Uno-3 - Hoval

advertisement
EN
Technical information
Installation instructions
Oil/gas boiler
Uno-3 (130-280)
Hoval products must be installed and commissioned only by appropriately qualified experts.
These instructions are intended exclusively for
the specialist. Electrical installations may only
be carried out by a qualified electrician.
This manual is valid for the following types:
7-Uno-3 (130, 160, 190, 220, 250, 280)
7-Uno-3 b-i * (130, 160, 190, 220, 250, 280)
and for the same types with increased operating pressure (H)
* = burner integrated
Uno-3 (130-280) boilers are suitable and
licensed for use as heat generators for hot water
heating systems with a permissible flow temperature of up to 100°C1). They are designed for
closed-circuit systems, but can also be installed
in open systems as per EN 12828.
1)
see point 3.2
4 205 118 / 01 - 08/09
Subject to modifications
Table of contents
1.
4 205 118 / 01
Important information
1.1
Other instructions.................................................................................................................................... 3
1.2
Safety instructions................................................................................................................................... 3
1.3
Regulations, official approvals............................................................................................................... 3
1.4Warranty.................................................................................................................................................... 4
2.Assembly
2.1
2.2
2.3
2.4
2.5
2.6
3.
Installation position................................................................................................................................. 5
Setting up, levelling................................................................................................................................. 5
Fitting the heat insulation....................................................................................................................... 6
Fitting the casing..................................................................................................................................... 8
Fitting the boiler controller on the side................................................................................................. 8
Fitting the boiler controller at the top.................................................................................................. 10
Technical information
3.1
Description of the boiler........................................................................................................................ 12
3.1.1
The Uno-3 (130-280) complies with the following directives + standards................................................ 12
3.2
Technical data Uno-3 (130-280)............................................................................................................. 13
3.3Dimensions............................................................................................................................................. 14
3.4
Dimensions without heat insulation and casing (transport dimensions)......................................... 14
4.Installation
4.1
Boiler room requirements..................................................................................................................... 15
4.2
Connection of the flue gas system and flue duct dimensions.......................................................... 15
4.3
Fitting the burner................................................................................................................................... 17
4.3.1
Sound insulation....................................................................................................................................... 17
4.4Fuel.......................................................................................................................................................... 18
4.5
Electrical connection............................................................................................................................. 18
4.5.1
Electrical connection of the burner........................................................................................................... 18
4.6
Flue gas regulator set............................................................................................................................ 18
4.6.1
Flue gas and performance diagrams....................................................................................................... 19
4.7
Flow mixing loop / minimum limitation of the boiler return temperature......................................... 21
4.8
Setting the temperature regulators...................................................................................................... 21
4.9
Safety valves.......................................................................................................................................... 21
4.10
Charging pump (boiler with free-standing calorifier)......................................................................... 21
4.11
Heating pump......................................................................................................................................... 21
5.Commissioning
5.1
5.2
5.3
5.4
5.5
5.6
Water quality........................................................................................................................................... 22
Heating water........................................................................................................................................... 22
Filling and replacement water.................................................................................................................. 22
Filling the heating system..................................................................................................................... 23
Filling the calorifier (if present)............................................................................................................ 23
Initial commissioning............................................................................................................................ 23
Oil/gas burner......................................................................................................................................... 23
Handover to the operator / storage...................................................................................................... 23
6.Maintenance
6.1
Information for fire inspector / chimney sweep regarding emission monitor key........................... 24
6.2Cleaning.................................................................................................................................................. 25
6.2.1
Preparatory work...................................................................................................................................... 25
6.2.2
Cleaning (dry or wet method)................................................................................................................... 25
6.2.3
Putting into operation again..................................................................................................................... 25
7.
7.1
7.2
2
Overview of settings
Table of parameters............................................................................................................................... 26
Overview of alarms TopTronic®T........................................................................................................... 36
4 205 118 / 01
1.
1.1
Important information
Other instructions
All instructions relevant to your system can be found
in the Hoval system manual! In exceptional cases,
the instructions can be found enclosed with the
components.
Further sources of information
- Hoval catalogue
- Standards, regulations
1.2
Safety instructions
The system may only be put into operation if all relevant
standards and safety regulations have been complied
with. However, for trial operation, the following are the
minimum conditions requiring fulfilment:
1.A safety valve has been installed (closed-circuit
system)
2. Controller in operation (connected to the power
supply)
3. The sensor for the safety temperature limiter is
located in the immersion sleeve
4. The system is filled with water
5. An expansion vessel is attached
6. Flue gas outlets connected to the flue gas conduit
at the chimney.
7. It must be ensured that there is an adequate supply
of fresh air.
8. The burner is preset
1.3
Regulations, official approvals
For installation and operation of the system, the following regulations must be observed:
Germany
- DIN EN 12831 Heating systems in buildings - Procedure for calculation of the standard heating load.
- DIN EN 303 Boilers with fan blowers.
- DIN EN 12828 Sheet 1 and 2
Heating systems in buildings - Design for waterbased heating systems.
- DIN 4755 Oil-fired combustion systems.
Design, construction and safety engineering requirements.
- DIN 4756 Gas-fired combustion systems: Design,
construction and safety engineering requirements,
design and construction.
- DIN 18160 Domestic chimneys, requirements,
design and execution.
- TRD 702 Steam boiler plants with calorifiers of the
group II.
- DIN EN 13384 Chimneys - thermal and fluid dynamic calculation methods.
- TRD 721 Safety equipment to safeguard against
excess pressures / safety valves / for group II steam
boilers.
Important information
- VDI 2035 Prevention of damage by corrosion and
the formation of scale in hot water heating systems.
- DIN 57 116 / VDI 0116 Electrical equipment in
combustion systems (VDE regulations).
- For further standards applicable in Germany, see
supplement N-430 020.
Austria
- ÖNorm 7550
- ÖNorm B 8130 Open hot water systems, safety
installations.
- ÖNorm B 8131 Closed hot water systems; safety,
design and testing regulations
- ÖNorm B 8133 DHW heating systems; safety
engineering requirements.
- ÖNorm B 8136 Heating systems, space requirements and other building requirements.
- ÖNorm M 7515 Calculation of chimney dimensions;
definition of terms, calculation methods.
- ÖNorm H 5171 Heating systems, construction
engineering requirements
- ÖVGW TR-Gas G1 Technical guidelines for low
pressure gas installations
- ÖNorm M 7445 Gas fan blowers
Switzerland
- VKF - Association of Cantonal Fire Insurers
- Fire prevention authority regulations.
- SVGW Switzerland. Gas and water association.
- SWKI 91-1 Guidelines on boiler room ventilation.
- SWKI 88-4 Water treatment for heating, steam and
air conditioning plants.
- SWKI 93-1 Safety engineering installations for
heating systems.
- KRW Corrosion caused by halogen compounds.
- KRW/VSO/FKR Ready-to-connect electrical connections on boilers and burners
and further regulations and standards prescribed by
the CEN, CEN ELEC, DIN, VDE, DVGW, TRD and
by law.
The regulations of the local building authorities, insurers and chimney inspectors must also be taken into
account. When gas is used as a fuel, the regulations
of the local gasworks must be observed, and official
authorisation may also be required.
3
Important information
1.4Warranty
Fault-free operation can only be guaranteed if these
instructions and the instructions in the operating
manual are followed and if the boiler is regularly
serviced by a licensed specialist. (service contract).
The rectification of faults and damage resulting from
the use of contaminated operating materials (gas,
water, combustion air), unsuitable chemical additives
to the heating water, improper handling, faulty installation, unauthorised modifications and damage due
to the use of force do not fall under our obligations
under warranty; this also applies to corrosion due to
halogen compounds, e.g. from spray cans, paints,
adhesives, halogenated refrigerants, solvents and
cleansing agents.
4
4 205 118 / 01
Assembly
4 205 118 / 01
2.Assembly
2.1
Installation position
Where limited space is available, the Uno-3 can
be transported standing on the door. Hex nuts are
mounted behind the door as supports for this purpose.
After transport, they can simply be screwed back to
the bracket.
Release and screw back 6 transport
counter nuts before commissioning.
Counter nut
There must be enough space to swing open
the boiler door, incl. the burner.
Boiler door pivotable to the left
It is possible to change the attachment of the boiler
door so that it opens towards the left. This can be of
advantage when installing the boiler in a corner.
