State Commission cannot be faulted. 8. Next contention of learned counsel for the petitioner is that though a plea was taken in the appeal that the complaint filed was pre-mature, it was not decided by the State Commission. This contention is misconceived for the reason that on perusal of the impugned order, we find that the State Commission has dealt with the aforesaid plea and dismissed the same with the following observations: “Furthermore, as per para 7.6 0f the written version he further made submission that the possession could be given within next 18-24 months without asking for any escalation of price. Said period is almost over by this time. Under the circumstances we find that the ground taken in appeal to justify delay in handing over the possession and on that basis to advance a submission that the complaint was premature does not hold good and we find no merit in such submission”. 9. Thirdly, the impugned order is assailed on the ground that both the fora below have failed to appreciate the bonafides of the petitioners who were prevented from delivering the possession of the flat in time because of genuine reasons and who had offered to refund the amount paid by the complainant, if she so desired vide their reply dated 25.10.2010 to the legal notice given by the complainant. 10. We find no merit in the aforesaid contention. Perusal of the notice dated 27.09.2010 sent by the complainant to the partner of the opposite party would show that vide this notice, the complainant had expressed her concerns about no progress of the construction work and called upon the petitioners to intimate the likely date on which the possession would be delivered to her. In response to that notice instead of intimating a firm date or approximate date of delivery of possession, the petitioner had offered to repay the amount deposited by the complainant alongwith interest paid by her on the home loan raised and appropriate interest. This response in our view does not certify the bonafides of the opposite party. It is a well known fact that during the relevant period, the rates of the property have gone high, therefore, the offer of the builder to return the money instead of delivery of flat is no evidence of his bonafides. On the contrary, it reflects on the malafides of the builder who wanted to make profit due to escalation of price of property by offering refund of money. 11. Lastly, the learned counsel for the petitioner has drawn our attention to clause 11 of the agreement between the parties which provides that the purchaser shall use the unit or any part thereof or permit the same to be used only for residential / commercial purpose. From this, learned counsel has urged us to conclude that the services of the opposite party were availed by the complainant for commercial purpose, therefore, the complainant does not fall within the definition of ‘consumer’ in terms of section 2 (1) (d) of the Consumer Protection Act, 1986. There is no merit in this contention. Merely because clause 11 of the agreement provides that the purchaser can use the flat for residential / commercial purpose, it cannot be concluded that the petitioner booked the flat for commercial purpose. Opposite party has led no evidence to provide this fact. Otherwise also, this contention is beyond the pleadings as plea of non maintainability of the complaint has not been taken in the written version filed in response to the complaint. Learned counsel for the petitioner has also tried to emphasise that the complainant is a property dealer and she had entered into the agreement with the opposite party with a motive to earn profit on account of escalation of price with the passage of time. This argument is not acceptable because it is beyond the pleadings. Otherwise also, there is no evidence on record to this effect. 12. Coming to the impugned order. The State Commission has dismissed the appeal relying upon the written version of the petitioner particularly para 7.6 wherein it was stated that opposite parties feel that they would be able to give possession within 18 to 24 months without asking for any escalation of price provided the complainant was willing to wait. When the appeal was decided the stipulated period of 18 to 24 months was over, therefore, the State Commission took a view not to interfere with the order of the District Forum. We do not find anything wrong in the approach adopted by the State Commission. In our considered view, the petitioner has failed to point out any illegality or material irregularity committed by the State Commission which may call for interference by this Commission in exercise of its revisional jurisdiction. The revision petition is, therefore, dismissed with cost of Rs.10,000/-. ……………………Sd/-………………… [ AJIT BHARIHOKE, J] ( PRESIDING MEMBER) ..…………Sd/-………………………. [ SURESH CHANDRA ] MEMBER Am/ NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI REVISION PETITION NO. 2446 OF 2013 (From the order dated 19.03.2013 in First Appeal No. 39/2012 of DELHI State Consumer Disputes Redressal Commission) 1. Canadian Institute for International Studies (Not known as Continental Institute of International Studies) Village Jalvehra P.O. Nabhipur, G.T. Road, NH-1, District Fatehgarh Sahib Punjab Through its Authorised Representative Mr. Bharat Lal 2. World Wide Immigration Consultancy Services Ltd (WWICS) A-31, 3rd Floor, Near Raja Garden Chowk, Rajouri Garden, New Delhi – 110027 Through its Authorised Representative Mr. Bharat Lal. ... Petitioners Versus Ekta Sharma w/o Mr. Rumeet Sharma Q/1A, Jangpura Extn. New Delhi – 110014 … Respondent(s) BEFORE HON’BLE MR. JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER HON’BLE DR. B.C. GUPTA, MEMBER APPEARED AT THE TIME OF ARGUMENTS For the Petitioner(s) Mr. Sunil Goyal, Advocate PRONOUNCED ON : 26th JULY 2013 ORDER PER DR. B.C. GUPTA, MEMBER This revision petition has been filed under section 21(b) of the Consumer Protection Act, 1986 by the petitioner against the impugned order dated 19.03.2013 passed by the Delhi State Consumer Disputes Redressal Commission (for short ‘the State Commission’) by which FA No. 39/2012 filed by the petitioner against the order dated 04.08.2011 passed by District Forum was dismissed on the ground that there was a delay of 135 days in filing the said appeal. 2. Brief facts of the case are that the respondent Ekta Sharma filed a consumer complaint number 703/2006 before the District Forum, saying that she had taken admission in the “Bachelor of Nursing” degree course being run by the petitioners with effect from 1.11.2004, and that she deposited the necessary fee amounting to Rs.2,82,000/- with the petitioners, out of which Rs.2,44,000/- had been raised as loan from the Bank. She was told later on that she was not eligible for the said course. The District Forum in their order dated 4.08.2011 directed the petitioners/OPs to refund 50% of the fee/charges paid/deposited by the complainant within one month of the receipt of the order. An appeal filed by the petitioners/OPs against this order, was dismissed vide impugned order by the State Commission, saying that the same had been filed after a delay of 135 days. It is against this order that the present revision petition has been filed. 3. At the time of admission hearing before us, learned counsel for the petitioner stated that the order passed by the District Forum was dated 04.08.2011, but they had shifted their working place from Mohali, Punjab to New Delhi in the year 2010 by virtue of letter dated 17.7.2010. The order, in question, had been received by them on 2.12.2011 and the appeal was filed before the State Commission on 17.01.2012. They had explained the reasons for delay but the State Commission wrongly relied upon some orders quoted in the body of the impugned order. 4. We have examined the material on record and given a thoughtful consideration to the arguments advanced before us. 5. The complaint, in question, was moved before the District Forum in the year 2006 and it was decided by the District Forum vide order dated 4.08.2011. In case, the petitioners had moved their place of work in the year 2010, it was their bound duty to inform the court about their new place of work. The District Forum, therefore, cannot be put to blame that they sent the copy of the order, in question, to a wrong address. Moreover the case has been contested by the petitioners before the District Forum and they are supposed to be in the knowledge of the order passed by the District Forum. The State Commission have rightly observed in their order that it was a contested case and the petitioners were regularly appearing before the District Forum. It is clear, therefore, that the petitioners have not been able to give any cogent and convincing explanation for the delay in filing the appeal. As per their own version, they received copy of the order on 2.12.2011 but the appeal was filed on 17.1.2012, i.e., after another period of one and a half month, for which they have not been able to give any explanation. 