fax message - Chinabidding.org

advertisement

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Metallurgy & Mining

(20110905-20110909)

Project Name: steel production project .............................................................................. 5

Project Name: Construction of granite mining project ......................................................... 6

Project Name: wood products production project ............................................................... 7

Project Name: insulation materials, fireproofing materials processing project ....................... 7

Project Name: aluminum, steel doors and windows processing projects .............................. 8

Project Name: Foshan Nanhai Danzao Trade Venture Limited 2 million tons of copper alloy expansion project ............................................................................................................. 9

Project Name: Shanxi Coal Transportation and Marketing Group Mountain Coal Co., 0.45Mt / a mergers and acquisitions integration project of mine ...................................................... 11

Project Name: Hui Co., the fourth city and there are stone quarrying area 100 tons / year production line quarrying ................................................................................................. 12

Project Name: Anhui Conch Cement production line Quanjiao (Phase II) Project ................. 13

Project Name: Foshan City super-sub Die Casting Plastic Co., Ltd. Expansion Project .......... 14

Project Name: Nanhai, Foshan City, Cao edge metal casting plant expansion project .......... 15

Project Name: Shanxi Coal Transportation and Marketing Zhongyue Coal Industry Group Co.,

Ltd. 90 million t / a mine mergers and acquisitions integration project ............................... 16

Project Name: Shanxi Coal Transportation Coal Industry Group Co., Ltd. Yuda gold 0.9Mt / a mergers and acquisitions integration project ............ Ошибка! Закладка не определена.

Project Name: Shanxi Coal Co. Po 300,000 t / a mine mergers and acquisitions integration project .................................................................. Ошибка! Закладка не определена.

Project Name: Shanxi Coal Co., Ma Yu Chang letter 1.2Mt / a mergers and acquisitions integration project of mine .............................................................................................. 18

Project Name: Shanxi Coal Transportation and Marketing Group charcoal valley Coal Co.

0.60Mt / a mergers and acquisitions integration project of mine ........................................ 19

Project Name: Zhengzhou Morishige annual output of 400,000 square meters Building

Materials Co., Ltd. Class A fire-retardant wall insulation materials used in construction projects .......................................................................................................................... 21

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Project Name: Henan Huamei Industry Co., Ltd. plastic profile plastic items ....................... 22

Project Name: produce 100,000 tons of equipment, steel projects ..................................... 22

Project Name: Qing Feng assimilation of new material Technology Co., Ltd. 20,000 tons of new material cellulose project .......................................................................................... 23

Project Name: Hui Co., the third city and there are stone quarrying area 100 tons / year production line quarrying ................................................................................................. 24

Project Name: Building Materials Co., Bavaria peak source 2000t / d clinker production line technological transformation project................................................................................. 25

Project Name: 16 × 13500KVA ferroalloy submerged arc furnace construction project ........ 26

Project Name: Jiaozuo City, Xin Cheng Special Materials Co., Ltd. 150,000 tons of special refractory materials production line .................................................................................. 27

Project Name: Air Port Aluminum Technology Co., Ltd. Fujian aluminum production project 28

Project Name: Sunrise Optoelectronics Technology Co., Ltd. Wuhu display glass substrate production line ....................................................... Ошибка! Закладка не определена.

Project Name: Hubei Science and Technology Development Co., Ltd. Wai Road polymer utilization of wood-plastic composites industry projects ..................................................... 31

Project Name: Gongyi City Public Source Co., 1000 tons of ultra-fine abrasive powder processing project ........................................................................................................... 31

Project Name: Dengzhou Stone Processing Co., Ltd. Oriental process 70,000 tons of quartz powder in the project ...................................................................................................... 32

Project Name: Forging an annual output of 680,000 tons and 60 tons of metal rolled products project (updated) .............................................................................................. 33

Project Name: Special cutting edge of solar silicon material of construction projects ........... 34

Project Name: Dragon Mining Ltd. Tianshui County, four children and ditch the West Gate

Gold 450t / d mining and engineering ..................... Ошибка! Закладка не определена.

Project Name: Hubei Golden Tiger New Material Technology Co., Ltd. energy saving highperformance flame-retardant composite exterior insulation system construction project ...... 36

Project name: Metal Material Co., Ltd. Wuhan Rui Saike precious metal resources recycling project ........................................................................................................................... 37

Project Name: Dingnan Ganzhou daily production 850 tons over the white ultra-thin solar glass project ................................................................................................................... 38

Project Name: Zhengzhou million base annual output of 900,000 cubic meters of concrete commercial concrete projects........................................................................................... 39

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Project Name: Hebei Yuk glass substrate production line equipment (Phase II) Project ....... 39

Project Name: Integrated precious metal recovery projects anode mud .............................. 40

Project Name: Jiangxi Datang development of new materials Co., Ltd. electronic grade purity ultra-fine silica powder production and construction projects ............................................. 41

Project Name: Zhuhai annual output of 22 tons of metal appearance of the composite material production line ................................................................................................... 42

Project Name: Ruoqiang County Hongyuan Mining Co., Ltd. Japan handle 500 tonnes of iron ore processing plant construction projects (update) .......................................................... 43

Project Name: annual output of 3.6 million boxes over white float glass project (update)

............................................................................. Ошибка! Закладка не определена.

Project Name: Kunshan City Star Co., Ltd. The annual production of non-ferrous metal alloy ingot 12000 tons projects ................................................................................................ 45

Project Name: Asahi Glass Display Glass (Kunshan) Co., Ltd. with annual production of TFT panels 6 million square meters of glass of the original expansion ....................................... 45

Project Name: handling 36,000 tons in cinder red mud utilization project ........................... 46

Project Name: East Hope (Sanmenxia) Aluminum Co., Ltd. 1 #, 2 # dry red mud red mud heap library renovation project ........................................................................................ 47

Project Name: Shenhua Energy Co., Ltd. New Street New coal storage stations (5.00Mt / a) project ........................................................................................................................... 48

Project name: Project an annual output of 1.6 million tons of slag ... Ошибка! Закладка не

определена.

Project name: Project an annual output of 1 million tons of slag ........................................ 50

Project Name: Henan Province Coalbed Methane Development and Utilization Co., Ltd.

Dongsheng Coal Co. preparation plant in 2011 upgrading project ...................................... 51

Project Name: Hunan key Bao Steel Co., Ltd. 350,000 tons of stainless steel two projects ... 51

Project name: Chenzhou 150,000 t of copper cathode a project ......................................... 53

Project Name: Mountain west Kangke Industrial Group Co., Ltd. 200,000 tons of refined ferro-nickel project .......................................................................................................... 53

Project Name: Shen Nong Qinyang City Industrial Company 20,000 tons of steel products, glass items ..................................................................................................................... 54

Project Name: 20,000 t metallurgical materials project ...................................................... 55

Project Name: Jiaozuo Kim Sun Special Refractories Co., Ltd. 20,000 tons of new high-purity spinel project .................................................................................................................. 56

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Project Name: Zhengzhou HuaChi Technology Co., Ltd. Sheet processing 500,000 tons in hot galvanized sheet, 300,000 tons of tin plating plate, 40 tons of metal coating, coating printing plate construction projects ............................................................................................... 57

Project Name: Building Material Co., Ltd. Luoyang Longjia 120,000 t ceramic sand project .. 58

Project Name: Long Refractories Co., Ltd. Gongyi City, three 55,000 tons annual output of refractory materials project .............................................................................................. 59

Project Name: Din Tai Yu Co., Ltd. Hotan Prefecture, Xinjiang Hotan jade mines in the county upstart cut feed five tons of jade mining project (updated) ................................................ 60

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Project Name: steel production project

Stage of progress: environmental impact assessment

Construction period: 2011 - 2012

Main equipment: CNC cutting machine, assembly machine, carbon dioxide protection welding machine, semi-automatic submerged arc welding machine, calibration machines, bending machines, drilling machines, gantry crane, driving, etc. (For reference)

Project:

Iron Mountain project is located southeast of the village street offices C, assaulting River Road North, an annual output of steel 20,000 square meters.

The total investment of 85 million investment in environmental protection 4 million.

