ALICE EMCal Preliminary Project Execution Plan at Lawrence Berkeley National Laboratory Berkeley, CA For the U.S. Department of Energy Office of Science Office of Nuclear Physics (SC-26) MIE-HILHC Document # EMCal.4.1.v0 December 2006 ALICE EMCal Project Execution Plan CONCURRENCES: Thomas M. Cormier ALICE EMCal Contractor Project Manager Date James Symons Director, Nuclear Science Division Lawrence Berkeley National Laboratory Date Barry Savnik ALICE EMCal Federal Project Director DOE Berkeley Site Office Date Aundra Richards Manager DOE Berkeley Site Office Date Jehanne Simon-Gillo Director Facilities and Project Management Division, Office of Nuclear Physics Date _________________________________________ Daniel R. Lehman Director Office of Project Assessment, Office of Science Date APPROVED: Dennis G. Kovar Associate Director of the Office of Science for Nuclear Physics Date 2 ALICE EMCal Project Execution Plan Table of Contents I. II. III. IV. V. VI. VII. VIII. IX. X. Introduction Mission Need Functional Requirements Project Overview Technical Scope and Deliverables Alternative Analysis Management Organization Schedule and Cost Scope Change Control Analyses, Assessments, and Plans 4 4 5 6 8 9 10 20 27 28 Appendix A – ALICE EMCal WBS Dictionary 3 33 ALICE EMCal Project Execution Plan I. Introduction The Large Hadron Collider (LHC) at the European Laboratory for Particle Physics (CERN) in Geneva, Switzerland will open a new high-energy frontier in the physics of ultra high-density hadronic matter and the Quark Gluon Plasma (QGP). The ALICEUSA Collaboration1 through Lawrence Berkeley National Laboratory (LBNL) has proposed a Major Item of Equipment (MIE) for the Department of Energy (DOE) Office of Nuclear Physics to fabricate a large electromagnetic calorimeter (ALICE EMCal) as an upgrade to the ALICE experiment at the LHC. Over the past several years, the collaboration has carried out pre-conceptual research and development (R&D) and has identified the technology needed to build a large electromagnetic calorimeter capable of addressing the physics requirements within the structure of the ALICE experimental infrastructure. The Mission Need (Critical Decision – 0) for a U.S. involvement in the LHC heavy ion program was approved by the DOE Office of Science on November 16, 2005. The total project cost (TPC) range of the ALICE EMCal has been refined from $5 – 16 million approved at CD-0, to $13 – 16 million proposed at CD-1. The TPC is currently estimated at $13.295 million. R&D is supported in fiscal year (FY) 2006 and completed in FY 2007. Project fabrication will start in FY 2007 and complete in FY 2011. This preliminary Project Execution Plan (PPEP) describes the coordination of efforts of the project team, including the processes and procedures used by the ALICE EMCal contractor project manager (CPM) and Federal Project Director (FPD) to ensure that the project is completed on time and within budget. The PPEP defines the preliminary project scope consistent with the assumed funding profile and organizational framework, identifies roles and responsibilities of contributors, and presents the work breakdown structure (WBS) and schedule under the assumed funding profile. The PPEP also describes the formal change control process by which project cost, schedule, or scope may be revised with appropriate review and approval by the FPD and the DOE Office of Science, Office of Nuclear Physics. II. Mission Need The mission of the Nuclear Physics (NP) program is to understand the evolution and structure of nuclear matter from the smallest building blocks, quarks and gluons, to the elements in the universe created by stars. A main objective of this nuclear science field is searching for the QGP and other new phenomena that might occur in extremely hot, dense plasma of quarks and gluons believed to have filled the universe about a millionth of a second after the “Big Bang.” The program provides world-class peer-reviewed research results in the scientific disciplines encompassed by the Nuclear Physics mission areas under the mandate provided in Public Law 95-91 that established the Department. The ALICE EMCal project directly supports the NP mission and will allow U.S. researchers to explore fundamental questions into the nature of the QGP which cannot be 1 ALICE-USA is a group of 13 U.S. institutions, National Laboratories and Universities that are participating in the fabrication and utilization of the proposed EM Calorimeter as members of the ALICE experiment at the LHC. 4 ALICE EMCal Project Execution Plan examined with any other experimental facility worldwide. In particular, the ALICE experiment in conjunction with the U.S. built calorimeter will complement and extend the ongoing investigations at the Relativistic Heavy Ion Collider (RHIC), currently the DOE’s flagship facility in this field. The most recent Nuclear Science Advisory Committee (NSAC) Long Range Plan recommended that the U.S. heavy ion community participate in the LHC heavy ion program with a focused effort which complements the RHIC program. Specifically, the plan recommended that the program focus on the measurement of probes produced in hard processes. Hard processes will play a dominant role in collisions at the much greater collision energy (s) of the LHC, and the ALICE EMCal would be the primary instrument within the ALICE experiment for the exploration of these hard processes. The scientific concept that requires the addition of an electromagnetic calorimeter to the ALICE experiment has been thoroughly vetted in a long series of lower energy measurements in experiments at RHIC. In these experiments, electromagnetic calorimetry combined with precision tracking of charged hadrons has become the primary method to trigger on and study hard probes in relativistic heavy ion collisions at RHIC. In its recent sub-committee study “U.S. Program in Heavy Ion Nuclear Physics: Scientific Opportunities and Research Requirements”, the NSAC concluded that: “The developing LHC facility at CERN offers outstanding opportunities for new discoveries in relativistic heavy ion physics, driven by the large increase in center of mass energy, which generates different initial conditions and a larger kinematic reach for hard probes.” III. Functional Requirements The ALICE EMCal project must deliver an electromagnetic calorimeter with acceptance sufficient2 for jet reconstruction in central PbPb collisions and an energy resolution and an electromagnetic shower shape determination sufficient for discrimination to PT ~ 30 GeV/c in central PbPb collisions. These are the most crucial considerations that the detector design must meet for the ALICE-USA physics program. The primary detector design goal is to preserve these latter parameters at the lowest possible cost. The corresponding technical scope and performance specifications required at Critical Decision-4 (CD-4) are described in Table V.2 and V.3 respectively. Summarizing from the ALICE EMCal Requirements Document, the system parameters desired from the ALICE EMCal are as follows: 1. Large effective acceptance for jets with analysis cones up to radii R=0.5. This is satisfied by a detector spanning 110 degrees in azimuth and 1.4 units of pseudo rapidity. 2. A photon or electron energy resolution better than or equal to = 15%/ E 2% averaged over the full detector acceptance at energies above 2 GeV and less than 100 GeV. At this resolution, the ALICE EMCal energy measurement for electrons is comparable to or better than the ALICE tracking system momentum measurement. 2 i.e. An acceptance sufficient to provide adequate statistics to permit fragmentation function reconstruction for single inclusive jets with PT through ~ 150 GeV/c 5 ALICE EMCal Project Execution Plan 3. A detector granularity and analog noise sufficient for good discrimination in central PbPb collisions out to transverse momenta of ~30 GeV/c IV. Project Overview The EMCal is a joint U.S./French/Italian project. The detector can accommodate up to eleven detector modules or “super modules”, of which eight are included in the scope of this DOE project. The U.S. is responsible for managing the ALICE EMCal project. The DOE deliverables are discussed in detail below in section V. Briefly, the DOE MIE will provide approximately 73% of the full detector acceptance (80 degrees in azimuth or 8 of the 11 supermodules) and produce a completely functional detector suitable to address the ALICE-USA physics goals. The technical activities within the MIE project may be divided into two main areas: (1) R&D and (2) Detector fabrication, integration, calibration and test. IV.1 R&D A substantial program of pre-conceptual R&D was completed prior to CD-0 and R&D has continued through the interval between CD-0 and CD-1. The objective of the R&D was to explore detector technology options and study detector performance for these technology alternatives. Prior to CD-0, an approximately 0.5m x 0.5m prototype was operated in a test beam at Fermilab to explore operational features of the preferred mechanical/optical technology. The results of the test strongly supported the basic conceptual design and only minor revisions in the mechanical and optical design were necessary. During the first full year of the MIE, R&D efforts are continued with the completion of another small prototype built from modules of the final design followed by a second test beam experiment. The goal of this second test beam will be to establish the operational characteristics of these modules, so that further progress can be made on software and simulation effort, and to demonstrate integration with ALICE online and data acquisition (DAQ) in a full systems test under realistic conditions with beam. IV.2 Construction In the following sections, the major systems and activities in the construction phase of the project are summarized. IV.2.1 Detector Modules and Super Modules Design and Fabrication The full acceptance electromagnetic calorimeter consists of a barrel section providing coverage for a 110o arc in azimuth and 1.4 units of pseudo rapidity along the beam direction (Figure I.1). The full