AGRICULTURE/FORESTRY
Co/Org Agriculture Western Cape
Name
Mail to
Bothma, JS, Mr
P O Box 227, Paarl, 7620
Tel/Fax/Cell/e-mail 021 872 1618/9, 021 872 3388, ,
Date Issue Raised Comment
01-Oct-01 Dear Ms Bowler
CSP: Integrated Env Mngmnt Legislation - ROD
Your letter dated 1 October refers.
Agri West-Cape has forwarded all correspondence received from your office to the various farmersassociations for their involvement in the process. We are however aware that the farmers in the Karoo area
(Beaufort West) indicated that they are not satisfied with the planned route of the Eskom Powerlines that are envisaged. This is due to bad experience with the present powerlines of Eskom Misbehave on private land.
Furthermore that the roads that give access to the powerlines for Eskom are not repaired properly and erosion took place.
Action
Faxed to Karin Bowler 11/10/01
K Bowler: Spoke to Mr. Bothma - he understood that he had the
RODs for the four projects confused with the 765kV and had not read the contents of the letter very well. He will inform his members accordingly. He will wait for the next documentation and feed through to his members again. Also discussed the ERF meeting with him and he was happy with the process and outcomes.
We suggest that you made direct contact with Mr. Pieter
Lund at Tel: 023 416 1685 whom is Agri Wes-Cape
Regional Representative for the Beaufort West area to get more information on their unhappiness.
Yours faithfully
29-Oct-01 1:250 000 MAP
Co/Org Beaufort West Boere Unie
Name
Mail to
Esterhuizen, Piet, Mr.
Posbus 1169, Beaufort West, 6970
Tel/Fax/Cell/e-mail 023 412 1665, , ,
JS Bothma
726992262 Page 1 of 133
Date Issue Raised
29-Oct-01 1:250 000 MAP
Comment
Co/Org Ceres Distrikse Landbou
Name
Mail to du Toit, Heinie, Mnr
Posbus 67, Koue Bokkeveld, 6836
Tel/Fax/Cell/e-mail 023 317 0685, 023 317 0896, 083 229 9132,
Date Issue Raised Comment
23-Jul-01 Telephonic Discussion Mnr du Toit het geskakel met die vraag of dit in die haak sal wees indien net hy die vergadering kan bywoon aangsien daar 'n veiligheids vergadering daardie selfde dag aan is in Ceres
Action
Action
Het mnr du Toit verseker dat solank hulle verteenwoordig word is alles in die haak.
29-Oct-01 1:250 000 MAP
Co/Org Dept of Agriculture
Name
Mail to
Louw, Antony, Mr.
P O Box 146, Malmesbury, 7299
Tel/Fax/Cell/e-mail 022 482 2265, 022 487 2331, , antonyl@wcape.agric.za
Date Issue Raised Comment
16-Oct-01
Notes by Doug Jeffrey on interviewing Mr Louw
1.Is spraying under the powerlines safe?
2.What about dust around the powerlines and shorting -
dust generated by farm vehicles e.g. tractors cause
- he has seen it happen on smaller power lines.
3.He mentioned a Wine Cellar somewhere near the lines
– I am going to see if I can find it on Wednesday - would let you know what I find.
Action
These issues have been raised by other I&APs, issues have been addressed in Impact Tables.
Co/Org Malmesbury
Name
Mail to van Aarde, Theunis G, Mnr
Posbus 147, Malmesbury, 7299
Tel/Fax/Cell/e-mail 022 482 2029, 022 482 2029, 072 153 2034,
Date Issue Raised Comment
29-Oct-01 1:250 000 MAP
18-Apr-02 Draft
Correspondence
EIR Subject: 765 kV EIA Draft EIR - Malmesbury Farmers
Ass
Date: Thu, 18 Apr 2002 10:08:12 +0200
From: "Karin Bowler" <karinbow@iafrica.com>
To: "Suzette Hattingh"
CC: "Stuart Dunsmore", "Nadia Mol",
"Koos van der Merwe", "Danie Boshoff", "Carol
Streaton"
Hi Suzette
Action
Subject: 765kv EIA draft EIR - I&AP feedback
Date: Fri, 19 Apr 2002 14:29:37 +0200
From: "Karin Bowler" <karinbow@iafrica.com>
To: <tgva@mweb.co.za>
CC: "Stuart Dunsmore", "John Geeringh", "Nadia Mol", "Koos van der Merwe", "Danie Boshoff" , "Carol Streaton", "suzette hattingh"
726992262 Page 2 of 133
726992262
June referred Mr. van Aarde to me:
My telephonic discussions with Mr. van Aarde,
Malmesbury Association on 18th April 2002 refer:
1. Please amend his spelling on the database from van
Aade to van Aarde.
2. Mr. van Aarde will be reporting back to his member’s i.t.o. progress on the 765 kV EIA at the Association's meeting (18 April 2002). Our discussions focused on this.
3. I informed him that letter has been sent to everyone on the database, including him.
4. He acknowledged he had been at the meeting with
Eskom Transmission negotiators last year.
5. He had a set of maps from that meeting.
6. I encouraged him to obtain the latest set of maps from either the municipality or library for the purposes of the meeting and to return them tomorrow.
7. I also informed him that the response date on the Draft
EIR is 19th April 2002.
8. Mr. van Aarde will contact me if he has any further queries. Please enter this info onto the database and confirm.
Regards
Karin Bowler
Geagte Mnr van Aarde
Te bevestiging van ons telefoniese gesprek van vandag:
Die Malmesbury Landbouvereniging het gisteraand 'n vergadering gehou waar die Eskom 765 kV projek bespreek is. Die lede het die volgende versoek:
1. Die 1:250 000 kaarte wat deel vorm van die verslag is nie aanvaarbaar nie - dit wil voorkom asof hulle uitgedateer is: baie van die plaasgrense het verander. a. Dit sal waardeer word indien meer opgedateerde kaarte verskaf kan word. Boere wil graag vooruitbeplan. b. Kaarte wat +/- 30 km noord en suid van Malmesbury strek word ook benodig om 'n beter idee te kry van die omvangs van die lyn. c. Lugfotos word ook benodig.
2. Meer duidelikheid word benodig i.t.v die bestuur van die serwituut. a. Daar is verduidelik dat die spesifieke reelings persoonlik met boere getref word, i.v.m. die finale plasing van die lyn. Die word nie as deel van EIA gedoen nie. Eskom Transmissie is hiervoor verandwoordelik. b. Die lyn sal nie gebou kan word totdat die hele servituut onderhandel is nie.
3. Dit sal waardeer word dat daar nog gesprekke gehou sal word i.v.m. die lyn . Dit word voorgestel dat Eskom Transmissie so gou as moontlik vir die Boere kontak om gesprekke te reel.
4. Daar is deur die lede gese dat die verslag te lywig was en dat dit in Engels is. Een van die lede is ingelig oor die onkoste van die druk en vertaling van die verslag, en dat die verhoed dat vertaling wel gedoen word.
5. Ek het onderneem om skriftelik (per e-pos) ons gesprek te bevestig. Ek ook verduidelik dat die kwessies wat u geopper het, deel van die finale verslag wat aan die Department Omgewingsake sal vorm.
Indien daar enige inligting is wat u nog wil byvoeg, laat weet so gou moontlik asseblief.
Groetnis
Karin Bowler
Page 3 of 133
Co/Org Riebeeck Boerevereniging
Name
Mail to de Jager, Pieter, Mnr
Posbus 78, Riebeeck-Wes, 6970
Tel/Fax/Cell/e-mail 022 461 2950, , 083 284 2294,
Date Issue Raised Comment
29-Oct-01 1:250 000 MAP
Action
Co/Org Sutherlandse Landbou
Name
Mail to van der Merwe, Koos, Mnr
Posbus 39, Sutherland, 6920
Tel/Fax/Cell/e-mail 023 571 1001, 023 571 1297, ,
Date Issue Raised
04-Jul-01
Comment Action
Phoned The Ko-op in regards to Agricultural Union Society meetings scheduled for 19 July 2001 (Have been unsuccessful at getting hold of Mr. Vlok & Mr.
Lambrecht).
Mr. van der Merwe suggested that he will be getting in contact with both these chairman to discuss the matter and notify them, taking all the details.
Discussed the fact that we need to forward them maps for the proposed transmission line route in preparation for the meeting, and he requested a set to be sent to them.
Co/Org Swartberg
Name
Mail to
Mitchell, L, Mnr
Posbus 140, Laingsburg, 6900
Tel/Fax/Cell/e-mail 023 551 1285, , ,
Date Issue Raised Comment
29-Oct-01 1:250 000 MAP
Co/Org Tulbagh Boerevereniging
Name
Mail to
Theron, Patrys, Mnr
Panorama, Tulbagh, 6820
Tel/Fax/Cell/e-mail 023 230 0770, , 082 892 9985,
Date Issue Raised Comment
Action
Action
29-Oct-01 1:250 000 MAP
Co/Org Victoria-Wes
Name
Mail to van Heerden, Gawie, Mnr
Posbus 17, Victoria-Wes, 7070
Tel/Fax/Cell/e-mail 053 6912 ask 3621, , ,
726992262 Page 4 of 133
Date Issue Raised
29-Oct-01 1:250 000 MAP
Comment
Co/Org Wolseley
Name
Mail to
Muller, Enrich (LEM), Mnr
Posbus 170, Wolseley, 6830
Tel/Fax/Cell/e-mail 023 231 1439, 023 231 1439, ,
Date Issue Raised Comment
29-Oct-01 1:250 000 MAP
DELETE
Co/Org
Name
Mail to de Waal Nigrini, A, Mr.
Post Office, Beaufort West, 6970
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised Comment
17-Sep-01 Trust/ID Nr.: 6201225100088
Action
Action
Action
14-Feb-02 21 Digit Code C00900000000016900005
Name
Mail to
Kirk, FCF, Mr.
14 Heseldon Road, Rondebosch, 7700
Tel/Fax/Cell/e-mail 021 685 3903, 021 685 3903, ,
Date Issue Raised Comment
04-Apr-02 Draft
Correspondence
EIR Subject: Cape Strengthening Programme
Date: Wed, 27 Mar 2002 09:22:39 -0800
From: "tkirk" <tkirk@freemail.absa.co.za>
To: <eskomcsp@acerafrica.co.za>
Dear Sir,
Please note that I am no longer the Mountain Club
Representative. Please in future email all your correspondence to Mr. H Nieuwmeyer at mailto:hnieuw@iafrica.com
F C F Kirk 14 Heseldon Rd, Rondebosch 7700 Tel/Fax
021-6853903, Cell 072-237 8203
Action
Subject: Cape Strengthening Programme
Date: Thu, 04 Apr 2002 08:58:29 +0200
From: suzette.hattingh@acerafrica.co.za
Organization: ACER (Africa)
To: tkirk <tkirk@freemail.absa.co.za>
Dear Mr. Kirk
Thank you for the notification. Unless you would still like to be informed regarding this project (please let me know if so), your name has been taken off the project mailing list.
Kind Regards
Suzette Hattingh
Name Zeeman, JS, Mnr
Mail to Posbus 144, Tulbagh, 6820
Tel/Fax/Cell/e-mail , , ,
726992262 Page 5 of 133
Date Issue Raised
02-Jan-02 Trust/ID Nr.:
Comment
Co/Org Almari Trust
Name
Mail to
, ,
120 Bree Street, Cape Town, 8001
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised Comment
29/98 16-Nov-01 Trust/ID Nr.:
Co/Org C. J. Petersen Trust
Name
Mail to
, ,
P O Box 206, Wellington, 7655
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised
05-Nov-01 Trust/ID Nr.:
14-Feb-02 21 Digit Code
Comment
C05200000000006400000
Co/Org
Name
Mail to c/o J.P. Alberts
Heyns, J, Mr.
P O Box 37, Laingsburg, 6900
Tel/Fax/Cell/e-mail 023 551 1819, , ,
Date Issue Raised
05-Nov-01 Trust/ID Nr.:
Comment
6008075003001
14-Feb-02 21 Digit Code C05200000000016300000
Co/Org D.H. Bothma Boerdery CC
Name
Mail to
, ,
Paul Sauer Str. 10, Stellenbosch, 7600
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised Comment
03-Oct-01 Trust/ID Nr.: 1989/008638/23
14-Feb-02 21 Digit Code C01900000000016100001
Co/Org
Name
Mail to
Dept of Minerals & Energy
Landman, Karel, Mr.
Private Bag X59, Pretoria, 0001
Tel/Fax/Cell/e-mail 012 317 9313, 012 320 2187, 082 447 2387,
726992262
Action
Action
Action
Action
Action
Page 6 of 133
Date Issue Raised
04-Apr-02 Draft EIR Correspondence
Comment
03 April 2002 FAX RECIEVED
Action
You are hereby requested to forward all correspondence to the Northern Cape Region and Western Cape Region specifically the addresses of which are enclosed for your perusal.
Mr. G Agenbach
Mr. L Selekane
Co/Org Du Toit Eindomme PTY Ltd -
Name
Mail to
Wege, Gys, Mnr
, ,
Tel/Fax/Cell/e-mail 023 312 3136, 023 316 1229, , farming@dutoit.com
Date Issue Raised Comment
19-Sep-01 Trust/ID Nr.: 199200159607
Action
Co/Org
Name
Mail to
F.J. Smuts Trust
, ,
6 Cheviot St., Florida Hills, 1709
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised Comment
04-Oct-01 Trust/ID Nr.: 24
Action
14-Feb-02 21 Digit Code C04600000000078300001
Co/Org Henri N.R. du Plessis Trust
Name
Mail to du Plessis, Henry NR, Mr.
p/a P Steenkamp P O Box 6268, Uniedal, 7612
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised Comment
17-Sep-01 Trust/ID Nr.: IT 917/96
14-Feb-02 21 Digit Code C01900000000036600012
Co/Org Injectaplas Pty Ltd
Name
Mail to
Jackson, PE, Mr.
P O Box 8948, Hennopsmeer, 0046
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised Comment
17-Sep-01 Trust/ID Nr.: 86/70230/07
14-Feb-02 21 Digit Code C07500000000022600000
Action
Action
726992262 Page 7 of 133
14-Feb-02 21 Digit Code C07500000000022500000
14-Feb-02 21 Digit Code C07500000000022400003
Co/Org Kareedoring Kraal Boerdery
Name
Mail to
Visser, JJ, Mnr
Voortrekkerweg 26, Velddrif, 7365
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised Comment
17-Sep-01 Trust/ID Nr.: 87/00480/07
14-Feb-02 21 Digit Code C04300000000004200002
Co/Org Klipvlei Land Pty Ltd
Name
Mail to
Stoch, PAL, Mr
P O Box 2785, Cape Town, 8000
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised Comment
17-Sep-01 Trust/ID Nr.: 89/06727/07
C01600000000004100001 14-Feb-02 21 Digit Code
Co/Org Lekkersukkel PTY Ltd
Name
Mail to
, ,
P O Box 62, Worcester, 6849
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised
19-Sep-01 Trust/ID Nr.:
Comment
197900409307
Co/Org Lushof Family Trust
Name
Mail to
, ,
P O Box 15072, Vlaeberg, 8018
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised Comment
03-Oct-01 Trust/ID Nr.: 1218/99
Co/Org
14-Feb-02 21 Digit Code C07500000000002000000
Co/Org
Name
Mail to
M & N Mostert Family Trust
, ,
P O Box 333, Citrusdal, 7340
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised Comment
16-Nov-01 Trust/ID Nr.: IT 791/95
National Portland Cement
726992262
Action
Action
Action
Action
Action
Page 8 of 133
Name
Mail to
, , c/o Ernst & Young, P O Box 4807, Weltevreden Park, 1715
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised Comment
17-Sep-01 Trust/ID Nr.: 05/11369/06
14-Feb-02 21 Digit Code C01900000000023400000
Co/Org
Name
Pioneer Voedsel Pty Ltd
, ,
Mail to P O Box 153, Riversdal, 6700
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised
03-Oct-01 Trust/ID Nr.:
Comment
195700063407
14-Feb-02 21 Digit Code C04600000000099300003
Co/Org Pugg Inv Pty Ltd
Name
Mail to
, ,
P O Box 257, Paarl, 7620
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised
05-Nov-01 Trust/ID Nr.:
18-Jul-01
Comment
Co/Org
Name
SAHRA
May, J, Ms
Mail to P O Box 1930, Kimberley, 8300
Tel/Fax/Cell/e-mail 053 831 2537, 053 833 1435, , sahra-nc@iafrica.com
Date Issue Raised Comment
726992262
Action
Action
Action
Action
Dear Ms May
ENVIRONMENTAL IMPACT ASSESSMENT FOR THE
PROPOSED 765kV TRANSMISSION LINE BETWEEN THE
GAMMA (VICTORIA WEST) AND OMEGA (KOEBERG) SITES
Increased demand in the Western Cape region for a reliable supply of electricity has necessitated that Eskom Transmission improves the reliability and capacity of the transmission network to the Western
Cape. As part of a strategy to do this, Eskom Transmission has proposed to develop a 765kV transmission line between the proposed
Gamma (Victoria West) and Omega substation (Koeberg) sites.
PD Naidoo & Associates, PBA International and ACER (Africa) have been appointed by Eskom Transmission to undertake the
Page 9 of 133
Co/Org
Name
Mail to
726992262
Technikon Pretoria
Haffter, Catherine, Ms
Private Bag X 680, Pretoria, 0001 environmental impact assessment (EIA) for the proposed 765kV
Transmission line between the Gamma and Omega sites.
The scoping phase of the EIA has commenced and a draft scoping report has been prepared. A summary of this draft report has been forwarded to your organization for your comment. It is proposed that two environmental review forum workshops will be held in the week
13th to 17th August 2001 to discuss the draft scoping report. An invitation has been forwarded to you in this regard.
The EIA study was initiated in 1999 and after a period of some 12 months on hold is now being continued with the issue of the draft
Scoping Report. At the same time we are updating our database of interested and affected parties (I&AP’s) particularly where new authorities, municipal demarcation areas, etc. have come into being.
As a result, and given the location and extent of the proposed development, we would like to have the opportunity to discuss the project with you. There are a number of opportunities for this including; comment on the draft Scoping Report (see attached list of venues where this may be viewed), attendance at our Environmental
Review Forums to which you will be specifically invited, or we would be happy to meet with you separately, preferably before or during the
Environmental Review Forum meetings (13 to 17 August).
As this is our first point of contact, we will be contacting you telephonically in this regard. However, your early thoughts on the matter would be appreciated.
Should you have any additional information requirements or queries at this stage, please do not hesitate to contact either Stuart Dunsmore or
Nadia Mol telephonically at (011) 486 4730 or (011) 482 2123 respectively.
Yours faithfully
Nadia Mol
PD Naidoo & Associates
Cc Stuart Dunsmore PBA International
Karin Bowler ACER (Africa)
Page 10 of 133
Tel/Fax/Cell/e-mail 012 318 6226, 012 318 6354, , haffterc@techpta.ac.za
Date Issue Raised Comment
15-Aug-01 E-mail Received
Action
Telcon refers >
Thank you for completing the I&AP registration form and for the interest shown in this project.
As agreed the following:
-You will receive an e-mail copy of the Draft Impact Table summarising all the issues identified during the Scoping Phase.
-You can access the Draft Scoping report for this project on Eskom's website: www.eskom.co.za/story/omega.htm
The Environmental Impact Assessment for the above project has been completed and we are waiting for the Record of Decision.
As you are registered on our database for this project, you will automatically receive a letter informing you when this has occurred.
Co/Org Theron Family Trust
Name
Mail to
Lategan, PJ, Mr
P O Box 138, Porterville, 6810
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised
16-Nov-01 Trust/ID Nr.:
Comment
384/92
Co/Org Uitsig Plase Pty Ltd
Mail to
Name van Tonder, D (le Roux), Mr
P O Box 22, Malmesbury, 7299
Tel/Fax/Cell/e-mail 022 482 8003, , ,
Date Issue Raised Comment
17-Sep-01 Trust/ID Nr.: 90/02838/07
Co/Org Western Cape Nature
Name
Mail to van Deventer, Jaco, Mnr
Posbus 26, Porterville, 6810
Tel/Fax/Cell/e-mail 023 230 0759, 023 230 0228, ,
Date Issue Raised
14-Feb-02 21 Digit Code
13-Aug-01 Telephonic Discussion
C01600000000004400001
Comment
Interested to see map depicting route. Requested rerouting letter addressed to PF Viljoen.
Action
Action
Action
Refered him to the Draft SR for Map. Invited him to the ERF Meeting.
726992262 Page 11 of 133
Co/Org Witzenberg Landbou
Name
Mail to
Bredell, Anton (AW), Mnr
Posbus 237, Ceres, 6835
Tel/Fax/Cell/e-mail 023 313 3182, 023 313 3114, ,
Date Issue Raised
19-Apr-00 Draft EIR Comments
Comment
19 April 2002
Ref: 99041
Gamma-Omega 765 kV Transmissielyn Omgewings
Impak Studie
Verwys na konsep omgewings impak verslag gedateer
Maart 2002.
Volgens die inligting wat ons ontvang en tot ons beskikking het, word daar beoog om ‘n transmissie lyn deur die Witzenberg vallei to laat loop.
Action
These comments have been addressed in the Comments and
Response Table in the Addendum to the Draft EIR.
Ons het nog geen besoek van enige persone vir inligting in die verband in die vallei ontvang nie. Die kaart wat ons na gekyk het wys dat die beoogde lyn deur bestaande geboue en boerdery ondernemings sal loop.
Die Witzenberg vallei is geleë in die Kouebokkeveld sowat 30 km vanaf Ceres. In die vallei word hoofsaaklik geboer met uitvoer vrugte van hoe gehalte. Die vrugte word verbou en in die binneland en buiteland bemark.
Om so ‘n lyn op te rig sal beteken dat daar ‘n groot hoeveelheid van die vrugte bome uitgetrek moet word.
Die plantegroei (fona & flora) wat hier aangetref word is baie skaars en volgens natuurbewaring is hier sekere plant soorte wat net hier voorkom. Van die skaars plantegroei is in die middel van die beoogde lyn. Gebied.
Natuurbewaring is al reeds besig, in samewerking met die eienaars, om die as ‘n reservaat te verklaar.
Op die kaart wat ons na gekyk het word sekere dele as erosie aangedui, maar in die werklikheid vind daar volskaalse boerdery aktiwiteite plaas.
726992262 Page 12 of 133
Die vallei het werklik nie plek vir so ‘n groot kraglyn nie.
Ons sal dit waardeur as u vir ons kan besoek en self vir u kan vergewis van hoe die vallei lyk. Op die kaart wat u het kan u nie die volle omvang van die vallei kry nie.
Ons verstaan dat daar ‘n lyn gebou moet word, maar om
‘n kraglyn deur so ‘n gebied te laat loop is nie omgewings vriendelik nie.
Ons aanbeveling is dat u die lyn langs die bestaande lyn laat bou waar die natuur al reeds versteur is.
Ons sal dit waardeer as u ons asseblief in die verband kan kontak.
By voorbaat dank.
Mnr A W Bredell
726992262 Page 13 of 133
ENV/CONSERVATION
Co/Org
Name
Mail to
Baecker, Albin (AAW), Dr
37 David McLean Drive, Westville, 3630
Tel/Fax/Cell/e-mail 031 266 8719, 031 266 8719, , albin@biotrans-uk.com
Date Issue Raised Comment
20-Jul-01 20 Jul 01
Documentation Received (25 Jul 01)
The Enclosed Documentation is for
1) circulation to all I&APs, and
2) inclusion in the Scoping Report, along with
3) the resultant correspondence, minutes, debate explanations in writing.
Re: EAP – Cape Strengthening Programme Gamma-
Omega 765 kV Transmission Line
As one of the registered I&APs, I hereby declare from the onset my scientific and commercial interest in wood preservation, and therefore, in the project. My written comment in response to the Scoping Report is hereby submitted as presented in the following points, and I look forward to reading your Project Team’s formal account of this submission in the Scoping Report (SR).
1. The local parastatal known as ESKOM uses creosoted wooden poles widely in its utility operations.
2. Creosote leaches from the poles and attempts have been made for years to prevent this (see 1984 document attached as App.1) because poles which have lost their creosote rot and collapse. In spite of such attempts, as recently as 1999 the problem seemed to have intensified
(see 1999 document attached hereto as: App. 2).
3. In spite of many creosote manufacturers, wood treaters’ committees and end-users’ committees since then (see 2000 document: App. 3) to alter creosote composition in ways that were hoped to prevent it from
Action
Forwarded 3 copies to Karin Bowler (copies for both PBAI &
ESKOM). Original kept in the I&AP DSR correspondence file.
8 August 01
Telephonic discussion: (Karin Bowler)
- Thanked him for the trouble of submitting the reports.
- Explained that the only timber poles that would be used would be during the stringing of the cables where these were crossing roads and needed to be temporarily kept off the ground. These structures are of a temporary nature.
- At no other time are timber poles used.
- In response to his statement, it was explained that no distribution lines can be fed off a 765 kV Transmission Line. This line was also going directly from Victoria West to Koeberg and was at no time distributing electricity.
- If asked if there were any further questions, Dr Baecker said that "it would be pointless".
- I told him that I had passed the copies on to the project manager as well as to Eskom for their information.
726992262 Page 14 of 133
726992262
4. The poles are still rotting and collapsing because evidence to date shows that, even in spite of claims made
4 attached hereto, dated as recently as July 2001), it still leaches from the poles (see App5, which is a current photograph taken recently at Eskom’s own Cato Ridge test facility, showing significant losses of creosote into soil from pole shortly after having being planted in it).
All the above weakens electricity poles and renders then physically dangerous, and I am both concerned and indirectly affected by that – for example, a storm last year was the catalyst that caused a line of weakened electricity poles to collapse in the Karoo, causing veldt fires and losses of livestock to such an extent that affected farmers’ livelihoods were threatened. However, in addition to physical dangers and financial losses such as these, the following points regarding the toxicity and health hazards of pole preservatives set out below also both greatly interest and directly affect me.
5. Apart from their unfortunate lack of permanence as wood preservatives when in ground contact, the health hazards directly attributable to the toxic nature of the preservatives used in utility poles by parastatals have been the subject of world-wide investigation for decades.
Such concerns have intensified since Scandinavian countries restricted the use of CCA in wood structures in children’s playgrounds many years ago (for the present readers information, CCA is chopper-chrome-arsenic, which, unlike blackened creosoted poles, is the preservative present in the green-tinted poles also familiar to all South Africans).
6. The toxic and hazardous natures of the of the preservatives used to treat utility poles have been of such concern to all stakeholders that they were documented by the United nations in 1993 (see App. 6) and many
European Directives have been issued to restrict the use of these preservatives in the environment.
7. Then, the National Coalition Against the Misuse of
Pesticides (Ncamp) in 1997 established an objective
Page 15 of 133
726992262 database on the world wide web with regard to the dangers associated with the use of, inter alia, CCA and creosote in wooden poles in Northern America.
8. In the year 2000, arising from the widespread public concerns such as those now documented here, the use of
CCA in constructions of the Olympic Village in Sydney, for example, was banned when players discovered the hazards of CCA, because those Olympics had been declared as the “Green Olympics.” Similarly, the use of creosote has been banned in the Netherlands, and in the same vain, as of 3 years ago, a North American utility company has been taking steps to alleviate the leaching of creosote from its poles to the environment (see App.
7).
However, in direct contrast to the above mitigating steps taken to responsibly deal with the problems associated with wood preservatives in various countries around the globe, when the existence of Ncamp’s web site was reported in the South African press 3 years ago (see App
8), the dismissive response of the SA Wood Preservers’
Association to the concerns of that report, which dismissive response was subsequently published, was in fact independently appraised as amounting to “no more than the subjective knee-jerk reaction of certain local stakeholders who have vested interests in the continuing sale and use of third rate chemicals in third world countries.” That the attitudes of such stakeholders should manifest themselves in such reactions is both alarming and breathtaking as far as this Interested and affected
Party is concerned particularly in the light of the following points.
9. In contrast to the above mentioned attitudes of certain local stakeholders, and in spite of their dismissive reaction to the toxicity of the pole preservatives used here, SA in general has always had admirable environmental concerns (as illustrated by every South
African’s constitutional right to an environment that is not harmful to health), and, since taking the right environmental road in 1996 (see App 9), this country now enjoys world-class environmental legislation
Page 16 of 133
726992262
(regulated by Acts such as the National Water Act 36 of
1998 and the National Environmental Management Act
107 of 1998), to the extent that legal action can be taken against the relevant Minister in the event that he/she fails to ensure that parastatal organisations comply with such legislation after breaches of it are brought to his/her attention. Indeed the legislation even extends to private organisations, and it seems to have teeth in that the operations of a privately-owned SA creosoting plant have recently been suspended for allegedly polluting the atmosphere with emissions (see App. 10). Furthermore,
ESKOM has committed itself to such ideal, as evidenced from its own Environmental Pledge, which is attached hereto as App. 11 for ease of reference.