Construction Unit:*******

Postal Address:*******

Tel:*******

Designer:*******

Postal Code:*******

Contact:*******

Tel:*******

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Project Name: Construction of granite mining project

Stage of progress: environmental impact assessment

Construction period: 2011 - 2012

Main equipment: crushers, air compressors, hole drilling, drilling machines, loaders, etc. (For reference)

Project:

Project is located in the old Zhen Li Pingdu Bucun, east, south and are adjacent to farmland, west, north are adjacent hills. Mining area of 0.0103 square kilometers, mainly in the construction of granite mining, mining construction was 40,000 cubic meters of granite, the production process: the barren hills and the weathered layer of topsoil stripping → → → drilling → blasting platform track laying flat → → → Saw

Stone Cutting loading → transport.

The total investment is unknown.

Construction Unit:*******

Postal Address:*******

Tel:*******

Designer:*******

Postal Code:*******

Contact:*******

Tel:*******

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Project Name: wood products production project

Stage of progress: environmental impact assessment

Construction period: 2011 - 2012

Main equipment: engraving machine, sawing wood, painting machines. (For reference)

Project:

Project is located 112 Pingdu New Road, Qingdao Wald Food Company's existing lease land and plant production, Qingdao, east China Wine Co., Ltd. Hunan, south of Manor Wine Co., Ltd. Qingdao Jia Rui, west of Qingdao, Cheong Tai Chemical Fiber Co., north of Century Boulevard. The total investment $ 2.1 million and covers an area of about 13,340 square meters, mainly engaged in wood products, annual output of about 5,000 sets of wooden doors, the production process: Timber → → puzzle sawing, planing wood

→ → → door machining Posts leather door → → → → product packaging.

The total investment is unknown.

Construction unit:*******

Postal Address:*******

Tel:*******

Designer:*******

Contact:*******

Tel:*******

Project Name: insulation materials, fireproofing materials processing project

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Stage of progress: environmental impact assessment

Construction period: 2011 - 2012

Major equipment: presses, vacuum pumps, lathes, milling machines, etc. (For reference)

Project:

Project is located in Southern towns Pingdu Zhu Zhu Lu 338, Seahorse Electronics Co., Ltd. Qingdao lease the land and the existing production plant, surrounded by all plant and plant adjacent to the lessor hospital. The total investment of 30 million yuan, mainly engaged in insulation materials, fireproofing materials processing, and annual output is 120 tons, the production process: aluminum foil bag → PE → calcium silicate board fill the vacuum → → → drying → packing → sticky side of product .

The total investment of 30 million.

Construction Unit:*******

Postal Address:*******

Tel:*******

Designer:*******

Contact:*******

Tel:*******

Project Name: aluminum, steel doors and windows processing projects

Stage of progress: environmental impact assessment

Construction period: 2011 - 2012

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Major equipment: clean-angle, dual remember, welding and other main and auxiliary equipment. (For reference)

Project:

By the way the project is located in Pingdu No. 1 Zhuhai Road east, south all the way across by the

Ceramics Co., Ltd. Qingdao Huaqing, west of Qingdao, with the wave of agricultural Co., north of Wan

Runfeng mill. The total investment 500 million, covers an area of 16,000 square meters, mainly engaged in aluminum alloy, steel doors and windows processing, 9050 square meters annual output of steel doors and windows, aluminum doors and windows 800 square meters, the production process: (1) windows and doors production process: Plastic Profile → Cut → drilling → insert liner assembly → → → melt welding products; (2) aluminum alloy doors and windows production process: steel profiles → Cut → drilling → → screws inserted liner assembly → → finished product.

The total investment 500 million.

Construction unit:*******

Postal Address:*******

Tel:*******

Design unit: Qingdao Environmental Protection Science Research Institute (EIA agencies)

Postal Address:*******

Tel:*******

Project Name: Foshan Nanhai Danzao Trade Venture Limited 2 million tons of copper alloy expansion project

Stage of progress: environmental impact assessment

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Construction period: 2011 - 2012

Main equipment: sintering machine, shaft furnace, rotary kiln, submerged arc furnace, blast furnace, converter, lime kiln, oxygen station. (For reference)

Project:

Project is located in Nanhai Danzao national eco-industrial park, the expansion after the dismantling of the original project remain the same size, also added frequency and intermediate frequency electric furnace for purchased copper (Cu 99.7% above) and zinc (zinc greater than 99.99%) for copper-zinc alloy, copper production was 60% of the brass rods and brass ingots, the production was 11,100 tons / year and 8862 tons

/ year. Foshan Nanhai Trade Venture Limited Danzao waste materials recycling business, the main project, including dismantling and processing plant, ancillary works including raw materials yard and the yard solid waste, waste gas treatment area, treatment area, with electrical room. Public works is mainly office space.

After expansion, the project consists of essentially the same, but the main project to increase alloy manufacturing projects. The planned total area of 22,176 square meters of land (33.26 acres total), with a total construction area of 9450 square meters, floor area ratio of 0.43, greening rate of 3%.

The total investment of 30 million.

Construction Unit:*******

Postal Code:*******

Contact:*******

Tel:*******

Fax:*******

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Project Name: Shanxi Coal Transportation and Marketing Group Mountain Coal Co., 0.45Mt / a mergers and acquisitions integration project of mine

Stage of progress: environmental impact assessment

Construction period: 2011 - 2012

Main equipment: coal machine, cited coal, lifting equipment, axial mine fan, belt conveyor, drilling equipment, coal machine, screening equipment, crushing equipment, cranes, coal centrifuges, conveyor belts, jig, pressure filter, flotation beds, filter press, cage, water pumps, fans, automatic control systems, explosion-proof electrical, elevator, conveyor, ball mill, vibrating screen, crusher, conveyor, water treatment equipment, heavy medium cyclone, sieve dehydration, coal centrifugal dewatering machine, flotation machine. (For reference)

Project:

Project is located in the south suburb of Datong City, the mine 9, 11, 12 (in the original alpine region),

14-2, 14-3 Longwall mining coal using a full height coal mining law, the former coal mine south suburban area of small kiln 12 coal mining method using high-grade conventional mining, the roof caving method using all the management. Auto Sinotrans, a total investment of 147,586,800 yuan, 11-month construction period, length of service 10.2a.

The total investment 147,586,800 yuan.

Construction Unit:*******

Postal Code:*******

Contact:*******

Tel:*******

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Fax:*******

Designer:*******

Postal Code:*******

Tel:*******

Pass Fax:*******

Project Name: Hui Co., the fourth city and there are stone quarrying area 100 tons / year production line quarrying

Progress stage: the record

Construction period: September 2011-March 2012

Major equipment: hole drilling, forklifts, cars, excavators, etc. (for reference)Project:

Project is located in the town of Mountain Lee Weihui grandfather quarrying of the area, the project is

100 tons / year production line of quarrying for cement stone supply and the Company 1.2 million tons of gravel supporting the project, hire Weihui grandfather Town on behalf of the meaning village bean trench hills northwest of 12.99 acres (do not add to, not for land clearance), the construction of annual extraction volume is 1 million tons of rock quarry. Process: open-pit mining; drilling, crushing, loading shovel, transport. The main drill hole equipment, forklifts, cars, excavators, etc..

The total investment 500 million.

Construction Unit:*******

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Postal Code:*******

Contact:*******

Tel:*******

Project Name: Anhui Conch Cement production line Quanjiao (Phase II) Project

Progress stage: construction started in

Construction period: 2011 - 2012

Main equipment: loose, screw type air compressor, conveyor belts, air purifier, modular air compressor, tank, bar-type gate, electric blinds valve, electric control valve shutters, electric gate valve, single layer of heavy hammer lock wind flap valve, heater, machine-made powder, dusting equipment, rotary kiln, reclaimer, decomposition furnace, cooling equipment, cooling towers, dosing devices, continuous blowdown expansion device, modular water softener equipment, water tanks, vacuum deaerator, crushing equipment, drying equipment, transportation equipment, ingredients, testing equipment, automatic control systems, ball mill, vibrating screen, crusher, conveyor. (For reference)

Project:

Project is located in Chuzhou Quanjiao cross town planning and construction of two new dry day 5000 tons of cement clinker production lines and annual output of 2.2 million tons of cement grinding system, and supporting construction of 18MW waste heat power generation projects. This is the second phase, construction of a Nissan 4500 tons of new dry process cement clinker production line.

