COMFIRSTNCDINST 4355.1B N3 COMFIRSTNCD INSTRUCTION 4355.1B From: Commander, FIRST Naval Construction Division Subj: CONSTRUCTION QUALITY PROGRAM Ref: (a) Unified Facilities Guide Specifications (UFGS) (b) NAVFAC Business Management System (BMS) B-1 Design and Construction (b) Corps of Engineers EP 415-1-261, Vols 1-4, Quality Assurance Representative Guide (d) COMFIRSTNCDINST 3502.2 Encl: (1) Sample Appointment Letter (2) Quality Control Inspection Plan (3) Construction Trade reference Library (4) Required Submittals Form (5) Quality Control Checklist examples (6) Preparatory Phase Checklist Form (7) Initial Phase Checklist Form (8) Daily QC Inspection (Follow up Phase) Checklist Form (9) Quality Deficiency Report (10) Design Change Directive (11) Field Adjustment Request (12) Definable Features of Work Submittal Form (13) Sample Project Package Disposition Letter 1. Purpose. To prescribe the policy, objectives, and procedures to ensure required quality construction is achieved on projects assigned to Naval Construction Force (NCF) units. 2. Cancellation. COMFIRSTINST 4355.1A. This instruction is a major revision and should be reviewed in its entirety. 3. Definition. Quality control (QC) and quality assurance are management systems of published and enforced standards which ensure construction projects are completed with a specified minimum quality. Quality construction is just as important as project execution. A product that falls below standards will not satisfy its intended purpose and may require excessive recurring maintenance costs. A product that exceeds the standards generally consumes more resources than planned. A project which costs a life or serious injury is not a "quality" project. Job safety and good project base house-keeping are important elements toward obtaining a finished product of acceptable quality. 4. Background. Reference (a) provides the business processes of the Naval Facilities Engineering Command (NAVFAC) Construction Quality Control (CQC) program. The NAVFAC philosophy establishes a mutual effort between the construction agent and the Resident Officer in Charge of Construction (ROICC)/Facility Engineering & Acquisition Division (FEAD) to deliver a facility which is acceptable as defined by the plans and specifications. Projects and Camp Maintenance assigned to the NCF are monitored by the ROICC/FEAD and Naval Construction Regiment (NCR) Camp Czar in accordance with normal CQC surveillance procedures which are set forth in reference (a). Oversight by the ROICC/FEAD or a designated representative does not relieve the construction agent of the responsibility to ensure projects meet the standards in the plans, specifications, and accepted construction practices. This instruction outlines procedures to help establish these programs. The program will require the assignment of personnel to non-direct labor billets. An effective inspection staff, working within an established command program, will yield the desired results. 5. Policy. The Commander, FIRST Naval Construction Division (COMFIRSTNCD) requires that all work tasked to NCF units is accomplished under an active CQC program. The entire chain of command is responsible to ensure quality work is put in place. Quality will be the normal not the exception for projects executed by the NCF. To prevent discrepancies where the quality of workmanship and materials fail to match the requirements in the plans and specifications each unit executing construction will establish and maintain an active CQC program. The NCF will utilize the three phases of control as the method of QC of work performed. The quality of all construction work done by NCF units will be closely monitored and the requirements of this instruction will be enforced through daily project QC inspections, ROICC/FEAD inspections, Quality Deficiency Reports (QDR) and all division or regimental visits or inspections. Results and feedback of these visits will be a significant factor when evaluating the unit’s overall performance. In conjunction with the above policy the following requirements are established: a. Roles and responsibilities (1) Echelon V commands: (a) The NCR is responsible for the identification, development, and oversight of all construction projects executed as unit tasking regardless of location or when they occur in the Fleet Readiness Training Plan (FRTP) cycle. The NCR will provide 2 construction management and quality oversight for: construction projects executed in the regimental deployed area of operations; Innovative Readiness Training projects; and pre-deployment construction projects. The NCR provides constructability reviews for assigned projects, coordinates with the local public works for the execution of quality assurance inspections, performs quality assurance inspections during project visits, and analyzes unit reporting. It also provides feedback on the performance of the unit's QC staff and CQC Program as part of the unit’s Unit Level Training Readiness Assessment-Sustainment (ULTRA-S). (b) The Seabee Readiness Group (SRG) is responsible for providing project management and quality oversight for projects that are constructed as part of Advanced Base Functional Component team training and Fleet Training Exercise training evolutions (i.e., projects that will be deconstructed upon completion of the training period.) The SRG provides direction and quality feedback during classroom periods of instruction and during execution of construction projects in the training environment. (2) Echelon VI Commanding Officers will perform all duties of a construction contractor for job accomplishment. The Commanding Officer is responsible for providing a quality product on time within the programmed cost in accordance with plans and specifications for the specific project. Units engaged in construction will organize to carry out an effective CQC program for all projects. NCF units will have as part of their Operations Department staff; construction inspection and material testing personnel specifically assigned and trained to perform these functions as their primary duty. Units that do not perform material testing are not required to man and train personnel for that skill. Normally personnel assigned as construction inspectors will be E-6 or above and fully trained to act as inspectors. Inspectors should be familiar with all aspects of construction. The Quality Control Branch will be led by a Chief Petty Officer or above and reports directly to the Operations Officer (S3). The establishment of the QC staff does not relieve the company organization from having an active and responsive CQC program which functions through the normal chain of command/organization. Each detachment (DET) will establish a QC organization tailored to the size and staffing of the DETs manning and tasking. The unit will consider the following items when establishing the CQC organization: (a) The QC staff is a valuable source of information and expertise. In addition to their quality oversight duties the QC staff should provide training and/or demonstrate proper construction techniques and methods to the project crews as needed. In order to ensure continuity and synergy of the CQC 3 program, once established, the QC organization will be maintained for a minimum of one FRTP cycle. 