IN THE HIGH COURT OF MALAYA AT KUALA LUMPUR COMMERCIAL DIVISION SUIT NO.: D-22-1555-2001 BETWEEN … PLAINTIFF … DEFENDANT RICHCON (M) SDN.BHD (Company No. 143677-T) AND SAFUAN GROUP BERHAD (Company No. 262210-V) Didengar bersama dengan SUIT NO.: 22-NCC-624-2010 BETWEEN PDLD LAND SDN.BHD … PLAINTIFF … DEFENDANT … THIRD PARTY AND RICHCON (M) SDB.BHD AND SAFUAN GROUP BERHAD GROUNDS OF DECISION 1 SUIT NO. D2-22-1555-2001 The plaintiff’s case 1. The plaintiff’s claims against the defendant is for wrongful retention of machineries and equipments of the plaintiff at Lot 72, Port Dickson, Negeri Sembilan (“Project Site”) for which the plaintiff seeks damages. 2. The machineries and equipments having been returned to the plaintiff in the year 2006. As part of the damages sought in this action, the plaintiff seeks the loss of rental income as the plaintiff being the owner of the machineries and equipments was deprived from hiring them out. 3. The plaintiff also seeks as part of the damages sought in this action the losses suffered by the plaintiff because the years of wrongful retention of the machineries and equipments has resulted in the machineries and equipments being in bad condition and therefore could only be disposed of as scrap metal. 2 4. The defendant on the other hand strongly contested the plaintiff's claim by stating that the plaintiff has wrongfully brought the above proceeding against the defendant and the rightful party which the plaintiff should have pursued the above legal action is Port Dickson Land Development Sdn Bhd ("PDLD Sdn Bhd”) which was wound up on 19.1.2001. The defendant’s case 5. PDLD Sdn Bhd is the beneficial and registered proprietor of the land hold under title Lot No. 72 H.S[D] 7295 Port Dickson Negeri Sembilan, where the project of Water Front Centre to be developed. 6. The defendant content that the plaintiff’s claim against the defendant is fictitious, vexatious and an abuse of process of court based on the following reasons: (i) At all material times, neither the defendant has involved in the above project nor having knowledge about the rental of machineries to one Wing Construction Sdn Bhd (“Wing 3 Construction”) by the plaintiff. In fact the plaintiff has never communicated with the defendant before the machineries were transferred to the site of the above project. (ii) The plaintiff should have filed this claim against PDLD Sdn Bhd or dealt with the Official Receiver as the Liquidator for PDLD Sdn Bhd in order to take possession of the machineries at the site of the above project. (iii) The plaintiff has negligent, failed or refused to adduce any evidence in order to show that the plaintiff is the registered owner for the abandoned machineries at the site of the above project from the very beginning to avoid any doubts on the status of the registered owner of those machineries. (iv) The plaintiff has failed with due and reasonable diligence and in accordance with the law to redeem or take possession of those machineries from the party involved even though the defendant has informed the plaintiff to redeem those machineries directly from PDLD Sdn Bhd. 4 (v) The plaintiff has failed to mitigate its losses specifically and the plaintiff is now put under strict proof for the claim. (vi) The defendant and PDLD Sdn Bhd are two separate entities and from the very beginning the plaintiff should have dealt with the Official Receiver as the Liquidator for PDLD Sdn Bhd in order to redeem and/or to take possession of those machineries which are alleged to be owned by the plaintiff. As such the plaintiff’s claim should not have been initiated against the defendant. Issues 7. Based on the pleadings and evidence adduced, the issues to be determined by the court are as follows : (i) Whether the plaintiff is the owner of the equipments; (ii) Whether the defendant prevented the plaintiff from taking away the equipments from the Project Site when demanded by the plaintiff ; and 5 (iii) Whether the plaintiff suffered damages due to the wrongful detention of the equipments. Whether the plaintiff is the owner of the equipments and machineries 8. The plaintiff has pleaded in paragraph 4 of its Statement of Claim that they are the registered owner of the equipments. The defendant on the other hand argued that the Sales and Purchase Agreement as seen on page 40-45 of Bundle B did not show that the plaintiff is the lawful registered owner of those equipments. 