REPORT OF THE INDEPENDENT REVIEW OF THE COMPULSORY ACQUISITION OF LAND AT CHARLESLAND, COUNTY WICKLOW, BY WICKLOW COUNTY COUNCIL SEAMUS WOULFE S.C. 8th February 2013. 2 Chapter 1 1.01 Introduction and Background On or about the 20th June 2012 the Minister for the Environment, Community and Local Government, Mr. Phil Hogan T.D., appointed me to carry out an independent review into the compulsory acquisition of land at Charlesland, County Wicklow, by Wicklow County Council (“the Council”) and to report thereon to him. This independent review follows on from my earlier review of the management by the Department of the Environment, Community and Local Government (“the Department”) of an application by the Council for loan approval in respect of the said compulsory purchase, and I refer to my report of that review dated the 12th March 2012 (“my first report”). Before setting out the Terms of Reference for this second independent review it might be helpful to set out the general background to this matter. Some of the general background was already set out in Chapter 1 of my first report, but it is proposed to repeat same hereunder, with appropriate modifications, for ease of reference. 1.02 The provision of social and, more recently, affordable housing has long been a feature of housing policy at central government level, although it is a matter for individual local authorities to develop housing strategies for their own areas. While decisions on housing strategy are matters for local government, local authorities would have been influenced over the past decade by the general concern to ensure that there was sufficient land in public ownership to underpin the social and affordable investment housing programmes. This general concern is well captured in a report on housing issued by the National Economic and Social Council in 2004 (“Housing in Ireland: Performance and Policy”, Report No. 112, December 2004). At page 171 of that report it is stated as follows: “In framing their local action plans for the provision of social and affordable housing, individual local authorities are required to indicate if there is sufficient supply of land in their ownership for future house building requirements. Where land availability arises as a particular 3 constraint to the supply of social and affordable housing, it is recommended that local authorities, in conjunction with central government, should take a more proactive role in setting targets for the acquisition and/or development of land for social and affordable housing including the development of adequate land banks for future supply (including the possibility of rezoning where appropriate). Where significant shortfalls in supply are projected or arise due to scarcity of land, the use of measures such as compulsory acquisition should be considered …”. 1.03 As regards the funding mechanism used to purchase land, in recent years the most common way for local authorities to fund the creation of land banks for social and affordable housing purposes was to obtain loan finance from the Housing Finance Agency. Loans obtained in this way could be redeemed, including the rolled up interest for a period of up to seven years, when the land was later used for a social housing project for which 100% Exchequer funding was normally provided under the Social Housing Investment Programme (“SHIP”). This capital funding was subject to the Department being satisfied with the project brief and having regard to the availability of funding under that programme. 1.04 In or about 2004 the Council decided to acquire certain land in Greystones for the purpose of accommodating social and affordable housing. The detailed history of this acquisition process will be set out in Chapter 3 below, but for the purposes of this introduction the history of same may be summarised as follows. On the 6th December 2004 the Council served a Compulsory Purchase Order (“CPO”) on the owner and on the occupier of this land, being 1.4022 hectares of land at Three Trouts, Charlesland, Greystones. This CPO was confirmed, without modification, by An Bord Pleanála on the 25th April 2006. A Notice to Treat was served on the 12th July 2006 on the above parties. The occupier of the land delivered a Notice of Claim on or about the 16th August 2006 giving details of the compensation claimed, and the owner delivered a Notice of Claim on or about the 17th August 2006. Under the relevant legislative provisions, once six weeks had expired from the date of the delivery of a Notice of Claim the local authority was not legally entitled to withdraw the Notice to Treat. 4 Therefore, in the present case, by around the end of September 2006 the Council were legally committed to proceed with the purchase of this land, and had no legal entitlement to withdraw from the compulsory acquisition process, irrespective of any future change in circumstances, including any change in the value of the land. As regards value, in assessing compensation for the acquisition of this land by this CPO, the date of service of the Notice to Treat was the relevant date by reference to which the market value of the property to be acquired had to be assessed. 1.05 After September 2006 the compulsory purchase process took its course, with efforts by valuers for both sides to negotiate an agreed amount of compensation. After a lot of discussions between all parties over the years the matter was ultimately referred to the Property Arbitrator, and a hearing was listed for the 1st November 2010 but was adjourned ultimately to the 24th March 2011, and on that date a settlement was reached whereby the Council agreed to pay compensation of €3m together with costs. 1.06 In the meantime, after September 2006 the Council began to engage with the Department regarding the land which it was now legally committed to purchase, and this engagement arose by way of the Council seeking two separate approvals pursuant to two distinct processes of approval. Firstly, the Council sought approval for capital funding under SHIP for a proposed housing project on the land being acquired, and the first communication from the Council to the Department was dated the 6th December 2006. This approval process took its course until around the middle of 2008, when it was effectively put on hold because of the lack of any further Exchequer funding for new housing schemes. Secondly, on or about the 19th August 2008 the Council sought the Department’s approval to raise a loan totalling €26m for land purchase and other purposes, on foot of a resolution by the Members of the Council dated the 18th August 2008. This application for sanction to borrow was made pursuant to Section 106 of the Local Government Act, 2001 (“the 2001 Act”) and the total figure of €26m included a slice of €5m in respect of the CPO land at Charlesland. 1.07 The application for sanction was under consideration by the Department after receipt of the letter dated the 19th August 2008, but was effectively put on hold in late 2008 5 while the amount of compensation under the CPO process had not yet been agreed. In 2009 the application for sanction was revived and ultimately the Council was granted approval to borrow €5m for the land at Charlesland by letter dated the 29th July 2009. However, the Council did not draw down any such loan from the Housing Finance Agency by the end of 2009 as the CPO compensation amount was still not agreed, and the sanction lapsed at the end of 2009. No fresh application was made for sanction in 2010, but by letter dated the 20th July 2011 the Council made a fresh application to the Department to sanction the borrowing of the sum of €3m for the acquisition of the land at Charlesland, on foot of a resolution of the Members dated the 18th July 2011. In advance of passing that resolution a number of Council Members expressed certain reservations about the compulsory purchase process, and the amount of compensation payable by the Council to complete the purchase. 1.08 Shortly after receipt of the application for sanction to borrow, the Department became aware of these reservations, after it received correspondence in relation to the matter from the Committee of Public Accounts by letter dated the 22nd July 2011. This application for sanction to borrow was then effectively put on hold, pending the receipt of legal advice from the Attorney General’s Office. This legal advice was received by the Department in the middle of October 2011, and it confirmed, inter alia, that under the CPO legislation one had to assess compensation by reference to the value of the land at the date the Notice to Treat was served, i.e. July 2006, and not by reference to any later date, even if the value of land had fallen sharply since the date of the Notice to Treat. In late October 2011 the Department was considering whether to grant Wicklow County Council the sanction to borrow as sought back in July, but before a decision was made the matter was the subject of representations by three Wicklow public representatives (Councillor James O’Shaughnessy, Councillor Thomas Cullen and Councillor Barry Nevin) to the former Minister for Housing and Planning, Mr. Willie Penrose T.D. The Minister’s Special Adviser met with these public representatives at the request of the Minister on the 3rd November 2011, and he was at that meeting given a document dated the 3 rd November 2011, which document set out a list of allegations or issues of public concern regarding the manner in which this land acquisition was dealt with by the Council, and also regarding the Department’s management of the loan applications by the Council to fund the 6 acquisition. He was subsequently sent a further document dated the 7th November 2011 regarding the CPO and valuation of the land. The two documents from the three Councillors are annexed to the Terms of Reference which are attached at Appendix 1 hereto. 1.09 Following receipt of these documents by the Department the Secretary General wrote to the Office of the Attorney General by letter dated the 16th November 2011 and stated that, in light of the serious issues raised in the documents submitted to Minister Penrose, the Department would not be further processing the application for loan sanction pending an examination of the validity, or otherwise, of the claims made in respect of the actions of the Department and the Council. She stated that independent review of the actions of the Department since the making of the original loan application by the Council was now necessary before final consideration would be given to the current loan application, and such a review should also be enabled to pursue any associated inquiry which might be necessary in respect of the manner in which the Council has itself dealt with this land acquisition. She commented that, in undertaking this review, it would be necessary to address the specific concerns of the public representatives and to consider whether the Department was fully compliant with relevant statutory and public policy obligations. A copy of this letter is attached at Appendix 2 hereto. 1.10 After this letter consideration was given to the nature and scope of the proposed independent review, and it was decided to proceed in the first instance with a review of the actions of the Department and to postpone further consideration of any associated review that might be necessary in respect of the manner in which the Council dealt with the land acquisition. I was subsequently appointed to carry out the first independent review by letter dated the 31st January 2012 and this led to my first report dated the 12th March 2012. 1.11 As stated at paragraph 1.01 above, I was appointed to carry out this second independent review by letter dated the 20th June 2012. It should be noted that as on the first occasion my appointment was to carry out this independent review on a parttime basis, and I began work on the review in early July 2012 when I had a 7 preliminary meeting with the Council on the 3rd July 2012. I also carried out a preliminary site visit to the subject site on that date. In order to ensure that the review was conducted by reference to all relevant materials, copies of all of the relevant files were obtained from the Council during July 2012. During September and October 2012 I reviewed the voluminous documentation, and after that I consulted with and met with both the Council officials and the public representatives to clarify the history of this matter, the specific concerns of the public representatives regarding the role of the Council and the response of the Council. Subsequent correspondence with both continued up until the middle of December 2012. 1.12 In conducting this review I did not have the benefit of any statutory powers, whether to compel the production of documents or otherwise. However, it is appropriate to record that I obtained the full cooperation of the Council and the public representatives and of the Department, and I am grateful for the prompt and detailed assistance which was given to me. It is important also to note that I have no statutory power to make any binding determinations of facts and that my review was essentially a documents review, albeit supplemented by detailed oral and written consultation with the Council and with the public representatives and any findings or conclusions made by me should be viewed in that context. 1.13 During the course of my oral and written consultation with the public representative a number of new issues were raised by the Councillors, such as an issue as to the potential overlooking of the proposed houses on the CPO site from the Charlesland estate. In my opinion these new issues went beyond the specific concerns of the public representatives in the documents annexed to my Terms of Reference, and were therefore outside my Terms of Reference. For this reason I have not dealt with these new issues in this report. 1.14 On a similar note I was also furnished with information regarding flooding incidents in recent years in the Greystones area, including details of a flooding incident on the 24th January 2013 at the Burnaby Lawns estate, which estate is on the other side of the Three Trout Stream from the CPO lands. It seems to me that the assessment of the 8 role of the Council must relate primarily to the information available to the Council officials and their state of mind at the time of the oral hearing conducted by An Bord Pleanála in March 2005 and March 2006. While any information regarding recent flooding could possibly cast some retrospective light on those matters, any such information would have to relate to the CPO site itself or else to other lands which have identical characteristics to the CPO lands. In my opinion, the recent information did not satisfy this test and therefore I have not dealt with same in this report. 9 Chapter 2 2.01 The Relevant Legal Requirements and Administrative Requirements or Practices regarding Compulsory Acquisition of Land by Local Authorities The vehicle generally used by local authorities when carrying out compulsory acquisitions of land is Part V of the Housing Act, 1966 (“the 1966 Act”) and the Third Schedule to that Act. In McDermott and Woulfe “Compulsory Purchase and Compensation: Law and Practice in Ireland” the authors set out in helpful tabular form the 18 steps which they suggest are required for a valid compulsory acquisition under the 1966 Act as follows (at p.56): “Steps in Acquisition under Housing Act 1966: 1. Identification of empowering statute after establishing the objects for which the lands are required. 2. Making of CPO by Local Authority after careful identification, description, categorisation and mapping of the lands, identification and accurate listing of various owners, lessees and occupiers. 3. Service of Notices by Local Authority on owners and lessees; publication in press. 4. Lodgement of objections (if any). 