1. The QC Chief is S3’s direct representative and is responsible for the CQC program. He/she reviews and directs action on each inspector’s daily report as required, ensures the ROICC/FEAD receives reports and test results, and coordinates with the ROICC/FEAD to resolve any deficiencies in plans, materials, or workmanship on any project. QC Chief has "By direction" authority to stop forward progress on any project when work is not performed per plans, specifications or industry standards. This may be delegated to the QC Inspectors as required. QC Chief duties include, but are not limited to: a. Coordinate and review all QC plans. b. Coordinate and review all Project Inspection Plans. c. Ensure daily inspections are done professionally and efficiently. Review reports daily and ensure they are promptly routed, and follow up on any discrepancy, comment, or other issue noted. d. Coordinate with the NCR Camp Czar and/or the Camp Maintenance staff to determine which Maintenance Control Division (MCD) projects will require CQC oversight. Once an MCD project has been identified as requiring CQC oversight, all reporting and monitoring requirements that apply to an assigned project apply to the MCD project. Forward daily reports to the Camp Czar and the Camp Maintenance Chief. A Safety plan and QC plan will be submitted to QC Chief and approved prior to MCD project commencement. Abbreviated project files are authorized and will include a QC plan, Safety plan, all daily reports, and will be kept by the Camp Maintenance staff. e. Ensure that proper logs and reports are maintained for all projects. f. Maintain weekly contact with DET QC Inspectors and Assistant Officers in Charge (AOIC). Discuss project quality and inspection methods. g. Generating QDRs when quality deficiencies are brought to light. 2. Quality Control Inspectors a. QC Inspector staff manning will be consistent with the nature and location of the workload. Ensure 4 that only highly competent Petty Officers with demonstrated technical expertise are assigned as inspectors. Commands will appoint each QC Inspector by letter that clearly defines all authority and responsibilities. The appointment letter is provided in enclosure (1). Provide copies of the letter to the ROICC/FEAD and maintain copies on file. Assign QC Inspectors to specific projects in order to ensure continuity and accountability. Do not assign duties to QC Inspectors which detract from their primary responsibility of inspecting project quality. b. Construction Inspectors will be trained in accordance with reference (e) and should be able to identify deficiencies and make recommendations on material quality, workmanship, and construction practices. Units may request additional training for specific tasking through their chain of command. QC Inspectors will be familiar with the unit QC and safety program instructions. QC inspectors should also possess experience to recognize safety violations on project sites and recommend corrective actions. c. The QC Inspector’s job is project quality, not resource scheduling and availability. They report directly to QC Chief. They are responsible for daily QC inspections, phase checks, and coordinating any special tests or inspections. They advise Project Supervisors on construction techniques and suggest better or more efficient methods if available. They visually inspect and report on the progress and quality of all work-in-place. They report and correct all safety violations, ensure proper material use and conservation, and can assist Project Supervisors in determining work-in-place for reporting purposes. If an inspector lacks knowledge about a particular aspect of the construction, it is solely his/her responsibility to get assistance from QC Chief, another inspector, the ROICC/FEAD, or any other qualified source. QC Inspector responsibilities also include but are not limited to: d. To be completely familiar with plans, specifications, and manufacturers recommendations for assigned projects. Assist Project Supervisors in developing QC plans. e. Develop a Project Inspection Plan that details all al QC inspections for the project and provides quantitative measurement. Specific care will be taken in plotting critical QC points. The inspection plan will be developed independently of the QC plan, but will be coordinated prior to project start to align inspection dates with activity start dates. The inspection plan will detail objectives for each project visit regardless of milestones. The inspection plan format is included as enclosure (2). 5 f. Become familiar with the unit safety instruction and acquire proper training to identify safety hazards/violations on projects. g. Visit all projects daily and submit daily reports. Proper documentation is a must. Daily reports must identify all discrepancies and solutions. Reports become the record and show how quality was measured and confirmed throughout construction. Without proper documentation all construction quality is suspect. The daily inspection form is found in enclosure (3). h. Discuss job progress and construction methods with the Company Operations Chiefs, Project Supervisors, and Crewleaders. i. Immediately notify QC Chief or Operations Chief (S3C) if questionable construction or safety practices are observed. j. Advise prime and subcontractor companies in project planning and project file maintenance. k. Review and coordinate all requests for information (RFI), field adjustment requests (FAR), excavation requests, utility outages, road closures, and concrete form designs for constructability and make initial recommendations. Ensure all RFI have been FULLY researched prior to submitting to ROICC/FEAD. l. Be present during all phase checks and certified system tests to ensure compliance with plans/specs and manufacturer recommendations. m. Brief QC Chief daily on inspections scheduled, project visits, inspection reports. n. Route daily inspection reports to ROICC/FEAD, QC Chief, and the Project Supervisor. o. Inspect project materials received at the job site and Material Liaison Office (MLO) to verify that they meet project specifications. p. Ensure timely delivery of any prints, specs, Bill of Material, or any other information to the prime contractor company. 6 q. Become familiar with local construction practices used at deployment sites. r. Maintain copies of all project correspondence, i.e., FAR, RFI, design change directive (DCD), utility requests, etc. Ensure all information is current and correct. Maintain a tickler on all unanswered correspondence. Ensure all reports and correspondence are properly logged and filed. s. Create and maintain a significant events calendar that will be placed in a conspicuous place to notify all interested personnel of project milestones (concrete placement, asphalt work, punch list inspections, beneficial occupancy date (BODs), ribbon cuttings, etc.) t. Review project submittals prior to submission to ROICC/FEAD. u. Ensure project files and as-built drawings are updated continuously (at least every two weeks) and are complete upon project completion. QC Inspectors will draft closeout letters and submit to the S3 Yeoman for typing. Project packages will be updated for all turnover projects to provide the relieving unit with as much information as possible. All operations and maintenance manuals will be turned over to ROICC/FEAD after project completion. 3. DET QC Inspectors duties are the same as noted in paragraph 5.a.(2)(a)2.c. thru u. DET QC Inspectors shall report to the DET AOIC or QC Chief (as appropriate) for daily review. DET QC Inspectors shall maintain as close a liaison as possible with the QC Chief for professional advice and guidance. 4. Engineering Chief is responsible for, but not limited to: a. Maintaining a complete laboratory, with all required testing equipment, to perform required tests. Ensure all required calibrations and certifications are up to date and properly recorded in logs. b. Performing all scheduled or required tests per established methods set forth by the specifications and accepted industry standards. c. Maintain accurate and complete test records and promptly deliver results to QC inspectors. 7 d. All surveying, project layout, and elevations. e. All drafting, as-built drawings, designs, and sketches on FARs and RFIs. f. Maintaining project history files for all projects completed at the Main Body site. Additionally, the engineering chief will maintain a list of all projects completed at DET sites associated with the Main Body site. Additional details provided in g. Maintain the unit construction trade library. 