9. I have carefully perused the documents on page 40-45 of Bundle B and I accept the submission of learned counsel for the defendant that the Sales and Purchase Agreement in respect of the equipments are flawed with discrepancies. At page 41, 43, and 45 of Bundle B, the terms and conditions of the Agreement states that the balance 90% of the purchase price shall be be paid subject to the transfer of title of the said vehicle to the new owner. However, the plaintiff did not adduce any document of title to show the ownership of these machineries has been transferred to them. In 6 fact, no proof of receipt of payment of purchase price made by plaintiff to the vendor of the equipments was produced as evidence before the court. 10. Further, the Sale and Purchase Agreement was not signed by the Directors for both the vendor's and purchasers despite the fact that both Companies are registered as "Sdn Bhd" and "Pte [Ltd] Companies" and the Article of Associations of the company, requires either a common seal of the company or a director in executing the said documents. The court notes that neither of this is found in the Sale and Purchase Agreement. 11. In this regard, the plaintiff has also failed to produce either the vendors or the purchasers as the maker of the documents. Page 40-45 of Bundle B are only marked as "ID-10" and not as an exhibit. Again there should be no weight to be attached to this documents. As such, the plaintiff has failed to prove the said document in order to be admitted as evidence. 12. In the absence of the maker of the documents being called and the plaintiff's failure to rectify and explain those various defects existing in the Sale and Purchase Agreement and also by not producing the registered title together with the receipt of purchase price paid to the vendors, the 7 court finds that the only irreversible conclusion that can be drawn against the plaintiff is that plaintiff has failed, to show the true ownership towards the said machineries. Whether the plaintiff was prevented from taking the equipments from the Project Site when demanded from the defendant 13. The next question to be considered is whether the plaintiff was prevented from taking the equipments from the Project Site when it demanded to take it away. 14. PW1 during examination in chief said that the plaintiff was prevented from taking away the equipments from the Project Site. 15. It is not disputed between the parties that the registered owner of the Project Site where the equipments, machineries were kept is PDLD Land Sdn Bhd (refer to pg 25 of Bundle C). 16. During cross-examination, PW1 did not agree to the question by the defendant’s counsel that neither the plaintiff nor Wing Construction 8 approached or wrote to the defendant for the release of the equipments from the Project Site. However when question further, PW1 admitted that the plaintiff did not write to PDLD Land for the release of the equipments. 17. At paragraph 6 of the plaintiff's Statement of Claim, the plaintiff pleaded that they have written a letter dated 15.1.2001 to the defendant demanded for the return of the equipments. However, despite referring to paragraph 6 during the trial, the plaintiff has failed to produce the said letter to support its case. 18. On this issue, learned counsel for the defendant submitted that the plaintiff's failure in not producing such letter despite being pleaded clearly goes on for the court to draw an presumption of adverse inference against the said letter dated 15.1.2001 under Section 114 [g] of the Evidence Act 1952 wherein the said letter if produced would be unfavourable to the plaintiff who withholds it. 19. In this respect, the court agrees that the adverse inference should be drawn against the plaintiff for not producing the said letter. In fact the letter 9 was clearly reflected under the defendant's letter of reply dated 26.2.2001 (D20). 20. It is the defendant’s case that at all material times, the plaintiff and Wing Construction are fully aware that the registered proprietor in which the machineries were kept is Port Dickson Land Development Sdn. Bhd. Thus, the plaintiff has sued the wrong party. 