coverage is built up from effectively 11 separate “super modules” spanning this acceptance. Each super module, which is the detector building block handled at installation time, thus corresponds to approximately 1/11 or 9% of the total detector area. As discussed in detail in section V., the U.S. DOE scope comprises 8 of these 11 super modules. Each super module is finely segmented into individual energy measuring channels called “towers”. There are a total of 12,672 separate towers in the full detector. Each of these 6 ALICE EMCal Project Execution Plan towers is a basic detection sensor of the detector capable of high resolution measurements of electromagnetic energy. Figure I.1 The conceptual layout of the full ALICEEMCal on its support structure IV.2.2 Electronics Electromagnetic energy deposition in the towers produces scintillation light which is transported over optical fibers within the tower to a 5mm x5mm Avalanche PhotoDiode (APD) which converts scintillation light into the electrical signal from the tower. A charge sensitive preamplifier is integrated directly to each APD. These electrical signals are sampled 4 - 5 times in a flash Analog-to-Digital Converter (ADC) on the front end electronics boards (FEE) and passed through a readout control unit (RCU) to data acquisition (DAQ). In parallel, the detector reads out to a trigger processor (TRU) which forms sliding 2x2 tower sums for electromagnetic triggers and to a patch trigger processor for jet triggers. The electronics associated with each detector super module resides in a water cooled crate mechanically attached to the super module and electrically cabled to each tower of the super module. Each of the super modules will include the associated electronics described here. Information from the ALICE EMCal readout electronics is transmitted directly in digital format to ALICE DAQ over optical fibers originating on the RCUs. DAQ software and hardware for the ALICE EMCal are the responsibility of the ALICE project. The ALICE DAQ is responsible for processing and storage of ALICE EMCal generated data. The ALICE EMCal project is required only to satisfy the interface specifications of the DAQ receiver boards and high level trigger (HLT) hardware. 7 ALICE EMCal Project Execution Plan V. Technical Scope and Deliverables The DOE technical scope and deliverables associated with the ALICE EMCal project are described in this section. The ALICE EMCal MIE project will be complete when all DOE deliverables have been received, tested and assembled at the ALICE detector site at CERN. The scope includes the installation of one super module into the ALICE detector, and its operation as described in the preliminary CD-4 performance specifications given below. Limiting the scope to the installation of only the first super module, largely decouples the project schedule from the CERN/LHC run schedule which is beyond the control of the project. The scope as described below produces a fully functional electromagnetic calorimeter capable of addressing the essential features of the ALICEUSA physics program with an acceptance equal to 8/11th of the full acceptance discussed in section IV.2. The scope associated with a single super module is: o o o o o 288 single modules with calibration light source, each with: 1,152 Towers with one S8664-55 APD 1 Water cooled FEE crate with LV power and control 1,152 HV Channels with control 1,152 FEE digitization and readout channels through 1 readout control unit (included in project scope) o 288 EM trigger channels through 3 trigger region units (TRU) (included in project scope) o 1 readout channel to jet patch trigger board (included in project scope) o 1 connection to the detector control system (DCS) The U.S. project scope is: o Eight functional Super Modules subjected to integrated systems testing and precalibrated with cosmic rays, delivered to ALICE at the LHC Point-2 site and ready for installation. o All mechanical systems required to handle and install super modules into the ALICE experiment and the associated system integration activities including mechanical support, cooling, power distribution, cable trays and all conventional systems required for EMCal operation in ALICE. o Installation and operation in an LHC run of the first super module. The French and Italian project responsibilities and contributions to this MIE are currently under negotiation and will be finalized prior to CD-2. At this point, it is envisioned that the French will contribute substantially to mechanical design, hardware associated with installation and the jet trigger while the Italians will contribute to mechanical design and to hardware associated with super module structure. In addition, the French and Italians will independently fabricate an additional three EMCal super modules outside the scope of this project. The preliminary performance specifications required at CD-4 are described below. These will be updated as necessary at CD-2. 8 ALICE EMCal Project Execution Plan All absolute gain curves for all APD’s in all 8 functional super modules will be determined to a precision of < 5% (RMS) for gains resulting in applied HV in the range of 0 to 400V. This requirement guarantees that gains can be efficiently adjusted during calibrations and initial trigger settings can be made at the first run start-up. o All towers and readout channels of all eight functional super modules will have an absolute energy pre-calibration to the precision of <10% using cosmic rays. This cosmic ray calibration will be transferred to the LED system to allow rapid absolute gain setting and monitoring at startup. This requirement guarantees that initial run data will be sufficiently calibrated to permit initial reconstruction of electrons and s required to begin the calibration bootstrap process. o One super module will be installed and fully integrated into the ALICE detector and have participated in LHC running. Analysis of actual run data will demonstrate a global energy calibration precise to <2% and a Gaussian energy resolution better than = 15%/ E 2%. The CD-4 criteria given above are sufficient to meet the goals of the ALICE-USA physics program and satisfy the specifications of the ALICE EMCal requirements that the ultimate performance of the detector will document. It is anticipated, however, exceed its CD-4 acceptance criteria. The ultimate performance is expected to be reached after the complete analysis of one full ALICE-year of running with the full complement of 8 super modules installed and is described below. It is anticipated that this performance could be achieved approximately 2 years after project complete. o All absolute gain curves for all APD’s in all 8 functional super modules will be determined to a precision of 2% (RMS). This precision allows adjustment of individual tower gains to a level better than required for trigger thresholds and where they have negligible effect on the global detector resolution. channels of all eight functional super modules will have an o All towers and readout absolute energy calibration to the precision of <2% using tracked conversion electrons, , J/ e+e- and other calibration standards. It is estimated that the ultimate precision of the energy calibration of the detector will approach ~1% after a few years of running but <2% will be achieved in the first year. o The full complement of 8 super modules will have been fully integrated into the ALICE detector and have participated in LHC running. Analysis of actual run data will demonstrate a global energy calibration precise to <2% and a Gaussian energy resolution better than = 12%/ E 1.7%. VI. Alternative Analysis One of the considered alternatives is to not proceed with the fabrication of the EMCal. This alternative has a number of significant negative impacts, however. The EMCal is essential to the execution of a successful jet physics program at the LHC and the maintenance of U.S. leadership of this important extension of RHIC physics into the new 9 ALICE EMCal Project Execution Plan energy domain that opens at the LHC. The U.S pioneered the use of hard probes including jets in the Solenoidal Tracker at RHIC (STAR) and the Pioneering High Energy Nuclear Interaction eXperiment (PHENIX) at RHIC as a tool to diagnose the properties of the QGP. These studies have been the centerpiece of the discoveries that have come from RHIC and without the EMCal in ALICE the U.S will have minimal presence in this important new discovery opportunity at the LHC. Substantial R&D and pre conceptual design studies over the past several years were carried out and the detector technology needed to satisfy the ALICE-USA physics requirements was identified. A prototype detector was assembled and tested in beam to allow a critical evaluation of performance parameters. During this process a number of alternatives in detector design were considered including both scintillation and Cerenkov crystal and scintillator/Pb tile-fiber sampling calorimeters. Based on performance, integration considerations, and cost, the current design, as described above, has been chosen. Manufacturing studies were also undertaken to establish “proof of principle” mass production techniques in the key areas of detector manufacturing and electronics. The concept of the present moderate resolution, large acceptance, “shashlik” sampling electromagnetic calorimeter has emerged from this R&D. The ALICE-USA Collaboration at large has reviewed the conceptual design and the associated requirements document http://rnc.lbl.gov/nsd/alice_review06/alice_rev_docs2006.htm (Appendix A) and endorses the current concept. Lastly, alternative total detector acceptances were considered. The acceptance of the calorimeter, effectively its net surface area, has a stronger than linear bearing on the scope of the proposed physics program. This results because the objects of primary interest, hadronic jets, are finite size objects with a cone-like topology that requires a well defined minimum detector surface area before the detection efficiency rises above zero. For example, simulations show that the detection efficiency for