5. Local inquiry (if objections made). 6. Minister’s decision - confirmation with or without alteration. 7. Possible challenge in High Court. 8. CPO becomes operative. 9. Decision to serve and service of Notice to Treat. 10. Notice of entry – entry. 11. Preparation and lodgement of claim. 12. Agreement on claim. 13. In event of disagreement on claim, steps to appoint property arbitrator at instance of the : a. Claimant; b. Local authority. 10 14. Service of Notice etc. by Local Authority in accordance with Article 6, Second Schedule Housing of the Working Classes Act 1890. 15. Arbitration hearing. 16. Arbitration award. 17. Adducing and taking of title by 18. 2.02 a. Conveyance or transfer. b. Vesting order. c. Deed Poll. Payment of award, costs (and interest)”. Some further comments might be made in relation to the 18 steps set out above. As regards step 1, it is important for a local authority to establish the objects or purposes for which the lands are required, and then to identify the statutory provision which empowers it to acquire the lands compulsorily for those objects or purposes. A local authority is by definition an artificial legal person, and in general can only do that which is permitted by a statute. As regards step 2, the first paragraph of the Third Schedule to the 1966 Act requires that a CPO shall in the prescribed form, and the prescribed forms are to be found under the Housing Act, 1966 (Acquisition of Land) Regulations 2000. As regards step 3, Article 4 of the Third Schedule specifies the notice procedure and the purpose of same is to enable the person affected to consider whether or not to make an objection to what the Supreme Court has described as an invasion of his constitutionally protected property rights. 2.03 As regards steps 4 and 5, the legislation provides for the making of an objection by any notified party after a CPO has been submitted to the confirming authority for confirmation. The confirmation function conferred on the Minister for the Environment under the 1966 Act was transferred to An Bord Pleanála (“the Board”) by Section 214 of the Planning and Development Act 2000 (“the 2000 Act”). If an objection is made to the CPO the Board must hold an oral hearing in relation to the matter, and since the 2000 Act this has replaced the previous requirement for the Minister to call for a public local inquiry to be held, as referred to in step 5 of McDermott and Woulfe’s table above. As regards step 6, the Board now has the power to confirm a CPO or any part thereof with or without conditions or 11 modifications, or to annul a CPO or any part thereof. As regards the exercise of that power, Simons, “Planning and Development Law” (2nd Edition, 2007) states as follows (at paragraph 8 - 419): “One of the greatest mysteries of compulsory purchase law is as to what precisely it is that An Bord Pleanála must be satisfied of before it confirms a compulsory purchase order. In particular, there is little guidance as to the nature and extent of the considerations which An Bord Pleanála is to take into account in reaching its decision.” 2.04 As regards step 7, Section 78 of the 1966 Act permitted any person aggrieved by a CPO which had been confirmed to challenge the validity of the CPO in the High Court, and this is now governed by Section 50 of the 2000 Act. Any challenge must be mounted by way of an application for judicial review under Order 84 of the Rules of the Superior Courts and a strict time limit of eight weeks applies, with limited scope for extension of that period in exceptional circumstances. As regards step 8, a CPO becomes operative three weeks from the date on which notice of the Board’s decision is first published, in the absence of any High Court challenge, in accordance with Section 217(7)(a) of the 2000 Act. 2.05 As regards step 9, once the CPO has been confirmed and has become operative, the acquiring authority is then at liberty to embark on the next step of the acquisition procedure, i.e. to serve a Notice to Treat pursuant to Section 79 of the 1966 Act. As stated at page 80 of McDermott and Woulfe, the expression “Notice to Treat” has an antique ring to it. It is a notice asking the party notified, usually the owner, to negotiate terms with the acquiring authority. A Notice to Treat is a formal commitment by the acquiring authority to proceed with the acquisition, which it is not obliged to do until the Notice to Treat is served. The date of service of the Notice to Treat is an extremely significant event in the entire CPO process, as Section 84 of 1966 Act provides that the value of the land acquired shall be set by reference to the date of service of the Notice to Treat. This provision is obviously of crucial significance in times of a falling market and in circumstances where there may be a 12 significant delay between service of the Notice to Treat and the date that compensation is assessed. 2.06 As regards step 10, under Section 80 of the 1966 Act the acquiring authority can serve a Notice of Entry on any owner and others at any time after serving a Notice to Treat, and, after 14 days can take possession of the land even though no compensation has yet been paid or even agreed. The drawback is that when compensation is ultimately agreed or determined by the Property Arbitrator, the acquiring authority must then pay interest on the compensation from the date of actual entry to the date of payment. For this reason, exercise of the power of entry is likely to be unattractive in most cases. 2.07 As regards steps 11 to 13, these steps deal with claiming for compensation and the method of resolving same. Under Section 79 of the 1966 Act the Notice to Treat requires each owner and occupier to state within a specified period the exact nature of the interest in the land in respect of which compensation is claimed by him, and details of the compensation claimed. This is generally referred to as a Notice of Claim. After delivery of the Notice of Claim the parties can seek to agree the amount of compensation payable, and in default of agreement either side can take steps to have an arbitrator appointed to assess the claim, in accordance with the provisions of the Acquisition of Land (Assessment of Compensation) Act, 1919 (“the 1919 Act”). 2.08 As regards step 14, there is a provision in old legislation known as the Housing of the Working Classes Act, 1890 requiring the publication of certain notices where an application for the nomination of a Property Arbitrator is made by a local authority, but these requirements do not apply where the Arbitrator has been nominated on the application of the claimant. As regards step 15, the procedure about these type of arbitrations is governed mainly by the 1919 Act and Rules made under that Act, known as the Acquisition of Land (Assessment of Compensation) Rules 1920. Article 5(3) of the 1920 Rules provides that the proceedings before the Arbitrator shall be such as the Arbitrator may in his discretion see fit, subject to the provisions of the 1919 Act and the said Rules. Section 3(5) of the 1919 Act provides that hearings before the Property Arbitrator shall be in public. In fact hearings before the Property 13 Arbitrator tend to be quite formal arbitrations and tend to follow the formal procedure of a hearing of a civil action in Court. The parties will generally be legally represented, often by Counsel, and witnesses will be examined under oath. The Arbitrator will normally inspect the subject property and will tend to pay particular attention to evidence relating to the valuations of comparable property put on the market in the previous few years. As regards step 16, at the end of the hearing the Arbitrator will generally reserve his decision and in due course will issue an award. Section 6 of the 1919 Act provides that the decision of the Property Arbitrator upon any question of fact is final and binding on the party. 2.09 As regards step 17, McDermott and Woulfe are referring here to different methods of the acquiring authority getting in title. The most simplest method appears to be by way of a conveyance or transfer, and in such cases there can be a formal contemporaneous closing whereby payment of the award or agreed compensation takes place at the same time. As regards step 18, in some cases payment of interest may also arise at the same time. Payment of costs will generally happen at a later stage, often following a separate taxation of costs process. 14 Chapter 3 3.01 The Process followed by the Council in regard to the Compulsory Acquisition of the Land including its consistency with the Relevant Legal Requirements and Administrative Requirements or Practices In my Terms of Reference I have been requested to establish the process followed by the Council in regard to the compulsory acquisition of the land including its consistency with the relevant legal requirements and administrative requirements or practices, and also to identify any deviation from such requirements and practices. The relevant legal requirements and administrative requirements or practices have been set out in Chapter 2. It is now necessary to set out the process followed by the Council in regard to this compulsory acquisition, and it is convenient to examine the constituent parts of this process in the context of the 18 required steps set out in Chapter 2 above. Before commencing that examination however it is important to consider the preliminary issue of site selection. Site Selection: 3.02 It appears that the subject lands were first identified on behalf of the Council by Mr. Tony O’Neill, Economic Development Executive on or about the 18th November 2003. The Council files contain a note of Mr. O’Neill dated the 18th November 2003 wherein he states that he met with Mr. William Irwin, Mr. John Nolan, and a third party, and that Mr. Irwin owned 4½ acres south of the Three Trout Stream, on which Mr. Nolan keeps horses, and that Mr. Irwin has had many offers but won’t sell. It appears that Mr. O’Neill had the task of trying to source suitable lands in Greystones for the Council in order to meet the Council’s statutory obligation of providing social and affordable housing. It appears that at the meeting on the 18th November 2003 there was also some reference to a second property owned by Mr. Irwin, a derelict large house on over 1 acre known as Killincarrig Lodge. The files record that Mr. O’Neill then discussed both of the sites with Mr. Des O’Brien, Director of Services, Housing and Corporate Estate on the 21st November 2003 and that his instructions were to “negotiation further and CPO if going nowhere”. On the 4th December 2003 Mr. O’Neill again asked Mr. Irwin to sell the Council the two sites previously identified. On the 18th December 2003 Mr. O’Neill told Mr. Nolan that Mr. Irwin was 15 worried about selling the subject lands to the Council because of Mr. Nolan’s horses on the lands, and he asked Mr. Nolan to encourage Mr. Irwin to sell either the subject lands or the other site. On the 14th January 2004 Mr. O’Neill visited Mr. Irwin and asked him again would he sell either site but he said no, that he was not interested. Mr. O’Neill told him that the Council was very anxious to buy and might consider a CPO and that the pressure was on Mr. O’Neill and the Council. Mr. O’Neill made a further unsuccessful attempt to visit Mr. Irwin on the 30th March 2004. By memorandum dated the 31st March 2004 to Mr. O’Brien, Mr. O’Neill described his efforts over recent months to progress the purchase of the two sites in the area owned by Mr. Irwin but stated that he felt he was getting nowhere in the negotiations. He recommended that the Council would establish, as best they could, title to the two sites and proceed to the compulsory purchase of either one or both of the sites. 3.03 The files suggest that on receipt of this memorandum Mr. O’Brien wrote a note to Ms. Lorraine Gallagher, Senior Executive Officer, Housing and Corporate Estate, dated the 6th April 2004 to “please progress to CPO”. It appears that Ms. Gallagher then discussed the matter with Mr. Eddie Murphy, Executive Technician on the 16th April 2004, and it was noted that Mr. Murphy would discuss with Mr. O’Neill with a view to preparing a map and verifying title. There is then a Memo from Mr. O’Neill to Ms. Gallagher dated the 5th May 2004 wherein Mr. Murphy states that the subject lands are registered to Mr. Irwin under Folio 2915, and he encloses a copy of the Folio and a map prepared by him showing the site and the area involved. The Council’s files suggest that there was then a gap of approximately three months until a report dated the 13th August 2004 from Mr. Michael Mangan, Senior Engineer, Housing and Corporate Estate. This report is significant as it comprised the principal element of any site selection procedure carried out by the Council at the time, given that Mr. O’Neill had simply identified the site as a potential site for purchase in the most general way. In his report Mr. Mangan stated that it was proposed to acquire these lands for residential development of social housing units, along with the provision of a section of a proposed linear park. He referred to the relevant provisions of the Greystones-Delgany Development Plan 1999 (“the 1999 Local Area Plan”) and stated that the need for social housing in the north-east of Wicklow and in the Greystones area in particular had been identified in the Social and Affordable Housing Plan 200416 2008 of May 2004. The number of units that could be provided on the site depended upon detailed design of the units and the layout of the site. However, for the purposes of assessing the servicing of the lands it was necessary to estimate the likely maximum level of development and he estimated that there were likely to be in the order of 30 units on this site. Vehicular access to the development would be via Burnaby Lawns and Mr. Mangan felt that the addition of 30 units would be well within the capacity of the main estate road. The proposed access would entail the construction of a bridge over Three Trout Stream and approximately 30 meters of new carriageway over the existing open space. Foul sewerage could be provided by the existing main sewer in Burnaby Lawns and Mr. Mangan felt there was more than sufficient capacity for 30 houses to be connected by crossing of the Three Trout Stream. Other services (water, gas, telephone) were available in the existing road, and Mr. Mangan’s opinion was that it would be possible for these to be extended over the proposed bridge and to serve the new development. It is noteworthy that Mr. Mangan does not appear to have considered that there was any issue of risk of flooding affecting these lands, as he makes no reference to same in his report. 3.04 Following this report the Council wrote to Mr. Irwin by letter dated the 19th August 2004 referring to his meetings with Mr. O’Neill regarding the possible purchase of his lands. The letter pointed out that the Council had an obligation to provide housing and that they considered Mr. Irwin’s land suitable for that purpose, and accordingly notified Mr. Irwin that the Council intended to proceed to compulsorily purchase these lands. There was then a further note from Mr. O’Brien dated the 6th September 2004 with a direction to “proceed to CPO”. The next substantive step in terms of any site selection procedure was a report from Mr. Paddy Hooper, Senior Planner, dated the 30th November 2004. In this report Mr. Hooper certified that the acquisition of the subject lands was in conformity with the Wicklow County Development Plan 2004 – 2010, the 1999 Local Area Plan and the proper planning and sustainable development of the area. The report is very bare in that there is a lack of any supporting detail. The above elements of a site selection procedure were cited in the Manager’s Order dated the 30th November 2004 as discussed below. 