Method Statement: Drainage

advertisement
N60 Balla to Claremorris
Road Realignment at
Heathlawn Scheme
Method Statement:
Drainage
Issue
Date
0
12/5/14
Ident No.
MS-N60-05 Rev 0
Version Issue.
Issue
0
Date
12/5/14
Version Details
First Issue
Revised by
Acceptance / Approvals.
Prepared by:
Name
M Blackweir
Signature
Date
12/5/14
Reviewed by:
A McGinley
12/5/14
Accepted by:
D Meade
12/5/14
1
Date: 12/05/2014
N60 Balla to Claremorris
Road Realignment at
Heathlawn Scheme
Method Statement:
Drainage
Issue
Date
0
12/5/14
Ident No.
MS-N60-05 Rev 0
Title:
Drainage
Location:
N60 Balla to Claremorris Road Realignment at Heathlawn Scheme
Task at Hand
This method statement outlines the procedure and methodology for the installation of
drainage.
Timing of Task
To be advised subject to Contractor appointment.
Supervision of Task
Contracts Manager:
Site Agent:
Foreman:
Site Engineer:
Suitably Qualified Ecologist:
Name
TBC
TBC
TBC
TBC
TBC
Contact Number
Employees Involved




Plant Operators
Site Supervisor
Pipe Layers
General operatives
Equipment to be used
20-30 Ton Excavator
A20-30 Volvo Dump Trucks
5-9 ton dumpers
Specific Training



All site personnel shall have FAS „Safe Pass‟ certification.
All Excavator & Dumper drivers shall have CSCS certification.
CSCS certified representative in underground service location
2
Date: 12/05/2014
N60 Balla to Claremorris
Road Realignment at
Heathlawn Scheme
Method Statement:
Drainage
Issue
Date
0
12/5/14
Ident No.
MS-N60-05 Rev 0
Personal Protective Equipment
Safety Gloves
Hearing
Protection
Eye
Protection
Respiratory
Protection
Coveralls
Other
Hi Vis- Vest
Hard Hats
Boots
Yes
Where required
Yes
Where required
No
Yes
Methodology
The design location of the proposed drainage is shown on detailed design drawings. The
drains shall be installed to NRA details RCD/500/01 filter drains and RCD /500/2 for carrier
drains.
General
 All personnel entering the site shall have received a site safety induction and have
attended a job toolbox talk.
 Before any excavations shall commence a permit to excavate shall be issued by the
site engineer and all persons involved in the task shall be fully briefed
Excavation

The location of the proposed drainage will be set out on the ground by marking with
spray paint and pegs at pit locations. Where works are along edge of existing
roadway traffic light or stop/go system shall be set up to carry out works. A trench
will then be excavated between pits using an excavator with material loaded to dump
truck. The trench width will vary depending on the size of the pipe.
Installation

Where drains are being installed a layer of geotextile material shall be placed along
the outline of the trench and a layer of filter stone shall then be placed in base of
trench to receive pipe work. The pipe work shall then be laid to the correct line and
level by using a grade laser.
3
Date: 12/05/2014
N60 Balla to Claremorris
Road Realignment at
Heathlawn Scheme
Method Statement:
Drainage
Issue
Date
0
12/5/14
Ident No.
MS-N60-05 Rev 0
Backfilling of Ducting
• The remaining stone shall then be placed by six ton dumper up to underside of
capping where geotextile shall be turned out under capping layer. The remainder of
the drain shall be topped up once surfacing works are carried out up to wearing
course level. Installation of layer of Geogrid shall also be carried out at this stage.
•
All chambers on the drain lines shall be constructed with pre-cast concrete catch pits
and shall be placed as pipeline proceeds.
Petrol Interceptors
•
•
•
•
Excavate a hole with sufficient length and width to accommodate the tank and a min
of 300mm surround to a depth for the burial of the unit plus the base slab and
haunch.
Construct a suitable base.
Pour no more than 300mm of depth of water into the unit, avoiding shock loads. For
units with more than one chamber, add water to each chamber simultaneously. Do
not overfill as units are not designed to hold water whilst unsupported.
Backfill to approximately 300mm depth under and to the sides of the tank ensuring
good compaction to remove voids. Continue adding backfill, simultaneously keeping
the internal water level no more than 200mm above the backfill level at all times, until
the backfill is just below the underside of the outlet drain, giving sufficient room to
connect the inlet and outlet pipe work.
Grass Surface Water Channel
•
•
•
•
•
The verge shall be filled to top of capping layer with an acceptable fill material.
After the Binder course is laid the shape of the verge is formed using an acceptable
class 2 fill.
In the areas where Narrow Filter Drain has been installed filter stone shall be topped
up to top of capping level.
This fill material shall be shaped, compacted and top-soiled to depth of 50mm as
detailed in the Design.
Specific grass mix to be utilised, specification to be developed with grass seed
specialist.
Swales & Soakaways
•
•
•
The area will be cleared and leveled out to allow for the construction of the swale or
soakaway.
Excavations will be executed in accordance with the design.
Once the area of the swale has been shaped & checked it will be backfilled with
suitable fill and topsoiled as required.
4
Date: 12/05/2014
N60 Balla to Claremorris
Road Realignment at
Heathlawn Scheme
Method Statement:
Drainage
Issue
Date
0
12/5/14
Ident No.
MS-N60-05 Rev 0