jets of dimensionless radius R=0.5 rises by approximately a factor of nine between 6 super modules and 8 super modules. Jets of smaller radii exhibit less dramatic dependence on the detector acceptance but the qualitative result remains – even a relatively minor reduction in the active surface area of the detector significantly reduces the effective jet efficiency and therefore the impact of the U.S. program in ALICE. Therefore, there is significant benefit to increasing the technical scope to 8 super modules to be integrated into ALICE. VII. Management Organization This section discusses the project management structure and practices governing detector design, fabrication. VII.1 Project Management Responsibilities This draft document provides the proposed management organization and delineates responsibilities within the ALICE EMCal construction project. Figure VII.1 shows the management organizational chart. VII.1.1 Department of Energy 10 ALICE EMCal Project Execution Plan Within DOE’s Office of Science (SC), the Office of Nuclear Physics (NP) has overall responsibility for the ALICE Electromagnetic Calorimeter (EMCal). The Acquisition Executive (AE) is Dennis Kovar, Associate Director of the Office of Science for Nuclear Physics (SC-26). As such, he has full responsibility for project planning and execution, and for establishing broad policies and requirements for achieving project goals. Specific responsibilities for the ALICE EMCal project include: Responsibilities: The ALICE EMCal Acquisition Executive responsibilities include: Chairs the Energy Systems Acquisition Advisory Board (ESAAB) Equivalent Board. Approves Critical Decisions and Level 1 baseline changes. Approves the Project Execution Plan. Conducts Quarterly Project Reviews. Ensures independent project reviews are conducted. The ALICE EMCal Program Manager is Jehanne Simon-Gillo, Director of the Facilities and Project Management Division in the Office of Nuclear Physics. The Division (SC-26.2) is responsible for planning and constructing instrumentation to provide special scientific and research capabilities to serve the needs of U.S. universities, industry, and private and Federal laboratories. Within NP, the Facilities and Project Management Division has direct responsibility for providing funding, and programmatic guidance to the ALICE EMCal project. Responsibilities: The ALICE EMCal Program Manager responsibilities include: Provides programmatic direction for ALICE EMCal via the Federal Project Director. Functions as DOE headquarters point-of-contact for MIE matters. Oversees MIE progress and organizes reviews as necessary. Prepares, defends, and provides project budget with support from the field organizations. Reviews and provides recommendations to the AE on Level 1 baseline changes. Controls other changes to MIE baselines in accordance with the PEP. Monitors Critical Decision, Level 1 and 2 technical, cost, and schedule milestones. Participates in Quarterly Reviews, ESAAB Equivalent Board meetings, and project reviews. Ensures ES&H requirements are implemented by the project. Coordinates with other SC Staff offices, HQ program offices and the DOE Office of Engineering and Construction Management (OECM). 11 ALICE EMCal Project Execution Plan Barry Savnik has been assigned as the Federal Project Director at the Berkeley Site Office (BSO). Responsibilities: The Federal Project Director responsibilities include: Overall responsibility for planning, implementing, and completing ALICE EMCal. Provides overall MIE management oversight. Issues work authorization. Provides necessary funds via approved financial plans. Manages and allocates the contingency funds according to the procedure defined in the Baseline Change Control. Chairs the BSO Baseline Change Control Board (BCCB), and approves Level 2 Baseline Changes. Submits project documents and critical decisions to DOE and reports project progress. Ensures that the MIE complies with applicable environment, safety and health (ES&H) requirements (e.g. National Environmental Policy Act [NEPA] requirements) 12 ALICE EMCal Project Execution Plan VII.1.2 Host Laboratory and Director of the Nuclear Science Division Office of Nuclear Physics D. Kovar (Acquisition Executive) J. Simon-Gillo (ALICE EMCal Program Manager) DOE Contracting Officer M. Robles Integrated Project Team LBNL Site Office A. Richards (Manager) B. Savnik (Federal Project Director) Host Laboratory T.J. Symons, LBNL (Director Nuclear Science Division) EH&S ALICE EMCal EH&S Liaison L. Wahl (LBNL) ALICE-USA Collaboration Coordinator J. Harris, Yale ALICE Installation L. Leistam, CERN Conventional Systems Integration KumpumaekCERN Installation Infrastructure KumpumaekCERN Mechanical Integration and Design M. Dialinas, Nantes Support Structure Bercowitz, LBNL InstallationTooling Stutzmann,Subatech Module Riso, WSU Strip Module Carduner, Subatech Super Module Palmeri, Catania ALICE EMCal Project Management T.M. Cormier, LBNL/WSU (Contractor Project Manager) J. Rasson, LBNL (Deputy, Contractor Project Manager) P. Jacobs, LBNL (Deputy, Contractor Project Manager) Production J. Riso, WSU ALICE Management Board J. Schukraft, CERN ALICE EMCal Quality Assurance J. Rasson, LBNL (Acting) ALICE EMCal Project Controls D. Peterson, LBNL Electronics T. Awes, ORNL Mod. / Strip Mod. Mechanical/ Optical Assy./Test Petrov, WSU Fiber Systems Westfall, MSU APD Test/Integrate Margetis, KSU Super Module Assy./Calibrate Witt (Yale) Design Muller, CERN Trigger P. Jacobs, LBNL L1 Trigger Muller, CERN Bourrion, Grenoble Calibrate/Test Sorensen, Tenn. Conventional Systems ORNL, Catania Slow Controls Cherney, Creighton High Level Trigger Pavlinov, WSU Trigger Commission, TBD, LBNL On Line Silvermyr, ORNL Commission TBD, ORNL Figure VII.1 ALICE-EMCal Project management Organizational Chart 13 ALICE EMCal Project Execution Plan Host Laboratory: The Host Laboratory is defined as the lead laboratory that is fully responsible for the construction of ALICE EMCal and assumes fiscal responsibility for the MIE. LBNL will be the Host Laboratory during the R&D, construction and testing of ALICE EMCal and will be responsible for ensuring that the manpower and necessary infrastructure are provided. Director of the Nuclear Science Division at LBNL: Funding for this project will be directed through the LBNL Nuclear Science Division. Thus, ultimate fiscal and management Contractor responsibility for the fabrication of ALICE EMCal will reside with the Director of the Nuclear Science Division, James Symons. Responsibilities: The Director of the Nuclear Science Division at LBNL shall be administratively and fiscally responsible for the entire R&D effort and the MIE. In particular he/she must provide the following: Provides overall management oversight for all aspects of the MIE. Appoints the Contractor Project Manager. Approves key personnel appointments made by the Contractor Project Manager. Approves major subcontracts recommended by the Contractor Project Manager. Ensures that adequate staff and resources are available to complete ALICE EMCal in a timely and cost effective manner (within constraints of the funding provided by DOE). Ensures that ALICE EMCal has demonstrated that it meets the functional requirements. Provides documentation and access to information necessary for operation of ALICE EMCal at CERN. Ensures the work is performed safely and in compliance with the Integrated Safety Management (ISM) rules VII.1.3 Contractor Project Manager (CPM) The Director of the Nuclear Science Division at LBNL has appointed T.M.Cormier LBNL /Wayne State University (WSU) as the ALICE EMCal Contractor Project Manager. Responsibilities: The CPM shall report directly to the Director of the Nuclear Science Division at LBNL and will be in charge of the overall management of ALICE EMCal project. The CPM shall appoint the key staff needed for the MIE with the approval of the Director of the Nuclear Science Division at LBNL. The Contractor Project Manager also will have the following responsibilities: 14 ALICE EMCal Project Execution Plan Responsible and accountable for the successful execution of contractor’s MIE scope of ALICE EMCal. Supports Federal Project Director in implementing DOE project management process. Provides input on project documentation. Implements contractor performance measurement system. Delivers project deliverables as defined in this project execution plan. Identifies and ensures timely resolution of critical issues within contractor’s control. Responsible for ALICE EMCal functionality requirements Allocates the contingency funds according to the procedure defined in the Baseline Change Control Procedures. Acts as the spokesperson for the project to the DOE, the Host Laboratory, other ALICE-USA participating institutions, the ALICE Collaboration and the scientific community at large. Keeps the ALICE-USA Collaboration and the ALICE Collaboration informed on the status of the ALICE EMCal project by regular updates at collaboration meetings. Appoints the Deputy Contractor Project Managers with the concurrence of the Director of the Nuclear Science Division at LBNL Collaborates with the Director of the Nuclear Science Division at LBNL and Deputy Contractor Project Managers to assemble the staff and resources needed to complete the project. Advises the Director of the Nuclear Science Division at LBNL on the selection of non-host-site construction teams and sub-contractors and in defining the areas of collaboration and the relationship between LBNL and other institutions participating in ALICE EMCal through Memoranda of Understanding (MOU). Recommends major subcontracts to the Director of the Nuclear Science Division at LBNL for approval. Ensures the work is performed safely and in compliance with the ISM rules. Appoints the Quality Assurance Manager (QAM) in consultation with the Deputy Contractor Project Managers. Produces necessary ES&H documentation (e.g., Hazards Analysis Documents). Recommends baseline changes up to Level 2. VII.1.4 Deputy Contractor Project Managers The ALICE EMCal CPM, with the approval of the Director of the Nuclear Science Division