17 Compliance with the Relevant Legal Requirements and Administrative Requirements or Practices: 3.05 The process followed by the Council in carrying out the compulsory acquisition of this site can be described and analysed within the umbrella of the 18 required steps set out and discussed in Chapter 2 above. Step One – Identification of Statutory Powers: As regards Step 1, it is clear from the Council’s files that the Council felt these lands were required for social housing purposes and they identify the statutory power to do so derived from s. 10 of the Local Government (Ireland) Act, 1898 (as amended), the provisions of Part V of the Housing Act 1966 and Section 213 of the Planning and Development Act 2000. Step Two – Making of CPO: 3.06 As discussed above, it appears from the Council’s files that Mr. Tony O’Neill first identified the subject lands for potential purchase in or about November 2003, and he recommended that the Council proceed to compulsory purchase by memorandum dated the 31st March 2004. Over subsequent months the matter went through an internal procedure which included the more precise identification and mapping of the lands and the establishment of Mr. Irwin’s title to the lands under Folio 2915 County Wicklow. Along the way the Council officials sought advice from the Law Agent regarding the form of the draft Compulsory Purchase Order. As of September 2004, the Law Agent advised that Mr. John Nolan should be listed in the Schedule as an occupier of the lands, on the basis that he might have a compensatable interest in the lands. Ultimately the making of the CPO was approved by a Manager’s Order dated the 30th November 2004. The actual Compulsory Purchase Order was then made by the Council on the 6th December 2004 when the official seal of the local authority was affixed thereto, and was entitled the “Wicklow County Council Compulsory Purchase (Lands at Charlesland, Greystones) Number 6 Order 2004”. A copy of the said Order is attached at Appendix 3 hereto. 18 Step Three – Service of Notices: 3.07 The Council complied with the requirements for service of notices and press publication as follows. They served notice on Mr. William Irwin, as registered owner of the lands, by letter dated the 8th December 2004. A similar notice was served on Mr. John Nolan, as occupier of the lands, by letter bearing the same date. As regards press publication, the Council published notice in the prescribed form of the making of the CPO in the Wicklow People on Thursday the 9th December 2004. Steps Four and Five – Lodgement of Objection and Oral Hearing: 3.08 The CPO was submitted by the Council to An Bord Pleanála for confirmation by letter dated the 9th December 2004. A written objection to the CPO was made by Mr. John Nolan dated the 10th January 2005. In this objection Mr. Nolan queried the suitability of the site for housing and stated that the entire river valley in which this field is situated had flooded as recently as November 2002. He referred to his use of the field for keeping horses, the long term history of use of the field by his family, and he claimed that Mr. Irwin had told him in 1980 that he had paid enough rent and that he could have the field. By letter dated the 9th February 2005 the Council responded as follows in relation to site suitability: “The lands in question are zoned within the 1999 Greystones/Delgany Development Plan Area Z1- “Provide for a comprehensive phased residential and public open space development on 53 Hectares at a gross density of 15.7 dwellings per hectare to accord with Action Area Plan Z1” (Shown on Map No. 2, Page 40). It is the Council’s intention to use these lands for housing along with public open space adjacent to the Three Trout Stream incorporating cycle and pedestrian ways. With regards to the issue of flooding of the adjacent Three Trout Stream, this has been investigated by J. B. Barry & Partners. Their report “Storm Water Review – Three Trout Stream” dated May 1996 (revised 19 February 1997) addressed the issue of capacity of this stream. Its recommendations are that the stream channel be upgraded to cater for a storm with 30 year return period (preferred method open channel – earth lined trapezoidal channel). In addition, floor levels shall be a minimum 1.0 m above the design top water level. Both of these recommendations can be complied with in the development of this site.” 3.09 The Board was required under Section 218 of the 2000 Act to hold an oral hearing into the objection made by Mr. Nolan and the Board arranged for Ms. Oznur Yucel – Finn, a Senior Inspector with the Board, to conduct an oral hearing on the 15th March 2005. The Council obtained copies of the transcripts of the oral hearing from An Bord Pleanála and made same available to me. The following is a summary of some of the salient evidence given at the oral hearing. 3.10 Mr. Michael Mangan, Senior Engineer in the Housing and Corporate Estate Department of the Council, was the first witness to give evidence. As regards the nature and extent of the site, he explained this site was located on the south side of the Three Trout Stream, south of the existing Council housing development at Burnaby Lawns which is on the north side of the stream. It was proposed that road access would be via Burnaby Lawns, and the proposed development on the subject site would entail the construction of a bridge over the Three Trout Stream. He explained how various services could be extended to provide services to the proposed new development. As regards the number of units that could be provided on the site, this would depend upon the detailed design of the units and the layout of the site. However, based upon standard figures it was likely that 34 units could be provided on the site. He noted how the site sloped slightly upwards in a southerly direction from the Three Trout Stream. 3.11 The next witness on behalf of the Council was Ms. Lorraine Gallagher, Senior Executive Officer in Housing and Corporate Estate. The functions of her department included the maintenance of the Council’s housing lists and assessing the housing needs of housing applicants in various areas of the County on an on-going basis. She explained how the Council historically has had approximately 1,800 people on its 20 housing list, and most recently 515 applicants had expressed a preference to live in Greystones and its environs. Of those 219 housing applicants who had expressed a first preference for Greystones, some 112 had expressed a first preference to live in the area of Greystones quite close to the subject site. Ms. Gallagher felt it was reasonably evident from these figures that there was a substantial housing need in Greystones and its immediate environs and if this CPO was confirmed it would enable the Council to construct 30 housing units to satisfy part of that need. 3.12 The last witness for the Council was Mr. Paddy Hooper, Senior Planner with the Council. He explained certain matters regarding the Greystones/Delgany development plan which was adopted by the Council in March 1999 and how the site is located to the north western corner of an area zoned Action Area Plan Z1, which was an action area plan adopted with the objective of providing phased residential and public open space development on approximately 53 hectares at a gross density of 15.7 dwellings per hectare. This would include up to 822 dwellings, and it was anticipated that a minimum of 14% of the total dwelling units would be social housing in accordance with the Council’s then housing strategy. It was further anticipated that there would be 12 hectares of public open space for active recreation, and cycling and pedestrian walkways were to be included particularly along the Three Trout Stream. While no detailed phasing or designs had been prepared for the Action Area Plan Z1, Mr. Hooper was of the view that the CPO would enable the Council to provide additional housing in accordance with the proper planning and sustainable development of the area generally, and would enable the Council to secure a reasonable level of social housing for the area in accordance with its housing strategy and the need to provide housing in the area. 3.13 The next witness was Mr. Alan Nolan, a nephew of Mr. John Nolan, and he read a written submission which had been sent into the Board by Mr. John Nolan. This submission was very similar to the written objection made by Mr. Nolan in his letter dated the 10th January 2005, as summarised at paragraph 3.08 above. As regards suitability and risk of flooding, he now added that during the 1930s the field had contained a lake which was reputed to be 30 foot deep and that this had been filled in for safety reasons after a pony, three calves and a cow were drowned there in 1934. 21 He mentioned that the Council had built houses in the adjoining field approximately ten years ago and that these had been flooded. 3.14 Mr. Mangan later responded on behalf of the Council in relation to the issues of suitability of the lands for housing and in particular risk of flooding. He stated that he carried out a visual inspection of the field as part of the CPO process. The lands as purchased were proposed for both residential development along with the provision of a linear park adjacent to the Three Trout Stream as required in the Action Area Plan or the zoning in the Development Plan. In this regard any proposed development would take place on the higher southern side of the field away from the stream, allowing the linear park to run along as required within the area adjacent to the stream. He acknowledged that there had been a history of flooding in the area and referred to a report carried out by J. B. Barry & Partners in 1996/1997 (“the Barry Report”) which made certain recommendations regarding works to the Three Trout Stream. In the area of the stream adjacent to the subject site the recommendations were that the channel should be excavated and widened forming an earth lined open channel. Mr. Mangan was informed that certain of those works were carried out at the time of construction of Burnaby Lawns when the channel was widened, and further works would be required downstream on adjoining landowners’ properties. The area that would be prone to flooding would be at the level of the housing on Burnaby Lawns, but the proposed housing development on the subject site would be accommodated in the higher part of the site adjacent to a development which was then taking place on adjoining property to the south, and away from the flood zone. 3.15 In response to the Inspector Mr. Mangan stated that there had been no further update to the Barry Report since 1997. The last flooding of which he was aware was 1997 he thought, and he wasn’t aware of flooding in 2002. He had checked with the Sanitary Services Section and the Local Area Engineer who would have been aware, and they had not informed him of anything. 3.16 At this point in the hearing Mr. Al Nolan intervened and stated that the whole area was definitely flooded in November 2000, which perhaps is an error in the transcript and should have been a reference to November 2002 as per the written submission 22 made by Mr. John Nolan. He referred again to the fact that the housing in Burnaby Lawns had been flooded, and Mr. Mangan confirmed that there had been an incident of those houses flooding soon after construction in 1997, and that works were carried out to the stream subsequent to that. Mr. Nolan maintained that the stream flooded since those works and that there were more works carried out after the 2002 flooding. The inspector suggested to Mr. Nolan that the subject site was at a higher level than the Burnaby Lawns development, and that the Council intended to put the proposed housing development on the higher section of the site because the site slopes down. Mr. John Nolan in response referred to a general problem regarding flooding in the area. In response to a question from the Inspector as to whether the flooding was more on the Burnaby Lawns side rather than the field, Mr. John Nolan responded that it was all down along his field, that it came in there as well down at the bottom of his field. 3.17 The hearing then moved on to deal with certain other issues. The Inspector raised the question as to what other sites the planning authority was acquiring in the Greystones area. In response Ms. Gallagher referred to the Social Housing Action Plan 20042008, which outlined the amount of land needed over the next four years in the Greystones area to be 7 hectares to deal with the first preferences for that area. She stated that the Council found it extremely difficult to acquire land in the north east of the County, both in terms of the availability and the cost of such land. She confirmed that there were no other sites being acquired by CPO in Greystones at that time. In addition the Council was not acquiring any land in the Greystones area by way of negotiations. 3.18 Mr. Mangan then gave evidence of having done a study of lands in the Greystones area which were in the ownership of the Council and which were zoned for housing in the current development plan. There was one site immediately to the north of the subject site which was zoned for a school within Burnaby Lawns. There was approximately 25 acres (approximately 10 hectares) to the east of the site which now had the dual carriageway servicing this area coming through. There was approximately 7 acres (it may be this is again a transcript error and should read 7 hectares) left there in the ownership of the Council which could accommodate around 23 160 units but that it was not the Council policy to provide 160 units in one block for social housing, but rather to integrate social and private housing together, so the maximum potential number of houses there would be in the order of 100 social houses. During further discussion with the Inspector Mr. Mangan stated that parts of the site to the east of the new dual carriageway were indicated as being suitable for a proposed hotel, and therefore the whole of the 10 hectares would not be available for residential development, but rather it would be approximately 100 housing units that could be provided there. While the transcript records Mr. Mangan as stating that this would represent probably less than “15%” of the needs of the area, it may be again that this is a transcript error and that he actually said that it would represent probably less than 50%, given that the total expressions of first preference to live in Greystones was a figure of 219. 3.19 The next section of the oral hearing dealt with the position of Mr. William Irwin, the registered owner of the land. The inspector had received a fax from Felton McKnight & Co., Solicitors stating that they were in the process of initiating Wardship proceedings relevant to Mr. Irwin, who was suffering from dementia. Once the Wardship application had been processed and an order made taking Mr. Irwin into Wardship, his Committee would then be able to deal with his affairs on behalf. In the meantime, they requested that no further steps be taken to process the CPO. They warned that otherwise they would have no option but to issue proceedings to have any CPO set aside until their client could be represented. The Inspector asked the Council for their position on the matter, and the Law Agent suggested that in the interests of fair procedures the Inspector might adjourn the hearing rather than conclude it. The Inspector decided to follow that course of action, and he adjourned the hearing for ten weeks to allow the Wardship application take place. 