RIICRC203A INSTALL SUB-SOIL DRAINAGE LEARNER GUIDE Module One – Plan And Prepare THE CUNNING FAMILY TRUST AND THE PEACHEY FAMILY TRUST TRADING AS SAFE WORK RESOURCES PTY LTD ABN 90 785 129 255 (“SAFE WORK RESOURCES”) The information, software, products, and services included in or available through the Safe Work Resources website, applications, documents or any other products may include inaccuracies, operational or typographical errors. Changes are periodically added to the information herein. Safe Work Resources and/or its associated companies/businesses may make improvements and/or changes in the Safe Work Resources website, applications, documents or any other products at any time. Advice received via the Safe Work Resources website, applications, documents or any other products is of a general nature and should not be relied upon for personal, medical, legal or financial decisions and you should consult an appropriate professional for specific advice tailored to your situation. Safe Work Resources and/or its associated companies/businesses make no representations about the suitability, reliability, availability, timeliness, and accuracy of the information, software, products, services and related graphics contained on the Safe Work Resources website, applications, documents or any other products for any purpose. To the maximum extent permitted by applicable law, all such information, software, products, services and related graphics are provided "as is" without guarantee, warranty or condition of any kind. Safe Work Resources and/or its associated companies/businesses hereby, to the maximum of extent permitted by applicable law, disclaim all guarantees, warranties and conditions with regard to this information, software, products, services and related graphics, including all implied warranties or conditions of merchantability, fitness for a particular purpose, title and non-infringement and to the extend guarantees, warranties and conditions are implied and cannot be excluded, Safe Work Resources limits its liability at Safe Work Resources option to the: replacement of the goods or the supply of equivalent goods; repair of the goods or payment of the cost of having the goods repaired; payment of the cost of replacing the goods or of acquiring equivalent goods; or resupplying the services or the costs of resupplying the services. To the maximum extent permitted by applicable law, in no event shall Safe Work Resources and/or its associated companies/businesses be liable for any direct, indirect, punitive, incidental, special, consequential losses or damages or any damages whatsoever including, without limitation, damages for injury or death, loss of use, data, profits, revenue, production, opportunity, goodwill or any similar loss whether or not in your reasonable contemplation, arising out of or in any way connected with the use or performance of the Safe Work Resources website, applications, documents or any other products with the delay or inability to use the Safe Work Resources website, applications, documents or any other products or related services, the provision of or failure to provide services, or for any information, software, products, services and related graphics obtained through the Safe Work Resources website, applications, documents or any other products or otherwise arising out of the use of the Safe Work Resources website, applications, documents or any other products whether based on contract, tort, negligence, strict liability or otherwise, even if Safe Work Resources or any of its associated companies/businesses has been advised of the possibility of damages. Because some states/jurisdictions do not allow the exclusion or limitation of liability for consequential or incidental damages, the above limitation may not apply to you. If you are dissatisfied with any portion of the Safe Work Resources website, applications, documents or any other products or related services or with any of these terms of use, your sole and exclusive remedy is to discontinue using the Safe Work Resources website, applications, documents or any other products or related services. Your use of the Safe Work Resources information, software, products & services is governed by the laws of the state of Victoria and you hereby agree to the exclusive jurisdiction of the courts of or in Victoria and courts of appeal therefrom. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 2 TABLE OF CONTENTS Review Log ..................................................................................................................................... 4! Module Basis .................................................................................................................................. 4! 1.1 Introduction .............................................................................................................................. 5! 1.2 Compliance Documentation ................................................................................................... 6! 1.2.1 Types Of Compliance Documentation ................................................................................................... 7! 1.2.1.1 Project Quality Requirements ........................................................................................................ 9! 1.2.2 Interpreting And Applying Information ................................................................................................. 11! 1.2.3 Workplace Communication ................................................................................................................. 12! 1.2.3.1 Civil Construction Terminology .................................................................................................... 14! 1.3 Safety Requirements ............................................................................................................. 15! 1.3.1 Occupational Health & Safety/Work Health & Safety Legislation ........................................................ 17! 1.3.1.1 Harmonisation Of Work Health & Safety Legislation ................................................................... 17! 1.3.1.2 Material Safety Data Sheets And Safe Handling Methods .......................................................... 19! 1.3.2 Site And Equipment Safety Requirements .......................................................................................... 21! 1.3.2.1 Personal Protective Equipment ................................................................................................... 22! 1.3.2.2 Tools And Equipment .................................................................................................................. 24! 1.3.2.3 Safety Documentation ................................................................................................................. 25! 1.3.2.4 Safe Operating Procedures ......................................................................................................... 27! 1.3.2.5 Emergency Procedures ............................................................................................................... 29! 1.3.3 Risk Management ............................................................................................................................... 32! 1.3.3.1 Consultation And Communicating With Others ........................................................................... 33! 1.3.3.2 Risk/Hazard Identification ............................................................................................................ 34! 1.3.3.3 Risk/Hazard Assessment ............................................................................................................ 35! 1.3.3.4 Risk/Hazard Treatment ................................................................................................................ 36! 1.3.3.5 Monitoring And Review ................................................................................................................ 36! 1.3.3.6 Reporting And Record Keeping ................................................................................................... 37! Appendix 1A – Work Health & Safety Common Terms And Definitions ................................. 38! Appendix 1B – Safe Work Method Statement ........................................................................... 39! RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 3 REVIEW LOG Version Number Date Updated Details of Updates Version 4H Released August, 2013 MODULE BASIS This module is based on the unit of competency RIICRC203A Install Sub-Soil Drainage: Element 1 – Plan and prepare. 1.1. Access, interpret and apply compliance documentation relevant to the work activity. 1.3. Obtain and confirm safety requirements from the site safety plan and organisational policies and procedures, and apply to the allotted task. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 4 1.1 INTRODUCTION Welcome to this unit, RIICRC203A Install Sub-Soil Drainage Systems. The information in this unit applies to the civil construction industry and will cover: Planning and preparing the area. Setting out. Excavating trenches. Installing bedding materials. Installing sub-soil drainage. Cleaning up. This information is aimed at people working within an operational role. Licensing, legislative and regulatory or certification requirements may apply depending upon the location of the worksite. You will need to identify for yourself any requirements that must be met prior to starting on a worksite. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 5 1.2 COMPLIANCE DOCUMENTATION Documentation is essential to all aspects of every worksite. From safety plans and environmental protection requirements through to workplace procedures and policies, documentation exists that outlines what to do, when to do it and how it is to be done. Compliance documentation is the name given to the documents that require you to undertake tasks in a particular way or to meet a given standard. Every worksite will have specific requirements, which will be outlined during your initial induction. Staff should be notified of any changes to compliance documentation during toolbox meetings, staff newsletters or other established forms of communication used on the site. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 6 1.2.1 TYPES OF COMPLIANCE DOCUMENTATION Compliance documentation will detail every step in the process of installing sub-soil drainage. Some examples of compliance documentation include: Legislative and regulatory requirements, e.g. Occupational Health & Safety/Work Health & Safety (OHS/WHS) requirements, equal employment opportunity, disability discrimination. These requirements are standard across every industry within all Australian states or territories. Australian Standards such as AS3798-2007 Guidelines on earthworks for commercial and residential developments. Manufacturer’s guidelines and specifications, e.g. prestart checklists, service requirements, plant and equipment operation manuals. Organisational policies and procedures, e.g. Workplace relations, sick leave requirements. An organisational policy or procedure is standard across the entire organisation regardless of where you are working. Vehicle specifications, e.g. operating limitations and capabilities, safe working limits. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 7 Site-specific policies and procedures e.g. emergency procedures, evacuation procedures. These policies and procedures have been developed to meet the specific hazards, risks or environmental considerations of the site you are working on. Australian guidelines and specifications, e.g. codes of practice such as WorkCover document 2000 – Excavation work or Electrical Practices: Construction and Demolition sites. Training records, e.g. your own training record or licensing requirements. Work instructions, such as work plans, procedures or job specifications. Operational details and quality requirements will also include work instructions and directions. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 8 1.2.1.1 PROJECT QUALITY REQUIREMENTS All civil construction tasks and activities must meet project quality requirements. These are based on project plans and specifications, as well as client expectations. Project quality requirements will detail exactly what you are expected to achieve and the standards you are expected to reach. They may include factors such as: Dimensions and tolerances of tasks. Material standards. Work standards. Documentation requirements. Project specifications and drawings. Client standards and expectations. Pipe depth and slope. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 9 It is essential that these quality requirements are known, understood and adhered to in all activities and tasks, including installing sub-soil drainage. To apply the requirements, you need to follow instructions and procedures exactly. Every task or activity relating to the installation of sub-soil drainage will have quality requirements for activities such as: Compaction. Slope. Levels. Drainage. Shape. If any adjustments need to be made to the stated requirements, you must discuss them with both your supervisor and the project design engineer. . RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 10 1.2.2 INTERPRETING AND APPLYING INFORMATION Being able to access, interpret and apply the requirements of the documents is part of any job on a civil construction worksite. During your site induction you will be told how to access the documentation relevant to your site and duties. It is essential that you are able to read and accurately interpret your workplace policies and procedures so that you can work efficiently and safely, meeting organisational and client expectations. Take the time to read through all the relevant documentation. Make notes about any points you aren’t clear about and then clarify them later. Read or listen to all instructions and follow them carefully. Check the wording of any labels, codes or markings. When interpreting documents it is vital that you understand the difference between words such as should, consider and must. If you have any difficulties interpreting and/or applying requirements or you don’t understand something, speak to your supervisor or team leader. It is always better to ask than to go ahead and possibly disrupt operations and/or cause a safety issue. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 11 1.2.3 WORKPLACE COMMUNICATION On all worksites, good communication is essential to ensuring the safety of personnel/workers and site visitors. Effective communication means that everyone knows what they are required to do, where and when they need to do it, and how they need to do it correctly and safely. It also ensures that all personnel/workers are aware of any problems or risks that may arise on the site and the controls measures that apply. Workplace communication may involve procedures such as: Site meetings. Toolbox meetings. Team briefings. Safe Work Method Statements. Policies, procedures and manuals. Notice boards. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 12 The communications equipment you might need to use could include: Two-way radios. Mobile phones. Landline phones. Computers (e.g. for email, internet, intranet). Fax machines. Signage, hand signals and other non-verbal methods may also be used in some situations, particularly noisy environments. Always use all communications equipment appropriately, following the required procedures and protocols. These requirements will be found in the site documentation and the operator’s manual for each item. Remember that for effective communication to take place, both the speaker and listener need to be properly engaged. You need to make sure that the listener understands what you mean and can make the appropriate response (e.g. answer your question) or take the required action (follow an instruction or direction). RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 13 Sometimes talking alone may not be enough to communicate your message clearly and you might come across communication barriers in your workplace. These barriers could include: Having a non-English speaking background. Using the wrong words. Using jargon, slang or unfamiliar terminology. Being dismissive or condescending. 1.2.3.1 CIVIL CONSTRUCTION TERMINOLOGY The civil construction industry has language standards or terminology that can vary between states, locations or worksites. Individual tasks and activities on a worksite may have a set of terms or phrases with specific meanings. Tools and equipment may be known by various names, and jargon or local slang words could also be used occasionally. It is essential that you are familiar with the terminology used on your site and for specific tasks. If you aren’t sure about the meaning of a particular term, phrase or word you should seek further clarification at team meetings or speak directly with your supervisor. This is important when you are getting your work instructions, carrying out your tasks or operating in any situation where communication is taking place. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 14 1.3 SAFETY REQUIREMENTS Every worksite must meet safety requirements for the state or territory where the site is located. A worksite could include any vertical or horizontal structure intended for construction. Some safety requirements are site-specific, i.e. they may relate to factors specific to the worksite such as weather, ground and environmental conditions. You will be advised of these before you start work. The requirements you need to obtain and confirm will be outlined in the site safety plan and organisational policies and procedures. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 15 Some of these requirements could include: Personal Protective Equipment (PPE). Legislation and regulations, e.g. Occupational Health & Safety/Work Health & Safety (OHS/WHS), environmental protection, material safety data sheets. Organisational requirements, e.g. policies and procedures, safe work method statements/job safety analyses, safe operating procedures. Site requirements, e.g. project plans, safety plans, environmental management plans. Tools, plant and equipment. Safe operating procedures. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 16 1.3.1 OCCUPATIONAL HEALTH & SAFETY/WORK HEALTH & SAFETY LEGISLATION State or territory legislation and regulations include Occupational Health & Safety/Work Health & Safety (OHS/WHS) requirements that will affect the way all operations are conducted on a worksite. All requirements for site and equipment safety, including confined space entry, excavation/trench work, materials handling and all other work activities, are based on OHS/WHS legislation. The aim of the legislation is to ensure the safety of everyone working on or visiting the site. 1.3.1.1 HARMONISATION OF WORK HEALTH & SAFETY LEGISLATION In response to industry calls for greater national consistency, the Commonwealth, states and territories have agreed to implement nationally harmonised Work Health & Safety (WHS) legislation to commence on 1 January 2012. While not all states and territories have actually implemented the model WHS legislation as of the start of 2012, it is important to be aware of these changes, as all states and territories will eventually implement them. Harmonisation aims to develop consistent, reasonable and effective safety standards and protections for all Australian workers through uniform WHS laws, regulations and codes of practice. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 17 Key Elements Of The Work Health & Safety Legislation The following key elements of the WHS legislation will impact the way you do your job, and the responsibilities of your workplace: The legislation also outlines requirements for: The reporting requirements for notifiable incidents. Licences, permits and registrations (e.g. for persons engaged in high risk work or users of certain plant or substances). Provision for worker consultation, participation and representation at the workplace. Provision for the resolution of health and safety issues. Protection against discrimination. Many specific details relating to WHS will be negotiated within the workplace in accordance with the legislation. It is important that you speak with your Health and Safety Representative or supervisor for more information on how these elements will effect your day-to-day operations, or if you have any concerns relating to health and safety. A list of common WHS terms and their definitions can be found in Appendix 1A. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 18 Duty of Care Everyone on a worksite has a legal responsibility under Duty of Care to do everything reasonably practicable to protect others from harm. This is done by complying with safe work practices, including activities that require licences, tickets or certificates of competency or any other relevant state and territory OHS/WHS requirements. 1.3.1.2 MATERIAL SAFETY DATA SHEETS AND SAFE HANDLING METHODS You will find further information that may relate to your work by checking Material Safety Data Sheets (MSDS) and applying materials handling methods. These will detail: Any risks and hazards associated with handling chemicals or other materials. Any special procedures and safe handling methods required. Risk controls. Emergency procedures. Hazardous material containers will usually have a placard or label attached showing the category of material, codes for handling issues and a contact number for expert advice. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 19 Safe material handling could include using effective manual handling techniques such as: Safety plans and site-specific documentation may include all or some of the above information, but normally you will find it in the project and work instructions. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 20 1.3.2 SITE AND EQUIPMENT SAFETY REQUIREMENTS All workers and visitors on a construction site must observe site and equipment safety requirements and procedures. These are outlined in the site safety plan and generally follow OHS/WHS guidelines. Site and equipment safety requirements and procedures cover such things as: Management of hazards and risks. Selecting and using PPE and clothing required for various tasks or the entire site. Selecting and using tools, plant and equipment. Emergency procedures, including the use of firefighting equipment and First Aid equipment. Safety documentation including Safe Work Method Statements, reporting and lines of authority. Safe operating procedures, including safe parking practices. Anything that is faulty or looks like it could create a hazard must be reported at once to your supervisor, team leader or OHS/WHS officer. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 21 1.3.2.1 PERSONAL PROTECTIVE EQUIPMENT Personal Protective Equipment (PPE) is the equipment you must wear or use to protect yourself. Every worksite will have PPE requirements. For construction worksites these pieces of equipment will need to be worn from the time you enter the site, for example, high-visibility clothing and steel-capped boots. Other pieces of PPE would need to be worn only when specific activities are undertaken. For example, hearing protection need only be worn when conducting high noise activities. Signs are usually placed in the workplace to indicate which specific item of PPE is needed. Common PPE includes: Clothing – high-visibility, protective, full body clothing, safety vests. Head– hard hats, sun hats. Hearing– ear muffs, ear plugs. Face– face shield, respiratory protection, dust mask. Hands and eyes – gloves and goggles. Safety harnesses, seat belts. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 22 PPE must be maintained in good condition and replaced if it becomes damaged or defective. PPE is the last line of defence for protecting you from workplace hazards and risks but will only be effective if it is worn correctly and is adjusted to fit the individual. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 23 1.3.2.2 TOOLS AND EQUIPMENT When working on a site, you will be using a variety of equipment and tools. Knowing how to use these safely is essential to keep you and those around you from harm. Read all documentation that applies to the tools and equipment you are using. Also make sure you are familiar with the common problems associated with the equipment or tools and the management of these problems. Speaking with team members or team leaders who have used the equipment before will help you identify any potential issues or problems. Use your PPE and the safety procedures for the site. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 24 1.3.2.3 SAFETY DOCUMENTATION Common tasks and activities that relate to installing sub-soil drainage will have predetermined safety documents. These include Safe Work Method Statements. Safe Work Method Statements A Safe Work Method Statement (SWMS), also known as a Safe Work Procedure (SWP) or Job Safety Analysis (JSA), details how specific hazards and risks, involved with installing sub-soil drainage tasks, will be managed. It is developed by the employer/PCBU for their employees/workers or by a sub-contractor. SWMS fulfil a number of objectives: They outline a safe method of work for a specific job. They provide an induction document that workers must read and understand before starting the job. They assist in meeting legal responsibilities for the risk management process, hazard identification, risk assessment and risk control. They assist in effectively coordinating the work, the materials required, the time required and the people involved to achieve a safe and efficient outcome. They are a quality assurance tool. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 25 To complete a SWMS: It must also be available for inspection at any given time, and be reviewed each year and amended if necessary. An example of an SWMS form can be found in Appendix 1B. Reporting Any safety issue that you identify will need to be reported in accordance with the worksite plans and procedures. This could include a written, computer-generated or verbal report and may be given to a safety officer, your supervisor or a member of the management team. Other reports may include hazard identification logs and records. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 26 1.3.2.4 SAFE OPERATING PROCEDURES Safe operating procedures (SOPs) – sometimes also known as standard operating procedures – are written documents that are used to prevent incidents occurring when using machinery or equipment that has a risk or hazard associated with it. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 27 SOPs for situations that you could come across in your work may include: Situation: Potential SOP details: Site Traffic And Other Machine Movement Overhead Or Underground Services Licensing, familiarisation, inductions, right of way rules. ‘Dial before you dig’ or ‘Look up and live’. Traffic Control And Restricted Access Barriers Stay within the bounds of the traffic and vehicle movement plans. Working At Heights, In Excavations/Trenches, Confined Spaces, Or In Proximity To Others Training, obtaining and abiding by permits, communication. Damaged Or Defective Equipment Tagging out, locking out, isolating equipment. Worksite Personnel/Workers, Visitors And The Public Mandatory worksite inductions, barriers to isolation areas. Environmental And Structural Hazards Environmental protection training, environmental isolations, fencing, barriers. Chemicals And Hazardous Materials Specialised training, keep away and keep others away, notify environmental officer. Weather Conditions Not working in conditions above or below a set temperature, shorter work periods, more work breaks. Restricted Access Areas Training required to enter the zone, PPE requirements, work instructions, emergency procedures. Safe Parking Practices Stay within the bounds of the traffic and vehicle movement plans. Often SOPs will contain a JSA, SWMS or MSDS as well. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 28 Safe Parking Practices Part of the safety requirements and procedures that are common on any worksite working with machinery is good parking procedures. Commonly these procedures include: Parking well clear of overhangs. Keeping all access ways clear. Parking well clear of refuelling locations and sites. Parking away from excavations or other possible environmental hazards. Ensuring vehicles are parked and secured from unauthorised access or movement. 