5. Material Testing Personnel a. There will be a sufficient number of trained personnel to conduct/coordinate required tests on concrete, asphalt, soils, and other materials, as required and to maintain equipment needed to perform these tests. b. Upon the completion of the project QC plan, the QC staff will develop an inspection plan incorporating required testing. This is the time to identify on-site testing requirements and capabilities. If a required testing capability is not available within the unit, the Operations Department should contact other government agencies and coordinate necessary testing services. c. During construction, testing personnel will conduct required tests in accordance with the inspection plan. All test results will be attached to the QC report for the date the work was put in place. For example, concrete cylinder break results at the seven, fourteen, and twenty-eight day point will be attached to the QC report filled out on the date of the concrete placement. The QC reports and attached test results will be signed by both the QC Inspector and Project Supervisor and two copies forwarded to the ROICC/FEAD. Provide copies of QC reports and test results to the NCR as requested for review. After ROICC/FEAD review, the report will be routed through the project chain of command and remain as part of the project package. For onsite tests, the designated ROICC/FEAD representative will be notified in advance to allow the opportunity to observe the test. 6. Company Commanders/DET OICs assign Project Supervisors and Crewleaders. They ensure that all planning documents, including specific QC plans for each project are complete, publicized, and understood prior to project start for 8 all assigned projects, in homeport or on deployment. He/she will ensure that experienced people are in charge and that crews have the necessary skills to complete the project. DET OICs and Company Commanders will monitor construction quality and efforts through QC reports and regular project visits. The Company or DET Chain of Command will take a proactive stance in project quality and are responsible for: a. Ensuring that Project Supervisors and Crewleaders share command concern for safe, high quality execution of work. b. Conducting a constructability review for each assigned project. c. Reviewing project plans and specifications, and submitting a report of all errors and omissions to QC Chief. d. Reviewing QC plans prior to submittal to the QC Staff. e. Making regular project visits to ensure that the job sites are safe, productive, and that crews are producing a quality project. f. Review and validate all FARs and RFIs prior to submission. 7. Company/DET Operations Chief/Project Chief is directly responsible to the Company Commander/DET OIC for all QC matters. These individuals will give added attention to training Project Supervisors and Crewleaders in developing QC plans and using the three phases of inspection. 8. Project Supervisors are responsible for the overall quality and workmanship on his/her job site including work performed by all subcontractors. A Project Supervisor typically is responsible for the supervision of two or more Crewleaders of various ratings engaged in the completion of a project. Assisted by the QC staff, he/she develops a specific QC plan for the assigned project. He/she will accompany QC Inspectors during job site visits and assist in completing daily reports. Upon completion of the rework make arrangements for reinspection. Project Supervisors are also responsible for: a. Conduct daily QC lectures to review Definable feature of work (DFOW) or activity QC requirements for that day. 9 b. Using the preparatory and initial phase checklist before starting each DFOW. c. Maintaining a continual job-site presence to ensure maximum quality and productivity. d. Maintaining a log for all DCDs, FARs, and RFIs in the project package, folder 4B. e. Reviewing the five-folder project package with the lead QC Inspector upon project completion. Ensure that all project information required for the project completion letter is current, accurate and in the file. f. Inspect and verify work before specific requested QC inspections occur, i.e., Concrete Placement, stack tests, etc. Identify all key inspections as milestones on the project schedule. g. Research all RFIs prior to submission. h. Ensure that project crews are familiar with daily/weekly construction schedules by posting them and/or discussing during daily project QC meetings. 8. Crewleaders will become familiar with project plans and specifications and ensure that the proper tools and equipment are available for the job. A Crewleader typically supervises a crew of two or more persons generally of the same rate in the completion of a phase or section of a project. He/she is responsible to the Project Supervisor to provide the highest quality workmanship possible from his/her assigned crew. He/she will keep the Project Supervisor updated on progress, potential delays or problem areas, required tests, and any and all changes necessary to the as-built drawings. The Crewleader will inspect his crew’s work and ensure it meets the required quality level. 9. Crewmembers will become familiar with project quality requirements. They will develop a complete understanding of work methods and question Crewleaders about any activity that they do not fully understand. The entire CQC Program hinges around the Crewmember and their ability to perform construction in accordance with plans, specifications, and accepted construction practices. 10. Material Expediters: The material expeditor along with the project supervisor and the QC Inspector will inspect all material when received by the MLO. These inspections ensure materials meet all the conditions set forth in the plans 10 and specifications. Further, the material expeditor will reinspect at least one month prior to planned use and materials received months in advance of their intended installation date. This re-inspection identifies expired shelf life, storage damage, and usability of material. The Material Testing Personnel will inspect mineral products upon delivery and reject them when they do not comply with the project specifications. b. Quality Control Implementation Guidance (1) Pre-Construction (a) Plans and specifications establish construction standards and accepted construction practices. Because of varying site conditions, intended purpose, and the life expectancies of various facilities, construction standards may vary from project to project. Units will use references (a) through (d) as the minimum acceptable standards when other defined standards are absent. (b) Commands will coordinate with the NCR to receive plans and specs. NCRs will coordinate with the Public Works/Design Agent to receive plans and specs approximately 10 months prior to project execution. Project planning should be done using the final signed version of plans and specs. During planning process the unit will develop a QC plan which will be submitted to the QC Staff for approval and incorporation into the inspection plan. (c) In cases where materials do not meet specifications, i.e., Theater Security Cooperation Plan (TSCP) missions the project leadership will coordinate with the chain of command and NCR to identify suitable local materials. (d) FARs and RFIs: Review plans and specifics to identify conflicts in construction methods and materials. Submit RFIs and FARs for clarification or adjustment in construction method. Changes which exceed 50 man-days of additional effort or $500 in additional cost must be approved by the appropriate NCR prior to submission to ROICC/FEAD. (e) Units will develop a QC Plan for each project. The QC Plan will identify quantifiable QC inspection points for each activity. Enclosure (5) is a QC checklist. The reference list in enclosure (10) is provided as a resource to assist the crew in developing valid inspection criteria. (f) Inspection Plan: Unit QC staffs will develop a construction inspection plan for each project specifically tasked to the unit. The construction inspection plan will identify each 11 item/phase of the project which requires a quality check (i.e., phase inspections, material tests, utility tests, etc.), and highlight critical inspection points. The frequency of required tests must be shown. The QC staff will prepare