at LBNL, has appointed two Deputy Contractor Project Managers: J. Rasson (LBNL) and Peter Jacobs (LBNL). The Deputy Contractor Project Managers will report to the CPM. The Deputy Contractor Project Managers support the function of the CPM by way of both shared and specific responsibilities. The following are responsibilities that the Deputy Contractor Project Managers share: 15 ALICE EMCal Project Execution Plan Shared Responsibilities: Under the direction of and by delegation from, the Contractor Project Manager, executes contractor’s MIE scope of ALICE EMCal, and supplies the deliverables on time and within budget. Collaborates with the Contractor Project Manager to assemble the staff and resources needed to complete ALICE EMCal. Collaborates with the Contractor Project Manager in the technical direction of ALICE EMCal project. Contributes to the preparation of regular reports and project reviews as required by DOE and LBNL. Collaborates with the Contractor Project manager to ensure that work is performed safely and in compliance with the ISM rules. Specific Responsibilities delegated individually to the Deputy Contractor Managers include but are not limited to: J. Rasson Responsibilities: Develops and maintains the ALICE EMCal documentation. Communicates the functional requirements to the subsystem managers Responsible for the development of the ALICE EMCal system design requirements, including interfaces between subsystems, and methods and practices for achieving these requirements. Controls changes in the ALICE EMCal system design requirements, including interfaces between subsystems. Responsible for overall engineering safety of project design Carries out monthly project review and reports results to the Contractor Project Manager. Participates in the preparation of project quarterly reports to the DOE. Supervises the LBNL staff of the ALICE EMCal project. Oversees the effort from other institutions participating in ALICE EMCal. Identifies and ensures timely resolution of critical issues within Deputy Contractor Project Manager’s control. Identifies and collaborates with the Contractor Project Manager in mitigating project risks. Maintains project files. Additional responsibilities as delegated by the Contractor Project Manager. P. Jacobs Responsibilities: Represents the project in discussions with the collaborations (see section VII.1.6) concerning physics requirements and functionality requirements as may arise in the change control process. Responsible for simulations that establish and support functionality requirements and CD-4 acceptance criteria. 16 ALICE EMCal Project Execution Plan Communicates the functional requirements and their relation to physics requirements to the ALICE-USA Collaboration Provides supervisory oversight in the preparation of the ALICE EMCal CDR, TDR and other major ALICE EMCal reports. Participates in the preparation of project quarterly reports to the DOE. Identifies and ensures timely resolution of critical issues within Deputy Contractor Project Manager’s control. Identifies and collaborates with the Contractor Project Manager in mitigating project risks. Additional responsibilities as delegated by the Contractor Project Manager VII.1.5 Subsystem Managers Separate ALICE EMCal Subsystem Managers are responsible for each of the five ALICE EMCal subsystems: ALICE Installation, Mechanical Design and Integration, Detector Fabrication, Electronics, Trigger and Computing Resources as shown in table VII.1. Table VII.1 ALICE EMCal subsystems and subsystem managers ALICE EMCal Subsystem Installation Mechanical Integration and Design Detector Production Electronics Trigger Subsystem Manager Lars Leistam (CERN) Manoel Dialinas (Nantes) Jose Riso (Wayne State) Terry Awes (ORNL) Peter Jacobs (LBNL) Subsystem Managers report directly to the CPM and will be responsible for the design, construction, installation, and testing of their respective subsystem, in consultation with the CPM and in accordance with the performance requirements, schedule, and budget. In particular, all subsystem managers have the following general responsibilities: Responsibilities Collaborates with the CPM and his Deputies to assemble the staff and resources needed to complete the subsystem. Communicates the system design requirements to the sub-system staff. Ensures that subsystems meet the ALICE EMCal system design requirements, including interfaces. Responsible for carrying out the design, construction and assembly of the subsystem in accordance with the scope, schedule and budget, assuming funding and resources as described in the PEP. Provides regular reports on the status of the subsystem to the Contractor Project Manager. Ensures the work is performed safely and in compliance with the ISM rules. In addition to these general responsibilities, the subsystem managers have the following specific responsibilities: 17 ALICE EMCal Project Execution Plan Installation The ALICE EMCal CPM has appointed Lars Leistam (CERN) as Subsystem Manager for ALICE EMCal Installation. Leistam is the ALICE Project Engineer and has oversight responsibility for all installation activities in ALICE and the and as such he is responsible for all ALICE EMCal installation and the associated installation tooling and infrastructure. As ALICE EMCal installation subsystem manager he oversees (1) implementation of ALICE EMCal conventional systems and services and their installation consistent with the overall ALICE integration plan and (2) all infrastructure associated with installation including Calframe, all supermodule handling and installation tooling and the physical installation of the first super module. Principal institutional participation in the installation subsystem is limited to CERN. Mechanical Design and Integration The ALICE EMCal CPM has appointed M. Dialinas (Nantes) subsystem manager for Mechanical Design and Integration. Dialinas has overall design and integration responsibility for the ALICE EMCal support structure (CalFrame), Super Module installation tooling, ALICE EMCal Module, Strip Module and Super Module. Principal institutional participation in Mechanical Design and Integration includes Nantes, LBNL, Subatech, Wayne State, and INFN Catania. Detector Fabrication The ALICE EMCal CPM has appointed J. Riso (WSU) subsystem manager for Detector Fabrication. Riso has overall responsibility for detector component procurement, construction and assembly including Module, Strip Modules and Super Modules as well as optical and photo sensor elements. Principal institutional participation in Detector Fabrication includes Wayne State, Michigan State, UCLA, Yale, University of Texas and University of Houston. Electronics The ALICE EMCal CPM has appointed T. Awes (ORNL) subsystem manager for Electronics. Awes has overall design, procurement, testing, installation and commissioning responsibility for ALICE EMCal beginning with the output connector of the APD charge-sensitive PreAmp through the full FEE system through optical cables to ALICE DAQ. Also included is responsibility for electronic conventional systems (LV, HV DC power, etc) and slow controls. Principal participating institutions include ORNL, CERN, University of Tennessee, INFN Catania, Creighton, UCLA and the University of Texas. Trigger The ALICE EMCal CPM has appointed P. Jacobs (LBNL) subsystem manager for the Trigger. Within the trigger subsystem, Jacobs has overall responsibility for design, procurement, testing and commissioning of the ALICE EMCalL1 trigger including the isolated electromagnetic cluster trigger and the jet patch trigger. Also included is 18 ALICE EMCal Project Execution Plan responsibility for the High Level (software) trigger. Principal participating institutions include LBNL, CERN, Grenoble, and Wayne State. VII.1.6 Quality Assurance Manager (QAM) J. Rasson (LBNL) will assume the duties of the interim QAM for the ALICE EMCal project until a permanent QAM can be appointed. Responsibilities: Collaborates with the CPM to ensure the quality of ALICE EMCal. Ensures that the quality control system is established, implemented, and maintained in accordance with the ALICE EMCal Quality Assurance Plan. Provides oversight and support to the partner labs and institutions to ensure a consistent quality program. VII.1.7 Integrated Project Team The composition of the ALICE EMCal Integrated Project Team (IPT) is given in Table VII.2. Its responsibilities are described in DOE Order 413.3A. The team plans to meet quarterly or as needed. The DOE FPD will chair the IPT. Table VII.2. ALICE EMCal Integrated Project Team DOE Federal Project Director LBNL/WSU Contractor Project Manager LBNL Deputy Contractor Project Manager LBNL Deputy Contractor Project Manager DOE Contracting Officer LBNL Contracting Officer LBNL ES&H Lead Lead/ALICE EMCal EH&S Liaison DOE EH&S Barry Savnik (chair) T.M Cormier J. Rasson P. Jacobs M. Robles E. Nasto L. Wahl J. Craven VII.1.8 Collaboration Liaisons Liaisons to the ALICE and ALICE-USA collaborations advise the CPM regarding the interests of these collaborations as the detector design, fabrication, and commissioning go forward. The Collaboration Liaisons work with their respective collaborations to monitor and assess project issues that have the potential to impact the ALICE EMCal physics performance. In particular, they are charged with the responsibility to monitor the impact on the physics performance or requirements, of any and all changes in functionality or schedule that might be introduced through the change control process. In addition, they will lead the collaboration review and approval of the initial Physics Requirements Document and any revisions, and they participate in the development of the corresponding functional requirements. The ALICE-USA Collaboration Liaison is John Harris (Yale), National Coordinator of ALICE-USA, and the ALICE Collaboration Liaison is Jurgen Schukraft (CERN), ALICE Spokesperson and Chair of the ALICE Management Board. 