Rooley Moor Wind Farm Environmental Statement Appendix 4.2: Borrow Pit Report ROOLEY MOOR WIND FARM Borrow Pit Report Coronation Power Job No JU095 R004 July 2014 Donaldson Associates Ltd Eastfield Church Street Uttoxeter Staffordshire ST14 8AA ROOLEY MOOR WIND FARM Borrow Pit Report Coronation Power Job No JU095 R004 July 2014 Date Revision Pages Appendices Originator Check Approved 17.06.14 B01 1 - 16 A-B DJL WT WT 01.07.14 B02 1 - 16 A-B DJL WT WT 18.08.14 B03 1 - 16 A-B DJL DW WT Donaldson Associates Ltd Eastfield Church Street Uttoxeter Staffordshire ST14 8AA Donaldson Associates Limited Rooley Moor Wind Farm Borrow Pit Report Coronation Power 1.0 INTRODUCTION 1 2.0 SOURCES OF INFORMATION 3 3.0 SITE LOCATION AND DESCRIPTION 4 4.0 GROUND MODEL 6 5.0 BORROW PITS 9 6.0 CONCLUSIONS & RECOMMENDATIONS 15 LIST OF TABLES TABLE 1: SOURCES OF INFORMATION LIST OF APPENDICES APPENDIX A SITE LAYOUT AND BORROW PIT LOCATION PLAN (JU095 - 023) APPENDIX B BORROW PIT DRAWINGS (JU095 - 021 & 022) 3 Donaldson Associates Limited Rooley Moor Wind Farm Borrow Pit Report Coronation Power 1.0 INTRODUCTION 1.1 Project Summary 1.1.1 Donaldson Associates Limited (DAL) was commissioned by Coronation Power Ltd to undertake a borrow pit study for the proposed Rooley Moor Wind Farm development in Lancashire. 1.1.2 The scheme is currently at concept design stage. 1.1.3 The proposed wind farm comprises 12No. turbines with a combined capacity of up to approximately 39.6MW, access tracks, a sub-station building, and a permanent anemometry mast. 1.1.4 Having estimated the amount of required crushed stone for the construction of the development on site, borrow pits can be designed to produce the required stone volume without the need to import stone from off-site sources, thus reducing construction traffic volume. 1.1.5 The crushed stone requirement calculated is based on a conceptual track design and wind farm layout only, which will be subject to change following any layout revisions and amendments at detailed design stage and following planning approval. The design has been undertaken without benefit of detailed topographical survey or ground investigation and is therefore approximate. 1.1.6 This report identifies the proposed borrow pit locations, their anticipated profile and volume of rock achievable. However this is only a conceptual design and the results of further detailed topographic and ground investigation surveys will result in the confirmation of actual rock quality and amendment to the borrow pit profile, to achieve the required rock volume. 1.1.7 The predominant sandstone bedrock of the site is characteristically interbedded with less suitable mudstone and thinly laminated siltstone and therefore allowances have been made in the borrow pit design and volume calculations for the extraction of surplus material which will not be used in the development. JU095/Reports/R004 Borrow Pit Report B02 1 Donaldson Associates Limited Rooley Moor Wind Farm Borrow Pit Report Coronation Power 1.2 Objective 1.2.1 The objective of this report is to identify suitable borrow pit locations and present a conceptual design of each borrow pit indicating the stone volumes to be extracted at each location. 1.2.2 Each borrow pit design will present the amount of stone to be obtained but also the approximate overburden strip required and subsequent restoration profile on completion of construction. JU095/Reports/R004 Borrow Pit Report B02 2 Donaldson Associates Limited Rooley Moor Wind Farm Borrow Pit Report Coronation Power 2.0 SOURCES OF INFORMATION 2.1 The following sources of information were used in assessing the site and borrow pit proposals: Table 1: Sources of Information Sources of Information British Geological Survey Aerial and satellite photography British Geological Survey Ordnance Survey SKM Enviros SKM Enviros JU095/Reports/R004 Borrow Pit Report B02 Details Date 1:10,000 Scale Geological Sheet Sheet SD81NE for Whitworth 2007 Web based 2014 Website; www.bgs.ac.uk online data (GeoIndex) Historical Mapping centred on NGR: 385718, 418709 & 385768, 416239 Rooley Moor Wind Farm: Mining Risk Assessment