Proceed as follows:
Close the boiler door and lock it in position before changing the attachment
of the door
1
2.2
Setting up, levelling
A special foundation plate for the boiler is not an
essential, but it is recommended.
Space requirement
for fitting the heat insulation and casing panelling:
at least 40 cm each on the left and right side of
the boiler.
If the space between the boiler and the wall is less
than 50 cm, all heat insulation and casing must be
fitted before the boiler can be pushed into its final
position.
Do not connect lines until the heat insulation
and casing have been fitted to the boiler!
There must always be enough space
between the back of the boiler and the
wall to allow easy access to the cleaning aperture in the flue gas collector.
2
Fig. 2
1. Remove special screw (1).
2. Swing the arm (2) to the opposite side.
3. Refit the special screw (1) on the other side.
4. Fit the burner plug on the other side (see also point
4.5.1).
The cable must not touch any hot
parts!
Levelling
Using a spirit level, align the upper edge of the boiler water jacket (longitudinal axis of the boiler) until
it is precisely horizontal or sloping very slightly upwards towards the rear by inserting the plinth rails
correspondingly, to allow the boiler to vent properly.
Before fitting the burner, first fit the double
door (Pos. 8a, Figure 6) (door casing).
5
6
Fitting the heat insulation
The remaining 2 insulation mats (17) are fitted after mounting the casing.
7. Attach insulation panels (7/7a/7b/7c/7d) to the pins welded onto the front wall of the boiler and secure with the retaining discs
(ø 38) provided.
-Insulation mat 7c (or 7d with boiler door pivotable to the right) can be cut for easier
fitting.
For your information: The insulation panels protrude 50 mm on the left and right.
6. Attach insulation panels (6/6a/6b/6c/6d) to the pins welded onto the flue gas collector and secure with the retaining discs
(ø 38) provided.
5. Attach the insulation mats (5/5a/5b/5c) to the pins provided on the rear wall of the boiler and secure with retaining discs (ø 38).
For your information: The insulation mats protrude 80 mm on the left and right.
Wrap the insulation mats (5d) around the connection fittings and secure with tension springs.
4. Attach the insulation mat (3) using 2 (or 3) plastic straps (4) and strap fasteners (4a):
- There are also tension springs (4b) for additional attachment
- Do not overtighten the straps
(reduced insulating value)
3. Place insulation mat (3) (on Uno-3 (250 / 280) = 2 mats) around the boiler body (with the joint at the top, black side facing outward).
2. Using M8 hex screws, nuts and washers, fit the rear retaining bracket (2) in horizontally aligned position.
- Attach C-clips.
1. Using M8 hex screws, nuts and washers, fit the front retaining bracket (1) to the front of the boiler in horizontally aligned position.
- Attach C-clips.
2.3
See separate assembly instructions for boilers with mounted calorifier
Assembly
4 205 118 / 01
7c
‌7b
7a
7
7d
3
4a
Fig. 3
‌4b
4
1
C-clips
6
‌6b
6d
5a
5
5d
5c
6a
5b
6c
2
C-clips
4 205 118 / 01
Assembly
7
8
9. Place support (9) on the door hinge (Figure 6a).
Attach 4 special screws (9a) with counter nuts to each side section (9b/9c). Fit burner plug (9d) into the front left (or right) side section and route the
burner cable (9e) (possibly over the boiler) to the opening for the controller (cable routing as shown in Figure 6). Place right and left side sections
(9b/9c) over the supports (9) and attach to the front brackets (1, Figure 3) with self-tapping screws ø 4.8 x 38.
Fitting the boiler controller on the side
The controller must be mounted on the side of the Uno-3. If this causes problems due to limited space, it
is also possible to fit the controller on the top of the Uno-3. You will find a description of how to do this on
the next page.
Caution: The capillaries must not be folded or kinked!
Fit cover plate (19,19a) with self-tapping screws ø 3.5 x 9.5.
21. Remove transport lock, see point 2.1.
20. Affix labels and where applicable, mount manual holder on the side.
19
16
16c
Fig. 5
18. Place casing cover (18,18a) in position and attach on the right and left side with self-tapping
screws ø4.8 x 38. (Model with accessible covers, see separate instructions)
17. Attach cover plate (15) with self-tapping screws ø3.5 x 6.5 and serrated washers.
16. Pull the capillaries with the immersion sensors (16, Figure 5) through the opening (16a, Figure 4)
in the side wall, insert them into the immersion sleeve (16b, Figure 6) as far as the stop and fix in
position with retaining spring (16c, Figure 5). Insert the burner plug (16d).
15. Remove controller box cover plate (15, Figure 6). Hook the switch control box (15a, Figure 4) into
the side wall (11a, Figure 6) with the recesses for the special screws and secure with
2 self-tapping screws ø3.5 x 6.5 and serrated washers (15b).
2.5
16a
13
‌15b
15a
Fig. 4
14. Attach bottom and top rear wall (14,14a) to the angled edges of the side walls (10,11,11a) with self-tapping screws ø 3.5 x 9.5 and C-clips. Fit
cover plate (14b) with self-tapping screws ø 3.5 x 9.5.
13.Applies only where the controller is fitted on the side (see point 2.5):
Fit 2 special screws (13, Figure 4) with counter nuts to the side wall on which you are mounting the controller.
12. Insert 2 insulation mats (12) (to prevent vertical circulation of air) longitudinally on the left and right.
11. Attach upper right and left side wall (11,11a) (proceed as for lower side walls, see point 10).
10. Hook lower right and left side wall (10) into the side sections (9b/9c) and attach to the rear retaining brackets (2, Figure 3) with self-tapping
screws ø 4.8 x 38.
Fitting the casing
8. Using a hex nut and washer, attach bolt (8) to the door and then fit the door casing (8a).
2.4
Assembly
4 205 118 / 01
Fig. 6a
8a
8
9
8a
9c
Fig. 6
11
19
12
19a
18
9d
‌9b
‌16b
9e
14
10
11a
9a
15
16d
18a
‌14b
14a
4 205 118 / 01
Assembly
9
Assembly
2.6
4 205 118 / 01
Fitting the boiler controller at the top
15. Remove controller box cover plate (15, Figure 7). The control panel (15a, Figure 7a) must be turned
around. To do this, remove the pressure lock sleeves (15b, press together and pull off) and the earthing
screw and serrated washer (15c). Attach the special screws (15d) in the casing cover (15e) with counter nuts. Position switch control box (15f) on the casing cover (15e) with the recesses for the special
screws and secure with 2 self-tapping screws ø3.5 x 6.5 and serrated washers (15h). Fit casing cover
(15e, Figure 7) and secure with self-tapping screws (ø4.8 x 38).
16. Pull the capillaries with the immersion sensors (16, Figure 5, Page 8) through the opening (16a, Figure 7a) in the cover, insert them into the immersion sleeve (16b, Figure 7) as far as the stop and fix in
position with retaining spring (16c, Figure 5, Page 8). Insert the burner plug (16d).
Caution: The capillaries must not be folded or kinked!
17. Attach cover plate (15) with self-tapping screws ø3.5 x 6.5 and serrated washers.
18. Fit casing cover (18) and secure on the right and left sides with self-tapping screws ø4.8 x 38. (Model
with accessible covers, see separate instructions)
19
Fit cover plate (19,19a) with self-tapping screws ø 3.5 x 9.5.
20. Affix labels and where applicable, mount manual holder on the side.
21. Remove transport lock, see point 2.1.
‌15b
18
15c
0°
15f
15h
15a
15d
Fig. 7a
15e
16a
10
Assembly
4 205 118 / 01
18
15
15e
16d
19a
Fig. 7
19
‌16b
11
Installation
3.
3.1
4 205 118 / 01
Technical information
Description of the boiler
The Uno-3 is a threepass boiler. At the end of the
circular cylindrical combustion chamber, the flame
gases flow through several cylindrical tubes arranged
above the combustion chamber and towards the front
to the turning chamber, from where they flow through
rectangular ducts (thermolyt. heating surface) towards
the rear and reach the flue gas collector.
The flue gas temperatures can be varied within a
specific range through the installation of various regulator combinations.
3.1.1 The Uno-3 (130-280) complies with the following directives + standards
We hereby declare that the product described, as an individual unit, complies with the standards,
guidelines and technical specifications listed below.