6. It has been observed by the Hon’ble Apex Court in many cases, decided recently that unless there is a convincing explanation about the delay in filing the case, the same could not be condoned. Reference may be given to the orders passed by the Apex Court in R.B. RamlingamVs. R.B. Bhavaneshwari 2009 (2) Scale 108, it has been observed: “We hold that in each and every case the Court has to examine whether delay in filing the special appeal leave petitions stands properly explained. This is the basic test which needs to be applied. The true guide is whether the petitioner has acted with reasonable diligence in the prosecution of his appeal/petition.” 7. In Ram Lal and Ors. Vs. Rewa Coalfields Ltd., AIR 1962 Supreme Court 361, it has been observed: “It is, however, necessary to emphasize that even after sufficient cause has been shown a party is not entitled to the condonation of delay in question as a matter of right. The proof of a sufficient cause is a discretionary jurisdiction vested in the Court by S.5. If sufficient cause is not proved nothing further has to be done; the application for condonation has to be dismissed on that ground alone. If sufficient cause is shown then the Court has to enquire whether in its discretion it should condone the delay. This aspect of the matter naturally introduces the consideration of all relevant facts and it is at this stage that diligence of the party or its bona fides may fall for consideration; but the scope of the enquiry while exercising the discretionary power after sufficient cause is shown would naturally be limited only to such facts as the Court may regard as relevant.” 8. Hon’ble Supreme Court after exhaustively considering the case law on the aspect of condonation of delay observed in Oriental Aroma Chemical Industries Ltd. Vs. Gujarat Industrial Development Corporation reported in (2010) 5 SCC 459 as under; “We have considered the respective submissions. The law of limitation is founded on public policy. The legislature does not prescribe limitation with the object of destroying the rights of the parties but to ensure that they do not resort to dilatory tactics and seek remedy without delay. The idea is that every legal remedy must be kept alive for a period fixed by the legislature. To put it differently, the law of limitation prescribes a period within which legal remedy can be availed for redress of the legal injury. At the same time, the courts are bestowed with the power to condone the delay, if sufficient cause is shown for not availing the remedy within the stipulated time.” 9. Hon’ble Apex Court in (2012) 3 SCC 563 – Post Master General & Ors. Vs. Living Media India Ltd. and Anr. has not condoned delay in filing appeal even by Government department and further observed that condonation of delay is an exception and should not be used as an anticipated benefit for the Government departments. 10. Hon’ble Apex Court in 2012 (2) CPC 3 (SC) – Ansul Aggarwal Vs. New Okhla Industrial Development Authority observed as under: “It is also apposite to observe that while deciding an application filed in such cases for condonation of delay, the Court has to keep in mind that the special period of limitation has been prescribed under the Consumer Protection Act, 1986, for filing appeals and revisions in Consumer matters and the object of expeditious adjudication of the Consumer disputes will get defeated, if this Court was to entertain highly belated petitions filed against the orders of the Consumer Foras”. 11. Based on the above discussion, this revision petition is ordered to be dismissed at admission stage and the order passed by the State Commission upheld. Sd/(K.S. CHAUDHARI J.) PRESIDING MEMBER Sd/(DR. B.C. GUPTA) MEMBER RS/ NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI FIRST APPEAL NO. 432 OF 2008 (Against the order dated 08.08.2008 in Complaint Case No. 122/2008 of the Delhi State Consumer Disputes Redressal Commission) Canara Bank Head Office at 112, J.C. Road Bangalore, Karnataka And Branch at Kashmere Gate Delhi … Appellant Versus 1. M/s Jain Motor Trading Company No. 2704, Kashmere Gate Delhi 2. Mr. Virender Kumar Jain R/o 49, Rajpur Road Civil Lines, Delhi … Respondents BEFORE: HON'BLE MRS. VINEETA RAI, PRESIDING MEMBER HON’BLE MR. VINAY KUMAR, MEMBER For Appellant : Mr. Manish Chauhan, Advocate For Mr. Vivek Kumar Tandon, Advocate For Respondents : Mr. Rohit Gandhi, Advocate with Mr. Virender Kumar Jain (R-2) in person Pronounced : 29th July, 2013 ORDER PER VINEETA RAI, PRESIDING MEMBER 1. This First Appeal has been filed by Canara Bank, Opposite Party before the Delhi State Consumer Disputes Redressal Commission and Appellant herein being aggrieved by the order of that Commission which had allowed the complaint of deficiency in service and unfair trade practice made against it by M/s Jain Motor Trading Company, Respondent herein and Original Complainant before the State Commission. 2. In his complaint before the State Commission, Respondent/Complainant had contended that he had bank account no. 184 with Appellant/Bank from the early 1970s which it was operating regularly. Since Respondent/Complainant felt need of an OCC account, it requested for the same to the Appellant/Bank, who converted their above account into an OCC account after the Respondent/Complainant had duly complied with the various formalities to open such a account, which included mortgaging his property at Kashmere Gate as collateral security against the said Account. This facility continued without any problems till 2004 when due to certain unavoidable reasons, Respondent/Complainant was unable to pay the outstanding amount of Rs.51.84 Lakhs as on September, 2004 to Appellant/Bank and, therefore, the OCC account was declared as NPA by the Appellant/Bank on 31.10.2004 vide its letter dated 28.02.2005. However, with a view to settle the issue Respondent/Complainant entered into One Time Settlement (OTS) with Appellant/Bank, according to which a sum of Rs.4 Lakhs (apart from Rs.1 Lakh already deposited) was to be paid immediately and the balance sum of Rs.47 Lakhs was to be deposited within 6 months from the date of issue of that letter and if this amount was deposited within 90 days then no interest was to be charged. In case it was deposited thereafter, then interest at PLR(s) was to be charged till clearance. In terms of the OTS, Respondent/Complainant started making the payments and requested Appellant/Bank for extension of time by another 6 months. However, despite this, Appellant/Bank cancelled the OTS on the grounds of non-payment. Appellant/Bank, however, accepted the money tendered Respondent/Complainant thereafter which amounted to extension of time to clear the dues. Further, as per verbal assurances given by the officials of Appellant/Bank, the time had been extended upto 25.06.2008 by which time the entire amount of Rs.52 Lakhs was paid. Respondent/Complainant thereafter approached Appellant/Bank to get back the property documents in respect of the mortgaged property, which Appellant/Bank refused to return on the ground that certain dues towards interest were still to be paid and raised an illegal demand of Rs.22,46,005/- in this respect. Being aggrieved, Respondent filed a complaint before the State Commission on grounds of deficiency in service and unfair trade practice and requested that Appellant/Bank be directed to release the documents of mortgaged property to him with compensation of Rs.5 Lakhs towards inconvenience, mental agony and harassment and further Rs.5 Lakhs by way of damages. 3. Appellant/Bank on being served filed a written rejoinder before the State Commission denying that there was any deficiency in service. It was contended that Appellant/Bank was fully justified in not releasing the documents of mortgaged property since there was a clear violation of the OTS. It was specifically stated that the terms and conditions under the OTS were as follows : “… the Bank has accepted your compromise proposal on the following terms and conditions: To pay Rs.52,00,000/- (Fifty Two Lacs Only) in full and final settlement payable as – (a) Rs.1,00,000/- already adjusted deposited by you at the time of submission of OTS Proposal. (b) Rs.4,00,000/- to be deposited immediately. (c) Balance of Rs.47,00,000/- will be deposited within six months from the date of this letter. If paid within 90 days no interest shall be charged. Beyond 90 days interest at PLR(s) shall be charged from the date of communication till clearance. You may treat the account closed only after depositing the amount as mentioned above. The securities will be released only after the liquidation of Bank’s outstanding as detailed above. You are to withdraw claim against the Bank, if any. If we shall not receive the amount as per above stipulations, the concessions permitted in the above proposal shall be withdrawn automatically and the bank shall have right to claim the full amount.” Since Respondent/Complainant did not adhere to the above terms and conditions of the OTS by not depositing the entire amount within a period of 6 months, the offer in the OTS became null and void and the Respondent/Complainant was liable to pay interest as claimed by the Appellant/Bank. It was specifically denied that any assurance, verbal or otherwise, had been made to extend the time limit for payment of the outstanding amount. In fact only a sum of Rs.25 Lakhs had been deposited upto 11.07.2007 i.e. after 6 months and the remaining amount was paid only in 2008. 