3.20 Ultimately the Wardship process took much longer than anticipated and as a result the second session of the oral hearing did not take place until the 21st March 2006, over a year since the first session. In the intervening period Mr. Irwin had been made a Ward of Court and his Committee in Wardship was now represented by Mr. Mark Felton of Felton McKnight Solicitors, and also by Mr. Gordon Lennox of Lennox 24 Estates, Auctioneers and Valuers. A copy of the transcript of the first session had been forwarded to representatives of Mr. Irwin in advance of the second session. 3.21 At the resumed hearing the Council’s representatives confirmed that there had been no changes in development plan policies or in housing policies since the first session. The Inspector queried whether the Council had purchased any lands since March 2005 for housing purposes, and Mr. Des O’Brien, Director of Services responded that the Council had purchased just under two acres of land at the edge of Greystones by agreement. The Inspector referred to some discrepancies in the previous evidence as to whether the last flooding had taken place in 2002 or 2000 or 1997, and Mr. Mangan stated that he had no further information on the issue. 3.22 Mr. Alan Nolan then made a small additional presentation on behalf of the Nolan family. He stated that the land beside John Nolan’s field, a little over three acres, had recently been bought by one of the developers involved in the nearby Zapi development. He referred to access issues and stated that this land appeared to be more suited to the Council’s needs than the developer’s needs. He queried whether the Council had considered purchasing this land or whether there was a possibility that the Council were planning to do a land swap with the developer and give them the CPO land in return for the field which the developer had bought. He asked why other lands owned by the Council which was closer to Greystones could not be used for housing. He suggested that the proposed housing on the subject site would not be in Greystones, but would be almost two miles from the town. He suggested that there had been evidence at the previous hearing of a huge land bank between Charlesland and Greystones owned by the Council which was being retailed for a hotel, and he asked was that more important than housing. In conclusion he stated that there was more than adequate land in Greystones which could be used to satisfy the Council’s housing requirements, without spending a fortune developing this unsuitable site. 3.23 In response on behalf of the Council Mr. Sweetman, the Law Agent, said it was the Council’s view that this land was reasonably suitable for housing, and reasonably conveniently adjacent to the Burnaby Lawns development. The other field which Mr. Nolan mentioned was less suitable because it had access problems via a church 25 property. In any event what the Council had decided was that the site in question was reasonably suitable for housing, and they had shown on the last occasion that there was a demand and a reasonable public need for housing in and around Greystones. 3.24 The next witness was Mr. Felton, who confirmed that he appeared on behalf of Mr. Irwin’s Committee in Wardship. He explained that the reason why they had objected to the CPO in the first instance was that at that time Mr. Irwin was not mentally capable of being in a position to deal with it himself, and the objection was made in order to facilitate the proper procedures being put in place culminating with the recent High Court Order. There was no longer any reason for the family to object to the CPO and the objection as originally lodged was now being withdrawn. The oral hearing then concluded. 3.25 Following the oral hearing the Inspector then submitted a detailed Report to the Board which appears undated. In Section 6 of the Report she dealt with her assessment of the issues arising. As regards the issue of need, the Inspector was satisfied that there was indeed a public need for provision of housing within the County and in the Greystones area, based on the figures provided by the Council. She referred to the objector’s question as to why such housing was not being provided in other lands owned by the Council and the Council’s evidence regarding their lands of ten hectares (25 acres) to the north of the Three Trout Stream, and how some of these lands would be severed by the construction of the new road and being located next to business uses would be more suitable for a hotel. While the remaining seven hectares could accommodate 160 units, it was not the Council policy to accommodate such an amount in one block for social housing, and so the maximum number of houses that could be provided there would be 100. There was no provision for social and affordable housing in the nearby Zapi development at Charlesland, and as a result the Council were actively looking for additional land. It would not have been possible for the Council to acquire other nearby lands which the objector had suggested, because of problems of access via church property. The Council had managed to acquire approximately two acres at the southern end of Greystones during the intervening year between the two sessions of the oral hearing. The Inspector then concluded on this issue as follows: 26 “Based on the above, and on the information provided during the hearing, while I do consider the argument put forward by the objector in relation to possible provision of social housing on other lands in the immediate vicinity of the subject site to be plausible, I am also satisfied that any need arising is in excess of the lands in the ownership of the Local Authority and social housing that would be provided through Part V requirement of development permitted in the immediate area, and the housing that can be provided in the recently purchased land at the southern end (Prettybush). Therefore, I am satisfied that there is a need for the Local Authority to acquire additional lands to meet the public need for housing through purchase of additional lands, whether by way of agreement or by way of CPO.” 3.26 The Inspector then dealt with the issue of the suitability of the site for provision of housing. She referred to the objector’s argument that the field is prone to flooding and was not suitable for housing, and to the evidence of the Council which acknowledged that the Three Trout Stream had indeed flooded soon after construction of the houses in 1997 but remedial action was then carried out on the basis of recommendations of a consultant’s report. She noted that in the vicinity of the Three Trout Bridge the stream goes through a rather narrow channel and in this section while some of the land remains at levels close to the stream the lands to the South of the stream rise quite steeply after a while. There was a wider area to the north that remained at lower levels. While she noted the channel was widened as one moved in the easterly direction, as recommended in the consultant’s report, she was satisfied that flooding could indeed incur in the lower levels which were immediately adjacent to the river. She referred to the evidence of the Council that the houses would be located on the higher ground near the houses in the Charlesland development, and a riverside walkway would be provided in the lower section of the site, and the Inspector was satisfied that this would indeed be possible based on her observation during her inspection. She drew the Board’s attention to a drawing presented at the oral hearing showing the Charlesland housing development and in particular the parkland at the northern end of that development along the Three Trout Stream. 27 Provision of a linear park and walkway in the northern section of the subject site would continue this in the westerly direction and would be in accordance with the objective indicated in the Action Plan and with the proper planning and sustainable development of the area. The Inspector was satisfied that detailed flood prevention measures could be introduced at the design stage by the Council to safe guard the public walkway. It seemed quite plausible to her that a road and services located at levels close to the river might be flooded. She was, however, satisfied that the Council in their detailed plans, would include necessary measures to counteract such a possibility. 3.27 At Section 7 of her report the Inspector recommended to the Board that the CPO be confirmed as proposed by the Council. Having regard to the submissions made by the Council and the objection to the CPO both prior to and at the oral hearing, and to the report of the person who conducted the oral hearing into the objections and to the purpose of the acquisition as set out in the CPO, it was considered that the acquisition by the Council of the lands referred to in the CPO was necessary for the purposes stated and the objections could not be sustained having regard to that necessity. Step 6 – Decision of the Board: 3.28 The Board accepted the Inspector’s recommendation and decided to confirm the CPO without modification, by Order dated the 25th April 2006. The Order stated that the Board’s decision to confirm was based on the reasons and considerations set out as follows: “Having considered the objections made to the Compulsory Purchase Order and the report of the person who conducted the oral hearing into the objections and having regard to the purposes of the compulsory acquisition as set out in the Compulsory Purchase Order, it is considered that the acquisition by the local authority of the lands in question is necessary for the purpose stated in the Order and the objections cannot be sustained having regard to the said necessity.” 28 Steps 7 and 8 – Possible Challenge / CPO Operative: 3.29 The Council notified Mr. Felton (on behalf of Mr. Irwin’s Committee) and Mr. Nolan of confirmation of the CPO by letters dated the 10th May 2006. Notice of the confirmation was also published in the Wicklow People on the 11th May 2006. The letters and the newspaper notice stated that an application for Judicial Review of the Board’s decision to the confirm the CPO could be made to the High Court within eight weeks in accordance with Section 50 of the 2000 Act. No application for Judicial Review was made to the High Court. In the absence of same this CPO became operative three weeks from the date on which the notice of the Board’s decision was first published. Step 9 – Notice to Treat: 3.30 The Council served a Notice to Treat on Mr. Felton (on behalf of Mr. Irwin’s Committee) and on Mr. Nolan under cover of letters dated the 12th July 2006 and these letters appear to have been sent by registered post on the 13th July 2006. Service of the Notice to Treat was done pursuant to Manager’s Order dated the 12th July 2006. The Notices stated that the CPO was now operative and that the Council had decided to acquire and was willing to treat for the purchase of the several interests in the lands. The Notice required the person notified to furnish a signed statement to the Council on or before the 18th August 2006 dealing with certain matters. These were firstly the exact nature of the interest in the lands in respect of which compensation was claimed by the person notified, and secondly details of the amount of compensation claimed by that person for his interest in the land and setting out how such amount had been calculated. As stated earlier, the date of service of the Notice to Treat is an extremely significant event in the entire CPO process, as Section 84 of the 1966 Act provides that the value of the land acquired shall be set by reference to the date of service of the Notice to Treat. In the present case, the Council were stuck with the fact that the value of the land acquired was set by reference to the value at the height of the market in July 2006. 29 Step 10 - Entry: 3.31 In the present case the Council did not exercise the power of entry prior to payment of compensation. If it had done so it would have been liable for interest on the compensation from the date of entry to the date of payment of compensation. Therefore it made no sense to serve a Notice of Entry in relation to this CPO, and vacant possession was later received by the Council at the closing of the transaction on the 31st August 2011. Steps 11 to 13 – Claims for Compensation and Arbitration: 3.32 A Notice to Treat dated the 17th August 2006 was furnished to the Council by Lennox Estates on behalf of Mr. Irwin. The Notice stated that Mr. Irwin was the freehold owner of the lands, and claimed an amount of €10,425,000 for compensation for the purchase of Mr. Irwin’s interest in the lands. As regards setting out how such amount had been calculated, the Notice stated that the valuer’s opinion as to a reasonable amount was calculated having regard to three comparable sales of land in the area, and details of these three comparables were set out and a weighted average of these comparables was relied upon. 3.33 A Notice to Treat dated the 16th August 2006 was furnished to the Council by Ganly Walters on behalf of Mr. Nolan. As regards showing the exact nature of Mr. Nolan’s interest in the lands, Ganly Walters stated that they had been advised that Mr. Nolan remained the sole and exclusive occupier of the lands, and had had the beneficial use of the property effectively for his lifetime and more particularly on a rent-free basis upwards and over for the past 25 years. They understood that the claimant’s title was possessory. The Notice claimed compensation in the total amount of €6,349,325, being €5,608,800 for the value of the lands being compulsorily acquired and an amount of €640,525 for temporary disturbance. As regards setting out such amount had been calculated, no comparables were set out as in the case of the other Notice to Treat. There was simply a general description of the subject property, and a statement that this type of holding would command a serious premium if brought to the market. 30 There was also a reference to the main effects of compulsory purchase on Mr. Nolan, and a statement that the acquisition would render the present agricultural enterprise carried on by Mr. Nolan inoperable, thus requiring the acquisition of alternative land or the destruction of livestock. 3.34 In the present case there was no agreement on the claims for compensation prior to arbitration. After receipt of the Notices to Treat the Council initially asked Remax Garden County Auctioneers (“Remax”) in November 2006 to carry out a valuation of the CPO lands on behalf of the Council. The Remax Valuation dated the 11th January 2007 valued the lands at €7m, having referred in a very general way to comparable sales of similar zoned lands in the area. There was also reference to access to the lands being limited and a certain discount was allowed for same. No reference was made to any issue of risk of flooding. 3.35 Following receipt of the Remax valuation the Council decided to get an alternative valuation done. There is a note on file dated the 9th March 2007 recording this decision, and the note also records that Ms. Catherine Halligan, Senior Executive Officer, Housing Directorate of the Council spoke with Mr. Ray Hanley of G.V.A. Donal O’Buachalla (“O’Buachallas”) , regarding this alternative valuation. However, a letter of instructions did not issue to Mr. Hanley until the 30th January 2008, and this was prompted by a reminder letter from Lennox Estates dated the 21st January 2008 stating that the Wards of Court Office had requested a report as to progress with resolving this CPO. This delay from March 2007 to January 2008 may be partly explained by the fact that Mr. Hanley had left the firm during the intervening period. By letter dated the 4th April 2008 Mr. Jack Devlin of O’Buachallas sought further information from the Council regarding various matters. Further communications between Mr. Devlin and the Council followed, leading ultimately to Mr. Devlin’s Report and Valuation dated the 30th June 2008 (“the O’Buachallas Valuation”). 