Directives:
90/396/EC
92/42/EC
73/23/EEC
89/336/EEC
97/23/EC
"Gas appliances directive"
"Efficiency directive"
"Low-voltage directive"
"Electromagnetic compatibility"
"Pressure equipment directive" (PED)
Regulations:Stability
prEN14394:2001
Building requirements EN303-1, EN303-2, EN303-3
Low voltage
DIN VDE 0722 / Ed. 04.83
EMC
EN 50082 Part 1 / Ed. 01.92
12
Installation
4 205 118 / 01
3.2
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
3
4
5
6
1
2
Technical data Uno-3 (130-280)
Type
Nominal heat output at 80/60°C 2
Heat output range (heating oil EL, natural gas H: Variant 1 and 3)
Heat output range (heating oil EL, natural gas H: Variant 2)
Maximum heat input
Maximum boiler operating temperature 3
Safety temperature limiter setting (water side) 3
Operating/test pressure at max. operating temperature 90°C 3
Maximum boiler operating temperature 4
Safety temperature limiter setting (water side) 4
Operating pressure at max. operating temperature 105°C 4
Minimum boiler operating temperature
Minimum boiler return temperature
Minimum flue gas temperature at boiler
Regulator set for 160 °C
flue gas temperature
Boiler efficiency at 80/60 °C
(related to net/ gross calorific value, heating oil EL)
Normal degree of efficiency (DIN 4702 Part 8 75/60 °C)
(related to net/ gross calorific value, heating oil EL)
Standby losses qB at 70 °C
Resistance on the heating gas side at nominal output
160 °C flue gas temperature, 12.5% CO2 , 500 m above sea level
(tolerance ± 20%)
Flue gas mass flow at nominal output
12.5% CO2 heating oil
Flow resistance boiler 5
Hydraulic resistance at 10K
Hydraulic resistance at 20 K
Water flow rate at 10 K
Water flow rate at 20 K
Boiler water content
Boiler gas content
Insulation thickness of boiler body
Weight (incl. casing)
Sound level 6
- Heating noise without absorber hood (EN 15036 Part 1)
- Heating noise with absorber hood (EN 15036 Part 12)
- Flue gas noise inside the flue (EN 15036 Part 2)
- Flue gas noise radiated from the mouth (DIN 45635 Part 47)
Combustion chamber dimensions Ø-inside x length
Combustion chamber volume
Dimensions
Maximum negative pressure in the flue pipe system (at the boiler
connection)
9R3/290
(160)
(190)
(220)
(250)
160
190
220
250
105-160 123-190 143-220 170-250
64-160
76-190
100-220 120-250
173.1
206.0
236.6
269.1
90
90
90
90
110
110
110
110
4.0/5.2
5.0/ 6.5
5.0/6.5
5.0/6.5
105
105
105
105
120
120
120
120
3.0
4.0
4.0
4.0
see table of operating conditions (below)
see table of operating conditions (below)
see table of operating conditions (below)
6R5/290
6R5+
9R5/290
6R5+
6R2/290
3R3/290
%
92.8 /87.6 92.5 /87.3 92.2 /87.0 92.6/87.6 9.28/87.6
%
96.1 /90.7 96.1 /90.7 96.2 /90.8 96.0/60.6
(280)
280
190-280
130-280
302
90
110
5.0/6.5
105
120
4.0
6R5+
6R2/290
96.3/9.4
95/90
Watts
440
440
570
570
610
610
mbar
0.86
1.50
1.40
1.7
1.6
2.8
kg/h
222
274
324
375
426
475
z-value
mbar
mbar
m³/h
m³/h
litres
m³
mm
kg
0.2
24.80
6.20
11.10
5.60
270
0.236
80
495
0.2
37.60
9.40
13.70
6.90
270
0.236
80
495
0.1
26.50
6.60
16.30
8.10
362
0.322
80
635
0.1
35.55
8.90
18.90
9.40
362
0.322
80
635
0.1
46.00
11.50
21.40
10.70
480
0.428
80
880
0.1
57.6
14.40
24.00
12.00
480
0.428
80
880
dB(A)
80
81
81
81
83
83
dB(A)
67
73
73
73
75
75
dB(A)
91
88
88
91
96
93
dB(A)
84
78
78
79
89
85
mm ø440x974 ø440x974 ø490x974 ø490x974 ø488x1434ø488x1434
m³
0.148
0.148
0.184
0.84
0.268
0.268
see dimensional drawing
Pa
30
30
30
30
30
30
For Switzerland only
At nominal output, the pollutant limit values and flue gas losses as per regulation LRV (92) are complied with.
Controller U3.1 and T2.2
Controller U3.2 and T2.2
Flow resistance boiler in mbar = flow rate (m3/h)2 x z
Data valid for Hoval oil compact heat station b-i
Possible operating conditions
Fuel
Variant 1
min. flue gas temperature °C
min. boiler temperature
°C
min. return temperature
°C
Return temperature controls
Boiler start-up protection 1
1
(130) 1
130
90-130
65-130
139.8
90
110
4.0/5.2
105
120
3.0
kW
kW
kW
kW
°C
°C
bar
°C
°C
bar
°C
°C
°C
Heating oil EL
Variant 2
Variant 3
Variant 1
Natural gas H
Variant 2
Variant 3
Heating oil L
130
48
35
yes
110
50
38
yes
130
52
No lower limit
no
130
58
45
yes
110
60
48
yes
130
62
No lower limit
no
130
58
45
yes
130
70
60
yes
no
no
yes
no
no
yes
no
no
Boiler minimum temperature limit effective on group actuators
13
Installation
4 205 118 / 01
3.3Dimensions
3
1
4
5
2
9
11
7
8
12
13
6
14
}
1
2
3
4
5
6
7
Flow type 130-160 DN 50, PN 6
Return type 190-280 DN 65, PN 6
Safety flow R 1 1/2
Flow for calorifier R 1 1/4
Return for calorifier R 1 1/4
Drain pipe R 1 1/2
Flue gas outlet
Uno-3
l
w
h
h1
a
c
Fig. 8
10
8 Cleaning aperture
9 Boiler controller optionally on the right, left or top
10 Plinth rail: width 50 mm
11 Boiler door attached on the right (on the left if desired)
12 Flue gas collector cleaning connection R 1
13 possible anti-vibration elements, width 80 mm, height 50 mm
14 Burner absorber hood
d
e
f
g
i
k
m
n
o
P
q*
r
s
t
u
Ø
130-160
1411 910 1198 1403 680 740
50
450 190 220/270 220 680 863 1072 265 546 179 158 1080 81
137
190-220
1431 910 1358 1563 750 740
50
450 240
270
195 675 950 1218 310 621 199 178 1080 81
134
250-280
1916 910 1358 1563 750 740
50
450 240
270
195 675 950 1218 310 596 249 178 1535 76
134
*q = flue gas outlet external diameter. Plate thickness 3 mm; adapter set for Uno-3 (250-280): D qø 199, A qø 200 (with tape)
3.4
Dimensions without heat insulation and casing (transport dimensions)
Boiler (without calorifier) incl. swivel flange, connections and flue gas collector
Fig. 9
Uno-3
Type
Width
B
130-160
190-220
250-280
680
750
750
14
Length
with connecwithout contions + flue gas nections + flue
collector
gas collector
L1
L2
1515
1531
2015
1210
1230
1685
Height
H
Weight
kg
1180
1335
1335
430
530
760
4 205 118 / 01
4.Installation
4.1
Boiler room requirements
Regarding the building specifications for boiler rooms
and their supply and extract air handling, the current
building supervisory office regulations specific to the
state or country are to be observed. In Germany, the
firing ordinances of the individual federal states must
be observed.
Ensure that there is an adequate supply of fresh
air to the boiler room,
so that the amount of combustion air required for
operation of all the burners installed there can be
continuously replenished without hindrance and that,
for the protection of operating personnel, there is no
shortage of oxygen.
Binding values for the size of supply air openings are
not generally specified in the relevant regulations; it is
merely required that no partial vacuum in excess of 3
N/m2 occurs. An opening or line leading into the open
air of at least 150 cm2. For every kW in excess of 50
kW, a further 2 cm2 must be calculated. In rectangular
openings, the ratio of the sides should not exceed
1.5:1; if a grid is fitted, an appropriate allowance must
be added so that the free cross-section area reaches
the amount given above.