4. The State Commission after hearing the parties and on the basis of evidence produced before it allowed the complaint by observing as follows: “4. It is contended by the Ld. Counsel for the O.P. that since the applicant/complainant did not adhere to the terms of OTS by depositing the entire amount within 90 days and deposited the same after more than six months, the offer in the OTS proposal became null and void making the complainant liable to pay interest as claimed by the O.P. Bank. … 5. Let us assure that time was the essence of OTS. But that does not mean that the late deposit of amount by few months was an act of malafide. For breach of OTS (One Time Settlement) terms the OP-Bank was at the most entitled to claim interest on late deposit and should not have resorted to the act of recovering money which was in the ordinary course due from him.” The State Commission, therefore, allowed the complaint in the following terms : “i) O.P-Bank shall release the security documents as it has already received Rs.52.00 Lakhs, but against payment of agreed interest for the delayed period of six months only on the entire amount of Rs.52.00 Lakhs, as this will take care of the pleas of the O.P. that time was the essence of OTS and also in view of the bonafide of the applicant/complainant in making the payment of the entire amount. However, the O.P-Bank is not concerned with the internal dispute of the partners. The O.P-Bank shall issue the documents in the name of the owner of the property whose property has been mortgaged. ii) Amount of Rs.3.00 Lakhs lying deposited with this Commission shall be released to the applicant/complainant.” 5. Being aggrieved by the order of the State Commission, the present appeal has been filed. 6. Learned Counsels for both parties were present and made oral submissions. 7. Counsel for the Appellant/Bank reiterated that there was a clear violation of the terms and conditions of the OTS and Respondent/Complainant was required to clear entire amount which was due by 11.03.2007. However, by that date Respondent/Complainant had only deposited Rs.25.00 Lakhs and in fact as indicated in the letter dated 19.02.2008 (Annexure-4 of the paper-book) Appellant/Bank wrote to the Respondent/Complainant that they would withdraw the OTS if Respondent/Complainant did not liquidate the amount due within 7 days of the receipt of that letter. Respondent/Complainant was again given additional time of 15 days by the Appellant/Bank for liquidating the account with interest vide letter dated 15.05.2008 (Annexure-5 of the paper-book). When there was no response, the OTS was withdrawn on 18.06.2008 i.e. well after the stipulated period for making the entire payment. Respondent/Complainant in the meantime filed a complaint before the State Commission for release of the documents of mortgaged property and during this period also paid the entire money in terms of the OTS. However, since time was the essence of the OTS, as observed by the State Commission, Appellant/Bank had rightly asked Respondent/Complainant to pay the amount of interest due once the OTS had been cancelled. Since this was not paid, Appellant/Bank was justified in not releasing the property documents which was mortgaged with them. Counsel for the Appellant/Bank also contended that in the written rejoinder filed before the State Commission they had stated that the Respondent firm being a commercial concern is not a ‘consumer’ as defined under the provisions of the Consumer Protection Act, 1986 and this fact has not been dealt with in the order of the State Commission. 8. Counsel for Respondent/Complainant on the other hand while agreeing that Respondent/Complainant had accepted the terms and conditions of the OTS stated that because of some financial problems it could not pay the entire amount by the stipulated period and, therefore, sought extension of time for the same. According to the Counsel for Respondent/Complainant, Appellant/Bank on their request seeking extension of time had extended the time for payment vide its letter dated 11.07.2007 till 25.06.2008 by which time the entire dues had been paid to the Bank. This was also the finding of the State Commission in its order. In fact as is clear from the letter dated 19.02.2008 (Annexure-4), the OTS was revoked after Respondent/Complainant had paid the entire amount and not before that period. Further, the State Commission had directed Respondent/Complainant to pay a sum of Rs.2 Lakhs as interest for the slightly delayed period in settling the OTS which had also been paid by him. Counsel for the Respondent/Complainant challenged the contention of Counsel for the Appellant/Bank that Respondent was not a ‘consumer’ in terms of Section 2(1)(d)(ii) of the Consumer Protection Act, 1986. It was stated that there was no commercial activity, profit or interest in taking the OCC account and this issue stands well settled by a number of judgments of the Hon’ble Supreme Court as also National Commission. The present appeal, therefore, deserves to be dismissed. 9. We have heard learned Counsels for the parties and have also carefully gone through the evidence on record. The fact pertaining to the Respondent/Complainant having an OCC account with the Appellant/Bank to help its financial conditions is not in dispute. It is also a fact that the said account was declared as NPA on 31.10.2004 and that subsequently the parties entered into an OTS as per the payment schedule, as has been reproduced in the order of the State Commission. It is also not disputed that the Respondent/Complainant could not pay the entire amount as per the payment schedule i.e. within 6 months during which time he paid only Rs.25 Lakhs upto 11.07.2007. The State Commission as a first Court of fact had clearly concluded that at the request of the Respondent/Complainant for paying the remaining amount, the Appellant/Bank had indeed written a letter extending this period. We see no reason to dispute the same because the first letter written by the Appellant/Bank giving time to Respondent/Complainant to settle the account was dated 19.02.2008 which clearly indicates that the time for making the payment was extended from 11.07.2007. It is further a fact that before the filing of the complaint before the State Commission, Respondent/Complainant had paid the entire amount which was accepted by the Appellant/Bank. If the Appellant/Bank wanted to scrap the OTS, it should not have then accepted the delayed payment. Further, as observed by the State Commission, if there was some delay on the part of Respondent/Complainant, the Bank could have charged interest on the same instead of not releasing the property documents once it had accepted the entire amount due from Respondent/Complainant as per the conditions of the OTS. To sum up, we agree with the finding of the State Commission for not accepting the contention of Appellant/Bank. 10. We also do not accept the contention of Counsel for Appellant/Bank that Respondent being a commercial firm is not a ‘consumer’ as per the provisions of the Consumer Protection Act, 1986. Commercial concerns per se are not excluded from filing a complaint under the Consumer Protection Act, 1986 if it does not involve direct generation of profits or resale. Also as stated in the instant case, the OCC facility was sought from Appellant/Bank to help resolve the financial difficulties being faced by Respondent which was not per se a commercial activity generating profits. As pointed out by Counsel for Respondent, these aspects are well settled in a number of judgments, including of this Commission as also of the Hon’ble Supreme Court e.g. Harsolia Motors Vs. National Insurance Co. Ltd. [I (2005) CPJ 27 (NC)] and Madan Kumar Singh Vs. Distt. Magistrate, Sultanpur [(2009) 9 SCC 79]. 