inspection plans per enclosure (2). The QC inspector will prepare the plan with sufficient detail to identify specific plans and specification requirements for each phase of work. The QC inspection plan will be developed using the current project schedule and QC plan. This is a required submittal to the ROICC/FEAD. (g) Hold a preconstruction conference with the ROICC/FEAD or designated representative, public works, customer, and project QC inspector, to discuss the scope of the project, construction schedule, utility requirements, the QC plan, and any other items which may affect construction. Maintain regular contact with the ROICC/FEAD representative throughout the life of each construction project until it is totally completed. (2) Project Execution: (a) QC will be accomplished utilizing the three phases of inspections; preparatory, initial, and follow-up. These inspections are based on definable features of work (DFOW). DFOW is defined as a task that is separate and distinct from other tasks and requires separate QC requirements. A DFOW is identified by different trades or disciplines and is an item or activity on the construction schedule. Each specification section could be considered a definable feature of work, but, there frequently is more than one definable feature of work under a particular section. A Construction Activity may be a DFOW, depending on the activities scope, quantity of work, skill intensity and/or resulting quality required for its completion. The three phases of inspection are defined as follows: (b) Preparatory Phase. Prior to starting the project and before the start of each DFOW the Project Supervisor will hold a QC preparatory phase meeting. This meeting will include all pertinent Crewleaders, QC staff, Project Manager, and FEAD/ROICC representative. The purpose of this meeting is to inform all personnel involved with the activities of the QC requirements. The meeting will also address all submittals, materials, tools, and equipment needed to accomplish the activities. These items should correlate directly with the project QC plan and applicable areas in the specifications. Enclosure (6) is the Preparatory Phase checklist. (c) Initial Phase. When construction starts on an activity, the QC Inspector and Project Supervisor will monitor the initial material installation to validate adherence to the plans ands specifications as agreed upon during the Predatory 12 Phase meeting. Any discrepancies in workmanship will be corrected immediately. Enclosure (7) is the Initial Phase checklist. (d) Follow up Phase. The Project Supervisor, QC Inspector, and chain of command will conduct continual inspections of the activities in progress. The QC Inspector will conduct daily checks during this phase and annotate findings on the daily QC reports, shown in enclosure (8). This will ensure that all work is done in accordance with the drawings and specifications. QC Inspector will submit the report to the Operations Officer or Detail OIC via the chain of command for final review, approval, and/or continuing action, as appropriate. QC will route a copy of the daily QC inspection report to the ROICC and the prime contractor company commander. (e) NCF units are required to make submittals for materials and construction methods used in the execution of projects. Submittals will be generated and provided to the FEAD/ROICC/Design Agent as identified in enclosure (4). (f) Operations Department personnel will review the original QC report daily. Provide a copy of each report to the ROICC/FEAD on the first working day following the period covered by the report. When discrepancies are noted in the report, immediately initiate action to correct the discrepancy. Note corrective actions taken on the QC report for the day during which corrective measures were taken. In addition, note the corrective actions taken and the date the actions were completed on the QC report which initially noted the discrepancy. Make copies of all inspection reports and test results a permanent part of the project records. (g) Quality Deficiency Reports will be generated when work in place fails to meet acceptable standards as set forth in the plan, specifications, references (a) through (d), and accepted industry standards. Un-reported, un-documented, or otherwise hidden quality defects found during follow-up inspections and/or turnovers may result in disciplinary action. Enclosure (12) is the form for the QDR. The following limits are established for the submission of QDRs. 1. Quality deficiencies or rework up to $2,500 are at the Commanding Officers discretion as to whether or not a QDR is submitted to the chain of command. 2. QDRs identifying poor quality or rework in excess of 50 mandays or between $2,500 and $5,000 in material costs require the QDR to be forwarded to the operational regimental commander for review and disposition. The 13 circumstances surrounding the QDR may require a Judge Advocate General (JAG) investigation to determine the facts. 3. QDRs identifying rework in excess of 100 mandays or $5,000 in material costs require a JAG investigation to determine the facts. The results of the JAG will be forward to the division Commander for review and disposition. (h) Conduct the final inspection of a completed facility with the ROICC/FEAD and correct any discrepancies. After all discrepancies are corrected and inspected during the acceptance inspection, forward a completion letter to the ROICC/FEAD along with a set of "as built" drawings, all manufacturer's literature, copies of Design Change Directives (DCDs) or change orders, operations and maintenance instructions, or other correspondence requested by the ROICC/FEAD. Enclosure (13) is a sample completion letter. (i). Forward a copy of all project completion letters to the appropriate regiment and COMFIRSTNCD. (j). Maintain completed project packages at main body and detachment sites for a period of three years to include a one year warranty period. At the end of the three year period forward a disposition request (Enclosure 13)to the operational regiment for guidance on disposal. R.E. CELLON Commander K. Gregory Chief of Staff Distribution: 14 1306 CO From: To: Commanding Officer, U. S. Naval Mobile Construction Battalion XXXX BU1(SCW) P. J. xxxxxxx, USN, 000-00-xxxx (Last four only) Subj: DESIGNATION AS QUALITY CONTROL INSPECTOR FOR PROJECT ####-### Ref: (a) COMFIRSTNCDINST 4355.1A (b) **Unit QC level instruction** (c) ** Unit level safety instruction** 1. You are hereby designated as the Quality Control inspector for (NMCB or Detachment xxxxxxx project ####-###). You are responsible for all matters of Construction Quality Control associated with projects. 2. You will familiarize yourself with the provisions of references (a) thru (c) in the performance of your duties. 3. This designation is effective immediately and expires upon the completion and acceptance of the project or if the project is turned over once the turnover is complete. J. R. WAYNE Copy to: S3 S3C S3QC Project Package RIOCC/FEAD Enclosure (1) Enclosure (2) Construction Reference Library Reference Title Author ISBN Basic Construction Management: The Superintendent's Job Basic Concrete Engineering for Builders Residential & Light Commercial Construction Standards Ten Steps To Jobsite Productivity Leon Rogers A Manual of Best Practice Volume 1 Exteriors A Manual of Best Practice Volume 2 Interiors JLC's Construction Tips & Techniques Finish Carpentry Journal of Light Construction Installing and Hanging Doors Gary Katz Masonry Skills, 5th Edition Richard T. Kreh Building with Masonry: Brick, Block and Concrete Masonry Problem Clinic Dick Kreh Building Tips & Techniques Fine Home Building Best Practices Guide to Residential Construction Basic Engineering for Builders Steve Bliss Construction Principles, Materials, and Methods Sixth Edition Basic Lumber Engineering for Builders Building with Engineered Lumber Harold Olin, John Schmidt Walter Lewis Max Schwartz Pocket Guide to the ADA : Americans with Disabilities Act Accessibility Guidelines for Buildings and Facilities JLC's