New South Wales Government Resolving disputes in construction contracts under the Procurement System for Construction a guide for Project Directors and Project Managers One dispute can double the cost of a project Three key objectives of dispute resolution Five levels of dispute resolution A single dispute can substantially increase project cost and duration and consume an enormous amount of project resources and time. Project Directors need to actively monitor dispute resolution and risk. When resolving a dispute there are three key objectives. There are potentially five levels in the dispute resolution process, each more costly and involved than the previous level. It is always best to fairly resolve the dispute at the lowest level possible. 1 3 1 Resolve issues cost-effectively Resolution agreements must be based on contract entitlements; however, the resolution process should be aimed at achieving value for money. It is rarely appropriate to incur substantial resolution costs over relatively minor matters. 2 Act quickly Definition A dispute occurs when a disagreement between the Contractor and the Project Manager is not resolved, and one party gives formal notice to the other party that it wishes to pursue the matter. (A dispute is called an Issue in C21/GC21 General Conditions of Contract.) Speedy action can resolve issues before they become formalised into disputes. Promptly working through the resolution process can protect project objectives, maintain productivity and prevent further disputes. The resolution process must be driven—do not allow it to stall. 5 Most contract disputes are resolved by negotiation. Negotiations occur throughout Levels 1 to 5. At different levels, negotiation may be driven by different people. Which Agencies does this approach apply to? This brochure summarises the Contract Dispute Resolution Guideline which is part of the Procurement System for Construction. Agencies that are required to use the System are required to adhere to the approach outlined in this brochure. 3 Maintain probity Probity includes adhering to public sector standards of behaviour, such as fairness, impartiality, consistency, and accountability. Probity is doing things the right way and being seen to do things the right way. Levels of dispute resolution There are potentially five levels in the dispute resolution process, each more costly and involved than the previous level. At different levels, negotiation may be driven by different people. Level 1 Deal with Level 5 Litigation Level 4 Expert determination Level 3 Intensive negotiation Level 2 Senior Executives confer disagreements Negotiation driven by Project Manager Senior Executive Dispute Manager Litigation Overview Team Level 1 Level 2 Level 3 Deal with disagreements Senior Executives confer Intensive negotiation Level 4 Level 5 Expert Determination Litigation (the contract prescribes the Expert Determination process, intensive negotiation is recommended in parallel) Disagreements and differences of opinion are common in contracts – but they don’t need to escalate to disputes. If the Project Manager and Contractor disagree and a formal dispute is notifi ed the matter is elevated to the Principal’s and Contractor’s Senior Executives. The majority of formal disputes are resolved at this stage. Negotiation is relatively quick and inexpensive. The majority of contract In Expert Determination an independent industry Expert makes a decision about disputes are resolved by negotiation. the dispute. This has generally resulted in Level 3 specifi cally focuses on intensive a satisfactory outcome and is signifi cantly negotiation, however negotiations continue throughout Levels 1 to 5. cheaper and quicker than litigation. Litigation is an expensive and timeconsuming process. Careful consideration is required before initiating litigation. New negotiations directed by the litigation overview team should also commence. Typical initial trigger Contractor verbally expresses dissatisfaction with an unresolved variation or other matter Contractor or Principal formally advises the other party that the matter is a Either party decides to reject Expert Contractor or Principal formally refers the dispute to Expert Determination. Determination. dispute under the contract. Key actions at this level Re-examine the issues Senior Executives confer Disagreements and differences of opinion can often be resolved by reasonable discussion. Considering the viewpoint of the other party and being objective is vital to resolving disagreements. C21/GC21 contracts typically require the Contractor to wait for at least 21 days after notifying a dispute before referring the issue to Expert Determination. During this time the Principal’s and Contractor’s Get advice It’s always worthwhile for the Project Manager to get another person’s opinion about the claim – they can provide a fresh perspective. Consider contract as a whole Consider the matter in the context of the overall contract and how it has been administered. Beware of focussing only on selective phrases from the contract. Work cooperatively Make every effort to help the Contractor meet its contractual obligations. Compromise on matters that will not adversely impact the project outcome while maintaining control over contract cost, quality and timing. Prepare thoroughly Prepare thoroughly Be aware of Government policy The Expert Determination process requires a coordinated and managed strategy. Additional resources may be required: programmers, engineering or building consultants, and solicitors. Senior Executive must promptly confer to resolve the dispute. Effective negotiation requires thorough preparation and an in depth understanding of the contractual