11. In view of these facts, we see no reason to interfere with the order of the State Commission especially since the Respondent/Complainant has also paid the interest on the delayed payment as directed by the State Commission. We, therefore, uphold the order of the State Commission in toto and dismiss the present appeal. No costs. Sd/(VINEETA RAI) PRESIDING MEMBER Sd/(VINAY KUMAR) MEMBER Mukesh NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI FIRST APPEAL NO. 430 OF 2012 (Against the order dated 03.05.2012 in CC/11/224 of the State Commission, Maharashtra) M/s. Tolani Shipping Co. Ltd., [A company registered under The Companies Act, 1956] Through its Authorised Signatory Seeta Venkatraman] 10- A, Bakhtawar Nariman Point, Mumbai- 400021 …..Appellant Versus Sterling Holiday Resort (I) Ltd. 427, 4th floor, B-Wing, Chintamani Plaza, Mathuradas Vasanji Road, New Gurunanak Petrol Pump Chakala Andher i (East), Mumbai- 400099 .....Respondent BEFORE: HON’BLE MRS. VINEETA RAI, PRESIDING MEMBER HON’BLE MR. VINAY KUMAR, MEMBER For the Appellant : Mr. S.K. Sharma, Advocate Mr. U.B. Wavikar, Advocate & Mr. Vikas Nautiyal, Advocate For the Respondent : Mr. Jayant Bhushan, Sr. Advocate with Mr. Buddy A. Ranganadhan, Advocate & Mr. Raunak Jain, Advocate PRONOUNCED ON: 30 July 2013 ORDER PER MR. VINAY KUMAR, MEMBER The appellant, M/s. Tolani Shipping Co. has challenged the order of the Maharashtra State Consumer Disputes Redressal Commission in Complaint Case No.CC/11/224. The complaint has been dismissed at the stage of admission itself on the ground of limitation. According to the State Commission, the cause of action had arisen in the year 2002 while the complaint was filed on 29.8.2011. The State Commission has made the following observations:“This letter of 2002 must be taken as the date on which cause of action accrued to the complainant company. By this letter no compliance was made for the demand made by M/s. Tolani Shipping Co. and from that day within two years this complaint should have been filed. But this complaint came to be filed on 29/08/2011 alleging that since Time Share Agreement permitted M/s. Tolani Shipping Co. employees to use Holiday Resorts as per membership given to them by M/s. Sterling Holiday Resort (I) Ltd. upto 2094-95, the complaint is having continuing cause of action and, therefore, it is within limitation. However, we should not forget the letter dated 27/02/2002 sent by the complainant to opponent company wherein demand for refund of 28,00,000/-, besides the liquidated damages of 30,00,000/- and compensation of 10,00,000/- aggregating to 68,00,000/was made and it was not paid at all by the M/s. Sterling Holiday Resort (I) Ltd. When this is so, in our view the complainant company should have filed consumer complaint within two years from 27/02/2002 and since it is not filed in the year 2004 and since it is filed for the first time on 29/08/2011, in our view the complaint as filed by the complainant is absolutely barred by limitation.” 2. Counsels for the Appellant and for the respondent have been heard and the records produced have been perused carefully. 3. Counsel for the appellant has argued that subsequent to the above mentioned letter of 27.2.2002 from the Complainant to the OP/Sterling Holiday Resort (I) Ltd, the latter had been acknowledging its liability and assuring to fulfil its obligations. Thereby the limitation has continued to run as the OP did not discharge its liabilities till the complaint was filed. In this behalf, learned counsel referred to the letter of 8.9.2010 from AGM (Customer Service) of the OP to Director (Legal and Secretarial) of the Complainant. The letter reads as follows:“We are in receipt of your letters dated 4.9.2009 and 3.08.2010 with regard to your memberships at Lonavala. We have already explained the situation vide letter dated 29th July 2009 due to which the delay in constructing our own resort at Lonavala has occurred. Having shown patience all this while we would request you to bear with us for one more year as we are taking all possible efforts to construct our-resort atLonavala.” 4. The appellant counsel forcefully argued that this letter has the effect of extending the cause of action till 8.9.2010. He also sought to rely upon the decision in Lata Construction and others Vs. Dr. Rameshchandra Ramniklal Shah and Anr., (2001) 1 SCC, 586. In this case, under an agreement of 27.1.1987 the developers had undertaken to provide a flat to the Complainant, but had failed to do so despite receiving payments towards the same. In 1991 the developers entered into a fresh agreement with the Complainant, agreeing to pay a sum of Rs.9.51 lakhs, in lieu of the flat. The respondent/Complainant entered into the fresh agreement with the appellant developers without prejudice to their rights under the agreement of 1987. The developers failed to act as per the commitment under both the agreements. Therefore, respondent/Complainant approached the National Commission, which awarded a sum of Rs.9.51 lakhs in favour of the Complainant, with interest from the date of the agreement in 1991. Hon’ble Supreme Court of India upheld the decision of the National Commission observing that since rights under the agreement of 1987 had not been given up, the developer was under continuing obligation to provide a flat to the Complainant. It was observed that:“11. In the instant case, the rights under the original contract were not given up as it was specifically provided in the subsequent contract that the rights under the old contract shall stand extinguished only on payment of the entire amount of Rs.9,51,000. Since the amount was not paid the appellants as stipulated by the subsequent contract, the rights under the original contract were still available to the respondents and they could legally claim enforcement of those rights. Obviously, under the original contract, the appellants were under an obligation to provide a flat to the respondents. This right would come to an end only when the appellants had, in pursuance of the subsequent contract, paid the entire amount of Rs.9,51,000 to the respondents. Since they had not done so, the respondents could legally invoke the provisions of the earlier contract and claim before the Commission that there was “deficiency in service” on the part of the appellants.” 5. The above facts stand on a very different footing from those in the matter before us. It has been argued by the respondent counsel that no novation of contract was involved. In fact, alternative facility, offered at other locations, had also been availed by the appellant. Therefore, it was contended that the question of refund would not arise. 6. Learned counsel for the respondent also relied upon the decision State of Kerala Vs. T.M. Chacko, (2000) 9 SCC 722. This was a matter in which the respondent, as a successful bidder in auction, had acquired a right to collect and remove the forest produce from the given area, on or before 31.3.1974. Only a part of it had been collected by him when fire broke out on 21.2.1974 and destroyed the remaining uncollected forest produce in the concerned area. On the representation of the respondent to reduce the bid amount on the ground of the fire, the Forest department granted him further time of 45 days to remove the produce. The respondent neither removed the produce nor paid the balance bid amount. The Government cancelled the contract and ordered auction at the risk and loss of the respondent. The respondent filed a civil suit claiming compensation and refund of the bid amounts. The trial court and the High Court both came to the conclusion that the suit was not barred by limitation as the appellant, State of Kerala, had acknowledged the liability, in the concerned two communications, one rejecting the prayer for remission of balance of the bid amount and the other communicating confiscation of the un-removed forest produce. 7. The Supreme Court disagreed with the above view and allowed the appeal of the State of Kerala. It was held that for treating a writing signed by the party as an acknowledgment, the person acknowledging must be conscious of his liability and the commitment should be made towards that liability. In this case, neither the claim for refund of the bid amount was under consideration of the department of Forest nor could the two communications from the department of Forest be treated as acknowledgment of the liability under the refund claim of the respondent. Hon’ble Supreme Court therefore, rejected the contention that in view of the fact that period to perform the contract had been extended by the State of Kerala till 10.8.1974, the failure date i.e. the date for seeking refund should also be taken as extended till 10.8.1974. 8. We need to consider the case of the appellant/ Tolani Shipping Company, in the light of the two decisions of Hon’ble Supreme Court of India detailed above. The cause of action, as rightly pointed out by the State Commission, arose on 27.2.2002 when the appellant/Complainant wrote to the respondent/Sterling Holidayh Resort (I) Ltd. that :“As per the terms and conditions of the Time Share Agreement you are liable to pay to us liquidated damages for delay in providing the holiday resort at Lonavala. Under these circumstances, we hereby demand payment of the principal sum of Rs.28.00 lakhs besides liquidated damages of Rs.30.00 lakhs computed at 18% per annum and compensation of Rs.10.00 lakhs aggregating to Rs.68.00 lakhs. It is very disparaging to note that instead of developing the resort at Lonavala your Company is adopting ways and means to hoodwink the customers. We are not agreeable to the allotment at “Kodai Valley View” resort and we once again demand the amount of Rs.68.00 lakhs, failing payment of which, appropriate proceedings for recovery of amount and winding up of the company will be adopted at your risk and consequences.” 