As a self-declared I&AP in the present process, I do not want to be left believing that Eskom’s Environmental
Pledge could be reduced to an example of a parastatal merely paying lip service to our legislation. Indeed, in the present process I have a right to be given written assurance to the contrary. However, I remain very, very confused by certain stakeholders’ conflicting opinions that have been put to me on this matter, and to be convinced by your efforts that my concerns herein are unfolded, I consequently write in this regard to ask for an effort from your Project Team to include in the Scoping
Report in considered analysis of the three following concerns (A,B and C) that have troubled me deeply for years:-
A. In light of all above documentation, and as is my right as a self-declared and registered I&AP, I wish to see, written in your Project Team’s Scoping Report, Eskom’s rationale whereby it is convinced that its continued use of creosoted poles does not render it liable to action from its own employees under Acts such as the Occupational
Health and Safety Act 85 of 1993 and/or the
Compensation of Occupational Injuries and Diseases Act
130 of 1993.
B. In light of all above documentation, and as is my right as a self-declared and registered I&AP, I wish to see, written in your Project Team’s Scoping Report, your
Page 17 of 133
726992262
Project Team’s satisfactory explanation of Eskom’s justification of its continued use of creosoted poles that pollute soil, because I have never seen such justification articulated anywhere. In other words, I want to see a written explanation of why ESKOM continues with this practice, and I believe that I have the right to see in the
SR.
C. In light of all above documentation, and as is my right as a self-declared and registered I&AP, I wish to see, written in your Project Team’s Scoping Report, Eskom’s explanation of why it is sure that its continued use of creosoted poles does not make it liable to legal action under the national Environmental Management Act 107 of 1998.
The above concerns are not put as questions – they are concerns that enquire your expertise and your considered response. My last point however is indeed a direct question that I require a direct and objective answer to. It is this:
Question – Is ESKOM certain that its creosoted poles are not poisoning the groundwater and river water being drunk by the very people to whom it is delivering electricity? If ESKOM is certain of this fact, I require to see the proof thereof, as properly documented evidence, that can be scrutinised by independent third parties in the
SR under discussion.
With due respect, I am obliged to make the point that correspondence and communication in this matter to date has been rather erratic. In order to timeously take any steps that I may have to take after reading it, I hereby request that you inform me of the date when the SR will be posted on the internet.
Sincerely
AAW Baecker
Page 18 of 133
08-Aug-01
726992262
17-Aug-01 Subject: Your decision to exclude my Submission from the Scoping Report of the EIA for Eskom's Cape
Strengthening Programme
Dr Alvin A W Baecker
37 David McClean Drive
Westville
3630
8 August 2001
Dear Dr Baecker
Re: Eskom Cape Strengthening Programme: Gamma- Omega 765 kV
Transmission Line Environmental Impact Assessment
I refer to your letter dated 20 July 2001. This serves as confirmation of our telephone discussion on 7 August 2001.
Thank you for the trouble taken in submitting the reports on the potential dangers of the use of creosoted poles. As discussed, the only time any poles will be used during this transmission line project, is during the “construction” phase. This is specifically limited to where the lines have to be kept off the ground surface during the stringing process to avoid infrastructure on the ground and poles are temporarily planted into the ground for this purpose.
Also, the only time wooden structures are used is for low voltage cables such as 33kv and 11kv distribution lines. According to Eskom, the tendency these days is to use concrete type structures for 66 kV distribution lines as opposed to wooden structures.
I have provided copies of your reports to Mr Stuart Dunsmore, the project manager and also to the Eskom official on this project.
Thank you once again for participating in this process.
Kind regards
Yours sincerely
KARIN BOWLER
Public Involvement Programme Leader
Dr A A W Baecker
37 David McClean Drive
Westville
Page 19 of 133
726992262
Date: Tue, 14 Aug 2001 21:29:35 +0200
From: "Albin Baecker" <albin@biotrans-uk.com>
To: "Suzette Hattingh"<eskomcsp@acerafrica.co.za>
CC: "Jeremy Ridl" <ridlj2@nu.ac.za>
Dear Ms. Hattingh
Your telephonic message to tell me of the above is noted with regret. By your own admission, creosoted poles are used in the stringing procedures, and your comment to the effect that the "temporary" nature of such procedures precludes their consideration in the present exercise reveals the fact that you have not read my submission properly. It is therefore necessary to draw your attention to App. 5 of my submission, which states clearly that the creosote contamination of the soil illustrated therein occurred within one month's service of that Eskom pole, which time period is comparable with any periods that you could want to describe as "temporary" in this matter.
With all due respect, but also most unfortunately, your attitude to my concern in this matter is all too typical of what I have come to expect. However, I do not intend to be fobbed off with platitudes perhaps designed to "pour oil over troubled waters" and make life easy for folk.
That attitude holds no place in modern South Africa - it is entirely regrettable that it seems that I have to point out to you that the good news for South Africa was its recent ascension to levels of environmental awareness comparable with the rest of the world in terms of environmental legislation, and I hereby notify you that I for one do not intend to stand by and watch folk in positions of influence abuse that hard-won position.
Therefore, in the first instance I ask again that you give due consideration to my submission as requested in the covering letter of it. I have the right to make this request,
However, if you decide to again refuse to accede to that very reasonable request, please inform me in writing (at this E-mail address), before close of business this coming
Friday, stating in full your reasons for refusal. and moreover, I have the right to see it attended to.
3630
17 August 2001
Dear Dr Baecker
Eskom Cape Strengthening Programme: Gamma-Omega 765 kV
Transmission Line Environmental Impact Assessment – Scoping
I note with concern your e-mail to Ms Hattingh on 14 August 2001. It seems as though there has been a misunderstanding regarding our telephonic discussion of 7 August 2001 and a significant misunderstanding of the environmental assessment process.
Transmitted herewith is a letter dated 8 August 2001 in which I have confirmed our telephone discussion and in which I have indicated to you that your submission has been passed on to the right people within the project team to be addressed as part of the environmental assessment for this proposed project. However, I acknowledge that you may not have received this letter prior to your email of 14 August
2001. Nevertheless, it is important that I confirm a number of matters:
ï‚·
Your input to the scoping process was received after the Draft
Scoping Report was compiled. By implication, there is no way that your input could have been included in the Draft Scoping Report.
ï‚· Arising from the above, it is, therefore, incorrect to assert that we have decided to exclude your submission from the Scoping Report.
Equally, it is totally unnecessary to make a host of allegations about our integrity. Indeed, I take the strongest exception to you implying that this office, viz. the Public Participation Office, in any way filters the inputs of Interested & Affected Parties. We reject all the allegations you have made, which we know are totally without foundation.
ï‚·
What is true is that this office has received your inputs, your inputs have been acknowledged with thanks, and we have tried to provide you with an explanation regarding the use of creosote poles on this project. Moreover, your inputs have been captured on the project data base, your inputs have been included in the Draft Comments and
Response Report (a living document that is only finalised at the end of the assessment process), and your inputs have been forwarded to the
EIA Project Manager in order that, collectively with the inputs of other
Interested & Affected Parties, issues, notably key issues, can be
Page 20 of 133
22-Aug-01
726992262
Sincerely,
Albin A W Baecker
Subject: Concern
Date: Tue, 21 Aug 2001 16:08:36 +0200
From: "Albin Baecker" <albin@biotrans-uk.com>
To: "Suzette Hattingh" eskomcsp@acerafrica.co.za
CC: "Jeremy Ridl" <ridlj2@nu.ac.za>
Att:- Ms. Karin Bowler
Dear Ms. Bowler,
Thank you for your E-mailed message of 17 inst. Your suggestion that there is on this part any misunderstanding of the environmental assessment process belies the fact that your organisation ought to be aware of the fact that your organisation and this were both part of the IOF EIA two years ago. Moreover, your message obliges me to make a few points very clear to you.
1) Your telephonic message to me did not convey the information that my submission will be "addressed as part of the environmental assessment for this proposed formulated in order to guide the investigative and assessment processes. It is only at the assessment stage that potential impacts arising from the use of creosote poles will be addressed and evaluated.
With regard to your specific request to include copies of your documentation in the Final Scoping Report, the inclusion of documentation received during the course of the study is the decision of the EIA Project Manager taking due consideration of the boundaries and framework of the environmental assessment. Nevertheless, as stated previously, your comments will be taken up in the compilation of the Final Scoping Report and the Environmental Impact Report as per the requirements of Government Regulation No. R. 1183 Section
6(1)(e), 1997).
Please contact Stuart Dunsmore, PBAI (011-486 4730 or 082 579
9149) or I if you have any further questions.
Yours sincerely
KARIN BOWLER
Public Involvement Programme Leader
Copy: Prof J Ridl
Page 21 of 133
726992262 project" as you now claim, and furthermore, your followup letter of 8 inst., that you refer to and which I have now received, does not make this point either. I therefore object to your most recent statements to the contrary.
2) My submission to the scoping process was received after the Draft Scoping Report was compiled, simply because I was never invited to submit to it and indeed the first time I heard that the Report had been compiled was when I received your organisation's statement to that effect. It seems very necessary to point out that the following account records the timetable of the only communication your organisation has made with me: a) February 2000 - I saw the obligatory EAP advertisement in one of the newspapers; b) 16 Feb., 2000 - I wrote to your organisation to register as an I&AP; c) 2 Nov., 2000 - your organisation wrote to me, with my name not spelt correctly, to inform me that the capturing of issues raised by stakeholders was what I could term a
"fait accompli" - and I insist that this was the only communication I had received from your organisation since the previous February; d) in June 2001 I saw an advertisement in the newspaper informing me that the Draft Scoping Report was available, and hot on its heels I received a letter to the same effect from your organisation (dated 28 June 2001).
If you call the above a good record of communication, well, that's up to you, but when you also falsely accuse me of making "a host of allegations" that I never made, and if that is typical of how the other I & AP's (who may well have been vociferous in commenting on the standard of communications well I can) have been treated in this process, well, perhaps you have been oversensitised and I could then imagine why you doth protest too much in my own case.
Notwithstanding the above, when I saw the advertisement of June 2001, I prepared and sent you my submission, and I fully expected it to be treated
Page 22 of 133
726992262 respectfully (which it was) and properly.
My submission addresses a very serious issue - for example, I suggest you read pages 44 and 45 of July
16th's (2001) "Time" magazine, and, after reading it, you may also be interested to know that the wood preservers' association in this country is treating the hazardous aspects of wood preservation in much the same dismissive way as that in which tobacco companies dismissed the hazards of cigarette smoking until very recently. Indeed, if you want to hear rash and untrue allegations which are not in step with mainstream thinking overseas, and which contribute to the endangerment of us all as far as wood preservation in
South Africa is concerned, that is who you should consult with - see the South African Wood Preservers'
Association's newsletter of 31 July 2001, which purports to respond to the Time article I quote here.
All I have ever asked for in this process was that my submission be considered according to the regulations that exist for this purpose. Your message of 18 inst. goes further than before, in that it does state that my comments will be "taken up" in the compilation of the Final
Scoping Report (and I reject as untrue your intimation that this is "as stated previously"). May I dare to ask you to explain what you might mean by "taken up" as this seems to be the key point at this stage?
In closing Ms. Bowler, I do know that, under the circumstances that operate, the work you have been charged with amounts to a very difficult task, requiring great organisational skills, patience, diplomacy, and a host of other skills that I myself do not possess. I take my hat off to folk such as yourself, and I wish to state for once and for all that I do not seek to get confrontational with you or anyone else at Acer Africa and I never intended to. I am just asking for a fair hearing in this extremely important matter.
With best regards,
Sincerely,
Albin A W Baecker
Page 23 of 133
05-Sep-01 E-mail Received Subject: Eskom Cape Strengthening - Scoping Report
Date: Wed, 5 Sep 2001 13:01:22 +0200
From: "Albin Baecker" albin@biotrans-uk.com
To: "Suzette Hattingh" <eskomcsp@acerafrica.co.za>
Att:- Ms. Karin Bowler
Thank you for your message of 31 ult., in which you advised me that Stuart Dunsmore would telephone me this week. He did so today, and one of the things he told me was that my submission to the EIA would be included in the Scoping Report. Would you please ensure that I receive a copy of it when it is released?
Re the IOF EIA that we were all involved in - I mentioned it to give you some comfort in your apprehension that I may not be familiar with the EIA process. Your last message indicates that ACER Africa would not have interfaced with me in that process because I was not at grass roots level.
I remain unclear about that - I was acting on behalf of
IOF's neighbour CTC, and CTC were involved because
IOF's fallout was killing the roots of their grass, and I submitted several photographs showing that phenomenon. That is why, in the present matter, I have submitted photographs of creosoted Eskom poles polluting the soil - to be included in the Scoping Report - as documentary evidence supporting the countermeasures to pollution that will be specified in the Environmental
Management Plan that will evolve, which is all parties' ultimate objective.
Sincerely
Albin A W Baecker
726992262 Page 24 of 133
05-Sep-01
726992262
28 August 2001
Dear Dr Baecker
Re: Eskom Cape Strengthening Programme: Gamma-Omega
765 kV Transmission Line Environmental Impact
Assessment – Scoping
Your e-mail dated 22 August 2001 has reference. In an attempt to gain some level of understanding between us with regard to our communication on this project, I should like to revisit and clarify process, timeframes, and issues raised thus far in this project. I have documented these in the following table:
Project Cape Strengthening Programme:
10 Project Components:
(Listed in the BID, “Announcement of Revised Programme” sent to you on 2 November 2000)
##
January 2000
Scoping Commences
Key stakeholder and Authority interaction Initial meeting with key stakeholders & authorities to discuss project and process
##
Fax received from Dr Baecker in response to one of the advertisements requesting registration as an Interested Party
– main interest soil pollution from creosoted poles in soil contact. This comment, the project team understood at the time, referred mainly to the 765 kV Transmission Line
##
21 February – 3 March 2000
Public engagement
Public Open days
Round of 11 Public Open Days in Study Area
##
Telcon with Stuart Dunsmore
- Dr Baecker acknowledged he has received the letter dated 29
August and is satisfied that his concerns regarding the use of creosote and creosote poles in the construction process have been recognised.
- Dr Baecker stated that he would be responding to Karin Bowler to thank her for the correspondence.
- I confirmed that we are still in the process of compiling our final Scoping Report, and that there had been many issues raised during the comments period. Therefore I could not comment on the detail of this particular issue at this stage.
- I noted that there are a number of different Eskom
Transmission projects underway at present, and that our team is only dealing with one of them.
- We briefly discussed my relationship with Eskom, and I confirmed that I am not an employee of Eskom, but an independent consultant appointed to undertake the EIA for the
Cape Strengthening Programme alone. I asked Dr Baecker if he was concerned about our independence in this study and he stated that he is not concerned about that.
- I stated that Dr Baecker would be notified of the issue of our
Final Scoping Report document.
- Should he then, or at any stage, wish to contact the EIA team he should do so preferably via ACER as the first point of contact, but that he is also welcome to contact me directly.
Page 25 of 133
726992262
November 2000
Eskom revises its strategy and makes the decisions as spelled out in the “Revised Programme” BID Public notification of
Eskom’s revised strategy and EIA programme
Invitation to stakeholders in areas relevant to four projects to comment on Draft Scoping Report Letter and BID sent to
I&APs informing them of change of project configuration and revised programme A copy of this BID accompanied the
I&AP letter sent to Dr Baecker in November 2000
##
February 2001
Record of Decision
Public comment included in Scoping Reports
Four Scoping Reports submitted for Record of Decision
In the process of receiving decisions on all projects
##
Consultants instructed to cease work on project once the
Final Scoping Reports of four projects were handed to the
Authorities.
No further communication was considered necessary as the revised programme had been explained in the BID mentioned above. Furthermore, I&APs will be informed of the four Records of Decision once these become available for the relevant projects.
##
Cape Strengthening Programme: 765 kV Transmission 28
June 2001Line
Scoping for 765 kV recommences
Project announcement Letter and BID sent to I&APs explaining recommencement of EIA and inviting participation
National, regional and local advertisements placed (the latter in study area)
Letter and BID sent to Dr Baecker
##
18 July – 18 August 2001
Publication of Draft Scoping Report for Public comment
Page 26 of 133
Comment period
Draft Scoping Report (For your convenience I refer you to pages 21 to 25 (of 63) where the technical aspects, construction, operation and decommissioning activities are described)
- 20 July 2001
ACER receives from Dr Baecker a covering letter and various supporting documents
- 7 August 2001
Telephonic discussion between Dr Baecker and Ms Bowler.
Ms Bowler acknowledged receipt of Dr Baecker’s correspondence and stated that it had been handed to the
Project Manager (a standard process with all IA&P issues received during Scoping)
- 8 August 2001
Letter from Ms Bowler confirming telephonic discussion
- 14 August 2001
E-mail from Dr Baecker to Ms Hattingh
- 17 August 2001
Ms Bowler provided a response by e-mail to Dr Baecker’s email
##
22 August 2001
Dr Baecker responded by e-mail
##
14 & 16 August 2001
Key stakeholder and Authority interaction
Environmental Review Forum Workshops in study area
Draft Scoping Report is discussed. Additional issues to be incorporated in Final Scoping Report.
The Final Scoping Report will be used by the Specialists as a basis, for their Terms of Reference for their studies
##
September/October 2001
Final Scoping Report submitted for Public comment
Comment period
726992262 Page 27 of 133
726992262
A draft Impact Table indicating issues, responses and proposed actions has been updated and will be submitted with the Final Scoping Report. This includes your issue regarding the use of creosoted poles.
##
October – December 2001
Impact Assessment Phase
Draft Environmental Impact Report will be produced for public comment I&APs will be notified accordingly Dr
Baecker will receive a letter notifying him of the availability of the Draft Environmental Impact Report for comment.
In addition to the report submitted by you, we have on record the following articles/reports:
-Time Magazine, 16 July 2001, Pages 44 & 45, “Toxic
Playgrounds”.
-SAWPA newsletter dated August 2001: “The safety of
CCA Treated Timber”.
-The scientific paper by Kenneth M. Brooks dated September
2000: “Assessment of Environmental Effects Associated
With Wooden Bridges Preserved With Creosote,
Pentachlorophenol, or Chromated Copper Arsenate.”
-Websites visited: :
> http://search.epa.gov/s97is.vts
> http:// www.preservedwood.com/safety/reserch_list.html
At no time has the issue you have raised, been treated with any less consideration than issues raised by other stakeholders. As indicated in the table above, issues and relevant literature that are raised by stakeholders during the
Scoping Phase are automatically passed on to the Project
Manager who evaluates the relevance of the material. Thus,
“taken up” means:
Recorded in the Comment & Response Document as an issue raised.
Evaluated by the Project Manager as to its relevance to this project.
A response is provided as to how this matter will be considered, if relevant to the project, i.e. does it require
Page 28 of 133
26-Mar-02 further investigation? Is it necessary to write the issue into the Environmental Management Plan?
With regard to your reference to Acer’s involvement on the
Indian Ocean Fertiliser Project, please note that Manyaka,
Greyling & Meiring (MGM) were the consultants appointed to conduct the public participation process as part of the
Environmental Impact Assessment undertaken by CWG.
ACER, sub-contracted by MGM, was responsible for community consultation at “grass roots level”. By implication, consultation with stakeholders not classified as
“grass roots level” would have been undertaken by MGM.
Therefore, although I provide clarity on the matter, I remain unclear as to the relevance of the IOF project to this one.
I sincerely hope that we can lay to rest issues related both to process, in terms of the project, and also as to how your specific issue will receive attention as part of the EIA. Also, a belated apology for the initial incorrect spelling of your name.
Once again, please contact Stuart Dunsmore, PBAI (011-486
4730 or 082 579 9149) or myself if you have any further questions.
Yours sincerely
KARIN BOWLER
Public Involvement Programme Leader
Draft EIR
Correspondence
Subject: Gamma-Omega - Draft EIR
Date: Tue, 26 Mar 2002 10:33:04 +0200
From: "Albin Baecker" <albin@biotrans-uk.com>
To: "Suzette Hattingh"<eskomcsp@acerafrica.co.za>
Subject: Electronic copies of the 765 kV Transmission line EIR
Date: Wed, 27 Mar 2002 11:38:43 +0200
From: Nadia Mol <Nadia.Mol@pdna.co.za>
To: albin@biotrans-uk.com
726992262 Page 29 of 133
Dear Ms. Hattingh Dear Interested and Affected Party
Thanks for your E-mail of even date re the errors in the table of venues at which the above is available for inspection. Is the report not also available electronically? Is there not a website at which I can access it for my own perusal? Failing that, may I ask for a copy to be mailed to me?
Thank you for your recent e-mails requesting further information on the draft EIR for the proposed Eskom 765 kV Transmission line between Gamma and Omega. A CD of this report is currently being fast-mailed to you.
I apologise for any inconvenience, but as committed environmentalist I am gratified to say that at the age of 51 I have still never driven a vehicle with an internal combustion engine and I instead always use public transport when the occasion demands, so in South Africa I cannot easily get to the venues listed in your table.
Sincerely,
Albin A W Baecker
Co/Org
Name
Botanical Society of SA
Maze, Kristal, Miss
Mail to Private Bag X10, Claremont, 7735
Tel/Fax/Cell/e-mail 021 797 2284, 021 761 5983, 082 890 0188,
Date Issue Raised Comment
14-Aug-01 E-mail Received Subject: Cape Strengthening Programme
Date: Tue, 14 Aug 2001 17:03:23 +0200
Action
From: "Kristal Maze" <wildflower@gem.co.za>
To: <Eskomcsp@acerafrica.co.za>
Dear Karin Bowler
We are unable to send a representative of the Botanical
Please contact Suzette Hattingh (ACER, Africa) should you have any further queries. Her contact details are as follows:
Tel (035) 340 2715
Fax (035) 340 2232
E-mail: Suzette.Hattingh@acerafrica.co.za
Yours faithfully
Nadia Mol - PD Naidoo & Associates
Subject: Eskom 765 kV Transmission Line Scoping Phase
Date: Wed, 15 Aug 2001 23:23:26 +0200
From: Karin Bowler <karin.bowler@acerafrica.co.za>
To: Kristal Maze <wildflower@gem.co.za>
Good day Kristal
Thank you for taking the trouble to respond, and to forward
726992262 Page 30 of 133
726992262
Society to your meeting in Ceres on 16 August 2001.
Please keep us informed of the progress on this project.
Attached you will find a short summary of our role as
I&AP's in landuse proposals.
Kind regards
Kristal Maze
+++
Since the promulgation of the Environmental Impact
Assessment regulations on 5 September 1997, the conservation staff and branches of the Botanical Society of
South Africa have been increasingly called upon to provide input and comment on a range of landuse proposals. The
Flora Conservation Committee of the Society has decided to make known the nature of our involvement in the IEM process, as well as our guidelines on what should be covered in a botanical specialist’s assessment.
OUR ROLE AS AN INTERESTED AND AFFECTED
PARTY
The Botanical Society has indigenous flora conservation as its core interest in landuse proposals. As it is impossible for either staff or members to respond to all requests for input, the society has adopted a general set of guidelines that it believes proponents and authorities need to consider.
Where possible we make inputs as an interested and affected party at both the scoping and EIA review stages.
The proponent and the appropriate authority are nevertheless ultimately responsible for adequately assessing flora conservation issues. It is not our general policy to get involved in management of areas or plant rescue activities, however, we can advise on these.
GUIDELINES FOR SPECIALIST BOTANICAL
ASSESSMENTS
In order to ensure that botanical assessments are of value to decision makers it is imperative that flora conservation concerns are professionally assessed in landuse proposals.
The following set of guidelines is based on the principles for a National Environmental Policy, as outlined in Chapter
1 of the Draft National Environmental Management Bill
(Government Gazette Notice 1195 of 1998): the FCC guidelines. I have forwarded same to the Project
Manager as well as the Ecologist appointed to the project.
Apologies for the delay in response, we are currently in the field and e-mail opportunities are limited.
Kindest regards
Karin
Subject: Karin Bowler - Cape Strengthening Programme
Date: Wed, 15 Aug 2001 00:39:25 +0200
To: "Kristal Maze" <wildflower@gem.co.za>
From: <Eskomcsp@acerafrica.co.za>
Dear Ms Maze
Thank you for the documentation you sent yesterday.
Regarding your request for the Botanical Specialist report, I have forwarded this to the Project managers well as the FCC document.
Kind regards
Suzette Hattingh
Page 31 of 133
15-Aug-01
726992262
Based on these principles we recommend that any appointed botanical specialist should:- be qualified in plant ecology and have proven knowledge and experience of the flora likely to occur on the affected site.
- be independent of the proponent as required by EIA regulations (i.e. no financial or other interest in the proposal).
- collect appropriate information on the flora from the proposed site, and in addition note aspects such as:
- unique attributes or sensitive areas (e.g. threatened species, protected species, catchment areas, important links with other natural areas, wetland habitats, etc.).
- condition of the site (e.g. past land use, veldt condition, degree of alien infestation, etc.). Please note that it is often incorrectly assumed that the presence of alien vegetation is sufficient reason to disregard any conservation value of a site.
- assess the relative botanical importance of the site, and possible impacts of the proposal, which should be placed in a local, regional, national and global context.
- where applicable, clearly spell out the conservation management requirements and mitigatory measures for the site.
Subject: Cape Strengthening programme
Date: Wed, 15 Aug 2001 11:54:47 +0200
From: "Kristal Maze" <wildflower@gem.co.za>
To: <Eskomcsp@acerafrica.co.za>
Dear Karin
Further to my email yesterday, I wish to enquire whether it is possible for you to forward us a copy of the botanical specialist report once it is completed. Our input in this
Subject: Fw: CSP - Botanical Soc 2
Date: Wed, 15 Aug 2001 23:30:57 +0200
From: Karin Bowler <karin.bowler@acerafrica.co.za>
To: Kristal Maze <wildflower@gem.co.za>
CC: suzette hattingh <suzette.hattingh@acerafrica.co.za>,
Stuart Dunsmore <stuartjd@icon.co.za>, Nadia Mol
<Nadia.Mol@pdna.co.za>,
<dougjeff@iafrica.com>
Doug Jeffery
Good day Kristal
Page 32 of 133
process would be based mainly on botanical grounds.
Regards
Kristal
Thank you once again for your e-mail and your interest in this project. The Draft Scoping Report contains the findings of the specialists during the Scoping Phase. Although the comment phase for the Draft Scoping Report Has lapsed, you may still wish to read through same for interest.
I will enquire as to whether this report can be sent to you electronically of if it will be necessary to direct you to the
Eskom website where the whole Draft Scoping Report is available.
I will inform you within the next day or two.
In terms of the Environmental Impact Report that will contain the complete specialist report for the Environmental Impact
Assessment Phase, it is currently envisaged that this should be available towards the end of the year. You will also be informed of this by mail.
Kindest regards.
Karin Bowler
Co/Org
Name
Mail to
Institution of Nuclear
Longden-Thurgood, RM, Mr
5 Nerina Street, Milnerton, 7441
Tel/Fax/Cell/e-mail 021 552 6634, 021 552 6634, , mikethurgood@yebo.co.za
Date Issue Raised Comment
16-Jul-01 E-mail Received Please let me know where the nearest copy of the draft
Action
Subject: ESKOM 765 kV Transmission line - Website
726992262 Page 33 of 133
24-Jul-01 Telephonic Discussion scoping report for the Eskom omega project is available to be read, relative to Milnerton, Cape Town.
Please note that the web site as given in the public notice appears not to be available - my server is unable to access it.
Do you not have a list of the I&AP's who were involved in the meetings held at the Koeberg Visitors Centre about three years ago?
R M Longden-Thurgood
Date: Mon, 23 Jul 2001 20:19:03 +0200
From: Suzette Hattingh <suzette.hattingh@acerafrica.co.za>
To: mikethurgood@yebo.co.za
Dear Mr Longden-Thurgood
Thank you for your interest shown in this project. Unfortunately the voluminous and technical nature of the Draft Scoping Report precludes us from sending out electronic copies or additional hard copies. However, the salient issues have been summarised into a
Draft Impact Table, which we are in a position to forward electronically.
Should you wish to peruse the full Draft Scoping Report, we attach a list of the venues at which this Report is available.
Eskom has informed us that technical difficulties are currently being experienced with the website. We apologise for the inconvenience and we sincerely hope that this will be sorted out in due course.
Kind Regards
Suzette Hattingh
- Represents the environmental interests of the members of the
Institute of Nuclear Engineers.
- Was involved in the consultation process, meetings and site visits for the proposed Omega sub station nearly four years ago.
- Read the Draft Scoping Advert in the Sunday Times. Thought that the 765 kV was part of this project
- Discussed the 765 kV project in broad terms.
- Understands that the two projects are separate issues.
- Will continue to try and access the Eskom website. If unsuccessful, will go to a public venue to peruse report.
- He makes a point of reading the report cover to cover. - Is interested in attending the ERF.