Guide to Moisture Control Terry Edwards Associates Ed. ISBN-10: 0867184523 ISBN-13: 978-0867184525 ISBN-10: 1572180919 ISBN-13: 978-1572180918 ISBN-10: 0876296584 ISBN-13: 978-0876296585 ISBN-10: 0867185236 ISBN-13: 978-0867185232 ISBN-10: 1928580246 ISBN-13:978-1-928580-24-9 ISBN-10: 1928580289 ISBN-13:9781928580287 ISBN-10: 1928580319 ISBN-13: 978-1928580317 ISBN-10: 1928580076 ISBN-13: 978-1928580072 ISBN-10: 1561586358 ISBN-13: 978-1561586356 ISBN-10: 0766859363 ISBN-13: 9781418037536 ISBN-10: 1561583367 ISBN-13: 9781561583362 ISBN-10: 0924659254 ISBN-13: 9780924659256 ISBN-10: 1561586870 ISBN-13: 9781561586875 ISBN-10: 0471648361 ISBN-13: 978-0471648369 ISBN-10: 0934041830 ISBN-13: 9780934041836 ISBN-10: 0471714054 ISBN-13: 9780442006051 ISBN-10: 1572180420 ISBN-13: 9781572180420 ISBN-10: 1561586978 ISBN13: 9781561586974 ISBN-10: 0471181374 ISBN-13: 9780470108703 Journal of Light Construction ISBN-13: 9781928580362 Moisture Control Handbook : Principles and Practices for Residential and Small Commercial Buildings Builder’s Guide to Mixed-Humid Climates Estimating with Microsoft Excel Joseph Lstiburek & John Carmody ISBN-10: 0471318639 ISBN-13: 9780471318637 Joseph Lstiburek ISBN-13: 9780975512722 Jay P. Christofferson Exterior Siding, Trim & Finishes Fine Home Building Windows & Sky lights Fine Home Building ISBN-10: ISBN-13: ISBN-10: ISBN-13: ISBN-13: 086718549X 9780131719835 1561586528 9781561586523 9781561581276 Construction Surveying & Layout Paul Stull, Ph.D., P.E., P.S. Wells and Septic Systems, Second Edition Excavation & Grading Handbook Max & Building Layout W.P. Jackson Inspecting A House Rex Cauldwell ISBN-10: ISBN-13: ISBN-10: ISBN-13: ISBN-10: ISBN-13: ISBN-10: ISBN-13: ISBN-10: ISBN-13: 1557013632 9780934041256 0830621369 9780830621361 1572181737 9781572181731 0910460698 9780910460699 1561584622 9781561584628 Max Schwartz RS Means & Contributing Authors James J. Adrian Journal of Light Construction Journal of Light Construction Gary Katz The Aberdeen Group Max Schwartz John Spier Charlotte Alth Nick & John Capachi Enclosure (3) Construction Reference Library Mold Survival Guide Jeffrey May Gypsum Construction Handbook United States Gypsum Company Finish Carpenter's Manual Jim Tolpin Tiling: Planning, Layout & Installation Drywall - Professional Techniques for Walls & Ceilings Basic Stair building Fine Homebuilding Editors 1001 Ideas for Trim work Wayne Kalyn Setting Ceramic Tile, Second Edition For Pros by Pros Plumbing Michael Byrne The Plumber's Trouble-Shooting Guide Remodel Plumbing R. Dodge Woodson The Rafter Book - A Modern Handbook for Roof Framers Roof Cutter's Secrets David Mahin McIntire Roof Framing Marshall Gross Construction Foreman's Safety Handbook NAHB-OSHA Jobsite Safety Handbook George Kennedy The OSHA Answer Book Mark Moran Advanced Framing Techniques Steven Bliss The Lead Carpenter Handbook Tim Faller Construction Nightmares from Hell Arthur F. O'Leary FAIA, MRIA & James Acret, Esq. John J. Haasl and Peter Kuchinsky II NAHB Production Checklist For Builders and Superintendents Residential Construction Performance Guidelines, 2nd Ed. Daily Field Guide, a Log Book for Builders Carpentry in Commercial Construction Commercial Metal Stud Framing Myron Ferguson Scott Schuttner Rex Cauldwell Rex Cauldwell Will Holladay NAHB ISBN-10: ISBN-13: ISBN-10: ISBN-13: ISBN-10: ISBN-13: ISBN-10: ISBN-13: ISBN-10: ISBN-13: ISBN-10: ISBN-13: ISBN-10: ISBN-13: ISBN-10: ISBN-13: ISBN-10: ISBN-13: ISBN-10: ISBN-13: ISBN-10: ISBN-13: ISBN-10: ISBN-13: ISBN-10: ISBN-13: ISBN-10: ISBN-13: ISBN-10: ISBN-13: ISBN-10: ISBN-13: ISBN-10: ISBN-13: ISBN-10: ISBN-13: ISBN-10: ISBN-13: ISBN-10: ISBN-13: ISBN-10: ISBN-13: 080187937X 9780801879388 0963686224 9780963686206 0934041822 9780934041829 1561587885 9781561587889 1561585297 9781561581337 1561583227 9781561583225 1580112609 9781580112604 1561580805 978-1561580804 1561583332 978-1561583331 007071777X 9780070717770 1561586986 9781561586981 0964778408 9780964778405 1928580327 9781928580089 091046040X 9780910460408 0827378823 9780827378827 0867185295 978-0867185294 1890966657 9781890966652 1928580211 9781928580218 0963226878 9780963226877 1557013977 9781557012982 0867185155 9780867185157 Tom Hrin ISBN-13: 9780867185164 Byron W. Maguire Painter's Handbook Bill McElroy UGLY'S Electrical Handbook George V Hart ISBN-10: 0934041334 ISBN-13: 9780934041331 ISBN-10: 157218079X ISBN-13: 9781572180796 ISBN-10: 0934041288 ISBN-13: 978-0934041287 ISBN: 978-0-9623229-8-3 National Electrical Code NFPA ISBN: 0-87765-790-4 International Building Code ICC 2009 International Mechanical Code ICC 2009 International Plumbing Code ICC ISBN: 1580017258 ISBN13: 9781580017251 ISBN: 1580017312 ISBN13: 9781580017312 ISBN: 0071606068 ISBN13: 9780071606066 ISBN: ASCC105 Ray Clark ACI Ascc-1(05) Contractors Guide To ASCC/ACI Quality Concrete Construction ACI 318-08 Building Code Requirements For Structural Concrete 2 Enclosure (3) Construction Reference Library ACI 530/530.1-08 Building Code And Specs For Masonry ACI Sp-4 Formwork For Concrete American Concrete Institute (ACI) M. K. Hurd Asphalt Handbook Asphalt Institute ISBN - 53008 ISBN: SP47TH 3 Enclosure (3) Required Submittals Enclosure (4) Quality Control Checklist Examples 1. Paving a. Sub-grade (1) Sub-grade is to proper elevation and cross-section. (2) Sub-grade is dense and properly compacted. (3) All drains, utilities and other underground construction are in place. (4) Trench backfill is performed as required. (5) Testing sub-grade is performed and recorded to include OMC (opt moisture content). (6) Material delivered is of uniform quality. (7) Hauling equipment does not produce ruts in sub-grade. (8) Location of manholes, outlets and surface features are known. b. Priming and Tack Coats (1) Prime coat properly seals the surface voids and provides adhesion. (2) Prime coat is applied to water free surface free from objectionable substances. (3) Prime coat is applied uniformly and receives proper curing time. c. Asphalt Paving (1) Concrete against which paving is to be placed is to be at least seven days old. (2) Asphalt mix is proper and approved for this work. (3) Temperature of mix when delivered is within limits required and when laid in mat. (4) Weather limitations are observed. (5) Materials are properly spread, raked and placed for thickness and uniformity. Joints are properly formed and tight. (6) All edges are straight and curves uniform. Enclosure (5) Quality Control Checklist Examples (7) Rollers are operated within speed range and have proper backup features, drum scrapes and wetting devices. Roller is backed only over compacted areas. (8) Correction of humps and depressions to obtain smoothness and uniformity is to be performed before the start of compaction. (9) Damage to adjacent surfaces is corrected. 2. Concrete a. Formwork (1) Location, dimensions and grades are as required. (2) Formwork is properly sealed, oiled (prior to placing RST), or wetted and treatment is compatible with other materials to be applied. (3) Re-used formwork is properly reconditioned and treated for re-use. (4) Construction provides mortar-tight condition, free from offsets, defects and free of debris. Joints may be taped not to allow more than +/- 3/16”. (5) Observe type of form ties and bracing used to see if adequate for form design. (6) Sleeves for pinning and conduits are provided as required. (7) Forms are secured against movement during placing operations. Screens are set to prohibit movement during placing phase. (8) Chamfer strips are accurately placed and aligned. (9) Clean-outs are provided at ends and low points of forms. Ports are provided in high forms. Verify number and location. (10) Expansion, construction and contraction joints are provided as required or indicated and installed or planned properly. (11) Form cut-offs and bulkheads are established in locations approved. (12) Forms are in alignment, especially at top of walls. 