Report Constraints Analysis – Peat Depth Contour Plan 3 2014 1851 - 2012 2012 2012 Donaldson Associates Limited Rooley Moor Wind Farm Borrow Pit Report Coronation Power 3.0 SITE LOCATION AND DESCRIPTION 3.1 Site Location and Setting 3.1.1 The site is located approximately 2km northwest of the centre of Rochdale and approximately 4km south of Bacup and Rawtenstall Lancashire. The site is elongated in shape following the ridgeline upon which the Rooley Moor Road public bridleway travels between Rochdale and Rawtenstall, orientated north-northwest to south-southeast. The site is approximately 4km2 in area and centred on Ordnance Survey (OS) National Grid Reference (NGR) SD 861 174, with the site area extending over 4.5km from north to south and over 1.5km west to east at its maximum extents. 3.1.2 The elevations of the site range from approximately 275m AOD in the far south of the site to over 470m AOD in the far north, on the flanks of Top of Leach (474m AOD). 3.1.3 The site is bounded predominantly by adjacent moorland grazing / heath land. The Naden and Greenbooth Reservoirs lie to the west of the southern half of the site, with Spring Mill Reservoir to the east. Cowpe Reservoir lies beyond the northwestern site boundary and the operational Scout Moor Wind Farm is located to the immediate west also. 3.1.3 The majority of the site limits are defined by existing field boundaries and watercourses with the exception of the central western area and the far northeast. 3.1.4 The active Britannia Quarries lie to the northeast, extracting from the Rough Rock Sandstone and Haslingden Flags (Millstone Grit Group -see Section 4.1.). A number of disused quarries lie within the site boundary also which include the larger Ding Quarry in the northwest of the site, the Bagden Quarry in the central east area of the site and the Pink Brow and Cat Stones quarries in the south which all extracted sandstone from the Millstone Grit Group and Coal Measures Group. 3.1.5 Both underground and surface coal mining is known to have been undertaken on the site with numerous mining features visible on the surface; including disused mine entries (shafts and adits) and areas of colliery spoil. The previous mining history of the site is discussed further in Section 4.5. JU095/Reports/R004 Borrow Pit Report B02 4 Donaldson Associates Limited Rooley Moor Wind Farm Borrow Pit Report Coronation Power 3.2 Site Reconnaissance 3.2.1 A number of site visits have been undertaken as part of the geotechnical assessment and conceptual design processes between January and March 2014. During these walkovers the existing quarry sites and other rock exposures were examined as well as the recording of additional peat probe data. Possible new borrow pit locations were explored as well as assessing the possibility of expanding a number of former, now disused, quarries on site. JU095/Reports/R004 Borrow Pit Report B02 5 Donaldson Associates Limited Rooley Moor Wind Farm Borrow Pit Report Coronation Power 4.0 GROUND MODEL 4.1 Solid Geology 4.1.1 Information from the British Geological Survey (BGS) particularly their 2007, 1:10,000 scale map, Sheet SD81NE for Whitworth, confirm that the underlying geology of the site comprises shallow dipping strata of the Upper Carboniferous (320-290Ma) Millstone Grit Group; characterised by thick sandstone beds, interbedded with siltstone, mudstone and rare coal, and the Pennine Lower Coal Measures Formation (Pennine Coal Measures Group), characterised by interbedded mudstone, siltstone and sandstone with numerous coal bands. 4.1.2 The Coal Measures strata comprises; exposed from south the north - the Darwen Flags (fine grained, thinly bedded sandstone), the Milnrow Sandstone (medium grained, cross bedded sandstone), the Helpet Edge Rock (fine to coarse grained, cross laminated and thickly bedded sandstone), the Great Arc Sandstone (fine grained, cross bedded sandstone), Gannister Rock (fine grained, micaceous sandstone) and the Woodhead Hill Rock (fine to medium grained, medium bedded sandstone). 