A Community Restaurant A Redesign 3 Project Ronnie Blomberg Leila Carrillo Tatjana Eggert-Reich John Ingham Lisa Mekis Elizabeth Neil Wei Ping Chang Sohaila Shooshtarian PAGE -1- Table of Contents Scope Statement Vision Statement Business Need Project Description Project Deliverables Objectives Assumptions Constraints High - Level Risks 3 3 3 4 5 6 6 7 Stakeholder Analysis Lifecycle Approach Lifecycle WBS Project Schedule Cost Baseline Cost Baseline Graph Communication Plan Responsibility Assignment Matrix Risk Matrix Risk Response Plan PAGE -2- 8 9 9 - 10 11 - 14 15 - 16 17 - 20 21 22 - 23 24 - 26 27 28 Scope Statement Vision Statement Design and construct a full service, neighborhood restaurant in San Francisco serving California cuisine focusing on locally grown food, and locally produced art to benefit the overall neighborhood community and economy Business Needs Currently San Francisco does not have one full service restaurant that is solely focused on locally grown organic food, local entertainment, and local art. The Fillmore neighborhood community is eager to support the opening of a restaurant that features food from local farms, creates employment for neighborhood youth and adults, and is an evening venue for conviviality, art, and community building. Project Description Design and build a full service restaurant on Fillmore Street in San Francisco. Priority will be given to local and green purveyors, merchants and contractors for all construction and design needs. The restaurant construction will meet all current building codes and regulations, be on time, and within budget. The design and construction of the restaurant will include: Seating for approximately 75 diners Sound system supporting acoustic performance Two wheel chair accessible bathrooms State of the art open kitchen Enclosed kitchen prep area Warm overall design that highlights the art, music, and food PAGE -3- Scope Statement (Continued) Project Deliverables IS IS NOT Planning Completed by 2/11/08 Promotional design (menus, logos, matchbooks, etc.) Permits & Licenses by 3/7/08 Finding a location, handling tax & insurance matters Design and Construction of Restaurant by 6/11/08 Marketing & organization of soft- open / grand opening Walk Through and Sign off by Sponsor by 7/3/08 Hiring chef, kitchen/front of house staff Providing tableware, linens, silverware, plates, platters, table, decorations, etc. PAGE -4- Scope Statement (Continued) Objectives Objective Criteria for Evaluation Complete Requirement for Plan Submission by 2/11/08 “J” Permit Obtained form City Hire Designer and General Contractor (GC) by 2/12/08 Sponsor Approval and Signed Contracts Complete Design Process 3/7/08 Sponsor Sign Off Complete Construction Requirements by 6/11/08 General Contractor and Project Manager Sign Off Final Inspection by 6/12/08 Final Inspection Document Received Sponsor Acceptance of Completed Work by 7/03/08 Signed “Final Sign Off Document” PAGE -5- Scope Statement (Continued) Assumption and Constraints Assumptions Constraints GC Will Obtain Construction Permit Funding – 1.2 MIL Owner/ Sponsor will hire a qualified General Contractor Timeline – Completion within 120 days of start Owner/ Sponsor will hire a qualified Interior Designer Cost of material will not increase more than 10% No labor issues / strikes Change order will not exceed more than 6% PAGE -6- Scope Statement (Continued) High Level Risks Risk Description Trigger Impact on Cost, Scope or Time Funding Cut Bank Pulls Out Kills Project Construction Costs Increase Costs Exceed 10% Cost Schedule Delays Labor Dispute Vendor Delays Time Inspections Failure Non Compliance with City Building Codes Cost and Time PAGE -7- Stakeholder Analysis Stakeholder Needs Wants / Expectations Bank Proper return on its investment Potential profit Breathe Local continues as a profitable business Interior Designer Clear understanding of design vision Clear understanding of code requirements Sufficient funds to obtain materials/supplies Weekly team meeting Prompt payment of invoices Recommendations for future business Design to achieve local recognition Local Residents To be considered in the design Communication of vision Milestone updates Notification of opening Neighborhood enhancement Owner / Sponsor