19 ALICE EMCal Project Execution Plan In addition, the ALICE-USA National Coordinator in consultation with the ALICE-USA Council will appoint an ALICE-USA Computing Coordinator. The ALICE-USA Computing Coordinator advises the CPM on progress of the ALICE-USA computing plan and its conformance with the ALICE computing model and the status of offline software development. X.6 PARTICIPATING INSTITUTIONS LBNL will be responsible for the fabrication of this MIE instrument. In additional to LBNL personnel, members of the ALICE-USA Collaboration from U.S. Universities and National Laboratories will share major responsibilities for the fabrication of the ALICE EMCal subsystems. These institutions have expertise and past experience in designing and fabricating similar subsystems. An MOU will define the relationship between the institution and LBNL. In addition, scientists will provide leadership for ALICE EMCal. 20 ALICE EMCal Project Execution Plan ALICE-USA Institutions participating in the ALICE EMCal MIE Project: Creighton University University of Houston Kent State University Lawrence Berkley National Laboratory Michigan State University Oak Ridge National Laboratory Purdue University University of Tennessee University of Texas Austin Wayne State University Yale University In addition to the ALICE-USA participating institutions, a number of European institutions are collaborating and contributing resources toward the MIE scope of this project: European Institutions participating in the ALICE-EMCal MIE Project: Nantes, France Catania, Italy Grenoble, France CERN, France/Switzerland INFN Frascati, Italy 21 ALICE EMCal Project Execution Plan VIII. SCHEDULE AND COST RANGE The ALICE EMCal has been organized into a Work Breakdown Structure (WBS) for purposes of planning, managing and reporting project activities. Work elements are defined to be consistent with discrete increments of project work. Project Management efforts are distributed throughout the project, including conceptual design and R&D. The ALICE EMCal has 5 WBS Level 2 components: WBS 1.1 1.2 1.3 1.4 1.5 1.6 Title Conceptual Design and R&D Design and Engineering Detector Production Electronics production System Integration Project Management VIII.1 Schedule The Gantt chart view of the project schedule is shown in Figure VIII.1. The project critical path is illustrated in red. The schedule is fully integrated to include non-DOE contributions to the DOE technical scope. A CD-4 is planned for Project Completion in 1Q FY 2012. This allows approximately eight months of schedule float. The critical path is determined by the rate of module production which in turn is set entirely by the project funding profile. 22 ALICE EMCal Project Execution Plan Figure VIII.1. The schedule of the high level WBS elements of the ALICE EMCal MIE showing the critical path. 23 ALICE EMCal Project Execution Plan VIII.2 Milestones The following list is a preliminary schedule of milestones dates for the ALICE EMCal MIE. Additional level 2 milestones will be established prior to CD-2. Critical Decision-2 establishing the Performance Baseline is planned for 4Q FY 2007. It is planned to request Critical decision 3 simultaneously. The existing conceptual design is advanced for a project at CD-1 and is based on the operational electromagnetic calorimeter at the STAR experiment at the Relativistic Heavy Ion Collider. As the detector design is primarily based on existing technology and the technical risk in the project is low, the final design can be completed by 4Q FY 2007. Milestones are assigned to different levels depending on their importance and criticality to other milestones and the overall Project schedule. In this document we summarize only Level-1 (Critical Decision) and Level-2 (Project Control) milestones. These are listed in Table VIII.1. Table VIII.1 Critical decision dates and level - 2 Milestones Level 1 Date CD 1 Q1 FY07 CD 2-3 Q4 FY07 CD 4 Q1 FY12 Level 2 Final Design and Safety Review complete Q3 FY07 Components Proc. Complete for SM 1 Q2 FY08 Super Module 1 Ready to Ship Q2 FY09 Super Module 3 Ready to Ship Q4 FY09 Super Module 5 Ready to Ship Q3 FY10 Super Module 8 Ready to Ship Q2 FY11 Super Module No. 1 Ready for Operation Q2 FY11 VIII.3 Cost Range The estimated TPC range at CD-1 for the project is $13 – $16 million. After peer review, it was determined that eight detector modules was the minimum scope to achieve the physics goals described in the Mission Need. The increase in the lower cost figure of the range (from $5 million to $13 million), reflects the inclusion of 8 super modules in the technical scope, rather than a minimum of 3 super modules considered at CD-0. The preliminary TPC for the project is $13.295 million, in Actual Year Dollars. The following escalation factors were used: Labor 3% at Universities, 4% at Laboratories and materials 2.6% per year. 24 ALICE EMCal Project Execution Plan The estimated budget of $13.295 million includes all DOE base costs developed “bottoms-up” from the lowest appropriate WBS level. The costs shown by fiscal year in Table VIII.2 are base costs (no contingency). The total contingency by WBS ID is shown in a separate column and totals $2.775 million or 26% of the base cost. Table VIII.2 CD-1 TPC estimate k$ WBS Title 1.1 Conceptual Design and R&D 1.2 Design and Engineering 1.3 Detector Production 1.4 Electronics Production 1.5 System Integration 1.6 Project Management Subtotal Contingency - 26% ALICE - EMCal Est. TPC Total Budget FY06 FY07 FY08 FY09 FY10 FY11 FY12 - - - - - 295 295 - 480 - 480 - - - - - 6,545 - - 985 2,555 2,385 620 - 1,550 - - 325 520 700 5 - 485 - 75 120 120 125 45 - 1,165 - 260 225 230 240 180 30 295 815 1,655 3,425 3,450 850 30 10,520 2,775 13,295 The elements of the EMCal could have a useful life of up to fifteen years. The components of a total life-cycle cost include: (a) Fabrication, as described in this document; (b) Operation; and (c) Decommissioning costs. The estimated yearly cost of operation is less than $20,000 and does not include management and operations (M&O) support for the U.S. research program under the conditions set by the LHC ALICE management and the required M&O and annual replacement costs for ALICE-USA computing resources. The decommissioning of ALICE EMCal covers the disposal of standard electronic, computer, and experimental lab equipment, which must follow accepted standard procedures for disposal of these items. The decommissioning activities are not anticipated to be complex or cost prohibitive, and would likely be carried out by U.S. researchers, as is commonly done for pieces of scientific instrumentation. Although a detailed analysis has not been carried out, it is estimated that the decommissioning is likely less than $100,000. The estimated life-cycle cost is less than $17 million. VIII.4 Funding The ALICE EMCal MIE project will be entirely funded by DOE-NP. Collaborating French and Italian institutions supported by L'Institut National de Physique Nucléaire et de Physique des Particules (IN2P3) and Istituto Nazionale di Fisica Nucleare (INFN), respectively, anticipate providing technical expertise and resources, as well as hardware to the MIE. Outside of the project scope, the French and Italians are expected to provide an additional three detector super modules. With refinements during the post CD-0 project phase, the estimate for the DOE TPC at CD-1 as shown in Table VIII.2 is $13.295 million. The DOE funding profile guidance at CD-1 is shown in Table VIII.3 25 ALICE EMCal Project Execution Plan Table VIII.3 ALICE EMCal Project Funding Profile Fiscal Year 2006 2007 2008 2009 2010 2011 Totals Authority Profile (M$) 0.3 1 2 4 4 2 13.3 The DOE TPC is allocated by cost category as shown in Table VIII.4: Table VIII.4 Allocation of the TPC Category CDR R&D EDIA Construction Pre-Ops DOE TEC DOE TPC Cost (M$) 0.2 0.1 0.9 12.1 13.0 13.3 VIII.5 Contingency Contingency funds will be managed in conformance with the policies contained in DOE Manual 413.3-1 and as defined in the Baseline Change Control section of this document. VIII.5.1 Contingency evaluation for CD-1 cost estimate At the present CD-1 phase (Approved Alternative Selection and Cost Range), the project contingency percentages are derived by a point system which was developed and applied successfully in the past to several DOE-funded projects3. Project contingency funds to bracket the cost range were determined by evaluating every task for cost, technical, schedule and design risks at the lowest appropriate WBS level and then applying a weighting factor to account for single or multiple risks in a single WBS entry. These first estimate contingency rates are determined by considering the current development status of each WBS item, and the uncertainties plus risks in completing the design, construction and testing. The guidelines used to establish the contingency 3 For example, STAR at RHIC. 26 ALICE EMCal Project Execution Plan percentages are listed in Table VIII.5 and VIII.6 for weight factors Wi and risk factors Ri respectively. The scalar product of the Risk and Weight vectors, WiRi, defines the WBS category contingency in percent as applied to the corresponding base cost. Total project scope presented in the project WBS and schedule includes contributed resources that are now or will be defined (no later than CD-2) by MOU’s between the ALICE EMCal collaborating institutions. These contributed resources have already played a significant role during the conceptual design phase and there is low to moderate risk that these resources will not continue to be available during the remaining phases of the project. However, the ALICE EMCal project management team believes that it is prudent to carry an additional level of cost contingency to cover scope that may not be performed as planned under the contributed resources scope. For CD-1, the average contingency on contributed resources is calculated by evaluating the risk associated with the likelihood that a given MOU may not be fully implemented. The composite contingency on all contributed resources estimated in this manner is $1.118 million. Based on previous experience with similar projects, this level of contingency is considered conservative but acceptable at this phase. This amount is added to the contingency