2 Enclosure (5) Quality Control Checklist Examples (13) Keys are provided in construction joints. (14) Forms allow sufficient space and openings for placing concrete. (15) Forms provide for openings (doors, windows, ductwork, etc.). Cross bracing is provided in formed openings to prevent bowing. (16) Proper provisions are made during pour for tools, equipment and personnel. (17) Note appearance of obvious defects in formwork that might impair its ability to withstand concrete pressure without excessive deflection. (18) Consider personnel movement on the formwork during the placement phase when inspecting bracing. (19) Shoring is checked for location and bearing. Check shores for settlement during pouring and ensure mud-sills are used when posts are set on bare ground. (20) Drain clean-outs, flanges, etc. are set at proper elevation and sufficient anchorage is provided to avoid movement. (21) Scaffolds or other accessories appear adequate and do not affect formwork. (22) All embedded items are securely anchored in place and in the proper location. b. Form Removal (1) Concrete is sufficiently strong before removal of forms. Check specifications. (2) All formwork is completely removed above and below grade. (3) Preparations for grouting are made as soon as practicable after removal of forms. c. Reinforcement (1) Steel is installed in accordance with approved drawings. (2) Required clearance of steel from earth and forms is provided. (3) Splice lapping, length of splices and staggering is performed as required 3 Enclosure (5) Quality Control Checklist Examples (4) Additional bars, such as at wall intersections, openings and at corners are provided. (5) Reinforcement is clean of all loose or flaky rust, oils or other foreign materials that might reduce bond. (6) Reinforcement is tied and supported to prevent displacement during placement. (7) Conductors are separated from other conduits and re-bar by a minimum of three (3) conduit diameters. (8) No contact of bars is made with dissimilar metals. (9) Bars are not placed near surfaces that might allow rusting. (10) Adequate space and clearance is provided for proper deposit of concrete and use of vibrators. (11) Avoid bending re-bar excessively. d. Concrete Placement, Finishing, and Curing (1) Concrete hard card has been submitted and approved. (2) EA’s on site with equipment for testing. (3) All areas to receive concrete are cleaned, wetted, or otherwise prepared prior to arrival of first truck. (4) All necessary tools are on hand and in working condition. Vibrators and stand-by vibrators are available and in working condition. (5) Adequate manpower is available for timely placement. (6) Arrangements have been made for specific curing, sawed joints and protection from the elements. (7) Delivery of concrete and sequence of delivery is scheduled to allow for continuous placement to prevent cold joints. Delivery tickets are checked for time limits. (8) Layers are kept approximately horizontal and do not exceed required lifts. (9) Bolts and loose items to be embedded are properly located and installed. (10) Grades, elevations, alignments are being checked during placement. 4 Enclosure (5) Quality Control Checklist Examples (11) Time delay is made for concrete in columns, piers, walls and openings to allow concrete to settle before placing concrete above them; however, initial set is to be avoided. (12) Vibration is performed properly. (13) Cylinders are cast and stored, slump tests performed. (14) Type of finish on surfaces is checked and provided as required. (verify type of surface required). (15) Screens are provided and removed when they are no longer required. (16) Overworking the surface is to be avoided. (17) Ensure that all joints, edges, and corners are carefully finished and/or match. (18) Curing methods are to be started as soon as possible. (19) When plastic or burlap is used as a curing method, avoid disfiguring the surface finish by dragging or dropping weight on the surface when securing it. 3. Masonry a. Layout of work, coursing and dimensions are as required or indicated. b. Joint size, type and tooling method is understood. c. Type of bond (pattern) is in accordance with prints. d. Joints are tooled to provide a dense surface. e. Mortar is applied to block/brick and is not “slushed” into the head joints. f. Cutting of units is as required. g. Clean-outs/weep holes are provided as required. h. Reinforcement as required, is of type, sized, splicing and spacing required. i. Bending of re-bar for site access is to be kept to a minimum. j. Door frames are secured and braced in position (plumb and square). 5 Enclosure (5) Quality Control Checklist Examples k. All embedded materials are on site and available. l. Provisions for flashing, cutouts and later installation of other items are made. m. Expansion and control joints are located and provided, as indicated or required. n. Prior to pouring the cores ensure they are properly cleaned out. Ensure that cores are filled on a maximum of 6 courses of block at a time. RST not resting against block/brick to allow is in proper placement of grout. o. Pipes, conduits, and boxes are located, secured and protected as required. 4. p. Hollow metal frames are filled solid. q. Methods of final cleaning are as required. Structural Steel (1) Size and type of bolts, washers, and hole diameters are, as required. (2) Delivered steel is new, undamaged, and free of rust and distortions. (3) Steel is properly stored, blocked off ground and covered where prolonged storage occurs. (4) Observe setting of base and bearing plates. See that full engagement of nut occurs and bending of anchor bolts or undue chipping of concrete does not occur. (5) Verify clearances required for finish coverings or materials are provided. (6) Drift pins are used to bring together parts but should not damage or distort metal. (7) Steel members are not cut for passage of pipe conduit, etc., unless so indicated on shop drawings. (8) Type, size and length of bolt, size and type of washer and size of hole are as required. (9) All bolt heads and nuts are resting squarely against metal and check to see that bolts have been drawn tight. Check specification. 6 Enclosure (5) Quality Control Checklist Examples (10) Holes are properly aligned. misalignment is not permitted. 5. Burning to correct Thermal and Moisture Protection a. Roofing (1) Surfaces are free from foreign material. (2) Excess mortar or concrete is removed; all holes, joints and cracks are pointed, and rough and high spots are ground smooth. (3) Surfaces are dry to receive heated asphalt, coal tar and petroleum solvent asphalt mastics. (4) Hot applied bituminous materials are not overheated. Method and sequence of transporting and application of bituminous material are adequate. (5) Surfaces are properly primed if required. (6) Pipes and other items penetrating membranes are flashed or made watertight as required. (7) Ensure membrane lapping details are understood. (8) No work proceeds during damp weather. to be present between layers. Allow no moisture (9) Stand roll roofing on end and keep free of moisture and earth. Protection/covering for roofing materials should be vented so condensation will not occur. (10) Felts are applied as required. Broom and laid so that each layer is free of air pockets, wrinkles and buckles. Do not allow “flopping” of roofing felts. (11) All sheet metal and roof accessories are in place or on hand as required, to be installed in conjunction with roofing. (12) Felts for asphalt bitumen are asphalt-saturated; felts for tar pitch are coal tar-saturated. (13) Under no condition allow exposure of insulation or organic overnight without mopping. (14) Aggregates spread over flood coat of quantity required, while pitch or asphalt is hot. (15) Cap sheet is utilized, is of weight, finish and color 7 Enclosure (5) Quality Control Checklist Examples as required. (16) Operations are done in a neat and workman like manner so as not to damage adjoining areas. b. Insulation (1) Method of installing over surface is as required. (2) Wood nailers/stops are provided and installed in accordance with the drawings. (3) Joints are staggered. (4) Insulation is installed in conjunction with roofing felts and sealed in for the night. (5) Runway over the insulation are required to support mechanical or heavy equipment. (6) Insulation remains dry until covered by roofing. c. Flashing (1) Isolation provisions are made for dissimilar metals. Do not allow copper and aluminum flashing to be in contact with each other or with ferrous metal. (2) Flashing does not interfere with structural requirements. (3) Generally see that the metal is lapped a minimum of four (4) inches. (4) All edge metal laps are coated with plastic cement on horizontal flange and vertical rise. Coating covers entire lap and is sandwiched between. (5) Lengths of flashing are as long as possible. (6) Installation is coordinated with roofing installation. (7) Flashing is embedded in roof membrane assembly. (8) Method of anchoring lower edge of fascia is as required; observe alignment, stiffness, etc. (9) Gravel stops are pitched to provide for drainage. (10) Gutters are pitched to provide for drainage. 