- ACER will forward an ERF invitation, Draft Impact tables and list
726992262 Page 34 of 133
Co/Org SAHRA
Name
Mail to
August, Ianda, Ms
P O Box 1930, Kimberley, 8300
Tel/Fax/Cell/e-mail 053 831 2537, 053 833 1435, , sahra-nc@iafrica.com
Date Issue Raised Comment
26-Mar-02 Draft
Correspondence
EIR Request electronic copy
Name
Mail to
Hart, D, Mr
P O Box 4637, Cape Town, 8000
Tel/Fax/Cell/e-mail 021 462 4502, 021 461 0738, , dhart@sahra.org.za
Date Issue Raised Comment
18-Jul-01
726992262 of DSR viewing venues.
- Non project related: What is current status of the Omega site?
- KB reported back on discussion with J Geeringh:
- EIA process has been completed. Eskom has purchased and rezoned the farm Groot Olifantshoek. Situated on the western side of the N7. Power lines already run through this farm. Farm is situated between the N7 and the lane of historic trees on the way to
Malmesbury.
Action
Copy sent 09 April 2002.
Action
Dear Mr Hart
ENVIRONMENTAL IMPACT ASSESSMENT FOR THE
PROPOSED 765kV TRANSMISSION LINE BETWEEN THE
GAMMA (VICTORIA WEST) AND OMEGA (KOEBERG)
SITES
Increased demand in the Western Cape region for a reliable supply of electricity has necessitated that Eskom Transmission improves the reliability and capacity of the transmission network to the
Western Cape. As part of a strategy to do this, Eskom Transmission has proposed to develop a 765kV transmission line between the proposed Gamma (Victoria West) and Omega substation (Koeberg) sites.
PD Naidoo & Associates, PBA International and ACER (Africa) have been appointed by Eskom Transmission to undertake the environmental impact assessment (EIA) for the proposed 765kV
Transmission line between the Gamma and Omega sites.
Page 35 of 133
726992262
The scoping phase of the EIA has commenced and a draft scoping report has been prepared. A summary of this draft report has been forwarded to your organization for your comment. It is proposed that two environmental review forum workshops will be held in the week 13th to 17th August 2001 to discuss the draft scoping report.
An invitation has been forwarded to you in this regard.
The EIA study was initiated in 1999 and after a period of some 12 months on hold is now being continued with the issue of the draft
Scoping Report. At the same time we are updating our database of interested and affected parties (I&AP’s) particularly where new authorities, municipal demarcation areas, etc. have come into being.
As a result, and given the location and extent of the proposed development, we would like to have the opportunity to discuss the project with you. There are a number of opportunities for this including; comment on the draft Scoping Report (see attached list of venues where this may be viewed), attendance at our
Environmental Review Forums to which you will be specifically invited, or we would be happy to meet with you separately, preferably before or during the Environmental Review Forum meetings (13 to 17 August).
As this is our first point of contact, we will be contacting you telephonically in this regard. However, your early thoughts on the matter would be appreciated.
Should you have any additional information requirements or queries at this stage, please do not hesitate to contact either Stuart
Dunsmore or Nadia Mol telephonically at (011) 486 4730 or (011)
482 2123 respectively.
Yours faithfully
Nadia Mol
PD Naidoo & Associates
Cc Stuart Dunsmore PBA International
Karin Bowler ACER (Africa)
Page 36 of 133
726992262
20-Jul-01 Fax Received
20-Aug-01
Thank you for your letter of 16 July 01 and attached documentation. In terms of the National Heritage
Resources Act (Act 25) of 1999, the heritage issues relating to the project must be addressed in the EIA to the satisfaction of SAHRA.
Given the magnitude of this project, and the potential of such a power line to severely negatively impact the heritage value of its surrounding area, it is requested that a recognised heritage practitioner form part of the team dealing with the EIA. The heritage issues picked up in your document will need expansion for the entire length of the proposed line, and involved issues ranging from archaeology, palaeontology, the built environment, the cultural landscape, visual impacts, sense of place, scenic routes as well as possible issues around cultural or spiritual association.
It would be appreciated if a meeting could be set up in the near future to address the handling of the heritage component of this project.
Fax forwarded to PBA Int. & PDNA.
Telephonic discussion - Karin Bowler
1. Mr Hart is pleased that we are making every effort to involve
SAHRA.
2. He is not sure if his diary will allow him to attend the ERF.
3. Has acknowledged that he has received a letter from SJD & NM.
4. Has indicated that he would prefer a "one-on-one" discussion with yourselves.
5. Agreed to my request that he responds to the ERF invitation by completing the response form provided, for record-keeping purposes.
From: Nadia Mol
Sent: 20 August, 2001 3:32 PM
To: 'DHart@sahra.org.za'
Cc: 'stuartjd@icon.co.za'
Subject: Meeting regarding the 765 kV transmission line
Dear Mr Hart
Thank you for your response. My e-mail has been out of order for about a week and therefore I did not receive your message until today.
Unfortunately we are already back in Johannesburg and are therefore unable to meet with you this week. We are in the process of finalising the scoping report (you should have received a summary report thereof) and will thereafter be drafting the terms of reference for the specialist investigations.
Page 37 of 133
Name
Mail to van Tonder, Kirstin, Ms
P O Box 4637, Cape Town, 8000
Tel/Fax/Cell/e-mail 021 462 4502, 021 462 4500, , kvantonder@sahra.org.za
Date Issue Raised Comment
02-Aug-01 Draft SR Comment Archaeological Phase 1 - will be needed.
Could you please confirm that you have received a summary of the draft scoping report? We have forwarded a summary electronically to Ms Kirsten van Tonder who I believe is also in the Western Cape office of SAHRA. We would appreciate it if you could review this and provide any comment on this document to us as soon as possible (by the end of this week).
The primary sources of impact from an archaeological perspective are likely to be the pylons and access roads. Because the locations for the proposed pylons and access roads have not yet been determined, we are proposing that the archaeological investigation at this stage will entail a desk top study to identify areas that are sensitive and management recommendations. Following more detailed design, an archaeological specialist will be required to go into the field to survey the proposed locations for the pylons and access roads. The more detailed work will be undertaken following the completion of the EIA.
We are happy to forward you a copy of the terms of reference for the archaeological study (for your comment). Please could you let us know if you require this and if you have any further information requirements at this stage.
Yours faithfully
Nadia Mol
Action
Telephoned Ms van Tonder to check whether she will be attending the ERF Workshop and within commented (have not read the DSR at that time) the above.
***
Forwarded the electronic Draft SR Summary copy for her records by post at her request and e-mail.
***
Subject: Cape Strengthening Programme
726992262 Page 38 of 133
726992262
22-Aug-01 E-mail Received From: Kirstin van Tonder
[mailto:KvanTonder@sahra.org.za]
Sent: 22 August, 2001 12:33 PM
To: Nadia.Mol@pdna.co.za
Subject: Re: EIA for the proposed Eskom 765 kV
Dear Nadia
Thank you for your response. It is quite in order for Mr
Hart to be the spokesperson for SAHRA: Western Cape in this respect. The proposed work crosses the boundaries of the assistant regional managers in this office.
Besides Mr Hart, who runs the office as well as his own region, there are three other people running a subregion. Besides myself there are Miss Joanna Marx and
Miss Beverley Crouts - just for your information.
Please communicate with Mr Hart and ask him to copy info to us, as we all need to be kept up to date with this proposal. I also saw his letter - unfortunately only once
I had already sent off mine - and his letter puts our
Date: Tue, 14 Aug 2001 22:37:13 +0200
From: Suzette Hattingh <suzette.hattingh@acerafrica.co.za>
To: KvanTonder@sahra.org.za
Dear Miss van Tonder
Thank you for your comment submitted regarding the
Archaeological phase one investigation.
Your comments have been recorded and sent on to the Project Team, they are currently engaged in the Environmental Review Forum
Workshop and will so in due course reply as soon as possible.
Kind Regards
Suzette Hattingh
***
15/08/01
Forwarded comments to Karin Bowler.
Subject: EIA for proposed Eskom 765 kV transmission line
Date: Wed, 22 Aug 2001 11:54:40 +0200
From: Nadia Mol <Nadia.Mol@pdna.co.za>
To: "'KvanTonder@sahra.org.za'" <KvanTonder@sahra.org.za>
CC: Karin Bowler, Stuart Dunsmore, Suzette Hattingh
Dear Kirsten
Thank you for your comment on the need for an archaeological investigation. Please could you clarify what a "phase one" investigation is.
We have previously been involving Mr Hart from your offices. He was invited to attend the Environmental Review Forum Workshops that were held last week and has been communicating with me with regard to the project. He has also received a summary of the draft scoping report.
Please could you indicate if you wish to be personally involved in this project or if further communication needs to be with Mr Hart as the representative for the Western Cape SAHRA office. Should
Page 39 of 133
22-Aug-01 E-mail Received position very clearly.
As far as the definition of a phase one archaeological investigation goes, I gladly attach a definition given to me by our previous archaeologist, Dr Janette Deacon.
With best wishes
Yours sincerely
Kirstin
From: Kirstin van Tonder
[mailto:KvanTonder@sahra.org.za]
Sent: 22 August, 2001 3:24 PM
To: Nadia.Mol@pdna.co.za
Subject: EIA for Eskom line
Dear Nadia
Would you kindly describe the area to me again which will be impacted upon/covered by the proposed Eskom line, as I cannot find your original document. I need to decide to which municipal area-files to copy our correspondence.
Also please confirm whether your project is at all linked to the Eskom Cape Strengthening programme, documentation for which I received from Suzette
Hattingh (Tel 035-340-2715).
Thank you very much!
With best wishes
Yours sincerely
Kirstin you wish to be personally involved, we will add you to our public involvement database and forward project documentation to you in the future.
I would appreciate it if you could come back to me regarding the definition of a "phase one" investigation and your involvement in the future. My contact details are as follows:
Tel (011) 482 2123 Fax (011) 482 4717
Yours faithfully
Nadia Mol
Subject: Eskom CSP - Municipal details
Date: Thu, 23 Aug 2001 12:28:36 +0200
From: Suzette Hattingh
To: KvanTonder@sahra.org.za
CC: Karin Bowler, Nadia Mol, Stuart Dunsmore
Dear Kirstin
Herewith please find attached, detailed list of Municipal Offices as per our data base, for your information.
I will fax you the Projects Background Information Document for your records.
ACER (Africa) Environmental Management Consultants
Suzette Hattingh
726992262 Page 40 of 133
726992262
23-Aug-01
03-Apr-02 Draft EIR Comments
From: Kirstin van Tonder
[mailto:KvanTonder@sahra.org.za]
Sent: 23 August, 2001 11:52 AM
To: Nadia.Mol@pdna.co.za
Re: Municipal areas within which the 765 kV falls
23 Aug 2001
Dear Nadia
Thank you for your reply. Now things are falling nicely into place and I trust we will see this project moving effectively from here on. It is great when all role players get to know who is who and what has to happen when!
Looking forward to receiving the info from your colleagues, but thanks, I do have a map showing the main towns from a document Suzette e-mailed me.
With best wishes
Yours sincerely
Kirstin
3 April 2002
Dear Karin
ESKOM CSP – 765kV Transmission Line
Thank you for your letter of 20 March 2002 with respect to the above project. In terms of the National
Heritage Resources Act (Act 25) of 1999, the heritage issues relating to the project must be addressed in the
EIA to the satisfaction of SAHRA.
Subject: Municipal areas within which the 765 kV falls
Date: Thu, 23 Aug 2001 11:32:15 +0200
From: Nadia Mol <Nadia.Mol@pdna.co.za>
To: "'KvanTonder@sahra.org.za'" <KvanTonder@sahra.org.za>
CC: "Stuart Dunsmore (E-mail)" <stuartjd@icon.co.za>, suzette.hattingh@acerafrica.co.za
Dear Kirstin
Thank you for your e-mail yesterday.
We are on the same team as Suzette Hattingh - she (ACER Africa) is one of the public involvement consultants.
With regard to the municipal areas within which the project falls,
Bongi Shinga will be forwarding you these details as we have them already (I hope that this helps you). Bongi or Suzette will also be forwarding you a copy of the latest background information document which may also be of some help.
You can also refer to the draft scoping report: a summary of which has been forwarded to you and Mr Hart. There are, however, copies of the full report available in public places and on Eskom's website.
Please let me know if you require further details in this regard.
Yours faithfully
Nadia Mol
Forwarded by Fax to Karin Bowler.
Page 41 of 133
Given the magnitude of this project, and the potential of such a powerline to severely negatively impact the heritage value of its surrounding area, it is requested that a recognised heritage practitioner form part of the team dealing with the EIA. The heritage issues that need to be addressed involve issues ranging from archaeology, palaeontology, the built environment, the cultural landscape, visual impacts, sense of place, scenic routes as well as possible issues around cultural or spiritual association.
It would be appreciated if a meeting could be set up in the near future to address the handling of the heritage components of this project.
Yours sincerely pp K van Tonder
Provincial Manager, Western Cape
GOVT LOCAL
Co/Org Beaufort Wes Munisipaliteit
Name
Mail to van Staden, Roelof, Mnr
Privaatsak X582, Beaufort-Wes, 6970
Tel/Fax/Cell/e-mail 023 415 2121, 023 415 2121 ext 244, 083 415 8461,
Date Issue Raised Comment
29-Oct-01 1:250 000 MAP
Name
Mail to
Welgemoed, DE, Mnr
Privaatsak X582, Beaufort-Wes, 6970
Tel/Fax/Cell/e-mail 023 415 2121, 023 415 2121, ,
Date Issue Raised Comment
29-Oct-01 1:250 000 MAP
Co/Org Blaauwberg Administration
Name
Mail to
Hollis-Turner, Trevor, Mr
P O Box 35, Milnerton, 7435
Tel/Fax/Cell/e-mail 021 550 1091, 021 550 7517, ,
Date Issue Raised Comment
Co/Org
Name
Mail to
29-Oct-01 1:250 000 MAP
Boland Distrik Munisipaliteit
Cordier, A, Mnr
Posbus 91, Worcester, 6849
Action
Action
Action
726992262 Page 42 of 133
Tel/Fax/Cell/e-mail 023 347 0945, 023 342 8766, 082 444 7424,
Date Issue Raised Comment
27-Aug-01 Draft SR Comment Telcon with Mr Cordier.
They have no further comments, will stand with what was given through at the ERF meeting.
Name
Mail to
Nieuwoudt, Ben, Mnr
Posbus 91, Worcester, 6849
Tel/Fax/Cell/e-mail 023 347 0945, 023 342 8766, 083 454 3500,
Date Issue Raised Comment
Action
Action
29-Oct-01 1:250 000 MAP
Co/Org Breede Vallei Munisipaliteit
Name
Mail to
Mercuur, Niel, Mnr
Privaatsak X3046, Worcester, 6849
Tel/Fax/Cell/e-mail 023 348 2800, 023 347 3671, 082 807 2112,
Date Issue Raised Comment Action
Co/Org Cape Town Administration
Name
Mail to
Hyde, M J, Mr
P O Box 82, Cape Town, 8000
Tel/Fax/Cell/e-mail 021 400 3158, 021 421 7697, , mhyde@cct.org.za
Date Issue Raised Comment
29-Oct-01 1:250 000 MAP
27-Aug-01 Draft SR Comment File: 818
Ref: 01/9913ltr Dev/mab
Action
Mr M J Hyde
Interim Convenor: Electricity
City of Cape Town
2001-08-24
Att: Karin Bowler
Cape Strengthening Programme EIA Comment on Draft
Scoping Report
With reference to your letter dated 2001-06-28 inviting comment on the merits and impacts of the proposed
Gamma Omega 765 kV Transmission line, I would comment as follows.
The interests of the City of Cape Town would be best served by developing the transmission system supplying
P O Box 82
Cape Town 8000
Tel : 021 400 3158
Fax: 021 421 7697
29 August 2001
Dear Mr Hyde
Cape Strengthening Programme EIA - Comment on Draft Scoping
Report
Your ref: File 818, 01/9913ltrDev/mab
726992262 Page 43 of 133
726992262 the Cape Metropolitan area in a least cost manner so as to minimise the eventual impact on the cost of bulk supply to the area.
The findings of the Feasibility Study on a 1 000 – 2 000
MW CCGT in the Cape Metropolitan area have been presented by Camala to Eskom, the Dept of Minerals &
Energy , and the National Electricity Regulator. This study shows that there is significant merit in establishing a base load power station in the Western Cape. The anticipated impact on the Eskom transmission system would be to postpone the need for constructing the 765 kV power line, to reduce the electrical losses incurred in transmitting power to the Western cape and to improve system stability.
The study indicates that the present value of the avoided costs resulting from deferment of the transmission system investment and the reduction in electrical losses, taken over the 20 year study period, is estimated to be US$ 440 million with the CPP power station operating as a base load power station. The PV of the savings in deferred investment in the transmission system alone is in the range of US$ 242 million to US$ 290 million depending on the capacity of the power station.
The case for the Cape Power Project is very strong and the project is accordingly being pursued actively.
Reference is made in the draft scoping report to the proposed Cape Power Project as a strategic consideration.
Phase 1 of the strengthening programme has to be completed by 2005. As the Cape Power Project would not be in place by then, there is no objection to this proceeding. However, I am strongly of the opinion that no further decision to invest in the 765 kV power line should be made untill very close attention has been given to the benefits that would accrue from the proposed CCGT power station. In considering such a decision equal weight should be given to the construction of a power station in the Western Cape as to strengthening of the transmission system.
Thank you for your comment received on 27 August 2001. Your response has been captured on the database and your letter forwarded to the EIA Project Management Team for a response from Eskom and inclusion in the final Scoping Report.
We will inform you in due course as to the availability of this report in the public domain. We appreciate your participation in this process.
Kindest regards.
Yours sincerely
KARIN BOWLER
Public Involvement Programme Leader
Page 44 of 133
Yours faithfully
Mr M J Hyde
Interim Convenor: Electricity
City of Cape Town
Co/Org City of Cape Town
Name
Mail to
Poolman, Adrian A, Mr
P O Box 82, Cape Town, 8000
Tel/Fax/Cell/e-mail 021 671 3086, , 083 635 8890,
Date Issue Raised
19-Jul-01
Comment
1 > Would it be possible for you to email me a copy of the
Draft Scoping Report ? At present we here at the City of Cape
Town Control Centre (situated in Newlands) do not have access to the Internet so I am unable to download.
Action
1 > Thank you for your interest, I will pass your request over to Project Management, and will advise you as soon as I hear what arrangements can be made.
2 > Thank you for your prompt response to my request. I shall access the SR at the Civic Centre.
The Scoping Report [SR] may be too big to e-mail, and will be available as of tomorrow, at the following venues:
Cape Town Library, Cape Town Administration * Civic
Center, 12 Hertzog Blvd, 8th Floor, and CMC Administration
* 44 Wales St.
Please advise if one of these is in your reach.
Co/Org
Name
CMC Administration
Ebrahim, AG, Mr
Mail to P O Box 16548, Vlaeberg, 8018
Tel/Fax/Cell/e-mail 021 487 2701, 021 487 2255, ,
Date Issue Raised Comment
29-Oct-01 1:250 000 MAP
Name
Mail to
Jackson, Joanne, Ms
P O Box 16548, Vlaeberg, 8018
Tel/Fax/Cell/e-mail 021 487 2184, 021 487 2255, , jjackson@cmc.gov.za
Date Issue Raised Comment
13-Jun-01 Subject: Contact details
Action
Date: Wed, 13 Jun 2001 16:38:39 +0200
From: "Joanne Jackson" <JJackson@cmc.gov.za>
To: <Suzette.hattingh@acerafrica.co.za>
Hi Suzette,
Details as promised: The switchboard number for the
City of Cape Town is 021 - 400 1111. If you need address information, I'm sure they could direct you to an
Action
Subject: Cape Strengthening Programme
Date: Thu, 14 Jun 2001 11:40:22 +0200
From: Suzette Hattingh
To: Joanne Jackson
Dear Mrs. Jackson
On behalf of the Project Team, I thank you for you valuable input.
Kind Regards
726992262 Page 45 of 133
24-Aug-01
726992262 appropriate person to ask (if they can't help themselves.)
The Mayor (Cllr Peter Marais)
City of Cape Town, Private Bag X9181, Cape Town,
8000.
Interim Manager : Planning and Environment (Mr David
Daniels) 20th Flr, Civic Centre, 12 Hertzog Blvd,
Foreshore , Cape Town , 8000.
Executive Councillor : Planning and Environment (Cllr
Brian Watkyns) Paul Sauer Building, 1 Adderley St,
Cape Town, 8000.
All Executive Councillors would have the same address.
The Executive Councillor for Trading Services (which includes Electricity) is Cllr David Erleigh.
The City Manager's address is the same as the Mayor's.
Electricity Services address is Po Box 82, Cape Town,
8000.
Neil Croucher is the Director.
Hope this helps.
Regards
Joanne
Subject: Fwd: Att : Suzette Hattingh
Date: Mon, 20 Aug 2001 13:40:37 +0200
From: "Joanne Jackson" <JJackson@cmc.gov.za>
To: <Suzette.Hattingh@acerafrica.co.za>
Dear Suzette,
As requested the posters advertising the Cape
Strengthening Programme 765 kV Transmission Line draft Scoping Report were placed in the CMC
Administration.
Suzette Hattingh
Subject: Cape Strengthening Programme
Date: Tue, 21 Aug 2001 04:32:19 +0200
From: Suzette Hattingh
To: Joanne Jackson
Dear Ms Jackson
Thank you for your feedback.
No, it will not be necessary for you to return the DSR viewing register if it is empty Regarding the I&AP registration, I find this all
Page 46 of 133
No members of the public requested to review the report.
The register is hence empty - do you still wish that it be returned to you?
For future reference for other processes you may run, the
CMC Administration's 44 Wale Street office, is generally one that the public does not visit - i.e. not an office at which the public would, for example, pay rates / electricity accounts etc. This may account for the fact that no persons requested the report. re. the IAPs forms that you requested to be returned by
24 August 2001. Unless other people in our organization have returned them indicating they specifically do not wish to be on the IAP list, I suggest you continue to keep them on the IAP mailing list.
Please contact me if you have any queries
Regards
Joanne
Name Weinronk, Eileen, Ms
Mail to P O Box 16548, Vlaeberg, 8018
Tel/Fax/Cell/e-mail 021 487 2133, 021 487 2255, ,
Date Issue Raised Comment
15-Aug-01 Draft
Correspondence
SR Request extension of comment date. in order.
Kind Regards
Suzette Hattingh
Action
Subject: Eskom 765 kV Transmission Line - Draft Scoping Report
Date: Thu, 16 Aug 2001 23:06:04 +0200
From: Karin Bowler <karin.bowler@acerafrica.co.za>
To: eweinronk@cmc.gov.za
CC: suzette.hattingh@acerafrica.co.za
, Stuart Dunsmore
<stuartjd@icon.co.za>, Nadia Mol <Nadia.Mol@pdna.co.za>
Good evening Eileen
We are currently in the field and have only today completed the
Environmental Review Forum Workshops at which additional issues were raised. These will need to be incorporated into the Final
Scoping Report over the next two weeks. As such, I do not foresee a problem in you providing additional comment by the end of next
726992262 Page 47 of 133
726992262
30-Aug-01 Draft SR Comment Ref:M17/9/71/1
Date:30 August 2001
Attention Karin Bowler
Public Involvement Programme Team Leader
Acer (Africa)
PO Box 503
Mtunzini 3867
Fax 035 340 2232
Dear Ms Bowler
CAPE STRENGTHENING PROGRAMME GAMMA
OMEGA TRANSMISSION LINE
We thank you for this opportunity to comment and for the extension to the review period that you have granted us.
However, as discussed with you telephonically, these comments are preliminary technical comments from the
City of Cape Town. It must be appreciated that a 30 day comment period is not adequate for this organization to prepare an informed and integrated comment on a proposal of this significance. Issues raised below could change with a more considered evaluation of the proposal as presented. This organization reserves the right to add to, subtract from, alter and review the issues raised and contained herein. week.
I would like you to confirm by return e-mail if you are comfortable with this arrangement.
Thank you for participating in this project and for making the effort to comment.
Kind regards
Karin Bowler
These issues were incorporated in the Addendum to the Draft Scoping
Report.
Page 48 of 133
726992262
A letter from this organization to DEAT regarding comment period on the proposed PBMR is attached for your information.
The contribution from our CMC Administration Spatial
Planning is attached as submitted. Some of the issues raised therein have been included in the comments below in our early attempts to integrate the comments received.
Comment was also received from the Economic and
Social
Development Department CMC Administration as well as from the Blaauwberg Administration Spatial Planning and Environmental Management. These comments have been incorporated into the following comments.
Comment on this proposal is restricted to the portion of the proposed power-line that falls within the boundaries of the City of Cape Town area.
Anticipated issues relating to the proposed transmission line deal with both the conceptual approach to the EIA and role of the proposed transmission line as well as site specific environmental impacts.
It is critical that the Western Cape has sufficient and diverse electricity supply,infrastructure and network to meet current and future demands that support the
Western
Capes competitiveness as a business location. Therefore, the costs of not ensuring this continued and improved supply must be considered in an evaluation of the impacts.
In terms of the EIA authorization process, the anticipated impacts of the “no-go” option need to be assessed. While the “no-go” option is mentioned in the
DSR, it gives a rather simplistic view of the anticipated impacts. It is recommended that these impacts are further defined so that these impacts can be evaluated against the anticipated impacts of the proposed line.
Page 49 of 133
726992262
The energy generation sector is being broadened to ensure scope for the generation of electricity by independent providers. While it is accepted that electricity generation it is not within the scope of this study, within the above mentioned framework and approach, it is critical to ensure that the proposed transmission line can receive and will purchase additional electricity requirements from local independent producers. This co-operative integrated and holistic approach to the proposed transmission line is essential to its acceptability and to the mitigation of anticipated impacts within the City of Cape Town area.
The DSR does also give some indication of alternatives, ie: above ground or below ground transmission. Below ground transmission is summarily dismissed as too expensive.
However, there might be areas where the visual impact of the line is too onerous and where the scenic beauty would be compromised beyond an acceptable situation. In these instances, it might be useful to have some alternative proposal.
It is recommended that the below ground installation be retained as an option in special circumstances.
In conclusion to the debate on alternatives, the transmission line is presented as a fait a compli and the DSR focuses its attention on mitigating measures in order to limit environmental impacts. The adequacy of this approach is questioned. It is recommended that the section on alternatives be further unpacked as described above.
The draft Scoping Report clearly states that the proposed project will rely on additional capacity being “transported” on the network transmission line in order to ensure a more even and enhanced electricity supply to the Western Cape.
According to the DSR, this additional
Page 50 of 133
726992262 supply is available from excess capacity being produced in Mpumalanga.
This statement in the DSR is of concern as is it in direct contradiction with information contained in the DSR for the proposed PBMR, the motivation for which is the fact that the Mpumalanga power supply is inadequate to meet the electricity demand in the short to medium term. It is anticipated that a number of the major and larger power stations will need to be overhauled or closed down within the near future. If, in the light of this apparent contradiction, the additional capacity in Mpumalanga is only anticipated to be short term, the costs of this investment and its anticipated impacts cannot be justified.
This contradiction in information arising out of the same organization is to be clarified and IAPs advised thereof.
At this stage, it need to be noted that the generation electricity from renewables is consistent with PAWC’s
White Paper on Economic Development. There are currently a number of electricity generation proposals currently being investigated in the Western Cape. Some of these proposals utilize renewable resources. It is recommended that every opportunity for the utilization and absorption of this additional local capacity be made and that this intention be stated clearly in the relevant and supporting documentation.
The draft Scoping Report makes reference to previous
EIA’s for the proposed sub stations undertaken prior to the implementation of the EIA regulations. This statement is misleading and unclear. It is anticipated that these EIA’s were done as part of in-house investigations and feasibility studies and have no authorization status. This statement needs to be confirmed and clarified and IAP need to be advised/informed.
Visual impacts:
It is noted that the site for the proposed Omega station is located at the southern gateway to the City of Cape Town on the N7, one of the significant scenic routes identified
Page 51 of 133
726992262 in the Scenic Drive Network Management Plan. This
Plan must be utilised in the visual impact assessment. A complete and thorough visual impact assessment is required before this proposed site can be considered for support by this organization.
Extent of the Work proposed:
There are concerns that the availability of increased supply will have a knock on effect and existing transmission lines into the city from the Omega site as well as the transmission line between Omega and
Koeberg will be upgraded. The extent of work anticipated in the medium term needs be affirmed and the public and relevant authorities informed. Proper and complete description of proposed development is required. It is also a requirement of the EIA authorization application process that cumulative impacts be addressed.
It appears as though the proposed site of the Omega
Station is the same as one of the sites for the proposed
Eskom Wind Electricity Generation project. This point needs to be clarified and if correct, included for public and authority information
Botanical issues:
It is noted that the botanical core area identified on Farm
Schoongezicht is one of the 37 Core Flora Sites within the City of Cape Town. This information needs to be reflected in the documentation for public and authority information.
It is proposed that The conservation of indigenous vegetation within the power line servitude area should be promoted. A fire management plan for this servitude should be developed. Recent experience in the City of
Cape Town area has not been satisfactory. Therefore it is recommended that this plan should be reviewed by other relevant stakeholders which must include the Cape Flats
Flora Core Conservation Sites Working Group and the
Environmental Management Department of the
Blaauwberg Administration.