1.3.2.5 EMERGENCY PROCEDURES Emergency procedures relate to all activities on a worksite and may include: Extinguishing fires. Emergency shutdown and stopping. Organisational First Aid requirements. Evacuation. Emergency Shutdown Of Site Or Equipment Use of emergency shutdown equipment on machinery and site emergency shutdown must be done in accordance with worksite requirements. This could need to be done in the case of fire, investigation, accident and incident. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 29 Use Of Fire Extinguishers Fire-fighting equipment on site could range from small hand held extinguishers through to large water cannons. While water cannons are commonly used for dust suppression, they can be turned into a fire-fighting unit if necessary. If a fire starts on site it is essential for the correct type of extinguisher to be used for the type of fire. Steps before using a fire extinguisher: Evacuate the area. Isolate the area. Call emergency services or other designated on-site procedure. If it is safe to use an extinguisher to attempt to control the fire, use the PASS system: Pull the pin. Aim at the base of the fire. Squeeze the trigger. Sweep the base of the fire. Notify your site emergency management team as soon as possible after a fire has been identified and call the fire brigade on 000. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 30 First Aid First Aid is the initial care given to an injured or ill person. Every site will have a first aid officer but you need to be ready to undertake basic first aid treatment until help arrives. Depending on the situation you may need to: Suppress bleeding – press on the bleeding area with a cloth and apply pressure. Monitor an unconscious person – keep them safe, watch for breathing, move them onto their side if you know how to. Treat heat stress – move person into the shade and give small sips of fluid. Assist a person with a broken bone – keep the person calm until help arrives. First aid is an important life skill. Undertaking a full first aid course is highly recommended. Evacuation Involves the removal of at risk personnel/workers from a dangerous area. Things to remember: Keep calm. Move away from the danger to a designated evacuation point. Do not allow bystanders entry to the area. Call for emergency services. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 31 1.3.3 RISK MANAGEMENT Risk management is the process of reducing or managing the risks when working with a hazard or in a hazardous situation and should take into consideration the context of the organisation and worksite. Risk management must be conducted in accordance with: Legislative, organisation and site requirements/procedures. Australian Standards (AS/NZS ISO 31000:2009). Codes of Practice. Employment and workplace relations legislation. Equal employment opportunity and disability legislation. Risk management is made up of the following stages: RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 32 1.3.3.1 CONSULTATION AND COMMUNICATING WITH OTHERS Consultation and communicating with others should be planned for and carried out at every stage of the risk management process. Identifying risks and hazards and coming up with ways of controlling them includes talking to the people with knowledge of the situation, or who are directly affected by any action you may take. Controlling a hazard can be a team effort and it’s important that everybody knows what they need to do and how/if they need to change their work process to suit. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 33 1.3.3.2 RISK/HAZARD IDENTIFICATION Hazards that may be found on a worksite may include: Installed services – underground or above-ground power lines, telephone lines, gas pipes, cables. Overhead structures and services. People – site personnel/workers, non-inducted personnel/workers, site visitors, others authorised or unauthorised. Weather conditions – storms, heat, floods, fires, gas leaks, humidity. Structural hazards – fences, facilities, buildings, other structures or obstructions, poles, traffic areas, work zones, out of area zones, access points bridges, through traffic bridges, buildings. Hazardous materials and substances. Traffic conditions. Working at heights or in confined spaces. Damaged or defective equipment – could include pressurised hoses and fastenings, non-pressurised hoses, ancillary machinery equipment, vandalised equipment. Equipment in use or unattended – vehicles, conveyors, plant, overhead structures and services, abandoned equipment. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 34 Chemical hazards – fuel, chemicals, contaminants, gases, dusts, hazardous substances or materials. Environmental hazards – adjoining walls, structures, unstable or uneven terrain, holes and pot holes, excavations, trenches both open and recently filled, cuttings, embankments, overhanging rocks, trees, dust and noise, unstable faces or areas. Manual handling issues. Material hazards – dangerous materials or other material hazards could include the danger from the hazard but also the manual handling issues around materials. 1.3.3.3 RISK/HAZARD ASSESSMENT A risk assessment involves completing a risk analysis and a risk evaluation. By assessing the likelihood and consequence of the risk, you are able to understand the situation better and respond in an appropriate way. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 35 1.3.3.4 RISK/HAZARD TREATMENT Once risks have been identified, analysed and evaluated, risk treatment options need to be considered and applied. Risk treatment involves selecting one or more options to modify a risk and then implementing the selected option/s. 1.3.3.5 MONITORING AND REVIEW Monitoring and review are an important part of the risk management process and should be planned for at every stage. Monitoring and review involves regular surveillance and checking, and responsibilities concerning it should be clearly defined. It is important that monitoring and review results are recorded and reported according to organisational policies and procedures. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 36 1.3.3.6 REPORTING AND RECORD KEEPING Make sure you record any action you’ve taken and talk to your supervisor and OHS/WHS officer about the control strategies in place. Reports and records could include: Risk Assessment Reports. Incident Reports. Job Safety Analysis. Safe Work Method Statements. Keeping records is important as they can help ensure that any risk management activities are traceable. Records also provide a basis for improving methods and tools in the risk management process, as well as improving the overall process. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 37 APPENDIX 1A – WORK HEALTH & SAFETY COMMON TERMS AND DEFINITIONS Person Conducting a Business or Undertaking (PCBU) A ‘person conducting a business or undertaking’ (PCBU) replaces the term ‘employer’. A PCBU includes all employers, sole traders, principal contractors, unincorporated associations, partnerships and franchisees. Volunteer organisations that also employ people will be PCBUs. A PCBU’s primary duty of care is to ensure the health and safety of everyone in the workplace, so far as is reasonably practicable. Officers An ‘Officer’ is a person who makes, or participates in making, decisions that affect the whole or a substantial part of a corporation. This includes Health and Safety Representatives (HSR). Workers ‘Worker’ replaces the term ‘employee’. It is defined broadly to mean a person who carries out work in any capacity for a PCBU. A ‘worker’ covers employees, contractors, sub-contractors (and their employees), labour hire employees, outworkers, apprentices, trainees, work experience students and volunteers. Reasonably Practicable Reasonably Practicable is defined as action that is, or was at a particular time, reasonably able to be done to help ensure health and safety based on the following factors: a) Chances of the hazard or risk occurring (likelihood). b) The degree of harm (consequence). c) The knowledge of persons involved in the situation relating to the hazard or risk and methods of eliminating or controlling it. d) The availability and suitability of ways to eliminate or control the hazard or risk. e) The costs involved in taking action to eliminate or control the hazard or risk including consideration of whether the cost involved is inconsistent to the level of risk. Due Diligence The Work Health and Safety Act 2011 (the WHS Act 2011) imposes a specific duty on officers of corporations to exercise due diligence to ensure that the corporation meets its work health and safety obligations. In short, they have a responsibility to ensure that the PCBU is doing everything it should to ensure health and safety. The duty requires officers to be proactive in ensuring that the corporation complies with its duty. Due diligence may be demonstrated through the following courses of action: 1. Acquiring knowledge of health and safety issues. 2. Understanding operations and associated hazards and risks. 3. Ensuring that appropriate resources and processes are used to eliminate or minimise risks to health and safety. 4. Implementing processes for receiving and responding to information about incidents, hazards and risks. 5. Establishing and maintaining compliance processes. 6. Verifying the provision and use of the resources mentioned in 1-5. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 38 APPENDIX 1B – SAFE WORK METHOD STATEMENT SWMS Name: SWMS Created By: SWMS Summary: Date of Creation: Last Reviewed Date: Company/Contractor Details: Project Details: Name: Client: ABN: Contact Name: Address: Site Address: Contact Number: Contact Number: Email: Start Date: How to complete this SWMS: 1. CONSULT: Consult with all persons who will be involved in the completion of the work. 2. LIST: List each of the steps in the task work being done. 3. IDENTIFY: Describe the health and safety hazards and risks arising from each step in the work. 4. RISK ASSESSMENT: Review the level of risk associated with each hazard listed. 5. CONTROL: Describe how the risks will be controlled, and describe what hazard control measures will be put in place. 6. RESPONSIBILITY: Allocate a person to be responsible for the hazard control measure. 7. REVIEW: Review the effectiveness of the control measures and apply further hazard control measures as required. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 39 Training/Qualifications Required To Carry Out Work: PPE Required To Carry Out Work: Are All Workers Adequately Trained And Qualified? Yes / No Legislation, Australian Standards & Codes Of Practice Relevant To Work (Where Applicable): Equipment Required To Carry Out Work: Environmental Statement: Safety Checks Required Prior To Commencement Of Work: Coordination With Other Trades: Permits Required For Commencement Of Work: Have These Permits Been Acquired? Yes / No RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 40 Risk Analysis Matrix Use this table to determine the level of risk associated with an identified hazard. CONSEQUENCE LIKELIHOOD Almost Certain Likely Possible Unlikely Rare RISK LEVEL VERY HIGH HIGH MEDIUM LOW Insignificant Minor First Aid Required Moderate Medical Attention and Time Off Work Major Long Term Illness or Serious Injury Severe Kill or Cause Permanent Disability or Illness M M L L L H M M L L H H H M M VH H H M M VH VH VH H M ACTION Act immediately: The proposed task or process activity must not proceed. Steps must be taken to lower the risk level to as low as reasonably practicable using the hierarchy of risk controls. Act today: The proposed activity can only proceed, provided that: 1. The risk level has been reduced to as low as reasonably practicable using the hierarchy of risk controls. 2. The risk controls must include those identified in legislation, Australian Standards, Codes of Practice etc. 3. The risk assessment has been reviewed and approved by the Supervisor. 4. A Safe Working Procedure or Safe Work Method has been prepared. 5. The supervisor must review and document the effectiveness of the implemented risk controls. Act this week: The proposed task or process can proceed, provided that: 1. The risk level has been reduced to as low as reasonably practicable using the hierarchy of risk controls. 2. The risk assessment has been reviewed and approved by the Supervisor. 3. A Safe Working Procedure or Safe Work Method has been prepared. Act this month: Managed by local documented routine procedures, which must include application of the hierarchy of controls. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 41 Safe Work Method Statement Work Step Associated/Identified Hazards Work your way through each step in the work process, giving a brief description of what is required at each stage. What hazards can be identified for this step? Risk Level (L, M, H, VH) What is the risk level? Hazard Controls Revised Risk Level (L, M, H, VH) Person Responsible What hazards controls will be put into place to deal with the identified hazards for this step? Has the risk been reduced? Who is responsible for carrying out the work and maintaining the hazard controls? RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 42 Work Step Associated/Identified Hazards Risk Level (L, M, H, VH) Hazard Controls RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 43 Revised Risk Level (L, M, H, VH) Person Responsible Personnel/Worker Signoff All personnel/workers required to carry out this task need to be listed below. By signing this SWMS, each person declares that they have carefully read the SWMS and that they understand their responsibilities and requirements to complete the work. Name (please print) Position / Qualification Signature Date Senior Management Signoff Does this SWMS meet the necessary safety requirements? Does this SWMS require review? Yes / No Yes / No Review Date: Additional Comments: Name: Position: Signature: RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module One – Plan And Prepare Page 44 Date: RIICRC203A INSTALL SUB-SOIL DRAINAGE LEARNER GUIDE Module Three – Prepare, Install And Connect Sub-Soil Drainage Systems THE CUNNING FAMILY TRUST AND THE PEACHEY FAMILY TRUST TRADING AS SAFE WORK RESOURCES PTY LTD ABN 90 785 129 255 (“SAFE WORK RESOURCES”) The information, software, products, and services included in or available through the Safe Work Resources website, applications, documents or any other products may include inaccuracies, operational or typographical errors. Changes are periodically added to the information herein. Safe Work Resources and/or its associated companies/businesses may make improvements and/or changes in the Safe Work Resources website, applications, documents or any other products at any time. Advice received via the Safe Work Resources website, applications, documents or any other products is of a general nature and should not be relied upon for personal, medical, legal or financial decisions and you should consult an appropriate professional for specific advice tailored to your situation. Safe Work Resources and/or its associated companies/businesses make no representations about the suitability, reliability, availability, timeliness, and accuracy of the information, software, products, services and related graphics contained on the Safe Work Resources website, applications, documents or any other products for any purpose. To the maximum extent permitted by applicable law, all such information, software, products, services and related graphics are provided "as is" without guarantee, warranty or condition of any kind. Safe Work Resources and/or its associated companies/businesses hereby, to the maximum of extent permitted by applicable law, disclaim all guarantees, warranties and conditions with regard to this information, software, products, services and related graphics, including all implied warranties or conditions of merchantability, fitness for a particular purpose, title and non-infringement and to the extend guarantees, warranties and conditions are implied and cannot be excluded, Safe Work Resources limits its liability at Safe Work Resources option to the: replacement of the goods or the supply of equivalent goods; repair of the goods or payment of the cost of having the goods repaired; payment of the cost of replacing the goods or of acquiring equivalent goods; or resupplying the services or the costs of resupplying the services. To the maximum extent permitted by applicable law, in no event shall Safe Work Resources and/or its associated companies/businesses be liable for any direct, indirect, punitive, incidental, special, consequential losses or damages or any damages whatsoever including, without limitation, damages for injury or death, loss of use, data, profits, revenue, production, opportunity, goodwill or any similar loss whether or not in your reasonable contemplation, arising out of or in any way connected with the use or performance of the Safe Work Resources website, applications, documents or any other products with the delay or inability to use the Safe Work Resources website, applications, documents or any other products or related services, the provision of or failure to provide services, or for any information, software, products, services and related graphics obtained through the Safe Work Resources website, applications, documents or any other products or otherwise arising out of the use of the Safe Work Resources website, applications, documents or any other products whether based on contract, tort, negligence, strict liability or otherwise, even if Safe Work Resources or any of its associated companies/businesses has been advised of the possibility of damages. Because some states/jurisdictions do not allow the exclusion or limitation of liability for consequential or incidental damages, the above limitation may not apply to you. If you are dissatisfied with any portion of the Safe Work Resources website, applications, documents or any other products or related services or with any of these terms of use, your sole and exclusive remedy is to discontinue using the Safe Work Resources website, applications, documents or any other products or related services. Your use of the Safe Work Resources information, software, products & services is governed by the laws of the state of Victoria and you hereby agree to the exclusive jurisdiction of the courts of or in Victoria and courts of appeal therefrom. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module Three– Prepare, Install And Connect Sub-Soil Drainage Systems Page 2 TABLE OF CONTENTS Review Log ..................................................................................................................................... 4! Module Basis .................................................................................................................................. 4! 