Soakaway excavation shall be backfilled with clean stone and the terram lapped over
top of soakway, in accordance with the design and completed to original ground with
excavated material/topsoil.
5
Date: 12/05/2014
N60 Balla to Claremorris
Road Realignment at
Heathlawn Scheme
Method Statement:
Drainage
Issue
Date
0
12/5/14
Ident No.
MS-N60-05 Rev 0
Potential Ecological / Environmental Impacts, including impacts on Balla Turlough
cSAC and/ or other European sites
NIS / EAR: Relevant Extracts:
Potential Impacts (in the absence of below Mitigation):
 Potential Surface & groundwater contamination during construction.
 Potential decrease in groundwater supply to Turlough during construction.
 Potential Increase in run-off volumes to Turlough during construction.
 Pollution from Surface Water run-off during Construction.
Mitigation:







Construction works carried out in the vicinity of the Turloughs will be monitored by a
suitably qualified ecologist.
To reduce potential increases in flows into the drainage system and downstream
Turloughs during construction, the period of exposure of bare areas and
uncontrolled runoff from new hardstanding areas will be limited. Early
covering/seeding/planting of exposed surfaces will be undertaken.
The grassed surface water channel, interceptor ditch and filter drain with 25m
centre outfalls and petrol interceptor (as detailed in 32103901/PDD/Figure 01 &
included in Appendix A) between Ch1000 and Ch 1500 on the south western side
of the carriageway, will be constructed and operating prior to excavation of Cutting
1 (Ch 1260 to 1340). These drainage features are adjacent to Balla Turlough SAC,
to facilitate the controlled discharge of any intercepted groundwater back into the
Turlough habitats in the case of the water being intercepted during excavations.
The outfalls to the Turlough will be open during construction only, and closed during
operation.
Material stockpiles will be kept to a minimum size, covered and located at least
10m from the drainage system and 100m from Turloughs.
To prevent contaminated or silt-laden runoff from entering the Turloughs, a range of
temporary measures will be implemented, including silt fences, cut-off ditches, silt
traps, straw bales, entrapment matting and drainage to vegetated areas.
Runoff will be controlled and, if required, directed to settlement ponds or sumps.
Any temporary attenuation and treatment facilities will be designed and
implemented in accordance with CIRIA C697 (2007). All temporary treatment
systems will be regularly inspected and maintained.
The extent of construction activities will be controlled to limit vegetation removal
and the exposure and/or compaction of soils. Land surrounding the immediate
construction area will be fenced off, or otherwise demarcated, to prevent
inadvertent intrusion from construction plant.
6
Date: 12/05/2014
N60 Balla to Claremorris
Road Realignment at
Heathlawn Scheme
Method Statement:
Drainage
Issue
Date
0
12/5/14
Ident No.
MS-N60-05 Rev 0