Page 52 of 133
30-Aug-01 Draft SR Comment
Other issues:
It has been suggested that the following be submitted for
Council’s consideration. The erection of the powerline structures will need to comply with any relevant legislation. A list of this legislation should be included in the DSR.
Confirm that the West Coast Biosphere Reserve
Management Board and local Ward Councillor has been contacted :
The impact of the development on the existing road infrastructure. A more detailed review of new access points and roads required for the development are required for an informed comment in this regard. It is recommended that these requirements need to be reflected in the description of the proposed activity and of the affected environment
A detailed Environmental Management Plan and
Decommissioning plan
We trust you find the above in order and look forward to your response
Yours faithfully
Eileen Weinronk
Late Comments arrive by fax 30 Aug 2001
Dated 3 Sept 2001
Ref: 30/15/5/2
For Acting Head : Spatial Planning Department
Filed I&AP Draft Scoping Comment section.
Subject: Cape Strengthening Programme - comments on the Draft
Scoping report
Date: Sun, 02 Sep 2001 11:19:52 +0200
From: Karin Bowler <karin.bowler@acerafrica.co.za>
To: Eileen Weinronk <EWeinronk@cmc.gov.za>
CC: suzette hattingh <suzette.hattingh@acerafrica.co.za>,Stuart
Dunsmore <stuartjd@icon.co.za>,
<Nadia.Mol@pdna.co.za>
Nadia Mol
726992262 Page 53 of 133
25-Mar-02 Draft
Correspondence
EIR Subject: Cape Strengthening Programme
Date: Mon, 25 Mar 2002 13:00:13 +0200
From: <Eileen.Weinronk@capetown.gov.za>
To: <Eskomcsp@acerafrica.co.za>
CC: <Joanne.Jackson@capetown.gov.za>,
<Keith.Wiseman@capetown.gov.za>
Thank you for your letter dated 15th March received today , 25th March .
In this correspondence you state that the EIA is available from the CMC administration. However, it is not clear which department this has been forwarded to. I confirm that we have not received this document and hereby request a full copy as soon as possible.
Good day Eileen
Apologies for not acknowledging your e-mail earlier - I have been without a landline in Pretoria. The comments have been faxed to the
Project Management Team and we will be incorporating the final comments into the Final Scoping Report.
I have as yet not been able to view the comments due to the landline problem, but will be communicating with the project team on
Monday.
Thank you for your participation in this project to date.
Kindest regards.
Karin Bowler
Copies forwarded to
S Dunsmore - PBA Int
N Moll - PDNA
K Bowler - ACER (PTA - MBB)
Subject: Report back on CMC contact
Date: Wed, 27 Mar 2002 11:30:33 +0200
From: Nadia Mol <Nadia.Mol@pdna.co.za>
To: <Suzette.Hattingh@acerafrica.co.za>, "Karin Bowler (Email)" karinbow@iafrica.com
CC <stuartjd@icon.co.za>
Dear Suzette and Karin
I have tried to contact Eileen (CMC) telephonically, but she is away until 8th April 2002. Instead I spoke to her colleague, Suzette to let them know that a copy of the report has been forwarded to Mr
Tomalin (CMC) along with an electronic version of the report. She stated that she will let Eileen know of this - but I will also e-mail
Eileen to answer this
726992262 Page 54 of 133
15-Apr-02 Draft
Correspondence
EIR
It is noted in your correspondence that the deadline for comment in 19th April 2002. This period of time for a co-ordinated and integrated comment from ourselves is not adequate and we request an extention of time to at least 60 days for a technical comment and additional 30 days for processing this comment through our political cycle.
In August 2001 we commented on the draft scoping report. We note that we have not received confirmation of receipt of these comments, nor any notification of a record of decision regarding the scoping report and are hence perplexed that the EIA is already out for comment.
Please respond to these queries and requests as soon as possible Many thanks
Eileen Weinronk
Review Co-ordinator
Environmental Management Department
Cape Metropolitan Council Administration
City of Cape Town query as well as her others. Will copy the e-mail to both of you.
Regards
Nadia
Subject: Draft EIR 765 kV Transmission line
Date: Fri, 12 Apr 2002 12:46:43 +0200
From: Sebola Shaka <SebolaS@pdna.co.za>
To: <eileen.weinronk@capetown.gov.za>
CC: <stuartjd@icon.co.za>, <karinbow@iafrica.com>,
<SuzetteHattingh@acerafrica.co.za>, <Nadia.Mol@pdna.co.za>
Dear Eileen
This serves as a record of the discussion that was held between
Shaka Sebola and Eileen Weinronk on 10th April 2002 regarding the request for extension of the review period.
* The Cape Metropolitan Council has requested that the
726992262 Page 55 of 133
726992262 current 30-day review period be extended to 60-days on the basis that they find it difficult to get hold of their Councillors who should ratify the comments that the council raise regarding the reports they normally review.
* the CMC sought clarity as to how the concerns and comments raised are addressed following the closure of the comments period.
* The CMC also feels that the 2-week period following the closure of the comments period and the submission of the final report to
NDEAT may be inadequate to address issues raised.
* The basis for this argument is that they forwarded comments during the review of the draft scoping report and never got a copy of the final scoping report to determine if the issues raised were addressed.
* Additional electronic copies are not desired.
In response to the above the following were highlighted:
* extension of the review period cannot be granted on the basis that the Project team has made a commitment to the client to submit the final EIR on the 30th April 2002.
* the reports that are issued to the public (serving as a record of the findings of the study, including discussion with interested and affected parties) are in draft form- implying that the IAPs are granted an opportunity to determine whether the issues they raised are correctly captured. Following the closure of the comments period the issues that have been raised are incorporated into the final reports and then submitted to the authorities.
* regarding the adequacy of the incorporation period, is difficult to say whether the feeling is true because the nature of the issues that may be raised is unknown. The study team, however, believes that this is a sufficient period to address any issues- assuming that all major issues have been raised during the scoping phase and prior to the compilation of the draft EIR report.
* The final scoping report was not made available for public comment and issues detailed on the draft scoping report were recorded in the draft EIR.
* Additional electronic copies of the draft EIR can be forwarded to the CMC if required to speed up the comments period.
regards
Shaka Sebola
For PD Naidoo & Associates
Page 56 of 133
17-Apr-02 Draft EIR
Correspondence
Subject: Re: Draft EIR 765 kV Transmission line
Date: Tue, 16 Apr 2002 13:30:00 +0200
From: <Eileen.Weinronk@capetown.gov.za>
To: <SebolaS@pdna.co.za>
CC: <SuzetteHattingh@acerafrica.co.za>,
<Keith.Wiseman@capetown.gov.za>,
<karinbow@iafrica.com>, <stuartjd@icon.co.za>,
<Nadia.Mol@pdna.co.za>
Dear Sebola
Thank you for your email in which you confirm your understanding of our discussion.
There are a number of issues contained therein that appear to have been misunderstood. Unfortunately I do not have the time at this stage to respond to each point therein.
However, there is one issue in particular that requires urgent correction.
The City of Cape Town is one legal entity and is governed by legal processes and delegations. These processes and delegations must be respected in the course of all our work including review.
Thus the problem of submitting political comment within the given time period is not an issue of making contact with
Councillors but rather with respect to Council's legal processes and delegations, supported by the approvals of relevant Heads. The request for comment from relevant sectors of the organization, review period, integration of comments received, responding to queries and concerns from relevant Heads and gaining their approval precedes processing of the comment through acknowledged legal processes of this Council.
726992262 Page 57 of 133
I trust that this clarifies for you our requirement of sufficient time to review and comment.
Please note that the CMC (Cape Metropolitan Council) no longer exists. The correct name is the City of Cape Town
(CCT). The CMC is now an Administration of the CCT and is referred to as the Cape Metropolitan Council
Administration (CMCA) of the CCT.
Issues regarding the incorporation and response to comments are unfortunately not particular to this application process and will be raised both in our comments on this process and with the authorizing agency at both a local and provincial level.
The reason for not extending the deadline is inadequate - the agreement between the consultant and their client has no bearing on the issue raised by us regarding formal comment. This has a bearing on the adequacy of the process and is of concern to us. We trust that this clarifies our situation to some extent.
As requested in our telephone discussion, please confirm that you will be able to receive comment up until 30th
April as confirmed with Mr Tomalin and myself telephonically last week.
Trust in order
Regards
Eileen Weinronk
726992262 Page 58 of 133
17-Apr-02 Draft EIR Correspondence
726992262
Subject: RE: 765kV Gamma-Omega
Date: Wed, 17 Apr 2002 12:45:38 +0200
From: "Karin Bowler" <karinbow@iafrica.com>
To: "Eileen Winlock" <Eileen.Weinronk@capetown.gov.za>,
"John Gearing" <John.Geeringh@eskom.co.za>
CC: "Carol Streaton" <Carol.Streaton@eskom.co.za>, "Ernest
Grunewald" <Ernest.Grunewald@eskom.co.za>,
<pbai@iafrica.com>, <Nadia.Mol@pdna.co.za>, "suzette hattingh"
<suzette.hattingh@acerafrica.co.za>
Dear John & Eileen
Thanks for sending this information through to me, I will ensure that same is recorded on the database.
Eileen, to confirm, my e-mail to you earlier this week becomes irrelevant, thus not requiring direct response from you. However, should you still wish to comment on its contents, please feel free.
I will also ensure that Suzette Hattingh effects the necessary changes on the database i.r.o CMC changing to Cape Metropolitan
Council Administration, City of Cape Town.
Kind regards
Karin Bowler
PBA International
Cell: 082 809 7624
-----Original Message-----
From: John Geeringh [mailto:John.Geeringh@eskom.co.za]
Sent: Wednesday, April 17, 2002 10:53 AM
To: Eileen.Weinronk@capetown.gov.za]
Cc: Carol Streaton; Ernest Grunewald; karinbow@iafrica.com
; pbai@iafrica.com; Nadia.Mol@pdna.co.za
Subject: 765kV Gamma-Omega
Hallo Eileen, thank you for your time on the phone this morning. This is just to confirm our discussion and hopefully address your concerns.
Page 59 of 133
17-Apr-02 Draft EIR Correspondence
726992262
We would like to thank you for meeting us halfway with the comments period and would like to stress that your final comments are welcome even after the date of 30 April 2002. We will submit the
EIA report to DEAT and they normally take approximately 60 days to respond, therefore some time will still be available. They are also dependant on receiving in[put from the provincial authority from the
Western Cape as well as the Northern Cape. Your comments and concerns will be forwarded to DEAT but I can assure you that we will respond to them directly to you. Our responses to your comments will also be forwarded to DEAT at the same time.
Kind regards and please say Hallo to Steven Granger for me.
John
From: stuart [mailto:stuartjd@icon.co.za]
Sent: Saturday, April 13, 2002 1:47 PM
To: Nadia Mol; Karin Bowler
Subject: Fw: Draft EIR 765 kV Transmission line Importance: High
Hi, After seeing this I'm even more keen that one of you please contact Eileen Weinronk to see that she is satisfied with things. I'd feel more comfortable that the queries raised by CMC are addressed with a bit more depth. As Karin's name is on the letter issued with the reports, I suggest she be the first to make contact (ASAP!). Any
PIP issues can be dealt with at the same time. If there are any technical issues, then Nadia should take over. This will hopefully give CMC the level of attention they want at the moment. They will be an important commentator on our draft EIR and I'd rather they comment with a positive attitude. If they think we are being hardnosed about it all they will be more aggressive.
Please let me know what transpires.
thanks stuart
Page 60 of 133
02-May-02 Draft EIR Correspondence From: Eileen Weinronk
[mailto:Eileen.Weinronk@capetown.gov.za]
Sent: Thursday, May 02, 2002 2:28 PM
To: Nadia.Mol@pdna.co.za
Cc: Keith Wiseman; karinbow@iafrica.com
; stuartjd@icon.co.za
Subject: Re: Comment on the draft EIR for the Eskom
765kV Transmission line
Nadia hi
Thanks for your email and tel conversation
This confirms earlier email correspondence with your organization that we will submit to you directly ASAP - but not necessarily before 30 th
Also please note that this comment is from the City of
Cape Town and not CMCA. trust of value
Eileen
1.
From: Nadia Mol [mailto:Nadia.Mol@pdna.co.za]
Sent: Thursday, May 02, 2002 10:47 AM
To: 'Eileen.Weinronk@capetown.gov.za'
Cc: Stuart Dunsmore (E-mail); Karin Bowler (E-mail)
Subject: Comment on the draft EIR for the Eskom 765 kV
Transmission line
Dear Eileen
This is just a reminder that we are still waiting for comment from the
CMCA on the draft EIR for the proposed Eskom 765 kV
Transmission line. The extended comments period closed on Tuesday
30th April 2002 and we are now required to finalise the draft report.
Please could you forward any comments that you may have on this document to us urgently.
Yours faithfully
Nadia Mol (PD Naidoo & Associates)
2.
From: Nadia Mol [mailto:Nadia.Mol@pdna.co.za]
Sent: Thursday, May 02, 2002 11:33 AM
To: Stuart Dunsmore (E-mail); Karin Bowler (E-mail); John
Geeringh (E-mail)
Cc: 'Eileen.Weinronk@capetown.gov.za'
Subject: Comment on draft EIR
Dear Stuart, Karin and John
I have just chatted to Eileen and she has mentioned that she has circulated the draft EIR to the necessary internal departments and to date has only received one comment back. She is thus anticipating that she will only be able to get the CMCA's comments through to us in a weeks time.
726992262 Page 61 of 133
She is aware of our previous submission date and I stated that we would prefer to include the CMCA's comments in our addendum report rather than forward these individually to DEA&T following submission.
Regards
Nadia
Co/Org
Name
Drakenstein Municipality
Carstens, J, Mr
Mail to P O Box 1, Paarl, 7622
Tel/Fax/Cell/e-mail 021 807 4500, 021 872 8054, , ceo@drakenstein.gov.za
Date Issue Raised Comment Action
29-Oct-01 1:250 000 MAP
Name
Mail to
Knaggs, Jimmy, Mr
P O Box 12, Paarl, 7622
Tel/Fax/Cell/e-mail 021 807 4707, 021 872 8054, , jimmy@drakenstein.gov.za
Date Issue Raised Comment
11-Aug-01 E-mail Received I will be attending the Ceres (ERF) meeting but need some background Information, especially a proposed route map.
Action
Thank you for your interest shown in this project. Unfortunately the voluminous and technical nature of the Draft Scoping Report precludes us from sending out electronic copies or additional hard copies. However, the salient issues have been summarised into a
Draft Impact Table which we are in a position to forward electronically.
17-Aug-01 > From: Jimmy Knaggs <Jimmy@drakenstein.gov.za>
> To: <jwhyte@mweb.co.za>
> Sent: Friday, August 17, 2001 10:36 AM
> Subject: ESKOM route
> ** Reply Requested by 8/20/2001 (Monday) **
> Hi
Should you wish to peruse the full Draft Scoping Report, with has a detailed 1 : 250 000 Map included depicting the proposed route & corridor. (I attach a list of the venues at which this Report is available.)
Subject: Re: ESKOM route
Date: Tue, 21 Aug 2001 09:35:19 +0200
From: IMAGIS <jwhyte@mweb.co.za>
To: Jimmy Knaggs <Jimmy@drakenstein.gov.za>
CC: Nadia Mol, "PBAI (network)", Suzette Hattingh, Karin
Bowler
Good Morning Jimmy
726992262 Page 62 of 133
726992262
> Just to remind you about the electronic info for the route for the new 765kV line. We need at least the section from Tulbagh to the Berg River.
> It would be useful if it was in WGS 84 and a Shape file. Please include the existing 400kV line route if possible.
>
> Regards
> Jimmy
Following my message to you earlier this morning, it appears as though I have bypassed standard protocol in my frustration with
MWEB's sloppy service. There are particular requirements regarding the recording of all communications in a public participation process that need to be addressed.
The deadline for comments from the stakeholder workshops is 24
August 2001. This deadline needs to be met as the independent consulting team has to collate all stakeholder issues shortly thereafter for the final draft scoping report. Please note, however, that this is by no means the last opportunity that your organisation will have to make comment as this project will go into the next phase where stakeholders will again play an important role. As you will see above, this message has been copied to both the project managers and the public participation coordinators. Should the Drakenstein
Municipality identify any potential conflicts with the proposed alignment of the 765kV line and their current and proposed planning initiatives, please would you be so kind as to forward these issues to
Karin Bowler at the email address provided above. Karin will ensure that any issues are discussed with yourself and appropriately collated into the scoping report. As discussed with yourself at the workshop in Ceres on Thursday last week, I appreciate that the current planning initiative of the Interim Integrated Development Plans
(IDPs) is embryonic at this stage. I sincerely hope that the digital data provided to you may facilitate the identification of any potential conflicts observable in previous planning exercises undertaken by the Municipality. Be assured, however, that your organisation will have the opportunity to make further input to this process once you have had the time to firm up on your IDP. I have been involved in many IDPs around the country and fully appreciate your frustration with the current status of interim planning that the newly demarcated
Municipalities have been thrown in to. If there is any way that I could be of assistance to you or your organisation, please do not hesitate to call.
Once again, on behalf of the team, thank you for your very valuable input to the Ceres workshop. We look forward to future collaboration.
Page 63 of 133
Co/Org
Name
Karoo Hoogland van Sittert, Aletta, Mev
Mail to Posbus 24, Sutherland, 6920
Tel/Fax/Cell/e-mail 023 571 1020, 023 571 1089, 082 460 4317,
Date Issue Raised Comment
29-Oct-01 1:250 000 MAP
Co/Org Laingsburg Munisipaliteit
Name
Mail to
Visser, Fanie (SA), Mnr
Privaatsak X4, Laingsburg, 6900
Tel/Fax/Cell/e-mail 023 551 1019, 023 551 1019, ,
726992262
Kind regards
Chris Whyte
PS - I have also attached the existing power network as you requested to assist in orientation.
----- Original Message -----
From: IMAGIS <jwhyte@mweb.co.za>
To: Jimmy Knaggs <Jimmy@drakenstein.gov.za>
Cc: PBAI (network) <pbai@iafrica.com>
Sent: Tuesday, August 21, 2001 7:48 AM
Subject: Re: ESKOM route
> Morning Jimmy
> Sorry about not replying yesterday, but it appears as though
MWEB, my service provider, is currently undergoing upgrades and shut down the server from about 12pm yesterday. As you can imagine, this caused havoc with my plans yesterday.
>> Herewith the proposed line you saw at the workshop, plus the two alternative routes identified at the workshop. These files are in shapefile format in the Clarke 1880 ellipsoid - your guys can project these directly into their system. Call me if you need any help
>. Thanks for all your input to the workshop. If you see any red flags regarding these line alignments and your current planning, please let the team know ASAP. Thanks again
>
> Kind regards
> Chris
Action
Page 64 of 133
Date Issue Raised
06-Jul-01 Telephonic Discussion
Comment
Mr Visser were interested to know where the line where going to run.
Action
Invited Mr Visser to the Laingsburg Farmers' Assoc. meeting.
Received route details from Koos van der Merwe (Eskom), and in a returned call explained to Mr Visser that the proposed line will be from Victoria West to Beaufort West following the current line and up to Komsberg near Sutherland close to the Capacitor Substation and from there to Ceres with a five meter flexibility.
Mr Visser was satisfied with information given
29-Oct-01 1:250 000 MAP
Co/Org Swartland Munisipaliteit
Name
Mail to
Janse van Rensburg, C, Mnr
Privaatsak X52, Malmesbury, 7299
Tel/Fax/Cell/e-mail 022 482 2996, 022 482 2935, ,
Date Issue Raised Comment
29-Oct-01 1:250 000 MAP
Co/Org
Name
Mail to
Tulbagh Munisipale Kantoor
Bezuidenhout, Gert, Mnr
Posbus 3, Tulbagh, 6820
Tel/Fax/Cell/e-mail 023 230 1020, 023 230 1250, ,
Date Issue Raised Comment
29-Oct-01 1:250 000 MAP
Co/Org Ubuntu Munisipaliteit
Name
Mail to
Nothnagel, Emil, Mnr
Privaatsak X329, Victoria-Wes, 7070
Tel/Fax/Cell/e-mail 053 621 0026, 053 621 0368, ,
Date Issue Raised Comment
29-Oct-01 1:250 000 MAP
Co/Org Witzenberg Munisipaliteit
Name
Mail to
Schuurman, JW, Mnr
Posbus 44, Ceres, 6835
Tel/Fax/Cell/e-mail 023 316 1854, 023 316 1877, ,
Date Issue Raised Comment
29-Oct-01 1:250 000 MAP
Action
Action
Action
Action
726992262 Page 65 of 133
Co/Org Witzenberg Munisipaliteit
Name
Mail to
Swanepoel, Johan, Mnr
Posbus 44, Ceres, 6835
Tel/Fax/Cell/e-mail 023 313 3545, 023 313 3688, 083 457 2375,
Date Issue Raised Comment
22-Apr-00 Draft EIR Comments19 April 2002
Ref: 16/3/4
Gamma-Omega 765 kV Transmissielyn: Omgewings Impak
Studie - Beswaar: Witzenberg Munisipaliteit
Hiermee kommentaar en beswaar op Konsep Omgewings
Impak verslag gedateer Maart 2002.
Daar word kennis geneem van die verskillende opsies van roetes wat in die verslag voorgele word. Hierdie munisipaliteit het reeds in die vorige skrywe beswaar gemaak teen die voorgestelde roete, “Alternate Central
Route” & “Preferred Alignment”. Daar word volstaan by die vorige kommentaar en besware van hierdie munisipaliteit soos vervat in raadsbesluit 10.7 van 26 September 2001.
Action
These comments have been incorportated in the Addendum to the
Draft EIR.
Die volgende verdere kommentaar en beswaar op die nuwe
“Preferred Alignment” soos vervat in die dokument:- Dit word gemerk dat die roete suid van Gydopas en dan deur munisipale meentgronde beweeg. Ingevolge die plaaslike
Struktuurplan is hierdie gronde geoogmerk vir toekomstige nywerheids, behuising en natuur area. Die Transmissielyn met gepaardgaande serwituut sal hierdie areas tragmenteer wat toekomstige onwikkeling sal ontwrig en kostes soos byvoorbeeld van infrastruktuur sal verhoog.
- Dit word ook gemerk dat die roete oor Hugo’s Berg in ‘n westelike rigting beweeg. Dit word genoem dat aan die westekant van Hugo’s Berg nog ‘n bergreeks loop bekend as die Skurweberg alvorens die lyn in die Witzenberg Vallei in beweeg.
726992262 Page 66 of 133
23-Aug-01
726992262
Twee redelike hoe bergreekse moet derhalwe gekruis word tussen Prince Alfred’s Hamlet en die Agter-Witzenberg
Vallei wat onprakties en nie koste-effektief is.
Met bogenoemde ingedagte asook vorige besware in ag geneem volstaan hierdie munisipaliteit by sy vorige aanbeveling van ‘n roete, naamlik langs die bestaande 400 kV lyne, of soos in die konsep genoem, die “Alternative
Southern Route”
Ons dank u vir die geleentheid om kommentaar te lewer en glo dat die besware en aanbevelings ter harte geneem sal word.
Die uwe
JH Swanepoel nms MUNISIPALE BESTUURDER
Subject: Summary report and issues table for 765 kV
Date: Thu, 23 Aug 2001 11:21:21 +0200
From: Nadia Mol <Nadia.Mol@pdna.co.za>
To: pahamlet@witzenberg.gov.za
CC: Stuart Dunsmore, Karin Bowler, Suzette Hattingh
Dear Mr Swanepoel
Please find the attached summary document including the issues table that you requested at the Environmental Review Forum workshop in Ceres. We would appreciate your comment on this document by the end of this week if possible).
Please contact me telephonically at (011) 482 2123, by fax at
(011) 482 4717 or by e-mail: nadia.mol@pdna.co.za, should you have any queries.
Yours faithfully
Nadia Mol <<ERF summary1.doc>>
Page 67 of 133
726992262
29-Aug-01 Draft SR Comment Subject: Comments on Draft Scoping Report: Eskom Cape
Strengthening Programme: Objection/Comments
Witzenberg Municipality
Date: Wed, 29 Aug 2001 16:49:23 +0200
From: "pahamlet" <pahamlet@witzenberg.gov.za>
To: <eskomcsp@acerafrica.co.za>
CC: "Dana Du Plessis" <dana@ceres.org.za>
Suzette Hattingh / Karin Bowler
The Draft Scoping Report dated July 2001 as well as discussions at a workshop held on 16 August 2001 at
Ceres regarding above mentioned, refers.
The issue was discussed at a meeting of the Development and Planning Committee, Witzenberg Municipal Council, on 21 August 2001. It was decided to raise an objection against the proposed route selected. The reasons are as follows:
- The route crosses the slopes of the Waboomsberg in the
Ceres valley which are habitat to the Geometric Tortoise
(PSAMMOBATES GEOMETRICUS). It is the only South
African land tortoise that appears on the International Red
Datalist. This type of tortoise are very specific regarding it's habitat and are not found in any other type of habitat.
- The route crosses the upper slopes of Gydo Pass, Agter
Witzenberg Pass, Witzenberg Valley as well as the Breede
River Valley, 1km south of Tulbagh. On this route the line will have a huge visual impact against the surrounding rural and natural areas. Ceres is well known for its natural beauty and the line along this route will not only have a negative impact on tourism but will also create a loss of place for the local inhabitants. Tourism is regarded as a strong upcoming industry and the region is in the beginning phases of exploiting this market. Snowfalls attracts tourists by the thousands each year and the area just above Gydo Pass is a favorite visiting place. The proposed line crosses Tulbagh just a kilometer to the south, the town is well known as a tourist attraction with a historical background and buildings.
Subject: Comments on Draft Scoping Report
Date: Fri, 31 Aug 2001 09:01:42 +0200
From: Karin Bowler <karin.bowler@acerafrica.co.za>
To: pahamlet@witzenberg.gov.za
CC: suzette hattingh <suzette.hattingh@acerafrica.co.za>, Stuart
Dunsmore <stuartjd@icon.co.za>,Nadia
<Nadia.Mol@pdna.co.za>
Mol
Dear Johan
Thank you for your comments received on 29 August 2001.
I have forwarded your comments to Stuart Dunsmore and Nadia
Mol to ensure that all the issues are captured in the Final Scoping
Report. Your letter serves to confirm many issues that were raised during our discussions around the maps during the second session.
The Witzenberg Municipality will indeed be receiving a copy of the Final Scoping Report. However, it is normally requested that this be made available to the public for viewing, does this create a problem for you and would it be necessary to arrange for an additional copy?
May I also take this opportunity to thank you for attending the
ERF meeting at Ceres. The contribution made by key stakeholders proved valuable.
Kindest regards
Karin Bowler
Page 68 of 133
It is proposed that the new line follow the existing routes of the two 400 kV lines crossing the Witzenberg Municipal area as the existing lines already creates a visual impact.
Please send us a copy of the final draft when finished. For more information you can contact Johan Swanepoel at
Witzenberg Municipality.
Yours truly
Johan Swanepoel
29-Oct-01 1:250 000 MAP
Co/Org Wolseley Administrasie
Name
Mail to
Strydom, A, Mnr
Privaatsak X4, Wolseley, 6830
Tel/Fax/Cell/e-mail 023 231 1021, 023 231 1361, ,
Date Issue Raised Comment
29-Oct-01 1:250 000 MAP
Co/Org WPK
Name
Mail to
Walters, A, Mnr van der Stell Str 195, Tulbagh, 6820
Tel/Fax/Cell/e-mail 023 230 1076 /7, 023 230 0942, ,
Date Issue Raised Comment
Action
Action
06-Jan-01 Telephonic Discussion Questioned the information requested on the
Registration form.
GOVT NATIONAL
Co/Org Dept of Mineral & Energy
Name
Mail to
Agenbagh, GA, Mr
Private Bag X9, Roggebaai, 8012
Tel/Fax/Cell/e-mail 021 419 6105, 021 419 6260, ,
Date Issue Raised Comment
Made arrangements to delivering 1: 25 000 MAP to him. He decided to rather look at this to see where the line will run to forward us landowner names.
Action
Phoned Karin Bowler, sent details for fastmail through to Pbai.
23-Apr-00 Draft
Correspondence
EIR Request map of route for the Western Cape.
Co/Org Ministry of Agriculture,
Name
Mail to van Rensburg, HG, Mr
Private Bag X9179, Cape Town, 8000
Tel/Fax/Cell/e-mail 021 483 4700, 021 483 3890, ,
726992262 Page 69 of 133
Date Issue Raised
01-Nov-01
Comment
Dear Ms Bowler
CSP: Integrated Env Mngmnt Legislation - ROD
Action
Thank you for your letter dated 1 October with regards to the Records of Decision.
We are satisfied with the mentioned process, and do not have any queries.