9. As seen from the record, this was followed by correspondence between two sides but the consumer complaint came to be filed only in 2011, not within the period two years computed from the letter of 27.2.2002. The appellant has sought to rely upon the letter of 8.9.2010 written to it by the respondent, discussed earlier in this order. Clearly, this letter does not even mention the claim for refund and interest thereon. Therefore, in our view, this letter cannot be treated as acknowledgment of a liability of Rs.68 lakhs, the issue raised in the Complainant’s letter of 27.2.2002. Therefore, the question of cause of action having continued from 27.2.2002 till 8.9.2010 or having arisen again on the later date, would not arise at all. 10. In conclusion, we find ourselves in complete agreement with the view of the State Commission that the complaint filed on 29.8.2011 is barred by limitation. Consequently, the First Appeal No. 430 of 2012 is held to be devoid of any merit and is dismissed as such. No order as to costs. …..……………Sd/-.…….…… (VINEETA RAI) PRESIDING MEMBER …..…………Sd/-….…….…… (VINAY KUMAR) MEMBER S./- NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI (1) REVISION PETITION NO. 1451 to 1489 OF 2011 (Against the order dated 20.12.2010 in Appeal No. 1224/2008 of the State Commission, Andhra Pradesh) Syngenta India Ltd. Rep. by its Managing Director Seeds Division, H. No. 1170/27,Revenue Colony, Sivaji Nagar, Pune – 411007, Maharashtra ....... Petitioner Versus 1. P.Chowdaiah S/o P.Naganna, Agriculturist, R/o Pamulapadu Village and Mandal Kurnool District, Andhra Pradesh 2. P.Sreenivasulu S/o Chowdaiah, Agriculturist R/o Pamulapadu Village and Mandal, Kurnool District, Andhra Pradesh 3. Sai Agro Agencies Rep. by its Managing Director Distributor of Syngenta Seeds Near RTC Bus-Stand, Nandyal, Andhra Pradesh …... Respondents BEFORE: HON’BLE MR. JUSTICE V.B. GUPTA, PRESIDING MEMBER HON’BLE MRS. REKHA GUPTA, MEMBER For the Petitioner : Mr. Subramonium Prasad, Advocate For the Respondents : Mr. Debojit Borkakali, Advocate ( In RPs No. 1451 to 1473 of 2011) For the Respondents : Mr. V. Sridhar Reddy, Advocate (In RP Nos. 1474 to 1489 of 2011 ) Pronounced on: 31st July, 2013 ORDER PER MR. JUSTICE V.B. GUPTA, PRESIDING MEMBER As common question of facts and law are involved in the above noted revision petitions, same are being disposed of by this single order. 2. Andhra Pradesh State Consumer Disputes Redressal Commission, Hyderabad (for short, ‘State Commission’) vide common impugned order dated 12.12.2010, disposed of 39 appeals in all filed by the unsuccessful complainants/agriculturists against manufacturer of ‘Roshini Chilly Seeds’. State Commission has taken (Appeal No. 1244 of 2008, Sygenta India Ltd. Vs. P. Chowdaiah and Ors.) that is, RP No. 1451 of 2011 as the lead case. 3. Case of Complainants in brief is that they are agriculturists owing agricultural land in Pamulapadu village of Kurnool District. They purchased 40 packets of hybrid chilly seeds called ‘Roshni’ @ Rs.170/- per packet. manufactured by Petitioner/O.P.No.2 and sold by its Distributor-cum-Agents/ Respondents, on 7.6.2006. Complainants had sown the seeds, adopted the agricultural practices and applied fertilizers and pesticides and incurred an expenditure of Rs.30,000/- per acre. Despite assurance of yield of 25 quintals per acre, complainants hardly could get 2 quintals per acre due to defect in the seeds. The growth was poor and did not give even the minimum yield. When they complained to the agricultural department, Joint Director of Agriculture along with Scientists and Asst. Agricultural Officer visited the crop in the last week of December, 2006 and opined that the seeds were defective. In fact local variety 334 had yielded around 12-14 quintals per acre. It has been further alleged by the complainants that then Senior Scientist, Regional Agricultural Research Station, Nandyal along with the Assistant Director of Agriculture and Agricultural Officer of Atmakur Division, visited to inspect the crops on 14.2.2007 and opined that the over-all hybrid vigor was very poor and due to this poor growth, less pod productive plants and more poor productive plants were observed and due to these reasons poor yields are expected. Thus, complainants had in all sustained a loss of 90 quintals and therefore claimed Rs. 6,800/- towards refund of cost of seeds, Rs.3,79,845/- towards compensation, Rs.1,10,000/- towards cost of fertilizers, pesticides and labour etc. besides Rs.50,000/- towards mental agony in all Rs.5,46,645/- A tabular form has been given mentioning the claims of each of the complainants in all these cases at para 19 of the impugned order. 4. On the other hand, case of petitioner’s company is that as per bills or the brochure, petitioner has not given any guarantee regarding the growth and yield of the crop, which depends upon the environmental components. Further, it is a common knowledge that condition of crop and quality of yield depends upon many factors including the physical condition of the soil, moisture content at the sowing time, the sowing methodology, water quality used for irrigation, long dry spell in the atmosphere and other diseases and virus that may attack the plants. It is further stated that that total period of crop duration is 6 – 9 months including the nursery period. The field inspection was done only after six months of sowing by the Scientist. By that time, the crop was at the end of its life. Further, report of experts shows that the crop was infected with pest and that too sucking pest. 5. It was further alleged that neither the taking of experts to the field nor the report of the experts were communicated to the petitioner’s company. Everything was done at the back of petitioner’s company and without its knowledge. Thus, there is no deficiency on the part of the petitioner’s company. 6. The District Consumer Forum, Kurnool (for short, ‘District Forum’) vide its order dated 1.12.2008, after considering the evidence placed on record, opined that the printed brochure relating to hybrid Roshini seeds do not anywhere mention the expected yield or that it was resistant to pests. It further held, that the complainants could not establish that the seeds were defective and as such dismissed 26 complaints. However, it had allowed 13 complaints. 7. Being aggrieved by the order of the District Forum, complainants filed appeals before the State Commission which allowed the same, vide its impugned order. 8. Now Petitioner’s Company has filed the present revision petitions. 9. We have heard Sh. Subramonium Prasad, learned counsel for the petitioner, Sh. Debojit Borkakali, learned counsel for respondents (in RPs No. 1451 to 1473 of 2011) and Sh. V. Sridhar Reddy, learned counsel for respondents (in RPs No.1474 to 1489 of 2011). We have also perused the record and have gone through the written submissions also. 10. It has been contended by learned counsel for the petitioner that complainants had to prove that they had taken the precautions at the time of sowing the seeds. In the cash bill issued by the distributors it is clearly mentioned that they do not give any guarantee regarding the growth and yield of the crop, which depends upon the environmental components. Further, factors guaranteed by the petitioner are specifically printed on the label and printed on the seed packet. There is no guarantee on the quantum of yield on the resistance from viral diseases and thrips. Even the pamphlets/brochure issued by the petitioner’s company regarding ‘Roshini’ do not say any guarantee of the resistance to viral diseases thrips of the yield of the crop. Further, it is a common knowledge that the condition of the crop and the quantity of the yield depends upon many factors including the physical condition of the soil, the moisture content at the showing time, the sowing methodology, salt accumulation in surface layers, water quality used for irrigation, long dry spell in the atmosphere and other disease and virus that may attack the plant. It also depends upon the remedial measures applied by the complainants when confronted with such situations. Strangely, complainants say that the bills for the fertilizers and pesticides used for the crop are missing. In absence of it, no premium can be given to the complainants for absence of evidence on crucial point. It is also contended that complaint is also silent as to the nature of the fertilizers or pesticides or fungicides used in this case. Further, complaint is also silent as to the nature of the disease to the plant and when it occurred and in that case what complainants did with it. It is an admitted fact that in June,2006 the seeds were sown. The correct procedure was that seeds should have been grown in a nursery and then transplanted to the field. At the very inception, the complainants went wrong. Further, the total period of crop duration is 6 – 9 months including the nursery period. In the present case, only after six months of sowing, complainants took the scientist and their team for field inception. By that time the crop will be at the end of its life. The reports of the experts show that the crop was infected with pest and that too sucking pest. Sucking pest is otherwise called thrips. It sucks under-surface of the leaves and if it is not controlled immediately by using frequently the required pesticides as advised by the Agricultural Officer or as recommended by the Agricultural University, it becomes uncontrollable and naturally the plant will be affected and the yield will be affected. It is also contended that it is clear from the complaint as well as from the expert report, that the crop failed because of the sucking pest which was not attended to by the complainants. 