3.36 As regards basis of valuation, under the heading “special assumptions” Mr. Devlin stated that for the purposes of the report O’Buchallas had to provide two separate valuations, one on the basis that the property was held freehold by Mr. Irwin and that access was limited to the track off the R761, and the second on the basis that Mr. 31 Nolan had acquired ownership of the property through adverse possession and that access could be provided through his adjoining property. The relevant valuation date was the 12th July 2006, i.e. the date of the covering letters which accompanied the notices to treat. The description of the subject property mentioned that the site sloped gently to a west-east direction towards Three Trout Stream. As regards ground conditions, it was stated that O’Buachallas had assumed “that there were no adverse ground conditions such as flooding”, in considering their valuation. The report discusses the planning situation regarding the lands, and how the subject plot was actually zoned for open space development as part of the area zoned Action Area Plan Z1, as referred to above. The report noted that at the date of the Notice to Treat the draft Greystones/Delgany Local Area Plan 2006 (“the LAP 2006”) was on display and the subject lands were zoned R2 “to preserve and improve residential amenity, max 17.3 units/hectare” which draft plan was subsequently adopted with this zoning provision in December 2006. The report then set out some of the planning history of certain adjoining lands and also noted that under the LAP 2006 a portion of the subject lands adjacent to the Three Trout Stream was also zoned green corridor “to protect the biodiversity value of the Three Trout Stream and associated habitat areas, preserve ecological buffer areas either side of the stream free of development, protect the flood plain of the stream, provide a green route (pedestrian and cycle linkages) along the course of the stream from the coast to Delgany village and westwards to the Glen of the Downs”. 3.37 Section 11 of the report dealt with valuation considerations. As regards location, the subject property was located in an area where there had been considerable development in recent years. As regards development potential, the subject property had no frontage and the existing access was via a narrow track leading off the R761. However, alternative access could in theory be provided from three locations. It was necessary to have regard to the local planning history and the reasons set out in the refusals of previous planning applications which highlighted the issues of poor access and traffic hazard. If the subject property was owned by Mr. Irwin, the property’s access to the R761 was confined to a long, three-metre wide laneway, totally unsuited to development. It appeared that the most suitable option for the provision of access for the development of the subject site (ignoring access via Burnaby Lawns) was via 32 the adjoining Zapi/Ballymore development. Under the heading “Market Commentary” Mr. Devlin noted that the property market was particularly buoyant in July 2006 with strong demand for new homes in Greystones, however the subject site was severely disadvantaged in terms of access. He concluded that, aside from the Council, the most likely party interested in acquiring the plot would have been Zapi/Ballymore for incorporation into the Charlesland development. He did not believe that any third party developers would compete for the acquisition of these lands, given the deficiencies in access. It was his opinion that Zapi/Ballymore would offer a price reflecting the unsuitability of the access to the lands and the fact that the potential for housing development could only be realised through development via Charlesland. In the circumstances, therefore, the developer would not pay a price equating to the value of zoned and serviced development land, which was capable of independent and immediate development, but rather would pay a price reflecting the fact that they controlled the only access suitable for development and offer a discount price accordingly. Having regard to all of these valuation considerations Mr. Devlin estimated compensation in the event that the lands were owned by Mr. Irwin at €4,580,000, or in the event that the lands were owned by Mr. Nolan at €5,215,000. 3.38 Following receipt of the O’Buachallas Valuation on the 1st July 2008 it appears that the proposed social housing scheme on these lands was effectively “mothballed”, as it appears to have come clear around this time that this scheme was not likely to proceed in the near future because of the collapse of the national finances and the lack of any further funding for new social housing projects, as set out at paragraph 3.08 of my first report. The Council did make an application to the Department for sanction to borrow a potential compensation figure of €5,000,000 in respect of the CPO lands in August 2008, which approval was ultimately granted by the Department in July 2009. However the Council did not drawdown any such loan from the Housing Finance Agency by the end of 2009 as the CPO compensation figure was still not agreed, and the sanction lapsed at the end of 2009. All of this is set out in detail in my first report. In the meantime there was very slow progress with seeking to agree the claims for compensation, and the position continued to be complicated by the competing claims to ownership. By email dated the 5th December 2008 Ms. Halligan informed O’Buachallas that Mr. Irwin and Mr. Nolan had both died recently, and that their 33 respective estates were anxious to try to move the process on as the beneficiaries of Mr. Irwin’s estate were anxious to bring closure to this CPO. By further email dated the 10th December 2008 Ms. Halligan asked Mr. Devlin of O’Buachallas to speak to Mr. Gordon Lennox of Lennox Estates on the Council’s behalf regarding the CPO, in the light of the contents of her previous emails. It appears from a document on file that Mr. Devlin spoke with Mr. Lennox in January 2009 but both parties were busy at the time and decided to leave this issue over for a little while, and that the matter then went dormant during the rest of 2009. There were, however, certain internal communications during 2009 which suggest to me that the Council had lost its appetite for proceeding with the CPO by this time. Ms. Halligan sent a memo to the Law Agent dated the 4th March 2009 stating therein as follows: “A Notice to Enter was not served in this instance and I wonder is the Council legally obliged to proceed with this CPO. It would suit us now at this point not to have to purchase this land, as we are not in a financial position to do so. We would have to borrow the money and as you know there are restrictions on this at present. I should be obliged to have your advice on this matter.” 3.39 In his replying Memorandum dated the 9th March 2009 the Law Agent referred to Section 5 of the Acquisition of Land (Assessment of Compensation) Act, 1919 whereby an acquiring authority may withdraw any Notice to Treat served on a claimant within six weeks after the delivery of a Notice of Claim and in effect walk away from their confirmed CPO. In the present case the Council had not exercised any such power within the stipulated period, and therefore it seemed to Mr. Sweetman “that the Local Authority now has no way out of this particular CPO”. At the end of his memo Mr. Sweetman made the following pertinent comment: “I regret that this is not what you want to hear but unfortunately, the provisions of the 1919 Act in a falling market work out against the acquiring Authority, in this case, ourselves.” 34 After this advice from the Law Agent Ms. Halligan then discussed the matter with Mr. Devlin on the 6th May 2009 and at that point Mr. Devlin was of the opinion that the Council should ascertain who was the rightful owner of the lands and deal with that party alone, as opposed to instructing a valuer to deal with both parties as only one could own the property. Ms. Halligan sought the further advice of the Law Agent on how to proceed, and by memorandum dated the 12th May 2009 the Law Agent suggested that the Council should take its own expert advice from Senior Counsel. It did seem to him however, that the ultimate resolution of the ownership dispute would be for the reputed owner to bring Court proceedings seeking a declaration that he, as reputed owner, was in fact the owner whom the local authority should deal with and to whom the relevant compensation should ultimately be paid. While a draft Manager’s Order for the appointment of Senior Counsel was prepared nothing further was done at that point and the matter lay dormant for the remainder of 2009. 3.40 Mr. Lennox revived the matter with Ms. Halligan in January 2010 and Ms. Halligan then asked Mr. Devlin to contact Mr. Lennox on the Council’s behalf to try to sort out the valuations for this land. Mr. Devlin’s replying email dated the 2nd February 2010 is interesting as he states therein that he had delayed taking up with Mr. Lennox as he believed that the Council “didn’t wish to proceed with the acquisition (even though the Notice to Treat has been served)”. By letter dated the 9th March 2010 Mr. Lennox wrote to Ms. Halligan and referred to the lack of any further news of progress. He asked whether he might reasonably expect to have the Council’s response to Mr. Irwin’s claim for compensation, or failing which was it the Council’s position that they wished to abandon this CPO process? This letter is further evidence of the Council displaying a lack of appetite for progressing with this CPO by this time, and of Mr. Lennox detecting same. On receipt of this letter Ms. Halligan again sought advice from the Law Agent as to how to proceed and by memorandum dated the 22nd March 2010 Mr. Sweetman stated that he would require more information from Felton McKnight Solicitors before he could advise further. 3.41 In the meantime, Mr. Devlin met with Mr. Lennox on the 29th March 2010 to discuss the matter, and reported back to Ms. Halligan by letter dated the 1st April 2010. Mr. Devlin outlined to Mr. Lennox at the outset that the Council’s preference would be 35 not to proceed with the acquisition of the lands and that funding would not be available. Mr. Lennox pointed out that the Council could not withdraw from the purchase at this stage without the landowners’ consent and he doubted that this would be forthcoming. For the purposes of opening negotiations, Mr. Devlin advised Mr. Lennox that in O’Buachalla’s opinion the lands were of little value, given the deficiency in access and accordingly the maximum figure which they were prepared to recommend for the Council’s acceptance was €200,000 per acre. Mr. Lennox advised Mr. Devlin that he could not possibly recommend his clients to consider an offer at the proposed levels, but he agreed to take instructions and revert to Mr. Devlin. In his report back to Ms. Halligan, Mr. Devlin pointed out that the Notice to Treat in this case was at the peak of the property boom and sales of residential zoned land at that time suggested values of up to €3.85m per acre. He advised Ms. Halligan that the stated figure of €200,000 per acre would clearly not be sustainable at arbitration, but if the Council were to be forced to acquire this property, then O’Buachallas had endeavoured to reduce the claimant’s expectations by making an offer at the lowest possible level. 3.42 The above meeting appeared to mark the end of any efforts to seek agreement on the claim made by Mr. Irwin, and by application dated the 5th May 2010 the beneficiaries of Mr. Irwin’s estate applied to a body known as the Reference Committee for the nomination of a Property Arbitrator to determine the question of compensation, in accordance with the relevant legislation. By Notice dated the 18th June 2010 the Reference Committee nominated Mr. Eoin O’Buachalla as Arbitrator to determine the said question. Step 14 - Service of Notices: 3.43 As regards Step 14, the requirements in the relevant legislation for the publication of certain notices, subsequent to nomination of a Property Arbitrator, did not apply in the present case as the Arbitrator was nominated on the application of the claimants. 36 Step 15 - Arbitration: 3.44 The next phase of this saga was preparation for the arbitration hearing which was ultimately to take place the following year on the 24th March 2011. By letter dated the 24th June 2010 the Arbitrator notified the parties that he proposed to hold the arbitration hearing on the 24th September 2010 and he gave directions regarding various matters, including the submission of pleadings and the exchange of expert reports etc. The Solicitors for the claimants delivered a Statement of Claim on or about the 5th August 2010 and claimed that the lands were valued at approximately €10,425,000 as of the date of the Notice to Treat, as per the claim in the Notice to Treat dated the 17th August 2006. The Law Agent sent a copy of the Statement of Claim to Mr. Devlin when he received it and by letter dated the 24th August 2010 he sent him on a draft Reply and asked him for his views. The Law Agent made reference to issues such as planning, access and access to services. He noted that Mr. Lennox had put forward comparables in the Notice to Treat and as regards Killincarrig Lodge he commented that this property may have easier services and no risk of flooding etc. The draft Reply awaited the input of Mr. Devlin as regards certain points, in particular the Council’s position regarding the value of the lands as of the date of the Notice to Treat. 3.45 By a memorandum of the same date to Ms. Halligan the Law Agent referred to Mr. Devlin’s view that the biggest reduction in value was the fact that the subject property was in fact land locked by a third party property between it and the R761, in circumstances where the R761 was untenable at that point in that in its present state no permission for development would be given fronting out on to the present road formation. The Law Agent sent a preliminary brief to Esmonde Keane S.C. by letter dated the 27th August 2010. The history of the matter was set out and references made to issues of access and road frontage, but one might note that no reference was made to any issue of flooding at this juncture. Mr. Devlin reverted to the Law Agent by letter dated the 27th August 2010 and suggested a number of amendments to the draft Reply, including references to zoning, lack of services and access problems. As regards values, Mr. Devlin suggested pleading a figure of €697,000, based on the 37 figure discussed with Mr. Lennox some months previously. However, Mr. Devlin added the following important rider: “As you will be aware from previous discussions with Mr. Lennox, we indicated our willingness to recommend a settlement of compensation at a rate of €200,000 per acre. However, you will appreciate that this was purely for negotiation purposes and that we believe that the date of valuation coincides with the height of the market and the comparable evidence will in all likelihood result in a substantially higher award from the arbitrator.” 3.46 Mr. Keane S.C. wrote back to the Law Agent by letter dated the 31st August 2010 having settled the draft Reply, and he noted that it did not appear as if the Arbitrator had been appointed to determine the claim of Mr. Nolan in addition to the claim of Mr. Irwin’s estate. Around this time the proposed hearing date was changed to the 1st November 2010. 