Kind regards
HG van Rensburg
Co/Org Ministry of Health
Name
Mail to
Meyer, P, Mr
P O Box 2060, Cape Town, 8000
Tel/Fax/Cell/e-mail 021 483 2171, 021 483 2217, ,
Date Issue Raised Comment
27-Mar-02 Draft EIR Correspondence 27 March 2002
Action
Dear Ms Bowler
The CSP 765 kV Transmission line: draft EIR
By direction of Mr P Meyer, MPP, Minister of Health, I acknowledge receipt of your letter dated 20 March
2002.
Kindly note that the above mentioned documentation has been referred to Mr Malatsi, Minister of
Environmental Affairs & Development Planning, for his attention and finalisation.
Kind regards
Herman van der Westhuizen
GOVT PROVINCIAL
Co/Org Dept of Land Affairs
Name
Mail to
Smit, David, Mr
Private Bag X5007, Kimberley, 8300
Tel/Fax/Cell/e-mail 053 831 4090, 053 831 4095, 082 822 5102,
726992262 Page 70 of 133
Date Issue Raised
26-Mar-02 Draft
Correspondence
EIR
Comment
Request hard copy
Co/Org Minister of Environmental
Name
Mail to
Malatsi, DM, Mr
P O Box 15653, Vlaeberg, 8000
Tel/Fax/Cell/e-mail 021 483 3915, 021 483 6081, ,
Date Issue Raised Comment
09-Apr-02 Draft EIR 09 April 2002
Correspondence
CSP Gamma-Omega 765 kV Transmission Line
By direction of Mr DM Malatsi, Minister of
Environmental Affairs and Development Planning, I acknowledge receipt of your letter dated 20 March 2002, the contents of which have been noted.
The matter is receiving attention.
Action
Yours faithfully
Mariaan Meyer
Appointed Secretary
Action
Subject: RE: 765 draft EIR
Date: Wed, 27 Mar 2002 15:18:29 +0200
From: "Karin Bowler" <karinbow@iafrica.com>
To: <Suzette.Hattingh@acerafrica.co.za>
CC: "Nadia Mol" <Nadia.Mol@pdna.co.za>
I spoke to David Smit this morning:
He understood that the copies are too expensive to reproduce. He was happy with the suggestion that he contacts Mr Edwin Segole at the Northern Cape Dept of Agric, Nature Conserv, Land Reform &
Env to have access to their hard copy. I also suggested that he tries to establish if this dept has electronic facilities available so that he may access the CD version.
Regards
Karin Bowler
726992262 Page 71 of 133
Co/Org National Electricity
Name
Mail to
Ellman, MJ, Dr
P O Box 785080, Sandton, 2146
Tel/Fax/Cell/e-mail 011 884 0118, 011 884 4355, , michaele@ner.org.za
Date Issue Raised Comment
24-Oct-00 The NER has not been informed about this proposed
Action
765kV project from Bloemfontein to Cape Town
(announced earlier this year) which has major implications for the South African transmission network.
These are projects which could impact on Eskom
Transmission’s bottom line and the NER would need to decide whether this project is in the interest of the ESI – before it is implemented!
Did you also handle the EIA for this project? I would appreciate it if you could send me a comprehensive and detailed information pack on the EIA as soon as possible, preferably by fax or e-mail.
Dr Ellman
04-Apr-02 Draft
Correspondence
EIR Subject: Electronic copies of the 765 kV Transmission line EIR
Date: Wed, 27 Mar 2002 11:38:43 +0200
From: Nadia Mol <Nadia.Mol@pdna.co.za>
To: michaele@ner.org.za
Dear Interested and Affected Party
Thank you for your recent e-mails requesting further information on the draft EIR for the proposed Eskom 765 kV Transmission line between Gamma and Omega. A CD of this report is currently being fast-mailed to you.
Please contact Suzette Hattingh (ACER, Africa) should you have any further queries. Her contact details are as follows:
Tel (035) 340 2715
Fax (035) 340 2232
E-mail: Suzette.Hattingh@acerafrica.co.za
Yours faithfully
Nadia Mol - PD Naidoo & Associates
726992262 Page 72 of 133
Co/Org Office of the Premier
Name
Mail to
, ,
Private Bag X20538, Bloemfontein, 9300
Tel/Fax/Cell/e-mail 051 405 5799, 051 405 4803, ,
Date Issue Raised
27-Mar-02 Draft
Correspondence
EIR
Comment
Office of the Premier
Free State Office – Bloemfontein.
27 March 2002
Acknowledgement of receipt of letter: The CSP 765 kV
Transmission line: draft EIR
We hereby wish to acknowledge with appreciation receipt of your correspondence dated 15 March 2002, with regards to the above mentioned subject, the contents of which have been noted.
Please be informed that your correspondence has been referred to the MEC, entrusted with Environmental,
Tourism & Economic Affairs, Ms TS Balot, for his attention.
Action
However we suggest that you make follow up with his office at this number 051 403 3728.
We hope you find the above in order.
With kindest regards
Thabo Masukela Administrative Secretary to the Premier
Co/Org Western Cape Nature
Name
Mail to
Gerber, Gerhard, Mnr
Private Bag 5014, Stellenbosch, 7800
Tel/Fax/Cell/e-mail 021 889 1560, 021 889 1523, , gerberg@cncjnk.wcape.gov.za
726992262 Page 73 of 133
Date Issue Raised
20-Aug-01 Fax Received
Comment
Ref: JNO17/8/3 Cape Strengthening Programme
20 August 2001
Att: Karin Bowler
The Cape Strengthening Programme: Gamma – Omega
765 kV transmission Line Environmental impact
Assessment: Scoping Phase Continuation
Action
Subject: Eskom Cape Strengthening Programme - 765 kV
Transmission Line
Date: Wed, 29 Aug 2001 15:11:25 +0200
From: Karin Bowler <karin.bowler@acerafrica.co.za>
To: gerberg@cncjnk.wcape.gov.za
CC: Stuart Dunsmore <stuartjd@icon.co.za>, Nadia Mol
<Nadia.Mol@pdna.co.za>,
<suzette.hattingh@acerafrica.co.za> suzette hattingh
Good day Dr/Mr Gerber
Your Ref No.: ECSL3.01
In response to you letter to Dr Kas Hamman dated 28
June 2001.
PRIMARY I&AP
With the establishment of the Western Cape Nature
Conservation Board on 1 April 2000, the Board came to separate entity from the Department of Environmental &
Cultural Affairs and Sports (DECAS). Whereas in the past members of Cape Nature conservation used to assist the
Environmental Impact Management Unit of the
Department with development application evaluation and authorisation, the Board will no longer be an authorising body, but rather one of the primary interested and affected parties that will have to be consulted during the Scoping
Process of the IEM procedure.
Herewith then the Board would like to request that it is registered as an I&AP for the CSP.
CO-ORDINATION OF BOARD”S INPUT & COPY OF
RECORDS
With a number of different employees of the Board
Thank you for your fax of 20 August 2001. Apologies for the delay in response. I have tried today to contact you by telephone 14:
29pm, 29 August 2001, unfortunately there was no reply.
This e-mail serves to acknowledge your letter and to respond to the following:
1. Thank you for emphasising the role of the Cape Nature
Conservation Board.
2. Although this is considered by DEA&T to be a national project,
We have since the start of this project with Paul Hardcastle (now, as you know, with DECAS) and have sought his advice on various issues.
3. We would like to amend our database according to your request,
I would however like you to confirm whether we should DELETE or MAINTAIN the following individuals: a. Dr Hamman b. Mr F P Viljoen c. Mr J van Deventer d. Mr D Laidler e. Mr H Stadler
726992262 Page 74 of 133
30-Aug-01
726992262
Having received the I&AP registration form, it would be best that all correspondence is routed through Scientific
Services. We will then consult with Operational Services and co-ordinate the Boards Input.
Being a primary I&AP, we also request our own copy of the Draft Scoping report (and other documentation).
Gerhard Gerber
The Manager: Scientific services
From: Gerhard Gerber < gerberg@cncjnk.wcape.gov.za>
To: Karin Bowler <karin.bowler@acerafrica.co.za>
Date: 30 August 2001 07:06
Subject: RE: Eskom Cape Strengthening Programme –
765kV
Hi Karin Bowler
4. Mr van Deventer was invited to attend the Environmental
Review Forum workshop held on 16 August 2001 in Ceres at which the summary of the Draft Scoping Report was discussed.
Unfortunately he was unable to attend. However he received a copy of the Draft Impact Table which summarizes all the issues identified during the Scoping Phase.
5. Although the comment period has closed for the Draft Scoping
Period, copies of the report are available at the Cape Library and the
Bloubergstrand Library (we have requested that the librarians catalogue the report), and from the Eskom Website: www.eskom.co.za/story/omega.htm.
6. If you are comfortable with this, approach, I would suggest that you respond to the Final Scoping Report that will be available during September (dates to be confirmed). It will also be available for public viewing at selected libraries and municipal offices and the
Project Team would welcome your comment. Although none of the other key stakeholders (apart from the DECAS, Northern Cape
DEA&T & National DEA&T) are receiving their own copy, I will put this request forward to the study team. (as per a database copy of your original fax attached hereto).
Should you have any further queries, please do not hesitate to contact me directly on 082 809 7624.
Kindest regards
Karin Bowler
Public Involvement Programme Leader
Subject: Eskom Cape Strengthening Programme
Date: Fri, 31 Aug 2001 08:44:29 +0200
From: Karin Bowler <karin.bowler@acerafrica.co.za>
To: Gerhard Gerber <gerberg@cncjnk.wcape.gov.za>
CC: suzette hattingh suzette.hattingh@acerafrica.co.za
>, Nadia
Mol <Nadia.Mol@pdna.co.za>, Stuart Dunsmore
<stuartjd@icon.co.za>
Page 75 of 133
With reference to my fax of 20 August 2001 and in response to your e-mail of 29 August 2001, the following:
I&AP Registration
In response to your point 3 the following - a. Dr Hamman - DELETE b. Mr F P Viljoen - DELETE c. Mr J van Deventer - DELETE d. Mr D Laidler - Dennis Laidler & Paul Hardcastle are both with the Sub-Directorate: Environmental Impact
Management of the Department of Environmental and
Cultural Affairs and Sport (EIM: DECAS) e. Mr H Stadler - DELETE
The Western Cape Nature Conservation Board should thus only be listed once, with Kevin Shaw being the contact person (e-mail: shawka@cncjnk.wcape.gov.za ; tel: 021-8891560 & fax: 021-8891523).
Draft Impact Table
Please forward a copy of the "Draft Impact Table" mentioned in your point 4 to Kevin Shaw.
Copy of Final Scoping Report
Although the Board would like its own copy of the final report, we trust that a copy will also be available on the
Eskom Website.
Kind regards,
GERHARD GERBER
Name
Mail to
Shaw, Kevin, Mnr
Private Bag 5014, Stellenbosch, 7800
Tel/Fax/Cell/e-mail 021 889 1560, 021 889 1523, , shawka@cncjnk.wcape.gov.za
Morning Gerhard Gerber
Thanks for your quick and informative response. It is not always easy weaving our way through the intricate web of departments.... much appreciated.
I will instruct my office as per this e-mail to make the necessary changes to the database as instructed by you. (Suzette Hattingh -
Please confirm when these changes have been made.)
A Draft Impact Table will be forwarded by e-mail to Mr Shaw.
(Suzette Hattingh - Please confirm when this has been done).
I am also forwarding this e-mail to the Project Team Manager to request a individual copy for the Board.
It is important that the Final Scoping Report be available on the
Eskom Website as many stakeholders accessed it via this means.
Stakeholders will be informed of the address as soon as it becomes available.
Kindest regards
Karin Bowler
726992262 Page 76 of 133
726992262
Date Issue Raised
24-Oct-01
30-Oct-01
Comment
Phoned regarding his concern as to if the final Scoping
Report has been made available.
Action
Subject: Eskom 765 kV - Final Scoping Report
Date: Wed, 24 Oct 2001 21:42:57 +0200
From: Karin Bowler <karinbow@iafrica.com>
To: Stuart Dunsmore <stuartjd@icon.co.za>, Nadia Mol
<Nadia.Mol@pdna.co.za>
Dear Nadia and Stuart
Suzette has been contacted by Mr Kevin Shaw from the Western
Cape Nature Conservation Board phoned regarding his concern as to if and when the Final Scoping Report have been or may be made available. The following comment:
1. I get this uncomfortable feeling that we are headed for some trouble in the public domain if DEA&T doesn't fulfil their duties shortly, we may be presented with some difficulties.
2. One of us should phone Mr Shaw and explain that we will be bringing out the Revised Impact Tables – in stead of the Final
Scoping Report.
Please advise.
Karin
Subject: Cape Strengthening Programme: EIA
Date: Tue, 30 Oct 2001 09:22:11 +0200
From: "PBAI (network)" <pbai@iafrica.com>
To: shawka@cncjnk.wcape.gov.za
CC: Karin Bowler <karinbow@iafrica.com>, Suzette Hattingh
<Suzette.Hattingh@acerafrica.co.za>, Nadia Mol
Nadia.Mol@pdna.co.za
Dear Mr Shaw,
I am the project manager for the EIA for Eskom's proposed 765kV
Transmission line between the Omega and Gamma sub-stations
(Koeberg and Victoria West respectively), and I have been asked by the Public Involvement Consultant (ACER Africa) to contact you regarding the issue of the Scoping Report for the study. I apologise that I didn't get back to you last Friday as promised, and I understand from your office that you are on leave this week.
Page 77 of 133
726992262
04-Apr-02 Draft EIR Correspondence Subject: Omega - Gamma
Date: Mon, 25 Mar 2002 16:05:47 +0200
From: "Kevin Shaw" <shawka@cncjnk.wcape.gov.za>
To: <eskomcsp@acerafrica.co.za>
Dear Karin
I have received your letter CSP EIR.LO7 dated
15/03/2002 today. It will not be possible for me to get to any of the venues stipulated in your letter, before the due date. Would it not be possible to email me a copy the draft EIR, or is it not available on the web page.
Regards
K.A. Shaw
The Scoping Report has been finalised and is due for delivery to
National DEA&T and the provincial offices this week. Although it is not intended to print and release the full document in the public domain, extracts of the document are being sent to all the key stakeholders who were invited to the Environmental Review Forum meetings in Beaufort West and Ceres in August. There are some 200 of these, and I believe you have a list of them. Your organisation is on the list and you should be receiving the document in the next few days. The content of the document is comprehensive in terms of the issues and their levels of impact, as well as what is intended for study in the EIA phase.
I hope that this will be sufficient for your needs at this stage. Iwill be away next week, but will be available from the 12th November should you require more discussion on the matter. Please e-mail me or leave a message at my office if need be.
Regards
Stuart Dunsmore
Subject: Electronic copies of the 765 kV Transmission line EIR
Date: Wed, 27 Mar 2002 11:38:43 +0200
From: Nadia Mol <Nadia.Mol@pdna.co.za>
To: shawka@cncjnk.wcape.gov.za
CC: "Karin Bowler (E-mail)" <karinbow@iafrica.com>, "Stuart
Dunsmore (E-mail)" <stuartjd@icon.co.za>,
<Suzette.Hattingh@acerafrica.co.za>
Dear Interested and Affected Party
Thank you for your recent e-mails requesting further information on the draft EIR for the proposed Eskom 765 kV Transmission line between Gamma and Omega. A CD of this report is currently being fast-mailed to you.
Please contact Suzette Hattingh (ACER, Africa) should you have any further queries. Her contact details are as follows:
Tel (035) 340 2715, Fax (035) 340 2232,
E-mail: Suzette.Hattingh@acerafrica.co.za
Yours faithfully
Nadia Mol - PD Naidoo & Associates
Page 78 of 133
726992262
16-Apr-02 Draft EIR Comments Western Cape
Nature Conservation Board
Scientific Services
Ref./Verw:JNO 25/4
Enquiries/Navrae:K.A. Shaw
Date/Datum:12 April 2002
COMMENTS ON THE DRAFT ENVIRONMENTAL
IMPACT REPORT: GAMMA – OMEGA 756kV
TRANSMISSION LINE
Comments are restricted to the specialist studies carried out on the effect that the proposed line would have on the avifauna and ecology, although some comments are relevant to the other studies that were commissioned.
General
1. The report considers the impact of the transmission line on a broad scale in that it only considers where the proposed routes are to be sited and even this is indicated as a 500m corridor. It should therefore be considered as a document, the purpose of which is to determine the best route that the transmission line should follow between Victoria West and Koeberg and the approval thereof will allow ESKOM to carry out more finer planning along the selected route which will be subjected to further scrutiny by interested and affected parties (I&AP’s). Seen in this light the document fulfils its function. If, however, the purpose of this document is to serve as an environmental impact report of the project in it’s entirety then it has serious shortcomings. Foot prints of pylons (albeit small) and other constructions like access roads and construction camps (which can have major impacts a fact substantiated by most of the specialists in their reports) associated with a development of this nature have not been evaluated by the specialists for the simple reason that they have not been identified on the ground. It is only once these foot prints have been identified and evaluated by the specialists that I&AP’s can truly evaluate whether all
Subject: Eskom 765 kV EIA Draft EIR comment
Date: Wed, 17 Apr 2002 09:29:00 +0200
From: "Karin Bowler" <karinbow@iafrica.com>
To: <shawka@cncjnk.wcape.gov.za>
CC: <Nadia.Mol@pdna.co.za>,
<suzette.hattingh@acerafrica.co.za>
Dear Kevin
In acknowledgement of the receipt of your comments on the Draft
EIR for the abovementioned EIA:
Thank you for the effort you have taken in reviewing the Draft EIR, it is a substantial document and demands a great deal of attention from Interested and Affected Parties.
Your response has been forwarded to the various specialists for review and additional comment. Your document, together with the specialist comments will be incorporated in the final EIR.
Our appreciation and kind regards
Karin Bowler
PBA International
Cell: 082 809 7624
Page 79 of 133
issues have been satisfactorily addressed and whether the mitigation and management measures proposed will in fact reduce the expected impact. Figure 1 of Chapter 1 is a table showing the processes that have been followed and gives the impression that this process will end with the approval of this document. If this is the case Western Cape Nature
Conservation Board (WCNCB) cannot support the development as it is of the opinion that this document is insufficient to evaluate the entire development.
2. It is disturbing to note that a large percentage of the specialists indicated that their evaluation had to be carried out under time and/or budgetary constraints. Considering the magnitude of the development and the possible effect it can have on the social and natural environment, one would have expected that this important aspect
(Environmental Impact Report) of the development phase be properly catered for. WCNCB is, however, satisfied that the ecological specialist and the avifaunal specialist has done enough work and provided enough information to be able to make a satisfactory decision as to the correct route.
It is, however imperative that the report should be followed by a more detail evaluation once the sites of the pylons, access roads, construction camps, and any other activity associated with a development of this nature have been identified on the ground (i.e. the footprint of the development needs to be physically determined and this also needs to go through the Environmental Impact
Assessment process.).
Avifauna specialist report
1. The report states that there are three types of impacts of power lines on birds: electrocutions, collisions and loss of habitat. The specialist is of the opinion that the two potential impacts that the proposed line would have are collisions and disturbance of nesting Martial Eagles on the nearby 400kV lines. It is unclear from the document whether the activity of clearing servitudes under lines will take place. If the vegetation is reduced either in height or density under these lines the open areas created could attract large terrestrial birds that have a preference to open
726992262 Page 80 of 133
areas increasing the probability of bird-power line interactions. If clearing below the lines is going to occur it is recommended that the specialist be requested to reevaluate whether this would have an effect on bird-power line interactions.
2. In the light of the fact that power lines are having a bigger impact on birds than what was originally thought (as indicated by the specialist) it is disturbing that only sections
1 and 2 were physically inspected (although not the entire route) and a desktop study plus personal knowledge of the area were used to evaluate sections 3, 4 and 5.
This was due to time and budget constraints. WCNCB would to recommend that sufficient time and funding be allocated to the specialist, enabling the specialist to carry out a thorough investigation of the entire line.
3. Proactive mitigations methods are recommended by the specialist along certain identified high risk sections of the line, which will definitely reduce the number of collisions.
The specialist, however, states that areas, especially in sections 3, 4 and 5 may not have been identified due to the methodology applied to identify high-risk areas.
Furthermore it is not possible to identify all high-risk areas.
Change of habitat (change of land use, construction of dams) in the future may attract certain bird species to areas presently not utilized by them. New collision sites may therefore be identified once the line has been erected.
WCNCB would like a commitment from ESKOM to implement mitigation measures as soon as new sites are identified in order to reduce the number of interactions between power lines and birds.
4. The report does not make provision for mitigation measures preventing electrocution of birds. The specialist has recommended the cross-rope suspension type pylon structure, which provides very limited perching sites thus limiting bird electrocutions. Unfortunately this type of structure cannot be used in steep mountainous terrain nor where the route changes at a 3° angle. At these sites it is proposed that a self-supporting tower (Figure 4, Chapter 1) will be used. While the specialist is of the opinion that the structures used on the large lines (275 – 765kV)
726992262 Page 81 of 133
usually pose no threat to birds the report does not clearly state what the possibilities are of electrocutions occurring on the self supporting structure. It is also interesting to note that the 400kV structures (similar in design to the proposed self-supporting 765kV structure) near Koeberg have been fitted with mitigation measures preventing birds from perching on them. WCNCB recommends that the specialist evaluate the potential of bird electrocutions on the selfsupporting structures and recommend applicable mitigation measures should they be required.
5. The specialist has recommended that the line be monitored on a six monthly basis to determine the effectiveness of the mitigation measures (Collision summary
(annex B) and assessment (annex F) tables). It should, however, be stipulated that ESKOM must monitor the entire length of the line in order to identify other sites where collisions occur.
Ecological specialist report
1. The specialist has compiled a very comprehensive report, but unfortunately because the area (500m wide strip between
Koeberg and Victoria West) which had to be covered was so large and the fact that the actual foot prints of the development had not (and possibly still have not) been identified it was not possible to provide information as to what the actual effect of the development will be on the environment. In order to compensate for this the specialist has made a number of recommendations which include amongst others, evaluation of the site pictures by an ecologist/botanist once the sites have been identified, the consultation of an ecologist with the placing of pylons and associated developments through sensitive areas, and the incorporation of various procedures and mitigation measures in the EMP. While WCNCB supports the recommendations and insist that they should be implemented, we would like to once again point out that the report does not deal with sitespecific issues except in the broader sense and we cannot support the development if it is to be approved based on this
EIR report.
726992262 Page 82 of 133
2. The specialist makes a number of recommendations with regards to rehabilitation. Rehabilitation is incorrect terminology and what the report should be referring to is restoration. Restoration must be implemented in all the areas, which have been affected by the development. These areas must be restored to the same state as that prior to the development. Restoration is a specialist field, and WCNCB recommends that a specialist (possibly two, one for the fynbos and one for the Karoo biome) be employed/contracted in to advise, supervise and monitor the restoration process. Furthermore restoration should be carried out to the satisfaction of the specialist and not the landowner as recommended in the report
Concluding remarks
WCNCB would like to reiterate that the environmental impact report adequately addresses the proposed and alternative routes of the transmission line. In this regard
WCNCB is willing to accept that the Central Route is the route that the transmission line should follow. This acceptance is only valid if the recommendations made by the respective specialists and in this letter are incorporated into the planning/development process. The report, however, provides very little (if any) information illustrating the effect of the development footprint on the environment. WCNCB can therefore not recommend that the proposed development be approved in its entirety while the actual footprint (site of pylons, construction camps, access roads, etc) of the development has not been subjected to the EIA process.
For: Manager (Scientific Services)
Nms. Bestuurder (Wetenskaplike Dienste)
Co/Org Western Cape Provincial
Name
Mail to
Ozinsky, Max, Mr
P O Box 648, Cape Town, 8000
Tel/Fax/Cell/e-mail 021 483 3238, 021 483 3883, 082 414 7147,
726992262 Page 83 of 133
Date Issue Raised
16-Jul-01 E-mail Received
23-Aug-01
Comment
Could you please email me a copy of the Draft Scoping report, and also register the ANC Western cape Env.
Desk as an I&AP.
Action
Emailed explaining time availability applies and that if he need further assistance at later stage he should let me know.
Mr Ozinsky telephonically requested an copy of the
DSR to be e-mailed to him
23 Aug 2001
Checked whether Mr ozinsky has been able to access the website.
Subject: ESKOM 765 kV Transmission line - Website
Date: Mon, 23 Jul 2001 20:19:03 +0200
From: Suzette Hattingh <suzette.hattingh@acerafrica.co.za>
To: mozinsky@pawc.wcape.gov.za
Dear Mr Ozinsky
I would like to extend this invitation to the Environmental Review
Forum Workshop to you.
Please find attached:
Invitation & Agenda
Preamble and draft SR Summary
Invitation and I&AP list
We look forward to your participation.
Kind Regards
Suzette Hattingh
JOB SEEKER/CONTRACTOR
Co/Org
Name
Mail to
ABB (South Africa)
Ravera, Claudio, Mr
Private Bag X37, Sunninghill, 2157
Tel/Fax/Cell/e-mail 011 236 7230, , , claudio.n.ravera@za.abb.com
Date Issue Raised Comment
16-Jul-01 Saw advert in Sunday Times.
Visited the website and read through report.
Company constructs towers.
Commented on footprint and noted that visual impacts and footprints should be considered for different farming activities, as this could have negative impact.
Would like to be kept informed of the project.
Action
Phoned ACER, Karin Bowler Contact him/got hold of 18 July 2001.
726992262 Page 84 of 133
LANDOWNER/RESIDENTS
Co/Org
Name
Mail to du Toit, Calla (CVDM), Mnr
Posbus 17, Prince Albert Hamlet, 6840
Tel/Fax/Cell/e-mail 023 313 3190, 023 313 3708, 082 445 4483,
Date Issue Raised
20-Aug-01 Telephonic Discussion
Comment at Ceres.
Action
Phoned regarding not being included in the ERF Workshop 21 Aug 01
Karin Bowler’s telcon with Mr du Toit - the main points:
1.Explained that the ERF was at a representative level.
2.The following issues he raised with me, have been recorded in the Comment & Response Document and are part of the Draft
Scoping Report:
- The historical cannon.
- The historical walls that were destroyed during the construction of the 400 kV lines.
- There is a lane of historical trees under the existing 400 kV line that were damaged during construction. These should be avoided with the 765kV
He has not yet seen the Draft Scoping Report & will make the effort to do so. I have asked him to inform ACER in writing if he is not satisfied with the manner in which we have captured the issues in the C&R document.
3. He also brought to my attention the following:
- The area over the Witzenberg mountains where the 400 kV currently runs and where the 765kV was originally planned, is considered to be of historical significance. For this reason alone, he feels that the route should be reconsidered.
- The route over the Witzenberg mountains should also be avoided from a visual and ecological perspective. He says that there are many sensitive plant species in this area.
- The access route to construct the 400kV was never rehabilitated properly and concrete slabs which should have been removed, are still there.
- He is concerned that the EMPs are of no value as these are not properly managed by either Eskom or the contractor.
726992262 Page 85 of 133
4. I explained that Eskom had held a special round of talks with the farmers' associations, but that these had not been very well attended.
He concurred that this may have been as a result of the holidays.
Mr du Toit belongs to the Ceres farmers' association, the current chairman is Mr Anton Bredel.
17-Apr-02 Draft EIR Correspondence Mr Calla du Toit telephoned.
- Unhappy with route. (- Giving up land used for fresh fruit.)
- Extend invitation to project team to visit for a meeting with the Farmers Association and to have a proper Site
Visit.
- Will fax comments and objections in writing.
Name
Mail to du Toit, Retief (RC), Mnr
Posbus 150, Ceres, 6835
Tel/Fax/Cell/e-mail 023 313 3242, 023 313 3594, , RC91@mweb.co.za
Date Issue Raised Comment Action
07-Sep-01 Trust/ID Nr.: 6903115076084
Name
Mail to
Engelbrecht, JJ & MH, Mnr & Mev
Posbus 339, Ceres, 6835
Tel/Fax/Cell/e-mail 023 312 2504, , ,
Date Issue Raised
07-Sep-01 Trust/ID Nr.:
Comment
1601275025082
Action
Name
Mail to
Lombard, J, Mnr
Posbus 46, Tulbagh, 6820
Tel/Fax/Cell/e-mail 023 230 0784 /5, 023 230 0740, , lombardfam@xsinet.co.za
Date Issue Raised Comment
07-Sep-01 Trust/ID Nr.: 5301315101086
Action
The following was agreed:
- Mr du Toit will send in written comment together with photographs of the areas of concern.
- He understands that there will be additional opportunity to comment in the future.
- He would appreciate a meeting with the Eskom negotiators during the next phase.
- It may be best that Eskom attends the association's meeting.
726992262 Page 86 of 133
Name
Mail to
Loubser, Nico, Mnr
P O Box 205, Riebeech Kasteel, 7307
Tel/Fax/Cell/e-mail , , 083 412 3113,
Date Issue Raised Comment Action
27-Mar-02 Draft EIR Correspondence Mr Loubser called regarding getting clarity of where the line would run and/or if it would be crossing his property.
