Chapter 9
Project Management
Operations
Operations Management
Management -- 55thth Edition
Edition
Roberta Russell & Bernard W. Taylor, III
Copyright 2006 John Wiley & Sons, Inc.
Beni Asllani
University of Tennessee at Chattanooga
Lecture Outline
Š Project Planning
Š Project Scheduling
Š Project Control
Š CPM/PERT
Š Probabilistic Activity Times
Š Project Crashing and Time-Cost
Trade-off
Copyright 2006 John Wiley & Sons, Inc.
9-2
1
What is a Project?
Š Project
„
unique, one-time operational activity or effort
Š Examples
„
„
„
„
„
„
„
constructing houses, factories, shopping malls, athletic
stadiums or arenas
developing military weapons systems, aircrafts, new ships
launching satellite systems
constructing oil pipelines
developing and implementing new computer systems
planning concert, football games, or basketball tournaments
introducing new products into market
Copyright 2006 John Wiley & Sons, Inc.
9-3
Project Elements
Š
Š
Š
Š
Š
Š
Š
Š
Objective
Scope
Contract requirements
Schedules
Resources
Personnel
Control
Risk and problem analysis
Copyright 2006 John Wiley & Sons, Inc.
9-4
2
Project Management Process
Š
Š
Š
Š
Project planning
Project scheduling
Project control
Project team
„
made up of individuals from various areas and
departments within a company
Š Matrix organization
„
a team structure with members from functional areas,
depending on skills required
Š Project Manager
„
most important member of project team
Copyright 2006 John Wiley & Sons, Inc.
9-5
Project Scope
Š Scope statement
„
a document that provides an understanding,
justification, and expected result of a project
Š Statement of work
„
written description of objectives of a project
Š Work breakdown structure
„
breaks down a project into components,
subcomponents, activities, and tasks
Copyright 2006 John Wiley & Sons, Inc.
9-6
3
Work
Work Breakdown
Breakdown Structure
Structure for
for Computer
Computer Order
Order
Processing
Processing System
System Project
Project
Copyright 2006 John Wiley & Sons, Inc.
9-7
Š Organizational Breakdown Structure
„
a chart that shows which organizational units are
responsible for work items
Š Responsibility Assignment Matrix
„
shows who is responsible for work in a project
Copyright 2006 John Wiley & Sons, Inc.
9-8
4
Project Scheduling
Š Steps
„
„
„
„
Define activities
Sequence
activities
Estimate time
Develop schedule
Š Techniques
„
„
„
„
Gantt chart
CPM
PERT
Microsoft Project
Copyright 2006 John Wiley & Sons, Inc.
9-9
Gantt Chart
Š Graph or bar chart with a bar for each
project activity that shows passage of
time
Š Provides visual display of project
schedule
Š Slack
„
amount of time an activity can be delayed
without delaying the project
Copyright 2006 John Wiley & Sons, Inc.
9-10
5
Example of Gantt Chart
0
|
2
|
Month
4
|
6
|
8
|
10
Activity
Design house
and obtain
financing
Lay foundation
Order and
receive
materials
Build house
Select paint
Select carpet
Finish work
1
3
Month
5
7
9
Copyright 2006 John Wiley & Sons, Inc.
9-11
Project Control
Š
Š
Š
Š
Time management
Cost management
Quality management
Performance management
„
Earned Value Analysis
z
a standard procedure for numerically measuring a
project’
project’s progress, forecasting its completion date and
cost and measuring schedule and budget variation
Š Communication
Š Enterprise project management
Copyright 2006 John Wiley & Sons, Inc.
9-12
6
CPM/PERT
Š Critical Path Method (CPM)
„
„
„
DuPont & RemingtonRemington-Rand (1956)
Deterministic task times
ActivityActivity-onon-node network construction
Š Project Evaluation and Review Technique
(PERT)
„
„
„
US Navy, Booz,
Booz, Allen & Hamilton
Multiple task time estimates
ActivityActivity-onon-arrow network construction
Copyright 2006 John Wiley & Sons, Inc.