3.47 A consultation was arranged by the Law Agent with Mr. Keane S.C. for the 11th October 2010. In advance of same a draft précis of his proposed evidence was prepared by Mr. Mark Devereux, Senior Engineer in the Housing Section of the Council. Paragraph 4 noted that the property presently consisted of a field which varied in levels from approximately 17 meters above ordnance datum on the north eastern corner adjacent to the Three Trout Stream to approximately 25 meters above ordnance datum at the south western corner adjacent to the existing substandard entrance laneway and the back of the adjacent Charlesland development. Paragraph 9 is also worth noting, wherein Mr. Devereux stated that any development which would be carried out on the site would be constrained by the proximity of the Three Trout Stream and the proposed pedestrian/amenity corridor which would make up to 30% of the site incapable of development, and also that in addition a reasonable protection zone would be included so as to ensure that the development would not be subjected to flooding even in an extreme flooding event. The consultation went ahead on the 11th October 2010, and it is clear from the Law Agent’s notes that among the issues discussed was the flooding issue, and the potential for works to raise ground levels 38 pursuant to the Barry Report recommendations. After the consultation the Law Agent sent a memorandum to Ms. Halligan dated the 12th October 2010, and this memorandum is a useful illustration of the uncertainty regarding the compensation which the Arbitrator might award. Mr. Keane had mentioned to the Law Agent that the Council should give serious thought to preparing and filing an unconditional offer at around €600,000 - €650,000 and on the day be in a position to offer €1.2m / €1.3m to purchase these lands. At the same time Mr. Devlin indicated that he would be concerned that the Arbitrator might, quite simply, take values generally in the area based on comparables put forward by Mr. Lennox and quite simply take one third or possibly one half of that value off because of the poor quality access etc. While this would be a formulaic approach and not necessarily in accordance with appropriate valuation principles, nevertheless it was something that an Arbitrator might quite reasonably do and this could land the Council with a bill of perhaps €4m / €5m, depending on the view the Arbitrator would take of the comparison evidence. In those circumstances the Law Agent felt that the Council should give serious thought to the unconditional offer suggested by Mr. Keane. 3.48 By letter dated the 19th October 2010 the Law Agent furnished the Arbitrator with a booklet containing the précis of evidence of the Council’s valuer, Mr. Devlin, the Council’s Engineer, Mr. Devereux, and the Council’s Engineer, Mr. Fergal Keogh, Senior Engineer in the Planning Department of the Council. On the same date the Law Agent delivered copies of the same booklet to the Solicitors for the Claimants, and requested in exchange a set of their clients’ précis of evidence. The contents of the précis of evidence merits some mention, as they illustrate the attitude of the various experts towards these lands as of mid-October 2010 with the arbitration hearing due to commence on the 1st November 2010. The précis of evidence of Mr. Devereux was similar to the draft précis referred to above with the references to the rising levels of the field as one moved in a south western direction away from the Three Trout Stream, and to the constraints on development arising from the proposed pedestrian/amenity corridor and a reasonable flood protection zone. The précis of evidence of Mr. Keogh was dated the 18th October 2010 and dealt with the development potential of the subject site, having regard to the recent planning history and some other relevant applications in the area. Various points were noted in 39 relation to the development potential of the site and Mr. Keogh referred to the flooding issue as follows: “The existence of a flooding problem was indicated in submissions to the Board at the time of the CPO hearing. Furthermore, flooding has been an issue along the Three Trout Stream historically. A report in this regard was prepared for the Council by the Consultants JB Barry & Partners entitled “Storm Water Review – Three Trout Stream”, in February 1997. Any restrictions that were identified due to flooding would impact on the development potential…”. Mr. Keogh’s conclusion was that were the zoning objective of public open space to be disregarded then the site could be developed, subject to the principles of good design. The quantum of the development could be limited by the requirements for a green area along the Three Trout Stream and any potential flooding issues. Access was a serious difficulty for this site, and without adequate access permission for development would not be granted. 3.49 As regards the précis of evidence of Mr. Devlin, while he again emphasised the issue of inadequate access as he had done in his June 2008 report, he now highlighted also the alleged additional deficiencies of open space zoning and risk of flooding on a portion of the lands. As regards comparables, he focused on the purchase by Zapi Developments of adjoining lands in July 2005 for €3.2m, equating to €2,133,330 per hectare. Allowing for an increase in the market of 20% between July 2005 and July 2006, but also allowing for a deduction for the alleged deficiencies of the subject site at 60%, leaving a net reduction of 40%, he arrived at a valuation of €1,436,000. . 3.50 By memorandum dated the 20th October 2010 the Law Agent suggested to Ms. Halligan that the Council should consider making an unconditional offer of roughly €1.5m in this case. This was clearly a substantial increase in the suggested unconditional offer figure mentioned by the Law Agent in his previous memorandum dated the 12th October 2010, just over a week beforehand, but was roughly in line 40 with the most recent valuation furnished by Mr. Devlin in his précis of evidence dated the 18th October 2010, and was presumably arrived at on that basis. 3.51 By letters dated the 20th October 2010 the Law Agent furnished Mr. Keane and Mr. Devlin with copy of the précis of evidence of the other side and the following points might be mentioned in relation to same. The first précis of evidence was in the form of an expert report from Mr. Frank O’Gallachoir, Planning and Development Consultant dated the 13th October 2010. In his report Mr. O’Gallachoir focused on the planning history of the relevant area and on the general planning policy affecting the acquired land. While he mentioned that the Three Trout Stream runs along the northern boundary of the subject lands and separates it from Burnaby Lawns and that the ground levels of the property fall gently from the south – west corner to the north – east, no reference was made to any issue of risk of flooding. Mr. O’Gallachoir’s conclusions were that the lands form part of the Z1 Action Area which was specifically designated for development in the 1999 Local Area Plan and he felt that adjacent developments which were permitted in the area prior to July 2006 established a precedent for the density, site layout and servicing of the subject lands. A second précis of evidence was in the form of an expert report from Mr. Michael Browne, Chartered Structural Engineer, dated the 14th October 2010. His report dealt with the availability of services and potential access to the subject lands and in his opinion the lands could be accessed via the existing Burnaby Lawns estate, by means of a bridge over the Three Trout Stream, or alternatively there could also be access from the Charlesland Estate to the South. His conclusion was that this was an excellent site in a prime location capable of being easily and readily serviced to provide valuable housing units. The most significant précis of evidence was probably that of Mr. Gordon Lennox dated the 13th October 2010, and this was really an expanded version of the Irwin Notice to Treat set out above. In describing the location Mr. Lennox mentioned that the lands were bounded in part by the Burnaby Lawns estate and separated from same by the Three Trout Stream, but again no reference was made to any issue of risk of flooding. The key aspect of his précis of evidence was his detailed treatment of eight comparable sales of land in the area, and his stated opinion of the open market value of the subject lands as of the 12th July 2006 in a figure of €10,425,000. He stated that his opinion was shaped primarily by the first three 41 comparables in his schedule of comparables, being the same three comparables relied upon in the Notice to Treat and he concluded that a weighted average of these three comparables yielded a figure per acre/per hectare leading to an amount of €10,426,236 which he had rounded to €10,425,000 as stated. Four of the other comparables were set out in order to further illustrate the background to speculative land purchases by consortia of investors and residential developers, in the year or so prior to the Notice to Treat, and the eighth comparable was added for the purpose of grounding a figure for the most conservative category of land to transact locally within two years of the Notice to Treat in a “cooling” market. Mr. Lennox’s conclusion was that if the subject land had been brought to open market in 2006, in common with his first three comparables, then the very competitive bidding evident in the other transactions would in all probability have produced a sale price in excess of €10,000,000 and he reiterated his stated opinion of open market value as of the 12th of July 2006 in the figure of €10,425,000. 3.52 On or about the 27th October 2010 the claimants’ Solicitors sent an email to the Law Agent containing some comments from Mr. Lennox, the claimants’ valuer, on the recent précis of evidence of Mr. Devlin. In response to Mr. Devlin’s section on ground conditions, Mr. Lennox commented as follows: “Why, if the land is allegedly prone to flood, do Wicklow County Council’s own Reports from the time of the CPO hearing describe the land as being suitable for housing? Equally, would not the County Council Estate (Burnaby Lawns etc.) as built be equally prone?” Mr. Lennox went on to strongly dispute Mr. Devlin’s treatment of valuation considerations and he disagreed absolutely with Mr. Devlin’s assertion that his comparables were of no assistance in determining the market value of the subject lands. He criticised Mr. Devlin’s reasoning on price, in terms of Mr. Devlin having allegedly selected just two comparables at the lowest achieved rate per hectare/acre instead of taking a more representative “basket” of transactions within a reasonable radius of the subject lands and under the auspices of the same section of the County Development Plan governed by the Greystones/Delgany area proposals. 42 3.53 These comments from Mr. Lennox were sent on to Esmonde Keane S.C. and to Mr. Devlin in advance of a meeting with them later that day, and may have had an impact upon potential values or settlement terms then under consideration, not necessarily in terms of acceptance of the comments of Mr. Lennox but in terms of displaying the serious conflict of evidence which was looming before the Arbitrator. A lengthy consultation was held with Esmonde Keane S.C. and Mr. Devlin on the 27th October 2010, and following this consultation the Law Agent sent an important memorandum to Ms. Halligan and to Mr. Michael Nicholson, Director of Services, Housing and Corporate Estate dated the 28th October 2010. This Memorandum is particularly important as it shows the crystallised thinking of the Council’s principal advisors as to potential settlement immediately prior to the scheduled hearing date of the 1st November 2010, and it appeared that this thinking eventually carried through to the ultimate hearing date in March 2011. In his memorandum the Law Agent pointed out the difference between the valuations of Mr. Devlin and the claimants’ valuer, Mr. Lennox, whereby Mr. Devlin considered that the property was worth somewhere between €800,000 and €1m per acre whereas Mr. Lennox was taking comparisons of about 2½ times that, i.e. €2m to €2,500,000 per acre or thereabouts. He noted that Mr. O’Buachalla had a reputation of being more generous to claimants than some former Arbitrators. He mentioned that Mr. Devlin and Mr. Keane were both very concerned that if the claimants’ figures were, with some deductions, accepted by the Arbitrator and even if he then made an allowance of 1/3 because of the difficulty in gaining access, an award might still be made of something of the order of €5,500,000 to €6,500,000. Mr. Devlin’s best comparison would provide a purchase price of €3.08m in round figures. Mr. Keane had asked that the Council consider the possibility of settlement and, while Mr. Devlin’s valuation was at roughly €1.5m in round figures, Mr. Devlin and Mr. Keane had asked for authority to approach the Irwin’s Senior Counsel to see if the matter could be resolved without the necessity for taking the risk of running the arbitration. The figure that Mr. Keane was likely to have to discuss with the other side was of the order of €2.7m in his view, and Mr. Sweetman asked the Council officials to consider whether or not they were in a position to instruct Mr. Keane and give him a total of €3m to negotiate with. Mr. Sweetman felt it appropriate to put this proposition to the Council officials in writing so that they were 43 aware “that there is, in the view of both Jack Devlin and Esmonde Keane, a significant risk that if the matter goes to arbitration, the Arbitrator may make an award somewhat higher and possibly of the order of €5,500,000 to €6,500,000 as mentioned above”. The Law Agent regretted that this was not an exact science but he thought it might well be wise to see if the matter could be resolved. Any agreed payment would be conditional on the Irwins eliminating the potential claim from Mr. Nolan’s estate. 