3.1 Select And Check Tools And Equipment .............................................................................. 5! 3.1.1 Common Tools And Equipment ............................................................................................................ 5! 3.1.2 Selecting And Using Tools And Equipment ........................................................................................... 6! 3.1.3 Reporting Faults And Defects ............................................................................................................... 7! 3.2 Set Out And Excavate Trenches ............................................................................................. 8! 3.2.1 Setting Out The Location ....................................................................................................................... 9! 3.2.2 Marking Up .......................................................................................................................................... 10! 3.2.3 Communicating With Plant Operators ................................................................................................. 11! 3.2.4 Check Trenches .................................................................................................................................. 13! 3.3 Lay Bedding Material ............................................................................................................. 15! 3.3.1 Determining The Bedding Material ...................................................................................................... 16! 3.3.2 Lay Bedding Materials ......................................................................................................................... 17! 3.3.3 Place Geo-Textile Fabrics ................................................................................................................... 18! 3.4 Prepare Drain Sections ......................................................................................................... 19! 3.5 Lay Sub-Soil Drain ................................................................................................................. 20! 3.5.1 Fitting Inspection Openings And Flush Out Points .............................................................................. 21! 3.6 Connecting Sub-Soil Systems .............................................................................................. 23! 3.6.1 Concrete And Concreting .................................................................................................................... 26! 3.7 Install Packing ........................................................................................................................ 27! 3.8 Backfilling ............................................................................................................................... 28! 3.9 Clear Work Area And Store Materials And Equipment ....................................................... 30! 3.9.1 Clearing The Work Area ...................................................................................................................... 31! 3.9.1.1 Disposal Or Recycling Of Materials ............................................................................................. 32! 3.9.2 Cleaning And Storing Plant, Tools And Equipment ............................................................................. 33! RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module Three– Prepare, Install And Connect Sub-Soil Drainage Systems Page 3 REVIEW LOG Version Number Date Updated Details of Updates Version 4H Released August, 2013 MODULE BASIS This module is based on the unit of competency RIICRC203A Install Sub-Soil Drainage: Element 1 – Plan and prepare. Element 2 – Set out and excavate trenches. Element 3 – Install bedding materials. Element 4 – Install sub-soil drainage. Element 5 – Clean up. 1.5 Select plant, tools and equipment to carry out tasks consistent with the requirements of the job, check for serviceability and rectify or report any faults 2.1. Check trench depths and grades to ensure conformity with plans and specifications. 2.2. Set out and clearly mark trench location. 2.3. Communicate with plant operator to ensure correct excavation of trenches, placement of shoring and battering. 3.1. Determine bedding material type and depth from plans and specifications. 3.2. Lay bedding materials to specified depths and grades. 4.1. Place geo-textile according to specifications. 4.2. Prepare drain sections and fittings. 4.3. Lay subsoil drain. 4.4. Provide inspection opening and flush out points according to plans. 4.5. Fit out and/or connect end structures/outlets/clean outs to culverts, storm water or subsoil drain systems. 4.6. Install packing and prepare system for backfilling. 4.7. Monitor backfill procedure to ensure work completed to specification. 5.1. Clear work area and recycle or dispose of materials in accordance with project environmental management plan. 5.2. Clean, check, maintain and store plant, tools and equipment. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module Three– Prepare, Install And Connect Sub-Soil Drainage Systems Page 4 3.1 SELECT AND CHECK TOOLS AND EQUIPMENT Before you can install any sub-soil drainage you need to ensure you have the correct tools and other equipment. Each item needs to be checked to ensure it is appropriate for the task and is in good condition. 3.1.1 COMMON TOOLS AND EQUIPMENT Tools and equipment that you might use during your activities may include: Tape measures. Cutting knives. Levelling equipment. Shovels. Hand saws. Appropriate PPE. Crow bars. Hammers. Trowels. Formwork. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module Three– Prepare, Install And Connect Sub-Soil Drainage Systems Page 5 3.1.2 SELECTING AND USING TOOLS AND EQUIPMENT When selecting tools and equipment you will need to consider the types and styles available as well as types of materials you will be working with. It is essential to choose the correct tool or piece of equipment for the task you are going to undertake. Using the wrong tools will make the job slower, harder and less safe. To ensure you have selected the correct item, you will need to check the task requirements, specifications and goals. You should also speak with your team leader or supervisor if you are unsure about what tools or pieces of equipment to choose. Always make sure you are aware of the equipment types, characteristics, technical capabilities and limitations for each tools or piece of equipment you are using. This will allow you to select the most appropriate option for the task you are undertaking. The details of characteristics, capabilities and limitations will be included in the operator’s manual for each item. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module Three– Prepare, Install And Connect Sub-Soil Drainage Systems Page 6 3.1.3 REPORTING FAULTS AND DEFECTS If you find anything wrong with any of the equipment, hand tools, machinery or vehicles you are going to use, you must report the fault or defect to your supervisor. This means the fault can be recorded and the equipment tagged or locked out until repaired, or the repairs can be organised. Equipment that is faulty should be moved to an isolation area. It should also be tagged with an appropriate ‘out of service’ symbol that meets the needs of the workplace. This will ensure that faulty items cannot be used and therefore won’t cause an accident or injury to other personnel/workers. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module Three– Prepare, Install And Connect Sub-Soil Drainage Systems Page 7 3.2 SET OUT AND EXCAVATE TRENCHES After confirming the requirements from the project drawings you are then able to set out and mark-up the location of the excavation/trench. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module Three– Prepare, Install And Connect Sub-Soil Drainage Systems Page 8 3.2.1 SETTING OUT THE LOCATION While project plans and survey information will usually be accurate, in setting out the location of the trench you need to be aware of site-specific issues such as: Changed conditions affecting the set up. Adequate area between operating plant and the excavation. Adequate room for slopes to be constructed beside the trench. Dumping areas for excavated material are properly sited (take note of the slope of piles depending on the type of material being excavated). Traffic is directed well away from where workers will be in the trench. Location of supplies for shoring or other protective measures. Approach ramps (for plant) and proper trench entry areas are planned and marked for set up. Ensure you set out your work correctly and where needed, report to your supervisor or the engineer on any issues you find. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module Three– Prepare, Install And Connect Sub-Soil Drainage Systems Page 9 3.2.2 MARKING UP Mark-up should be done according to the work plans. Markings should be clear and able to remain in place for the duration of the work. Barriers, fencing and signage should be in place to prevent the excavation area being used for other purposes. Marking of trench locations can be done through: Areas limited to traffic or plant because of safety requirements must be specifically marked to prevent increased risk to workers. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module Three– Prepare, Install And Connect Sub-Soil Drainage Systems Page 10 3.2.3 COMMUNICATING WITH PLANT OPERATORS It is important that you communicate with the plant operator who is actually excavating the trench. You need to make sure they have a complete understanding of their task and are aware of the excavation requirements, as follows: Excavation requirements include: Depth of the trench– this is normally 600mm plus the depth of the required bedding materials but this can vary depending upon local requirements. Width of the trench–The trench should be 1.5 times the external pipe diameter. This can vary depending upon your local council and the materials the pipe is made from. The type of subsoil pipe may also be a determining factor. Trench allowance for bedding and support materials. Some councils do not require bedding materials in earth bottomed trenches but always check. Slope or grade of the trench– This is essential for achieving correct gravity feed of water. Location of any other services either underground or overhead. Position of the trench– This can be determined by GPS and survey readings. Some trenching equipment is controlled by GPS readings but you should never rely on these. Always double check the end result. Make sure the plant operator is aware of layout information such as where material is to go when excavated and where the traffic lanes are. You should also inform them about schedules, the requirements for breaks and any site-specific safety issues. After the trenching is completed you will need to ensure the specified shoring and battering has been completed. This process of shoring and battering is used to ensure the trench does not collapse. The requirements for shoring and battering will vary depending upon the nature of the sub-soil drainage system and the environmental conditions. For example trenching in sandy soils requires different shoring and battering methods than shoring in clay based soils. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module Three– Prepare, Install And Connect Sub-Soil Drainage Systems Page 11 Always double check your specification and work plans for shoring and battering. These plans will have been developed with the local environmental conditions and available equipment in mind. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module Three– Prepare, Install And Connect Sub-Soil Drainage Systems Page 12 3.2.4 CHECK TRENCHES Regular inspection of the work must be performed to ensure everything is proceeding in line with project and job requirements. You need to regularly check the trench depths and slope as well as the grade or fall. This is because soil factors such as the following can change during the work: Changes in soil type below the surface can affect work conditions. Extra shoring may be needed for wet ground. Looser than expected soil may require a changed batter slope. Cracks in the surface or walls of the trench may develop, indicating weakness or slippage planes. Seepage may indicate liquid reservoirs that will impact trench stability. The condition of the trench walls is of utmost importance in reducing or controlling risk to workers entering the trench. Trenches must not be entered by workers until after an inspection is done and the section is approved. Inspections need to be done regularly and especially after rain. Any signs of weakness in the soil structure must be reported and examined, to determine any possible impact on the safety of the work. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module Three– Prepare, Install And Connect Sub-Soil Drainage Systems Page 13 Any faults or slippage lines must be checked by qualified personnel/workers as soon as they are found. Slippage or trench collapse can occur very quickly and without warning. Workers must not be put in danger. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module Three– Prepare, Install And Connect Sub-Soil Drainage Systems Page 14 3.3 LAY BEDDING MATERIAL Once the trench is prepared, you need to determine the type and specification of the bedding materials to be laid. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module Three– Prepare, Install And Connect Sub-Soil Drainage Systems Page 15 3.3.1 DETERMINING THE BEDDING MATERIAL Bedding materials could include sand or aggregate and will be identified in the specifications and plans for the sub-soil drainage you are installing. It is essential you correctly identify the required bedding material to ensure you are laying the right materials. Incorrect materials could compromise the long term integrity of the drainage system by wearing holes in the pipes. Once you have identified the type of bedding materials from the specifications, you will need to identify the amount or depth of the materials. This is the depth of materials as measured from the base of the trench. The larger the pipes or components for the sub-soil drainage system the thicker the layer of bedding materials will be. Once you have identified the depth of the bedding materials you will be able to mark this depth on the trench and start laying the bedding materials in the trench. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module Three– Prepare, Install And Connect Sub-Soil Drainage Systems Page 16 3.3.2 LAY BEDDING MATERIALS Once you have identified the bedding materials, you will place them in the trench. Always ensure you maintain the correct grade and depth of materials. Bedding materials that do not maintain the correct grade will cause the pipes in the sub-soil drainage system to hold water rather than move water away from the site. The depth of materials may change for different sections of the trench, depending upon the components for the system. Once you have finished laying the bedding materials, always check to ensure the materials meet the specifications and requirements. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module Three– Prepare, Install And Connect Sub-Soil Drainage Systems Page 17 3.3.3 PLACE GEO-TEXTILE FABRICS Geo-textile fabrics are placed in the drains to help keep debris and foreign materials out of the pipes. How it is placed will be determined by: Type and size of the pipes being installed. Manufacturer’s specifications and directions. Site conditions. There are two main methods of laying geo-textile fabrics. The first method is to loosely wrap the fabric around the pipe or slip a fabric sock over the pipe. The pipe is then laid as normal. For the second method, the trench is dug and lined with geotextile fabric, with a large overhang. The bedding materials are placed in the trench with care being taken to keep a good overhang of fabric. The pipes are then placed in the trench with packing materials used to keep the pipe in the appropriate location. Before the trench is backfilled the overhang pieces of materials are folded over the packing materials. The trench is then backfilled and compacted according to plans and specifications. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module Three– Prepare, Install And Connect Sub-Soil Drainage Systems Page 18 3.4 PREPARE DRAIN SECTIONS Before the drain sections and fittings can be laid down, they need to be prepared. This preparation process could include: Pipe preparation is determined by the type of system being installed. Always refer to the specifications and directions for the task to ensure you are undertaking the correct actions at the appropriate location and time. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module Three– Prepare, Install And Connect Sub-Soil Drainage Systems Page 19 3.5 LAY SUB-SOIL DRAIN Once all preparations have been completed, it is time to lay the drain in the prepared bed. This is done by lowering and placing the pipes in the trench. Lowering and placing the pipes into the correct position requires you to use the appropriate slings or other lifting equipment and the most appropriate lifting plant. You may also be required to lay the pipes in a particular order or manner depending upon the specification and the manufacturer’s requirements for the pipes. When using lifting slings and other equipment you need to check the equipment is rated for the load you are lifting and lowering. Equipment should also be checked by a qualified person to ensure the safety and security of the equipment. Each piece of the equipment should be inspected before use and at the end of the day to check for damage. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module Three– Prepare, Install And Connect Sub-Soil Drainage Systems Page 20 3.5.1 FITTING INSPECTION OPENINGS AND FLUSH OUT POINTS Inspection openings are placed regularly along the sub-soil drainage system. This is to allow for easy inspection of the pipes when empty or to ensure the water is moving away correctly when they are full. Inspection points or openings can also be used to clear debris, dirt and silt from the pipes during dry times to avoid the pipes backing up during run off events. These points are called flush out points. How these inspection points are fitted will vary depending upon the size of the system, the materials the system is constructed of and the design specifications and drawings. When fitting inspection points, pits or other structures, you must ensure: Correct size of inspection point. This will be determined by local council guidelines and the design specifications. Correct jointing of the inspection point into the pipe system. Specifications are met. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module Three– Prepare, Install And Connect Sub-Soil Drainage Systems Page 21 Inspection points and fittings must be located at exactly the correct place. If for any reason, you cannot place the inspection point exactly where it should go, you will need to speak with your supervisor. Your supervisor will then need to consult with the system designer or engineer before approval can be given to relocate the inspection point or fitting. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module Three– Prepare, Install And Connect Sub-Soil Drainage Systems Page 22 3.6 CONNECTING SUB-SOIL SYSTEMS Once the sub-soil drainage system is in place, you need to ensure you connect all fittings correctly. These fittings could include: End structures. Outlets. Clean outs. Culverts. Other components as determined by the specifications. Before installing fittings, you need to identify what joining system or products need to be used. These will be listed in the manufacturer’s specifications and the task specifications. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module Three– Prepare, Install And Connect Sub-Soil Drainage Systems Page 23 How pipes, joints and structures are joined will depend upon the task and manufacturer’s specifications. Pipe joints will vary depending upon the materials used to make the pipes. Some of the different methods of joining pipes could include: Different methods of joining pipes may include: Rubber Rings These come in two types: a rolling ring (dry) and a skid ring (lubricated). Used with a range of pipe materials, including PVC and concrete. Sleeve Connections An external connection method, usually involving a rubber sleeve and a steel jacket to secure the connection. Solvents And Glues Are applied to the join. Used with PVC and UPVC pipes. Solvent Welded Some products are welded together using a combination of heat and solvent. These joints are more secure and stable than a simple solvent or glue joint. Snap Together Fittings These are pieces that are attached to the pipes and then ‘snapped together’ for a secure join. These make the process of joining structures and pieces simple and quick. Mechanically Jointed How this jointing is done will depend upon the piping materials being used. One common form of jointing used with stormwater and sub-soil drainage drains is a sand band. This is where a large elastic band like piece of material is placed over one end of the pipe. The next piece of pipe is then pushed up against the first and the band is folded down to cover both sections of the pipe. This band is then covered in sealant, slurry or concrete as detailed in the specification. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module Three– Prepare, Install And Connect Sub-Soil Drainage Systems Page 24 When joining pipes you must ensure the joint is secure so that no fluids can leak of out of the pipes. For some jobs, GPS or marker systems can be used to identify where joints should be located. This enables the joints to be easily located in the future. Always check the specifications and plans to determine these requirements. It is vital to the efficient use of the sub-soil drainage system that all components are fitted according to the specifications. The specifications will be determined by the type of subsoil drainage system being installed and the environmental conditions on the site. A sub-soil drainage system may include: Strip filter drains and perforated pipes with or without geo-textile fabric. Granular materials enclosed in geo-textile fabric. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module Three– Prepare, Install And Connect Sub-Soil Drainage Systems Page 25 3.6.1 CONCRETE AND CONCRETING Sometimes it is necessary to use concrete to join structures into place, including: You must use the correct concreting mix to ensure you achieve the desired results. Concreting may be used for: Repairs to existing structures. Grouting or joining of sections and segments. Rendering of areas. Concrete and concreting should only be undertaken when required by the specifications. By concreting areas not specified you could obstruct the flow of water into the sub-soil drainage system. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module Three– Prepare, Install And Connect Sub-Soil Drainage Systems Page 26 3.7 INSTALL PACKING Once the system is in place, it is necessary for you to install the packing materials, which are used to keep the pipes in place. Packing materials will need to be placed carefully to ensure they do not move the pipes or other components of the subsoil drainage system. The amount of packing materials you will require will be detailed by your specifications and task requirements. Commonly the materials used for packing will be the same materials used for bedding the pipes. Once the packing materials are in place you will need to prepare the system for backfilling. Preparation for backfilling will be determined by the needs of the tasks and activities. All activities will be outlined in your worksite procedures and processes. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module Three– Prepare, Install And Connect Sub-Soil Drainage Systems Page 27 3.8 BACKFILLING Backfilling is the process of filling in the trench that contains the pipes. When backfilling you must ensure the procedure outlined in the specification is used. This procedure will detail what: Materials that should be used. Compaction levels that must be met. Any clean up requirements, often things such as revegetation. Normally backfilling is done with the materials that were excavated from the trench. This is done to keep all materials within the site and to return the site to as close to normal condition as possible. Occasionally materials excavated from the trench are not suitable to be used for backfilling of trenches. This could be for many reasons such as the material being: RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module Three– Prepare, Install And Connect Sub-Soil Drainage Systems Page 28 If the materials are unsuitable you will need to source more suitable materials. The list of materials that could be considered suitable will be contained within the specification and the local council requirements. These requirements must be met. If you are unsure of the quality of the materials, speak with a supervisor or local council officer for additional guidance. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module Three– Prepare, Install And Connect Sub-Soil Drainage Systems Page 29 3.9 CLEAR WORK AREA AND STORE MATERIALS AND EQUIPMENT Once your tasks are completed, you need to clear the work area and make sure that all tools and equipment are cleaned, checked, maintained and stored. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module Three– Prepare, Install And Connect Sub-Soil Drainage Systems Page 30 3.9.1 CLEARING THE WORK AREA Good housekeeping is necessary to control hazards and risks on the worksite, but it also promotes good work practices, pride and ownership of the job. It is your responsibility to clean up after your work activities. Worksite requirements for clearing the work area and disposing or recycling materials will be outlined in the project environmental management plan, quality requirements and/or site-specific procedures. Clean-up procedures may include: Cleaning up and using the bins provided to dispose of rubbish from workers, e.g. food and scraps. Removing any potential hazards. Duty of care towards others means not leaving a possible source of accident or danger for other people. Preparing any equipment or materials for transport away from the site. Making sure you use appropriate Personal Protective Equipment (PPE) when dealing with waste or possible hazardous materials as you clean. Disposing of materials or recycling them (where possible) in line with the site Environmental Management Plans or Waste Disposal Plans. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module Three– Prepare, Install And Connect Sub-Soil Drainage Systems Page 31 3.9.1.1 DISPOSAL OR RECYCLING OF MATERIALS Common waste materials that may be found in your work area could include: Geo-textile fabric. Marking materials. Strip filter drains. Perforated pipes. Pipe jointing materials. Backfill and bedding materials. Marker post. Stones. Concrete. Other materials used onsite. Each of these will need to be managed in accordance with the project environmental management plans and the site waste management plans. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module Three– Prepare, Install And Connect Sub-Soil Drainage Systems Page 32 3.9.2 CLEANING AND STORING PLANT, TOOLS AND EQUIPMENT After using plant, tools and equipment, it is important to ensure they are: Cleaned – to remove all dirt, mud moisture or other contaminants, in accordance with manufacturer’s specifications. Checked for any damage – if anything is wrong, report it; then, if possible, carry out any repairs. Maintained in line with manufacturer’s recommendations or your worksite procedures/standard work practices. Stored correctly in the appropriate location. Most equipment, plant and tools will have designated storage instructions to ensure the items are kept free from damage and can be easily found the next time they are needed. The site procedures and manufacturer’s guidelines for cleaning, maintenance and storage should be followed regardless of the type of plant, equipment and tools being used. Keeping them in the best possible condition prolongs their working life and ensures they are safe to use. RIICRC203A – INSTALL SUB-SOIL DRAINAGE Module Three– Prepare, Install And Connect Sub-Soil Drainage Systems Page 33