The scheme drainage system will be inspected daily, or after storm events, to
check for blockages during construction.
Construction works will be avoided during prolonged periods of very heavy rainfall
adjacent to the Balla Turlough cSAC and Un-named Turlough.
No construction plant or construction vehicles to enter the Balla Turlough cSAC
boundary other than where this boundary has already been generally encroached
by the existing road.
Refuelling of machinery shall be carried out off-site, or when on-site not within 100m
of Turlough habitat.
All fuels, oils, greases, hydraulic fluids and chemical storage areas will be stored in
bunded compounds/areas on impermeable bases at least 10m from the proposed
drainage system and 100m from the cSAC and Un-named Turlough.
Drip-trays shall be utilised for refueling of machinery, machine servicing, concretemixing, etc.
No machinery to enter Turlough habitats, no temporary access or haul routes are
located in Turlough habitats and no temporary storage areas, plant or other
obstacles are located within Turlough habitats.
Monitoring of turbidity (suspended solids) levels in Balla Turlough SAC and the Unnamed Turlough will be undertaken on a monthly basis for a minimum of 6 months
prior to construction and will include monitoring during the winter season when
Turlough water levels are most likely to be present. Monitoring will also be
undertaken on a weekly basis during construction for turbidity (suspended solids). In
the event of suspended solids concentrations that are higher than the 95th %ile of
those monitored during the pre-construction monitoring period, a review of the
Sediment and Erosion Control measures and plan will be implemented and
additional sediment control measures put in place as required. Daily visual
inspections of Balla Turlough SAC and the Un-named Turlough will also be
undertaken during the construction phase to confirm the absence of sediment from
construction works.
The N60 Balla to Claremorris Erosion and Sediment Control Plan shall be
implemented to prevent sediment or pollutants from reaching the Balla or Un-named
Turloughs.
Untreated sewage will be collected and be disposed of off-site via a licensed
contractor.
The following Construction Industry Research and Information Association (CIRIA)
best practice guidance will be adhered to:
o CIRIA C648 – Control of Water Pollution from Linear Construction Projects.
o CIRIA C649 – Control of Water Pollution from Linear Construction Projects:
Site Guide.
o CIRIA C697 – The SUDS Manual.
o CIRIA C698 – Site handbook for the construction of SUDS.
All mitigation contained within the N60 Environmental Assessment Report and
NATURA Impact Statement shall be implemented in full.
7
Date: 12/05/2014
N60 Balla to Claremorris
Road Realignment at
Heathlawn Scheme
Method Statement:
Drainage
Issue
Date
0
12/5/14
Ident No.
MS-N60-05 Rev 0
Relaying of Information; To each operative:
“I wish to confirm that the information in this method statement has been communicated
to me and I have understood it. I shall bring to the attention of the supervisor any issues,
which may affect Safety whilst carrying out the task”.
Information provided by Supervisor;
NAME (BLOCK)
Signature
DATE
In the event of the need for a deviation from the Method Statement, no further work will be
done until agreement has been reached and recorded in writing between the client & the
contractor on the method of work to be followed in the new circumstances.
8
Date: 12/05/2014
N60 Balla to Claremorris
Road Realignment at
Heathlawn Scheme
Method Statement:
Drainage
Issue
Date
0
12/5/14
Ident No.
MS-N60-05 Rev 0
Appendix A
9
Date: 12/05/2014
P
S
[
?
í
í
Š
í
ä
ï
æ
è
à
Ý
ó
S
[
k
[
N
‘

Œ

Ž

Ž

Œ
‹
m
i
_
l
j
i
›
›
ž


…
˜


‘
œ
š
š
š
™
‚
€
‡
˜
„
—
2
S
R
Q
P
S
\
P
k
\
P
R
^
O
O
[
.
.
T
T
N
r
o
o
]
]
4
1
0
/
/
/
3
-
-
1
0
/
/
/
-
-
?
í
í
Š
í
ä
ï
:
ð
à
è
ã
$
Ù
Ù
Ž
–
•
‹