Mr Daniel boshoff from ESKOM contacted Mr H Truter regarding this matter.
Suzette Hattingh informed Mr Loubser to contact Mr Truter.
Name
Mail to
Reitz, FHW, Mr
Posbus 29, Wolseley, 6830
Tel/Fax/Cell/e-mail 023 231 0904, 023 231 0904, 082 411 3795,
Date Issue Raised Comment Action
07-Sep-01 Trust/ID Nr.: 3901045065188
Name
Mail to
Smuts, Johan (JB), Mnr
Posbus 272, Malmesbury, 7299
Tel/Fax/Cell/e-mail 022 482 2074, 022 482 2074, 082 452 9482,
Date Issue Raised
03-Aug-01 Draft SR Comment
Comment
Toekomstige Toerime Atraksie - weens natuurskoonheid
Action
Broeiplek - kruisarend
Verskeie advertensie aanbiedinge
19-Sep-01 Swartland Farmers
Meeting
Issues Raised:
1.In the low point where we propose the line crosses the
Porseleinberg there is a Black Eagles nest - this should be confirmed during the avifaunal study.
2.The low point through the Porseleinberg is a preferred route for racing pigeons.
3.They were concerned that the terrain was not suitable for a power line - I explained that the terrain seemed suitable but that this would be confirmed during the EIA phase.
4.The line passes close to the houses and “werf” of
Dassenheuwel and Tweekuil - this is true but I explained that the line can be finally placed behind the houses as well.
5.They indicated that the area was used for filming adverts - my answer was that if the line had to be placed
726992262 Page 87 of 133
across the Swartland this may be a problem along all routes.
6.There is a 4X4 route on the Porseleinberg at this point - it seems that this route is very seldom used and I do not necessarily see this as a highly significant issue.
7.Health - EMR
8.A power line through their wheatlands will be problematic for crop sprayers (aeroplanes)
9.There is a crop sprayer landing strip on Tweekuil close to the proposed route.
10.THE FARMERS OF THE AREA HAVE NOT BEEN
NOTIFIED - they say that they attended the open day at
Malmesbury and filled in the attendance list/or had their names and addresses taken but have not received any notifications since and were not notified of the availability of the scoping report. they say there are a number of farmers who still don't know of the proposed line.
Acknowledged that a power line has to cross somebody’s property but feel that they have legitimate reasons why the route is not entirely satisfactory. Alternative possible routes
-Sept 2001 1.Realign the route from once the line crosses the Berg
River near Gouda, southwards to link up with our alternative from the existing line below Voëlvlei Dam across below the Porseleinberg.
2.Cross the Porseleinberg just north of the proposed route somewhere. The line will then be visible as it crosses the mountain but this may be better than a long way around the bottom of the mountain range.
Name
Mail to
Venter, Jan (JH), Mr
P O Box 405, De Aar, 7000
Tel/Fax/Cell/e-mail 053 631 0821, 053 631 1155, 083 722 1818,
Date Issue Raised Comment Action
07-Sep-01 Trust/ID Nr.: 4808135074088
Co/Org Ouplaas Trust
Name
Mail to du Toit, Josua (JJ), Mnr
Posbus 17, Prince Albert Hamlet, 6840
Tel/Fax/Cell/e-mail 023 313 3190, 023 313 3708, 082 445 4483,
Date Issue Raised Comment
07-Sep-01 Trust/ID Nr.: 3811245017089
Action
726992262 Page 88 of 133
Co/Org Tweekuil Plase
Name
Mail to
Louw, Albertus (AJ), Mnr
Posbus 1, Malmesbury, 7299
Tel/Fax/Cell/e-mail 022 482 3057, 022 482 3057, 082 321 1681,
Date Issue Raised
07-Sep-01 Trust/ID Nr.:
19-Sep-01 Swartland Farmers
Meeting
Comment
7007295015083
Action
Issues Raised:
1.In the low point where we propose the line crosses the
Porseleinberg there is a Black Eagles nest - this should be confirmed during the avifaunal study.
2.The low point through the Porseleinberg is a preferred route for racing pigeons.
3.They were concerned that the terrain was not suitable for a power line - I explained that the terrain seemed suitable but that this would be confirmed during the EIA phase.
4.The line passes close to the houses and werf of
Dassenheuwel and Tweekuil - this is true but I explained that the line can be finally placed behind the houses as well.
5.They indicated that the area was used for filming adverts - my answer was that if the line had to be placed across the
Swartland this may be a problem along all routes.
6.There is a 4X4 route on the Porseleinberg at this point - it seems that this route is very seldom used and I do not necessarily see this as a highly significant issue.
7.Health - EMR
8.A power line through their wheatlands will be problematic for crop sprayers (aeroplanes)
9.There is a crop sprayer landing strip on Tweekuil close to the proposed route.
10.THE FARMERS OF THE AREA HAVE NOT BEEN
NOTIFIED - they say that they attended the open day at
Malmesbury and filled in the attendance list/or had their names and addresses taken but have not received any notifications since and were not notified of the availability of the scoping report. they say there are a number of farmers who still don't know of the proposed line.
Acknowledged that a power line has to cross somebody’s property but feel that they have legitimate reasons why the route is not entirely satisfactory. Alternative possible routes
726992262 Page 89 of 133
-Sept 2001 1.Realign the route from once the line crosses the Berg
River near Gouda, southwards to link up with our alternative from the existing line below Voëlvlei Dam across below the Porseleinberg.
2.Cross the Porseleinberg just north of the proposed route somewhere. The line will then be visible as it crosses the mountain but this may be better than a long way around the bottom of the mountain range.
Co/Org Witzenberg Properties (Pty)
Name
Mail to du Toit - Die Bestuurder, Francois (FJ), Mnr
Posbus 293, Ceres, 6835
Tel/Fax/Cell/e-mail 023 313 3347, 023 313 3729, ,
Date Issue Raised Comment Action
07-Sep-01 Trust/ID Nr.: Co Reg No.: 1954/000760/07
Name
Mail to
Prins - Plaasbestuurder, Johan (JB), Mnr
Posbus 120, Ceres, 6835
Tel/Fax/Cell/e-mail 023 313 3110, 023 313 3532, ,
Date Issue Raised Comment
07-Sep-01 Trust/ID Nr.: Co. Reg. No.: 1954/000760/07
Name Theron - Plaasbestuurder, Jannie (JO), Mnr
Mail to Posbus 92, Ceres, 6835
Tel/Fax/Cell/e-mail 023 313 3108, 023 313 3486, ,
Date Issue Raised Comment
07-Sep-01 Trust/ID Nr.: Co Reg No.: 1954/000760/07
ORGANISED BUSINESS
Co/Org ESKOM - Transmission
Name
Mail to
Willemse, Douw, Mr
P O Box 1047, Oakdale, 7530
Tel/Fax/Cell/e-mail 021 915 9279, 021 915 9285, ,
Action
Action
726992262 Page 90 of 133
Date Issue Raised
22-Apr-00 Draft
Correspondence
EIR
Comment
>>> Douw Willemse 04/19/02 02:32PM >>>
Hallo John,
Skakel my asb. dringend ivm die EIA en die kommentare.
Die tyd was min om te kyk na die dokument. Kan jy asb verseker dat die huidige bird interactions en die talle foute wat tans op die bestaande lyne voorkom, ingesluit is in die verslag. Dit lyk vir my of ons ernstig moet kyk na die foute voordat ons sommer gaan en die lyne in dieselfde korridors plaas.
Verder wil ek hoor of ons 'n verslag op 'n stadium onder oë kan kry. En het julle met Distribusie ook gesels, veral oor die uitbreidings wat hulle in die Ceres gebied doen?
Soos ek sê, ek kon nie daarby uitkom om 'n dag of twee daar by die biblioteek te gaan sit en die document deurwerk nie.
Action
From: John.Geeringh@eskom.co.za
Sent: Monday, April 22, 2002 8:45 AM
To: Douw Willemse
Cc: karinbow@iafrica.com
Subject: Re: Cape Strengthening EIA
Ek kan vir jou 'n afskrif van die EIR op 'n CD kry as jy sou belangstel. 'n Hard copy kos meer as R1000-00 om te verkry. Die inligting rakende die interactions sal nog verdere detail studie kry, ons probeer 'n ROD kry vir 'n korridor sodat ons kan negotiate.
Detail studies vir Argeologie, plantegroei en voëls sal ook nog tydens die EMP fase gedoen word, met spesifieke mitigation.
Laat weet maar of jy 'n CD wil hê.
John
Maar skakel my asb, miskien kan ek jou Dinsdag daar bo sien, alhoewel my dag redelik vol is.
Groete uit 'n warm Kaap; ek dink dis die hoogdruk voor die koue front.
Douw G Willemse
Senior Environmental Advisor
Transmission Western Region
Co/Org
Name
Mail to
National Electricity
Boeije, Willie, Mr
P O Box 785080, Sandton, 2146
Tel/Fax/Cell/e-mail 011 263 9820, 011 884 4355, , willie@ner.org.za
726992262 Page 91 of 133
Date Issue Raised
22-Nov-01 Draft SR Comment
Comment
Subject: Cape Strengthening
Date: Thu, 22 Nov 2001 12:32:17 +0200
From: "Willie Boeije (Senior Manager IRP)"
To: "'eskomcsp@acerafrica.co.za'"
21 November 2001
Per Email to eskomcsp@acerafrica.co.za
Dear Karin
CAPE STRENGTHENING PROGRAMME:
COMMENTS ON DRAFT SCOPING REPORT
Thank you for your letter dated 29 October. Herewith some further comments on the documents provided.
Strategic Alternatives
The conclusion of item 1.1 cannot be considered in isolation. The transmission licensee has the obligation to transmit subject to minimum standards on quality of supply. If the quality of supply standards can no longer be guaranteed, the transmitter will either have to invest in new transmission capacity or encourage the entry of generation, or both depending on the economics at the time. If agreements cannot be reached in time the transmitter has to commit to those options under his control. There may, however, be options other than the construction of the 765 kV line.
Comments on Table of Issues
- Tariffs
My understanding of the proposed Transmission Tariff under the Wholesale Pricing System would mean that the cost of the 765 kV line would allocate a larger proportion of Transmission’s operating costs to power being taken off in the Western Cape Zone and would provide a greater incentive to generation in that zone. These tariffs are not
Action
726992262 Page 92 of 133
yet approved or implemented, but must be considered in the long-term decisions.
- Alternatives: Strategic considerations
The response to the item on further strategies for when
765kV is no longer sufficient raises further questions.
The 765 kV line will have a very high power transfer capability and its life extends beyond the planning horizon. We can thus assume that this will be the last transmission line to the sensitive Western Cape area for a very long time. Eskom need to state when the next line be required as it has strategic implications for whether this ‘last opportunity’ should not be applied differently.
Some further key questions are: Would there not be a long-term need for strengthening the western part of the
Northern Cape, using 400 kV and other new routes? How would this affect the utilisation of the proposed 765kV line(s)? Is it planned to construct the line for 765kV operation and to operate it at 400kV? If so, when is will the line be operated at 765 kV?
With all the uncertainties around potential development in the Western Cape, the recommendation that the need for construction of the line be continually reviewed is supported. Other incremental options must, however, be considered to maintain the reliability of supply to the
Western Cape.
Yours sincerely
Willie Boeije
Co/Org Shell S.A. (Pty) Ltd
Name
Mail to
Fortune, David, Mr
P O Box 2231, Cape Town, 8000
Tel/Fax/Cell/e-mail 021 408 4073, 021 408 4643, 082 800 0477,
726992262 Page 93 of 133
Date Issue Raised
16-Apr-02 Draft EIR Correspondence
Comment
Dear Ms Bowler
The CSP 765 kV Transmission Line - EIA
Thank you for your letter dated 15 March and the CD of the draft EIR. At this stage we have no comments.
I do however request that you keep us on your list, so that we can be advised of any further developments.
Yours sincerely for SHELL SOUTH AFRICA (PTY) LIMITED
David Fortune
Action
OTHER
Co/Org CEN Integrated
Name
Mail to
Cohen, Mike, Dr
36 River Rd, Walmer, Port Elizabeth, 6070
Tel/Fax/Cell/e-mail 041 581 2983, 041 581 2983, , steenbok@iafrica.com
Date Issue Raised Comment
16-Jul-01
04-Apr-02
E-mail Received
Draft EIR Correspondence
I should be most grateful if you would let me have a electronic copy of the DSR. I am unable to access the document on the web address given in the Sunday Times.
Subject: Gamma-Omega draft EIR Raport
Date: Thu, 4 Apr 2002 05:48:00 +0200
Action
Explained that the time availability applies.
Checked the 24 Jul 01 if he had been able to access the site, and he had been successful.
Subject: Gamma-Omega draft EIR Raport
Date: Thu, 04 Apr 2002 07:45:52 +0200
From: steenbok@iafrica.com
To: Suzette.Hattingh@acerafrica.co.za
Suzette
Thanks for the venue table. As I am not in a position to travel to any of the venues I would be grateful if you could forward a copy of the EIR to me via email of post it on a website for downloading.
Thanks and regards
Mike
From: suzette.hattingh@acerafrica.co.za
Organization: ACER
(Africa)
To: <Nadia.Mol@pdna.co.za>, Karin Bowler
<karinbow@iafrica.com>
Dear Nadia
Please forward a cd copy to Mr Cohen as attached. Thank you.
Kind Regards
Suzette Hattingh
726992262 Page 94 of 133
PREFERRED ROUTE LANDOWNER
Co/Org
Name
Mail to
Basson, Andries Hendrik, Mnr
Posbus 76, Malmesbury, 7299
Tel/Fax/Cell/e-mail 022 482 3901, , ,
Date Issue Raised
05-Nov-01 Trust/ID Nr.:
14-Feb-02 21 Digit Code
Name
Mail to
Basson, Hein, Mnr
Posbus 79, Tulbagh, 6820
Tel/Fax/Cell/e-mail 023 230 0723, , ,
Date Issue Raised
05-Nov-01 Trust/ID Nr.:
Name
Mail to
Bester, Willem Burger, Mnr
Posbus 162, Ceres, 6835
Tel/Fax/Cell/e-mail 023 312 2506, , ,
Date Issue Raised
08-Oct-01 Trust/ID Nr.:
Name
Mail to
Botha, PJ, Mr
P O Box 48, Merweville, 6940
Tel/Fax/Cell/e-mail 02062 1113, , ,
Comment
4910095062085
C04600000000081400002
Comment
Comment
5206135046082
726992262
Action
Action
Action
-----
Subject: Gamma-Omega draft EIR Raport - Electronic copy
Date: Thu, 04 Apr 2002 07:49:20 +0200
From: suzette.hattingh@acerafrica.co.za
Organization: ACER
(Africa)
To: Mike Cohen <steenbok@iafrica.com>
Dear Mr Cohen
I have forwarded your request to the Project Team in Johannesburg where they will post a cd copy to you (normally this goes by priority mail).
Kind Regards
Suzette Hattingh
COPY SENT 9 APR 2002
Page 95 of 133
Date Issue Raised
17-Sep-01 Trust/ID Nr.:
14-Feb-02 21 Digit Code
Name
Mail to
Bothma, AJ, Mr
P O Box 33, Merweville, 6940
Tel/Fax/Cell/e-mail 02062 1122, , ,
Date Issue Raised
17-Sep-01 Trust/ID Nr.:
14-Feb-02 21 Digit Code
Comment
5210215044082
C04300000000002000000
Comment
5108255041085
C04300000000001900001
14-Feb-02 21 Digit Code C04300000000001500004
Name
Mail to
Burger, Michiel Johannes, Mr
P O Box 290, Malmesbury, 7299
Tel/Fax/Cell/e-mail 022 482 2113, , ,
Date Issue Raised Comment
17-Sep-01 Trust/ID Nr.: 4208145016080
C04600000000081100004 14-Feb-02 21 Digit Code
Name Calldo, Douglas J, Mr
Mail to P O Box 75, Laingsburg, 6900
Tel/Fax/Cell/e-mail 023 551 1812, 023 551 1812, ,
Date Issue Raised
17-Sep-01 Trust/ID Nr.:
14-Feb-02 21 Digit Code
Comment
5204115040084
C04300000000007300001
Name
Mail to
Conradie, Francois Daniel, Mr
P O Box 137, Laingsburg, 6900
Tel/Fax/Cell/e-mail 023 551 1817, 023 551 1817, ,
Date Issue Raised
17-Sep-01 Trust/ID Nr.:
14-Feb-02 21 Digit Code
Comment
5601025051087
C04300000000007400001
C04300000000007500000 14-Feb-02 21 Digit Code
Name
Mail to
Conradie, OG, Mr
P O Box 92, Laingsburg, 6900
Tel/Fax/Cell/e-mail 023 551 1821, , ,
Date Issue Raised
17-Sep-01 Trust/ID Nr.:
Name
Mail to
14-Feb-02 21 Digit Code
Conradie, Pieter J, Mnr
Posbus 183, Laingsburg, 6900
Comment
6210275121084
C04300000000004000002
726992262
Action
Action
Action
Action
Action
Action
Page 96 of 133
Tel/Fax/Cell/e-mail 023 551 1711, , 082 966 2189,
Date Issue Raised
17-Sep-01 Trust/ID Nr.:
Comment
5912155054084
Name
Mail to
Conradie, Pieter J, Mr
P O Box 287, Moorreesburg, 7310
Tel/Fax/Cell/e-mail 022 433 2549, , ,
Date Issue Raised Comment
17-Sep-01 Trust/ID Nr.: 3804235029008
13-Feb-02 21 Digit Code
14-Feb-02 21 Digit Code
C04300000000004000000
C07200000000020700003
14-Feb-02 21 Digit Code
14-Feb-02 21 Digit Code
Name Conradie, Pieter Jacobus, Mnr
Mail to Posbus 90, Laingsburg, 6900
Tel/Fax/Cell/e-mail 023 551 1826, , ,
Date Issue Raised
05-Nov-01 Trust/ID Nr.:
14-Feb-02 21 Digit Code
C07200000000020700000
C04300000000004300000
Comment
5912155054084
C04300000000007300000
Name
Mail to
Conradie, Willem S, Mnr
P O Box 81, Prince Alfred Hamlet, 6840
Tel/Fax/Cell/e-mail 023 313 3256, , ,
Date Issue Raised Comment
04-Oct-01 Trust/ID Nr.: 321008
14-Feb-02 21 Digit Code C01900000000032300003
Name
Mail to
Dreyer, Wilhelm, Mnr
Posbus 50, Malmesbury, 7299
Tel/Fax/Cell/e-mail 022 485 7003, 022 485 7003, 083 283 5548,
Date Issue Raised Comment
17-Sep-01 Trust/ID Nr.: 5404235043089
14-Feb-02 21 Digit Code C04600000000081800001
Action
Action
Action
Action
Action
726992262 Page 97 of 133
25-Mar-02 Draft
Correspondence
EIR Would like further information on the route of the line over his property. Saw maps but can not make out where precisely the line would run through.
Subject: Re: 765kV - Landeienaars
Date: Mon, 15 Apr 2002 13:26:02 +0200
From: <Daniel.Boshoff@eskom.co.za>
To: <Suzette.Hattingh@acerafrica.co.za>
Ek het Mnr Dreyer vandag geskakel. Hy wou net 'n beter roete plan kry om sy toekomstige druiwe daarom te beplan. Die kaart is gestuur.
Groete
D Boshoff
Name
Mail to
Fortuin, Dennis, Mr
P O Box 720, Beaufort West, 6970
Tel/Fax/Cell/e-mail 023 414 3903, , ,
Date Issue Raised Comment
17-Sep-01 Trust/ID Nr.: 4610275068080
14-Feb-02 21 Digit Code C00900000000016900003
Name
Mail to
Frick, Helena N, Ms
P O Box 12, Prince Alfred Hamlet, 6840
Tel/Fax/Cell/e-mail 023 313 3257, , ,
Date Issue Raised Comment
03-Oct-01 Trust/ID Nr.: 5005180096004
14-Feb-02 21 Digit Code C01900000000036500000
Name
Mail to
Geldenhuys, Catharina Jacoba, Me
P O Box 316, Malmesbury, 7299
Tel/Fax/Cell/e-mail 022 482 2093, , ,
Date Issue Raised Comment
17-Sep-01 Trust/ID Nr.: 2904150031004
14-Feb-02 21 Digit Code C04600000000081400006
Name
Mail to
Geldenhuys, Mattheus Lourens, Mr
P O Box 161, Ceres, 6835
Tel/Fax/Cell/e-mail 023 312 2184/312 1582, 023 316 1500, 082 456 9928,
Date Issue Raised Comment
19-Sep-01 Trust/ID Nr.: 3612045022083
14-Feb-02 21 Digit Code C01900000000024400001
14-Feb-02 21 Digit Code C01900000000024400000
14-Feb-02 21 Digit Code C01900000000023800000
Action
Action
Action
Action
726992262 Page 98 of 133
14-Feb-02 21 Digit Code
Name
Mail to
Green, Douglas W, Mr
P O Box 231, Tulbagh, 6820
Tel/Fax/Cell/e-mail 023 230 0673, , ,
Date Issue Raised
05-Nov-01 Trust/ID Nr.:
C01900000000034200000
Comment
2308055046002
Name
Mail to
Hattingh, BS, Mnr
P O Box 335, Beaufort West, 6970
Tel/Fax/Cell/e-mail 022 412 1628, , ,
Date Issue Raised Comment
17-Sep-01 Trust/ID Nr.: 5601225019082
14-Feb-02 21 Digit Code
14-Feb-02 21 Digit Code
14-Feb-02 21 Digit Code
C00900000000030800008
C00900000000030800007
C00900000000030800004
14-Feb-02 21 Digit Code C00900000000029400001
Name
Mail to
Herselman, JS, Mnr
P O Box 39, Beaufort West, 6970
Tel/Fax/Cell/e-mail 023 414 3572, , ,
Date Issue Raised Comment
17-Sep-01 Trust/ID Nr.: 4407105033008
14-Feb-02 21 Digit Code
Name Heyns, Johannes Abraham, Mr
Mail to P O Box 37, Laingsburg, 6900
Tel/Fax/Cell/e-mail 023 551 1819, 023 551 1819, ,
Date Issue Raised
17-Sep-01 Trust/ID Nr.:
C00900000000041300000
Comment
4003055011084
14-Feb-02 21 Digit Code
Name Hugo, Daniel P, Mnr
Mail to Posbus 16, Victoria West, 7070
Tel/Fax/Cell/e-mail , , 082 496 0644,
Date Issue Raised
07-Sep-01 Trust/ID Nr.:
C01900000000016300000
Comment
6007115060080 /05
Name
Mail to
Janse van Vuuren, Josimus P, Mr
P O Box 264, Beaufort West, 6970
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised Comment
08-Oct-01 Trust/ID Nr.:
726992262
Action
Action
Action
Action
Action
Action
Page 99 of 133
Name
Mail to le Roux, AJ, Mr
P O Box 18, Leeu Gamka, 6960
Tel/Fax/Cell/e-mail 02082 2011, , ,
Date Issue Raised
17-Sep-01 Trust/ID Nr.:
Comment
6402295061081
14-Feb-02 21 Digit Code C00900000000029400000
14-Feb-02 21 Digit Code C00900000000028300001
Name
Mail to le Roux, Gerrit J van Niekerk, Mr
Posbus 51, Riebeeck Kasteel, 7307
Tel/Fax/Cell/e-mail 022 448 1805, 022 448 1805, ,
Date Issue Raised
04-Oct-01 Trust/ID Nr.:
Comment
3701255037087
14-Feb-02 21 Digit Code
Name
Mail to le Roux, Willem J, Mr
P O Box 18, Leeu Gamka, 6960
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised
17-Sep-01 Trust/ID Nr.:
C04600000000064800000
Comment
3007095021004
14-Feb-02 21 Digit Code
14-Feb-02 21 Digit Code
C00900000000028200001
C00900000000028200002
Name
Mail to
Malherbe, Gideon Jacobus, Mr
P O Box 38, Ceres, 6835
Tel/Fax/Cell/e-mail 023 312 1993, , ,
Date Issue Raised
17-Sep-01 Trust/ID Nr.:
14-Feb-02 21 Digit Code
Comment
5611305037003
C01900000000024400001
14-Feb-02 21 Digit Code
Name
Mail to
Mans, Antonie W, Mnr
Posbus 51, Merweville, 6940
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised
08-Oct-01 Trust/ID Nr.:
Name
Mail to
Marais, Hendrik (HS), Mnr
Posbus 181, Victoria-Wes, 7070
Tel/Fax/Cell/e-mail 053 621 0186, , ,
C01900000000036300003
Comment
4201045007085
726992262
Action
Action
Action
Action
Action
Page 100 of 133
Date Issue Raised
01-Aug-01 Fax Received
14-Sep-01 Trust/ID Nr.:
14-Sep-01 Trust/ID Nr.:
Comment
I am the owner of the farm Phezantekraal. The wall of the road under the existing ESKOM Line is washed away, causing the road to be washed away. There are places where erosion holes are forming, and unless something urgently is done about it I might be too late.
6705015103086
3409065017089
Action
Forwarded this fax to Karin Bowler whom will take it up to the needed Eskom level.