The total investment of 1.5 billion, two investment of about $ 0.6 billion.

Construction Unit:*******

Postal Code:*******

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Contact:*******

Tel:*******

Fax:*******

Project Name: Foshan City super-sub Die Casting Plastic Co., Ltd. Expansion Project

Stage of progress: environmental impact assessment

Construction period: 2011 - 2012

Main equipment: CNC lathe, milling, drilling, machining centers. (For reference)

Project:

Project is located in Dali Town, Nanhai District, Foshan City, North Industrial Zone, Lek, expanded, diecasting products production from 25,000 / year increased to 100,000 / year, die-casting products production in the original production process to increase the product cleaning, some painting, drying and other sectors, the original 0.1T cooker (cooker before the expansion of the role of melting aluminum ingot) to 0.5T melting furnace; mold production scale and production processes were not changed, that is, 100 sets / year .

In addition, injection products no longer in production, injection molding equipment removed. Workshop and the main works include melting pressure (water) casting workshop, painting workshop and die shop and other production plant, ancillary works including warehouses, gas treatment facilities, solid waste temporary field, water treatment facilities. Including office buildings and other public works. The planned total land area of 5,000 square meters, total construction area of 3,600 square meters, floor area ratio of

0.72.

The total investment 200 million yuan.

Construction unit:*******

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Contact:*******

Tel:*******

Fax:*******

Project Name: Nanhai, Foshan City, Cao edge metal casting plant expansion project

Stage of progress: environmental impact assessment

Construction period: 2011 - 2012

Main equipment: die-casting machines, lathes, EDM machine. (For reference)

Project:

Project is located in Dali Town, Nanhai District, Foshan City, Cao edge industrial three areas, the original intended site for technical innovation, expansion, the expansion of the existing reverberatory furnace to 3 t 10 t, out rub ash furnace, flue gas desulphurization dust supporting measures. Covers an area of 1500 m2, renovation and expansion, the principal producer of zinc alloy ingots, involving processes including casting, die casting machine casting process, cancel the rub gray machine processes, produce zinc-aluminum alloy ingots of about 8550t / a.

The total investment is unknown.

Construction Unit:*******

Contact:*******

Tel:*******

Fax:*******

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Project Name: Shanxi Coal Transportation and Marketing Zhongyue Coal Industry Group Co., Ltd. 90 million t / a mine mergers and acquisitions integration project

Stage of progress: environmental impact assessment

Construction period: 2011 - 2012

Main equipment: coal machine, cited coal, lifting equipment, axial mine fan, belt conveyor, drilling equipment, coal machine, screening equipment, crushing equipment, cranes, coal centrifuges, conveyor belts, jig, pressure filter, flotation beds, filter press, cage, water pumps, fans, automatic control systems, explosion-proof electrical, elevator, conveyor, ball mill, vibrating screen, crusher, conveyor, water treatment equipment, heavy medium cyclone, sieve dehydration, coal centrifugal dewatering machine, flotation machine. (For reference)

Project:

Project is located in Township Wangjiazhuang large Zezhou Village, venue to be selected row in the gangue Township Wangjiazhuang Zezhou large village in the west of the ravines. Approved mining 3 # -

15 # coal seam, Ida area 6.6853km2, approved the scale of 900,000 tons of mine production / year.

The total investment is unknown.

Construction Unit:*******

Postal Code:*******

Contact:*******

Construction period: 2011 - 2012

Main equipment: coal machine, cited coal, lifting equipment, axial mine fan, belt conveyor, drilling equipment, coal machine, screening equipment, crushing equipment, cranes, coal centrifuges, conveyor belts, jig, pressure filter, flotation beds, filter press, cage, water pumps, fans, automatic control systems,

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us. explosion-proof electrical, elevator, conveyor, ball mill, vibrating screen, crusher, conveyor, water treatment equipment, heavy medium cyclone, sieve dehydration, coal centrifugal dewatering machine, flotation machine. (For reference)

Project:

Project is located in rural Shanxi Province, Linfen Yaodu Cang on the pillow near the village, township administrative divisions are under the jurisdiction of the pillow. Ida integrated area 16.1274km2, integrated planning capacity of 0.90Mt / a. Approval of 11 coal mining 2. Service life of 44 years, pioneering the use of means shaft, a longwall mining method adopted full-height, full management of the roof caving method.

The total investment 772,604,600 yuan.

Construction Unit:*******

Postal address:*******

Postal Code:*******

Contact:*******

Stage of progress: environmental impact assessment

Construction period: 2011 - 2012

Main equipment: coal machine, cited coal, lifting equipment, axial mine fan, belt conveyor, drilling equipment, coal machine, screening equipment, crushing equipment, cranes, coal centrifuges, conveyor belts, jig, pressure filter, flotation beds, filter press, cage, water pumps, fans, automatic control systems, explosion-proof electrical, elevator, conveyor, ball mill, vibrating screen, crusher, conveyor, water treatment equipment, heavy medium cyclone, sieve dehydration, coal centrifugal dewatering machine, flotation machine. (For reference)

Project:

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Project is located in the town of Jia guocun Qinyuan County west of King and approved coal mining from 1 to 3, Ida area 1.0575km2. Mine production capacity from 90,000 t / a, upgraded to 300,000 t / a, net capacity of 210,000 t / a. The No. 1 mine is mining coal, the use of high-grade Pu inclined longwall coal mining methods, the use of all cross off the roof control method management, to develop methods for the inclined open.

The total investment is unknown.

Construction Unit:*******

Postal Address:*******

Tel:*******

Fax:*******

Design units: Institute of Environmental Science, Shanxi Province (EIA agencies)

Postal Address:*******

Tel:*******

Fax:*******

Project Name: Shanxi Coal Co., Ma Yu Chang letter 1.2Mt / a mergers and acquisitions integration project of mine

Stage of progress: environmental impact assessment

Construction period: 2011 - 2012

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Main equipment: coal machine, cited coal, lifting equipment, axial mine fan, belt conveyor, drilling equipment, coal machine, screening equipment, crushing equipment, cranes, coal centrifuges, conveyor belts, jig, pressure filter, flotation beds, filter press, cage, water pumps, fans, automatic control systems, explosion-proof electrical, elevator, conveyor, ball mill, vibrating screen, crusher, conveyor, water treatment equipment, heavy medium cyclone, sieve dehydration, coal centrifugal dewatering machine, flotation machine. (For reference)

Project:

Project is located in Shanxi Province, Hu Jia Zhuang Shi Qiaoxiang Qinyuan County along the Red, Red

Shiqiao Xiang is under the jurisdiction of the administrative divisions. The combined area of 16.7578km2, new area 8.5099km 2, production capacity from 300,000 t / a raised to 1.2 million t / a, new production capacity 900,000 t / a. After the reorganization of the whole layer of coal mine field can be 1, 9 +10, 10, the

No. 11 coal seam, after the actual exploitation of a reorganization, 9 +10, 10, the No. 11 coal. New main shaft, Vice inclined, pedestrian inclined, return air brush inclined to use large existing wellbore.

The total investment is unknown.

Construction Unit:*******

Postal address:*******

Postal Code:*******

Contact:*******

Tel:*******

Project Name: Shanxi Coal Transportation and Marketing Group charcoal valley Coal Co. 0.60Mt / a mergers and acquisitions integration project of mine

Stage of progress: environmental impact assessment

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Construction period: 2011 - 2012

Main equipment: coal machine, cited coal, lifting equipment, axial mine fan, belt conveyor, drilling equipment, coal machine, screening equipment, crushing equipment, cranes, coal centrifuges, conveyor belts, jig, pressure filter, flotation beds, filter press, cage, water pumps, fans, automatic control systems, explosion-proof electrical, elevator, conveyor, ball mill, vibrating screen, crusher, conveyor, water treatment equipment, heavy medium cyclone, sieve dehydration, coal centrifugal dewatering machine, flotation machine. (For reference)

Project:

Project is located in the south suburb of Datong City, the rural population Springs Village, the combined charcoal coal valley open way inclined - adit development, 8 #, 19-22 #, 23-24 #, 25 # coal seam mining classified as a level , the level of elevation of +1180 m. The use of mechanized coal mining all Ida, all roof caving method management, mine production capacity 0.6M0t / a, car Sinotrans, a total investment of

305,212,700 yuan, 32.6 months construction period, length of service 31.2a.