Ž

Œ
Š
‹
Š
‰
ˆ
”
‘
“
’
‘
u
\
w
x
z
|
|
{
z
w
x
y
u
x
w
v
S
R[
[
[
S
q[
P
^
Ž
Ž
Ž
‹

Ž

Œ
Š
‹
Š
‰
ˆ
‡
~
†
~
…
„

ƒ
‚

€




‚

€

~
}

V
~
}
Y
ha
ha
Úa
bÍ
Ø
Ø
Ø
T
T
_
]
N
p
]o
n
Ñ
Z
Y
Ó
s
t
R^
Q
P
O
Õ
Õ
Õ
Õ
×
Ö
Ô
Õ
Ô
Ò
Ò
X
U
p
]
N
ã
ä
ß
ç
è
ð
ã
è
ß
à

î
ä
ã
ß
è
{
z
î
Ý
]
:
ð
ß
Ý
|
ã
ä
ß
ç
è
ð
ã
è
ß
à

Z
W
Y
Î
X
V
U
î
î
í
æ
í
è
ë
ÏW
f
Í
Y
Í
8
7
!
6
$
$
+
'
ú
5
&
'
$
(
$
5
þ
ú
&
þ
#
(
Ð
X
`
è
ç
Ý
{
ã
è
Ý
ã
ã
í
œ
Î
Í
Y
X
X
¹
Ì
U
ß
è
î
ß
å
]
œ
9
ï
â
„
‚
…
†€
ƒ
—
‚
Z
dW
dY
ca
b
a
Ë
‡
‡
ˆ
™
˜
–
z
y
•

”
“
~
x
ù
œ
9
ï
â
÷
Þ
î
è
à
à
í
:
œ
ã
è
ß
í
9
è
ð
í
>
ã
å
ï
æ
è
Þ
Þ
í
ã
â
`
Ê
Ã
É
Å
Å
Ã
Ä
Ã
Â
È
#
!
)
$
#
ú
$
%
'
'
$
'
'
þ
ÿ
þ
ú
$
%
ú
!
#
&
’
ú
$
Ç
Æ
Á
è
?
Û
á
à
Ý
æ
æ
ä
ø
à
Ý
í
ã
|
ã
è
ß
î
Ý
›
À
¿
`
¾
½
¼
`
»
U
¾
½
¼
`
¼
»
º
¹
M
I
H
G
B
B
C
@
L
K
E
B
Z
hW
a
f
Y
FJ
J
D
F
D
?
A
ú
,
þ
ÿ
+
þ
$
+
þ
"
$
*
!
#
)
(
þ
!
#
'
&
#
#
!
%
$
#
þ
ÿ
"
!
þ
ÿ
ÿ
þ
ý
ü
û
ú
g
e
ß
Ý
ç
:
ð
ß
í
œ
ñ
?
è
š
‰
†
„
ƒ
‚