4.1.3 The Coal Measures beds dominate the southern half of the site and fault action has resulted in this succession being exposed again in the most northern part of the site also, separated by the Millstone Grit (interbedded named sandstone, siltstone and mudstone), with identified beds of the Rough Rock (coarse grained, cross bedded sandstone) and the Upper Haslingden Flags (fine grained sandstone interbedded with sandy siltstone), which is present over the majority of the northern half of the site. 4.1.4 The bedrock on the site is unknown in terms of its material properties and would require further assessment of its suitability for use as engineering material at the site, although the extraction history of the site is a positive indicator. The interbedded nature of the bedrock indicates a variable overall composition and a significant proportion of this material may not be suitable for a track surfacing application, for example where thick bands of finer grained mudstone is present. For the above reasons, a 100% volume increase has been applied to the volume JU095/Reports/R004 Borrow Pit Report B02 6 Donaldson Associates Limited Rooley Moor Wind Farm Borrow Pit Report Coronation Power of stone estimated to be required for the development to that used to calculate the borrow pit volumes. 4.2 Drift Geology 4.2.1 The BGS identify only limited superficial geology over the site, with peat deposits being most prominent in the northern half of the site. Glacial till is also identified in the lower lying areas beyond the southern site boundary. 4.2.2 The peat probe surveys undertaken by SKM and supplemented by DAL’s own probing during the walkover; presents results which generally collaborate with the mapped peat deposits, in that the majority of significant peat is confined to the higher elevations in the north of the site. 4.3 Structural Geology 4.3.1 There are a number of northwest – southeast orientated faults which cross the site with downthrows to the northeast and southwest. These have resulted in a large up-thrown area of the older millstone Grit strata being located between the younger Coal Measures strata in the northern half of the site. 4.3.2 There is also a singular northeast – southwest trending fault, with a south-easterly down-throw crossing between two larger, northwest – southeast trending faults near the site’s centre. 4.3.3 The bedrock dips to the south by up to 10 degrees and is sub-horizontal in some areas. 4.4 Outcrops 4.4.1 There are numerous rock exposures within the site, those of sandstone being more numerous due to the more massive bedded nature and the resistance to weathering when compared to mudstone. The bedrock is exposed not only in previous quarry sites but natural sandstone bedrock exposures have been utilised along un-surfaced sections on the route of the Rooley Moor Road. JU095/Reports/R004 Borrow Pit Report B02 7 Donaldson Associates Limited Rooley Moor Wind Farm Borrow Pit Report Coronation Power 4.5 Extraction History 4.5.1 The site shows significant evidence of stone extraction with quarries of various scale scattered around the site. There are workings from at least two coal seams beneath the site with a number of underground coal mine entries and areas of spoil tipping within the site boundary also. Historically the surrounding area of the site has been exploited for quarried stone and coal. JU095/Reports/R004 Borrow Pit Report B02 8 Donaldson Associates Limited Rooley Moor Wind Farm Borrow Pit Report Coronation Power 5.0 BORROW PITS 5.1 Overview 5.1.1 A significant volume of stone is required for the Development. The geology of the site indicates that borrow pits proposed for use in the construction of the Development could potentially be adequate for all potential rock fill required for access tracks, including their finishing surface, hardstandings and up-fill beneath turbine bases where required. This will be confirmed following (i) ground investigation of the site and borrow pit locations and, (ii) detailed design of the project. 