The total investment is unknown.

Construction Unit:*******

Postal Code:*******

Contact System : Han Should

Tel:*******

Fax:*******

Designer:*******

Postal Code:*******

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Tel:*******

Fax:*******

Project Name: Zhengzhou Morishige annual output of 400,000 square meters Building Materials Co., Ltd.

Class A fire-retardant wall insulation materials used in construction projects

Progress stage: under construction

Construction period: August 2011 to March 2012

Major equipment: mixer, hydraulic press, etc. (for reference)Project:

Project is located in Zhengzhou Machinery Manufacturing (processing) industrial park, office Bai

Zhaicun be water, land lease construction projects with a total area of 2700 square meters, total construction area of 1,200 square meters, including workshop 800 square meters, warehouse 200 square meters, the other 200 square meters, process technology: mixing raw materials, molding module → → air dry (winter maintenance) → products. Major equipment mixers, hydraulic machine 3 / sets. Product raw material for the fly ash, fire protection materials, finished size is 300mm × 500mm × 50mm, 300mm ×

500mm × 40mm.

The total investment 107 million.

Construction Unit:*******

Postal Code:*******

Contact:*******

Tel:*******

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Project Name: Henan Huamei Industry Co., Ltd. plastic profile plastic items

Progress stage: under construction

Construction period: August 2011 to December 2011

Major equipment: profile extrusion machine, milling machine, mixer, etc. (For reference)Project:

Private industrial park project is located in Zone No. 3 Road, the project covers an area of 10.6 mu, annual output of ten thousand tons steel profiles; technology: PVC and accessories mix - co-extrusion molding - cool shape - cutting - Inspection - Packing - storage; Profile Extrusion of major equipment, flour mill, mixer and so on.

The total investment of 45 million.

Construction unit:*******

Postal Code:*******

Contact:*******

Tel:*******

Project Name: produce 100,000 tons of equipment, steel projects

Progress stage: under construction

Construction period: August 2011 to December 2013

Major equipment: leveler, NC straight cutting machine, shearing machine, gantry automatic submerged arc welding machine, shot blasting machine (for reference)Project:

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Project is located in Yuanyang County Industries, the project covers an area of 222.64 acres, the new production plant, warehouse, office buildings, staff quarters, auxiliary buildings and other construction area of 120,000 square meters total. Technology: outsourcing steel, steel and other raw materials, the materials organization, shearing (cutting), combination, welding, straightening, drilling, painting, testing, Sinotrans, the installation finished. Major equipment leveler, NC straight cutting machine, shearing machine, gantry automatic submerged arc welding machine, shot blasting machines.

The total investment 550 million yuan.

Construction unit:*******

Postal Code:*******

Contact:*******

Tel:*******

Project Name: Qing Feng assimilation of new material Technology Co., Ltd. 20,000 tons of new material cellulose project

Progress stage: the record

Construction period: October 2011 to October 2012

Major equipment: field emission environmental scanning electron microscopy, scanning electron microscopy, atomic force microscopy, nuclear magnetic resonance spectrometer and so on. (For reference)Project:

Qingfeng industry cluster project is located, the project covers an area of 40 mu, annual output of 20,000 tons of new material cellulose. Technology: semi-cellulose, the primary analysis of fiber infrared

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us. instrument data selection → → → Fiber Products granulation particle diameter control fibers with different fiber combinations → → integrate the best products; major equipment field emission environmental scanning electron microscopy, scanning electron microscopy, atomic force microscopy, nuclear magnetic resonance spectrometer and so on. The product is widely used in food, water, etc., can be used to the field of medicine.

The total investment 300 million yuan.

Construction Unit:*******

Postal Code:*******

Contact:*******

Tel:*******

Project Name: Hui Co., the third city and there are stone quarrying area 100 tons / year production line quarrying

Progress stage: the record

Construction period: September 2011-March 2012

Major equipment: hole drilling, forklifts, cars, excavators, etc. (for reference)Project:

Project is located in the town of Mountain Lee Weihui grandfather quarrying of the area, the project is

100 tons / year production line of quarrying for cement stone supply and the Company 1.2 million tons of gravel supporting the project, located in the mountain town of Lee Quarry planning grandfather area northwest of the West on behalf of the village, meet the "Weihui mining gravel, lime producers regional planning", Town grandfather rented Weihui justice on behalf of the village ditch hills northwest of 12.99 acres of beans (do not add to, not for land clearance) construction in the amount of one million tons of rock

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us. mining quarry. Process: open-pit mining; drilling, crushing, loading shovel, transport. The main drill hole equipment, forklifts, cars, excavators, etc..

The total investment 500 million.

Construction Unit:*******

Postal Code:*******

Contact:*******

Tel:*******

Project Name: Building Materials Co., Bavaria peak source 2000t / d clinker production line technological transformation project

Progress stage: engineering design

Construction period: 2011 - 2012

Main equipment: loose, screw type air compressor, conveyor belts, air purifier, modular air compressor, tank, bar-type gate, electric blinds valve, electric control valve shutters, electric gate valve, single layer of heavy hammer lock wind flap valve, heater, machine-made powder, dusting equipment, rotary kiln, reclaimer, decomposition furnace, cooling equipment, cooling towers, dosing devices, continuous blowdown expansion device, modular water softener equipment, water tanks, vacuum deaerator, crushing equipment, drying equipment, transportation equipment, ingredients, testing equipment, automatic control systems, ball mill, vibrating screen, crusher, conveyor. (For reference)

Project:

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Project is located in Xinjiang Uygur Autonomous Region Bayingolin Mongol Autonomous Prefecture

Qiemo a station southwest of 3km, covers an area of 21.33hm, the construction of 2000t / d cement production line and auxiliary facilities with the construction of power generation waste heat, produce the clinker 62 tons, annual output of 850,000 tons of cement.

The total investment 292,085,600 yuan.

Construction unit:*******

Postal Address:*******

Tel:*******

Design unit: Xinjiang Institute of Building Design

Postal Address:*******

Tel:*******

Fax:*******

Project Name: 16 × 13500KVA ferroalloy submerged arc furnace construction project

Progress stage: has the record

Construction period: 2011 - 2012

Major equipment: submerged arc furnace, refining furnace, automatic mechanical presses, grinding machines by type, such as desulphurization and dust removal system (for reference)

Project:

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Project is located in Xinjiang Korla Economic & Technological Development Zone, set aside land for development, an area of 330,000 square meters, planned to build 16 × 13500kVA short HOOD semi-closed mine hot furnace of industrial silicon, silicon Nissan about 450 tons, annual output of industrial Silicon

130,000 tons.

The total investment 200 million yuan.

Construction unit:*******

Postal Code:*******

Contact:*******

Tel:*******

Project Name: Jiaozuo City, Xin Cheng Special Materials Co., Ltd. 150,000 tons of special refractory materials production line

Progress stage: under construction

Construction period: August 2011-February 2013

Main equipment: mixing equipment, 2500T presses, isostatic molding machines, large vibration molding machine, extrusion machine equipment. (For reference)Project:

Project is located in Jiaozuo City, the western industrial agglomeration area by three-way North West

Weiwu, 150,000 tons of special refractory materials production line, covering 232 acres, construction of factory workshop 60,000 square meters, 40,000 square meters of raw materials library, finished 40,000 square meters, and other facilities 20,000 square meters, construction of four high temperature tunnel kiln.

Technology: materials (A12O3 powder, super calcined coke, Suzhou soil, etc.) - the ratio - sintering - test -

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us. finished. Major equipment mixing equipment, 2500T presses, isostatic molding machines, large vibration molding machine, extrusion machine equipment. Products with a high temperature, corrosion resistance, high strength, low moisture absorption and extended a series of outstanding small properties, widely used in the energy, petrochemicals, electronics, metallurgy, construction, light industry, aerospace, environmental protection departments.

The total investment 800 million yuan.