8 Enclosure (5) Quality Control Checklist Examples (11) Gutter and downspout joints are lapped in direction of flow. (12) Gutter and downspouts are installed plumb. (13) Base flashing extends up sufficiently; flange is embedded at least four (4) inches in roofing membrane. (14) Cap flashings are installed to provide secure anchorage, allow movement and have sufficient laps and spacing. (15) Review drawings and specifications for sheet-metal items called for in one and not the other. 6. Doors and Windows a. Doors (1) Doors are approved-size, type design, etc., and have no defects such as dents, buckles, and warps. (2) Additional reinforcement is provided for hardware. (3) Fire rated doors have labels and proper identification. Keep free of paint or stain. (4) Observe installation and verify proper clearances provided. (5) Doors function smoothly and easily and hardware is properly adjusted. (6) Factory prime is retouched; factory finish is not damaged and surfaces are adequate to receive applied finish. (7) Doors are cleaned. Report all doors that cannot be properly cleaned. Protection is provided as required to avoid marring and other damage. (8) Proper type and number of anchors for frames are provided; verify adequate anchorage is made during installation. (9) Frames are grouted during installation if required and caulked if required. (10) Frames are installed straight, level, and plumb and adequately braced where “built in”. b. Windows 9 Enclosure (5) Quality Control Checklist Examples (1) Delivered windows are of type, size, finish, operation, etc., as required. (2) Windows are properly stored until installed. (3) Special items are furnished, such as bolts, pull down hooks, trim, etc. (4) Required type of glazing beads or stops are provided and are suitable to receive glass thickness. (5) Windows are set plumb, square, and level in alignment. (6) Windows have provision for suitable anchorage and it’s provided during installation, windows are adequately braced where built in. (7) Finish is protected and maintained during and after installation. (8) Windows are installed to be weather tight. (9) Dissimilar metals are isolated. (10) Windows are properly adjusted for operation before glazing. (11) Cleaning of metal and glass is properly performed. (12) Screens of type, mesh and size are provided. c. Hardware and Specialties (1) Hardware is installed in accordance with manufacturer’s templates and instructions. (2) Finishes are as required and finishes match in each area. (3) Hardware is removed and/or protected during painting and cleaning operations. (4) Recommended order or inspection: a. In storage room before installation. b. Door butts and hinges during and after installation. c. Door closers after installation. 10 Enclosure (5) Quality Control Checklist Examples d. Doorstops, holders and push, pull, and kick-plates after installation. (5) Mortise-type hinges are mortised flush. (6) Lock-set cylinder cores are installed with tumbles up. (7) Observe operation of closers as soon as possible after installation for proper operation, silent closing and smooth operation. Panic devices latch properly. (8) Closers are adjusted after air moving system is operational. (9) Every door is provided with a doorstop to protect doors, walls and hardware. (10) All hardware is complete and with required type number of screws, bolts and fastening devices properly installed. 7. and Finishes a. Gypsum Drywall (1) Stud spacing is as required. Studs are doubled-up at jambs. Nailers/sleepers are in place. (2) Studs are securely anchored to walls and columns and fastened to securely anchored floor plates. (3) Location, layout and plumb of framing system is verified. (4) Metal studs are secured with proper fasteners. Washers will be used for bottom plate and cuts are properly painted before gypsum is hung. (5) Wood materials are sufficiently dry to avoid “nail popping” due to shrinkage. (6) Wallboard type, thickness and length are as required. Verify if horizontal or vertical application is to be required. (7) Wallboard is not erected until building is closed in. (8) Wallboard is held up from floor 3/8 inch minimum. (9) Wallboard is installed with staggered application. (10) Nailing/screwing or fastening performed as required. 11 Enclosure (5) Quality Control Checklist Examples Begin nailing from center outward, paper surfaces not broken, sheets not driven together, etc. (11) Check for excessive piercing or jointing. (12) Tapping system is as required; observe number of coats, feathering out 12” to 16”, check for high spots and dimples. b. Tile (1) Wall tile is set straight, plumb, perpendicular and with uniform joints. Design is per plan/spec. (2) Accessories are provided and firmly anchored. (3) Walls are installed before floors. (4) Floor tile slopes to drains. (5) Proper type of grout and/or sealant is used. (6) Tile/grout coloration is consistent. (7) Proper trim shapes are provided and used as required. (8) Tile pattern is correct as per plan/spec. (9) Layout starting points are correct. c. Suspended Ceiling Systems (1) Layout of system is coordinated with rates and work crews to allow adequate workspace and avoid interference. (2) Hangers are of proper material and spacing. (3) Perimeter and edge conditions are provided and installed as required. Joint treatment is consistent. (4) System is installed and adjusted in true alignment, even and level. (5) If more than one lot of tile is used for one area, ensure tiles are taken from several packages for random distribution. d. Resilient Flooring (1) Type, size, thickness, pattern, and color of materials are as required. 12 Enclosure (5) Quality Control Checklist Examples (2) Primer, adhesive, or cement is as required. (3) On slabs, surface is free of cracks, holes, trowel marks, and other defects. Surface primed if required. (4) On slabs, all patching, grinding and correction of defects is performed before installation. All areas are clean, dry, and hard. (5) Floor material is installed in proper sequence to minimize damage by other crews. (6) Direction of tile is as specified. Layout is as specified, allow ½ tile minimum at border. (7) Joints and seams are tight and level. (8) Excess adhesive material and stains are removed immediately after installation. (9) Temporary protective cover is provided if required. e. Painting (1) Color schedule is complete and understood. (2) Surface to receive paint is dry. Damp (not wet) surfaces are allowed for water thinned paints. (3) Surfaces to receive paint are properly prepared. Holes filled and sanded, pitch pockets and knots sealed. (4) Protection for adjacent areas, surfaces and items are provided. (5) Required number of coats is provided. (6) Texture and method of application is understood. (7) Painting is done in a neat and workmanlike manner. (8) No runs, drops, brush marks, color variation, etc. are permitted. (9) Curing time between coats is provided. (10) Hard to get at places are painted. f. Cabinets (1) Blocking is provided during framing to mount cabinets. 13 Enclosure (5) Quality Control Checklist Examples (2) Visually inspect product for correct finish. (3) Doors are properly fitted. Countertops are per finish schedule. 