9-13
Project Network
Š Activity-on-node (AON)
„
nodes represent activities,
and arrows show
precedence relationships
Š Activity-on-arrow (AOA)
„
arrows represent activities
and nodes are events for
points in time
Š Event
„
Node
1
2
3
Branch
completion or beginning
of an activity in a project
Copyright 2006 John Wiley & Sons, Inc.
9-14
7
AOA Project Network for
a House
3
Lay
foundation
1
3
Design house
and obtain
financing
2
2
Dummy
0
1
Order and
receive
materials
4
Select
paint
Build
house
6
3
1
Finish
work
1
7
1
Select
carpet
5
Copyright 2006 John Wiley & Sons, Inc.
9-15
Concurrent Activities
Lay foundation
2
Lay
foundation
3
Order material
(a) Incorrect precedence
relationship
Copyright 2006 John Wiley & Sons, Inc.
2
3
Dummy
2
0
1
4
Order material
(b) Correct precedence
relationship
9-16
8
AON Network for House
Building Project
Lay foundations
Build house
4
3
2
2
Start
Finish work
7
1
1
3
Design house
and obtain
financing
3
1
Order and receive
materials
6
1
5
1
Select carpet
Select paint
Copyright 2006 John Wiley & Sons, Inc.
9-17
Critical Path
4
3
2
2
Start
7
1
1
3
3
1
A:
B:
C:
D:
1-2-4-7
3 + 2 + 3 + 1 = 9 months
1-2-5-6-7
3 + 2 + 1 + 1 + 1 = 8 months
1-3-4-7
3 + 1 + 3 + 1 = 8 months
1-3-5-6-7
3 + 1 + 1 + 1 + 1 = 7 months
Copyright 2006 John Wiley & Sons, Inc.
6
1
5
1
Š Critical path
„
„
Longest path
through a network
Minimum project
completion time
9-18
9
Activity Start Times
Start at 5 months
4
3
2
2
Start
Finish at 9 months
7
1
1
3
3
1
Start at 3 months
Finish
6
1
5
1
Start at 6 months
Copyright 2006 John Wiley & Sons, Inc.
9-19
Mode Configuration
Activity number
Earliest start
Earliest finish
1
0
3
3
0
3
Latest finish
Activity duration
Copyright 2006 John Wiley & Sons, Inc.
Latest start
9-20
10
Forward Pass
Š Start at the beginning of CPM/PERT network to
determine the earliest activity times
Š Earliest Start Time (ES)
„
„
earliest time an activity can start
ES = maximum EF of immediate predecessors
Š Earliest finish time (EF)
„
„
earliest time an activity can finish
earliest start time plus activity time
EF= ES + t
Copyright 2006 John Wiley & Sons, Inc.
9-21
Earliest Activity Start and
Finish Times
Lay foundations
Build house
2
Start
3
5
4
2
5
8
3
1
0
3
7
1
Design house
and obtain
financing
8
9
1
6
3
3
4
1
Order and receive
materials
Copyright 2006 John Wiley & Sons, Inc.
6
7
Finish work
1
5
5
6
1
Select carpet
Select pain
9-22
11
Backward Pass
Š Determines latest activity times by starting at
the end of CPM/PERT network and working
forward
Š Latest Start Time (LS)
„
Latest time an activity can start without delaying
critical path time
LS= LF - t
Š Latest finish time (LF)
„
„
latest time an activity can be completed without
delaying critical path time
LS = minimum LS of immediate predecessors
Copyright 2006 John Wiley & Sons, Inc.
9-23
Latest Activity Start and
Finish Times
Lay foundations
Build house
Start
2
3
5
2
3
5
4
5
8
3
5
8
1
0
3
7
8
9
1
0
3
1
8
9
Design house
and obtain
financing
3
3
4
1
4
5
Order and receive
materials
Copyright 2006 John Wiley & Sons, Inc.
5
5
6
1
6
7
6
6
7
1
7
8
Finish work
Select carpet
Select pain
9-24
12
Activity Slack
Activity
Activity
LS
LS
ES
ES
LF
LF
EF
EF
Slack
Slack SS
*1
*1
*2
*2
00
33
00
33
33
55
33
55
00
00
33
*4
*4
55
44
55
33
55
55
88
44
88
11
00
66
77
55
66
77
88
66
77
88
88
99
99
11
11
00
66
*7
*7
** Critical
Critical Path
Path
Copyright 2006 John Wiley & Sons, Inc.