Construction Unit:*******

Postal Code:*******

Contact:*******

Tel:*******

Project Name: Air Port Aluminum Technology Co., Ltd. Fujian aluminum production project

Progress stage: preliminary design

Construction period: 2011 November - November 2012

Major equipment: construction materials, wall decoration materials, glass doors and windows, sanitary ware, elevators, cranes, waterproof anti-corrosion materials, paint coatings, valve components, ceramic products, instruments, water supply and drainage systems, fire systems, pipe fittings, water supply equipment, outdoor drainage, building electrical, lighting, low voltage electrical appliances, wire and cable, weak systems, lightning protection systems, low voltage power distribution equipment, steel structures.

(For reference)

Project:

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Project is located in Fuzhou, Fujian, Fuzhou Airport Industrial Zone, the construction of ten blocks of five single-storey complex building, covers an area of 137,944 square meters, total construction area of

87,000 square meters, including: factories, office buildings, dormitory, warehouse, canteen.

Total investment 34,128 yuan.

Construction Unit:*******

Postal Code:*******

Contact:*******

Tel:*******

Construction Unit:*******

Postal Code:*******

Contact:*******

Tel:*******

Designer:*******

Postal address:*******

Postal Code:*******

Contact:*******

Stage of progress: environmental impact assessment

Construction period: 2011 - 2012

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Main equipment: coating equipment, steel equipment, flat curved steel furnace, flat steel furnace, vacuum induction melting furnace, insulating line, pretreatment equipment. (For reference)

Project:

Project is located in Wuhu Economic Development Zone, Eastern District, covers an area of about 1,000 acres (666,670 m2), a total investment of 8.57 billion yuan, the construction of eight sixth-generation flat panel display glass substrate production line, two touch-screen glass production lines and supporting facilities, After the completion of an annual 5.5 million glass production capacity.

The total investment 8.57 billion yuan.

Construction Unit:*******

Postal Address:*******

Tel:*******

Fax:*******

Designer:*******

Postal Code:*******

Contact:*******

Tel:*******

Fax:*******

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Project Name: Hubei Science and Technology Development Co., Ltd. Wai Road polymer utilization of wood-plastic composites industry projects

Stage of progress: environmental impact assessment

Construction period: 2011 - 2012

Main equipment: granulators, shredders. (For reference)

Project:

Project is located in Hubei (Xiangyang) Shenzhen Industrial Park project, the polymer to achieve an annual output of 40,000 tons plastic composite materials production capacity.

The total investment of 80 million, of which 31 million yuan investment in equipment.

Construction:*******

Postal address:*******

Postal Code:*******

Contact:*******

Tel:*******

Project Name: Gongyi City Public Source Co., 1000 tons of ultra-fine abrasive powder processing project

Progress stage: the record

Construction period: October 2011 to December 2011

Major equipment: Crusher, Raymond Mill, screening machine (for reference)Project:

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Chi Tian Zhenyi project is located in Gongyi City, Waterloo Village home, 3000 square meters, total construction area of 2200 square meters. Material: corundum, silicon carbide and so on. Process: raw materials - crushing - screening - packaging - the finished product. Major equipment crusher 2, Raymond 1 units, screening machine 2. Products are mainly used for photovoltaic, and metallurgy industries.

The total investment 10 million yuan.

Construction Unit:*******

Postal Code:*******

Tel:*******

Project Name: Dengzhou Stone Processing Co., Ltd. Oriental process 70,000 tons of quartz powder in the project

Progress stage: the record

Construction period: September 2011-September 2012

Major equipment: broken stone machine, grinding machine, screening machines and other equipment (for reference)Project:

Project is located in Dengzhou waist Dianxiang, Deng project covers an area of 30 acres to build production plant and support facilities area of 12,000 square meters; to Xingshan white fruit quarry (mining

Certificate No. 411 381 071 009) of ore and scrap as raw material, the introduction of two production line, using ore crushing grinding → screening → → → finished product inspection and storage process; major purchase of broken stone machines, grinding machines, screening machines and other equipment; products are widely used in glass, foundry, ceramics and construction, rubber, refractories, etc. industries.

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

The total investment 11 million yuan.

Construction Unit:*******

Postal Code:*******

Contact:*******

Tel:*******

Project Name: Forging an annual output of 680,000 tons and 60 tons of metal rolled products project

(updated)

Progress stage: has the record (EIA at the same time)

Construction period: 2011 - 2012

Major equipment: electric arc furnace, hydraulic press, vertical, horizontal CNC lathe, milling machine, boring machine, etc. (For reference)

Project:

Shashi project is located in Jingzhou City Economic Development Zone, annual production capacity of

680,000 tons and 600,000 tons of metal casting and forging products, production lines rolling. The main products of this project is Φ 10-32mm rods, casting and forging products including special high-quality shape casting of 180,000 tons, not stereotypes casting 0.5 million tons.

The total investment 696.85 million yuan.

Construction Unit:*******

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Postal Code:*******

Contact:*******

Tel:*******

Designer:*******

Postal Code:*******

Tel:*******

Project Name: Special cutting edge of solar silicon material of construction projects

Stage of progress: environmental impact assessment

Construction period: 2011 - 2012

Major equipment: jaw-breaking machines, milling machines, centrifuges, air compressors, dryers, Europe grams, ultrasonic shaker. (For reference)

Project:

Project is located in Yicheng, Hubei Province Economic Development Zone, Song four, 500 acres of land to build solar wafer cutting edge material dedicated production lines, a total of three phases, a project is finished, the normal annual output of 25,000 tons can be achieved solar wafer cutting special edge materials that produce 12,240 tons of solar silicon cutting fluids and cutting powder, 12,760 tons of solar silicon. Construction Content: exclusive cutting edge of solar silicon material production lines, warehouses, comprehensive building and other facilities.

The total investment is unknown.

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Construction:*******

Contact:*******

Stage of progress: environmental impact assessment

Construction period: 2011 - 2012

Main equipment: rock drill, winch, air compressor, excavator, transformers, pumps, cage, motor vehicles, boring machine, the shield machine, drilling mud circulation reserve tanks, fans, hoists, hooks, crushers, shovel car, DTH drilling. (For reference)

Project:

Project is located ten miles west and County Township Kawamura, away from the county about 12km2, covers an area of 40.1674hm2. Mining using underground mining methods, the thickness of less than 6 m ore mine left a shallow hole method, the thickness of the ore body uses more than 6 meters using Sublevel law, supporting the construction of mine ventilation, gas, drainage, communication systems. Ore cyanidation carbon-wide mud slurry process, a closed-circuit crushing and screening using two crushing process; grinding using two closed-circuit grinding process; carbon dip - all-clay adsorbed cyanide - carbon slurry adsorption process, carbon leaching process for two additional sixth prepreg suction side upstream side dip process, electrolysis and smelting works include desorption purification of two golden section in the mud. Wei ditch the project intends to build a total capacity of 1,930,700 m3 of tailings.

The total investment 184.38 million yuan.

Construction Unit:*******

Postal Code:*******

Contact System : Wang Fu-Kuo

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Tel:*******

Designer:*******

Tel:*******

Project Name: Hubei Golden Tiger New Material Technology Co., Ltd. energy saving high-performance flame-retardant composite exterior insulation system construction project

Stage of progress: environmental impact assessment

Construction period: 2011 - 2012

Major equipment: foam tunnel kiln, annealing kiln, equipment for cutting and polishing, dusting devices.

(For reference)

Project:

Project is located in Jiangbei District, Huangshi City, Huangshi Gang Industrial Park. Project land area

26035.4m2, the project designed to produce a new type of organic and inorganic flame-retardant polymer foam composite materials 8,000 tons.

The total investment 42 million yuan.

Construction:*******

Postal Code:*******

Contact:*******

Tel:*******

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Designer:*******

Postal Code:*******

Contact System : Wang Su Wen

Tel:*******

Project name: Metal Material Co., Ltd. Wuhan Rui Saike precious metal resources recycling project

Stage of progress: environmental impact assessment

Construction period: 2011 - 2012

Major equipment: ball mill, classifier, flotation level, filter, thickener, magnetic separator, corrosion mixing bad and so on. (For reference)

Project:

Project is located in Wuhan Economic and Technological Development Zone, four on the 18th business, the annual disposal of 1000 tons scrap containing precious metals, including palladium-containing scrap, platinum scrap, gold scrap, silver scrap.

The total investment 600 million.