3.54 By a further memorandum dated 28th October 2010 the Law Agent raised certain matters with Mr. Devereux, and in particular raised the issue of the area liable to flooding in the context of amending a map which was then in existence. He asked Mr. Devereux to send a map showing the proposed roadway that Mr. Devereux had sketched out for purposes of access and his costing because, in particular, that map also showed the area that was liable to flooding. It appears that Esmonde Keane S.C. had seen this map which Mr. Devereux had sent to Mr. Devlin, and Mr. Keane had suggested that the area liable to flooding would be amended slightly by being crosshatched or shaded, and that it would also be helpful that the area, or approximate area, could be calculated. It appears that the map being referred to here may be a draft drawing dated October 2010 entitled “Lay Out Proposed New Roadway”, which draft drawing also shows the area of the subject site over 17.50 metres contour as 2.27 acres outlined and shaded in red. A copy of this draft drawing is attached at Appendix 4 hereto. The clear implication of this draft drawing is that the Council regarded the area outlined and shaded in red as not liable to flooding, on the basis that the ground levels in this area were over 17.50 metres, which compared with the maximum predicted flood level of 17.27 metres O.D. for a 100 year fluvial five year tide, as per Table 4.1 at page 10 of a September 2009 update to the Barry Report. The draft drawing also shows the area that is liable to flooding, in the sense that it shows the remaining area of the subject site which is not outlined and shaded in red. In my review of the voluminous Council’s files I have not seen an amended version of this “map” or draft drawing which shows the area liable to flooding crosshatched or shaded, as requested by Mr. Sweetman in the said memorandum. As regards calculating that area, Mr. Devlin did state in his précis of evidence dated the 18th October 2010 that he had been advised by the Council that approximately 0.53 44 hectares of the subject area was below the 17.50 metre flood level, and this would be 0.53 acres of approximately 1.4022 hectares in total, or approximately one third of the total area of the site. This would tie in with the draft précis of evidence of Mr. Devereux referred to above. What is important about all of this is that it demonstrates the Council’s belief that only approximately one third of the subject site was in any way at risk of any flooding, and this area was adjacent to the Three Trout Stream where there would be a green corridor and a flood protection zone. 3.55 The next event which arose was the adjournment of the arbitration hearing which was scheduled for the 1st November 2006. On the 28th October 2010 Rutherfords Solicitors, on behalf of the personal representative of John Nolan, deceased, wrote to the Law Agent proposing that the arbitration procedure initiated by Felton McKnight Solicitors (on behalf of the Irwin estate), be deferred until the title issue was resolved. They said that they had only very recently received notice of the arbitration procedure and that the title issues between the Irwin estate and the Nolan estate could only be resolved by the issue of High Court proceedings which were currently in the course of issue. Rutherfords Solicitors then wrote to the Arbitrator the following day, the 29th October 2010, along similar lines. They pointed out that on foot of advices received from Senior Counsel they were that day issuing High Court proceedings seeking declarations as to their client’s interest in the lands, together with necessary ancillary orders, and enclosing a copy of the Plenary Summons. They claimed that their client would be fundamentally prejudiced in his ability to effectually present his claim for compensation, if the arbitration hearing were to proceed on the following Monday. Given the nature of the proceedings about to be issued on his behalf, it was their respectful view that the arbitration issue should be adjourned until such time as the High Court proceedings had been determined. By letter dated the 29th October 2010, the Law Agent informed the Arbitrator that the Council in the circumstances would not oppose any application for an adjournment which might be made to him by Rutherfords Solicitors. The outcome of this entry into the fray by Rutherfords Solicitors was that the matter did not proceed in any substantive way on the 1st November 2010. It appears that before the hearing commenced the legal representatives of the Nolan estate agreed with the representatives of the Irwin estate that they would meet and discuss their respective claims over the next few weeks. 45 Accordingly an application for an adjournment was made by Senior Counsel on behalf of the Irwin estate, and it was agreed on consent that the matter be put back to the 10th December 2010, for mention only in the first instance. Any progress in relation to the title issue would then be reviewed and the fixing of a new hearing date would then be considered. The Arbitrator had to reschedule the resumed hearing due to unforeseen circumstances, and ultimately the arbitration hearing was rescheduled to resume on the 24th March 2011. 3.56 As the resumed hearing day approached it was clear from the Law Agent’s file that the substantive issues remained pretty much where they had been the previous October, immediately in advance of the original hearing date of the 1st November 2010. The Council intended to rely upon the précis of evidence prepared earlier on behalf of their witnesses in October 2010. By memorandum dated the 10th March 2011 the Law Agent gave certain directions to the Council representatives and advised that by way of general preparation they should read the Council’s own précis of evidence and those received from the other side, and also the letter from Mr. Lennox dated the 22nd October 2010 with his comments on the précis of evidence of Mr. Devlin as discussed above. The question of authorising Mr. Keane S.C. to negotiate a settlement to a total figure of €3m as discussed previously in October 2010 appears to have gone into cold storage while the matter stood adjourned. The Law Agent returned to this issue in a memorandum dated the 23rd March 2011 to Ms. Halligan. He stated that Mr. Devlin considered that if the Arbitrator were advised that the Nolan and Irwin sides were now united i.e. that they had resolved their differences, the Arbitrator might choose to make a substantial award on the basis of an unencumbered freehold title. In that regard Mr. Devlin considered that the Council team should seek authority to negotiate and the sort of figure he was looking at was between €3m and €3.5m. This might or might not be sufficient to settle the case but if the Council team were to negotiate with anything resembling serious intent, then they would have to have that sort of figure available. 3.57 It appears that as a result of this memorandum Ms. Halligan did discuss the issue of a settlement figure with Mr. Nicholson, and that Mr. Nicholson gave the Council team authority to go to €3/€3.5m to settle the matter. This is recorded in the Law Agent’s 46 attendance note of the pre-hearing consultation with Mr. Keane S.C. and the Council witnesses on the 24th March 2011. It is noted that while Mr. Devlin expressed the view that his valuation was on a reasonably correct basis, he felt the Arbitrator would probably give a significantly higher award, and after discussing the matter it was agreed that the authority which Ms. Halligan had received from Mr. Nicholson to go to €3 / €3.5m to settle the matter was reasonable. It was possible, however, according to Mr. Devlin that the Arbitrator would award as much as perhaps €5m depending on the view he took of Mr. Lennox’s comparison. 3.58 The Arbitration hearing then commenced later the same morning. At the outset the legal representatives for the Irwin Estate and the Nolan Estate confirmed to the Arbitrator that the title issue had now been resolved, by agreement between the Irwin Estate and the Nolan Estate, and it was now acknowledged that there was no claim to the subject property by the Nolan Estate. The first and ultimately the only witness who gave evidence was Mr. O’Gallachoir on behalf of the Claimants. He first read into the record his précis of evidence, and then answered a couple of questions from his own Senior Counsel. After this he was cross-examined by Mr. Keane S.C. on behalf of the Council. Mr. Keane first challenged Mr. O’Gallachoir in relation to the availability of services to service the subject lands and then in relation to his calculations as to the density of the development. At page 33 of the transcript Mr. Keane moved on to the issue of flooding, and suggested to Mr. O’Gallachoir that he had not considered the impact of flood risk in relation to his densities. The witness accepted that it hadn’t been considered explicitly but he was not aware of any significant flooding problems in the area. From his understanding and from his personal knowledge he thought flooding would not be a significant issue, particularly in the form of layout that he thought most people agreed would be likely for this site. Mr. Keane then put to the witness the evidence given by Mr. Nolan at the oral hearing into the CPO regarding flooding in this field in the past, and in particular flooding of a number of houses in the Burnaby Lawns estate in 2002. There was then a dispute about Mr. Keane seeking to rely upon hearsay evidence, and the Arbitrator directed that Mr. Keane would have to produce engineering evidence if he wanted to rely upon the point that the site was subject to flooding. Mr. Keane accepted that requirement for engineering evidence in due course, but in the meantime he suggested to Mr. 47 O’Gallachoir that keeping out of the floodplain would act as a restriction in relation to the extent of development on the subject site. The witness repeated that he wasn’t aware specifically of flooding in this area, but he thought it was obvious that the kind of site layout for the development of this land would provide a buffer between any housing development and the stream. 3.59 Mr. Keane asked would this be by virtue of setting back the development on the site away from the stream, and the witness confirmed that it would be to ensure that a sufficiently wide public open space was available in case of any flooding. Mr. Keane then moved on to suggest that there were certain other potential restrictions on development such as the objective in the 1999 Local Area Plan for the provision of cycle and pedestrian ways in an east-east/west access along the stream, and the fact that the subject lands appeared to be within the area zoned for public open space in the Z1 Action Area Plan in the 1999 Local Area Plan. At the end of the crossexamination the Arbitrator asked Mr. O’Gallachoir would he reconsider his figure for density of development of 28 houses per hectare, “having heard and having mentioned some of the difficulties with this site yourself”. After some delay the witness said that 28 was the maximum but given the constraints on the site and there were a reasonable number of constraints on the site, he would think it was likely to be lower than that and he thought maybe 24 houses per hectare. The hearing then broke up for lunch at the conclusion of Mr. O’Gallachoir’s evidence. 3.60 After the luncheon adjournment Senior Counsel for the Irwin Estate informed the Arbitrator that the parties had reached an agreement which had been reduced to writing and signed by the parties. Under the settlement agreement the Irwin claimants agreed to convey good marketable unencumbered fee simple registered title to the subject lands, and the Council agreed to pay the sum of €3m in consideration of the said conveyance, such sale to close on the 31st August 2011. The Council also agreed to pay the pre-reference costs and the costs of the reference to arbitration of the Irwin Claimants, such costs to be taxed in default of agreement. It was noted and confirmed that the Nolan Claimant had reached an agreement with the Irwin Claimants and he acknowledged in his capacity as legal personal representative of the estate of John Nolan deceased that he would execute all necessary documentation to confirm a good 48 marketable title, in consideration of the matters set out in the settlement agreement. There were some other miscellaneous provisions and finally there was a term that the arbitration would be adjourned generally with an Order for taxation of costs in default of agreement, and with liberty to apply in relation to the terms of the settlement. Step 16 – Arbitration Award: 3.61 In the present case it appears that no formal award was ultimately required from the Arbitrator. An award by an Arbitrator resembles an Order made a Court when it decides a case. It appears from the transcript that Counsel debated the possible form of any award that the Arbitrator might make, after the settlement was announced. The Arbitrator suggested that any award would cite that the compensation amount was agreed, and the order which he would make would be in relation to costs. However, the Arbitrator noted that there would be stamp duty payable on the award which would be payable by the Council, and for that reason the parties indicated that they probably would not need a formal award and they could implement the terms of settlement without requiring same. Steps 17 and 18 – Taking Title and Payment: 3.62 In the present cast the Council acquired title to the subject lands by virtue of a Deed of Transfer dated the 31st August 2011. Pursuant to this Deed of Transfer Mr. Edwin Irwin and Mr. Herbert Irwin as personal representatives of Mr. William Irwin deceased, the registered full owner, in consideration of the sum of €3m transferred all of the property comprised in Folio 2915 of the Register of Freeholders, County Wicklow to the Council. The Council also received a Deed of Waiver dated the 31 st August 2011 executed by Mr. Thomas Alphonsus Nolan, the legal personal representative of John Nolan deceased, whereby Mr. Nolan waived any claim of the deceased over the property. A formal contemporaneous closing took place on the 31st August 2011 whereby the Council gave the Solicitors for the Irwin Estate a cheque for the €3m agreed compensation. No interest was payable in relation to the CPO, in circumstance where the Council had not entered the lands prior to payment of the 49 compensation. As regards payment of costs, the process of submitting invoices and seeking to agree costs has proceeded subsequent to the 31st August 2001. 50 Chapter 4 4.01 The Specific Concerns of the Public Representatives regarding the Role of the Council In my Terms of Reference I have been requested to address the specific concerns of the public representatives in the annexed documents regarding the role of the Council and to consult as necessary with these public representatives. Some of the specific concerns of the public representatives in the annexed documents relate to the role of the Department rather than the role of the Council, and I have already addressed those concerns at Chapter 4 of my first report, and I do not propose to address same again unless there is some additional aspect arising relating to the role of the Council. As mentioned at paragraph 1.11 above, I consulted and met with these public representatives on a number of occasions during the course of my review in order to clarify certain aspects of the concerns raised by them. Before dealing with the specific concerns of the public representatives individually it is necessary to examine some earlier matters raised by the Councillors in their report dated the 3rd November 2011. Preliminary Matters 4.02 Under the heading “Background”, the Councillors refer to the fact that both Mr. Irwin and Mr. Nolan were claiming title separately to the same property, i.e. the CPO lands, “in a clear conflict of ownership”. Technically speaking there were conflicting claims to ownership rather than a conflict of ownership, as there could only have been one owner of the fee simple interest, to whom compensation would be payable. If necessary these conflicting claims would ultimately have had to be decided by the Courts as the Property Arbitrator had no jurisdiction to determine same, but as discussed in Chapter 3 the claim by the Nolan estate was ultimately compromised and withdrawn. However, prior to this compromise the conflicting claims undoubtedly added an extra layer of complication to this CPO and this complication was increased when Mr. Irwin was made a Ward of Court along the way, and all of this gave rise to delay and a lot of additional paperwork. 51 4.03 Under the heading “Council’s Valuation”, the Councillors suggest that the Council employed valuation consultants GVA Donal O’Buachalla to carry out a market evaluation of this land in 2008. In fact Mr. Devlin of O’Buachallas was originally retained by the Council by letter dated the 1st March 2006, and in that letter Ms. Gallagher stated that she was enclosing therewith “all documentation in relation to the CPO procedure so far”. At that stage Mr. Devlin’s brief was to contact Mr. Lennox with a view to entering into preliminary discussions regarding land valuations rather than to do a formal valuation as such. The Council’s files show that O’Buachallas were again briefed by the Council on 30th January 2008, and on this occasion they were furnished with copies of three other valuations carried out to date, a copy extract from the Local Area Plan 1999 and other relevant documentation. By letter dated the 8th May 2008 O’Buachallas were also furnished with a copy of the planning report prepared by Mr. Fergal Keogh, Senior Engineer, Planning and Development Section of the Council. I will return to this issue of the information furnished to O’Buachallas when dealing with the 10th stated “issue of public concern” below. 