In Austria, ÖNorm H 5171 also requires an extract air
opening. Up to a nominal heat output of 100 kW, this
opening must have a minimum cross-section of 180
cm2. For every further kW, the cross-section must be
increased by 1 cm2.
Installation
Existing flue gas systems may require upgrading or adjustment of the flue duct crosssection as indicated by a chimney engineer.
The correct functioning of the flue duct, i.e. the generation of the required delivery pressure depends on:
a) type (materials and characteristics) of the flue duct
(thermal insulation, internal surface roughness,
leak-tightness etc.)
b)connection of the boiler to the flue gas system
according to applicable regulations and standards
c) correct dimensioning of the flue duct cross-section.
re: a)
Flue gas systems in accordance with EN 13384, Part
2, types I and II, conform to state-of-the-art combustion
systems (a chimney engineer must be consulted).
re: b)
The flue gas pipe connecting the boiler to the flue gas
system must be as short as possible and placed at
an angle of 30-45°.
Carefully seal the flue gas pipe against the flue gas
system.
The insertion of the flue gas pipe into the flue gas
system (a) must be carried out in such a way that no
condensation water can flow from the flue gas system
into the flue gas pipe and into the boiler. (Fig. 10)
The flue gas system must be watertight, acid-proof and approved for the
corresponding flue gas temperatures.
As a general rule, only one heat generator
should be connected to the chimney! When
using two heat generators, the corresponding
regulations must be observed.
4.2
Connection of the flue gas system
and flue duct dimensions
Boiler and flue gas system must be mutually compatible and operate as a single functional unit in order
to guarantee trouble-free and economical operation.
a
Fig. 10
Where possible, avoid 90° bends in the flue gas system!
Flue gas pipes over 1 m in length must be insulated.
Moisture-resistant and acid-proof flue gas systems must be used in new installations.
15
Installation
4 205 118 / 01
As a general rule, only one heat generator may be connected to the chimney!
Flue gas pipes over 1m in length must be insulated.
If an adapter (reducer) from the flue gas outlet of the
boiler to the entry point into the flue gas system is
required, it must take the form of a slim cone.
vom
Kessel
zum
Schornstein
re: c)
Dimensioning of the flue duct cross-section. The
cross-sections must be calculated for boilers without delivery pressure requirement in accordance
with EN 13384. (Please also observe DIN 18160,
Part 1 "Domestic chimneys"). Take into consideration location-specific factors (hillside location of the
building, chimney position, slope of the roof, chimney
stack exit shape, etc.)!
In Switzerland, SIA recommendation 384/4 must be
observed!
In Austria, calculation is performed as prescribed by
ÖNorm M 7515.
Non-binding guide values for dimensioning of the
flue duct for boiler types Uno-3 (130-280).
Inside diameter of flue duct in mm
Boiler type
Uno-3
kW *
Chimney
height
11-15 m
130
130
~ 200
160
160
~ 200
190
190
~ 200
220
220
~ 250
250
250
~ 250
280
280
~ 250
*kW = maximum boiler output Based on:
flue gas conduit 5 m long, two 90° bends and one
45° bend, outside air 15°C, height above sea level
max. 800 m, flue gas conduit of same ø as flue gas
outlet on the boiler.
However, it is always advisable to consult the chimney engineer in the planning stages!
16
Installation
4 205 118 / 01
4.3
Fitting the burner
Fig. 11
Uno-3
A
B
C
D
Ø
Ø
130-160
190
220/270
450
170
190-220
240
270
450
250-280
240
270
450
E
F
G
H
L max
M
N
O
Ø
Ø
310
240
440
974
630
320
31
101
195
335
240
490
974
630
340
31
121
195
335
240
488
1434
630
340
31
121
- Depending on the size of the burner flange, an
intermediate flange may be required to attach the
burner.
- To allow the burner to be swung out 90° to the
left or right, the connections must be flexible and
routed to the burner in sufficiently large loops.
- The cavity between burner pipe and boiler flange
must be insulated with the fireproof fibre provided.
4.3.1 Sound insulation
- Gas pipes must be mounted in such a way that no
vibrations are transferred to the building.
- The burner can be equipped with a sound-absorbing
hood.
-We recommend that you install silencers
downstream of the boiler in the flue gas pipe.
Fig. 12
17
Installation
4.4Fuel
The boiler may only be operated with
the fuel designated on the boiler rating plate.
Uno-3 boilers are suitable for the combustion of the
following fuels:
- Heating oil EL in accordance with DIN 51 603 / SN
181 160 /2 /
ÖNorm C 1109
- Heating oil L in accordance with ÖNorm C 1108
- all fuel gases as defined by DVGW process sheet
G 260
4.5
4 205 118 / 01
4.6
Flue gas regulator set
The flue gas regulators fitted in each case are listed
on a label on the boiler casing (side section Figure
6, Pos. 9b/9c).
The installer can change the flue gas regulator set
fitted and thus vary the flue gas temperature within
a specific range.
Even in partial load operation, the flue
gas temperature must not fall below
100 °C.
Electrical connection
All electrical connections must be carried out by a
licensed electrician.
Regulators
For Switzerland, the following applies:
For the electrical connection, the circuit diagram
specific to the plant must be observed!
For Austria only:
The diagram folder is located in the switch control
box. Please affix the correct connection diagram to
the inside of the terminal cover.
An electrical circuit diagram is supplied with the boiler
controls.
An all-phase main switch with a minimum contact spacing of 3 mm must be fitted in the power supply line.
Applies only for Germany:
The diagram folder is located in the switch control box.
An electrical circuit diagram is supplied with the boiler
controls.
An all-phase main switch with a minimum contact spacing of 3 mm must be fitted in the power supply line.
Fig. 13
4.5.1 Electrical connection of the burner
- The burner must be connected to the boiler with
the standard plug-in connection.
- The burner cable must be shortened so that the
plug-in connection has to be parted to swing out
the burner.
18
Inspection hole
Installation
4 205 118 / 01
4.6.1 Flue gas and performance diagrams
Uno-3 (130) for Switzerland only
200
9R3/290
190
180
170
°C
160
150
140
130
120
110
100
75
80
85
90
95
100
105
110
115
120
125
130
kW
Uno-3 (160)
200
6R5/290
190
180
170
°C
160
150
140
130
120
110
100
85 90 95 100 105 110 115 120 125 130 135 140 145 150 155 160
kW
Uno-3 (190)
200
6R5 + 6R2/290
190
180
170
°C
160
150
140
130
120
110
100
95
105
115
125
135
145
155
165
175
185
195
kW
Uno-3 (220)
200
9R5/290
190
180
170
°C
160
150
140
130
120
110
100
130
140
150
160
170
180
190
200
210
220
kW
19
Installation
4 205 118 / 01
Abgastemp.
6-Uno-3 130-280
°C°C
Uno-3 (250)
200
190
180
170
160
150
140
130
120
110
100
150 160 170 180 190 200 210 220 230 240 250
6R5 + 3R3/290
kW
kW
Abgastemp.
°C°C
Uno-3 (280)
6-Uno-3 130-280
Seite 1
200
190
180
170
160
150
140
130
120
110
100
160 170 180 190 200 210 220 230 240 250 260 270 280
6R5 + 6R2/290
kWkW
Seite 1
The curves shown here represent an average value based on measurements taken with burners from various manufacturers. Deviations of ± 10% are normal.
kW = heat output
°C = flue gas temperature with heating oil EL,
boiler flow 80°C
return flow 60°C.
CO2 = 13%
During the combustion of natural gas or heating oil L, the flue gas temperature is approx. 15°C higher.
Flue gas temperature under other operating conditions
Influence of the boiler water temperature on the flue gas temperature
A change in the boiler water temperature of ± 10 K results in a change of approximately ± 6K in the flue gas
temperature.
Influence of the CO2 content in the flue gases
A change in the CO2 content of ± 1% changes the flue gas temperature by approx. ± 8°C.
Key to regulator designation
No. of regulators
Regulator height (example: 5 units)
6R5/290
Length of the regulators
20
4 205 118 / 01
4.7
Installation
Flow mixing loop / minimum limitation of the boiler return temperature
Hydraulic and control measures must be provided
to ensure that the temperatures do not fall below the
permissible minimum boiler flow and return temperature under any operating conditions.
4.8
Setting the temperature regulators
- without heating regulator:
Set the boiler temperature in accordance with the
outside temperature.