Construction Unit:*******

Postal Address:*******

Tel:*******

Design:*******

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Contact:*******

Tel:*******

Fax:*******

Project Name: Dingnan Ganzhou daily production 850 tons over the white ultra-thin solar glass project

Progress stage: engineering design

Construction period: 2012 January - December 2012

Major equipment: tin bath, launder, air separation equipment, annealing kilns, furnaces, testing equipment, water treatment equipment, instrumentation. (For reference)

Project:

Projects are located in Ganzhou, Jiangxi Dingnan old town Duan village, an industrial development area of approximately 166,750 square meters, including: plant, two production lines.

The total investment of 80 million.

Construction Unit:*******

Postal address:*******

Postal Code:*******

Contact:*******

Tel:*******

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Project Name: Zhengzhou million base annual output of 900,000 cubic meters of concrete commercial concrete projects

Progress stage: the record

Construction period: September 2011-January 2012

Main equipment: mixer imports of 180 strong, 120 strong of the mixer, the material can, CH80-type sand separator, 50 forklifts, mixer truck, concrete pump, 200 tons of weighbridge (for reference)Project:

New city project is located under the curved beams cattle town village, covering 13 acres. Construction of offices, laboratories, control room 1,000 square meters, factory building 2500 square meters, storage yard and related facilities covering 2500 square meters. New production of C15-C60 900,000 cubic meters of concrete mixing station one; the main raw material: Qualified stones, river sand, cement, fly ash, slag, additives and so on. Main processes: the computer automatically ingredients, stir into the C15-C60 concrete mixer to the site. The main equipment of mixer imported a 180 strong, 120 strong of a mixer with 8 materials can, CH80-type sand separator set, 3 sets of 50 forklifts, 18 sets of mixer truck, concrete pump two, 200 tons a weighbridge and other equipment.

The total investment 10 million yuan.

Construction Unit:*******

Postal Code:*******

Contact System By: Wei Huijun

Tel:*******

Project Name: Hebei Yuk glass substrate production line equipment (Phase II) Project

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Progress stage: engineering design

Construction period: 2011 November - May 2012

Main equipment: coating equipment, steel equipment, flat curved steel furnace, flat steel furnace, vacuum induction melting furnace, insulating line, pretreatment equipment. (For reference)

Project:

Project is located in Shijiazhuang High-tech Zone Plot No. 73, with a total floor area of approximately

57,200 square meters, including: plants, R & D center, production line.

The total investment 100 million yuan.

Construction Unit:*******

Postal Code:*******

Contact:*******

Tel:*******

Fax:*******

Project Name: Integrated precious metal recovery projects anode mud

Progress stage: under construction

Construction period: August 2011-April 2012

Major equipment: side-blown reduction furnace, blowing furnace, refining furnace, reverberatory furnace antimony, bismuth converter (reference)Project:

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Kim Lee's project is located within the plant, the construction scale: anode slime treatment capacity of

10,000 tons / year, production of silver bullion 800t / a, gold bullion 800Kg / a, antimony white 2000t / a, copper 272t / a, fine bismuth 360t / a. Technology: the use of advanced production technology to restore bilateral direct blow, with a metal straight high yield, short production cycle, environmental benefits and good. Major equipment side-blown reduction furnace, blowing furnace, refining furnace, reverberatory furnace antimony, bismuth converter.

The total investment 149 million yuan, of which 58 million yuan raised by the enterprise, domestic bank loan 91 million yuan.

Construction Unit:*******

Postal Code:*******

Contact System By: Yanyong Zhou

Tel:*******

Project Name: Jiangxi Datang development of new materials Co., Ltd. electronic grade purity ultra-fine silica powder production and construction projects

Progress stage: the record

Construction period: 2011 - 2012

Major equipment: Silica production line (for reference)Project:

Economic transformation project is located in Jiangxi Anyuan industrial base, the new Silica production line 10, building area of 158,000 square meters, an annual high-purity electronic grade ultra-fine silica powder 50,000 tons and 50,000 tons of industrial grade silica production capacity.

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

The total investment 321.56 million yuan, sources of funding solutions for the enterprise itself.

Construction Unit:*******

Tel:*******

Project Name: Zhuhai annual output of 22 tons of metal appearance of the composite material production line

Progress stage: preliminary design

Construction period: 2011 12 Month - October 2012

Major equipment: construction materials, wall decoration materials, glass doors and windows, sanitary ware, elevators, cranes, waterproof anti-corrosion materials, paint coatings, valve components, ceramic products, instruments, water supply and drainage systems, fire systems, pipe fittings, water supply equipment, outdoor drainage, building electrical, lighting, low voltage electrical appliances, wire and cable, weak systems, lightning protection systems, low voltage power distribution equipment, steel structures.

(For reference)

Project:

Gaolan Port project is located in Zhuhai, Guangdong, Hong Pingsha sea economic zone north side, an industrial development area of approximately 66,755 square meters, total construction area of approximately 53,404 square meters, including: factories, workshops, three production lines.

The total investment of 60 million yuan.

Construction Unit:*******

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Postal Address:*******

Tel:*******

Project Name: Ruoqiang County Hongyuan Mining Co., Ltd. Japan handle 500 tonnes of iron ore processing plant construction projects (update)

Stage of progress: environmental impact assessment

Construction period: 2011 - 2013

Major equipment: mining, air compressor, cage, mining equipment, pumps, cranes, monitoring equipment, ventilation equipment, dust removal equipment, crusher, ball mill, flotation machine (for reference)

Project:

Project is located in Ruoqiang County Industrial Park according to swallow Braque, daily processing of iron ore 500 tons of ore was 100,000 tons / year, annual output of iron powder (content of 63% - 65%) 5 tons. Construction of the concentrator, aided engineering and environmental engineering and other ancillary works. Project uses the commonly used two broken, three magnetic separation process.

The total investment $ 9.2 million.

Construction Unit:*******

Postal Code:*******

Contact:*******

Tel:*******

Design unit: Xinjiang Department of Building Environmental Assessment (EIA agencies)

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Postal Address:*******

Construction period: 2011 - 2012

Major equipment: material system, glass furnace, rolling machine, annealing furnace and steel equipment.

(For reference)

Project:

Project is located in Hamilton alkali industry plant in the region, adding an area of 200,000 m2 (about

300 acres), to build a complete 600t / d ultra-white float glass production line, from raw, burning materials into the finished glass factory to factory to the production and its accompanying power supply, water supply, control and other auxiliary production facilities and assisted living facilities.

The total investment of 350 million yuan.

Construction Unit:*******

Postal Code:*******

Contact:*******

Tel:*******

Design unit: Xinjiang Department of Building Environmental Assessment (EIA agencies)

Postal Address:*******

Tel:*******

Fax:*******

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Project Name: Kunshan City Star Co., Ltd. The annual production of non-ferrous metal alloy ingot 12000 tons projects

Stage of progress: environmental impact assessment

Construction period: 2011 - 2012

Major equipment: frequency melting furnace, medium frequency induction furnace and other equipment.

(For reference)

Project:

Project is located in Kunshan City Town Club Lane Road, south of alloy ingot 12000 tons annual production.

The total investment of 26 million.

Construction units:*******

Postal Address:*******

Tel:*******

Fax:*******

Project Name: Asahi Glass Display Glass (Kunshan) Co., Ltd. with annual production of TFT panels 6 million square meters of glass of the original expansion

Stage of progress: environmental impact assessment

Construction period: 2011 - 2012

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Major equipment: glass cutting machine, washing machine, steel furnace, screen printer, Stretching

Machine . (For reference)

Project:

Project is located in Kunshan, Jiangsu Province Economic Development Zone Industrial Park, Weishan

Lake Road photoelectric north, pengxi Road, west side, the original annual production capacity of TFT glass plate 6 million square meters.

Total investment $ 295 million.

Construction Unit:*******

Postal Code:*******

Contact:*******

Tel:*******

Design:*******

Postal Code:*******

Contact:*******

Tel:*******

Project Name: handling 36,000 tons in cinder red mud utilization project

Progress stage: has the record

Construction period: 2011 - 2012

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Main equipment: dismantling equipment, compactors, separators, conversion equipment, sorting equipment, waste crushing equipment (for reference)

Project:

Project is located in Changsha, Hunan Wangcheng brass circular economy industrial base, works in the red mud slag processing 36,000 tons, annual output of 21,600 tons of iron oxide, the annual extraction of precious metals gold 423 kg, 2300 kg of metal silver, mixed metal 2000 t , year square tiles 135,000 square meters.