11. It is further contended that at the earliest point of time of the attack, the complainants should have intimated to the petitioner and should have approached the agricultural officer for proper remedies. Complainants’ action are highly belated, by which time the whole damage has been done to the crop. Further, neither taking of expert to the field nor the report of the expert were communicated to the petitioner. The rules require that such communications should have been conveyed to the petitioner, so as to help the complainants to prevent the damage. Everything has been done at the back of the petitioner and without any knowledge to the petitioner. Thus, there is no deficiency in service on the part of the petitioner and the claims of the complainants are not tenable. In support, learned counsel has cited a decision of this Commission, Hindustan Insecticides Ltd. Vs. Kopolu Sambasiva Rao and Ors. 1V (2005) CPJ 47 (NC) 12. On the other hand, it has been contended by learned counsel for the respondents that respondents-farmers had sown the seeds on adopting the agricultural practices, applied fertilizers and pesticides, incurring an expenditure of Rs.30,000/- per acre. The petitioner-company had given assurance of yield of 25 quintals per acre, but the respondents could hardly get even 2 quintals per acre due to defect in the seeds. Further, the growth was poor and it did not give even the minimum yield. Therefore, farmers complained to the Agricultural Department about the defective seeds. After receiving the complaint, the Joint Director of Agriculture along with Scientists and Assistant Agricultural Officer visited the crop of the farmers in the last week of December, 2006 and opined that the seeds were defective by comparing with local variety 334 which yielded around 12-14 quintals per acre. 13. It is further contended that the case of respondents have been proved by way of evidence of the experts. The experts report states that hybrid vigor was very poor and due to poor growth, complainants got poor yields. Therefore, there are defects in the seeds as well as deficiency of service in supplying of the seeds. 14. Learned counsel for respondents in support of their contentions relied upon following judgments; (i) National Seeds Corpn. Vs. P. V. Krishna Reddy 2009 (CTJ) 522; (ii) D. J. Damani and Sons Vs. Deepak Madanlal Agarwal and Anr. II (2013) CPJ 102(NC); (iii) Maya Seeds Development Corpn. Vs. Sandhu 2005 CPJ 13(SC); (iv) National Seeds Corporation Vs. Madhusudhan Reddy [2012 (1) Scale 367]; (v) M/s Maharshtra Hybrid Seeds Company Ltd. Vs. Alavalapati Chandra Reddy Reported in III (1989) CPJ 8 (SC) and (vi) H. N. Shankara Sastry Vs. Assistant Director of Agriculture, Karnataka reported in II (2004) CPJ 37 (SC). 15. The District Forum, while dismissing the complaints, in its order held; “6. The complainant did not place any such cogent material which holds with any definiteness and specificness that the seed purchased and sowed in their lands was defective and effected the yield. Nor any material is placed in substantiation of the complaint averment as to inspection of field by Joint Director of Agriculture along with scientific in the month of December 2006 and holding defect in Roshini Hybrid Chilly seed. 7. The Ex.A1 is the inspection report of Dr.Y.Rama Reddy, Scientist, RARS Nandyal pertaining to Roshini Chilli Hybrid crop in the fields of the farmers in Ramireddypalli of Koilakuntala Division and Pamulapadu, Eskala, Santhinilayam, and Abdullahpuram Villages of Atmakur Division. The said inspection and observation was said to have been made on his visit, on 13-2-2007 and 14-22007, along with Assistant Director of Agriculture and Agricultural Officer of said division. The said observation report nowhere alleges defect in the seed resulted to this state of circumstances which it observes in the said Ex.A1 as to the Roshini Chilly Yield in said fields of the farmers. On the other hand it observes sucking pest to the crop therein the fields and thereby not rooting out the possibility for the said state of circumstances to the crop on account of the sucking pest. Even though it takes further that Hybrid vigour was very poor (to the crop) and due to this poor growth ,less pod productive plants and more poor productive plants, but as the said was not attributed in reference to any defect of the seed sowed in said fields that to without any scientific test of the said crop as to Hybrid vigour and further with the said circumstances to the crop expecting a further two or three poor yields not assessing the probable quantity of the said probable yield, the said Ex.A1 observation remains with any cogent reliability to hold any defect in the seed especially when there is any complaint as to germination of seed and plant population and its growth and any other abnormal physiological features of leaf size, petal colour , pod colour, length of pod . Further the Ex.A1 observation report being on mere physical look at the said crop and not being arrived on any approved pathological test and there being any material to hold that the sacking pest to the crop is on account of the defective seed only, and as the evidence of P.W.1 says that he did not conduct any seed test , the Ex.A1 is remaining of any much avail to the complainant’s case to hold the loss of expected yield to the complainant is on account of defect in seed alone 8. The P.W.1 is a mere breeder scientist. Entomologists deal with deceases of the crops and scientific study in respect of pest. While evidence of P.W.1 says as to several types in sucking pest such as thrips , mites and aphids , neither his observation report nor his evidence could classify the kind of sucking pest observed on the crop in the fields and further he does not appear to be in know of hybrid as he says at one juncture hybrids are of two types as F1 & F2 and at other juncture says the F2 is not hybrid as it is produced in resowing the F1 seed . Hence his evidence appear to be of any much help to the case of the complainant especially when Section 12 and 13 of Seeds Act empowers the seed analysis to seed inspector and the P.W.1 , the author of Ex.A1, was shown as any such empowered seed inspector for holding any seed analysis . 9. The Vyavasaya Panchangam for 2006-2007, published by Aacharya N.G. Ranga Agricultural University, Rajendra Nagar, Hyderabad in its Pg.270 to 273 deals with chilly crop and of the precautionary measures to be taken in crop cultivation for good yield and for fighting the pest and thrips till harvest . At Pg.No.272 it envisages of the measures to be taken for crop production from various pests including thrips and recommends use of Carboril 3 grams, or Fasalone 3 ml or Esiphate 1.5 grams or Fipronil 2 ml or Spinosad 0.25 ml with 1 litre of water and its spraying on effected parts. As preventive measure it recommends the use of 8 kilos of 0.3 % Fiprosil Capsules on 15th and 45th day of plantation when moisture is still in field. It recommends the processing and culturing of the chilly seed with Imideclofrid and balanced use of organic and inorganic fertilizers and manures in cultivation of said crop . Neither the complaint averments nor the evidence of complainant takes any mention of the adoption of said measures in crop management in their fields. Nor any bills of purchase of those pesticides, fertilizers and manuals is filed by the complainant with any assertion as to its use as recommended to meet the said contingent state of circumstances to their chilly crop. By this what is remaining clear is that the complainant had not taken any adequate required measures in crop management and thereby remaining as a cause for such state of circumstance to the crop and so