Final design and construction/design to meet ‘local’ vision Communication Plan Project on schedule and within budget Weekly status report Owner/Sponsor approval Sufficient cash flow Authority to control project Qualified labor Communication Plan Deliverables on schedule and within budget Success will solidify contract for sponsor’s next project Weekly group status meeting Detailed plans/drawings Clear understanding of deliverables Sufficient funds to obtain materials/supplies Prompt payment of final invoices Recommendations for future business Project Team Contractors /Vendors PAGE -8- Lifecycle Approach Linear, restaurants have previously been constructed and designed and models used in those instances can be applied here. The uniqueness of this project lies in the design implementation of a neighborhood atmosphere. To that end, we also utilize a progressive elaboration approach. Lifecycle (1 of 2) PROJECT MANAGEMENT DELIVERABLES REQUIREMENTS PLANNING Project Charter Preliminary Scope Statement Project Mgmt. Plan: Scope Statement WBS Project schedule Cost Baseline Responsibility Assignment Matrix Communication Plan Risk Response Plan PAGE -9- CONSTRUCTION / EXECUTION CLOSING Milestone List Status Report Change Control Closing Documents Sponsor Sign-off Lessons Learned Lifecycle (2 of 2) PRODUCT PROCESS DELIVERABLES CONSTRUCTION / EXECUTION REQUIREMENTS PLANNING Licensing and Permitting Construction Requirements GC/Designer Requirements Civil Engineering Plan Architectural Plan Plan Submitted to City Designer Contracted Design Completion GC Contracted “J” Permit (Demolition) City Permit Building Permit Schedule Approval PAGE - 10 - Construction of Restaurant City Inspections CLOSING Final City Inspection Operational Hand Off WBS REQUIREMENTS 1. Project Charter 2. Preliminary Scope Statement 2.1. Preliminary WBS 2.2. Preliminary time line 2.3. Preliminary cost baseline 2.3.1. Obtain cost estimates from GC and Designer 2.3.2. Labor cost estimates 3. Licensing and Permitting 3.1. Determine building permit requirements 3.2. Determine local jurisdiction 3.3. Determine Gas/Water/Electricity requirements 3.4. Permits cost estimates 4. Construction Requirements: 4.1. Obtain Building plan from sponsor 4.2. Obtain sponsor’s requirements and specifications 4.3. Understand sponsor’s internal procedure (bidder qualification-bonding requirements etc.) 5. Designer and GC Requirements 5.1. Obtain designs 5.2. Understand responsibility of designer and construction manager 5.3. Establish construction responsibilities 5.4. Set up temporary Utilities 6. Civil Engineering Plan 7. Architectural Plan 8. Plan Submittal to City PAGE - 11 - WBS (Continued) PLANNING 1. Scope statement 2. WBS 3. Project Schedule 3.1. GC schedules (Construction) 3.2. Designer schedules (Furniture Procurement) 3.3. Bar-chart schedule 3.4. Inspections schedules 4. Cost Baseline 4.1. Reviewed GC & designer estimates 4.2. Permits & licenses payment 5. Responsibility Assignment Matrix (RAM) 6. Communication Plan 7. Risk Response Plan 8. Designer Contract 9. Design Completion and Approval 10. GC Contract 10.1. Have GC hire subcontractors for plumbing / Drainage / Power / Electricity / Telephone lines 10.2. Worker / Vendor Contracts 11. “J”-Permit (Demolition) 12. City Permit 13. Building Permit 14. Schedule Approval 14.1. Sponsor Schedule approval PAGE - 12 - WBS (Continued) CONSTRUCTION/ EXECUTION 1. Milestone List 2. Status Report 2.1. Constant monitoring of progress, budget and permit process 2.2. Weekly review meetings 3. Change Control 4. Construction of Restaurant 4.1. Aluminum flush tube frame (for 1/4" glass, 1-3/4"x4", 5'x6' opening, no intermediate horizontals) 4.2. Glazing panel, plate glass, 1/4" thick, tempered 4.3. Exterior Doors 4.4. Roof Construction 4.5. Partitions-rough framing 4.6. Interior Doors 4.7. Fittings-Pluming Fixture 4.8. Wall Finishes 4.9. Floor Finishes 4.10. Ceiling Finishes 4.11. Plumbing Fixtures 4.12. Terminal & Package Units, Multi zone-Air condition-Heating 4.13. Sprinklers 4.14. Electrical Service/Distribution 4.15. Communications and Security 4.16. Other Electrical Systems 4.17. Indoor Furniture and fixture procurement finished 5. City Inspections PAGE - 13 - WBS (Continued) CLOSING 1. Closing Documents 2. Sponsor