The total investment 177.38 million yuan.

Construction Unit:*******

Postal Address:*******

Tel:*******

Project Name: East Hope (Sanmenxia) Aluminum Co., Ltd. 1 #, 2 # dry red mud red mud heap library renovation project

Progress stage: the record

Construction period: September 2011-November 2011

Major equipment: forklift, forklifts, power distribution facilities, excavators, bulldozers, lifting equipment, hoist, gates, valves, pumps (for reference)Project:

Project is located MianChiXian Industries, the company's 1 #, 2 # wet red mud discharge the remaining capacity of the existing library for the transformation of red mud dry heap, increased capacity of 6.6 million tons of red mud emissions. The company was drained alumina plant about 2.2 million tonnes of red mud, 1

#, 2 # dry red mud heap library renovation is complete dry tailings stack library in line with national

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us. standards for third-class libraries, and libraries around the dry stack anti-seepage treatment casual meet environmental requirements; the project does not increase the transformation of land, can further improve the surrounding environment, greatly reducing the safety, environmental pressures, and the comprehensive utilization of red mud for the future development for raw materials.

The total investment 50,011,000 yuan.

Construction unit:*******

Postal Code:*******

Contact:*******

Tel:*******

Project Name: Shenhua Energy Co., Ltd. New Street New coal storage stations (5.00Mt / a) project

Stage of progress: environmental impact assessment

Construction period: 2011 - 2012

Major equipment: spray facilities, nuclear weighbridge, laboratory equipment, loading equipment. (For reference)

Project:

Project is located within the package Ordos City Yinjinhuoluo Longwan God railway tunnel turn at

North 1.2km, transforming the train station after the transfer Longwan venues. Near the coal mine or coal preparation plant acquired from high-quality thermal coal, Jiancang stored inside the station, and then transformed through the transfer station of coal Sinotrans Longwan sales. Storage station planning to build five and a half-underground product storage; belt conveyor bridge; reproduced point; high and low voltage

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us. power distribution room; production, life, fire water; material library; machine repair shop; weighbridge room; boiler room; sewage treatment stations, public toilets and other joint construction office.

The total investment 97,422,000 yuan.

Construction Unit:*******

Postal Address:*******

Construction period: 2011 - 2012

Major equipment: vertical mill, dryer, air compressor, product tank, belt conveyor, boiling furnace, filter, bucket elevator, feeder, loaders and other equipment. (For reference)

Project:

Iron Mountain project is located in Beihai Port industrial area, construction materials and products including storage, drying systems, grinding system and the corresponding ancillary works.

The total investment 240 million yuan.

Construction units:*******

Postal Code:*******

Contact:*******

Tel:*******

Design:*******

Postal Code:*******

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Contact:*******

Tel:*******

Project name: Project an annual output of 1 million tons of slag

Stage of progress: environmental impact assessment

Construction period: 2011 - 2012

Major equipment: vertical mill, dryer, air compressor, product tank, belt conveyor, boiling furnace, filter, bucket elevator, feeder, loaders and other equipment. (For reference)

Project:

Iron Mountain project is located in Beihai Port industrial area, construction materials and products including storage, drying systems, grinding system and the corresponding ancillary works.

The total investment 150 million yuan.

Construction units:*******

Postal Address:*******

Tel:*******

Design:*******

Postal Code:*******

Contact:*******

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Tel:*******

Project Name: Henan Province Coalbed Methane Development and Utilization Co., Ltd. Dongsheng Coal

Co. preparation plant in 2011 upgrading project

Progress stage: the record

Construction period: from November 2011 to September 2012

Major equipment: two heavy medium cyclone products, coal de-referral screening, referral screen waste rock removal, coal centrifugal dryer, cyclone coal classification group, coarse coal slurry centrifuges, filter presses, roller dryer (for reference)Project:

Project is located in the town of Jiaxian the ecliptic, the annual handling 1.2 million tons of coal mining group based coal preparation plant. Technology: heavy medium cyclone separation, jigging separation process. There are two major equipment, heavy medium cyclone 1 product sets, 2 sets of screen-mediated removal coal, waste rock off the screen a referral units, coal centrifugal dewatering machine 2, the coal classification cyclone Group 1 Group, coarse coal 1 slime centrifuge units, filter presses, 3 sets of drum dryer 2.

The total investment 135,325,500 yuan.

Construction unit:*******

Tel:*******

Project Name: Hunan key Bao Steel Co., Ltd. 350,000 tons of stainless steel two projects

Progress stage: engineering design

Construction period: 2012 June - June 2013

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Major equipment: construction materials, wall decoration materials, glass doors and windows, sanitary ware, elevators, cranes, waterproof anti-corrosion materials, paint coatings, valve components, ceramic products, instruments, water supply and drainage systems, fire systems, pipe fittings, water supply equipment, outdoor drainage, building electrical, lighting, low voltage electrical appliances, wire and cable, weak systems, lightning protection systems, low voltage power distribution equipment, steel structures.

(For reference)

Project:

Project is located in Luxi County, Hunan Tujia and Miao Autonomous Prefecture Wu River Industrial

Park, an industrial development, with a total area of about 266,666 square meters, including: factories, office buildings, warehouses.

The total investment of 200 million yuan.

Construction Unit:*******

Postal Code:*******

Contact System : Ma Qi-yong

Tel:*******

Construction Unit:*******

Postal Code:*******

Contact:*******

Tel:*******

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Project name: Chenzhou 150,000 t of copper cathode a project

Stage of progress: environmental assessment feasibility study

Construction period: 2012 March - March 2013

Major equipment: construction materials, wall decoration materials, glass doors and windows, sanitary ware, elevators, cranes, waterproof anti-corrosion materials, paint coatings, valve components, ceramic products, instruments, water supply and drainage systems, fire systems, pipe fittings, water supply equipment, outdoor drainage, building electrical, lighting, low voltage electrical appliances, wire and cable, weak systems, lightning protection systems, low voltage power distribution equipment, steel structures.

(For reference)

Project:

Project is located in Guiyang County, Hunan Chenzhou Jiaoxiang sub-Long Village, an industrial development, with a total area of 509,490 square meters, including: workshops, offices, staff quarters.

The total investment of 2.5 billion.

Construction Unit:*******

Postal Address:*******

Tel:*******

Project Name: Mountain west Kangke Industrial Group Co., Ltd. 200,000 tons of refined ferro-nickel project

Progress stage: the record

Construction period: 2011 --- 2012

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Major equipment: 33000kVA submerged arc furnace, 25500kVA submerged arc furnace, kiln (for reference)Project:

Hejin City street project is located in West Wangda Kang Industrial Park office, no additional land.

Water 400m3 / d, power 2.3 million kWh / d, water, electricity and rely on the company to resolve the existing public auxiliary facilities. The main construction content using the efficient use of refined nickellaterite nickel ore smelting iron rotary kiln - submerged arc furnace technology (RKEF), New 33000kVA submerged arc furnace 1, 25500kVA submerged arc furnace 2, the rotary kiln 3 and related facilities and equipment, new by building area 33000m2, the formation of annual output of 200,000 tons of refined nickel-iron production capacity.

The total investment 460 million yuan, including fixed assets investment 380 million yuan, initial working capital of 80 million. Sources of funding: apply for bank loans to 300 million yuan, 160 million yuan raised by the enterprise.

Construction unit:*******

Tel:*******

Fax:*******

Project Name: Shen Nong Qinyang City Industrial Company 20,000 tons of steel products, glass items

Progress stage: under construction

Construction period: August 2011-August 2012

Major equipment: industrial digital control computer, the spindle frequency drive system, servo system operation wire, photoelectric sensor group, electrical boxes and other operations (for reference)Project:

Project is located in industrial parks purple Qinbei gulingzhen Zhao Zhaicun, the project covers an area of 44 acres, plant, office building area of 22,500 square meters; the main production line using a computer system programmed to achieve the lining system, winding, curing, stripping, etc. the whole process

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us. automatic control; mainly from industrial equipment, digital control computer, the spindle frequency drive system, servo system operation wire, photoelectric sensor group, composed of electrical control box.

The total investment 150 million yuan.