and factual issues surrounding the dispute. Negotiation must be approved by the Agency and undertaken by experienced and well-informed people. It is NSW Government policy to resolve disputes using alternatives to the court system wherever possible. Litigation is generally a last resort. Usually litigation is initiated by the Contractor but is occasionally initiated by the Principal. ‘Conferring’ typically involves making contact with the Contractor, understanding its position, presenting the For risk management reasons, at least two people must be present in intensive negotiations to represent the Principal. The Expert Determination process and timeframe will be specifi ed in the contract. Principal’s opinion and reasons for it, and seeking to resolve the issue. Follow the contract dispute procedure C21/GC21 contracts prohibit the Contractor from referring an issue to Expert Determination (or taking any other action) more than 49 days after notifi cation of a dispute. This ensures issues are addressed promptly and it is important to preserve this time bar. The dispute resolution method and timeframes defi ned in the contract must be followed unless there are exceptional circumstances and Contractor agreement. Failure to follow the contract may result in waiving the Principal’s rights. Negotiate The negotiating team should be receptive to the Contractor’s arguments yet examine them rigorously. Negotiation involves each party working to convince the other of their position. Typically each party moves towards a compromise position both can accept and justify. Negotiation is an opportunity to resolve all outstanding disagreements, not just the issue in dispute. To avoid misunderstandings, a list of matters agreed, including payment and related issues, should be prepared at the time of negotiation and then formalised. Engage an Expert The parties agree on an Expert, or the independent body nominates one. The Principal engages the Expert, and both parties share equally the fees of the Expert and bear their own costs. Make submissions Establish a litigation overview team This team provides advice regarding the instruction to be given to the legal team – the outcome of litigation is only as good as the instruction given. The team must include the Project Director, the Dispute Manager, representatives of the Agency, and a person from the Contract Dispute Resolution Unit. Both parties make submissions to the Expert within timeframes defi ned in the contract. The Expert considers the submissions and makes a determination. The process may take some months. Engage a legal team The legal team receives instruction, provides legal advice, prepares for court proceedings and represents the Principal. The Expert’s determination is fi nal and binding if the value is under a specifi ed amount. If over the specifi ed amount (often $500,000) the decision is not binding and either party can choose to commence litigation. Project Manager (including Contract Administrator / Principal’s Authorised Person / Principal’s Representative) Seeks advice from others in their own organisation and the Senior Executive under the contract Becomes familiar with the contract dispute resolution clauses and timeframes Re-examines the issue Liaises with Senior Executive and Attempts to resolve the disagreement with the Contractor provides relevant documents Advises Senior Executive if a dispute is expected If resolution is achieved, prepares submission to obtain Agency approval and formalises the agreement. Prepares the initial position paper (typically within 14 days of dispute notifi cation) Formally notifi es Contract Dispute Resolution Unit If resolution is achieved, prepares submission to obtain Agency approval and formalises the agreement. Provides information to Dispute Manager, including copies of the contract documents; relevant communications; and details of other related disputes or disagreements Contributes to the Expert Determination process as required Contributes to the litigation process as required Reviews summary of determination and makes comment. Reviews updated position papers and gives advice on the issue as required. Reviews updated position papers and provides input Provides information to the negotiation team Assists to formalise resolution if achieved. Senior Executive (or Principal’s Agent) May take a proactive role in preventing disputes Receives copy of dispute notifi cation from Contractor Continues to takes part in negotiation process if requested by the Project Contributes to the Expert Determination process if required Contributes to the litigation process if required Provides advice to Project Manager Provides support to Project Manager and reviews initial position paper Director Reviews summary of determination and makes comment, if required. Reviews updated position papers and makes comment, if required. Responsible for resolving the dispute Responsible for resolving the dispute Reviews all relevant documents and gathers information from Project Manager, Senior Executive and the Contractor Manages the Expert Determination process, including defi ning the issue, preparing recommendations for Agency approval and helping to select and engage the Expert Updates the previous position paper, including the litigation strategy and a new negotiation strategy and provides further updates of position paper as required May speak informally with people at an equivalent level in the Contractor organisation May attend some or all key site meetings. Promptly confers with Contractor’s Senior Executive to resolve dispute Reviews updated position papers and provides input May assist to formalise the resolution. May assist to formalise the resolution. Dispute