Risky (Project Management) Business Jason Dunn Project Capabilities Office Freddie Mac September 26, 2014 1 Introduction to the Data and I • Me (Jason Dunn) – Working on projects or with project teams/systems for over 25 years – Most clients were Fortune 200 companies > Freddie Mac is the smallest company that I have worked with > Assessed performance and risk of hundreds of projects and the performance of PMOs and their associated processes for over 60 companies – Currently responsible for project processes and PM maturity at Freddie • The Data – Nearly 600 projects > 8 different industry sectors > Range in size from $150k to $1B > Represents nearly all continents > 2000+ pieces of data per project > All independently collected and verified PMI-WDC – PM Symposium 2014 2 Some Fun with Numbers Value A Short Quiz…Guess the Percentage*… 0% Had a Risk Log 81% 35% Kept the Risk Log continuously updated 40% 0% Distinguished between Risks and Issues 52% 5% Had actions that addressed the risks 36% 25% Executed the actions that addressed the risk 24% 35% Assigned an Owner to risk actions 17% *Source: Effectiveness of Project Risk Analysis and Mitigation, IPA, Inc., 2007 PMI-WDC – PM Symposium 2014 33 Successful Projects Incorporate Both Risk-Related Activities Risk Taking Actions that take advantage of a potential improvement in project outcomes PMI-WDC – PM Symposium 2014 Risk Management Actions that address a potentially negative situation 4 What Makes a Project Risky? Challenging Objectives Management Challenges • Aggressive cycle times • Tight budgets • Difficult customer requirements • Stakeholder mis-alignment • Sponsor inattentiveness • Difficult interdependencies Technical Challenges • New technology • Complex integrations • Data changes Resource Challenges • Timely availability • Appropriate skills • Untimely turnover PMI-WDC – PM Symposium 2014 5 Most Project Teams Felt Their Projects Were Risky Mean 1,000 Project Size (in millions) 500 250 100 50 10 1 0.1 No Risk Low Risk Moderate Risk High Risk Extreme Risk Project Risk Index PMI-WDC – PM Symposium 2014 6 Well-Managed, Risky Projects Do Not Compromise Schedule Performance Risky Project Profiles* - Std. Dev. + Std. Dev. Well-Managed Risk Approach Industry Average Poorly-Managed Risk Approach 0.40 *Projects that scored High on risk profile questionnaire PMI-WDC – PM Symposium 2014 0.60 0.80 1.00 1.20 1.40 1.60 Definition and Execution Schedule Competitiveness 7 Relatively Risky Projects Can Deliver Good Customer Satisfaction Risky Project Profiles* + Std. Dev. - Std. Dev. Well-Managed Risk Approach Industry Average Poorly-Managed Risk Approach Far 5Exceeds *Projects that scored High on risk profile questionnaire PMI-WDC – PM Symposium 2014 Exceeds 4 Meets 3 Partially 2 Meets Does Not Meet 1 Customer Satisfaction Index 8 The Best PMs Have More Than Just Process Knowledge and Skills Entrepreneurial PMs have eight key attributes, two of which are: 1) Judgment – the ability to balance risk taking with risk mitigation 2) Risk Management – Ability to identify and anticipate risks while taking advantages of opportunities *Source: Accelerating Project Manager Effectiveness, PMO Executive Council, Corporate Executive Board, 2011 PMI-WDC – PM Symposium 2014 9 Objectives of the Session • Discuss why risks need to be taken • Discuss what risks are worth taking and ones that you should not take • Provide some suggestions on how to identify those risks • Provide some suggestions on how to manage those risks PMI-WDC – PM Symposium 2014 10 Why take risks? Aren’t we supposed to avoid them? • In general, Yes, avoid most risks. However… – Taking risks often helps projects offset inherent risks • For example: – Spending additional time to conduct Joint-Application Development sessions > Risk: prolongs requirements gathering phase; puts schedule objectives at risk – Using Agile methods for the first time in order to develop new customer-facing application > Risk: lack of understanding of the process creates learning curve delays; inability to properly control the project’s scope – Conducting Work Process Redesign prior to kicking off the project > Risk: extends overall cycle time; may significant change the solution approach PMI-WDC – PM Symposium 2014 11 Here is an example… Risk-weighted Return on Investment No Risk • 100% chance to make $1000 • $500 investment Some Risk • 75% chance to make $10,000 • $2000 investment Significant Risk • 33% chance to make $1MM • $10,000 investment Taking a risk depends on other factors… PMI-WDC – PM Symposium 2014 12 Here is the Key Message What if I walked on a tight rope? Lesson: Take Risk Purposefully Be Prepared PMI-WDC – PM Symposium 2014 13 Rule #1: Don’t Take Stupid Risks • Don’t execute projects without a schedule or timebox • Don’t do integrated testing before you do unit testing • Don’t assume you know what the customer wants • Don’t base your estimate’s contingency on a fixed percentage • Don’t drive cost predictability if you have an inconsistent estimating process • Don’t ask if you don’t want to know PMI-WDC – PM Symposium 2014 14 Rule #2: The Risk from Taking a Risk Must Be Manageable What is manageable? It has a reasonably predictable outcome PMI-WDC – PM Symposium 2014 It will not The risk can cause me to be addressed comprise the (at least in most part) important drivers 15 What does Risk Predictability mean? Awareness • Can you see it coming? Quantifiable NonDependent PMI-WDC – PM Symposium 2014 • Do you know how it will impact the project? • If it occurs, does it prevent or escalate other risks? 