9-25
Probabilistic Time Estimates
Š Beta distribution
„
a probability distribution traditionally used in
CPM/PERT
a + 4m
4m + b
Mean (expected time):
t=
6
Variance:
where
b-a
σ2=
6
2
a = optimistic estimate
m = most likely time estimate
b = pessimistic time estimate
Copyright 2006 John Wiley & Sons, Inc.
9-26
13
P(time)
P(time)
Examples of Beta Distributions
a
m
t
b
a
t
Time
m
b
P(time)
Time
m=t
a
b
Time
Copyright 2006 John Wiley & Sons, Inc.
9-27
Project Network with Probabilistic
Time Estimates: Example
Equipment
installation
4
6,8,10
2,4,12
System
development
Start
Equipment testing
and modification
1
2
3,6,9
Position
recruiting
3
1,3,5
System
training
8
Manual
testing
3,7,11
1,4,7
9
1,10,13
5
2,3,4
Job Training
6
3,4,5
Final
debugging
10
Finish
11
2,4,6
System
testing
System
changeover
Orientation
7
2,2,2
Copyright 2006 John Wiley & Sons, Inc.
9-28
14
Activity Time Estimates
TIME ESTIMATES (WKS)
ACTIVITY
1
2
3
4
5
6
7
8
9
10
11
MEAN TIME
VARIANCE
a
m
b
t
б2
6
3
1
2
2
3
2
3
2
1
1
8
6
3
4
3
4
2
7
4
4
10
10
9
5
12
4
5
2
11
6
7
13
8
6
3
5
3
4
2
7
4
4
9
0.44
1.00
0.44
2.78
0.11
0.11
0.00
1.78
0.44
1.00
4.00
Copyright 2006 John Wiley & Sons, Inc.
9-29
Activity Early, Late Times,
and Slack
ACTIVITY
1
2
3
4
5
6
7
8
9
10
11
t
б2
ES
EF
LS
LF
S
8
6
3
5
3
4
2
7
4
4
9
0.44
1.00
0.44
2.78
0.11
0.11
0.00
1.78
0.44
1.00
4.00
0
0
0
8
6
3
3
9
9
13
16
8
6
3
13
9
7
5
16
13
17
25
1
0
2
16
6
5
14
9
12
21
16
9
6
5
21
9
9
16
16
16
25
25
1
0
2
8
0
2
11
0
3
8
0
Copyright 2006 John Wiley & Sons, Inc.
9-30
15
Earliest, Latest, and Slack
1 0
8 1
Start
2 0
6 0
3 0
3 2
8
9
3
5
10 13 17
8 9
7 9
6
6
Critical Path
4 8 13
5 16 21
16
9
6 3
4 5
9
7
3
Finish
16
9
5 6
3 6
1 0
9 9 13
4 12 16
11 16 25
9 16 25
7 3 5
2 14 16
Copyright 2006 John Wiley & Sons, Inc.
9-31
Total project variance
σ2 = б22 + б52 + б82 + б112
σ = 1.00 + 0.11 + 1.78 + 4.00
= 6.89 weeks
Copyright 2006 John Wiley & Sons, Inc.
9-32
16
Probabilistic Network Analysis
Determine probability that project is
completed within specified time
Z=
where
x-µ
σ
µ = tp = project mean time
σ = project standard deviation
x = proposed project time
Z = number of standard deviations x
is from mean
Copyright 2006 John Wiley & Sons, Inc.
9-33
Normal Distribution Of Project
Time
Probability
Zσ
µ = tp
Copyright 2006 John Wiley & Sons, Inc.
x
Time
9-34
17
Southern Textile Example
What is the probability that the project is completed
within 30 weeks?