5.1.2 The estimated calculations for the rock volume required take into account the main site access roads, smaller access roads (including those for borrow pit access and met mast), rock up-fill at gravity turbine foundations, construction and sub-station compounds and crane hardstandings. The volumes were determined using the Development layout presented on drawing JU095– 023 (Appendix A) and also takes into account the stone volume obtained from other necessary excavations, such as at the construction compound location. 5.1.3 The difference between the density of placed and compacted crushed stone (20kN/m3) and in situ rock density (approximately 25kN/m3) indicates that there will be 25% bulking between original rock and placed volume, this would theoretically reduce the borrow volume to 40,000m3. Due to conceptual nature of the design and the size of the development it is considered that a more conservative approach is adopted and therefore, it is assumed that the 50,000m3 is required and when applying the 100% volume increase to allow for processing losses this equates to a volume requirement of 100,000m3. 5.1.4 Through site visits and analysing of pre-existing data and documents, including topography, geology, peat depth and stability, and overall superficial cover; potential borrow pit locations were determined. Two potential areas of extraction were investigated with volume calculations and borrow pit sections undertaken for both locations. 5.1.5 An assumed 0.75m thickness of superficial cover was included in the borrow pit design, based on site visit records and the peat probing results. The exact volume JU095/Reports/R004 Borrow Pit Report B02 9 Donaldson Associates Limited Rooley Moor Wind Farm Borrow Pit Report Coronation Power and quality of rock available cannot be confirmed until a topographic survey and ground investigation has taken place. 5.1.6 The borrow pits are designed so their excavation does not adversely affect any adjacent infrastructure, particularly the stability of Rooley Moor Road and other site tracks. 5.1.7 During their excavation the disturbance to users of Rooley Moor Road must be considered and measures implemented to reduce the effect of noise and dust to those users by way of optimising the extraction methods e.g. mechanical ripping instead of blasting, the use of silenced vehicles and processing equipment and constructing earth bunds and / or debris / dust fences. 5.1.8 Measures must be employed to prevent waste material from the borrow pits entering adjacent watercourses. The borrow pits will be designed with a front wall, lip or bund on their outer edge to prevent any surface water run-off from the borrow pit fouling the watercourses. 5.1.9 It is recommended that a suitable drainage scheme, in line with the requirements set out in the Environmental Statement, is designed and installed for each borrow pit. Space for a drainage scheme has been accommodated within the designed borrow pit area (the location of the borrow pit area is shown indicatively as dashed area on borrow pit drawings in Appendix B), either within the extents or on the periphery of the excavated pit. It is expected that suitable drainage methods such as filter strips, swales, filter drains, and settlement ponds, be combined and an attenuation system provided to manage surface water run-off. This water could then be discharged under a consented licence following robust settling, clarification and testing processes. 5.1.10 The borrow pit site area is larger than the borrow pits to facilitate working space and storage of overburden until it can be used in subsequent borrow pit reinstatement. 5.1.11 Borrow pits will be reinstated with surplus excavated material to provide a more aesthetic appearance and prevent any unstable and steep rock faces. Complete infilling of borrow pits should be undertaken only under controlled conditions as loose or unstable infill can pose a risk to walkers and animal life. Borrow pit filling JU095/Reports/R004 Borrow Pit Report B02 10 Donaldson Associates Limited Rooley Moor Wind Farm Borrow Pit Report Coronation Power will be controlled and engineered to minimise the risk of future excessive settlement or instability of the fill. 5.1.12 Excavated peat may be used in borrow pit restoration, dependent on the final restoration profiles and the ground conditions around each borrow pit location, which will be confirmed in the peat management plan. The use of unconsolidated peat will be limited to a maximum depth of 1m which will aid landscaping purposes, but the final design will also consider the stability of the placed peat to ensure there are no residual risks resulting from peat slides. 