16 Addressing the Risk Must Be Possible What is manageable? It has a reasonably predictable outcome PMI-WDC – PM Symposium 2014 It will not The risk can cause me to be addressed comprise the (at least in most part) important drivers 17 How do we determine if a risk is “addressable”? High/Low Assessment Determine the best and worst outcomes Larger ranges are harder to manage Span of Control Do I have the resources to address potential side-effects? If No, then determine who does and if they will help Identify Linkages Are there compounding effects of taking this risk? Be sure to include the cost of these risks in your cost/benefit assessment PMI-WDC – PM Symposium 2014 18 Strategies for dealing with Positive Risks • Acceptance: Taking advantage of the opportunity if it arises, but not actively pursuing it • Enhancement: Actively working to increase the likelihood or positive impact of the opportunity. – E.g., Canceling a project that I am working on, in order to deliver another, more important project quicker • Exploiting: Eliminating the uncertainty around realization of the opportunity. – E.g., Assigning subject matter experts to directly work on the project to complete the project faster and with higher quality • Sharing: Involving a third party to enhance the chances of realizing the opportunity. – E.g., Creating an incentive-based contractual arrangement to increase focus on key project drivers PMI-WDC – PM Symposium 2014 19 Major Trade-Offs Are Not Required What is manageable? It has a reasonably predictable outcome PMI-WDC – PM Symposium 2014 It will not The risk can cause me to be addressed comprise the (at least in most part) important drivers 20 Intelligent Risk Taking Generally Improves the Likelihood of Success Costs Sweet Spot Benefits • Significant potential to compromise key project objective(s) • Significant potential to deliver on key project objective(s) • Will significantly distract my team or myself from getting work done • Can be translated into an organizational benefit • Does not have sponsor or management enthusiastic support • Increase team morale, excitement, and commitment PMI-WDC – PM Symposium 2014 21 So, how do I determine which “risks” that I should take? Assess Project • What are the greatest risk to project success or a critical enabler? Challenges • Can I successfully address these issues/opportunities by “acceptance”?? Assess the Risks • What are my best options to address the risk or take advantage of an opportunity? of Actions Determine Likelihood of Success PMI-WDC – PM Symposium 2014 • Are the actions “Manageable”? • What is the cost/benefit for this opportunity? • Are there indirect benefits or costs that might result from my actions? 22 Common Risks and Strategies for Taking Them Head On Aggressive Schedule New Technology Organizational Change Work hard to clarify objectives Do proof of concept Identify change agents and embed in project Use Agile methods Prioritize requirements Add time to testing Do trial runs using prototypes Use Joint Application Development Use Agile methods Add time to warranty period Spend lots of time communicating Increase User Involvement PMI-WDC – PM Symposium 2014 Uncertain Requirements 23 Ask Yourself These “Stretch” Questions • What if I could bring this project in earlier than expected? • What if I could improve the quality of the product? • What if I could implement a system that addresses the resource constraints that I have? • What if I could implement something that I used at another company? • What if I could implement something that I learned at a conference? PMI-WDC – PM Symposium 2014 24 Keys to Taking Risks Communicate • Ensure that decision makers understand the reasons for the risks you are undertaking • Enlist team, sponsors and stakeholders to share ownership Plan • Ensure that risks are manageable • Thoroughly plan and resource any required mitigation activities • Implement risk-based activities Execute PMI-WDC – PM Symposium 2014 • Actively monitor progress and look for changes in risk profile 25 PMI-WDC – PM Symposium 2014 26 And I Leave You With This Thought… PMI-WDC – PM Symposium 2014 27 Thanks to Today’s Attendees Enjoy the Rest of the Conference PMI-WDC – PM Symposium 2014 28