14-Feb-02 21 Digit Code
14-Feb-02 21 Digit Code
C05200000000000100000
C05200000000001500000
Name
Mail to
Marais, Johannes Hendrik, Mnr
Posbus 6, Merweville, 6940
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised
19-Sep-01 Trust/ID Nr.:
14-Feb-02 21 Digit Code
Comment
6107075134004
C00900000000026700000
Name
Mail to
Mocke, Anthonie JJ, Mr
P O Box 54, Merweville, 6940
Tel/Fax/Cell/e-mail 023 501 4034, , ,
Date Issue Raised
08-Oct-01 Trust/ID Nr.:
Comment
5012035004084
Name
Mail to
Mocke, JG, Mr
P O Box 49, Merweville, 6940
Tel/Fax/Cell/e-mail 02062 vra 2131, 023 501 4112, ,
Date Issue Raised Comment
17-Sep-01 Trust/ID Nr.: 4708165051081
14-Feb-02 21 Digit Code C00900000000041600000
Name
Mail to
Muller, Abraham JM/Belia M, Mr
Voortrekker Str 6, Merweville, 6940
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised
19-Sep-01 Trust/ID Nr.:
Comment
6006305072002
Name
Mail to
Muller, Johannes CH, Mnr
Posbus 50, Merweville, 6940
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised
Name
08-Oct-01 Trust/ID Nr.:
Muller, Johannes Willem, Mr
Comment
5602045041009
Action
Action
Action
Action
Action
726992262 Page 101 of 133
Mail to P O Box 87, Merweville, 6940
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised
17-Sep-01 Trust/ID Nr.:
14-Feb-02 21 Digit Code
Comment
5709245139002
C04300000000001500005
14-Feb-02 21 Digit Code C04300000000010500000
Name
Mail to
Murray, AGL, Mr
P O Box 262, Beaufort West, 6970
Tel/Fax/Cell/e-mail 023 415 1552, , 082 495 9531,
Date Issue Raised Comment
17-Sep-01 Trust/ID Nr.: 4102215017088
C00900000000015300003 14-Feb-02 21 Digit Code
Name
Mail to
Myburgh, HW, Mr
P O Box 35, Merweville, 6940
Tel/Fax/Cell/e-mail 02062 1813, , ,
Date Issue Raised
17-Sep-01 Trust/ID Nr.:
Comment
3112045020005
14-Feb-02 21 Digit Code
14-Feb-02 21 Digit Code
C009200000000027100001
C00900000000027300000
Name
Mail to
Nel, FJ, Mnr
P O Box 320, Beaufort West, 6970
Tel/Fax/Cell/e-mail 023 414 3346, , ,
Date Issue Raised Comment
17-Sep-01 Trust/ID Nr.: 4711215049006
14-Feb-02 21 Digit Code C00900000000016900004
Name
Mail to
Nel, J, Mnr
Posbus 388, Beaufort Wes, 6970
Tel/Fax/Cell/e-mail 023 414 3340, , 083 961 5033,
Date Issue Raised Comment
17-Sep-01 Trust/ID Nr.: 4103085048005
14-Feb-02 21 Digit Code C00900000000016800001
14-Feb-02 21 Digit Code
Name
Mail to
Niehaus, AS, Mr
P O Box 214, Merweville, 6940
Tel/Fax/Cell/e-mail 02062 1821, , ,
Date Issue Raised
17-Sep-01 Trust/ID Nr.:
C00900000000017000033
Comment
390429
726992262
Action
Action
Action
Action
Action
Action
Page 102 of 133
14-Feb-02 21 Digit Code
14-Feb-02 21 Digit Code
C00900000000028100000
C00900000000027200000
Name
Mail to
Nigrini, AJ, Mr
P O Box 191, Beaufort West, 6970
Tel/Fax/Cell/e-mail 023 416 1683, , 082 789 3037,
Date Issue Raised Comment
17-Sep-01 Trust/ID Nr.: 4109255131083
14-Feb-02 21 Digit Code C00900000000015500000
Name
Mail to
Nigrini, Chris, Mr
P O Box 259, Beaufort West, 6970
Tel/Fax/Cell/e-mail 023 414 3323 /4 /5, , 082 537 7088,
Date Issue Raised Comment
17-Sep-01 Trust/ID Nr.: 2710075011009
14-Feb-02 21 Digit Code C00900000000030500002
Name
Mail to
Oosthuizen, AM, Me
P O Box 15, Merweville, 6940
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised
14-Feb-02 21 Digit Code
17-Sep-01 Trust/ID Nr.:
C00900000000030500000
Comment
4104280062007
14-Feb-02 21 Digit Code C00900000000026600000
Name Pienaar, JL, Mr
Mail to Danie Theron Str 34, Beauford-Wes, 6970
Tel/Fax/Cell/e-mail 023 414 3355, , 072 225 9812,
Date Issue Raised Comment
19-Dec-01 Trust/ID Nr.: 6903255071085
14-Feb-02 21 Digit Code C00900000000017200000
Name Prins, Lodewyk A, Mnr
Mail to Posbus 20, Ceres, 6835
Tel/Fax/Cell/e-mail 023 312 1848 /1684, 023 312 1848, 082 921 4695,
Date Issue Raised Comment
17-Sep-01 Trust/ID Nr.: 4412185028001
14-Feb-02 21 Digit Code C01900000000036300000
Name Rautenbach, Lukas J, Mnr
Mail to Posbus 23054, Claremont, 7735
Tel/Fax/Cell/e-mail 021 683 2958, 021 671 2676, 082 881 1133,
726992262
Action
Action
Action
Action
Action
Page 103 of 133
Date Issue Raised
03-Oct-01 Trust/ID Nr.:
14-Feb-02 21 Digit Code
Comment
4503215013086
C05200000000033800001
Name
Mail to
Scheun, FHS, Mr
31 Murray Street, Beaufort West, 6970
Tel/Fax/Cell/e-mail 023 415 1824, , ,
Date Issue Raised Comment
17-Sep-01 Trust/ID Nr.: 3103295009004
14-Feb-02 21 Digit Code C06100000000000700016
Name
Mail to
Schindler, Klaus Karl Franz, Mr
P O Box 317, Tulbagh, 6820
Tel/Fax/Cell/e-mail 023 230 0659, 023 230 0661, 083 270 3449,
Date Issue Raised Comment
05-Nov-01 Trust/ID Nr.: 5003045210100
Name Simon, JJ, Mr
Mail to P O Box 61, Laingsburg, 6900
Tel/Fax/Cell/e-mail 023 551 1915, , ,
Date Issue Raised
17-Sep-01 Trust/ID Nr.:
Comment
3909075031004
14-Feb-02 21 Digit Code
Name Snyman, JP, Mr
Mail to P O Box 4, Merweville, 6940
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised
17-Sep-01 Trust/ID Nr.:
Name
Mail to
C04300000000004200004
14-Feb-02 21 Digit Code C00900000000026500015
Name Starke, CJ, Mr
Mail to P O Box 132, Durbanville, 7551
Tel/Fax/Cell/e-mail 021 972 1882, 021 972 1882, 082 800 7307,
Date Issue Raised Comment
21-Nov-01 Trust/ID Nr.: 4607295025009
Name
Mail to
Theron, Jan Stefanus, Mnr
Posbus 24, Tulbagh, 6820
Tel/Fax/Cell/e-mail 023 230 0631, , ,
Date Issue Raised
05-Nov-01 Trust/ID Nr.:
Comment
4307035046007 van Aarde, Cornelius J N, Mr
P O Box 186, Malmesbury, 7299
Comment
7612215122008
726992262
Action
Action
Action
Action
Action
Action
Action
Page 104 of 133
Tel/Fax/Cell/e-mail 022 482 2198, , ,
Date Issue Raised
17-Sep-01 Trust/ID Nr.:
Comment
4504045015002
14-Feb-02 21 Digit Code
Name van Aarde, Louis J H, Mnr
Mail to P O Box 87, Malmesbury, 7299
Tel/Fax/Cell/e-mail 022 481 3603, , ,
Date Issue Raised
17-Sep-01 Trust/ID Nr.:
C04600000000081400001
Comment
160912
Name
Mail to van Aarde, Pieter Abraham, Mnr
P O Box 87, Malmesbury, 7299
Tel/Fax/Cell/e-mail 022 481 3603, , ,
Date Issue Raised Comment
17-Sep-01 Trust/ID Nr.: 4707235118003
14-Feb-02 21 Digit Code
14-Feb-02 21 Digit Code
C04600000000082700000
C0460000000082800000
Name
Mail to van der Merwe, Jan Hendrik, Mnr
Posbus 239, Victoria-Wes, 7070
Tel/Fax/Cell/e-mail 053 612 4704, 053 621 0438, 082 775 9333,
Date Issue Raised Comment
07-Sep-01 Trust/ID Nr.: 7011225039080
14-Feb-02 21 Digit Code C05200000000006500003
Name
Mail to van der Merwe, JH, Mnr
P O Box 1019, Beaufort West, 6970
Tel/Fax/Cell/e-mail 023 414 3353, , ,
Date Issue Raised Comment
17-Sep-01 Trust/ID Nr.: 4609125013080
14-Feb-02 21 Digit Code C00900000000017200001
14-Feb-02 21 Digit Code C00900000000017000010
Name
Mail to van der Westhuijzen, Petrus J, Mnr
Posbus 3, Malmesbury, 7299
Tel/Fax/Cell/e-mail 022 482 2610, 022 482 3213, ,
Date Issue Raised Comment
05-Nov-01 Trust/ID Nr.: 3812245021006
Name
Mail to
Viviers, Frans Gerhardus, Mnr
Posbus 1144, Beaufort Wes, 6970
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised Comment
726992262
Action
Action
Action
Action
Action
Action
Action
Page 105 of 133
08-Oct-01 Trust/ID Nr.:
Name
Mail to
Walters, Sameul Hendrik, Mr
P O Box 395, Tulbach, 6820
Tel/Fax/Cell/e-mail 023 232 0335, , ,
Date Issue Raised
17-Sep-01 Trust/ID Nr.:
Comment
6701205021006
Co/Org Akbar Dairy Trust
Name
Mail to
, ,
4 Bute Rd., Wineberg, 7824
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised
14-Feb-02 21 Digit Code
14-Feb-02 21 Digit Code
04-Oct-01 Trust/ID Nr.:
14-Feb-02 21 Digit Code
C07500000000025400006
C07500000000038300000
Comment
C01600000000004100002
Co/Org
Name
Mail to
Andbell Pty Ltd
, ,
P O Box 364, Bellville, 7530
Tel/Fax/Cell/e-mail 021 950 4102, 021 919 1184, 083 255 4536,
Date Issue Raised Comment
17-Sep-01 Trust/ID Nr.: 59/03848/07
14-Feb-02 21 Digit Code C01900000000023400001
Co/Org Andre Both Family Trust
Name
Mail to
Both, AA, Mr
P O Box 42, Gouda, 6821
Tel/Fax/Cell/e-mail 023 232 0322, , ,
Date Issue Raised
16-Nov-01 Trust/ID Nr.:
Comment
T 3328/96
Co/Org
Name
Austroboer Prop Pty Ltd
, ,
Mail to P O Box 597, Malmesbury, 7300
Tel/Fax/Cell/e-mail 022 482 2835, 022 482 2835, , kretzelp@intekom.co.za
Date Issue Raised Comment
199400963307
Co/Org
Name
Mail to
10-Oct-01 Trust/ID Nr.:
Bakenfontein Trust
, ,
P O Box 107, Malmesbury, 7299
726992262
Action
Action
Action
Action
Action
Page 106 of 133
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised
16-Nov-01 Trust/ID Nr.:
Comment
32/87
Co/Org Basie Geldenhuys Trust
Name
Mail to
, ,
P O Box 161, Ceres, 6835
Tel/Fax/Cell/e-mail 023 312 1582, 023 316 1500, 082 456 9928,
Date Issue Raised Comment
08-Oct-01 Trust/ID Nr.: 5515/97
14-Feb-02 21 Digit Code C01900000000033900000
Co/Org Beaufort Wes Municipality
Name
Mail to
Stroemfer, Petrus, Mr
Private Bag X582, Beaufort West, 6970
Tel/Fax/Cell/e-mail 023 415 2121, 023 415 2121, ,
Date Issue Raised Comment
14-Feb-02 21 Digit Code C00900000000016300001
14-Feb-02 21 Digit Code C05200000000018500000
Action
Action
Action
14-Feb-02 Trust/ID Nr.:
Co/Org Boerskaap Agente CC
Name
Mail to
Brink, Niel (NJM) & C, Mr
P O Box 69, Prince Alfred Hamlet, 6840
Tel/Fax/Cell/e-mail 023 313 3537, 023 313 3537, 082 966 3348,
Date Issue Raised Comment
17-Sep-01 Trust/ID Nr.: CK 88/29218/23 > 7302085023086
06-Dec-01 Fax Received Meneer
Gamma – Omega 765 kV Transmission Line
Hiermee erken ek NJM & C Brink die geskrewe van 7
November 2001.
Ons wil dit weereens onder u aandag bring dat die eiendom spitskop alleenlik deur u lyne gekruis mag word as u die bedrag van Een Miljoen Rand aan ons sal uitbetaal vir die grond gebruik voordat enige persone op die plaas toegelaat sal word.
Oor die eiendom Goedgevonden sal onder geen
Action
Koos v d Merwe het met Mnr Brink gepraat - die gesprek was net i.v.m onderhandelings vir die servituut. Koos het gesê hy sal die gesprek op die regte tyd weer vorentoe neem.
726992262 Page 107 of 133
omstandighede toestemming gegee word vir kraglyne nie, omdat daar reeds vyf lyne oor die plaas loop wat ons geweldig baie probleme verskaf.
Die ander rede is dat ons vasgestel het dat enige Eskom lyn
‘n geweldige negatiewe effek het op die waardasie van ons eiendom en in die huidige ekonomiese klimaat is dit ondenkbaar dat ons nog lyne sal toelaat.
Bogenoemde besware en voorwaardes is ook reeds mondelings aan Mnr Koos van der Merwe gestel.
Ons verneem graag verder van u.
14-Feb-02 21 Digit Code
Baie Dankie
NJM & C Brink
C04300000000004200003 14-Feb-02 21 Digit Code
14-Feb-02 21 Digit Code C04300000000004200001
Co/Org Boterberg Trust
Name
Mail to
Blake, PR, Mr c/o Boch Acc., P O Box 7223, Noorder Paarl, 7623
Tel/Fax/Cell/e-mail 021 872 9509, , ,
Date Issue Raised
17-Sep-01 Trust/ID Nr.:
23-Nov-01 Telephonic Discussion
Comment
5217/97
Action
Mr Blake phoned requesting more information regarding Koos v d Merwe phoned Mr Blake explaining the route corridor
& negotiation process.
the proposed line.
Is the route decided on.
What size corridor will it take up from his land.
Will they be compensated.
C01600000000004100000
Co/Org Bothma Trust
Name
Mail to
, ,
P O Box 62, Laingsburg, 6900
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised
19-Nov-01 Trust/ID Nr.:
Comment
IT 4566/96
Action
726992262 Page 108 of 133
10-Apr-02 Draft
Correspondence
EIR Ms Antoinette Bothma phoned to verify content of letter received.
Were worried that the line will be built on their farm without them knowing about it.
Suzette Hattingh ACER (Africa):
Explained that the draft EIR is out in the public domain for comments.
Assured her that negotiations will happen in future before the line can be built.
Co/Org Brakfontein Trust
Name
Mail to
, ,
P O Box 8, Hermon, 7308
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised
16-Nov-01 Trust/ID Nr.:
Comment
3992/98
Co/Org C.H. du Plessis CC
Name
Mail to
Claasen, Jan, Mr
P O Box 39, Malmesbury, 7299
Tel/Fax/Cell/e-mail , , 072 150 3058,
Date Issue Raised Comment
17-Sep-01 Trust/ID Nr.:
Name
Mail to du Plessis, AS, Mev
Posbus 39, Malmesbury, 7299
Tel/Fax/Cell/e-mail 022 482 3502, 022 482 3502, 072 150 3058,
Date Issue Raised Comment
17-Sep-01 Trust/ID Nr.: CK 85/01597/23
14-Feb-02 21 Digit Code C08000000000026500000
Co/Org Ceres Cascade Farms Pty
Name
Mail to
Wolfaardt, PJ, Mr
Posbus 38, Prince Alfred Hamlet, 6840
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised Comment
17-Sep-01 Trust/ID Nr.: 197101349307
14-Feb-02 21 Digit Code C01900000000036500001
Co/Org D Cohen & Sons Pty Ltd
Name
Mail to
, ,
P O Box 300, Ceres, 6835
Tel/Fax/Cell/e-mail 023 317 0662, 023 317 0672, 082 657 0664,
Date Issue Raised Comment
19-Sep-01 Trust/ID Nr.: 19053243407
Action
Action
Action
Action
Action
726992262 Page 109 of 133
Co/Org Dagbreek Trust
Name
Mail to
, ,
P O Box 10, Riebeeck Kasteel, 7307
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised
16-Nov-01 Trust/ID Nr.:
Comment
3720/97
Co/Org Dassenheuwel Trust
Name
Mail to
Lesch, G.J./Kobus & Lida, Mr & Mev
Posbus 206, Malmesbury, 7299
Tel/Fax/Cell/e-mail 022 482 2130, 022 482 2130, gj0828969124,
Date Issue Raised Comment
03-Aug-01 Witkruis Arend Neste
4X4 Roete (Toerisme)
23-Aug-01
Action
27/08/01
Mrs Lesch did receive correspondence e-mail dated 23
Aug 01.
Action
Subject: Eskom 765 kV - Response to Lida Lesch - concerned
Malmesbury Farmers
Date: Thu, 23 Aug 2001 18:09:45 +0200
From: Karin Bowler <karin.bowler@acerafrica.co.za>
To: unitrade@netactive.co.za
CC: trust@ewt.org.za, gbaard@wwfsa.org.za,
Ernest.Grunewald@eskom.co.za
, Peter.Nelson@eskom.co.za,
Daniel.Boshoff@eskom.co.za
,
<john.geeringh@eskom.co.za>,
<suzette.hattingh@acerafrica.co.za>, jwhyte@mweb.co.za
John
Stuart
Geeringh
Dunsmore
<stuartjd@icon.co.za>, Nadia Mol <Nadia.Mol@pdna.co.za>, Doug
Jeffery <dougjeff@iafrica.com>, suzette hattingh chris whyte
Good day Mr Pieter van Heerden.
This is in response to your e-mail dated 12 August 2001 sent on behalf of Ms Lida Lesch. With regard to my telephonic discussion with Ms Lesch on Thursday 23rd August 2001, I would like to confirm the following:
- Mr & Mrs Lesch had heard about the project during the first phase, but did not attend the Open Day in Malmesbury in March 2001. As there was no further communication in the public domain (and they were not registered on the database), they had assumed the project had come to an end.
- However, the chairman of the farmers' association informed them of the meeting at the Malmesbury library held on 3August 2001 with the Eskom team. Mr Lesch attended this meeting.
726992262 Page 110 of 133
726992262
- The concerns raised by Ms Lesch in her e-mail, will be recorded on the database as part of the Public Involvement process. Additionally,
Ms Lesch referred to the historical significance of the transport route over Porseleinberg. She suggested that a route along the "vlei area" may be more suitable. I also explained that additional issues such as avoiding construction activities during certain planting and harvesting periods and crop spraying had been raised and would be recorded in the Final Scoping Report.
- I explained the next phase of the Environmental Assessment process and that the specialist team would include an ecologist (Mr
Doug Jeffery)and an ornithologist (Mr Chris van Rooyen).
- Ms Lesch said that they had contacted Mr Koos de Goede for advice on the potential effects of the line on bird life.
- It was agreed that it would be ideal if Mr Doug Jeffery could personally contact Ms Lesch to arrange for an appointment to discuss the issues on site.
- The most important aspect of the next phase being the
Environmental Impact Report that would make recommendations on preferred routes after having investigated all the potential impacts of the transmission line. The public would once again be invited to comment on this report.
- I also explained the servitude negotiation process followed by
Eskom.
- In terms of this I explained that a likely condition of the Record of
Decision issued by the Department of Environmental Affairs &
Tourism would be that servitude negotiation with affected landowners would have to be completed before construction could commence.
- In general, I thanked Ms Lesch for the interest the farmers had shown in the project by attending the meeting in Malmesbury, as this had not always been the case in other areas.
If Ms Lesch feels that I have not captured our conversation accurately, she should please have the freedom to contact me on 082
809 7624 at any time.
Thank you for your willingness to participate in this process. The study team always welcomes input from stakeholders and Interested and Affected Parties.
Kindest regards
Karin Bowler
Page 111 of 133
23-Aug-01 Telephonic Discussion
17-Sep-01 Trust/ID Nr.:
19-Sep-01 Swartland Farmers
Meeting
699/2000
Issues Raised:
1.In the low point where we propose the line crosses the
Porseleinberg there is a Black Eagles nest - this should be confirmed during the avifaunal study.
2.The low point through the Porseleinberg is a preferred route for racing pigeons.
3.They were concerned that the terrain was not suitable for a power line - I explained that the terrain seemed suitable but that this would be confirmed during the EIA phase.
4.The line passes close to the houses and werf of
Dassenheuwel and Tweekuil - this is true but I explained that the line can be finally placed behind the houses as well.
5.They indicated that the area was used for filming adverts - my answer was that if the line had to be placed across the Swartland this may be a problem along all routes.
6.There is a 4X4 route on the Porseleinberg at this point - it seems that this route is very seldom used and I do not necessarily see this as a highly significant issue.
7.Health - EMR
8.A power line through their wheatlands will be problematic for crop sprayers (aeroplanes)
9.There is a crop sprayer landing strip on Tweekuil close to the proposed route.
10.THE FARMERS OF THE AREA HAVE NOT BEEN
NOTIFIED - they say that they attended the open day at
Malmesbury and filled in the attendance list/or had
Doug Jeffery
Mrs Lesch has stressed that she needs to be in on the discussions and if you could take along 1:50 000 maps, it would be appreciated.
There was not enough detail on the 1:250 000.
Karin Bowler
726992262 Page 112 of 133
-Sept 2001
14-Feb-02 21 Digit Code
25-Mar-02 Draft EIR Correspondence
27-Mar-02 Draft EIR Correspondence their names and addresses taken but have not received any notifications since and were not notified of the availability of the scoping report. they say there are a number of farmers who still don't know of the proposed line.
Acknowledged that a power line has to cross somebody’s property but feel that they have legitimate reasons why the route is not entirely satisfactory.
Alternative possible routes
1.Realign the route from once the line crosses the Berg
River near Gouda, southwards to link up with our alternative from the existing line below Voëlvlei Dam across below the Porseleinberg.
2.Cross the Porseleinberg just north of the proposed route somewhere. The line will then be visible as it crosses the mountain but this may be better than a long way around the bottom of the mountain range.
C04600000000078300000
Phone call from Mr Kobus Lesch.
1. He is aware of a few neighbours that have no idea about the project.
2. He is frightened that their voice have not been heard to date.
3. Would like to read the draft EIR in Afrikaans.
4. Would like meetings with someone from the project together with other landowners.
Will phone if needed in future.
1. Requested that he forward any details of neighbours to us so that we inform them of the project to date.
2 & 4. Would be addressed in negotiation process at late stage of project.
3. Will see if arrangements can be made.
Suzette Hattingh.
Forward conversation details to Karin Bowler
Telephonic conversation with Ms Lesch
1. I apologized for the report not being in Afrikaans, but explained that it is not possible to translate it.
2. Encourage her to read same, even if were the most important chapters and to look at the maps. I also encouraged her to contact me if there were any issues that needed clarifying.
3. Other issues were once again raised:
- That some of the neighbours knew nothing of the line and
726992262 Page 113 of 133
Co/Org DB Conradie Trust /Ceres
Name
Mail to
Conradie, Dirk Brasler, Mnr
Posbus 91, Ceres, 6835
Tel/Fax/Cell/e-mail , , ,
726992262 when farmers attended previous meetings, they left when they saw the line was far from their property.
- The Lesch’s don’t read newspapers on a daily basis and never saw the adverts. This applies to other people in the area.
- She also said that the Farmers’ Associations don’t always inform their members on these issues and also, farmers don’t attend all the meetings.
- She confirmed that a meeting had taken place with Doug Jeffery and that a bird specialist had been to see them regarding the nesting eagles.
4. I explained to here how issues raised during Scoping had been incorporated in the Draft EIR.
5. I also reiterated that the EIA and the negotiation process is separate and that I cannot accept any responsibility for discussing process and land values. This would be done by Eskom.
6. She says that their family farm is very small and that they crop spray, a line would make it economically unviable and they would not be able to plant and spray new crops. Mrs Lesch is also of the opinion that the compensation should not be once –off as the negative impact would extend indefinitely.
7. I explained that these issues had been captured in the report and that i.t.o. the Eskom negotiation process, these issues are discussed in detail with the affected Landowners
8. Mrs Lesch is a pharmacist and her family is prone to cancer.She is concerned about the EMF emissions and the potential to cause cancer. We discussed this matter in much detail and I explained the precautionary principle followed i.t.o. the 80 m servitude.
However, Mrs Lesch says that it is not her choice to expose herself to these lines and if in a few years she gets cancer, she is of the opinion that it would be hard for her to prove and that
Eskom would shrug its shoulders. I provided her with an e-mail address of jmoulder@its.mcw.edu, the author of an article on
EMFs & Human Health (Power lines & Cancer FAQs) which appeared on the internet.
Karin Bowler
Page 114 of 133
Date Issue Raised
16-Nov-01 Trust/ID Nr.:
Comment
IT 1221/97
Action
Co/Org Doornfontein Trust
Name
Mail to
Basson, JH, Mr c/o C de Jager, P O Box 504, Malmesbury, 7299
Tel/Fax/Cell/e-mail 022 487 2046, , ,
Date Issue Raised Comment
17-Sep-01 Trust/ID Nr.: 707/92
Action
14-Feb-02 21 Digit Code C04600000000081400000
Co/Org
Name
Doringbos Trust
, ,
Mail to P O Box 82, Prince Alfred Hamlet, 6840
Tel/Fax/Cell/e-mail , , 083 231 1730,
Date Issue Raised Comment
17-Sep-01 Trust/ID Nr.: 549/90
Action
14-Feb-02 21 Digit Code
24-Aug-01 Telephonic Discussion
C01900000000036600002
Co/Org Du Toit Groep (Edms) Bpk
Name
Mail to du Toit, Gys C, Mnr
Posbus 236, Ceres, 6835
Tel/Fax/Cell/e-mail 023 312 3136, 023 316 1229, 082 491 7214, gys@dutoit.com
Date Issue Raised Comment
Mr JL du Toit phoned Acer
Not being able to make the ERF meeting requested summary and final outcome feedback.
Action
27 / 08 / 01
Telcon
K Bowler provided a summary of the ERF meeting and the outcomes. The following was discussed:
1. An updated Impact Table and Map will be sent to I&APs who attended or apologised for not attending the ERF.
2. The final Scoping Report will be distributed to the Municipal offices and also the libraries for public comment.
3. Letters will be sent to all I&APs on the database.
4. The Specialists will commence their studies after the Scoping
Report has been accepted by DEA&T.
5. The EIR will also be available for public comment.
6. Eskom will meet with landowners at the various Farmers'
Association meetings.
7. Mr du Toit will contact K Bowler if necessary.
726992262 Page 115 of 133
04-Oct-01 Trust/ID Nr.:
14-Feb-02 21 Digit Code C01900000000037900004
14-Feb-02 21 Digit Code
14-Feb-02 21 Digit Code
C01900000000031600000
C01900000000032300001
Co/Org Eikelaan Landgoed Pty Ltd
Name
Mail to
Willers, LJ, Mr
P O Box 57, Malmesbury, 7299
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised Comment
17-Sep-01 Trust/ID Nr.: 75/1414
14-Feb-02 21 Digit Code C04600000000083400006
Co/Org
Name
Eljolet Family Trust
Visser, JA, Mr
Mail to P O Box 366, Tulbagh, 6820
Tel/Fax/Cell/e-mail 023 230 1714, 023 230 1714, 082 925 4232,
Date Issue Raised
16-Nov-01 Trust/ID Nr.:
Comment
4510305069084
Co/Org Engen Petroleum Ltd
Name
Mail to
, ,
P O Box 35, Cape Town, 8000
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised
17-Sep-01 Trust/ID Nr.:
23-Jan-02 Telephonic Discussion
Comment
198900375406
Was happy with route description and would contact if further assistance is needed.
Cell: 083 627 2890
C01600000000004100007
Action
Action
Action
Mr Jimmy Kilfoil contacted the ACER office and requested a more specific area because of the large amounts of property they own.
14-Feb-02 21 Digit Code
Co/Org
Name
Erdams Farm CC
, ,
Mail to P O Box 327, Ceres, 6835
Tel/Fax/Cell/e-mail 023 316 1264, , ,
Date Issue Raised
08-Oct-01 Trust/ID Nr.:
Comment
CK 96/52776/23
Action
726992262 Page 116 of 133
Co/Org F D Conradie Trust
Name
Mail to
Conradie, F D, Mr
P O Box 4, Prince Alfred Hamlet, 6840
Tel/Fax/Cell/e-mail 023 313 3531, 023 313 3689, 083 261 6190,
Date Issue Raised
17-Sep-01 Trust/ID Nr.:
Comment
IT 125/95
Co/Org Fairview Trust
Name
Mail to
, ,
P O Box 2293, Cape Town, 8000
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised Comment
16-Nov-01 Trust/ID Nr.:
Co/Org FJ Nel Bothma Trustees
Name
Mail to
Gallerini, , Mev
36 Madeira Street, Rugby, 7441
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised
17-Sep-01 Trust/ID Nr.:
14-Feb-02 21 Digit Code
4112/95
Comment
C04300000000004900000
Co/Org G.J. Viviers Boerdery Trust
Name
Mail to
, ,
P O Box 72, Beaufort West, 6970
Tel/Fax/Cell/e-mail 023 416 1682, , ,
Date Issue Raised Comment
17-Sep-01 Trust/ID Nr.: 727/98
14-Feb-02 21 Digit Code C00900000000007300001
14-Feb-02 21 Digit Code C00900000000012300001
Name
Mail to
Vivier, G, Mr p/a Loubser, du Plessis, P O Box 920, Stellenbosch, 7599
Tel/Fax/Cell/e-mail 021 883 8181, , ,
Date Issue Raised
17-Sep-01 Trust/ID Nr.:
Comment
727/98
Co/Org GJV Esterhuise Family Trust
Name
Mail to du Plessis, CA, Mr
40 Richelieu Str, Everglen, Durbanville, 7550
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised Comment
16-Nov-01 Trust/ID Nr.: 740/94
726992262
Action
Action
Action
Action
Action
Action
Page 117 of 133
Co/Org Gouda Boerdery CC
Name
Mail to
, ,
P O Box 138, Porterville, 6810
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised
17-Sep-01 Trust/ID Nr.:
Comment
CK 95/45907/23
Action
14-Feb-02 21 Digit Code C07500000000007300005
Co/Org Hartebeesfontein Boerdery
Name
Mail to
Basson, A L, Mr
P O Box 981, Stellenbosch, 7600
Tel/Fax/Cell/e-mail 023 416 1639, 021 887 3875, 082 572 5272,
Date Issue Raised
04-Oct-01 Trust/ID Nr.:
Comment
11-Dec-01 FAKS
AAN: Die Publieke Betrokkenheidsbeampte: ESKOM
VAN: A L Basson
Hartebeesfontein Boerdery
Posbus 981, Stellenbosch, 7600
DATUM: 11 Desember 2001
1) Ek verwys na Karin Bowler se brief gadateer 7
November 2001 wat ek eers op 4 Desember onvang het aangesien ek uitstedig was.
2) In die agtergrondskrywe van bogenoemde brief melt u dat “uitgebreide samespreking met deelhebbers en belanghebbende en geaffekteerde partye gehou is en voorts dat skriftelik kommentaar nie later nie as 18
Augustus 2001 ingedien moet word”.
3) Ek dra geen kennis van enige onderhandelinge nie.
Bogenoemde brief is die eerste wat ek van die voorgestelde projek verneem het.
4) Daar is tans drie transmissie lyne oor my plaas, met gapaardgaande gronderosie en vernietiging van weiding.
Geliewe kennis te neem dat ek nie beried is om die konstruksie van verdere transmissie lyne oor my plaas toe te laat nie. Ek was ook nie in staat om my besware voor die sperdatum van 18 Augustus 2001 in te dien nie omdat u my eers op 7 November 2001 van die onheilsplanne verwittig het.
Action
20 December 2001
Mnr Basson
Ek verwys na u brief gedateer 11 Desember 2001 en ons telefoongesprek op 20 Desember 2001. Ek antwoord graag op u brief en bevestig ook die inhoud van ons telefoongesprek.