cannot blame anybody and nonetheless attribute it to any defect in seed. 10. The Ex.A10/Ex.B1 a xerox of printed broucher relating to Roshini Hybrid Chilies and its beneficial features. It no where says of the quantum of expected yield for acre or lends any assurance to any quantity. It says the yield starts its commencement from 55 to 60 days of plantation. As per Ex.A3 chilly seed of Roshini Hybrid was purchased in the month of June, 2006. As per sworn affidavit of the complainant the purchased seed was sowed in the same month in their lands for growing nursery and after the necessary nourishing they were transplanted. The inspection of the fields, where said roshini variety was raised, was done by the P.W.1 on 13-2-2007 to 14-2-2007. Hence from the said time factor what appears is that the said inspection was done about 8 months after to the purchase of the seed and its sowing. As the yielding of said variety commences from 55 to 60 days of its transplantation, the complainant must have got several periodical cuttings of yield of said chilly crop by the date of inspection of the said fields by P.W.1. But neither the complaint nor the sworn affidavit of the complainant nor the evidence of P.Ws.1 and.2 could say of the yield got by the complainant by the date of said inspection. When the Ex.A1 says a further probability for 2 or 3 yields to said crop it is not clear from the complainant side even the quantum of yield got to the complainant in said 2 or 3 further probable yields. 11. 12. 13. The complainants side expect alleging it was assured of 25 quintals of yield per acre by the opposite parties, did not substantiate it. Nor any other cogent material appears from the complainant side to the effect that the said hybrid variety was made understood to yield 23 quintals per acre. Nor any material as to earlier years of yield of said variety was placed to establish the truth in said contention of the complainant. A local variety No.334 said to have yielded 12 to 15 quintals per acre, which is not proved by evidence of persons who raised said crop is of any avail to the complainant as comparison as to any merit or demerit must be with the same kind but not with the other kinds . Copy of adangal extract in Ex.A4 said to be of land of complainant in Sy.No.28/1 of Pamulapadu envisaging cultivation of chillily crop in the extent stated therein is remaining of any avail to the case of the complainant as it does not envisage to which year the said account pertains to and the concern of the complainant to the said land for want of the name of the complainant in relevant columns of cultivation or pattadar . Another copy of adangal covered in Ex.A4 said to be pertaining to land in Sy.No.29/1 of Pamulapadu envisaging cultivation of Chilly crop on an extent of Ac.1.50 cents in the Fasli year 1416 is also remaining of any avail to the complainant as it does not show the concern of the said land to the complainant for want of the name of the complainant in relevant columns of cultivation or pattadar”. 14. As discussed in supra paras as to the viability of the Ex.A1 report and evidence of P.W .1 in reference to Ex.A1 against to complainant’s contentions as to the aspect of defect in seed and in the absence of any cogent material as to defect in seed the mere paper clippings in Ex.A5 ,A9 and representations in Ex.A6 & A7 remains any avail to the complainant’s case as they cannot be substitute proof for holding defect in seed”. Lastly, the District Forum held ; “22. When the defect in seed is not established in an approved manner and on the other hand the said state of circumstances to the crop in the field appears to be on account of thrips with which it was infested and thrips to said crop appears to be at the deficient crop management of the farmer and after germination the progress of the crop not only depends upon the crop management and field management, but also on friendly agro environmental conditions as no seed yields crop in the mere air , the cause for said improper yield or less than expected yield is more at the deficiency of the complainant in crop management rather than any inherent defect in the seed and thereby there being any material to hold the defect in seed supplied by the opposite parties which must have ensured loss of expected yield to complainant, there appears any liability of the opposite parties for the claim of the complainant. 23. Hence, there being any merit and force in the claim of the complainant the case of the complainant is dismissed”. . 16. State Commission while reversing the decision of District Forum in its impugned order observed ; “For the contention of the learned counsel for the opposite parties that the shelf life of the seed was over and therefore they could not send for analysis does not stand in the light of Section 13 of the Seeds Act. If we compare the format and contents of Ex. B1 with which alone the purchaser was obliged to make do, with Rule, 8 of Seeds Rules is crystal clear that the respondents gave a go by even to the barest minimum of compliance with law. This disobedience to law on the part of respondent becomes all the more clear if we compare Ex. B1 more so when Rule 13(3) of Seeds Rules set out above costs an obligation on the part of the seller of seeds to preserve the samples of seeds in terms thereof for the purpose of getting them tested if required. The dispensation in Rule 13(3), thus, amply indicates that when the quality of seeds sold is called in question the seller has to raise to the occasion to dispel it. It is for the seller to get them tested for their efficacy in germination and genetic purity and other purity in quality especially when such data is not proved by producing the statutory labels. It is therefore clear from the material available that the opposite parties totally failed in showing the seeds in question were free from defect namely standard germination and genetic purity. This deficiency smacks both the defect in sees as also deficiency in service of supply of seeds. 13 The complainants are agriculturists who own lands could find that crop did not grow nor the yield as promised approached the agricultural authorities in fact gave a report to the Joint Director of Agriculture, Kurnool, who in turn deputed the Senior Scientist, Regional Agricultural Research Station, Nandyal. The Scientist and Agricultural Officers who visited the crop categorically stated that over all hybrid vigor was very poor. Due to this, there was poor growth, less productive plants and more poor productive plants were observed. In fact they compared with the local variety 334 and opined that there would be very low yield. Taking cue from the report of the scientists that sucking pest was afflicted, the learned counsel for the respondents contended that no where it was stated that it was not resistant to pests. There is no meaning in creating hybrid variety after conducting resistance tests etc., if they are not resistant to pests. In fact the manufacturer ought to have mentioned that it would resist to pests, and in case if afflicted the precautions to be taken to contain these pests or viruses. 14. Obviously the agriculturists do not have wherewithal to conduct tests etc. as that of a manufacturer. What all they could do is obtain an opinion of the agricultural officer and expert in the subject”. It further observed; “18. At the cost of repetition, we may state that the complainants have proved their cases beyond doubt by examining the Scientist as well as the Joint Director of Agriculture that the crop had failed. The Scientists also compared this crop with that of the neghbouring crop raised with a different variety, and found that it had yielded 12 – 15 quintals per acre. The manufacturer did not sent the seeds that were released to the market under the said batch in order to prove that the seeds were not of inferior in quality. It did not even file the laboratory test reports that were conducted before releasing the seeds to the market. The questions in regard to nature of land, irrigation facilities etc. were of general nature. As we have earlier pointed out PW1 did not state that the lands were not suitable for raising chilly crop and there was any adverse climatic conditions. The very fact that in the neighbouring lands yield was good show that there was deficiency in the seeds manufactured by the respondent. There could not have been total loss of crop for all these agriculturists had seeds been in conformity with the specifications. We have absolutely no hesitation to hold that the crops were failed due to defective seeds. The complainants have proved by leading both oral and irrefutable documentary evidence that they have sustained loss in view of defect in the seeds. 