…
„
ƒ
‚
‚

€
ˆ
‡
}
}
~
{

~
}
}
|
y
{
z
y
x
w
m
m
m
f
e
fc
e
f
i
fa
s
f
a
s
a
dc
f
a
j
f
i
a
f
e
dc
a
v
r
p
h
c
u
o
t
b
q
o
l
nl
b
l
k
g
b
`
_
x
x
v
ñ
w
è
î
í
ð
ï
î
í
ð
Ý
ß
ã
è
ò
x
x
x
w
ñ
w
è
î
í
ð
ï
î
í
ß
à
ä
ì
Ý
ã
ä
ë
x
ê
é
æ
è
Þ
ä
ç
ä
ã
{
+
+
+
+
+
+
+
+
+
+
+
+
+
.
.
.
0
0
0
0
0
0
0
0
0
0
+
+
/
/
+
/
+
+
+
+
+
+
/
/
/
/
/
/
/
+
(
(
(
(
+
+
+
+
+
(
+
+
+
+
+
+
+
(
(
(
(
(
-
-
-
-
-
-
+
+
+
+
+
-
+
-
-
1
1
1
1
1
1
1
1
1
1
-
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
)
)
)
)
)
)
)
)
)
)
+
+
+
+
+
+
+
+
+
+
+
1
)
2
,
.
0
/
(
-
1
)
2
,
.
0
/
(
-
1
)
2
,
.
0
/
(
-
1
)
2
,
.
0
/
(
-
1
)
2
,
.
0
/
(
-
1
)
2
,
.
0
/
(
-
1
)
2
,
.
0
/
(
-
1
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
W
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
J
N
OW
)
M
V
U
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
8
4
8
C
4
8
4
8
C
8
8
C
4
4
4
<
6
D
=
D
6
3
B
>
<
7
>
A
D
?
D
D
5
D
3
>
>
>
>
>
>
6
5
@
=
6
=
6
>
5
3
>
>
>
>
>
>
>
5
@
\
W
JF
Z
M
R
[
8
4
8
8
4
8
4
4
7
6
?
<
9
3
>
>
>
>
>
;
9
@
5
5
<
9
?
3
B
7
?
<
6
A
:
8
4
8
;
<
=
<
;
9
3
8
4
:
4
:
4
:
8
>
>
?
>
5
5
3
>
>
?
>
5
5
3
>
>
>
>
5
<
@
Y
W
O
G
GF
Z
R
M
X
:
8
4
3
6
9
7
7
6
5
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
/
/
/
/
/
/
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
+
+
+
0
0
.
.
.
,
.
.
.
.
.
.
.
.
.
.
.
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
2
2
2
)
)
)
)
)
)
2
,
.
0
/
/
/
/
(
(
(
(
-
-
-
-
-
-
-
-
1
1
1
1
)
)
)
)
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
+
+
+
+
+
+
+
+
0
,
0
-
0
)
/
-
-
(
(
/
0
.
.
,
2
)
)
)
)
)
)
1
-
1
)
1
/
.
,
/
.
2
-
1
(
/
/
(
(
2
0
-
)
.
(
1
)
,
.
.
0
/
-
)
,
0
(
.
/
-
,
/
1
+
+
+
+
+
+
+
+
2
2
,
1
1
1
.
/
(
1
,
0
0
1
.
0
/
(
(
2
/
,
-
/
,
0
1
)
,
-
0
(
)
)
(
0
,
(
)
0
,
0
,
0
-
.
0
0
2
(
/
2
2
)
1
0
,
1
1
2
2
0
)
,
0
+
+
+
+
+
+
+
+
+
O
T
G
F
ON
I
Q
.
-
/
-
.
.
2
,
.
1
-
/
1
/
(
1
,
(
1
(
0
1
.
-
(
0
/
2
)
/
2
/
/
(
,
/
-
)
2
/
.
)
1
.
,
)
0
-
0
/
0
(
,
1
2
,
0
/
.
(
,
,
(
1
K
S
M
R
M
P
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
+
+
+
+
)
0
0
.
.
.
.
.
.
.
.
.
.
.
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
.
.
.
.
.
.
.
.
.
0
0
0
0
0
0
/
/
/
/
/
(
(
(
(
-
-
-
-
-
-
1
1
1
1
)
)
)
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
+
+
+
+
+
+
+
+
2
0
(
,
2
)
1
1
-
(
/
0
.
,
2
)
)
1
1
1
-
-
-
-
-
-
-
1
1
)
2
2
,
.
0
/
-
1
2
,
0
(
1
)
,
0
(
1
)
.
/
-
)
2
.
/
(
1
)
,
0
-
,
0
-
+
+
+
+
+
+
+
(
)
/
,
1
)
0
0
)
1
)
2
2
,
,
.
.
0
(
1
2
)
/
,
-
(
(
-
1
)
.
-
0
,
)
1
)
.
(
/
)
-
0
,
2
2
2
.
/
1
,
-
)
2
1
0
2
1
-
(
-
1
2
,
-
.
+
+
+
+
+
+
+
+
O
I
J
J
I
G
H
G
N
F
,
0
/
/
-
0
0
)
(
)
-
)
/
)
)
/
)
/
)
/
)
-
,
0
(
.
0
-
1
-
/
2
(
)
1
2
,
,
(
)
.
0
,
1
,
/
(
(
0
)
/
-
1
/
-
2
-
,
1
.
0
/
2
1
/
M
L
K
E
"
x
x
x
y
u
'
&
%
$
#
|
w
#
î
î
í
>
ß
å
]
v
#
î
î
í
>
ß
å
]
^
î
î
í
>
ß
å
]
x
ê
é
æ
è
Þ
ä
ç
ä
ã
{
æ
à
å
ä
ã
â
á
à
Ý
ß
Þ
Ý
Ü
Û
"
á
à
Ý
í
ã
æ
Þ
Ý
:
ß
à
ä
à
ä
Ý
ß
í
;
ã
ä
>
à
Ý
ã
è
:
ß
ä
ß
ð
è
>
>
í
?
í
;
Þ
Ý
:
ß
æ
à
í
ß
à
è
;
à
á
Ý
î
í
è
:
ß
>
ä
Þ
ß
ã
í
ç
ä
ß
Þ
è
á
à
í
:
ð
à
Ý
ß
î
å
Þ
è
ã
?
í
;
:
ð
Ý
:
Þ
Þ
è
ð
ä
ã
ç
à
á
Ý
Þ
è
æ
æ
è
î
Ý
í
ß
è
æ
!
è
:
ß
á
à
Ý
ã
å
æ
æ
è
à
>Ý
è
ã
ã
è
:
ß
ã
å
>
è
=
î
î
Ý
à
á
Ý
Þ
è
æ
è
:
ß
è
;
è
:
ð
Þ
î
í
ð
Ý
ß
ð
í
ã
ç
í
Þ
í
à
ä
:
Þ
è
=
ä
ß
?
î
ß
à
è
Ý
ð
>Ý
>
å
Þ
æ
è
à
á
Ý
Þ
è
æ
à
è
è
=
Þ
í
:
ß
à
è
;
è
<
ä
ã
ç
;
Ý
æ
è
Þ
ä
ç
ä
ã
ç
Þ
Ý
:
ß
ß
Þ
î
Ý
:
9
>
=
0
<
2
;
9
4
:
0
9
0
8
7
4
6
0
3
5
2
4
3
2
1
0
/
)
!
%
'
+
,
'
*
)
!
+
-
)
%
,
#
.
-
,
!
&
,
'
!
'
*
&
&
"
$
'
,
!
)
%
"
#
#
"
!
(
'
&
%
$
ª
«
+
"
*
¬
Ÿ
"
"
"
­
®
¡
¯
ö
;
õ
v
Ü
;
õ
ö
Ü
;
õ
¢
°
£
¤
±
Þ
à
ä
Ý
Þ
à
è
;
Ý
æ
ß
Ý
ç
è
ß
í
;
Ý
Ü
ä
ã
ç
ç
#
¥
²
£
³
¦
?
í
í
Š
í
ä
ï
æ
è
à
Ý
ó
´
§
¤
±
¥
µ
´
£
³
¨
¶
·
©
¸
©
¸
¶
´
²
ô
ô
ù
w
æ
í
ä
ø
è
æ
Ý
ï
÷
x
ê
v
ö
õ
ê
ó
"
;
w
v
Ü
;
v
Ü
;
õ
ö
Þ
à
ä
Ý
Þ
à
è
;
Ý
æ
è
ß
í
;
Ý
Ü
ä
ã
ç
ç
#
?
í
í
Š
í
ä
ï
:
ð
à
è
ã
$
"
;
ö
v
Ü
;
u
Ü
;
x
ê
Þ
à
ä
Ý
Þ
à
è
;
Ý
æ
è
ß
í
;
Ý
Ü
ä
ã
ç
ç
#
?
í
í
Š
í
ä
ï
:
ð
à
è
ã
$
N60 Balla to Claremorris
Road Realignment at
Heathlawn Scheme
Method Statement:
Drainage
Issue
Date
0
12/5/14
Ident No.
MS-N60-05 Rev 0
Risk Assessments –
(Civil Works)
10
Date: 12/05/2014
N60 Balla to Claremorris
Road Realignment at
Heathlawn Scheme
Method Statement:
Drainage
Issue
Date
0
12/5/14
Ident No.
MS-N60-05 Rev 0
APPENDIX B
Risk Assessments
Hazard/Risk Assessment Proforma
Project:
Operation/Task:
Location/Area:
N60 Balla to Claremorris Road
Realignment at Heathlawn Scheme
Installation of drains
All locations
Risk Assessment No:
N60/RA011 Rev 0
Method Statement Title:
Method Statement No:
Installation of drains
MS-N60-05 Rev 0
Review Dates:
May 2014
CATEGORY OF PERSONS AT RISK AND MEANS OF BRIEFING
Means of Briefing
RAMS
SCS
Other
Y
CATEGORY OF PERSONS
Occupations involved in Activity (Specify):
Others Persons at Work (Specify):
Public or Other Parties (Specify):
1.
Plant operators, general operatives ,
N/A
NA
Description of the task/operation
Excavation of trenches to receive new filter drains along edge of existing road and along verge of new carriage way..
11
Date: 12/05/2014
N60 Balla to Claremorris
Road Realignment at
Heathlawn Scheme
Method Statement:
Drainage
Issue
Date
0
12/5/14
Ident No.
MS-N60-05 Rev 0
KEY:
S = Severity Rating
L = Likelihood of Occurrence
1.
Negligible
1.
Improbable
2.
Minor
2.
Reasonably likely
3.
Notifiable/Major/Fatal
3.
Certain or near certain
Severity
RR = Risk Rating
Unacceptable risk, plan out or add further controls
9
3
3
6
9
4-6
Acceptable only if no other method viable and with high level controls in place
2
1
4
6
2-3
Acceptable if suitable controls
1
1
2
3
1
1
2
3
Acceptable, no further action required
Likelihood
Risk Assessment Prepared by (Name):
Signature:
Date:
Risk Assessment Reviewed by (Name):
Signature:
Date:
12
Date: 12/05/2014
N60 Balla to Claremorris
Road Realignment at
Heathlawn Scheme
Method Statement:
Drainage
Issue
Date
0
12/5/14
Ident No.
MS-N60-05 Rev 0
Item
01
Hazards/Risks
Identified
Activity