- with heating regulator:
The heating regulator automatically sets the correct
boiler temperature. The boiler temperature varies
between the minimum and maximum boiler temperatures entered.
If a calorifier is connected, the priority circuit
disables the boiler temperature regulator until
the temperature is reached. The boiler temperature can rise to approx. 85 °C.
4.9
Safety valves
The heating system and hot water supply must each
be protected with one safety valve against impermissibly high pressures. The discharge capacity of
the heating system safety valve must correspond
to the boiler’s maximum nominal heat output. The
valve is installed in the safety flow. In Germany, only
safety valves with the code letter "H" in the approval
mark may be connected, and they must always be
connected at the boiler safety flow. Water shortage
protection in accordance with EN 12828 Part 2 Section
9 is mandatory.
4.10 Charging pump (boiler with free-standing calorifier)
Speed of rotation and output regulation must correspond to the requirements of the free-standing calorifier.
Setting carried out by the heating installation engineer.
4.11 Heating pump
Speed of rotation and output regulation must correspond to the requirements of the system. They are to
be set by the heating installation engineer.
21
Commissioning
4 205 118 / 01
5.Commissioning
• Parts of the boiler which have contact with water
are made of ferrous materials.
Heating Water
• On account of the danger of stress cracking corrosion the chloride, nitrate and sulfate contents of the
heating water must not exceed 200 mg/l in total.
5.1
Water quality
The European Standard EN 14868 and
the directive VDI 2035 must be observed.
In particular, attention must be paid to the following
stipulations:
• Hoval boilers and calorifiers are designed for heating plants without significant oxygen intake (plant
type I according to EN 14868).
• Plants with
- continuous oxygen intake (e.g. underfloor heating systems without diffusion proof plastic piping) or
- intermittent oxygen intake (e.g. where frequent
refilling is necessary)
must be equipped with separate circuits.
• Treated filling and replacement water must be
tested at least 1x yearly. According to the inhibitor
manufacturer‘s instructions, more frequent testing
may be necessary.
• A refilling is not necessary if the quality of the heating water in existing installations (e.g. exchange of
boiler) conforms to VDI 2035.
The Directive VDI 2035 applies equally to the replacement water.
• New and if applicable existing installations need
to be adequately cleaned and flushed befor being
filled. The boiler may only be filled after the heating
system has been flushed!
• The pH value of the heating water should lie between 8.3 and 9.5 after 6-12 weeks of heating operation.
Filling and replacement water
• For a plant using Hoval boilers untreated drinking
water is generally best suited as heating medium,
i.e. as filling and replacement water. However, as
not all drinking water is suitable for use as as filling
and replacement water the water quality must fulfil the standard set in VDI 2035. Should the mains
water available not be suited for use then it must
be desalinated and/or be treated with inhibitors.
The stipulations of EN 14868 must be observed.
• In order to maintain a high level of boiler efficiency
and to avoid overheating of the heating surfaces
the values given in the table should not be exceeded (dependent on boiler performance ratings - for
multi-boiler plants rating of smallest boiler applies
- and on the water content of the plant).
• The total amount of filling and replacement water
which is used throughout the total service life of
the boiler must not exceed three times the water
capacity of the plant.
Maximum filling capacity based on VDI 2035
Total hardness of the filling water up to ...
[mol/m3] 1
f°H
d°H
e°H
~mg/l
Conductance 2
Boiler size of the
individual boiler
50 to 200 kW
200 to 600 kW
over 600 kW
1
2
<0,1
<1
<0,56
<0,71
<10
<20
0,5
5
2,8
3,6
50,0
100,0
1
10
5,6
7,1
100,0
200,0
1,5
15
8,4
10,7
150,0
300,0
2
20
11,2
14,2
200,0
400,0
2,5
25
14,0
17,8
250,0
500,0
3
30
16,8
21,3
300,0
600,0
>3,0
>30
>16,8
>21,3
>300
>600
maximum filling quantity without desalination
NO REQUI50 l/kW 20 l/kW 20 l/kW
RE50 l/kW 50 l/kW 20 l/kW
MENT
always desalinate
Sum of alkaline earths
If the conductance in µS/cm exceeds the tabular value an analysis of the water is necessary.
22
4 205 118 / 01
5.2
Commissioning
Filling the heating system
Filling of the heating system must be carried out by
trained personnel. The filling and replacement water
must comply with the quality requirements in the
relevant state or country (VDI 2035 or SWKI 88-4 or
ÖNORM H 5195).
5.3
Filling the calorifier (if present)
The heating boiler may be put into operation even
when the calorifier is not filled.
5.4
Initial commissioning
Important:
On first commissioning, check that all safety and control devices are functioning properly (in accordance
with the operating manual).
The operation and maintenance of the system must
be explained to the user in detail.
In some areas, gas or dual-fuel systems may only be commissioned by
an engineer from the local gasworks.
Check with the local gasworks to
make sure.
5.5
Oil/gas burner
Setting the burner must also be carried out by a specialist, and the setting must correspond to the heat
demand of the system.
Please see the technical information / assembly instructions supplied with the burner.
5.6
Handover to the operator / storage
Have the operator confirm in writing that the operating
and maintenance procedures have been explained
and that he or she has received a copy of the relevant
operating manuals. (see sample on page 40). The
system manufacturer is responsible for providing operating instructions for the whole plant. This technical
information / these installation instructions must not
be destroyed after completing the commissioning
procedures, but should be permanently stored with
the unit.
23
Maintenance
4 205 118 / 01
6.Maintenance
6.1
Information for fire inspector / chimney sweep regarding emission monitor key
All other control elements of the control unit are described in the operating instructions.
The emission monitor key can also be used to change over to manual operating mode.
Emission monitor key / Manual operation
To protect under floor heating systems
against invalid overheating during
emission monitoring / manual operation it is necessary to implement appropriate safety measures (e.g. safety
temperature limiter with pump switchoff). The duration of the emission monitoring is limited to 20 minutes and shall
be restarted, if necessary.
Scalding hazard due to hot water temperature, since the hot water temperature can exceed the temperature setpoint!
Emissions metering


PRESS
SHORTLY
Immediate end
Remaining time display
REACTIONS for emissions metering
- Time unit automatically 20 min. – thereafter reverts
- Boiler temperature - > maximum temperature restriction
- Regulate to the maximum temperature… the heating circuits and the water heaters
(at the direct heating circle only, if the warm water mode of operation is adjusted to parallel operation)
- With 2-step heat generator both stages are in operation
Manual operation


PRESS
> 5 seconds
REACTIONS for manual operation
- Set reference boiler temperature with button!
- All heating pumps ON
- Mixer without current - manual setting necessary!
- Note the maximum permissible temperature of the floor heating!
- The hot water temperature reaches the set DHW maximum temperature
(expert level standard 65°C).
24
Immediate end
4 205 118 / 01
Maintenance
6.2Cleaning
Cleaning should be performed at least twice per year.
Cleaning at intermediate intervals is necessary if the
flue gas temperature rises.
6.2.1 Preparatory work
- Switch boiler off (controller: set switch to "O," pull
the burner plug)
- Interrupt the fuel supply
- Open the boiler door
- Remove regulators (Figure 13)
- Remove flue gas collector cleaning cover (back)
6.2.2 Cleaning (dry or wet method)
- Clean combustion chamber, 2-pass (cylindrical
tubes), 3-pass (ribbed heating surface) thoroughly
with a brush or spray and then remove any combustion residue or sprayed liquid from the flue gas
collector and from the combustion chamber.
For wet cleaning:
Treat seals with graphite before carrying out
wet cleaning.
- Dispose of the cleaning fluid (scrubbing liquid) in
accordance with regulations.
6.2.3 Putting into operation again
- Insert the regulators
- Fit cleaning cover
- Close boiler door and reconnect burner plug.
Do not overtighten boiler door screws.
- Reconnect the fuel supply
- Where applicable, refit front cover
- Reset boiler switch to "I"
25
Overview of settings
7.
7.1
4 205 118 / 01
Overview of settings
Table of parameters
Designation
Regulator
Factory
10
20
30
40
50
Setting range /
Setting values
Type of device:
DHW:
SW:
Address:
Surface operation
Key :
Heating curve HC
OFF
OFF, 0,20 .... 3,5
Heating curve MC1
1,0
OFF, 0,20 .... 3,5
Heating curve MC2
1,0
OFF, 0,20 .... 3,5
Daytime target temperature HC
*)
20°C
5 .... 30°C *)
Daytime target temperature MC1
*)
20°C
5 .... 30°C *)
Daytime target temperature MC2
*)
20°C
5 .... 30°C *)
Night-time target temperature HC
*)
16°C
5 .... 30°C *)
Night-time target temperature MC1 *)
16°C
5 .... 30°C *)
Night-time target temperature MC2 *)
16°C
5 .... 30°C *)
DHW target temperature
50°C
5 ... DHW-Max.