deduced using the point method to produce the total contingency of $2.775 million shown in Table VIII.2. Table VIII.5 Contingency weighting factors TECHNICAL, COST, SCHEDULE and DESIGN WEIGHTING FACTORS Condition Technical Cost Schedule Design Weighting Factor Design OR Manufacturing Design AND Manufacturing Material Cost OR Labor Rate Material Cost AND Labor Rate Same for all 2 4 1 2 1 Same for all 1 27 ALICE EMCal Project Execution Plan Table VIII.6 Contingency risk factors TECHNICAL, COST, SCHEDULE and DESIGN RISK FACTORS Risk Factor Technical Cost Schedule Design 0 Not used Not used Not used Detail design > 50% done 1 Existing design and off the shelf H/W Off the shelf or catalog item Not used Not used 2 Minor modifications to an existing design. Vendor quote from established drawings. No schedule impact on any other item Not used 3 Extensive modifications to an existing design Vendor quote with some design sketches Not used Not used 4 New design; nothing exotic In-house estimate based Delays completion Preliminary design on previous similar of non-critical >50% done; some experience subsystem item analysis done 6 New design; different In-house estimate for from established designs item with minimal or existing technology experience but related to existing capabilities 8 New design; requires some R&D but does not advance the state-of-theart In-house estimate for Delays completion item with minimal of critical path experience and minimal subsystem item in-house capability Conceptual design phase; some drawings; many sketches 10 New design of new technology; advances state-of-the-art Top-down estimate from analogous programs Not used Not used 15 New design; well beyond current state-ofthe-art Engineering judgment Not used Concept only 28 Not used Not used ALICE EMCal Project Execution Plan The contingency assignment per WBS element resulting from the contingency analysis is shown in Table VIII.7 below. These contingency amounts were utilized to develop the overall project contingency. WBS 1.1 1.2 1.3 1.4 1.5 1.6 Title Conceptual Design and R&D Design and Engineering Detector Production Electronics Production System Integration Project Management Subtotal Contingency - 26% ALICE - EMCal Est. TPC Budget 295 480 6,545 1,550 485 1,165 10,520 2,775 13,295 Cont % 170 1,900 310 200 195 2,775 35% 29% 20% 42% 17% 26% Table VIII.7 Contingency assignment per WBS element IX Change Control Changes to the technical, cost and schedule baselines will be controlled using the thresholds described in Table IX.1 All changes that include or exceed Level 3 approval thresholds (as defined in Table IX.1) will be submitted to the CPM using a Project Change Request form (PCR). All PCRs become part of the permanent project documentation maintained by the CPM. For changes exceeding Level 3, the CPM will endorse the request (i.e., recommend approval) to higher authority or reject the request. If endorsed, the CPM will then transmit the PCR to the FPD with recommendations. If the request exceeds Level 2, the BSO Baseline Change Control Board (BCCB – see below) will submit the PCR to the ALICE EMCal Program Manager in DOE Headquarters for approval. All Level 2 PCRs will be reviewed and approved by the BSO BCCB and all Level 3 PCRs will be reviewed and approved by the CPM. The BSO BCCB will consist of the ALICE EMCal FPD (chair), the BSO Director, the Director of the NSD at LBNL (or designee), the CPM, and others as directed by the FPD. Technical advisors will be included as needed in the BSO BCCB. The chair has the final responsibility to endorse the PCR. For Level 3 changes and requests for higher-level changes the CPM will consult with the Deputy CPMs. If the change is approved, the copy of the approved PCR, together with any qualifications or further analysis or documentation generated in considering the request is returned to the requestor, and copies are sent to the official at the next higher control level and to ALICE EMCal CPM for filing. If approval is denied, a copy of the PCR, together with the reasons for denial, is returned to the requestor, and a copy is filed. The official at the next higher control level may review the granted change to ensure proper application of the procedure and consistency of the change with the goals and boundary conditions of the project. 29 ALICE EMCal Project Execution Plan Table IX.1. Summary of Baseline Change Control Thresholds Change Level Cost Schedule Technical Scope DOE-SAE (Level 0) > 25% cumulative increase to TPC 6 or more months increase (cumulative) to project completion date DOE-SC-26 Program (Level 1) Any increase in the TPC or cumulative allocation of more than $500k contingency A cumulative increase of more than $250k in WBS Level 2 or cumulative allocation of more than $250k contingency Any increase of >$50k in the WBS Level 2 3-month or more delay of a Level 1 milestone Any change affecting conformance to mission need requirement (Section II) Any change in CD-4 deliverable that affects mission need requirement (Table V.3) Any deviation from technical deliverables that does not affect expected performance specifications (Table V.2) DOE-BSO Federal Project Director (Level 2) ALICE EMCal Contractor Project Manager (Level 3) 1-month delay of Level 1 milestone or >3 month delay of Level 2 milestone > 1-month delay of a Level 2 milestone date Any significant change in the System Requirements Document. (Appendix A) X Analyses, Assessments, and Plans X.1 ENVIRONMENT, SAFETY AND HEALTH The basic detector design concept is very similar to other calorimeters successfully constructed by the present EMCal design team for the STAR detector at RHIC, AGS experiment E864, and the Aleph detector at CERN. Therefore, the safety and environmental hazards associated with this project are expected to present almost identical concerns as those encountered in past detectors. Given this general appreciation for the risks and hazards associated with calorimeter construction and commissioning, a detailed safety plan has been generated (Documents EMCal.2.1.v1 and EMCal.2.2.v1). For the purposes of this Project Execution Plan, the underlying philosophy of the ALICE EMCal safety plan is presented. 30 ALICE EMCal Project Execution Plan X.1.1 Integrated Safety Management policy This ALICE EMCal safety plan identifies the steps that will be taken to manage and control risks to an acceptable level in accordance with LBNL’s Integrated Environment, Health and Safety Management Policy, PUB-3140. Environment, safety and health (ES&H) concerns will be integrated into all phases of planning and implementation through to the final design and production processes of ALICE EMCal by applying the Integrated Safety Management (ISM) policy. This plan requires that safety management functions and principles apply to all activities through all phases of the project. The ALICE EMCal management team is committed to conducting all work so that the mission can be accomplished with adequate controls in place to protect the public, the workers, and the environment. X.1.2 ES&H Line Management As discussed in section X.1.1, the Integrated Safety Management policy employed in the ALICE EMCal project requires the full commitment of the project management team. The line management of each organization involved in ALICE EMCal retains supervisory authority of their personnel and responsibility for the safety of work at their home Laboratory or University. Line management in each Laboratory and University will inform the CPM about their Laboratory’s management and EH&S organization structures. Any safety related concerns of ALICE EMCal personnel are to be communicated to the ALICE EMCal CPM, the line management where the concern occurs and the employee’s home Laboratory or University. The ALICE EMCal project line management is responsible for the preparation of all safety reports for the ALICE EMCAL project. The ALICE EMCal line management is described in section IV of this document. In particular, we emphasize here the line management authority for ES&H vests executive authority with the Director of the Nuclear Science Division at LBNL through the CPM and his Deputies. X.1.3 Fabrication and Assembly Work at Wayne State University (WSU): Since the bulk of the fabrication and assembly will take place at WSU and Yale under subcontract from LBNL, the ALICE EMCal management team is planning to implement specific steps to insure that all work is carried out in a manner consistent with PUB-3000, LBNL’s Health and Safety Manual to protect project personnel, equipment and the environment. Both WSU and Yale have very extensive EH&S program in place. WSU has an excellent track record as was demonstrated during the design and construction of the EMCal for the STAR detector. Detailed information about the WSU’s EH&S program can be found at the following URL: (http://www.oehs.wayne.edu/) 31 ALICE EMCal Project Execution Plan X.1.4 Installation and Commissioning work at CERN On site at CERN, installation of general infrastructure plus the single super module installed under the project scope and operational EH&S concerns will be managed directly by CERN’s Safety Commission. CERN has extensive experience in similar operations. Because of CERN’s international status and because some of its activities are unique in Europe, CERN has its own specific safety regulations based on those of the Member States, with a bias in favor of those safety regulations that are the most rigorous. In all cases, CERN is required to comply with the rules in force on the territory of the Host States and to ensure that a level of safety is maintained that is at least equivalent to that provided for by the latter’s own regulations. X.1.5 NEPA and CEQA A NEPA review has been completed and a determination made that ALICE EMCal is included under a Categorical Exclusion covering a range of research and related activities. Work at LBNL would be covered for California Environmental Quality Act (CEQA) purposes under existing CEQA documentation. X.2 Quality Assurance ALICE EMCal defines Quality as the “fitness of an item or design for its intended use” and Quality