19. Coming to the quantum of compensation, it is not in dispute that the complainants have raised the chilly crop in an extent of land as mentioned in the complainants. If we take minimum 12 quintals per acre as deposed by PW1 and computing @ Rs.4,500/- per quintal the loss would come to Rs.54,000/- per acre. The complainants would get the yield after applying fertilizers and pesticides etc. All this includes cost of the crop. Therefore the complainants are not entitled to value of the seeds, fertilizers and pesticides etc. separately, PW1 in fact deposed that the expected yield would be 12 quintals per acre. Since the manufacturer did not dispute the rate of chilly at Rs.4,500/- per quintal, the complainants are entitled to 12 quintals per acre @ 4,500/- per quintal together with compensation of Rs.5,000/- each besides costs of Rs. 3,000/- each”. 17. The short question which arises for consideration is as to whether hybrid chilly seeds called ‘Roshini’ as manufactured by petitioner’s company and sold by its distributor, were defective or not. 18. In this regard, complainants have relied upon two inspection reports conducted by the Officers of Agriculture Department. 19. First report is dated 6.12.2006 with regard to the Chillies Crops grown in Alampur village, Allagadda Mandal Kurnool District, copy of which has been placed (at page no. 567 of the paper-book) and same is reproduced as under; “COURT ON VISIT OF CHILLIES CROP IN ALAMUR VILLAGE, ALLAGADDA MANDAL, KURNOOL DISTRICT On request of Assistant Director Agriculture, Allagada through letter ROC. No. C/120/06 DATED 1.12.2006 Sri I. J. Michale Ragiv, Horticultural Officer, Allagadda mandal Sri R. Narasimha Reddy, Scientist( G& PB), RARs Nandyal and Sri G. V. Bhaskar Reddy, Assistant Director of Agriculture, Allagadda Agricultural Division inspected formers’ fields who have grown chilies crop in Alamur village on 6.12.2006. The team observations are; Chilies are grown in large area. Chilies variety is Rhosni and is the product of Syngeta company. All plants were infected with thrips. High Incidence of virus(Poty and Tospo). No or less fruit set observed. High incidence of die back and fruit not diseases. Most of the plants were in stunted in growth due to the diseases. Symptoms of Sphondylia capsici insect also observed in about plants. 5% of On enquiry farmers said they have not observed flowering even though the crop attained the age of 100 days and they were in distress mood. Even then they have spent about Rs. 25,000/- till now towards for cultivating the crop leaving inside their family man power and land lease. They have harvested two quintals of green chillies only and they are dropped into bankrupt. Remarks: 1. The Crop is infected with Thrips and Viruses. 2. Die back and fruit not incidence is more. Suggestions: 1. Farmers are requested to approach the concerned officials for needy help. 2. It is requested to help the farmers to get rid off from the bankrupancy”. Sd/-” 20. The second report is an inspection report conducted by Dr. Y. Rama Reddy, Senior Scientist, PARS, Nandyal (copy of which has been placed at page no. 559 of the paper-book). The same is reproduced as under; “Inspection report of Dr. Y. Rama Reddy, Senior Scientist, PARS, Nandyal during the month of February 2007, pertaining to Roshini chilli Hybrid. I visited Roshini Chilly hybrid plots under revenue divisions of Koilkuntla and Atmakur on 13.2.2007 and 14.2.2007 respectively along with Assistant Director of Agriculture and Agriculture Officers of above divisions. Observations as follows: S. No. Characters Ramireddy under Palli Pamulapadu Iskala, Koilkuntia division Santhinilayam and Abdullapuram under Atmakur division , 1. Plant Population Normal Normal 2. Plant (cm) 45-60 45-60 3 Leaf size Small to medium Small to medium 4. Petal color White White height 5. Pollen Color Green Green 6 Pod color Dark green at Dark green at developm-ental stage, red at maturity developmental stage, red at maturity 7 8 Length of the Pod (cm) Productive plant 6 to 9 6 to 9 Very poor i.e , 1 or 2% only, rest poor productive Very poor i.e 1 or2% 2 only, rest poor productive (10 to 25 pods/plant) (10 to 25 pods/ plant ) 9 Pest Sucking observed pest 10. Yield Q/acre 2 to 3 poor yields are expected Sucking pest observed 1 to 2 poor yields are expected Over all hybrid vigor was very poor, due to this poor growth, less pod productive plants and more poor productive plants were observed. Due to these reasons poor yields are expected. But local variety 334 was observed good performance and yields expected around 12 to 15 Q/acre in all divisions”. 21. Both the Fora below have considered the above reports. 22. District Forum did not rely upon these reports, whereas State Commission on the basis of these reports, has allowed the complaints and has awarded the compensation. 23. It is an admitted fact that Chilly Seeds were sown in the first week of June, 2006. However, the first inspection was conducted in December, 2006 and second inspection was conducted in February, 2007. 24. There is nothing on record to show as to why the complainants did not make any complaint to the concerned authorities when there was no flowering in the crop for 100 days. There is also no explanation as to why complainants-farmers approached the concerned authorities only after 6 to 8 months after the crops had been sown. 25. As per inspection report dated 6.12.2006, complainants have stated that they did not observe flowering even though crop attained the age of 100 days. There is also no explanation as to why even after three months of the sowing of the seeds, complainants did not make any complaint to the manufacturer or seller of the seeds. 26. Further, as per remarks given by the inspecting officials in their report dated 6.12.2006, it categorically states that; “1 The Crop is infected with Thrips and Viruses. 2. Die back and fruit not incidence is more”. 27. Moreover, as per this report inspecting officials requested the farmers to approach the concerned officials for needy help. 28. The above inspection report dated 6.12.2006, nowhere states that there was any defect in the seeds. On the other hand, it has been stated that the “Crop is infected with Thrips and Viruses”. There is nothing on record to show that due to the quality of the seeds only, the crop can be infected with Thrips and Viruses. The crop can be affected by so many factors such as, the quality of the soil or due to nature of the pesticides and fertilizers and other chemicals used, if in excess or in less quantity. Thus, report dated 6.12.2006, has nowhere put any blame upon the Petitioner’s Company. 29. Now coming to the second report which is dated 13/14.2.2007. It also mentioned about pest as its states: “9 30. Pest Sucking pest observed Sucking pest observed”. Thus, from the second report dated 13/14.2.2007 also, it is very clear that the crops were infected with “Sucking Pest”. However, this inspection was done only after about eight months after the crop has been shown. Therefore, much reliance cannot be placed at this belated inspection report. 31. Further, it is well established that defects in the seeds cannot be detected on the basis of visual inspection of the fields alone. On the other hand, visual inspection conducted by the Agricultural Officials shows that plants were infected. Moreover, complainants have not placed on record any data with regard to the yield of chillies for the previous years. 32. Another aspect to be noted in the present cases is that there has been violation of principles of natural justice. It is an admitted fact that before conducting the inspection of the fields of the farmers on 6.12.2006 as well as on 13/14.2.2007, no notice was given to the petitioner’s company to join the inspection. Whatever inspection have been conducted on these two dates, the same were done at the back of the petitioner’s company. There is also nothing on record to show that copy of these reports was ever supplied by the inspecting officials to the petitioner’s company so as to give an opportunity to the petitioner’s company to present its view. Under these circumstances, we hold that there has been violation of the principles of natural justice, for which respondents cannot derive any benefit. 33. None of the judgments cited by learned counsel for the respondents are applicable to the facts of the present case. 34. It is well settled that crop can be affected due to various reasons viz. poor quality of seeds, fertilizers, inadequate rainfall or irrigation, and also due to poor quality or inadequate or overdose of pesticides/insecticides. In the present cases, the respondents-farmers have miserably failed to prove that due to the defective seeds their crops have failed. 35. Under these circumstances, impugned order passed by the State Commission cannot be sustained. Accordingly, we set aside the impugned order passed by the State Commission and restore the order of the District Forum. 36. Accordingly, present petitions stand disposed off. 37. Parties shall bear their own costs. ……..……………………J (V.B. GUPTA) ( PRESIDING MEMBER) ………………………… (REKHA GUPTA) MEMBER SSB/