Excavations



Work on or near steep
embankments
Work in trenches or near
saturated ground / high
water table.
Excavation Collapse
Trench Collapse
Falls from Height into
excavations
Pre-Control Risk
Rating
S
L
RR
2
1
1
Residual Risk
Rating
Control Measures












Detailed Method Statements and Risk
Assessments to be carried out pertaining to
each particular activity
Permit to Dig System to be Implemented
Area to be surveyed by a person qualified in
FAS CSCS location of underground services
Suitable Plant to be utilized in excavation
Operations
All excavations to be monitored on a daily
basis and AF2 form completed
Competent Machine Operators to be utilised
FAS CSCS qualifications
Adequate Trench Support Systems to be
utilised i.e. trench boxes/sheets
Dewatering systems to be implemented
where required.
Suitable access to be provided to trenches
Perimeter fencing and signage to be put in
place and secure excavations
S
L
RR
1
1
1
Responsibility
Full site Team
Monitoring
Responsibility
Contractor
13
Date: 12/05/2014
N60 Balla to Claremorris
Road Realignment at
Heathlawn Scheme
Method Statement:
Drainage
Issue
Date
0
12/5/14
Ident No.
MS-N60-05 Rev 0
Item
02
Hazards/Risks
Identified
Activity
Heavy Plant
and
Equipment






Struck by site transport
Falls from vehicles.
Splashed by fuel during
refuelling.
Tipping or overturning of
vehicles.
Contact with moving
parts of machinery.
Struck by mater dropped
while in lift.
Pre-Control Risk
Rating
S
L
RR
3
2
6
Residual Risk
Rating
Control Measures











Detailed Method Statements and Risk
Assessments to be carried out for all
activities to address the movement use
of heavy equipment.
Worker Briefings to be carried out
Plant to be operated by Competent
Personnel
Plant to be in good order and inspected
prior to commencement of any works on
site
Auxiliary devices and visual aids on
plant as highlighted in Schedule 6 of
2006 Construction Regulations.
Carry out plant checks and record on
plant checklists
Vehicle Banksmen to be utilised where
required
Segregate traffic from public and work
force where possible
Implement work exclusion zones where
appropriate
Implement Traffic Management Plans
Ensure all personnel were appropriate
PPE and high visibility clothing
S
L
RR
3
1
3
Responsibility
Full site Team
Monitoring
Responsibility
Contractor
14
Date: 12/05/2014
Download