PREFEASIBILITY REPORT OF Proposed Black Trap OF Maruti Metals

advertisement
PREFEASIBILITY REPORT
OF
Proposed
PROJECT OF MINORE MINERAL
Black Trap
OF
Maruti Metals
AT VILLAGE:- DEGAM,
TALUKA:- CHIKHLI,
DIST.:-NAVSARI
1
CONTENTS
1.0
INTRODUCTION
1.1
PREAMBLE
2.0
EXCUTIVE SUMMARY
3.0
INTRODUCTION OF THE PROJECT /BACKGROUND INFORMATION
4.0
PROJECT DESCRIPTION
4.0
AVAILABLITY OF RAW MATERIAL
5.0
SELECTION OF SITE & LOCATION OF STONE MINE
6.0
PLANNING BRIEF
7.0
EXISTING INFRASTRUCTURE
8.0
REHABILITATION AND RESETTLEMENT (R & R) PLAN
9.0
PROJECT SCHEDULE & COST ESTIMATES
10.0 ANALYSIS OF PROPSAL (FINAL RECOMMENDATION)
2
1.0
INTRODUCTION
1.1
Preamble
Black Trap is base of all types of Building works, Construction of Road,
Construction of Cement Concrete road, The need of Stone in all fields
are very essential as it is a compulsory material for all types of
construction, and Industries fields. Stone Mines are providing
employments to the local Labour in Rural area, as the labour of rural
area have no any work for labour, They are Unemployed, Thus this
existing
mine is providing work to many labours and it is a good
employment.
2.0
Executive Summary
Maruti Metals is a Proposed mine, as the demand of Black Trap
in all
industries which contains foundry. This project is providing and fulfil
some demands of carbonaceous shale in around area. About 01-7857 hectare of land is under possession of Maruti Metals At, Village :
Degam, Taluka : Chikhli, Dist : Navsari.
As per the statuary obligation this project needs environmental
clearance from department of Environment and forest dept. (GPCB)
Gujarat. For grant of lease and to start quarrying operations
(production) Accordingly project proponent has submitted form 1, prefeasibility report and copy of Approval letter from department of mines
and geology Gujarat, to the state level environmental assessment
authority of Gujarat constituted by MOEF, GOI for issuing environmental
clearance, as per EIA, September 14.2006 notification.
3.0
Introduction of the Project/Background information :
3.1
Name of the existing unit
: Maruti Metals
Registered Office
Maruti Metals
At : Degam,
Ta : Chikhli,
3
Dist : Navsari
Location of existing unit
:
Village : Degam
Private Block no. 1642 paiky
Taluka : Chikhli.
Dist : Navsari.
Name of partners
:
Maruti Metals
3.2 Brief description of nature of the project :
It is a Black Stone Quarrying, it contains black stone concrete which is
used in building construction and construction of infrastructures and
road, railways etc.
3.3
Demand - Supply Gap :
As black trap is used as raw material in construction of building and
infrastructure projects, the demand of black trap is increasing day by
day. In past, demand was not too much but now a days due to rapid
industrialization and urbanization its demand increasing with pace of
time. At present, demand of black trap is more than the supply.
3.4
Imports vs. Indigenous Production :
In Navsari of Gujarat, a number of Black Trap mines are there. There is
abundance of Black Trap in the area; it had become a major source of
economy in the area/region.
3.5
Export Possibility :
3.6
Domestic / Export Markets :
N.A.
Black Trap produced is used locally as well as circulated in nearby area.
So clearly there is a huge market of Black Trap in the domestic area.
3.7
Employment Generation (Direct and Indirect) due to the project :
4
By this mining project of Black Trap in the area, peoples will get
employment, The project will directly generate the employment for the
local people and indirectly for the others. Also the marketing of the
product will generate the employment for peoples. By this project,
approximately Skilled labours-3 and Unskillled-8 to 10 labours will be on
project site.
4.0
Project Description :
4.1
Type of project including interlinked and interdependent project if
any : No others material is interlinked with this mining work.
4.2
Location (map showing general location, specific location and
project boundary & project site layout) with co-ordinates The area
has been marked on Google map including the mining lease location.
This comprises the mining lease near village : Degam, Taluka : Chikhli,
Dist : Navsari of Gujarat location of the mining lease is as under.
5
6
The geographical location of the project is as follows :
NAME
A
4.3
NORTHING
20°47'18.81"N
EASTING
73° 5'12.06"E
Details of alternate sites, considered and the basis of selecting the
existing site, particularly the environmental considerations gone
into should be highlighted : No alternative site was examined,
because this is a proposed mine manufacturing unit.
4.4
Size or magnitude of operation : B category semi mechanized.
The existing capacity / year will be 1,00,000 TPA. Total area of mining
lease is 01-78-57 Ha. The mining operation will be @ 1,00,000 Tonne
Production of Black Trap per annum
4.5
Project description with process details (a schematic diagram/flow
chart showing the project layout, components of the project etc. is
given below:
Open cast mining