5.1.13 The following sections describe each proposed borrow pit in turn. 5.2 Borrow Pit 1 5.2.1 Overview 5.2.1.1 Borrow Pit 1 is located in the south of the site, close to the entrance, on the eastern flank of Rooley Moor Road, approximately 9m from the road edge. The proposed borrow pit location is an extension of the former Cat Stones Quarry and lies immediately adjacent to the main site access track (along Rooley Moor Road) allowing simple access (See drawing JU095 – 021, Appendix B). 5.2.2 Geology 5.2.2.1 The potential borrow pit location geology comprises fine to coarse grained, cross laminated to thickly bedded sandstone of the Helpet Edge Rock formation. 5.2.3 Hydrology 5.2.3.1 The proposed borrow pit lies approximately 0.7km west of the Spring Mill Reservoir and 0.8m northwest of the smaller Prickshaw Reservoir. Small un-named watercourses feed directly to these water-bodies from an area immediately adjacent to the proposed borrow pit site. Specific drainage measures will have to be employed to retain any borrow pit waste to within the consented borrow pit boundary. JU095/Reports/R004 Borrow Pit Report B02 11 Donaldson Associates Limited Rooley Moor Wind Farm Borrow Pit Report Coronation Power 5.2.4 Peat / Superficial Cover 5.2.4.1 The results of the peat probing survey in this area indicates that the peat and superficial cover in this location appears to be less than 0.50m. However isolated deeper pockets of peat may still be present and there is also the chance of disturbed bedrock and overburden material being present as a remnant of the previous quarry workings. An assumed overall superficial material cover and likely zone of weathered bedrock near the surface of 0.75m thickness in total has been adopted in the borrow pit design and volume calculations. 5.2.5 Topography 5.2.5.1 Topography in this area provides natural cover to reduce effects on residential properties and primary landscape and visual viewpoints to the north. south and west. Although likely to be visible from this direction, there is a separation of the borrow pit from properties to the east of approximately 1km. 5.2.6 Summary 5.2.6.1 The location should be capable of a borrow pit producing up to 40,000m³ of rock; this could be achieved by a 250 by 68m excavation (average dimensions) with a typical maximum excavation depth of 3.5m. Effects on residential properties would be negligible due to separation distance and natural topographic cover. The formation of the borrow pit would be integrated into the development of the main access track. Overburden stripped from the area of the borrow pit excavation will be temporarily stored adjacent to the borrow pit or at a designated temporary storage area before being used in reinstatement of the borrow pit. 5.3 Borrow Pit 2 5.3.1 Overview 5.3.1.1 Borrow Pit 2 is located along a proposed temporary section of access track on the eastern side of Rooley Moor Road (approximately 300m east of Rooley Moor Road), in the centre of the site, between Bagden Hillocks and the disused Bagden Quarry to the east. The proposed borrow pit location lies immediately adjacent to JU095/Reports/R004 Borrow Pit Report B02 12 Donaldson Associates Limited Rooley Moor Wind Farm Borrow Pit Report Coronation Power the temporary access track, approximately 10m away, allowing simple access (See drawing JU095 – 022, Appendix B). 5.3.2 Geology 5.3.2.1 The geology at the potential borrow pit location comprises Millstone Grit lithology (interbedded sandstone, siltstone and mudstone) as well identified beds of the Rough Rock Sandstone (coarse grained sandstone) and the Upper Haslingden Flags (fine grained sandstone interbedded with siltstone). The strata of the borrow pit area dip gently ( approx. 