Sign-Off 3. Lessons Learned 4. Final City Inspection 5. GC closing document 5.1. Final Bill payment 5.2. Punch List with all the sub-contractors 6. Operational Hand-Off 6.1. Sponsor acceptance and Sign-off 6.2. Obtain final payment 6.3. Recommendations for future projects PAGE - 14 - Project Schedule View Gantt PAGE - 15 - Calendar PAGE - 16 - Bottom-Up Estimate (1 of 4) PAGE - 17 - Bottom-Up Estimate (2 of 4) PAGE - 18 - Bottom-Up Estimate (3 of 4) PAGE - 19 - Bottom-Up Estimate (4 of 4) PAGE - 20 - Cost Baseline PAGE - 21 - Communication Plan X = Consulted/Reviewed O = Organizer * = Additional Updates As Needed Sponsor PM Project Team Members Designer Architect GC GM Freq. Dist. Method Doc Type Project Charter X O X Once Mtg / Email Word Project Scope X O X Once* Mtg. / Email Word WBS O X Once Mtg. / Email Word Project Schedule O X X Weekly Mtg. / Email Word Cost Baseline O X X Once* Mtg. / Email Excel X X PAGE - 22 - X Communication Plan (Continued) Sponsor PM Project Team Members Risk Plan X O X Sponsor Report X O X O X Reports & Minutes Design Mtg Minutes RFP O X Sign-Off X O X Final Report To Stakeholders X O X Designer Architect GC GM X Freq. Dist. Method Doc Type Once Mtg. / Email Word Weekly WebEx Mtg. / Email Word X X X Semi Monthly Mtg. / Email Word X X X Weekly Email Word X Once* Mtg. / Email Word X Once* Mtg. / Email Word X Once* Mtg. / Email Word X X X PAGE - 23 - X Responsibility Assignment Matrix (RAM) E E E E E E E E E E E E E E E C C C,I C,I C,I C,I,E C,I C,I C, I C,I C,I C,I C,I C C,I PAGE - 24 - C,I C,I I,A I C C C,I C,I C,I C,I,E C,I C,I C,I C,I C,I C,I C,I C C,I Community A,C,I A,C,I A,C,I A,C,I A,C,I A,C,I A,C,I A,C,I A A,C,I A,C,I A,C,I A,C,I A,C,I A,C,I Interior Designer Project Charter Preliminary Scope Statement WBS Scope Statement Project Schedule Cost Baseline Risk Response Plan RAM Communication Plan Milestone List Status Report Change Control Closing Document Sponsor Approval Lesson Learned RAM Deliverables Be Informed = I Bank Project Contractors Vendors Approval Authority = A Project Management Consultation = C Sponsor Execution = E C C C C C C C C Responsibility Assignment Matrix (RAM) (Continued) Licensing and Permitting Construction Requirements GC/Designer Requirements Civil Engineering Plan Architectural Plan Submit Plan to City Hire Designer Design Completion Hire GC “J” Permit (Demolition) City Permit Building Permit Schedule Approval I A,I A,I I A,I I A A A E E E I E E I E E E E E A PAGE - 25 - Community Interior Designer Be Informed = I Bank Contractors Vendors Product (1 of 2) Approval Authority = A Project Management RAM Deliverables Consultation = C Sponsor Execution = E I E E E E E C E C I E E E C C C C I C C C C C Construction of Restaurant City Inspections Final City Inspection GC closing document Operational Off A I I A A E E E E PAGE - 26 - E E E Local Community Be Informed = I Interior Designer (2 of 2) Contractors / Vendors Product Approval Authority = A Project Management RAM Deliverables Consultation = C Sponsor Execution = E (Continued) Bank Responsibility Assignment Matrix (RAM) RISK MATRIX High P R O B A B I L I T Y Medium • Scope Change • Poor Workmanship • Defective Product • Cost Overrun • Late Delivery • Theft / Vandalism • Sickness / Accident • Communication Block • Natural Force delays • External economy • Inspection and Permit Issues Low Low Medium IMPACT PAGE - 27 - High Risks Response Plan Affected Areas Probability Impact Priority Strategy / Action Owner Status Design Change Cost / Sched. / Scope Low Mid Low Accept PM / Sponsor / Vendor / GC O Sched. Delays Sched. / Cost High High High Accept PM / Sponsor / Vendor / GC O Scope Change Sched. / Cost Mid High Mid Accept PM / Sponsor O Permits / Insp / Issues Sched. / Cost Low High High Avoid PM / GC C Natural Force Delay Sched. / Cost Low High Low Accept PM / Sponsor / Vendor / GC C Vendor Issues Sched. / Cost Med Low High Transfer PM / Sponsor / Vendor / GC C Med Mid Low Mitigate PM / Sponsor / Vendor / GC O Risk Communication Block Sched. / Planning Legal Issues Sched. / Cost / Closure Med Mid High Accept PM / Team / Insurance O Theft / Vandalism Cost / Sched. Med Mid Mid Avoid Insurance O Cost Overrun Cost / Budget Med Mid Low Accept GC O PAGE - 28 - END OF PROJECT PLAN PAGE - 29 -