Construction units:*******

Contact:*******

Tel:*******

Project Name: 20,000 t metallurgical materials project

Progress stage: under construction

Construction period: August 2011 to December 2012

Major equipment: ball mill, Raymond mill, crusher, dryer, dust equipment. (For reference)Project:

Yue Village project is located in Wen County auspicious Avenue, the construction scale of 20,000 t metallurgical materials (slag anti-sticking agent), covering 80 acres, the construction of integrated building, workshop, warehouse, staff quarters, dining and other infrastructure area of 45,000 square meters. The project is mature technology, the main processes: outsourcing Steel Group, Hebei Iron Railway ditch ramming material (waste), Guangxi, silica and other raw materials - broken - mixing - classification - to adjust the ratio of - testing - finished product storage. Major equipment ball mill, Raymond mill, crusher, dryer, dust removal equipment. Products as steel, metallurgy, container, spray paint, sticky residue clean-up can not only reduce the workload, but also to reduce refractory consumption, but also help to improve steel quality, the products are mainly exported to China Railway Equipment Group, Hebei, China Iron and Steel

Group.

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

The total investment 96 million yuan, of which 60 million yuan raised by the enterprise, domestic bank loan 36 million yuan.

Construction Unit:*******

Postal Code:*******

Contact:*******

Tel:*******

Project Name: Jiaozuo Kim Sun Special Refractories Co., Ltd. 20,000 tons of new high-purity spinel project

Progress stage: the record

Construction period: September 2011-February 2012

Major equipment: electronic batching machine, jaw crusher, sand making Bamako, electrical and automation control systems, belt bucket elevator 250, etc. (for reference)Project:

Project is located in Jiaozuo City, the new industrial park in the station area, the construction of highpurity spinel produce 20,000 tons of new production lines. The project covers an area of 3 acres of factory building area of 1,500 square meters. Technology: the dolomite, magnesium oxide and other raw materials through the Park → Library → computing, said screw conveyor bucket → → → cone mixer bucket → middle → Database → bucket feeding Ogura → → Sheng calcined material package unpacking → → → demolition crushing and screening options. Major equipment electronic batching machine, jaw crusher, sand making Bamako, electrical and automation control systems, belt bucket elevator, etc. 250. Products are mainly used in steel smelting, cement kilns and other industrial kiln and glass high-temperature refractory lining.

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

The total investment 10 million yuan.

Construction Unit:*******

Postal Code:*******

Contact:*******

Tel:*******

Project Name: Zhengzhou HuaChi Technology Co., Ltd. Sheet processing 500,000 tons in hot galvanized sheet, 300,000 tons of tin plating plate, 40 tons of metal coating, coating printing plate construction projects

Progress stage: the record

Construction period: September 2011-December 2012

Major equipment: high-speed reversible cold rolling mill 1450, 1450 electrolytic degreasing unit, trimming slitting machine, 1450 formation, straightening machine, full hydrogen bell-type annealing, 1450 electrogalvanized units, 1450 units of tin plating, painted 1450 printing unit. (For reference)Project:

Project is located in industrial parks Xinzheng City, Newport Avenue, Newport West, the project's original use of space, the main building of 88,000 square meters workshop, office, warehouse and other ancillary facilities 2,400 square meters. Electro-galvanized sheet Process: hot-rolled coil - Slitting - continuous pickling - cold - hot dip galvanized - finished; plating tin plate technology: hot rolled coil -

Slitting - continuous pickling - cold - Degreasing Cleaning - Heat Treatment - tin - drying - the finished product; color coated printing plate technology: hot rolled coil - Slitting - continuous pickling - cold - color coated printing - the finished product. All of the above process does not produce cyanide-containing substances. Devices have high-speed reversible cold rolling mill 1450, 1450 electrolytic degreasing unit, trimming slitting machine, 1450 formation, straightening machine, full hydrogen bell-type annealing, 1450 electro-galvanized unit, tin plating unit 1450, 1450 printing color coating unit.

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

The total investment 550 million yuan.

Construction Unit:*******

Postal Code:*******

Contact:*******

Tel:*******

Project Name: Building Material Co., Ltd. Luoyang Longjia 120,000 t ceramic sand project

Progress stage: under construction

Construction period: August 2011-February 2012

Main equipment: mixer, blender, shaker, granulators, rotary kiln, cooling kiln, gas stove (for reference)Project:

Town project is located in Yichuan high gold Hutuo Village, the project covers an area of 23 acres, plant area of 5,000 square meters. Main raw materials: coal gangue, aluminum, manganese, iron, kaolin; production process: raw materials - screening - in proportion to mixing - mixing - pellet - Heating - Cooling

- Packing. Major equipment mixer, mixer, shaker, granulators, rotary kiln, cooling kiln, gas furnace.

The total investment 46 million yuan, of which 31 million yuan raised by the enterprise, domestic bank loan 15 million yuan.

Construction Unit:*******

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Postal Code:*******

Contact:*******

Tel:*******

Project Name: Long Refractories Co., Ltd. Gongyi City, three 55,000 tons annual output of refractory materials project

Progress stage: under construction

Construction period: August 2011-August 2012

Major equipment: roller machine, jaw Crusher, Raymond Mill, mixer, shaker, shaking table (for reference)Project:

Project is located in Gongyi City, North Shan Kouzhen West Village, an area of 10 mu, building area of

4700 square meters. Construction of three major workshops, management, housing and so on. Raw materials: bauxite, sodium tripolyphosphate, sodium hexametaphosphate, sodium pyrophosphate, Emery, corundum aggregate. Process: stone materials - selection - broken - Mill - produced hybrid - finished - the factory. The main equipment of the roller machine 2, jaw-breaking machine 3, Raymond 2, sand machine 5 sets, 2 sets of vibrating screen, vibrating table 2.

The total investment 24 million yuan.

Construction Unit:*******

Postal Code:*******

Contact:*******

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Tel:*******

Project Name: Din Tai Yu Co., Ltd. Hotan Prefecture, Xinjiang Hotan jade mines in the county upstart cut feed five tons of jade mining project (updated)

Stage of progress: environmental impact assessment

Construction period: 2011 - 2012

Main equipment: rock drill, winch, excavators, transformers, pumps, cage, motor vehicles, boring machine, the shield machine, drills, fans, hoists, hooks, crushers, forklifts, air compressors, drill hole and so on. (For reference)

Project:

Kunlun Mountains in the Xinjiang Uygur Autonomous Region Project Mulberry trees Tage - Liu Shi

Tage middle uplift alpine mountains, located in the southwest city of Hotan, Xinjiang-Tibet Highway from

2.5km, Hotan County under the jurisdiction of the administrative divisions. Mining center geographic coordinates: longitude 78 ° 50 '10 ", latitude 36 ° 14' 28", mine an area of about 1.6 square kilometers. Jade mining ore resources within the 57.5 tons of mine is a small mine. There are three ore mining were L1, L2,

L3. Terrain and from the mine location to see the road layout outside the mining area, combination ore size analysis, design the first phase of mining L2 orebody, followed by exploitation of L1, L3 orebody. Design scale mining 5t / a, for the open pit mining methods, length of service 10.74 years, the project is expected to total 347,600 yuan investment, the design work of mine was 120 days, 8 hours day. Configure all mine

12. Mine the main production unit for the living area, waste rock field (set to three waste rock site), blasting equipment, library, road mines, covering the type of barren land. Bring their own diesel generators, mining, domestic water from the mine in the valley near the river channel pull perennial water transport, the

Ministry of mine living area built a 3 m3 tank.

Total investment 347,600 yuan.

Construction Unit:*******

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

The weekly issued Project E-journal collects the latest information of projects which are approved by the Chinese government. If you are interested in the E-journal with contact, please Contact us.

Postal Code:*******

Contact:*******

Tel:*******

Design:*******

Postal Code:*******

Contact:*******

Tel:*******

Fax:*******

Chinabidding

11th Floor, Guoxing Tower, No.22 Capital Gymnasium South Road, Haidian District, Beijing,

China 100044

Phone : +86-10-82744588

Fax :

E-Mail :

+86-10-82743720 contact@chinabidding.com.cn, chinainfo@chinabidding.com.cn http://www.chinabidding.com.cn

www.chinabidding.org

Download