*) Depending on the setting of system parameters 03 OPERATING MODE
Remote operation/room stations
Type
26
Heating circuit
Address
HW
SW
Overview of settings
4 205 118 / 01
Table for Time programs
DHW circuit
Time program P1
Tag
Cycle 1
from
to
Cycle 2
from
to
Time program P2
Cycle 3
from
to
Cycle 1
from
to
Cycle 2
from
to
Time program P3
Cycle 3
from
to
Cycle 1
from
to
Cycle 2
from
to
Cycle 3
from
to
Mo
Tu
We
Th
Fr
Sa
Su
Direct circuit
Time program P1
Tag
Cycle 1
from
to
Cycle 2
from
to
Time program P2
Cycle 3
from
to
Cycle 1
from
to
Cycle 2
from
to
Time program P3
Cycle 3
from
to
Cycle 1
from
to
Cycle 2
from
to
Cycle 3
from
to
Mo
Tu
We
Th
Fr
Sa
Su
Mixer Circuit 1
Time program P1
Tag
Cycle 1
from
to
Cycle 2
from
to
Time program P2
Cycle 3
from
to
Cycle 1
from
to
Cycle 2
from
to
Time program P3
Cycle 3
from
to
Cycle 1
from
to
Cycle 2
from
to
Cycle 3
from
to
Mo
Tu
We
Th
Fr
Sa
Su
Mixer Circuit 2
Time program P1
Tag
Cycle 1
from
to
Cycle 2
from
to
Time program P2
Cycle 3
from
to
Cycle 1
from
to
Cycle 2
from
to
Time program P3
Cycle 3
from
to
Cycle 1
from
to
Cycle 2
from
to
Cycle 3
from
to
Mo
Tu
We
Th
Fr
Sa
Su
27
Overview of settings
4 205 118 / 01
HYDRAULIC
Par.
Designation
Factory
10
20
30
40
50
Lev.
2
Function allocation of the output DHW charging pump
1
HF
3
Function allocation of the output Mixer circuit 1
3
HF
4
Function allocation of the output Mixer circuit 2
3
HF
5
Function allocation of the output Direct circuit Pump
2
HF
6
Function allocation of the variable output 1
OFF
HF
7
Function allocation of the variable output 2
OFF/ 4/ 43
HF
8
Function allocation of the variable input 1
OFF
HF
9
Function allocation of the variable input 2
OFF
HF
10
Function allocation of the variable input 3
OFF/ 2/ 33
HF
11
Indirect return increase
OFF
HF
12
Maximum limit energy management
80 °C
HF
13
Activation cooling buffer
OFF
HF
14
Release contact cooling to KVLF
OFF
HF
SYSTEM
Par.
Designation
LANGUAGE Selection of the style-language
10
20
30
40
50
Lev.
EN
BE
P1
HF
1
HF
2
Number of cleared switching time programs
3
Clearing for separate operating mode
4
Limit temperature for summer disconnection
22 °C
HF
5
System frost protection
3 °C
HF
6
Demand contact module for VE1
1
HF
7
Demand contact module for VE2
1
HF
8
Demand contact module for VE3
1
HF
9
Air conditioning zone
-12 °C
HF
10
Building type
Automatic reversion time (surface end user level, except
info. level)
Pump and mixer compulsory operation
2
HF
5 Min
HF
11
12
13
ON
HF
OFF
HF
ON/ OFF
HF
15
Logical fault signal
Automatic SET function
(after 24:00, is automatically set to OFF)
Blocking code for heating Installer
18
Release cycle temperature
19
Frost protection mode
21
RTC adjustment
23
Blocking code operator level
OFF
HF
24
Temperature display in Fahrenheit
OFF
OEM
26
First commissioning date (after 24:00)
-
OEM
27
Fault report (only TTT/UG)
2
HF
28
Fault stack 2
ON
HF
29
Characteristic curve emergency operation
0 °C
HF
30
Thermostat function sensor allocation
31
Thermostat function reference value
32
33
14
RESET
28
Factory
OEM
OFF
HF
30 Min
HF
0
HF
AF
HF
1 °C
HF
Thermostat function switching difference
3K
HF
Thermostat function anti-blocking protection
Top: ArtNo - HW Index
Bottom: Code:REV - Software version
Reset parameter values
ON
HF
-----
OEM
BE
Overview of settings
4 205 118 / 01
DHW
Par.
Designation
Factory
10
20
30
40
50
Lev.
40/ 45 °C
BE
2
DHW-legionella protection-day
OFF
HF
3
DHW-egionella protection-time
HF
4
DHW-legionella protection-temperature
5
DHW-temperature recording
6
DHW-maximum temperature limit
7
DHW-mode of operation
2:00
50/ 55/ 65/
70 °C
1
50/ 55/ 65/
70 °C
1
8
DHW-tank discharge protection
DHW-NIGHT DHW - economy temperature
9
DHW-charging temperature excess
10
DHW-switching difference
HF
HF
HF
HF
ON/ OFF
HF
7/ 20 K
HF
5K
OEM
11
DHW-charging pump follow-on
0.5/ 1/ 2/ 5 Min
OEM
12
ZKP-switching time program
AUTO
HF
13
ZKP-economy interval (pause)
0 Min
HF
14
ZKP-economy interval (period duration)
17
H-GEN behaviour during SLP follow-on time
18
DHW-parallel loading
19
DHW-time-out
20
PI-reference value control
21
PI-amplification factor, P-portion Xp
22
PI-scanning time Ta
23
PI -reset time Tn
20 Min
HF
AUTO/ OFF
HF
OFF
OFF/
30 Min
OFF
HF
HF
0,1 %/ K
OEM
20 sec
OEM
600 sec/ °C
OEM
HF
UNMIXED CIRC
Par.
Designation
Factory
10
20
30
40
50
Lev.
1
Type of reduced operation
ECO/ ABS
HF
2
Heating system (exponent)
DK= 1,30
HF
3
Room override (in connection with room sensor)
3
HF
4
Room factor
OFF
HF
5
Adaptation heating curve
OFF
HF
6
Switch-on optimisation
1
HF
7
Heating limit
0,5
OEM
8
Room frost protection limit
10 °C
HF
OFF
HF
0
HF
20 °C
HF
9
Room thermostat function
10
Outside temperature allocation
11
Constant temperature reference value
12
Minimum temperature limit
10 °C
HF
13
Maximum temperature limit
55/ 75 °C
HF
14
Temperature elevation Heating circuit
DK=0
HF
15
Pump follow-on
5 Min
HF
16
Screed function
OFF
HF
23
Room control K-factor
8
HF
24
Room control Tn-factor
35 MIN
HF
25
Vacation mode
STBY
HF
36
Minimum value override
OFF
HF
XXXXX
HF
Name heating circuit (max. 5 letters)
29
Overview of settings
4 205 118 / 01
MIX. VALVE-1
Par.
Designation
10
20
30
40
50
Lev.
1
Type of reduced operation
ECO/ ABS
HF
2
Heating system (exponent)
MK= 1,10
HF
3
Room override (in connection with room sensor)
4
Room factor
5
Adaptation heating curve
6
Switch-on optimisation
7
Heating limit
8
9
10
Outside temperature allocation
11
Constant temperature reference value
12
13
14
15
3
HF
100 %
HF
ON
HF
1
HF
0,5
OEM
Room frost protection limit
10 °C
HF
Room thermostat function
OFF
HF
0
HF
20 °C
HF
Minimum temperature limit
10 °C
HF
Maximum temperature limit
55/ 75 °C
HF
Temperature elevation/ abatement heating circuit
0/ 8 K
HF
Pump follow-on
5 Min
HF
16
Screed function
OFF
HF
18
P-portion Xp
2,0 %/ K
OEM
19
Scanning time Ta
20 sec
OEM
20
I-portion Tn
270 sec
OEM
21
Running time servomotor
150 sec
HF
22
End position function, valve
1
OEM
23
Room control K-factor
8
HF
24
Room control Tn-factor
35 MIN
HF
25
Vacation mode
STBY
HF
36
Minimum value override
OFF
HF
37
Mixer lead time
OFF
HF
38
Regulation offset
0
HF
50
Cooling switch-on point, OT
OFF
HF
51
Cooling max. point, OT
35 °C
HF
52
Cooling reference flow temp. at switch-on point
18 °C
HF
53
Cooling reference flow temp. at max. point
24 °C
HF
54
Cooling reference room temp. at switch-on point
23 °C
HF
55
Cooling reference room temp. at max. point
28 °C
HF
18 °C
OEM
XXXXX
HF
56
Min. temp. cooling
Name heating circuit (max. 5 letters)
30
Factory
Overview of settings
4 205 118 / 01
MIX. VALVE-2
Par.
