News release via Canada NewsWire, Toronto 416-863-9350 Attention Business Editors: Jericho Diamond Project - Updated Feasibility Study TAHERA CORPORATION (TSX: TAH) TORONTO, June 18 /CNW/ Highlights - Developing Tahera's wholly-owned Jericho Diamond Project as Nunavut's first diamond mine - Updated Jericho Diamond Project feasibility study indicates robust economics for a diamond mining operation centered on the land-based Jericho kimberlite - Forecast diamond production of +3,000,000 carats over a minimum mine life of 8 years - IRR of 44% and NPV(5%) of $123 MM (WWW modeled diamond valuation) - NPV(5%) increased by 8% (WWW valuation), and NPV(5%) increased by 26% (SRK valuation) versus previous study Tahera Corporation is pleased to announce the results of the updated Jericho Diamond Project feasibility study. SRK Consulting completed the original feasibility study in 2000, and Tahera engaged SRK Consulting to update the study to reflect current conditions. Dowding Reynard & Associates (Pty) Ltd. (DRA), who have extensive experience in design and construction of diamond plants; Nuna Logistics, experienced Nunavut mining contractors; and WWW International Diamond Consultants Limited (WWW), well known diamond industry experts, provided input for the study. SRK Consulting also engaged Tinus Oosterveld, a professional mining engineer, for input regarding diamond valuation and reserve estimates. Mr. Oosterveld was previously employed with De Beers Consolidated Mines Ltd., where he was in charge of the mineral resource department, and responsible for the assessment of kimberlite deposits throughout the world. The mineral reserves changed slightly in the updated study versus the original study, resulting from increasing the open-pit dilution factor. The mine plan, which indicates that approximately 3.1 million carats will be produced over an eight-year mine life, is relatively unchanged. The current plan consists of open-pit mining of approximately 2 million tonnes (2.4 million carats) of kimberlite reserves, followed by underground mining of 615,000 tonnes (673,000 carats) of kimberlite reserves. The following chart shows a summary of the updated feasibility study results. SRK Consulting utilized an average diamond valuation for the base case feasibility study (i.e. mid point between WWW diamond valuation and Tinus Oosterveld diamond valuation). The feasibility study results using the WWW diamond valuation is indicated in the right hand column. << ------------------------------------------------------------------------Jericho Diamond Project 2003 Feasibility Study (C$ 000's, unless otherwise noted) --------------------------------------SRK Consulting WWW modeled diamond valuation diamond valuation ------------------------------------------------------------------------Total resource 7.1 million tonnes 7.1 million tonnes (at) 0.84 c/t (at) 0.84 c/t ------------------------------------------------------------------------Indicated resource 3.7 million tonnes 3.7 million tonnes (at) 1.17 c/t (at) 1.17 c/t ------------------------------------------------------------------------Inferred resource 3.4 million tonnes 3.4 million tonnes (at) 0.52 c/t (at) 0.52 c/t ------------------------------------------------------------------------Diamond valuation US$81/ct US$92/ct ------------------------------------------------------------------------Mineral reserve 2.6 million tonnes 2.6 million tonnes (at) 1.2 c/t (at) 1.2 c/t ------------------------------------------------------------------------Total carats produced 3,115,000 3,115,000 ------------------------------------------------------------------------Carats mined open-pit 2,442,000 2,442,000 ------------------------------------------------------------------------Carats mined underground 673,000 673,000 ------------------------------------------------------------------------Revenue 364,628 412,451 ------------------------------------------------------------------------Operating cost 173,289 173,289 ------------------------------------------------------------------------Operating cost per carat (C$/ct) 56 56 ------------------------------------------------------------------------Operating cash flow 191,339 239,162 ------------------------------------------------------------------------Capital expenditures - open pit Diamond Plant Facilities 13,995 13,995 Ancillary Facilities 14,896 14,896 Site Preparation 5,537 5,537 Mobilization / Demobilization 2,954 2,954 Owners' Costs 1,621 1,621 Pre-production mining 8,929 8,929 --------Sub-total 47,932 47,932 ------------------------------------------------------------------------Contingency 4,793 4,793 ------------------------------------------------------------------------Total Capital Open pit 52,725 52,725 ------------------------------------------------------------------------Capital - Underground 8,672 8,672 ------------------------------------------------------------------------Sustaining capital 2,854 