Assurance (QA) as “the set of actions taken to avoid known hazards to quality and to detect and correct poor results.” Prior to CD-2, the ALICE EMCal project team will define an ALICE EMCal QA plan. The plan will classify in grade levels how poor quality can impact the project, and then, associated with these grade levels, a set of actions to control and maintain quality. The plan also defines responsibilities of the QAM. X.3 Risk Management ALICE EMCal views risk management as an ongoing task that is accomplished using a formalized plan to identify, analyze, mitigate and monitor the risks that arise during the course of completing the project. Risk is a measure of the potential of failing to achieve overall project objectives within the defined scope, cost, schedule and technical constraints. ALICE EMCal has established its own formal Preliminary ALICE EMCal Risk Management Plan (Document EMCal.4.3.v1) using the guidelines set forth in Chapter 14 of DOE Publication M 413.3-1, Project Management for the Acquisition of Capital Assets. The purpose of this analysis is not solely to avoid risks, but to understand the risks associated with a project and devise methodologies and strategies for managing them. The final responsibility for risk management will rest with the CPM, in consultation with the Deputy Contractor Project Managers. However, effective risk management is a multi-step process that requires continued involvement of all project members, and the ALICE EMCal management will encourage such involvement. ALICE EMCal will use key procedures proven to be an effective strategy in the management of risk on scientific projects: planning, assessment, handling and monitoring. A preliminary risk analysis has been begun as the project approached CD-1 and the initial entries have been made in a 32 ALICE EMCal Project Execution Plan Risk Registry. This will be completed and fully integrated into project management prior to CD-2. Cost and Schedule Range: ALICE EMCal is judged to be low risk in terms of completing the MIE on cost and schedule. The cost estimates are based in part on existing quotes for the detector parts and components, actual cost of production of similar items, in part on budgetary quotes, and in part on engineering experience. Based on the preliminary funding profile listed in Section 2 above, procurement of long lead-time items will begin in FY 2008 and Start of Operations is scheduled for FY 2012. To the extent feasible, procurements will be accomplished by fixed-price contracts awarded on the basis of competitive bids. Incremental awards to multiple subcontractors to assure total quantity or delivery will be performed to reduce schedule risk. The cost estimates are based in part on existing contracts for the prototype, actual cost of production of similar items, in part on budgetary quotes, and in part on engineering experience. It is probable that the EMCal project will include foreign procurements. Due to the cost risk associated with an unfavorable dollar vs. Euro or dollar vs. Yen exchange rate change additional contingency has been applied to several key items. In addition, risk will be reduced by placing early procurements of some of these key items. Adequate cost and schedule contingencies will be included in this MIE’s performance baselines. The current estimated cost contingencies for the remaining design and fabrication (Estimate to Completion) totals $2.775 million or 26%. This includes $1.118 million of contingency to cover the risks associated with planned contributed resources based on evaluating the risk associated with the likelihood that a given MOU may not be fully implemented. Delays in project funding due to Congressional Continuing Resolution could delay the placement of procurements during the early part of the fiscal year. To mitigate this risk, there will be an attempt to avoid scheduling critical procurements for the first quarter of a fiscal year and it is expected that some funds will be carried over from a previous fiscal year into the next. Funding Range and Budget Management: ALICE EMCal is budgeted as an MIE in the DOE-NP Program starting in FY 2007. The estimated funding to complete the project is currently planned in the NP five year budget. Funding will be provided by NP to LBNL per the terms of its management and operating (M&O) contract with DOE. These funds are under the management of the ALICE EMCal FPD at the DOE Berkeley Site Office. LBNL will be responsible for distributing the funds to collaborating institutions. Technology and Engineering: The technical risks of the ALICE EMCal project are low. R&D efforts have decreased risk related to a design being able to reach desired performance specifications critical to the ALICE-USA program. This work culminated in a full systems test in beam at Fermi National Accelerator Laboratory (FNAL) of a 16module prototype detector. Moderate risk is associated with the limited number of vendors available for the intricate ALICE EMCal scintillator tiles. Currently, only two known, qualified vendors, both located in Europe, exists for the manufacture of these 33 ALICE EMCal Project Execution Plan tiles. The capabilities of the vendors were fully explored as part of the prototype effort as a key risk management step. At the moment, as a result of this R&D work, both of these vendors are both judged as qualified. An additional round of detector prototyping in FY07 will further explore their capabilities. X.4 Value Engineering A Value Engineering (VE) study will be performed before ALICE EMCal seeks approval for CD-2/CD-3. The study will follow the traditional approach to VE, according to applicable procedures. A review team formed by members of the IPT and representatives of the ALICE EMCal management and technical teams will evaluate alternative design approaches and evaluate the flexibility of the design for present and future research. The VE approach will determine the impacts on cost (both ALICE EMCal and life-cycle) of any suggested changes to the design. Additionally, the project team will perform informal VE evaluations throughout the duration of this MIE. X.5 Project Controls and Reporting System The ALICE EMCal MIE project has been entered into the Project Assessment and Reporting System (PARS) and will be updated on a monthly basis by the FPD. The Deputy Contractor Project Manager (J. Rasson) will lead monthly cost and schedule performance reviews based on schedule, cost, and technical data and report the result to the CPM and FPD. The CPM will lead quarterly overall cost, schedule and technical performance reviews and report the results to the BSO-DOE office. The FPD will report progress to the DOE Program Manager on a quarterly basis. The Office of Nuclear Physics will conduct annual progress reviews with a committee of experts. The standard LBNL accounting system will be the basis for collecting cost data. A direct one-to-one relationship will be established between each WBS element of Level 3 or lower and a separate account code under the LBNL accounting system. Technical performance will be monitored throughout the project to insure conformance to approved functional requirements. Design reviews and performance testing of the completed systems will be used to ensure that the equipment meets the functional requirements. 34 ALICE EMCal Project Execution Plan WBS Dictionary for the ALICE-EMCal MIE-HILHC A collaboration of: Wayne State University Lawrence Livermore National Laboratory Nuclear Science Division Lawrence Berkeley National Laboratory Oak Ridge National Laboratory 35 ALICE EMCal Project Execution Plan WBS Dictionary for the ALICE - EMCal CONCURRENCES: _________________________________________ Tom Cormier ALICE - EMCal Project Manager Date: _______________ _________________________________________ Joseph Rasson ALICE – EMCal Deputy Project Manager Date: _______________ _________________________________________ Denis Peterson ALICE – EMCal Project Controls Manager Date: _______________ This document details the ALICE – EMCal Work Breakdown Structure at the Control Account level. The Responsibility Assignment Matrix, showing Control Accounts and Control Account Managers is shown as Attachment 1. 36 ALICE EMCal Project Execution Plan WBS Title 1 ALICE - EMCal - MIE 1.1 Conceptual Design and R&D 1.1.1 Modules Conceptual Design 1.1.2 Strip Module Conceptual Design 1.1.3 Super Module Conceptual Design 1.1.4 Electronics Conceptual Design 1.2 Design and Engineering 1.2.1 Mechanical Components Design 1.2.2 Elec. System Design 1.2.2.1 Electronics Design 1.2.2.2 Jet Trigger Design (CERN/Grenoble) 1.2.3 Mechanical Components Fab Process: Development & Qualification 1.2.3.2 Assembly Tooling Development and Qualification 1.2.4 Production of a Prototype for Test Beam (16 Module) 1.2.4.1 Assembly of 16 Module Prototype 1.2.4.2 Test Beam (FNAL) 1.2.5 Final Design and Refinement of Mass Production Processes 1.2.5.1 Final Design of Mechanical Components 1.2.5.2 Final Design of Assembly and Handling Tooling 1.2.5.8 Final Design - Jet Trigger 1.2.5.4 Detector System Final Design and Safety Review 1.3 Detector Production 1.3.1 Mechanical Component Procurements and Fab. 1.3.2 Fabrication of Additional Production Tooling & Fixtures 1.3.3 Super Module Production 1.3.3.1 Module Processing and Assembly 1.3.3.2 Strip Module Assembly 1.3.3.3 Super Module Assembly, Test and Ship 1.4 Electronics Production 1.4.1 1.5 1.6 Develop Fabrication and Assembly Process Suitable for Mass Production 1.2.3.1 Electronics Components Fabrication, Assembly and Test Site and System Integration 1.5.1 ALICE-EMCal Site Integration and Planning 1.5.2 Integration and Installation Project Management 37 ALICE EMCal Project Execution Plan WBS: 1.1 Sub-element: 1.1.1 Funds Type: Title: Conceptual Design and R&D Subtitle: Modules Conceptual Design TEC OPC EQ OPC OP Description: Cost Content: Costs of Wayne State engineering and technical staff needed to develop conceptual design and processes for individual modules. Technical Content: Conceptual design of necessary components, assembly tooling and review of safety issues surrounding the