21. The court notes that based on the evidence adduced by DW1, the defendant vide a letter dated 26.2.2001 (D20), even prior to the commencement of this suit has notified the plaintiff that the defendant were not the registered proprietor and had no control over the Project Site (Lot 72). 22. Paragraph 3 of the defendant letter states as follows : 3. We have informed you specifically that the Registered Proprietor for the above project site is Port Dickson Land Development Sdn. Bhd. which was wound-up on 19.1.2001 and we have nothing to do as far as your machineries is concerned which you have stated that they have been placed at the project site as both companies are different in their entities. 10 23. However, in cross-examination the defendant denied receiving the plaintiff’s letter dated 26.2.2001 and they were not aware that the Port Dickson Land has been wound-up. 24. In this case, the court is faced with conflicting testimony of PW2 and DW1 as to whether the plaintiff received the letter dated 26.2.2001. 25. The court in thus faced with the task of having to choose whose evidence to believe. In discharging this task, I am guided by the decision of the following authorities in Tindok Besar Estate Sdn Bhd v Tinjar Co [1979] 2 MLJ 229 where Justice Chang Min Tat (as he then was) said: “For myself, I would with respect feel somewhat safer to refer to and rely on the acts and deeds of a witness which are contemporaneous with the event and to draw the reasonable inferences from them than to believe his subsequent recollection or version of it, particularly if he is a witness with a purpose of his own to serve and if it did not account for the statements in his documents and writings. Judicial reception of evidence requires that the oral evidence be critically tested against the whole of the other evidence and the circumstances of the case. Plausibility should never be mistaken for veracity.” 11 26. The above approach was also applied by James Foong J (as he then was) in Industrial Concrete Products [2001] 8 CLJ 262 and Low Hop Bing J (as he then was) in the case of Nuri Asia Sdn Bhd (Supra). 27. Further, in Noorianti Zainol Abidin & Ors. v Tang Lei Nge [1990] 1 CLJ 943 Lim Beng Choon J (as he then was) had occasion to say that the trial judge should not approach the case on the basis of deciding which story out of the conflicting stories that should be believe, but rather to consider which version was inherently probable or improbable. All things being equal, it is trite law that if the version of one of the parties is inherently probable, then the judge has no choice but to accept the version forthwith (see Chua Chong Cher v Teo Lang Keow & Ors [1970] 2 MLJ 27. Abdul Kadir bin Mohamad v Kamarulzaman bin Mohd Zin & Anor [2000] MLJU 658). 28. In Muniandy & Ors v Public Prosecutor [1966] 1 LNS 110; [1966] 1 MLJ 257, the trial judge accepted the evidence of certain witnesses because they had remained unshaken in cross examination. Based on that evidence he convicted the appellant. The Federal Court reversed the decision, Ong Hock Thye FJ said: 12 “In the instant case, it is stated by the learned trial judge as the ground for his belief in the main prosecution witnesses, that they had been unshaken in cross-examination. In our view, being unshaken in cross examination is not per se an all-sufficient acid test of credibility. The inherent probability or improbability of a fact in issue must be the prime consideration. The fact that the trial judge believed implicitly in the truthfulness of Nagarachnam and Ramasamy does not preclude closer scrutiny of their evidence and this we have done.” 29. Returning to this issue, PW1 in his evidence claims that he was not aware of the defendant’s letter dated 26.2.2001. On the contorary, DW1 pointed in the second paragraph of the defendant’s letter dated 28.2.2001 that the plaintiff had made reference to the plaintiff’s letter dated 28.6.2000 and 15.1.2001. In paragraph 6 of the Statement of Claim, the plaintiff had made reference to the said letter. As such, the court finds that it would be highly improbable for the plaintiff not to know about the letter dated 28.2.2001. In fact no evidence was led by the plaintiff to rebut this fact. 30. The plaintiff contended that the plaintiff’s equipments and machineries were not being retained by PDLD Sdn Bhd or PDLD Land but 13 by the defendant. This is evident by paragraph 2 of the Letter of Undertaking and Indemnity at page 46 in Bundle B which states that : In connection with the removal of the equipments and the materials listed in the Annexure hereto from the Lot by us with the knowledge and consent of the said Safuan Group Berhad. 