Designation
Factory
10
20
30
40
50
Lev.
1
Type of reduced operation
ECO/ ABS
HF
2
Heating system (exponent)
MK= 1,10
HF
3
Room override (in connection with room sensor)
4
Room factor
5
Adaptation heating curve
6
Switch-on optimisation
7
Heating limit
8
9
10
Outside temperature allocation
11
Constant temperature reference value
12
13
14
15
3
HF
100 %
HF
ON
HF
1
HF
0,5
OEM
Room frost protection limit
10 °C
HF
Room thermostat function
OFF
HF
0
HF
20 °C
HF
Minimum temperature limit
10 °C
HF
Maximum temperature limit
55/ 75 °C
HF
Temperature elevation/ abatement heating circuit
0/ 8 K
HF
Pump follow-on
5 Min
HF
16
Screed function
OFF
HF
18
P-portion Xp
2,0 %/ K
OEM
19
Scanning time Ta
20 sec
OEM
20
I-portion Tn
270 sec
OEM
21
Running time servomotor
150 sec
HF
22
End position function, valve
1
OEM
23
Room control K-factor
8
HF
24
Room control Tn-factor
35 MIN
HF
25
Vacation mode
STBY
HF
36
Minimum value override
OFF
HF
37
Mixer lead time
OFF
HF
38
Regulation offset
0
HF
50
Cooling switch-on point, OT
OFF
HF
51
Cooling max. point, OT
35 °C
HF
52
Cooling reference flow temp. at switch-on point
18 °C
HF
53
Cooling reference flow temp. at max. point
24 °C
HF
54
Cooling reference room temp. at switch-on point
23 °C
HF
55
Cooling reference room temp. at max. point
28 °C
HF
18 °C
OEM
XXXXX
HF
56
Min. temp. cooling
Name heating circuit (max. 5 letters)
31
Overview of settings
4 205 118 / 01
HEAT GENER.
Par.
Designation
Factory
10
20
30
40
50
Lev.
1/ 2/ 5
HF
OFF/ 3
5/ 48/ 65/ 75
°C
75/ 85 °C
HF
HF
1
HF
1
OEM
2 Min
HF
1
H-GEN model
2
Start-up protection H-GEN
3
Minimum temperature limit H-GEN
4
Maximum temperature limit H-GEN
5
Mode of action minimum temperature limit H-GEN
6
Sensor mode operation for H-GEN
7
Minimum burner running time
8
Burner switching difference I
6K
HF
HF
9
Burner switching difference II
12 K
HF
10
Time-out stage II
10
HF
11
Release mode stage II
1
HF
12
DHW charging mode 1-2 stage
2
HF
13
Lead time, boiler circuit pump
1 Min
HF
14
Follow-on time, boiler circuit pump or parallel boiler release
5 Min
HF
15
Search time feed pump, primary pump
5 Min
HF
16
Exhaust gas temperature monitoring
OFF
HF
17
Exhaust gas limit value
18
Boiler gradient
19
Modulation P-portion Xp
20
Modulation scanning time Ta
21
Modulation adjustment time Tn
22
23
24
Modulation start-up output
70
HF
25
Outside temperature block
OFF
OEM
26
Basic charge elevation
27
29
Minimum temperature limit, heating circuits
Switching difference, minimum temperature limit Heating
circuits
H-GEN forced discharge
30
OEM Maximum limit
31
Minimum load control
34
Output limitation heating
35
Output limitation hot water
100 %
HF
36
ET blocking 2.burner stage
OFF
HF
37
Running time meter
38
DHW release regulator (CD)
39
Emergency operation temperature H-Gen (e.g. for 70-8)
40
Heat balance (from V3.2)
41
Reset heat balance
28
200 °C
HF
OFF
OEM
5 %/ K
OEM
20 sec
OEM
180 sec/ °C
OEM
Modulation running time
12 sec
HF
Modulation starting time
200 sec
HF
42
Volumetric flow rate
43
Density, medium
44
Specific thermal capacity, medium
0 K/ 10K
OEM
5/ 38/ 65 °C
HF
2K
OEM
OFF
HF
110 °C
OEM
OFF
OEM
100 %
HF
1
HF
ON
HF
70 °C
HF
ON
HF
HF
0,0 l/ Min
0,0 l/ IMP
1,00 kg/ l
4,2
HF
HF
HF
RESET ST-1 Reset counters starts and running time, stage 1
OEM
RESET ST-2 Reset counters starts and running time, stage 2
OEM
32
Overview of settings
4 205 118 / 01
RETURN CONTR
Par.
2
Designation
Minimum limit return temperature / referance value return
temperature
Switch-off difference
3
Pump follow-on time
1
Factory
10
20
30
40
50
38 °C
Lev.
HF
2K
HF
1 Min
HF
SOLAR
Par.
Designation
1
Switch-on difference
2
Switch-off difference
3
Minimum running time SOP
Factory
10
20
30
40
50
Lev.
10 K
HF
5K
HF
3 Min
HF
4
Solar collector maximum temperature
100 °C
HF
5
Solar tank maximum limit (KSPF)
65 °C
HF
6
Solar mode of operation
2
HF
7
Heat generator cycle lock (only when parameter 06=1,3,4)
0,5 h
HF
8
Solar priority parallel changeover
10 K
HF
Solar heat balance
OFF
HF
9
SOLAR
RESET
Reset heat balance
11
Volumetric flow rate
12
Density, medium
13
Specific thermal capacity, medium
14
15
16
17
HF
0,0 l/ Min
0,0 l/ IMP
1,05 kg/ l
HF
HF
3,6 KJ/ kgK
HF
Final switching-off temperature
120 °C
HF
Test cycle solar charging switch-over
10 Min
HF
Switch-over temperature (SLVF)
60 °C
HF
Solar minimum temperature
OFF
HF
SOLID FUEL
Par.
Designation
Factory
10
20
30
40
50
Lev.
1
Minimum temperature
60 °C
HF
2
Maximum temperature
95 °C
HF
3
Switch-on difference
10 K
HF
4
Switch-off difference
5K
HF
5
Clock block, heat generator
15
HF
33
Overview of settings
4 205 118 / 01
BUFFER
Par.
Designation
Factory
10
20
30
40
50
Lev.
1
Minimum temperature
5/ 20 °C
HF
2
Maximum temperature
95 °C
HF
3
Temperature elevation, H-GEN
8/ 10/ 12K
HF
4
Switching difference
2/ 5/ 10K
HF
5
Forced discharge
OFF
HF
6
Skimming function switch-on difference
10 K
HF
7
Skimming function switch-off difference
5K
HF
8
Start-up protection
OFF
HF
9
Discharge protection
OFF
HF
10
Buffer mode of operation
2/ 3
HF
11
Pump follow-on time
3 Min
HF
12
Switch-off reference value temp.
70 °C
HF
13
H-GEN release temp. skimming function
60 °C
HF
MAIN SUPPLY
Par.
Designation
1
PI-amplification factor, P-portion Xp
2
PI-scanning time Ta
3
PI -reset time Tn
Factory
10
Lev.
0 %/ K
HF
20 sec
HF
600 sec/ °C
HF
CASCADE
Par.
Designation
Factory
10
Lev.
1
Switch-off difference
3K
OEM
2
Connecting delay
20
OEM
3
Switch-off delay
5
OEM
4
Switching output stage sequence
65
OEM
5
Stage reversal
OFF
OEM
6
Control stage
1
BE
7
Peak load stage
OFF
OEM
8
Group switch-over
OFF
OEM
9
DHW fast activation
OFF
OEM
10
Peak load elevation
10 K
OEM
BUS
Par.