procurement and assembly of individual modules. Prototyping of inividual components to develop effective manufacturing designs and methodology. Work Scope: Components Conceptual Design Assembly Tooling Conceptual Design Process Development of assembly methods for prototype and test Review of Safety issues Component prototyping and needed Design Improvement 38 ALICE EMCal Project Execution Plan WBS: 1.1 Sub-element:1.1.2 Funds Type: Title: Conceptual Design and R&D Subtitle: Strip Module Conceptual Design TEC OPC EQ OPC OP Description: Cost Content: Effort by Wayne State and Nantes personnel Technical Content: Conceptual Design of the strong back support for the 16 unit strip module, processes for strip module integration and review of safety issues. Prototyping of necessary components and development of commercial manufacturing processes. Work Statement: Conceptual Design of the strong back support for the 16 unit strip module Conceptual Design for the strip module Itegration Document safety issues and mitigation Prototype components and revise designs for effetive mass manufacturing 39 ALICE EMCal Project Execution Plan WBS: 1.1 Sub-element: 1.1.3 Funds Type: Title: Conceptual Design and R&D Subtitle: Super Module Conceptual Design TEC OPC EQ OPC OP Description: Cost Content: Effort by Wayne State personnel Technical Content: Conceptual design of super module layout, crate design and component prototyping. Work Statement: Layout of Super Module conceptual design Conceptual Design of Crates Safety Analysis Prototyping components and design improvement for commercial manufacture. 40 ALICE EMCal Project Execution Plan WBS: 1.1 Sub-element: 1.1.4 Funds Type: Title: Conceptual Design and R&D Subtitle: Electronics Conceptual Design TEC OPC EQ OPC OP Description: Cost Content: All costs are labor from ORNL and CERN. Technical Content: Develop Conceptual Design for the ALICE EMCal electronics based on the PHOS model. Work Statement: Electronics coceptual design based on those used in PHOS Develop preliminary parts lists of eletronic components Develop cost estimate for electronics procurements 41 ALICE EMCal Project Execution Plan WBS: 1.2 Sub-element: 1.2.1 Title: Design and Engineering Subtitle: Mechanical Components Preliminary Des. Funds Type: TEC OPC EQ OPC OP Description: Cost Content: Effort from Wayne State engineering and technical Technical Content: Preliminary design efforts for the various Detector mechanical parts and safety analysis. Work Statement: Module preliminary design Strip module preliminary design Super Module preliminary design Preliminary Design and Safety review. 42 ALICE EMCal Project Execution Plan WBS: 1.2 Sub-element: 1.2.2 Title: Design and Engineering Subtitle: Elec. System Preliminary Design Funds Type: TEC OPC EQ OPC OP Description: Cost Content: Effort labor from ORNL and CERN. Technical Content: Preliminary design efforts for the various electronics controls and components. Work Statement: Elec. Design Redesign Transition Card Redesign of PHOS GTL buses Design EMCal FEE Crate Design LED driver High Level Trigger Design Jet Trigger Design 43 ALICE EMCal Project Execution Plan WBS: 1.2 Sub-element: 1.2.3 Funds Type: Title: Design and Engineering Subtitle: Develop Fab. & Assem. Process for Mass Production TEC OPC EQ OPC OP Description: Cost Content: Effort from Wayne State engineering and technical staff. Technical Content: Development of fabrication processes and tooling fixtures for use in mass production of parts and component assembly Work Statement: Develop fabrication processes for each module component (lead tiles, scintilators, etc. and qualify vendors for production. Develop Tooling and Assembly fixtures needed for production of modules, strip modules and super modules. 44 ALICE EMCal Project Execution Plan WBS: 1.2 Sub-element: 1.2.4 Title: Design and Engineering Subtitle: Production of Prototype for Test Beam Funds Type: TEC OPC EQ OPC OP Description: Cost Content: Effort from Wayne State engineering and technical staff. Technical Content: Assembly of a 16 module prototype and testing with beam. Work Statement: Assembly of a 16 module prototype detector with all components and electronics. Align and bench check. Calibrate short system. Ship prototype unit to FNAL for test in beam Gather and analyze preliminary data Ship back to Wayne State 45 ALICE EMCal Project Execution Plan WBS: 1.2 Sub-element: 1.2.5 Funds Type: Title: Design and Engineering Subtitle: Final Design and Refinement of Mass Production Processes TEC OPC EQ OPC OP Description: Cost Content: Effort from Wayne State engineering and technical staff. Contributed effort from Nantes on Strip Module Assembly Tooling. Technical Content: Final design of all components, assembly tooling and integration. Work Statement: Final design of Mechanical Components o Lead/Scintillators o Machined parts o Side Straps o Lead Tiles o Injection Molded parts o Belleville Washers and Fastners o Fiber Bundles Final Design – Strip Module Strong Back Final Design – Super Module Crate Final Design – Integration o Configuration Control o Procure and Install service from EMCal to racks o Fabrication and test of Super Module installation fixture o Develop installation scenarios and safety procedures Review of Final Design and Safety Documentation 46 ALICE EMCal Project Execution Plan WBS: 1.3 Sub-element: 1.3.1 Title: Detector Production Subtitle: Mechanical Components Procurement and Fab Funds Type: TEC OPC EQ OPC OP Description: Cost Content: Procurement of mechanical components for detector production at Wayne State. Cost for procurement admin support at Wayne State. Costs based on T. Cormier worksheet. Technical Content: Procurement and fabrication of mechanical parts for detector. Work Statement: Procure through Wayne State all mechanical components for assembly of modules, strip modules and supper modules. Timing of procurements matched to established DoE funding profile. 47 ALICE EMCal Project Execution Plan WBS: 1.3 Sub-element: 1.3.2 Title: Detector Production Subtitle: Fabrication of Production Tooling & Fixtures Funds Type: TEC OPC EQ OPC OP Description: Cost Content: Effort and material at Wayne State to procure and fabricate necessary tooling and fixturing to allow increased module assembly as required by schedule demands. Technical Content: Procurement and fabrication of tooling and assembly fixturing for detector assembly. Work Statement: Procure through Wayne State additional tooling and fixturing needed to increase detector module assembly stations at Wayne State or other assembly sites. 48 ALICE EMCal Project Execution Plan WBS: 1.3 Sub-element: 1.3.3 Title: Detector Production Subtitle: Super Module Production Funds Type: TEC OPC EQ OPC OP Description: Cost Content: Labor and misc. material to assemble individual modules, strip modules and super modules. Assembly of modules and strip modules with Wayne State staff. Super Module assembly is being conducted at Yale. Technical Content: Detector assembly and electronic integration. Work Statement: Assembly at Wayne State of 288 modules (12 per Strip Module) for each Super Module Prepare Super Module assembly facilities at Yale Assembly strip modules at Wayne State (24 per Super Module) Assemble Super Module 1, check alignment, connect and route cables, assemble carriages and rollers, integrate electronics, perform cosmic ray test, pack and ship to CERN Assemble Super Module 2 – 8, integrate electronics, perform Cosmic ray test, pack and ship to CERN. 49 ALICE EMCal Project Execution Plan WBS: 1.4 Sub-element: 1.4.1 Funds Type: Title: Electronics Production Subtitle: Electronics Components, Fabrication, Assembly and Test TEC OPC EQ OPC OP Description: Cost Content: Material and labor at ORNL and CERN to procure and oversee assembly of all electronics components for the ALICE - EMCal detector. Wayne State to provide technician support for the assembly. Technical Content: Electronics system procurement and assembly at ORNL. Work Statement: Procure electronics components as specified by parts list. Utilize Wayne State labor to assemble electronics components for each Super Module. Test all electronic components and assemblies 50 ALICE EMCal Project Execution Plan WBS: 1.5 Sub-element: 1.5.1 Title: System Integration Subtitle: ALICE-EMCal Site Integration and Planning Funds Type: TEC OPC EQ OPC OP Description: Cost Content: Labor contributed by Nantes Technical Content: Maintenance and revision of the ALICE – LHC interface documents. Work Statement: Maintain in current form all necessary documents describing the necessary interfaces with the LHC experiment and equipment. 51 ALICE EMCal Project Execution Plan WBS: 1.5 Sub-element: 1.5.2 Title: System Integration Subtitle: Integration and Installation Funds Type: TEC OPC EQ OPC OP Description: Cost Content: Labor contributed by Nantes. Oversite effort also provided by LBNL. Travel costs for LBNL staff. Technical Content: Complete design and installation of all outstanding conventional facilities and services to the ALICE – EMCal. Oversight and interface with LHC for the smooth installation of ALICE – EMCal with the LHC. Work Statement: Complete any design efforts necessary for the set-up and installation of ALICE – EMCal into the LHC equipment. Arrange for installation of all outstanding conventional facilities and services necessary for the operation of the ALICE – EMCal experiment. Provide expertise, guidance and resources during the installation of Super Modules into the LHC. 52 ALICE EMCal Project Execution Plan WBS: 1.6 Sub-element: 1.6.nn Title: Project Management Subtitle: Project Mangement Funds Type: TEC OPC EQ OPC OP Description: Cost Content: Level of effort tasks to provide for Project Management costs at LBNL and Wayne State. Also includes budget for misc. project expenses and travel. Technical Content: Provide Project Management and controls needed to deliver project objectives within the agreed upon constraints of scope, time and cost. Work Statement: Provide overall project management Provide timely reporting of project status, issues and accomplishments. Develop any necessary plans to mitigate risk 53