Objective Notes: W300 – Agreements, rights & responsibilities UNIT 22 - MANUAL THREE DISCHARGE 1 When contracts are discharged Parties by agreement may end contract/ release each other from future obligations subject to basic rule = agreements to end/ vary contracts must themselves be contracts with offer, acceptance, consid & contractual intention but if agreement is to accept part payment in settlement of debt, creditor not normally bound since debtor not provided consid (Foakes v Beer) unless shows common law exceptions (e.g. earlier than due payment etc - Pinnel’s Case) or Promissory Estoppel (reliance on promise intended to be relied on - High Trees); But where parties agreed to release others from o/s obligations each provided consid, so valid contract discharging original & A cannot subsequently insist B’s original obligations be carried out but, where A completely discharged his obligations & agrees to release B from his, agreement not = discharge & not binding since B not provided consid for promise; Performance (perf) – o If parties performed all contractual obligations, have done what is required of them & contract is at end but, traditionally, contracts subject to entire obligation rule - where contract entire/ indivisible & B does some work but then abandons job, cannot sue for payment because A’s obligation entirely dependent on B carrying out all obligations so where fails so to do, claim falls foul of rule (Cutter v Powell (1795)); o Exceptions = Where B wrongfully prevented A from completing obligations, A may sue for breach &, in awarding damages courts seek to place A where would have been had B allowed him to complete or by Planche v Colburn (1831), A could claim quantum meruit (QM) (= as much as he deserved) – amount reasonable vis-à-vis work done but often better to claim damages rather than QM since puts him where would have been on completion & higher award likely; Where B agreed to accept partial perf, A entitled to some payment provided B had real acceptance choice (Sumpter v Hedges [1898]); Where work substantially perf & defect repair cost comparatively low, guilty party entitled to some payment (Hoenig v Isaacs [1952]) but where work seriously defective (& repair cost accordingly substantial), not so entitled (Bolton v Mahadeva [1972]); Where obligations divisible, contractor entitled to payment on stage completion even if subsequently abandons work & courts generally interp contracts without express payment terms to enable party who has done some work to receive some payment (Roberts v Havelock (1832)). Breach by A may entitle B to terminate (term) contract & sue for damages where condition (major term) broken but if innominate (innom), innocent party can term on breach only where thereby deprived of substantially entire contract benefit & where B terms contract, treats it as repudiated, A having committed a repudiatory breach but breaches of minor terms (warranties) not enable term but entitle innocent party to sue for damages; Breach anticipatory (anticip) where A indicates in advance to B not intend to perform obligations & B’s right to repudiate of immediate effect so may term straight away –doesn’t have to wait until perf date(s) stated in contract - & may immediately sue for damages but right at his election – may prefer to wait until due date, especially if hopes A may still carry out obligations, & then sue (Hochester v De la Tour (1853)); Page 1 Objective Notes: W300 – Agreements, rights & responsibilities 2 B has the choice of either term or affirming contract – o If terms, contract is at end ,all future obligations discharged & normally, B must communicate decision to A but not always essential as acceptance requires no particular form provided clearly communicated & unequivocally conveys B treating contract as at end so not necessarily have to tell A provided info comes to A’s attention (e.g. via intermediary) since non-perf of obligation may constitute acceptance depending on contractual relationship & particular circumstances (Vitol SA v Norelf Ltd [1996]); o But risk if breach not in fact repudiatory & not give B term rights where B mistakenly believes A committed breach since acting on belief, B’s action may result in him breaching own obligations which may enable A to term &/ or claim damages from him but where in good faith so relies, not necessarily follow B be treated as having repudiated obligations since repudiation drastic conclusion which should only be held to exist where clear A refused to perform (Woodmar Investment Development Ltd v Wimpey Construction UK Ltd [1980]); o If affirms, contract not at end & both must continue to perf obligations but B must make it clear is treating contract as continuing &, whilst B entitled to damages for losses suffered, may continue to perform - despite knowing this against A’s wishes - & then sue for contract price (White & Carter (Councils) Ltd v McGregor [1962]); o But B not absolved from perf own obligations & if fails so to do, can’t rely on anticip breach to justify this (Fercometal SARL v Mediterranean Shipping Co SA [1988]) o Where parties agreed time is of the essence (e.g. time clause contract condition or, if innominate that B deprived of substantially contract’s entire benefit), B may claim damages & where not originally of the essence but A has unduly delayed in perf, B can make it of essence if gives A notice perf required within reasonable time (Charles Rickards Ltd v Oppenheim [1950]). Discharge effect Contact comes to end & no future obligations need to be performed by either party; Where discharge is by breach, damages may be awarded & court seeks to place innocent party where would have been had contract been properly performed; Where substantial perf found, A, having done work, may sue for contract price & B may counterclaim for defect remedying costs. Page 2