P(x ≤ 30 weeks)
σ 2 = 6.89 weeks
σ =
6.89
σ = 2.62 weeks
µ = 25 x = 30
Z=
=
x-µ
σ
30 - 25
2.62
= 1.91
Time (weeks)
From Table A.1, (appendix A) a Z score of 1.91 corresponds to a
probability of 0.4719. Thus P(30) = 0.4719 + 0.5000 = 0.9719
Copyright 2006 John Wiley & Sons, Inc.
9-35
Southern Textile Example
What is the probability that the project is completed
within 22 weeks?
x-µ
Z= σ
σ 2 = 6.89 weeks
P(x ≤ 22 weeks)
σ =
6.89
σ = 2.62 weeks
=
22 - 25
2.62
= -1.14
x = 22 µ = 25
Time
(weeks)
From Table A.1 (appendix A) a Z score of -1.14 corresponds to a
probability of 0.3729. Thus P(22) = 0.5000 - 0.3729 = 0.1271
Copyright 2006 John Wiley & Sons, Inc.
9-36
18
Project Crashing
Š Crashing
„
reducing project time by expending additional
resources
Š Crash time
„
an amount of time an activity is reduced
Š Crash cost
„
cost of reducing activity time
Š Goal
„
reduce project duration at minimum cost
Copyright 2006 John Wiley & Sons, Inc.
9-37
Project Crashing: Example
4
2
8
12
7
4
1
12
3
4
Copyright 2006 John Wiley & Sons, Inc.
5
4
6
4
9-38
19
Project Crashing: Example (cont.)
$7,000 –
$6,000 –
Crash cost
$5,000 –
Crashed activity
Slope = crash cost per week
$4,000 –
$3,000 –
$2,000 –
Normal activity
Normal cost
$1,000 –
–
0
Normal time
Crash time
|
2
|
4
|
6
|
8
|
10
|
12
|
14
Weeks
Copyright 2006 John Wiley & Sons, Inc.
9-39
Normal Activity and Crash
Data
ACTIVITY
1
2
3
4
5
6
7
NORMAL
TIME
(WEEKS)
CRASH
TIME
(WEEKS)
NORMAL
COST
12
8
4
12
4
4
4
7
5
3
9
1
1
3
$3,000
2,000
4,000
50,000
500
500
15,000
$5,000
3,500
7,000
71,000
1,100
1,100
22,000
$75,000
$110,700
Copyright 2006 John Wiley & Sons, Inc.
CRASH
COST
TOTAL
ALLOWABLE
CRASH TIME
(WEEKS)
5
3
1
3
3
3
1
CRASH
COST PER
WEEK
$400
500
3,000
7,000
200
200
7,000
9-40
20
$7000
$500
$700
12
7
4
1
12
$400
Project Duration:
36 weeks
4
2
8
3
4
6
4
5
4
$3000
FROM …
$200
$200
$500
$7000
2
8
12
4
$700
7
4
1
TO…
7
Project Duration:
31 weeks
Additional Cost:
$2000
$400
3
4
$3000
5
4
6
4
$200
$200
Copyright 2006 John Wiley & Sons, Inc.
9-41
Time-Cost Relationship
ƒ Crashing costs increase as project
duration decreases
ƒ Indirect costs increase as project
duration increases
ƒ Reduce project length as long as
crashing costs are less than indirect
costs
Copyright 2006 John Wiley & Sons, Inc.
9-42
21
Time-Cost Tradeoff
Minimum cost = optimal project time
Total project cost
Cost ($)
Indirect cost
Direct cost
Crashing
Project duration
Copyright 2006 John Wiley & Sons, Inc.
Time
9-43
Copyright 2006 John Wiley & Sons, Inc.
All rights reserved. Reproduction or translation of this work beyond
beyond that
permitted in section 117 of the 1976 United States Copyright Act without
express permission of the copyright owner is unlawful. Request for further
information should be addressed to the Permission Department, John
John Wiley &
Sons, Inc. The purchaser may make backup
copies
for
his/her
own
use only and
back
not for distribution or resale. The Publisher assumes no responsibility
responsibility for
errors, omissions, or damages caused by the use of these programs
programs or from the
use of the information herein.
Copyright 2006 John Wiley & Sons, Inc.
9-44
22