3 degrees) to the southeast. The northeast – southwest trending fault described in Section 4.3 lies at the north-western corner of the proposed borrow pit and the borrow pit’s proximity to the fault may reveal the fault fracture zone on excavation. 5.3.3 Hydrology 5.3.3.1 A number of small un-named minor watercourses lie to the east and south east of the proposed borrow pit location, which eventually converge in Fern Isle Brook which flows into Prickshaw Brook before this watercourse flows into Spring Mill Reservoir to the southeast. Specific drainage measures will have to be employed to retain any borrow pit waste to within the consented borrow pit boundary to avoid waste and debris flowing down slope into the sensitive watercourse. 5.3.4 Peat / Superficial Cover 5.3.4.1 The results of the peat probing survey in this area indicates that the peat and superficial cover in this location appears to be less than 0.5m. However isolated deeper pockets of peat may still be present and there is also the chance of disturbed bedrock and overburden material being present as a remnant of the previous quarry workings. An assumed overall superficial material cover and likely zone of weathered bedrock near the surface of 0.75m thickness in total has been adopted in the borrow pit design and volume calculations. 5.3.5 Topography 5.3.5.1 Topography in this area provides natural cover to reduce effects on residential properties and primary landscape and visual viewpoints to the north, west and JU095/Reports/R004 Borrow Pit Report B02 13 Donaldson Associates Limited Rooley Moor Wind Farm Borrow Pit Report Coronation Power south. Although likely to be visible from this direction, there is a separation of the borrow pit from properties to the southeast of approximately 1km. 5.3.6 Summary 5.3.6.1 The location should be capable of a borrow pit producing up to 60,000m³ of rock; this could be achieved by a 137 x 105m benched excavation (average dimensions) with a typical maximum excavation depth of just over 7m. Due to the size of the excavation and the topography, the excavation will be benched with two levels to achieve the required volume of stone without one excessively deep face. Effects on residential properties would be negligible due to separation distance and natural topographic cover. The formation of the borrow pit would be integrated into the development of the main access road. Overburden stripped from the area of the borrow pit excavation will be temporarily stored adjacent to the borrow pit, before being used in the borrow pit reinstatement. JU095/Reports/R004 Borrow Pit Report B02 14 Donaldson Associates Limited Rooley Moor Wind Farm Borrow Pit Report Coronation Power 6.0 CONCLUSIONS & RECOMMENDATIONS 6.1 Conclusions 6.1.1 Published sources and the site walkover confirm that the majority of the site and the location of each of the borrow pits is underlain by the Upper Carboniferous Millstone Grit Group and the Pennine Coal Measures Group, characterised by interbedded sandstone, siltstone, mudstone and coal seams. The bedrock geology at each borrow pit site is overlain by a mixture of peat, residual soil and weathered bedrock. 6.1.2 Varying depths of peat and peaty soil deposits are present over the site, with some isolated areas having depths greater than 2m. 6.1.3 The bedrock on the site is unknown in its definitive quantity and properties; however; visual examination on site of available exposures and the extraction history of the site indicates that the majority of the bedrock may be of suitable quality for use as engineering fill on the wind farm development and for use in site track construction. 6.1.4 There may be significant bands or beds of unsuitable finer grained mudstone or shale, interbedded with the more favoured medium to thickly bedded sandstone and for this reason a generous 100% volume increase has been applied to the volume of stone estimated to be required for the development to that used to calculate the borrow pit volumes. Until a ground investigation and topographic survey is complete there are risks associates with stone quality and available volume. 