1) Dit is belangrik om die onafhanklikheid van die omgewingsassesseringsproses en die grondeienaar-onderhandelingsproses te beklemtoon:
- Eskom Transmissie het die reg om ten enige tyd met ‘n grondeienaar vir ‘n servituut te onderhandel. Maar as deel van die organisasie se goeie omgewingspraktyk, gee Eskom Transmissie instrukies dat ‘n omgewings-assesseringsproses terselfdetyd uitgevoer moet word.
- Die omgewings-assesseringsproses word deur onafhanklike konsultante behartig. Dit is die konsultante se taak om seker te maak dat alle impakte (beide positiewe en negatiewe) wat die 765 kV Transmissie lyn kan hê op die sosiale en natuurlike omgewing, geïdentifiseer en inageneem is wanneer die verskillende alternatiewe roetes evalueer word. Dit sluit in dat ons al die grondeienaars (sowel as ander belangehebbendes) se kommentaar op rekord plaas).
726992262 Page 118 of 133
726992262
5) Die gewysigde databasis vorm is hierby ingesluit:
Die uwe
A L Basson
Afskrif aan: Klantediens Area Bestuurder
ESKOM
Posbus 2015
GEORGE
6350
Aandag : Tobie Nortje
- Die servituut-onderhandelingsproses word deur ‘n Eksom
Transmissie beampte behartig. Soos verduidelik, sal Mnr Koos van der Merwe u direk skakel.
- Die konsultante kan ‘n roete aanbeveel maar neem nie die finale besluit nie, dié word in samewerking met die onderhadeling span gedoen.
2) U kan van die agtergrond inligtingsdokument aflei dat die studie verlede jaar begin het en vir ‘n tyd lank tot stilstand gebring is en eers weer in Julie hierdie jaar hervat is. Die proses om grondeienaars te identifiseer is ‘n lang proses en word deur die verloop van die studie gedoen en dit is heel moontlik dat al die eienaars nie teen die eiende van die studie gekontak is nie. Dit is te wyte aan die feit dat addresse baie moeilik bekombaar is nadat inligting deur die Akte Kantoor verskaf is. U is een van die grondeienaars wie se inltigting eers in Oktober 2001 bekom is.
Inligting is onmiddelik aan u uitgestuur.
3) Alhoewel die Omvangsbepalingsfase voltooi is en die versper datum vir terugvoer verby is, is drie punte belangrik:
- ACER (Africa) plaas u faks (en gewysigde inligting) van 11
Desember 2001 op rekord.
- The EIA is not yet complete…..
- Daar is nog ‘n Konsep Omgewingsimpakverslag wat ten einde
Januarie 2001 in verskillende publieke plekke vir publieke kommentaar beskikbaar sal wees. U sal binnekort hiervan in kennis gestel word.
- Die serwituut onderhandelingsproses moet tussen Eskom
Transmissie en die grondeienaars nog plaas vind.
Alhoewel daar seker maalpyle is in die studie wanneer belanghebbende partye amptelik moet reageer op verslae, kan u enige tyd vir die studiespan kontak om u kwessies te opper en op rekord te plaas.
4) Soos bespreek, is gronderosie en die vernieting van weiding gedurende konstruksie deur ander grondeienaars geopper en hierdie sake word in die Konsep Omgewingsimpakverslag bevat.
Soos ooreengekom, stuur ek hierdie brief per spoedpos aan u
Mosselbaai adres en ek het ook vir Mnr van der Merwe van die datums van 11 & 12 Januarie 2002 verwittig, indien hy vir u op die plaas wil besoek.
Page 119 of 133
03-Jan-02
726992262
Subject: The Cape Strengthening Programme -
Gamma-Omega 765kV Transmission Line
Date: Thu, 3 Jan 2002 22:15:36 +0200
From: "Mari Carstens" <maric@mweb.co.za>
To: <eskomcsp@acerafrica.co.za>
CC: <info@acerafrica.co.za>
Vir Aandag:Me Karin Bowler/Suzette Hattingh
Ek verwys na u skrywe gedateer 20 Desember 2001 in antwoord op die skrywe van mnr AL Basson van
Hartebeesfontein Boerderye, gedateer 11 Desember
2001.
In u skrywe van 7 November 2001 verwys u na "a Final
Issues Report" wat op aanvraag beskikbaar is. Sal u asb
So vriendelik wees om die verslag aan ons te email.( maric@mweb.co.za
) Ek plaas voorts op rekord dat daar in terme van die omgewingsregulasies, soos afgekondig gedurende September 1997, nie geleentheid aan ons gebied is om Enige kwessies aan u oor te dra nie, ten spyte van die feit dat die korekkte adres beskikbaar was. Ons behou dus die reg voor om volledige insette te lewer sodra die verslag aan ons gestuur is. Ek sal dit ook waardeer indien u 'n meer duidelike kaart van die voorgestelde roete kan e-mail.
Ek verneem ook graag tot watter mate die betrokke plaaslike owerhede betrokke is by die proses aangesien
Indien u enige verdere inligting wil bekom, skakel weer gerus vir my.
Groete.
Die uwe
Karin Bowler
Subject: 765kV Transmissie Lyn - Gamma-Omega -
Hartebeesfontein Boerdery
Date: Mon, 7 Jan 2002 09:25:17 +0200
From: "Karin Bowler" <karinbow@iafrica.com>
To: <maric@mweb.co.za>
CC: "Nadia Mol" <Nadia.Mol@pdna.co.za>, "Stuart
Dunsmore" <stuartjd@icon.co.za>, "suzette hattingh"
<suzette.hattingh@acerafrica.co.za>
Geagte Mnr en Mev Carstens
Dankie vir u e-pos van 3 Januarie 2002.
Ek verneem julle is ook van Hartebeesfontein Boerdery, dit sal waardeer word indien u vir ons rekord doeleindes kan verwitting of u, tesame met Mnr A L Basson, vennote is van Hartebeesfontein
Boerdery. In terme van die Omgewingsimpakstudie en die publieke konsultasie proses is dit is belangrik dat ek u aandag vestig op 'n paar punte in my brief aan Mnr Basson:
Punt no 2.
Die identifiseering van belanghebbendes (belangrik hier is die grondeienaars) is 'n proses wat regdeur die studie geskied en soos die inligting bekom is, is die betrokke partye ingelig oor die projek.
Addisioneel tot die "akte kantoor roete" wat in die brief verduidelik is, is dit belangrik om kennis te dra van die volgende feite:
- Die projek is ook geadverteer is in verskeie media
- Daar is besprekings met boereverenings al langs die roete
Page 120 of 133
726992262 die voorgestelde kraglyn 'n afwyking van die normale landbougebruike is?
By voorbaat dank
PG Carstens nms Hartebeesfontein Boerdery
From: Mari Carstens [mailto:maric@mweb.co.za]
Sent: Thursday, January 10, 2002 7:44 PM
To: Karin Bowler
Subject:
Beste Me
Baie dankie vir 'n spoedige en volledige reaksie. Nou u e-pos:
1. Ek, Mev Carstens & Mnr en Mev Basson is venote in die Hartebeesfontein boerdery.
2. Ek sal dit waardeer indien die planne na Posbus 981,
Stellenbosch, 7599 gestuur kan word.
3. Enige verdere inligting (hetsy dit Afrikaans of Engels) tov die Eskom proses sal waardeur word.
Die uwe gehou. Die voorsitters is gevra om al hulle lede te verwittig van die projek en om inligting van die geafekteerde grondeienaars aan ons te verskaf.
Ten spyte van die bogenoemde is daar altyd 'n kans dat grondeienaars nie deur hierdie roetes ingelig kan word oor die
Omgewings Asessesering Studie(EIA) nie.
Soos verduidelik in die brief, is die serwituut onderhandelingsproses 'n onafhanlike proses en word alleenlik deur
Eskom behartig. Indien u belangstel, kan ek onder 'n aparte e-pos
(ongelukkig in Engels) inligting aangaande die onafhanklike verhouding tussen die EIA en die serwituut onderhandelings proses vir u stuur.
Ek wil ook graag u aandag daarop vestig dat ons as onafhanklike konsultant 'n study korridor vir die lyn evalueer, die finale lyn word direk tussen Eskom en die grondeienaars onderhandel. Soos verduidelik, sal 'n Eskom beampte, as deel van sy program, direk vir u skakel.
Punt no 3.
Die kommentaarfase om die "Final Issues Report" mag wel verby wees, maar u en ander partye het nog 'n kans om op die Draft
Environmental Impact Report (Draft EIR) kommentaar te lewer. Die dokument behoort einde Januarie 2002 in die publiek te wees en u sal wel hiervan per pos verwittig word. Dit is baie belangrik vir ons as onafhanklike konsultante, dat u geskrewe kommentaar binne die kommentaartydperk lewer.
Betrokke Plaaslike owerhede:
Aangesien die Transmissie lyn oor twee provinsies sal gebou sal word, is die Nasionale, Noordkaap en Weskaap se betrokke omgewingsdepartemente van die begin van die studie af betrokke.
Die departemente word regdeur die studie op hoogte gehou van die vordering en sal almal betrokke wees by die finale
Page 121 of 133
31-Jan-02
04-Feb-02
726992262 evalueeringsproses as deel van die amptelike Besluitnemingsproses
(Record of Decision)
Ek verneem van ACER (Africa), Me Suzette Hattingh dat daar nog een stel kaarte beskikbaar is en sy sal reel dat die per spoedpos aan u gestuur word. Verwittig haar asseblief van die adres waarheen dit gestuur moet word.
Indien u enige verdere vra het, voel asseblief vry om my direk te skakel.
Alles van die beste
Groete
Publiekebetrokkenheids programleier
Karin Bowler
PBA International
Mnr Basson (Hartbeesfontein plaas) het by Mnr Tobie Cronje
(Eskom, George) 'n draai gemaak en navraag gedoen oor opvolg gesprekke oor die projek, spesifiek dink ek i.v.m. kontak met die onderhandelaar.
Ek het vir Koos v.d. Merwe (Eskom) vanoggend geskakel met Mnr
Basson se kontak nommers en hom verwittig dat ons ook met Mev
Mari Carstens (Mnr Basson se vennoot) ekorrespondeer het. Ek het ook vir Koos gesê dat ons 1:250 000 kaarte aangestuur het.
From: Koos Van Der Merwe [jjvdm@eskom.co.za]
Sent: Monday, February 04, 2002 11:28 AM
To: karinbow@iafrica.com
Subject: Mnr. Basson
Hi Karin
Ek het vanoggend met Mnr. Basson gepraat. Sy probleem is dat hy alreeds 3 kraglyne oor sy eiendom het en voel dis baie beter dat die lyn oor sy buurman se grond gaan. Hy sê ook dat hy self die erosie moes regmaak maar as 'n nagedagte het hy darem na 'n ruk bygevoeg dat Eskom hom betaal het daarvoor.
Ek het aan hom gesê om alles aan julle te gee aangesien julle onafhanklik is en dit sal in die EIA gedokumenteer word.
Koos van der Merwe
Page 122 of 133
14-Feb-02 21 Digit Code
14-Feb-02 21 Digit Code
C05200000000006500001
C05200000000006800000
Co/Org Herman de Vries Trust
Name
Mail to
, ,
P O Box 115, Beaufort West, 6970
Tel/Fax/Cell/e-mail 023 414 3392, , ,
Date Issue Raised Comment
17-Sep-01 Trust/ID Nr.: IT 4582/95
14-Feb-02 21 Digit Code C00900000000017800000
Co/Org
Name
Mail to
J C Liebenberg & G J van
, ,
P O Box 33, Tulbagh, 6820
Tel/Fax/Cell/e-mail 023 230 0667, , ,
Date Issue Raised Comment
05-Nov-01 Trust/ID Nr.: 4212225103008
Co/Org J S Zeeman Trust
Name
Mail to
, ,
Posbus 244, Tulbagh, 6820
Tel/Fax/Cell/e-mail 023 230 0657, , 082 775 3057,
Date Issue Raised
05-Nov-01 Trust/ID Nr.:
Comment
IT 5115/97
Co/Org Jakhals Nest Farm Pty Ltd
Name
Mail to
, ,
P O Box 99, Ceres, 6835
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised Comment
19-Sep-01 Trust/ID Nr.: 96/01906/07
Co/Org Karoo Ochse Kaap
Name
Mail to
, ,
Posbus 1816, Bedfordview, 2008
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised
10-Oct-01 Trust/ID Nr.:
Comment
65/00480/07
Co/Org Keert de Koe Trust
Name
Mail to
, ,
P O Box 5, Malmesbury, 7299
Tel/Fax/Cell/e-mail , , ,
726992262
Action
Action
Action
Action
Action
Page 123 of 133
Date Issue Raised
04-Oct-01 Trust/ID Nr.:
Comment
1909/99
14-Feb-02 21 Digit Code
14-Feb-02 21 Digit Code
C01600000000007500001
C01600000000007800000
Co/Org Kleinfontein Boerdery - Joan
Name
Mail to
Rogers, JF, Mrs
2nd Floor Attwell House, Belmont Rd, Rondebosch, 8001
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised Comment
16-Nov-01 Trust/ID Nr.: 764/98
Co/Org Kleinfontein Boerdery Trust
Name
Mail to de Jager, LA, Mr
P O Box 83, Koringdal, Aderdeen, 6270
Tel/Fax/Cell/e-mail 049 846 9033, 049 846 9033, 082 825 6483,
Date Issue Raised Comment
17-Sep-01 Trust/ID Nr.:
14-Feb-02 21 Digit Code C05200000000006500004
14-Feb-02 21 Digit Code C05200000000006500000
Co/Org Koelfontein Family Trust
Name
Mail to
Conradie, FD, Mr
P O Box 4, Prince Alfred Hamlet, 6840
Tel/Fax/Cell/e-mail 023 313 3531, , ,
Date Issue Raised
17-Sep-01 Trust/ID Nr.:
Comment
1196/94
14-Feb-02 21 Digit Code
14-Feb-02 21 Digit Code
C01900000000026300000
C01900000000026300003
Co/Org
Name
14-Feb-02 21 Digit Code
14-Feb-02 21 Digit Code
14-Feb-02 21 Digit Code
Laastedrif Boerdery
Cillié, Pieter (PR), Mnr
C01900000000032300010
C01900000000032300000
Co/Org
Name
Kulumela Pty Ltd van Breda, DJ, Mr
Mail to P O Box 1088, Stellenbosch, 7599
Tel/Fax/Cell/e-mail 021 881 3077, 021 881 3247, 082 850 6101,
Date Issue Raised Comment
17-Sep-01 Trust/ID Nr.: 73/07159/07
C04600000000064900008
726992262
Action
Action
Action
Action
Action
Page 124 of 133
Mail to Posbus 135, Ceres, 6835
Tel/Fax/Cell/e-mail 023 316 1330, 023 312 2091, 082 453 1486,
Date Issue Raised Comment
07-Sep-01 Trust/ID Nr.: 6408285171087
14-Feb-02 21 Digit Code C01900000000034300002
Co/Org
Name
Mail to le Roux Familie Trust le Roux, FJH & Jacobus J, Messrs
Posbus 30, Laingsburg, 6900
Tel/Fax/Cell/e-mail 023 551 1904, 023 551 1910, ,
Date Issue Raised
17-Sep-01 Trust/ID Nr.:
Comment
4201195025002
793/94
Action
Action
14-Feb-02 21 Digit Code C04300000000003000000
14-Feb-02 21 Digit Code C04300000000003200000
14-Feb-02 21 Digit Code C04300000000003100000
14-Feb-02 21 Digit Code C04300000000007100000
14-Feb-02 21 Digit Code C04300000000007400000
14-Feb-02 21 Digit Code C04300000000007400003
14-Feb-02 21 Digit Code
Co/Org Leeuwenfontein Trust
Name
Mail to
, ,
P O Box 93, Ceres, 6835
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised
03-Oct-01 Trust/ID Nr.:
C04300000000007500001
Comment
4593/97
Action
14-Feb-02 21 Digit Code C01900000000036100013
Co/Org Lomina Agtien Pty Ltd
17-Jul-01
Name
Mail to
Young, M, Mr
Posbus 1069, Beaufort Wes, 6970
Tel/Fax/Cell/e-mail , , 082 421 1984, mjyoung@worldonline.co.za
Date Issue Raised Comment
Ask James Bredenkamp about 11kV railway transformer
& link 3 phase from rail supply. (Spoke to Mrs Smit)
Action
Co/Org
Name
17-Sep-01 Trust/ID Nr.:
14-Feb-02 21 Digit Code
Mooi Nooientjies Trust
Matthee, Christo J, Mnr
199700093007
C00900000000017300000
726992262 Page 125 of 133
Mail to Posbus 57, Stellenbosch, 7600
Tel/Fax/Cell/e-mail 021 883 2828, 021 883 8861, 082 568 3002,
Date Issue Raised Comment
04-Oct-01 Trust/ID Nr.: 46
14-Feb-02 21 Digit Code C04300000000007600001
Co/Org
Name
Mail to
Olyvenhoek Trust
, ,
P O Box 8, Malmesbury, 7299
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised
04-Oct-01 Trust/ID Nr.:
Comment
4151/94
14-Feb-02 21 Digit Code C04600000000081800000
Co/Org Ossedo PTY Ltd
Name
Mail to
, ,
P O Box 300, Ceres, 6835
Tel/Fax/Cell/e-mail 023 317 0662, 023 317 0672, 082 657 0664,
Date Issue Raised Comment
19-Sep-01 Trust/ID Nr.: 19691108507
Co/Org
Name
Mail to
Ouplaas Trust du Toit, MH, Mnr p/a vd Ahee, P O Box 12246, Stellenbosch, 7600
Tel/Fax/Cell/e-mail 021 887 1011 /3 /4, , ,
Date Issue Raised Comment
17-Sep-01 Trust/ID Nr.: 869/99
14-Feb-02 21 Digit Code C01900000000037900002
Name
Mail to du Toit, MH, Mr
P O Box 12246, Stellenbosch, 7600
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised Comment
05-Nov-01 Trust/ID Nr.: 869/99 > 421011026003
Co/Org Pembrey Trust
Name
Mail to
Vadas, PS, Mr
P O Box 2130, Knysna, 6570
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised
05-Nov-01 Trust/ID Nr.:
Co/Org
Name
Pick 'n Gro Pty Ltd
Joubert, AP, Mr
Comment
726992262
Action
Action
Action
Action
Action
Action
Page 126 of 133
Mail to P O Box 3, Koelenhof, 7605
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised
17-Sep-01 Trust/ID Nr.:
14-Feb-02 21 Digit Code
Comment
80/10009/07
C04600000000095300000
Co/Org Pieter de Bod Family Trust
Name
Mail to de Bod, Pieter Andries, Mr
P O Box 9047, Klein Drakenstein, 7628
Tel/Fax/Cell/e-mail 021 862 2194, 021 862 2537, 082 779 5581,
Date Issue Raised Comment
03-Oct-01 Trust/ID Nr.: 1322/93
14-Nov-01
Action
Action
Mr Dian Dreyer Phoned (Member of the Pieter de Bod
Family Trust):
Requested a Final issues report > Emailed same to info@naturereserve.co.za
Requested someone to speak to regarding local distribution.
> Forwarded request & details to Koos van der Merwe.
Koos v d Merwe (ESKOM) het Mnr Dreyer gekontak en die volgende bespreek. Die kontakpersoon is Johan Lech in Worcester maar dis 'n privaat lyn wat die naaste aan die Reservaat is. Johan het met Dian gepraat en die storie aan hom verduidelik. (Distribusie se samewerking en hulle houding teenoor die publiek het nogal baie met die projek te doen en dis vir my belangrik dat hulle, soos in hierdie geval, goeie terugvoer aan die publiek gee.)
14-Feb-02 21 Digit Code
14-Feb-02 21 Digit Code
C01900000000023400002
C01900000000026100000
Co/Org Pioneer Voedsel Pty Ltd
Name
Mail to
Malherbe, DJ, Mr
P O Box 153, Riversdal, 6700
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised
17-Sep-01 Trust/ID Nr.:
Comment
195700063407
14-Feb-02 21 Digit Code C07500000000038900000
Co/Org
Name
Mail to
Portuplaas Pty Ltd
Brink, PJ, Mr
P O Box 85, Paardeneiland, 7420
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised Comment
17-Sep-01 Trust/ID Nr.: 71/13474/07
14-Feb-02 21 Digit Code C04600000000106700000
Action
Action
726992262 Page 127 of 133
Co/Org Raywilgo Farms Pty Ltd
Name
Mail to
, ,
P O Box 146, Ceres, 6835
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised
17-Sep-01 Trust/ID Nr.:
Comment
79/00876/07
14-Feb-02 21 Digit Code C01900000000037900001
Co/Org Rooihoogte Trust
Name
Mail to
Smuts, WB, Mr
14 Hoof Str, Riebeeck Kasteel, 7307
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised
17-Sep-01 Trust/ID Nr.:
Comment
T 1396/94
14-Feb-02 21 Digit Code
17-Sep-01 Trust/ID Nr.:
14-Feb-02 21 Digit Code
C04600000000064900004
Co/Org Sabre Trust
Name
Mail to de Jager, Julian, Mr
P O Box 1025, Beaufort West, 6970
Tel/Fax/Cell/e-mail 023 416 1684, 023 416 1684, ,
Date Issue Raised Comment
C00900000000012200001
14-Feb-02 21 Digit Code C00900000000012200011
Co/Org
Name
Sandkamp Boerdery Pty Ltd
Kriel, Hermanus J, Mr
Mail to P O Box 186, Wolseley, 6830
Tel/Fax/Cell/e-mail 023 312 1487, 023 231 0538, 082 924 4937,
Date Issue Raised Comment
08-Oct-01 Trust/ID Nr.: 197301328907
Co/Org Sheersprops 1025 / 25 Pty
Name
Mail to
, ,
P O Box 137, Prince Alfred Hamlet, 6840
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised Comment
08-Oct-01 Trust/ID Nr.: 1997/003168/23 // 97/17357/07
Co/Org
Name
Mail to
Skaaprivier Plaas Pty Ltd
Mouton & Wolfaardt, A & AJ, Messrs
Posbus 34, Ceres, 6835
726992262
Action
Action
Action
Action
Action
Page 128 of 133
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised
17-Sep-01 Trust/ID Nr.:
Comment
199701097307
14-Feb-02 21 Digit Code
Name Wolfaardt, AJ, Mr
Mail to Posbus 34, Ceres, 6835
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised
18-Sep-01 Trust/ID Nr.:
C01900000000036300002
Comment
199701097307
Co/Org South African Preserving Co
Name
Mail to
, ,
P O Box 1587, Somerset West, 7129
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised Comment
05-Nov-01 Trust/ID Nr.: 60/01918/07
Co/Org Swartdam Trust /
Name
Mail to
, ,
P O Box 2510, Paarl, 7620
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised
03-Oct-01 Trust/ID Nr.:
Comment
1753/93
14-Feb-02 21 Digit Code
14-Feb-02 21 Digit Code
14-Feb-02 21 Digit Code
14-Feb-02 21 Digit Code
Co/Org
Name
Mail to
Swellengift Pty Ltd
Loubser, PE, Mr
P O Box 3, Durbanville, 7551
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised
17-Sep-01 Trust/ID Nr.:
C04600000000066100008
C04600000000066700002
C04600000000066100012
C04600000000066700000
Comment
199901174007
14-Feb-02 21 Digit Code C01600000000143300000
Co/Org Truter Beleggings
Name
Mail to
Truter, Hennie, Mr
P O Box 11, Riebeeck Kasteel, 7307
Tel/Fax/Cell/e-mail 022 448 1811, , 082 772 9183,
726992262
Action
Action
Action
Action
Action
Page 129 of 133
Date Issue Raised
16-Nov-01 Trust/ID Nr.:
04-Dec-01
28-Mar-02
Telephonic Discussion
Draft
Correspondence
EIR
Co/Org Tygerhoogte Farms Pty Ltd
Name
Mail to
Coetzee, CP, Mr
P O Box 126, Touws River, 6880
Tel/Fax/Cell/e-mail 023 358 2011, , ,
Date Issue Raised Comment
20-Nov-01 Trust/ID Nr.:
Co/Org Verlorenvlei Inv Pty Ltd
Name
Mail to
, ,
P O Box 578, Cape Town, 8000
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised
08-Oct-01 Trust/ID Nr.:
Comment
98/07399/07
Co/Org Waterbron Trust
Name
Mail to
, ,
P O Box 107, Malmesbury, 7299
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised Comment
16-Nov-01 Trust/ID Nr.: 2626/98
Comment
4119/2000
Mnr Truter het geskakel en het verduidelik dat hy dink die kaart wat ons vir hom gestuur het is onduidelik.
Mr Truter called requesting clarity whether or not the line will be going over his property. The maps are unclear.
Action
Dit is aan Mnr Truter verduidelik dat 'n 1 : 250 000 kaart aan Mnr de
Jager gestuur is van Riebeek Boerevereniging, en dat hy hom kan skakel indien hy dit sou wou bestudeer. Hy was tevrede en sou so maak.
Subject: 765 PRLO Phone details #2
Date: Thu, 04 Apr 2002 13:10:11 +0200
From: <Daniel.Boshoff@eskom.co.za>
To: <Suzette.Hatting@acerafrica.co.za>
Hi Suzette
Ek het Hennie Truter vandag geskakel. Hy wou weet of die lyn sy grond sal affekteer. Ek het dit bevestig en 'n kaart aan hom gesfaks.
Hy beweer die kaart in die biblioteek is nie baie duidelik nie.
Action
Action
Action
Co/Org Welgegund Family Trust
Name
Mail to
, ,
P O Box 248, Malmesbury, 7299
Tel/Fax/Cell/e-mail , , ,
726992262 Page 130 of 133
Date Issue Raised
19-Nov-01 Trust/ID Nr.:
Comment
4492/96
Co/Org Werner Koster Prop Trust
Name
Mail to
, ,
P O Box 206, Cape Town, 8000
Tel/Fax/Cell/e-mail , , ,
Date Issue Raised Comment
05-Nov-01 Trust/ID Nr.: 5163/96
14-Feb-02 21 Digit Code C00900000000012300003
14-Feb-02 21 Digit Code
14-Feb-02 21 Digit Code
C00900000000012300004
C00900000000015400000
Co/Org
Name
Mail to
Witzenberg Properties (Pty)
Graaf - Bestuurende Direkteur, Pieter (PJ), Mnr
Posbus 92, Ceres, 6835
Tel/Fax/Cell/e-mail 023 313 3108 /316 1915, 023 313 3486, ,
Date Issue Raised Comment
19-Sep-01 Trust/ID Nr.: 1954/000760/07
14-Feb-02 21 Digit Code C01900000000016200000
14-Feb-02 21 Digit Code
Co/Org Ysterklip Trust
Name
Mail to
Vlok, Luther, Mnr
Posbus 46, Victoria-Wes, 7070
Tel/Fax/Cell/e-mail 053 621 0076, , ,
Date Issue Raised
17-Sep-01 Trust/ID Nr.:
14-Feb-02 21 Digit Code
TRANSPORT
Co/Org Petronet
Name
Mail to
Scrooby, Jeff, Mr
P O Box 3113, Durban, 4000
Tel/Fax/Cell/e-mail 031 361 1343, 031 361 1534, ,
C01900000000016800006
Comment
C05200000000001500002
726992262
Action
Action
Action
Action
Page 131 of 133
Date Issue Raised
04-Jul-01
Comment
Your letter ECS3.01 refers.
Action
Petronet, being a division of Transnet Ltd, is not affected by the proposal as depicted on your drawing.
Your awareness of the existance of Transnet's pipeline servitudes and concern for their integrity is however appreciated.
JL Scrooby
04-Apr-02 Draft EIR Correspondence 26 March 2002
Send Cd with draft EIR copy.
27 March 2002
Nadia Moll left message on his answering machine that the cd was being mailed to him.
Co/Org Spoornet
Name
Mail to
Bredenkamp, James, Mr
P O Box 1276, Joubert Park, 2044
Tel/Fax/Cell/e-mail 011 773 8232, , ,
Date Issue Raised Comment
20-Jul-01 E-mail Received You letter ECSL3.01E dated 28 June 2001 refers.
Action
E-mailed copy of the letter dated 2 November 2000.
You are kindly requested to furnish this office with the reference number of the correspondence that you are referring to in the first paragraph.
Jack Maponya
Senior Admin Official
011 773 4490
08-Jan-02 08 February 2002
Dear Madam
Cape Strengthening Programme: Gamma - Omega 765 kV
Transmission line
Your application ECS3.01E dated 28 June 2001 Refers.
In principle there is no objection to the proposed subject to the following conditions:
- A positive record of decision will be required from the
726992262 Page 132 of 133
Dept of Environmental Affairs.
- A formal application must be submitted by Eskom for final approval.
Kind regards.
James Bredenkamp
Junior manager
Copies to: Depot Engineer, P O Box 737, Bergville, 7535.
726992262 Page 133 of 133