34
Designation
Factory
10
20
30
40
50
Lev.
1
Bus address central device
10
HF
2
Bus right RS direct circuit
1
HF
3
Bus right RS mixer circuit 1
1
HF
4
Bus right RS mixer circuit 2
1
HF
Overview of settings
4 205 118 / 01
SERVICE
Par.
Designation
Factory
10
20
30
40
50
Lev.
Service 1 (Cleaning ST1 )
7
BE
Cleaning according to fixed date
OFF
BE
Cleaning according to fixed interval
OFF
BE
4
Cleaning according to cleaning counter
OFF
BE
5
Reset cleaning display 1
1
Suspend message «CLEANING ST-1» for X days
2
3
BE
Service 2 (Cleaning ST2)
6
Suspend message «CLEANING ST-2» for X days
7
BE
7
Cleaning according to fixed date
OFF
BE
8
Cleaning according to fixed interval
OFF
BE
9
Cleaning according to cleaning counter
OFF
BE
10
Reset cleaning display 2
BE
Service 3 (maintenance ST1 )
11
Suspend message «MAINTENANCE ST-1» for X days
7
HF
12
Maintenance according to fixed date
OFF
HF
13
Maintenance according to fixed interval
OFF
HF
14
Maintenance according to maintenance counter
OFF
HF
15
Reset maintenance display 1
HF
Service 2 (maintenance ST2 )
7
HF
Maintenance according to fixed date
OFF
HF
Maintenance according to fixed interval
OFF
HF
19
Maintenance according to maintenance counter
OFF
HF
20
Reset maintenance display 2
16
Suspend message «MAINTENANCE ST-2» for X days
17
18
HF
ALARM 1
Par.
Designation
10
20
30
40
50
Lev.
1
Alarm 1
OEM
2
Alarm 2
OEM
3
Alarm 3
OEM
4
Alarm 4
OEM
Alarm 5 - 20
OEM
Reset fault signals
OEM
5 ... 20
21
ALARM 2
Par.
(can ony be activated with H-Gen 5)
Designation
10
20
30
40
50
Lev.
1
Alarm 1
OEM
2
Alarm 2
OEM
3
Alarm 3
OEM
4
Alarm 4
OEM
Alarm 5 - 20
OEM
Reset fault signals
OEM
5 ... 20
21
35
Overview of settings
4 205 118 / 01
FAULT REPORTING OVERVIEW TopTronic®T
Status
36
Designation
Fault type
Code
System
External sensor
Interruption
10-0
System
External sensor
Short-circuit
10-1
Remark
System
Boiler sensor
Interruption
11-0
System
Boiler sensor
Short-circuit
11-1
System
Flow sensor 1
Interruption
12-0
MC1=off, YK1=no current
MC1=off, YK1=no current
System
Flow sensor 1
Short-circuit
12-1
System
Storage sensor
Interruption
13-0
System
Storage sensor
Short-circuit
13-1
System
VE 2
Interruption
14-0
System
VE 2
Short-circuit
14-1
System
VE 2
Alarm
14-7
System
VE 3
Interruption
15-0
System
VE 3
Short-circuit
15-1
System
VE 3
Alarm
15-7
System
VE 1
Interruption
16-0
System
VE 1
Short-circuit
16-1
System
VE 1
Alarm
16-7
System
Solar tank sensor
Interruption (KSPF)
17-0
System
Solar tank sensor
Short-circuit (KSPF)
17-1
System
Flow sensor 2
Interruption
18-0
MC2=off, YK2=no current
MC2=off, YK2=no current
System
Flow sensor 2
Short-circuit
18-1
System
Collector sensor
Interruption (KVLF)
19-0
System
Collector sensor
Short-circuit (KVLF)
19-1
System
Room sensor (RS)
Interruption
20-0
System
Room sensor (RS)
Short-circuit
20-1
System
Burner 1
No switching off (1 min.)
30-2
With par. log. alarm can be switched off
System
Burner 1
No switching on (10 min.)
30-3
With par. log. alarm can be switched off
System
Burner 2
No switching off (1 min.)
31-2
With par. log. alarm can be switched off
System
Burner 2
No switching on (10 min.)
31-3
With par. log. alarm can be switched off
System
Exhaust gas temperature
Exceeding
33-5
System
Exhaust gas temperature
SLT triggered
33-8
System
Cleaning stage 1
Triggering by date
40-1
System
Cleaning stage 1
Triggering by interval
40-2
System
Cleaning stage 1
Triggering by counter
40-4
System
Maintenance stage 1
Triggering by date
41-1
System
Maintenance stage 1
Triggering by interval
41-2
System
Maintenance stage 1
Triggering by counter
41-4
System
Cleaning stage 2
Triggering by date
42-1
System
Cleaning stage 2
Triggering by interval
42-2
System
Cleaning stage 2
Triggering by counter
42-4
System
Maintenance stage 2
Triggering by date
43-1
System
Maintenance stage 2
Triggering by interval
43-2
System
Maintenance stage 2
Triggering by counter
43-4
Overview of settings
4 205 118 / 01
FAULT REPORTING OVERVIEW TopTronic®T
Status
Designation
Fault type
Code
Logical
Boiler temperature
Not reached (90 min.)
50-4
Logical
Tank temperature
Not reached (4 hr.)
51-4
Logical
Flow temperature MC1
Not reached (1 hr.)
52-4
Logical
Flow temperature MC2
Not reached (1 hr.)
53-4
Logical
Room temperature HC
Not reached (3 hr.)
54-4
Logical
Room temperature MC1
Not reached (3 hr.)
55-4
Logical
Not reached (3 hr.)
56-4
Address collision
70-0
System
Room temperature MC2
Lock by energy supply company
ST 2
Activity
System
Activity
System
Activity
System
System
Activity
HP return sensor
System
HP return sensor
System
QF
System
QF
System
System
System
System
System
System
System
No T2B signal
70-1
No FA signal
Regulator with address 10 is
missing
Data bus error
Return min. temp. below setpoint
70-6
Return max. temp. exceeded
Heat source min. temp. below
setpoint
Heat source max. temp. exceeded
(cooling operation)
85-5
QF
WPS
Fault heat source sensor
Variable input HP fault
-87-7
Pulse counter
Fault
Fault
Fault
No pulse (5 min.)
Warning
Lock-out
Blocking
90-0
W:XX
E:XX
B:XX
Remark
70-8
70-9
85-4
No Hoval regulator
86-4
86-5
Standard signal «VE-x»
Warning in automatic firing device
Fault in automatic firing device
Fault in automatic firing device
SENSOR ALLOC.
Par.
1
RS-T
Designation
Factory
Balancing external sensor
0
10
20
30
40
50
Lev.
OEM
Balancing room sensor (only adjustable with RS-T)
0
HF
2
Balancing heat generator
0
OEM
3
Balancing tank sensor
0
OEM
4
Balancing flow sensor 1
0
OEM
5
Balancing flow sensor 2
0
OEM
6
Balancing solar collector sensor
0
OEM
7
Balancing solar buffer sensor
0
OEM
8
Balancing variable input 1
0
OEM
9
Balancing variable input 2
0
OEM
10
Balancing variable input 3
0
OEM
37
4 205 118 / 01
38
4 205 118 / 01
39
Copy for plant user
C O N F I R M AT I O N
The user (owner) of the system herewith confirms that
- he has received adequate instruction in the operating and maintenance of the installation,
- received and taken note of the operating and maintenance instructions and, where applicable
other documents concerning the heat generator and any further components.
- and is consequently sufficiently familiar with the installation.
Place, Date:
Installation address: ...........................................................................
...........................................................................
.............................................................
Type:
.............................................................
Ser.No.: .............................................................
Year of manufacture: .........................................
System installer:
System user:
............................................................................
...........................................................................
Copy of system installer
C O N F I R M AT I O N
The user (owner) of the system herewith confirms that
- he has received adequate instruction in the operating and maintenance of the installation,
- received and taken note of the operating and maintenance instructions and, where applicable
other documents concerning the heat generator and any further components.
- and is consequently sufficiently familiar with the installation.
Place, Date:
Installation address: ...........................................................................
...........................................................................
.............................................................
Type:
.............................................................
Ser.No.: .............................................................
Year of manufacture: .........................................
System installer:
System user:
............................................................................
...........................................................................
Download