31. The question that arises is whether based on this Letter of Undertaking can the court conclude that the defendant has the control and custody of the Project Site and thus prevented the plaintiff from taking away the equipments. 32. Since it is the plaintiff who alleged that the defendant has the control and custody of the Project Site and it prevented the plaintiff from removing those equipments on the Project Site, based on section 101, 102 and 103 of the Evidence Act, the burden of proof lies with the plaintiff. 33. In this regard, the court agrees with the submission of learned counsel for the defendant that the plaintiff has been advised vide a letter dated 28.2.2001 to forward their claims to the liquidator of PDLD Sdn Bhd. 14 However the court finds that for reasons known to the plaintiff, the plaintiff did not to do so. 34. In fact in cross-examination, PW1 agreed that the plaintiff did not take any actions such as injunctive relief to remove the machineries from the Project Site. There is also no evidence to show that the plaintiff wrote to seek the liquidator’s consent to remove the said machineries from the Project Site. 35. Based on the evidence adduced by all parties, in my judgment, the plaintiff has not proof on the balance of probabilities that the defendant has full control and possession of the Project Site and that it did not deliver the equipments to the plaintiff when demanded that it should be released. The court finds that the plaintiff has not produced any evidence to show that the defendant has deliberately withhold the equipments for the plaintiff to support its cause of action for detinue. 36. In the case of Perbadanan Kemajuan Negeri Selangor, the Federal Court referred to Lord Diplock’s decision in General and Finance 15 Facilities, Ltd v Cooks Cars (Romford), Ltd [1963] 2 All ER 314, where at page 317, it was held that : "There are important distinctions between a cause of action in conversion and a cause of action in detinue. The former is a single wrongful act and the cause of action accrues at the date of the conversion; the latter is a continuing cause of action which accrues at the date of the wrongful refusal to deliver up the goods and continues until delivery up of the goods or judgment in the action for detinue. ... Demand for delivery up of the chattel was an essential requirement of an action in detinue and detinue lay only when at the time of the demand for delivery up of the chattel made by the person entitled to possession the defendant was either in actual possession of it or was estopped from denying that he was still in possession." 37. I must stress that the plaintiff has not proved on the balance of probabilities that the defendant has the actual possession of the Project Site and that it refused to allow the plaintiff to remove the equipments when demanded to do so by the plaintiff. It is not safe for the court to rely on the letter of Undertaking and Indemnity to conclude that the defendant had full control and custody of the equipments at the Project Site. 16 38. The court notes that the Letter of Undertaking and Indemnity was issued by the plaintiff to Port Dickson Land Development Sdn. Bhd. and not to the defendant. DW1 explained during cross-examination that the reason why he was at the Project Site during the material time of inspection by the authorised representative of the plaintiff was because he has to protect the interest of the defendant because of the ongoing legal suit against the defendant. 39. Based on the facts and circumstances of this case, I accept the defendant’s submission that the plaintiff has sued the wrong party in this suit. 40. From the evidence adduced, PDLD Sdn Bhd has sold off their shares of RM40,000,000.00 in the defendant’s company on 28.11.1997 i.e. even before the commencement of this proceedings (pg 4-20 of Bundle B). This evidence was never rebutted by the plaintiff. Even if defendant were to share common management, the defendant company is a legal entity by itself. 