California Independent System Operator Data Templates for Determining the Baseline Transmission Capacity Allocation on Path 26 to LSEs in the ISO Control Area for Purposes of Resource Adequacy Planning As part of Decision 07-06-029, the California Public Utilities Commission (CPUC) adopted the “Path 26 Counting Constraint” proposal. Similar to the ISO’s Import Capability Allocation process under ISO Tariff section 40.4.6.2.1, the Path 26 Counting Constraint proposal is a multi-step, iterative process to allocate Path 26 capability that will prevent over reliance by Load Serving Entities (LSEs) on the limited transfer capability across this transmission path when meeting resource adequacy (RA) requirements. The Path 26 Counting Constraint is not currently incorporated into the ISO Tariff. Accordingly, the Path 26 Counting Constraint, as outlined in the Proposed Decision, applies only to CPUC-jurisdictional LSEs during the 2016 RA compliance year. Nevertheless, the ISO requests that all Scheduling Coordinators (SC) for LSEs serving load within the ISO Control Area respond to this request so that the ISO can accurately implement the Path 26 Counting Constraint proposal with all available data. RA commitments are used in the Path 26 Counting Constraint in two ways: For determining an LSE’s “baseline” allocation For determining the effect of “netting” This data template applies ONLY to the baseline determination. A subsequent data template will be forwarded by the ISO that explains and addresses netting across Path 26. Determining the “Baseline” Allocation The baseline is the amount of Path 26 transfer capability that an LSE is eligible to receive in the allocation process without consideration of the impact of netting the north-south and south-north Path 26 flows related to RA resources. The baseline amount is the higher of (1) the LSE’s load-ratio share of the load in the zone or (2) the sum of the LSE’s existing commitments, including Existing Transmission Contracts on Path 26 and “Grandfathered RA Commitments.” Grandfathered RA Commitments are those RA commercial arrangements, whether contracts or other ownership rights in supply in effect as of March 22, 2007. Scheduling Coordinators (SC) for LSEs must, therefore, submit information on Grandfathered RA Commitments. This may include: (1) imports into the ISO control area, (2) physical RA resources within the ISO control area, and (3) Firm LD contracts 1 with delivery within a specified zone. For existing import commitments that meet the definition of Grandfathered RA Commitments, SC for an LSE may limit its submission in this template to only those existing RA import commitments that were entered into between March 10, 2006 and March 22, 2007 that are deliverable in 2016. The ISO will capture any import Grandfathered RA Commitments existing prior to March 10, 2006 through the Pre-RA Import Commitment Data Templates sent to implement ISO Tariff section 40.4.6.2.1. Instructions: Please complete and submit the correct data based on one of the scenarios below: My load is completely within SP26 My load is completely within NP26, i.e. (NP15 & ZP26) My load is in both zones: NP26 & SP26 Complete templates 1 and 2 for existing RA commitments within NP26 only. Complete templates 1 and 2 for existing RA commitments within SP26 only. Complete templates 1 and 2 for existing RA commitments within both NP26 & SP26 Questions: 1. I don’t know in which zone my generator is located. Please use the “Path 26” column in the most current NQC list posted at: http://www.caiso.com/planning/Pages/ReliabilityRequirements/Default.aspx Attention: North = north of Path 26 and South = south of Path 26. 2. I can’t find my unit in the above-mentioned list (or the unit has no associated Zone). Please contact cmicsa@caiso.com or (916)-608-5704. 3. I don’t know in which zone my load is located. Please contact your ISO client representative. Information Format Requirements Scheduling Coordinators (SC) for LSEs are asked to submit the required information on the corresponding sample templates provided below. Some of the information requested is categorical, while some is numeric; however, several topics are descriptive in nature. A separate form will be needed for each contract. Templates 1 and 2 request general contract and/or resource information. 2 Contracts Covered By This Request For each and every firm contract that specifies a supply of energy or capacity that must be within the ISO control area boundary, Scheduling Coordinators (SC) for LSEs must provide the information described below and shown on the corresponding form below. Glossary: Supplier Name the contracted supplier/producer of energy and/or capacity according to the contract. This entity is sometimes called the counter party to the contract. Initial Date Contract was entered into State the date when this contract was originally signed. Initial Delivery Start Date State the initial delivery date of the product(s) being purchased. Contract type State the type of contract originally signed, like set term contract, evergreen, etc. Set term length contracts Provide the initial (as originally signed), as available on March 22, 2007 and current data regarding expiration term and expiration date. If this date is contingent upon future actions by parties to the contract, market conditions, this should be explained in notes appended to the form. Information regarding the ability of one party to unilaterally terminate the contract after its inception should be entered under Performance Requirements and Termination/Extension Clauses and Rights or in notes appended to the form. Evergreen contracts Provide the length of current contract term and its current expiration date. If the contract has renewed since March 22 of 2007 provide date it renewed and the renewal period. If this date is contingent upon future actions by parties to the contract, market conditions, this should be explained in notes appended to the form. Information regarding the ability of one party to unilaterally terminate the contract after its inception should be entered under Performance Requirements and Termination/Extension Clauses and Rights or in notes appended to the form. Other contract types Provide a copy of your contract. Qualifying Capacity (MW) List the Qualifying Capacity during summer annual super-peak load conditions, as defined by the relevant Local Regulatory Authority. 3 Generation Resource Name Please specify the actual generation resource name(s) and/or its market ID if known. Availability Please identify provisions of the contract that describe the use of the qualifying capacity during system peak conditions. Branch Group/Delivery Points Name the ISO Branch Group that the contract capacity or energy is most frequently scheduled across. Name the point(s) at which energy can be delivered (e.g., NP15, Malin, Lugo substation). If multiple points, indicate whether buyer or seller has option. 4 TEMPLATE 1 Resource Adequacy Transmission Capability Allocation for Path 26 Pre-RA Existing Firm Energy and Capacity Contract Information Filing LSE: Date: Contact: Contact Number: Supplier: Initial Date Contract was entered into: Initial Delivery Start Date: Contract type: ⃞Set term length ⃞Evergreen ⃞Other IF contract type is Set term length: 1. Initial expiration term: 2. Initial expiration date: 3. Contract expiration term as of March 22, 2007: 4. Contract expiration date as of March 22, 2007: 5. Current expiration term: 6. Current expiration date: IF contract type is Evergreen: 1. Has the contract renewed since March ⃞Yes ⃞No 22, 2007? 2. If yes (to 1 above) date it renewed: 3. If yes (to 1 above) renewal period: 4. Length of current contract term: 5. Expiration date of current contract term: IF contract type is Other: 1. Attach a copy of your contract: ⃞ Copy Attached Qualifying Capacity (MW): Generating Resource Name: Availability: Branch Group/Delivery Points: 5 TEMPLATE 2 Resource Adequacy Transmission Capability Allocation for Path 26 Existing Pre-RA Utility Owned Generation Resources Filing LSE: Date: Contact Name: Contact Number: Initial Date Contract was entered into: Initial Ownership Expiration Date (if any): Ownership Expiration Date as of March 22, 2007 (if any): Current Ownership Expiration Date (if any): Qualified Capacity Generating Resource Name 6 Branch Group (if necessary)