14 Enclosure (5) Unit ?? PREPARATORY PHASE CHECKLIST (CONTINUED ON SECOND PAGE) Project No. Definable Feature of Work: Personnel Present Name Specification Section: Date: Schedule Activity No. Index No. Position Company Material Storage Submittals Review submittals and/or submittal register. Have all submittals been approved? Yes Are all materials on hand? Yes No If no, what items are missing? Check approved submittals against delivered material. Comments: (This should be done as material arrives.) Do materials on hand meet contract drawings and specifications? YES discrepancies are present? Are materials stored properly? Yes No NO If no, what If no, what action is taken? Are necessary tools on hand to complete activity? Yes Tools No If no, what items have not been submitted? No If no, what action is taken? Is working condition of tools adequate to complete activity? Yes No If no, what action is taken? Specifications Review each paragraph of specifications. Discuss procedure for accomplishing the work. Preliminary Work & Permits Clarify any differences. Ensure preliminary work is correct and permits are on file. If not, what actions are taken? N/A Enclosure (6) UNIT ?? PREPARATORY PHASE CHECKLIST (CONTINUED FROM FIRST PAGE) DEFINABLE FEATURE OF WORK CONTRACT NO SPEC SECTION DATE SCHEDULE ACT NO. INDEX # IDENTIFY TEST TO BE PERFORMED, FREQUENCY, AND BY WHOM. TESTING WHEN REQUIRED? WHERE REQUIRED? REVIEW TESTING PLAN. HAS TEST FACILITIES BEEN APPROVED? ACTIVITY HAZARD ANALYSIS APPROVED? YES NO SAFETY REVIEW APPLICABLE PORTION OF EM 385-1-1. MEETING COMMENTS NAVY PWD/ROICC COMMENTS DURING MEETING. OTHER ITEMS OR REMARKS OTHER ITEMS OR REMARKS: QC MANAGER DATE 2 Enclosure (6) INITIAL PHASE CHECKLIST PRELIMINARY WORK PROCEDURE COMPLIANCE PERSONNEL PRESENT CONTRACT NO DEFINABLE FEATURE OF WORK GOVERNMENT REP NOTIFIED______ HOURS IN ADVANCE YES NO NAME POSITION COMPANY/GOVERNMENT IDENTIFY FULL COMPLIANCE WITH PROCEDURES IDENTIFIED AT PREPARATORY, COORDINATE PLANS,SPECIFICATIONS, AND SUBMITTALS. COMMENTS: ENSURE PRELIMINARY WORK IS COMPLETE AND CORRECT. IF NOT WHAT ACTION IS TAKEN? SOLUTI ON WORKMANSHIP ESTABLISH LEVEL OF WORKMANSHIP. IS SAMPLE PANEL REQUIRED? YES BE CONSIDERED AS A SAMPLE? YES WHERE IS WORK LOCATED? NO NO WILL THE INITIAL WORK (IF YES, MAINTAIN IN PRESENT CONDITION AS LONG AS POSSIBLE AND DESCRIBE LOCATION OF SAMPLE) RESOLVE ANY DIFFERENCES. COMMENTS: REVIEW JOB CONDITIONS USING EM 385-1 AND JOB HAZARD ANALYSIS OTHER CHECK SAFETY COMMENTS: OTHER ITEMS OR REMARKS Enclosure (7) Route to Initial Date Remarks S3 DAILY S3C S3QC QUALITY CONTROL 00S Prime INSPECTOR’S REPORT Date: Time: Project No.: Prime Co.: Project Title: Sub Co.: Weather: Supervisor: Activity Sub Report No.: Inspector: Rate Description of work performed Activities Started: QC Meetings Held: Activities Completed: Yes No Construction Inspection Plan Items Checked: Results: Delays Safety Hazards Present: Remarks Materials On behalf of the government I certify that all work is IAW the drawings and specifications. Project Supervisor Dist: 1. ROICC/FEAD 2. QC File via S3 Quality Control Inspector 3. Prime Contractor Quality Control Branch Head 4. Crewleader Enclosure (8) The following explanation and information is provided for completion of the Quality Control Report. a. Date: Self-explanatory. b. Time: Self-explanatory. c. Inspector: The name and rate (or rank) of the individual filling out the report. d. Report Number: Start and maintain a numerical system for each project. If two or more visits are conducted in one day’s time, fill out a report and number each time an inspection is made. e.Project Supervisor: This will be the job supervisor, the person directly responsible for the particular project. f. Project Number: Self-explanatory. g. Project Title and Location: Self-explanatory. h. Prime Company: This is the company assigned as the prime contractor. In the case of Det/DFT, the Det/DFT is the prime contractor. i. Sub Company: Self-explanatory. j. Weather Conditions: Self-explanatory. k. Preparatory Section: Lists Construction Activity Number and Definable Feature Of Work (DFOW) of Preparatory Phase activities started on this days report. l. Initial Section: Lists Construction Activity Number and Definable Feature of Work (DFOW) of Initial Phase activities started on this days report. m. Follow-Up Section: Lists Construction Activity Numbers, Description of Work performed for Follow-Up phases of each Definable Feature of Work to include specifications references, locations, etc. n. Material Received Section: Material received since last QC inspection only. The construction inspector has the responsibility of checking on-site materials. A remark will be made in this block about material compliance with plans and specifications, proper stowage, protection from the elements, etc. If a substitution is made, a statement is required regarding the circumstances leading to the substitution and the authority for making the substitution. o. Delays/Safety Hazards Present: Anything that creates a delay to the scheduled completion of the project should be recorded here, such as inclement weather, transportation of materials, equipment breakdowns, etc. List specific safety hazards that require correction. p. Remarks: This is the catch-all-block. Record the Construction Activity Number, Crew Members assigned to the activity and the description of work performed. Any item of particular interest is recorded here. In this block, tell how it is being done, site conditions, job conditions, quality of work (good, bad, acceptable), and any items found unsatisfactory. Briefly explain what action was taken or will be taken to correct the deficiencies. 2 Enclosure (8) q. Description of Work Performed: Do not write down the name of the construction activity, give the actual description of the work that is being performed (i.e. hanging drywall, taping drywall, applying finish coat of compound to drywall, etc.). r. Percent Complete: Previous WIP% complete and Current WIP% complete for the construction activity as reported to the prime company on project SITREP. s. Signatures: Self-explanatory t. Routing Block: This area of the QC Report is designated for internal battalion routing comments as well as ROICC Quality Assurance Representative remarks. 3 Enclosure (8) Enclosure (9) FAR Number: FIELD ADJUSTMENT REQUEST (FAR) Page_______ of_______ Project Number: Project Title: Submitted By: Date: Description of and reason for request: (include drawing and sheet numbers and attach drawings as necessary for description) Route Approved:(In Disapproved:(I Date: Estimated Additional Cost: to: itial) nitial) Prime Co. QC Estimated Additional Mandays: Eng. S3 ROICC As Built:____________Date:_____ ROICC (Initial) Signature:__________________________________ ______ ______ Notes: 1. Route original and 3 copies to ROICC. 2. ROICC returns original and 2 copies. Enclosure (11) LIST OF DEFINABLE FEATURES OF WORK (DFOW) SPEC SECTION SCHEDULE ACTIVITY ID 16200 09220 09800 09810 10600 10610 16700 15110 08200 09700 09710 DESCRIPTION Rough Electrical Hang Drywall Unit 4 Apply Text Coat Unit 3 Apply Text Coat Unit 4 Install Cabinets Unit 3 Install Cabinets Unit 4 Finish Electrical Finish Plumbing Install Doors and Closets Install Laminate Flooring Unit 3 Install Laminate Flooring Unit 4 PREPARATORY MEETING DATE PLANNED 22JAN09 ACTUAL 22JAN09 INITIALS INITIAL MEETING DATE PLANNED 23JAN09 30JAN09 ACTUAL 23JAN09 22JAN09 INITIALS Enclosure (12) From: To: Commanding Officer, U. S. Naval Mobile Construction Battalion XXXX Commander XXXXXXX Naval Construction Regiment Subj: DISPOSITION OF PROJECT DOCUMENTATION ICO (Enter project number and title) Ref: (a) COMFIRSTNCDINST 4355.1A 1. The subject project was completed (Enter Completion Date) and the prescribed project package archive period has elapsed. In accordance with reference (a), request disposition guidance for the project documentation. 2. XXXXXXXX is the command point of contact and can be reached at XXXXXXXXX. J. R. WAYNE Copy to: S3 R3 Enclosure (13)