17 41. In the case of People’s Insurance Co (M) Sdn Bhd v People’s Insurance Co Ltd & Ors [1986] 1 MLJ 68 at p 69 which was cited by the defendant, Zakaria Yatim J (as he then was) held on page 69 as follows : “The plaintiff company is a legal entity by itself. Although it is a subsidiary of the first defendant company, the plaintiff company maintains its own separate entity. In Ebbw Vale Urban District Council v South Wales Traffic Area Licensing Authority [1951] 2 KB 366,Cohen L.J. said: "Under the ordinary rules of law, a parent company and subsidiary company, even a 100 percent subsidiary company, are distinct legal entities ...” Losses suffered by the plaintiff 42. Since I have decided that the plaintiff has failed to proof that the defendant has wrongfully detained the equipments therefore, the issues of losses by the plaintiff do not arise. 43. Even if I am wrong in deciding that there is no cause of action by the plaintiff against the defendant for detinue, the question that arises is 18 whether the plaintiff has proved that it has suffered losses due to the wrongful detention of the equipments by the defendant. 44. In paragraph 5 of its Statement of Claim, the plaintiff has pleaded that it has entered into a Rental Agreement with Wing Construction to lease out the equipments and machineries. The monthly charges appeared under Schedule A at page 4 of Bundle B. However, because of the wrongful detention, it was unable to rent it to Wing Construction. 45. On this issue, the court has perused the Rental Agreement (pg 1 of Bundle B) and finds that it is flawed with few discrepancies if it to be accepted as evidence. 46. In my view, the discrepancies are as follows : (i) It is not stamped in accordance with the Stamp Ordinance for it to be admitted as evidence in court. (ii) It was not signed by the director or shareholders of the plaintiff. PW1 admitted that “Ragawan” who signed the Rental 19 Agreement was the supervisor of the plaintiff and he is not even a director or shareholder of the plaintiff. (iii) 47. It was not executed with the plaintiff’s common seal. The court finds that the plaintiff has not adduced any evidence to prove that it has suffered losses by hiring machineries elsewhere. All the invoices on page 1-7 of Document D involve Wing Construction. In this respect, Wing Construction is not a party to this suit. 48. Thus, the court finds that the plaintiff has failed to prove that it has suffered losses. It is trite law that damages have to be proven. 49. Referring to the decision of Lord Goddard in Bonham-Carter v Hyde Park Hotel Ltd. 64, TLR 177, 178; Edgard Joseph JR. FCJ in the case of Tan Sri Khoo Teck Puat & Anor. v Plenitude Holdings Sdn. Bhd. 1995 1 CLJ 15 said as follows : ... plaintiffs must understand that if they bring actions for damages it is for them to prove their damage; it is not enough to write down the particulars, so 20 to speak, throw them at the head of the Court, saying: 'This is what I have lost, I ask you to give me these damages'. They have to prove it. This dictum was referred to and applied by our Court of Appeal in John v. Dharmaratnam[1961] 1 LNS 35 7. And, in Popular Industries Limited v. Eastern Garment Manufacturing Sdn. Bhd. [1989] 3 MLJ 360, the Court had occasion to say this (at p.367): It is axiomatic that a plaintiff seeking substantial damages has the, burden of proving both the fact and the amount of damages before he can recover. If he proves neither, the action will fail or he may be awarded only nominal damages upon proof of the contravention of a right. Thus nominal damages may be awarded in all cases of breach of contract (see Marzetti v. William ). And, where damage is shown but its amount is not proved sufficiently or at all, the Court will usually decree nominal damages. See, for example Dixon v. Deveridge and Twyman v. Knowles . In Malaysian Rubber Development Corporation Bhd. v. Glove Seal Sdn. Bhd. [1994] 3 MLJ 569, at 582 E to F, Mohd Dzaiddin, SCJ, speaking for the Supreme Court quoted, with approval, the above passage in the Popular Industries case. 21 50. At all material times, plaintiff and Wing Construction are fully aware that the Registered Proprietor in which the machineries were kept is PDLD Sdn Bhd. 51. The court finds that the defendant's letter dated 26.2.2001 (D20) even prior to the commencement of the legal proceeding has notified the plaintiff to liase directly with the Official Receiver of PDLD Sdn Bhd. Despite such notification, the plaintiff and his previous solicitors did not write to the Official Receiver seeking for consent for the release of the equipments. 