6.1.5 An estimated 21,600m3 of unsuitable overburden, including peat, will be produced in the development of the borrow pits. This overburden will be temporarily stored on site adjacent to the borrow pits prior to its use in the restoration of the borrow pits on completion of construction. JU095/Reports/R004 Borrow Pit Report B02 15 Donaldson Associates Limited Rooley Moor Wind Farm Borrow Pit Report Coronation Power 6.2 Recommendations 6.2.1 It is recommended that a comprehensive ground investigation is undertaken prior to development to confirm the ground conditions over the site, including the nature and thickness of the superficial cover along with the weathering state and strength of the bedrock for both foundation assessment and borrow pit suitability. 6.2.2 A detailed topographic survey of the proposed infrastructure locations, including the borrow pit sites will complement the detailed topographic survey of the track layout already obtained. The detailed design of the borrow pits can then be undertaken following detailed cut and fill design, which will provide the actual stone volumes required for the development. 6.2.3 The achievable rock volumes from each borrow pit can then be confirmed. Until a detailed design of earthworks and site infrastructure is undertaken, there are risks associated with required stone quantity. 6.2.4 Consideration must be given at detailed design stage and within the construction stage method statements to the stability of the borrow pits and the overburden storage areas with regard to bedrock, slope and peat stability. Management of the excavations and placement of material must be undertaken and some temporary works may be required prior to use and a safe working distance from the Rooley Moor Road maintained at all times. JU095/Reports/R004 Borrow Pit Report B02 16 Donaldson Associates Limited Rooley Moor Wind Farm Borrow Pit Report Coronation Power APPENDICES JU095/Reports/R004 Borrow Pit Report B02 Donaldson Associates Limited Rooley Moor Wind Farm Borrow Pit Report Coronation Power Appendix A JU095/Reports/R004 Borrow Pit Report B02 Site Layout and Borrow Pit Location Plan Path ) (um 440 LE Y Top of Leach MO OR RO AD 0 45 440 Direction Indicator 0 44 44 0 44 0 RO O Boundary Stone um th ( Pa ) Shaft (disused) d Un BS BS Boro Const Bdy Bdy Co Const & Met Dist 0 46 460 460 d Un 440 450 Und ) Path (um) Red Pits 440 440 44 y W Bd yF nst Bd Co ist ro Bo et D &M nst Co 0 Co 44 0 ac Tr k Refuse Tip Tr ac k Hamer Hill FW ro Bo Co n Co y t ns & LEY Bd Co st ROO 430 M D et MOO ist Bd R RO y 420 AD Def FW 400 De f Tra ck 0 40 Pa th 410 (um ) FW Clegg Ding 380 37 0 410 Bagden Hillocks Bagden Hillocks Bagden Hillocks Rooley Moor Brow 360 RO E OL 40 Y 0 OR MO 0 39 Tra ck AD RO um th ( Pa ) FW Co Boro Const & M Const e Bdy t Dist Bd y 0 38 37 0 Path (um) (um) D ROA Prickshaw Slack Path OR MO 380 LEY ROO 390 Windy Hillock Naden Head Wa rd 0 Co 0 39 Con 3 st & 90 Path (um) Reddyshore Top SP ) (um Bdy th Pa Top of Pike Revision Description Rev. Drn Chkd Appd. Date Status: Higher Croft Hole 380 Refuse Tip 0 38 Cat Stones Refuse Tip Pike Brow Quarry (disused) Refuse Tip CR Refuse Tip 370 360 Reddyshore Pike Brow Cat Stones Quarry (disused) Path (u 0 m) Track 350 35 Client: (um ) Warm Slack Hill Path 340 Pa th (um ) Pa um ) 330 Path (um) 320 Project: Whimsy Hill CR EY OL RO MO 320 C o C on st & W AD ar d RO Bd OR y 0 32 Pa th (um 0 30 ) 300 0 31 31 0 Trac k CJBH WT DJL JULY'14 A1 WT 29 L ET 0 Forsyth Brow L ET Track 1:5000 28 0 Bottom of Rooley Moor 0 th ( 28 36 0 0 39 (um 430 Pa th Pa th (um ) Cattle Grid Turnshaw Hill 2 70 JU095-023 B Donaldson Associates Limited Rooley Moor Wind Farm Borrow Pit Report Coronation Power Appendix B JU095/Reports/R004 Borrow Pit Report B02 Borrow Pit Drawings FW De f Path (um ) 410 Pa th (um ) FW Trac k 400 380 Bagden Hillocks 410 Bagden Hillocks Bagden Hillocks Rooley Moor Brow EY OL RO MO OR AD RO 400 39 0 Trac k Bagden Hillocks 380 Bagden Hillocks Bagden Hillocks EY OL RO OR MO 0 AD RO 40 B A O Revision Description Rev. Drn Chkd Appd.Date Tra ck Status: Client: Project: TKH DJL WT JUNE 2014 A3 WT AS SHOWN JU095-022 B