2,854 ------------------------------------------------------------------------Contingency 1,152 1,152 ------------------------------------------------------------------------Total Project Capital 65,403 65,403 ------------------------------------------------------------------------Cash flow after capex 125,936 173,759 ------------------------------------------------------------------------NPV (at) 5% 85,510 123,089 ------------------------------------------------------------------------IRR 32.7% 43.6% ------------------------------------------------------------------------Mine life (years) 8+ 8+ ------------------------------------------------------------------------Figures are before taxes, royalties, and financing. C$ (equal sign) 0.70US$ Approximately 80% of the mineral reserve is derived from the high-grade centre lobe, containing a mineral reserve of approximately 2.08 million tonnes with a recovered grade of 1.31 carats per tonne. Approximately 520,000 tonnes of ore at a recovered grade of 0.75 carats per tonne will be mined from the northern lobe, which will be processed at the end of the mine life. As part of the mine plan, approximately 1.63 million tonnes of inferred resource will be mined and stockpiled. Tahera is confident that a considerable amount of this inferred resource may be converted to mineral reserve following adequate assessment of its diamond grade and value, resulting in an extension of the mine life. The proposed 50 tonne per hour diamond processing plant will be constructed approximately 1 kilometre from the Jericho kimberlite and will operate year round. At full capacity, the diamond processing plant is capable of processing 68 tonnes per hour. Capital and operating costs increased by approximately 19% and 11% respectively versus the 2000 study. The increased capital cost is in part due to an increased contingency factor applied in the updated study. The operating cash flow increased significantly in the current study versus the 2000 study (13% - 25% increase), as did the NPV(5%) (8% - 26% increase). Permitting, Project Financing & Timeline ---------------------------------------The Nunavut Impact Review Board (NIRB) recently determined that the Final Public Hearings for consideration of the Jericho Diamond Project Environmental Impact Statement (EIS) would be rescheduled to ensure that all of the relevant environmental and socio-economic data and information are available before the NIRB executes its decision-making obligations regarding the Project. To facilitate the EIS review process, Tahera has organized a series of meetings with various regulatory groups who submitted additional information requests regarding the Project. The meetings, which are scheduled to occur during the week of June 16th, will provide a discussion forum whereby Tahera and the regulatory groups can address and clarify any outstanding issues regarding the Project. Many reviewers have focused on issues related to water quality and details regarding the design of the processed kimberlite containment area in their submissions. Tahera will endeavour to respond to all issues and information requests within 90 days. Following this schedule, it is likely that the Final Hearings will be rescheduled as early as September, which will allow for the Company to meet its original goal of achieving approval of the Jericho Diamond Project EIS during 2003. In conjunction with the permitting activities, Tahera is actively pursuing project financing for the Jericho Diamond Project, with the goal being to debt finance a large portion of the required project capital. Development of the underground mine will be financed from project cash flow. The following time line been established for development of the Jericho Diamond Project: Target to complete permitting Project financing Design & procurement of plant Mobilization Diamond plant construction & commissioning 2003 2003/04 2004 2004/05 2005 >> Andrew Bradfield, P. Eng. of SRK Consulting is the qualified person with respect to the Jericho Diamond Project. About Tahera Corporation Tahera Corporation (www.tahera.com) is a unique Canadian diamond Company in that it has a positive feasibility study completed on an advanced-stage diamond project. Tahera is focused on developing its wholly-owned Jericho Diamond Project as CANADA'S NEXT and NUNAVUT'S FIRST DIAMOND MINE. Tahera has several other prospective diamond projects in Canada's prolific Slave Craton, including the Rockinghorse Property joint venture, where the significantly diamondiferous Anuri kimberlite occurs. The common shares of the Company trade on the Toronto Stock Exchange under the symbol 'TAH'. %SEDAR: 00003313E /For further information: Tahera Corporation, Grant Ewing - Vice President, Investor Relations & Corporate Development, Tel: (416) 777-1998, Fax: (416) 777-1898, Toll free: (877) 777-2004, Email: investor_relations(at)tahera.com/ (TAH.) CO: Tahera Corporation CNW 10:02e 18-JUN-03