52. The plaintiff witness further admitted during trial, that had only the plaintiff has taken reasonable measures within a reasonable period of time, the plaintiff would have taken out the equipments from the Project Site. Instead of doing what is practical to mitigate plaintiff losses, the plaintiff witness testified that the plaintiff left to the hands of their solicitor who did not do anything for the past 8 ½ years. 53. Having full knowledge of the whereabouts of the machineries and also knowing who is the rightful proprietor of Lot 72, the plaintiff elected and 22 choose not to do the needful but instead proceeded to commence legal proceeding against the defendant, a wrongful party. 54. As for the prayer at page 8 of Bundle A, the plaintiff did not plead specifically for a claim on General Damages. Since parties are bound by their pleading, plaintiff claim for General Damages must fail and should not be allowed especially when plaintiff has failed to proof its case against the defendant. 55. Based on the above reasons, the plaintiff’s claim in Suit No. D2-22- 1555-2001 is dismissed with costs. Civil Suit D-22-NCC-624-2010 56. The plaintiff in Civil Suit No. D-22-NCC-624-2010 (NCC Suit) is the majority shareholder in PDLD Sdn Bhd and commenced the above cause of action against the defendant for the losses it has incurred whilst the equipments were kept on PDLD Project Site due to the defendant’s failure to remove those equipments. 23 57. Based on the evidence adduced by all parties, the court finds that the plaintiff in NCC Suit has failed to proof on the balance of probabilities that they suffered losses of rental, cost of fencing and cost of security. 58. It is the plaintiff’s contention that the project was abandoned in May 1998 and until the date the machineries were removed by the defendant in 18.12.2006, the plaintiff has suffered the following losses : (a) Loss of Rental - RM8,973,360.00 (b) Cost of Fencing - RM18,560.00 (c) Cost of Employing Security Guards Total 59. RM164,800.00 = RM9,156,720.00 With regard to the security and fencing costs, the court agrees with the defendant contention that the costs incurred by the plaintiff in respect of the security and the fencing costs was solely for the protection of the plaintiff’s machineries and equipments. The plaintiff’s witness in NCC Suit (Mohd Iskandar bin Mohd Isa) admitted during cross-examination that the project was abandoned and there were piles on the ground. Therefore the 24 fencing and the security would be for the protection of the whole project area. 60. With regard to the loss of rental, the plaintiff claims that the machineries and equipments were at prime spot of the land and therefore that portion of the land could not be rented out and therefore it is claiming for loss of rental to that area. 61. The court finds that the total area of the land is 36.38 acres. The area to be rented out by the plaintiff shows that only 10,000 sq ft in area was occupied by the defendant’s equipments/machineries. If the spot is required to be rented out, the plaintiff should have mitigated its losses by removing the equipments/machineries from the spot to other area of the land. There is no evidence to show that the plaintiff has mitigated its losses. Hence, the court finds that due to its failure, the plaintiff cannot claim the losses from the defendant. 62. Based on the foregoing reasons, the court finds that the plaintiff in NCC Suit has failed to prove on the balance of probabilities that it has 25 suffered the losses as claimed in prayer 15 (a) and (b) of its Statement of Claim. Thus, the plaintiff’s claim is dismiss with costs. (Hanipah binti Farikullah) Judicial Commissioner Commercial Division Kuala Lumpur High Court Dated : 8.2.2011 26 Solicitors for the Plaintiff Ajit Kumar Messrs Ajit & Company Suite 8-10-7, 10th Floor Menara Mutiara Bangsar Jalan Liku Off Jalan Bangsar 59100 Kuala Lumpur Solicitors for the Defendant Joshua T. Sambanthan Messrs Joshua Sambanthan & Associates No. 3A-20, blok A3, No. 9, Jalan PJS 8/9 46150 Petaling Jaya Selangor Darul Ehsan 27