SECTION 02201 SUBGRADE PREPARATION PART 1 GENERAL 1.01 WORK INCLUDED 1. Preparation of the existing ground surfaces under all embankment, structure and crushed aggregate base course, and high density polyethylene pond liner construction areas that are required by these Specifications or so indicated on the Drawings. 2. In the event that materials beneath the existing ponds are too wet to obtain the densities required by this section, work will be suspended until such time that the requirements can be met. There will be no additional payments made to the contractor for any costs associated with work stopping and restarting as a result of this delay. 1.02 RELATED WORK 1. Section 01410: Testing Laboratory Services A. Section 02120: Temporary Water Pollution and Erosion Control B. Section 02200: Clearing and Grubbing C. Section 02220: Excavation and Backfill D. Section 02601: Sewer Manholes 1.03 REFERENCES 1. American Society for Testing and Materials: 1. ASTM D-422, “Particle Size Analysis of Soils”. 2. ASTM D-698, “Test for Moisture-Density Relations of Soils (Standard Proctor) Using 5.5-lb Hammer and 12-in Drop”. 3. ASTM D-1556, “Density of Soil in Place by the Sand-Cone Method”. 02201 - 1 4. 5. 6. 7. 8. 9. 1.04 ASTM D-1557, “Test for Moisture-Density Relations of Soils (Modified Proctor) Using 10-lb Hammer and 18-in Drop”. ASTM D-2216, “Laboratory Determination of Moisture Content of Soil”. ASTM D-2167, “Density and Unit Weight of Soils in Place by the Rubber Balloon Method”. ASTM D-2922, “Density of Soil and Soil-Aggregate in Place by Nuclear Methods (Shallow Depth)”. ASTM D-3017, “Moisture Content of Soil and Soil-Aggregate in Place by Nuclear Methods (Shallow Depth)”. ASTM D-4318, “Standard Test Method for Liquid Limit, Plastic Limit, and Plasticity Index for Soils”. QUALITY ASSURANCE A. Contractor shall provide material testing for quality control during subgrade preparation at the following frequencies: 1. Structures and Crushed Aggregate Base Course Construction Areas 1. One in-place soil density per 2500 square feet of structure or CBAC subgrade area or as requested by the Engineer according to ASTM D-1556, ASTM D-2167, or ASTM D-2922, and ASTM D3017. 2. One sieve analysis and plasticity index per each type of subgrade material encountered per ASTM D-422 and ASTM D-4318. 3. One moisture density curve per each type of subgrade material encountered according to ASTM D-1557. 2. Embankment and HDPE Pond Liner Construction Areas 1. One in-place soil density per 9000 square feet of embankment or HDPE pond liner subgrade area or as requested by the Engineer according to ASTM D-1556, ASTM D-2167, or ASTM D-2922, and ASTM D-3017. 2. One sieve analysis and plasticity index per each type of subgrade material encountered per ASTM D-422 and ASTM D-4318. 3. One moisture density curve per each type of subgrade material encountered according to ASTM D-698. B. Following approval by the Engineer of clearing activities and initial cross section data, subgrade elevations required by these Specifications or as indicated by the Drawings shall be approved by the Engineer prior to the commencement of any subgrade preparation activities. 02201 - 2 1.05 SUBMITTALS 1. Moisture Density Curve: For each type of material encountered per ASTM D-698 or ASTM D-1557. B. Sieve Analysis and Plasticity Index Test Results: For each type of material encountered per ASTM D-422 and ASTM D-4318. 3. In-Place Field Density Test Results for all subgrade preparation areas per ASTM D-1556, ASTM D-2167, or ASTM D-2922 and ASTM D-3017. PART 2 PRODUCTS 2.01 SUITABLE MATERIALS A. Suitable materials shall consist of materials encountered at the site and are subject to approval by the Engineer. B. Any underlying soft or otherwise unsuitable material shall be removed and replaced with suitable material as directed by the Engineer. 2.02 WASTE A. Disposal of excavated materials shall be the responsibility of the Contractor. PART 3 EXECUTION 3.01 GENERAL 1. Subgrade preparation activities are to be performed on approximately horizontal surfaces that terrace up the native slopes, at the elevations set forth in these Specifications and as indicated by the Drawings. 1. Perpendicular to the embankment the horizontal benches shall be terraced into the native slope with elevation changes per step not to exceed twenty four (24) inches. 02201 - 3 2. 2. 3.02 Parallel to the embankment the horizontal benches shall be terraced into the native slope with elevation changes per step not to exceed thirty six (36) inches. Surfaces requiring subgrade preparation activities shall be exposed by the overexcavation of native materials to the required depths below existing grades obtained from approved cross section data, below bottom of structures, CABC, and as approved by the Engineer. EXECUTION 1. 3.03 Prior to the commencement of any fill activities the following subgrade preparation activities shall be performed: 1. Scarify and blend the subgrade material to a depth of eight (8) inches and a moisture content to within + or - 2% of optimum. 2. Begin compaction efforts immediately after obtaining a uniform subgrade material blended to the required depth and at the required moisture content. COMPACTION REQUIREMENTS 1. Beneath structures and CABC construction areas, a minimum of 95% of Modified Proctor (ASTM D-1557) is required. 2. Beneath embankment a minimum of 95% of Standard Proctor (ASTM D-698) is required. 3. Compaction areas shall be kept separate, and no lift shall be covered by another until the proper density is obtained. 4. The Contractor shall make the necessary corrections and adjustments in methods, materials or moisture content in order to achieve the specified compaction requirements. END OF SECTION 02201 - 4