Manager (role usually performed by Project Manager if dispute is less than $250,000) Not involved at this level Not involved at this level Prepares updated position paper, including a negotiation strategy and an Expert Determination strategy, and provides further updates if required Implements negotiation and Expert Determination strategies Manages and usually prepares the Principal’s submissions Summarises determination and, if it is not binding, recommends whether it should be accepted or not and why. Supports the litigation overview team and the legal team, including preparing detailed estimates and taking part in negotiation as required Drafts Agency briefi ng notes and recommendations as required. Reports on outcome of negotiations to Project Director If resolution in principle is achieved, prepares submission to obtain Agency approval and formalises the agreement. Project Director (the link to the Agency) Monitors the dispute risk factors (including the number and duration of unresolved claims) and intervenes as required Finds out whether the relationship between the Project Manager and the Contractor is becoming adversely affected by disagreement. If so, addresses the issues. Reviews issues and cost estimates presented in the initial position paper Engages Dispute Manager Obtains Agency approval of proposed Reviews updated position papers Expert Provides support to the Senior Executive, including obtaining Agency approval and funding to settle if required Selects the people to be involved in negotiation Monitors Expert Determination process Liaises with Agency and obtains approval of strategies. Seeks approval for additional resources if required Assists Agency to make a decision to accept or reject the determination. Monitors resolution progress and intervenes if progress stalls Prepares to engage Dispute Manager should dispute not be resolved at this level. Monitors negotiation process and intervenes, if required. Reviews summary of determination Regularly informs Agency of progress, provides advice to and takes directions from Agency Appoints litigation overview team as approved by the Agency and considers their advice Engages, briefs and gives instructions to the legal team as directed by the Agency, upon consideration of litigation overview team’s advice. Position papers provide rigour Position papers are prepared for the Principal and the contents must not be disclosed to the Contractor or its agents. Writing a position paper provides a disciplined procedure to re-examine the issue in dispute and to consider it from different perspectives. It provides a concise summary to the Agency so that it can make informed decisions about the resolution process. All disputes require a position paper including a risk assessment. Over time, position papers provide an audit trail of the dispute management process. Selecting a Dispute Manager The Project Manager manages the dispute resolution process at Levels 1 and 2. However, if a dispute resolution process stalls at Level 2, or if the Project Manager has a conflict of interest, the Project Director should engage a different person as Dispute Manager. Once the matter is referred to Expert Determination, the Project Director engages a Dispute Manager who may be: • the Project Manager (if the dispute is less than $250,000) • the Senior Executive • selected from the Prequalification panel, or The Dispute Manager must have the necessary skills, experience, aptitude and time and have no conflict of interest. Feb 2007 Position papers should include: • a description of the dispute and all contributing factors • a consideration of the possible sources of liability and the likelihood of each being accepted by an Expert • an estimation of the range of possible amounts involved— most probable outcome and worst case scenario • a discussion of the options available to resolve the dispute and the costs associated with each • a recommendation for the next step in the dispute resolution process. The importance of a formalised settlement agreement Successful negotiations should result in full and final settlement of all issues. Writing down a list of agreed matters jointly prepared at the time of the discussion creates a shared understanding and reduces the opportunity for future disagreement. The agreement must then be formalised, for example by: • a variation approval (suitable if a disagreement has been resolved early), • an exchange of letters (suitable if a dispute has been notified but resolved quickly), or • a Deed of Release (suitable for negotiated resolution of more complex matters). The level of detail in the position paper should be appropriate to the complexity of the dispute and the stage of the resolution process. When the threshold stated in the guideline (typically $100,000) is exceeded, direction-setting position papers must be reviewed by the CDRU. The CDRU will either confirm the direction or suggest alternative approaches. See the Contract Dispute Resolution Guideline for more detail. It is available from the web at www.procurepoint.nsw.gov.au . ‘Security of Payment’ and disputes The Building and Construction Industry Security of Payment (SoP) Act 1999 addresses Contractor cash flow. Some Contractors may attempt to deal with a dispute by submitting an adjudication application under the SoP Act. If an adjudication requires the Principal to pay the Contractor, the Principal must make this payment. However, an adjudication does not resolve the underlying dispute–either party may still pursue the matter as a dispute under the contract. If both parties choose to accept the adjudication as an appropriate resolution, it is still necessary to close the dispute and formalise the agreement.