Site preparation

Fencing

Drilling Blasting

Mining by manual 

Transportation to the end use
7

4.6
Raw material required along with estimated quantity, likely source,
marketing area of final products. Mode of transport of raw
materials And finished products :
TPA will be about 1,00,000 and this raw material will be produced by
project proponent from the mine allotted by Govt. and raw materials and
final products are transported by trolly and tractors.
4.7
Resource optimization / recycling and reuse envisaged in the
project. If any, should be briefly outlined :
Resources are exploited optimistically, waste dumps will be reused for
land refills.
4.8
Availability of water its source, Energy/power requirement and
source should be given :
Total water requirement in the mine will be about 3.0 KLD for drinking &
domestic use, dust suppression and plantation. Drinking water will be
brought by water tanker from nearby village Degam. Diesel will be used
in dumpers and tractors.
Nearby village Degam is well electrified.
4.9
Quantity of wastes to generated (liquid and solid) and scheme for
their Management/disposal :
No waste generation is there.
4.10 Schematic representations of the feasibility drawing which give
information of EIA purpose :
According to MOEF mining project containing area ≤5 Ha. are
considered in category B2. Schematic representations of the feasibility is
as under.
Project Concept and Site selection
8

Form 1 pre-feasibility project report
with existing TOR to MOEF (EAC)

Scoping by SEAC (site visit by
sub group of SEAC, if necessary

Category B2 - EIA not required

Appraisal and recommended by SEAC

Approval by SEIAA 

Display on the SPCB/UTPCC website
& project proponent website
5.0
Site Analysis
5.1
Connectivity :
:
Mine site is well connected with road transport. Nearest railway station
is at Chikhli Railway Station (3.30 km) in of mine site. State Highway
No. 15 (1.45 km). Nearest highway is a National Highway No. 360
Passes in about (2.85 km).
5.2
Land Form - Land use and land Ownership : The area of lease
01-78-57 Ha. The lease area forms part of private land is involved in
leased area. Details are given in below table.
S.
Type of Land
No.
1
Area in Near
(Ha.)
Black
Trap 01-78-
Private
land
Tehsil
District
State
Chikhli
Navsari
Gujarat
Village
Degam
57
9
Block
no.
1642 paiky
5.3
Topography (Google image) : The lease area is situated of village :
Degam. Topographically, the area is almost flat area.
10
11
5.4
Existing land use pattern (agriculture, non-agriculture, forest,
water bodies including area under CRZ), shortest distances from
the periphery of the project to periphery of the forests, national
park, wild life sanctuary, eco sensitive areas, water bodies
(distance from the HFL of the river), CRZ. In case of notified
industrial area, a copy of the Gazette notification should be given:
Nearest
Name
Distance
Sensitive
from the
Area
Project
within 10
kms
a) Reserve
There is no
Forest
reserve or
protected
forest within
10.0 km of
lease area.
b)
National
There is no
Park
national
park or wild
c) Wild life
life
Sanctuary
sanctuary
within 10.0
km of lease
area.
12
d)
Eco
There is no
sensitive
eco
areas
sensitive
area within
10.0 km of
lease area
e)
Water
The
source
grounder
Ground
water level
water
is 40 to 50
mt. deep
The project is
Seismic zone map
located in
seismic
zone-III.
There is no
flood.
cloudburst
and landslide
reported so
far.
13
f) CRZ
CRZ :- There is no CRZ within the 10.00 km
periphery of lease area.
5.5
Existing infrastructure : N.A.
5.6
Soil classification :
N.A.
Soil of the region falls within Average rain fall zone of 780-800 mm. The
soils are sandy loam, shallow depth reddish-black soils.
5.7
Climatic data from secondary sources :
Data is not Available
5.8
Social Infrastructure available : N.A.
6.0
Planning Brief :
6.1
Planning Concept (type of industries, facilities, transportation etc.)
Town and country planning development authority classification :
No industries and town planning programmers in the existing area.
6.2
Population projection :
No Human settlements near project area.
6.3
Land use planning (breakup along with green belt etc) :
Details will be given in land use pattern of quarry plan.
14
6.4
Assessment of Infrastructure Demand (Physical & Social) :
There is no large infrastructure demand near to existing area.
6.5
Amenities / Facilities :
Not applicable as it is a small project.
7.0
Existing Infrastructure :
7.1
Industrial Area (processing Area) : --NA--
7.2
Residential Area (Non Processing Area) :
7.3
Green Belt :
--NA--
The plant will follow the norms and will be in process to developing 33%
green belt in lease area.
7.4
Social Infrastructure : N.A.
7.5
Connectivity (Traffic and Transportation Road/Rail/Metro/Water
ways etc) :
Well connected with Road/Rail. No metro and water ways.
7.6
Drinking Water Management (Source & Supply of water) :
Drinking water will be procured from nearby villages.
7.7
Sewage system :
The domestic waste water will be treated in the septic tank followed by
soak pit.
7.8
Industrial waste management :
--NA--
7.9
Solid waste management :
--NA--
7.10 Power Requirement & Supply / Source :
No electricity required for industrial purpose.
8.0
Rehabilitation and Resettlement (R & R) Plan :
Policy to be adopted (Central / State) in respect of the project affected
persons including home outstees, land outstees and landless labourers
(a brief outline to be given) : --NA--
15
9.0
Project Schedule & Cost Estimates :
9.1
Likely date of start of construction and likely date of completion
(Time schedule for the project to be given) :
It is a proposed project .
9.2
Estimated project cost along with analysis in terms of economic
viability of the project :
Project cost
No.
Particulars
Amounts (Rs.)
1
Trolley based tractors
2,50,000/-
2
Tanker based tractors
2,50,000/-
3
Mining Equipments
1,00,000/-
4
Safety Equipments
1,00,000/Total 7,00,000/-
The proposed cost of the project is Rs. 7.00 lacs and it is economically
10.0 Analysis of proposal (Final Recommendation) :
Financial and social benefits with special emphasis on the benefit to the
local people including population, if any, in the area : This project has
created employment potential for approximately about 8 to 10 local people.
THANKS