4.04 Under the same heading the Councillors state that in 2011 “the O’Buachalla valuation was once again used when the County Manager sought loan approval to raise a sum of €3m by a vote of the Council on 18/7/11”. The Council are referring here to a report prepared by Ms. Halligan of the Council dated the 29th June 2011 which report was prepared for the information of the Council members pending the Council meeting on the 18th July 2011. While the report dated the 29th June 2011 did make reference to the O’Buachalla valuation dated the 30th June 2008, the request for approval for the borrowing of €3m was ultimately based upon the settlement figure of €3m as agreed in March 2011 and not on the June 2008 valuation figures. I will return to this issue below. 4.05 Under the heading “Special Assumptions of the 2008 Report” the Councillors suggest that Mr. Devlin of O’Buachallas made two incorrect assumptions in his 2008 Report, firstly, that this property was held freehold by one or other of the Claimants, and secondly that no ground adverse conditions such as flooding was present on the land. As regards the first matter, it is clear that Mr. Devlin made an assumption along these lines in Section 2 of his report under the heading “Special Assumptions”, and then 52 proceeded to provide two separate valuations to take account of this assumption as to two alternative scenarios, but it is equally clear that this assumption was entirely correct and in line with his instructions. 4.06 As regards the second matter, at Section 7 of his report under the heading “Ground Conditions” Mr. Devlin stated that in considering our valuation “we have assumed that there are no adverse ground conditions such as flooding…”. On the face of it this assumption was clearly incorrect, as the issue of risk of flooding had featured during the CPO confirmation procedure, albeit with a dispute as to the extent and significance of the said risk. During the course of my review I consulted with Mr. Devlin to clarify this apparent error and he furnished me with a detailed explanation by letter dated the 7th December 2012. Mr. Devlin first confirmed that in preparing his valuation in June 2008 he was fully aware of the potential of that portion of the site along the Three Trout Stream to flood, and that the relevant information to this effect was provided to him by the Council prior to undertaking the valuation. His valuation was informed by his inspection of the site where he noted that its principle inadequacy in terms of development potential was the lack of a suitable independent access, and he also noted that a portion of the lands along the Three Trout Stream, particularly in the north western corner, were low-lying and potentially liable to flooding. He had reviewed all of the information provided to him by the Council, including the submission regarding flooding made by Mr. Nolan to An Bord Pleanála in 2005, and the response by Ms. Gallagher of the Council dated the 9th of February 2005, which included reference to the two principal recommendations of the Barry Report, namely that the stream channel be upgraded to cater for a storm within the 30year return period, and that floor levels should be a minimum of 1metre above the design topwater level. On the basis of his inspection and the information supplied, Mr. Devlin had concluded that the questions of suitability of the site and flooding raised by Mr. Nolan were not accepted by An Bord Pleanála in confirming the CPO. He had concluded that the value of the site would not be materially impacted by any risk for flooding, but that a more significant shortcoming in terms of development was the inadequacy of access. Later in his letter Mr. Devlin referred to his experience that Local Authorities do not get a sympathetic hearing when arguing before the Property Arbitrators that a site is unsuitable for development for any reason (in this case 53 flooding), when An Bord Pleanála have already heard evidence on the matter and confirmed a CPO for a particular use (in this case, housing). 4.07 Overall, while this stated assumption was literally incorrect, this was in my opinion due to slightly loose language employed by Mr. Devlin and was really a matter of form rather than a matter of substance. It is clear that Mr. Devlin was aware of the risk of flooding issue as potentially affecting a portion of the site, but his opinion was that the value of the site would not be materially impacted by any such risk. Ideally his stated assumption in Section 7 of his Report would have included that amplification or clarification, but it seems to me that his somewhat incomplete or ambiguous statement did not affect the substance of his valuation. 4.08 Under the heading “Revised Valuation 2010” the Councillors state that on the 27th August 2010 O’Buachallas gave a new market value of the CPO lands, revising the valuation downwards to a figure of €697,000 taking all factors into account. They complain that the revaluation of the lands was never disclosed to the elected Council members prior to the vote on loan sanction on the 18th July 2011. Two issues arise here, firstly, whether there was a significant revised valuation by O’Buachallas in 2010, and secondly whether there was some element of non-disclosure to the Council members in July 2011. 4.09 As regards revised valuations, I have set out in Chapter 3 how the figure of €697,000 arose in Mr. Devlin’s letter to the Law Agent dated the 27th August 2010, and the background and context in which that figure arose. This figure first arose out of Mr. Devlin’s opening negotiations with Mr. Lennox on the 29th March 2010, as outlined in Mr. Devlin’s letter to Ms. Halligan dated the 1st April 2010 where he recorded that “for the purposes of opening negotiations” he had advised Mr. Lennox that in the opinion of O’Buachallas the lands were of little value, given the deficiency in access and accordingly the maximum figure which they were prepared to recommend for the Councils acceptance was €200,000 per acre. The stated area of 3.46 acres therefore led to a value of in the region of approximately €692,000. However, it is clear from the text of the letter that this figure was suggested by Mr. Devlin “for the purposes of opening negotiations” and he confirmed this by adding the following rider: 54 “Clearly, this position would not be sustainable at arbitration, but if the County Council are to be forced to acquire this property, we have endeavoured to reduce the Claimant’s expectations by making an offer at the lowest possible level”. 4.10 On the 27th August 2010 Mr. Devlin relied again upon his earlier suggested rate of €200,000 per acre, in the context of suggesting a figure for compensation to be inserted into the draft Reply to the Statement of Claim which had been delivered by the Claimants. However, Mr. Devlin added a similar rider to the effect that this was purely for negotiation purposes and that the comparable evidence would in all likelihood result in a substantial higher award from the Arbitrator. In those circumstances the suggested value of €697,000 did not in substance amount to a revised valuation by O’Buachallas in August 2010, and it is clear from their correspondence that they were not revising the factors taken into account in the June 2008 valuation. However, there was a form of revised valuation contained in Mr. Devlin’s précis of evidence dated the 18th October 2010, as described in Chapter 3 above. While Mr.Devlin again emphasised the issue of inadequate access as he had done in his June 2008 report, he now highlighted also the alleged additional deficiencies of open space zoning and risk of flooding on a portion of the lands. As regards comparables, he focused on the purchase by Zapi Developments of adjoining lands in July 2005 for €3.2m, equating to €2,133,330 per hectare. Allowing for an increase in the market of 20% between July 2005 and July 2006, but also allowing for a deduction for the alleged deficiencies of the subject site at 60%, leaving a net reduction of 40%, he arrived at a valuation of €1,436,000 4.11 The valuation of €1,436,000 was the valuation which Mr. Devlin intended putting forward at the arbitration hearing which was scheduled to take place on the 1st November 2010. As described above in Chapter 3, this hearing did not ultimately take place until the 24th March 2011. In his letter to me dated the 7th December 2012 Mr. Devlin explained that, in advance of the rescheduled hearing, he gave consideration to amending the estimated value by reducing the “deductions” for disabilities from 60% to 50%, as the latter would have been more sustainable with the 55 Arbitrator. On further reflection he decided that a more appropriate deduction was 50%, and amended versions of pages 10 and 11 of his précis of evidence were prepared for the hearing on the 24th March 2011. It appears from page 5 of the transcript that this was flagged by Mr. Keane at the outset of the hearing, and it appears from page 56 of the transcript that the amended text was circulated by Mr. Keane just before the Arbitrator broke for lunch. The net effect of reducing the deduction from 60% to 50% was that the valuation of the lands rose from €1,436,000 to €1,848,000. 4.12 While the documentary records show that O’Buchallas did furnish a revised valuation of €1,436,000 in October 2010, which was later revised again upwards to €1,848,000 in March 2011, it must be borne in mind that this was in the context of presenting the Council’s case in the most favourable light in order to secure the best possible result, within the confines of the duty of an expert witness to give truthful and impartial evidence. While Mr. Devlin was giving these revised valuations as his best professional opinion, he was at the same time warning the Council that there was no guarantee that the Arbitrator would accept his valuation and there was a significant risk that the Arbitrator might make a much higher award, possibly of the order of €5.5m to €6.5m. 4.13 As regards the alleged non-disclosure to the Council members, the position was as follows. As set out in my first report, in recent years the most common way for local authorities to fund the creation of land banks for social and affordable housing purposes was to obtain loan finance from the Housing Finance Agency. In the present case the settlement agreement arrived at on the 24th March 2011 required the Council to pay the Claimants an agreed figure of €3m for compensation on or before the 31st August 2011, and the Council wished to raise a loan for that amount. However, pursuant to Section 106(7) of the Local Government Act, 2001 a decision to borrow by a local authority is a reserved function, i.e. a function requiring a resolution of the elected members as opposed to an executive function exercisable by the manager of the local authority and those to whom he may delegate, and it was therefore necessary to seek the approval of the elected members for the proposed borrowing. This approval was sought at a special meeting of the Council on the 18th July 2011, and in 56 advance of same each member of the Council was notified about the matters arising by letter from Ms. Halligan dated the 28th June 2011. The letter referred to the arbitration hearing for the purpose of the CPO lands having concluded, the agreed purchase price of €3m and the payment date of 31st August 2011, the up-to-date zoning of the lands, and requested the approval of the Councillors for the borrowing of the agreed sum of €3m. The Councillors were also furnished with an attached report from Ms. Halligan dated the 29th June 2011, which set out some additional details. 4.14 The attached report stated that the CPO had been issued on the basis of Mr. Mangan’s report dated the 13th August 2004, as set out in Chapter 3. It referred to the claims for compensation received on behalf of Mr. Irwin and Mr. Nolan, and the valuation of these lands by O’Buachallas dated the 30th June 2008. It later concluded as follows: “After a lot of detailed discussion and correspondence passing between all parties the Irwin interest referred the matter to the Property Arbitrator. This Hearing took place on the 24th March 2011 with a settlement figure of €3m having been agreed between representatives of the Irwin and Nolan Estates. This amount has to be paid before the 31st August 2011 and your approval is requested for the borrowing of €3m.” 4.15 As can be seen from the above, no reference was made in this report to the revised valuation furnished by Mr. Devlin of O’Buachallas in his précis of evidence dated the 18th October 2010, nor to the amended version of same submitted to the arbitration hearing on the 24th March 2011. On the one hand it could be argued that the revised valuations were not all that relevant, as the bottom line was now the settlement figure of €3m, and the net issue was whether the €3m was to be funded by the Council out of its own resources or whether it should seek to borrow to pay for this land. On the other hand the report did make reference to the original valuation of O’Buachallas dated the 13th June 2008, and on balance it seems to me that an error was made in not supplementing the information provided by referring also to the later revised 57 valuations of Mr. Devlin. The fact that Mr. Devlin had revised valuations at lower levels, and at levels lower than the settlement figure of €3m, did not mean that there was anything wrong with the settlement. In his letter to me dated the 7th December 2012 Mr. Devlin stated his opinion that this was an excellent settlement which would not have been bettered by having the matter determined the Arbitrator, and in fact in his opinion it was highly likely that the Arbitrator could have awarded compensation well in excess of €3m for a number of reasons as set out by him. The report to the Councillors could also have included some material along these lines regarding the expert advice available to the Council in agreeing the settlement figure, and it seems to me that it would have been in the interests of greater openness and transparency for the report to have included this type of additional information, and it would have saved some of the difficulties which later arose. Issues of Public Concern: 4.16 The first stated concern which is relevant to this review is as follows: “(1) lt is now evident from documents disclosed subsequent to the Council vote of the 18/7/11 that WCC were aware that the lands in question were subject to serious flooding as outlined in the "Barry Report” of 1997 on flooding in this area. With this information why did WCC proceed to issue a CPO order on lands that were subject to serious flooding, in fact a flood plain in contradiction of national building policy and base common sense.” 4.17 It is necessary to examine carefully the component elements of this stated concern which appear to be as follows. Firstly, that the Barry Report had outlined that the lands in question were subject to serious flooding and were in fact a flood plain. Secondly, that the Council were aware of this information at the time the CPO was made on the 6th December 2004. Thirdly, that in so proceeding, the Council acted in contradiction of national building policy and base common sense. As regards the first matter, I have reviewed the Barry Report and it does not appear to me that this Report outlined that the CPO lands were subject to serious flooding and were in fact a flood 58 plain. The Introduction stated that the report “assesses the capacity of the Three Trout Stream and reports on the improvement works required to cater for future developments within the stream’s catchment”. So at the outset the context was potential future development within the stream’s catchment, which catchment includes the CPO lands the subject of this review. The report considers the capacity of different sections of the Three Trout Stream, including the section shown between Nodes 5A and 5B on an accompanying drawing, which section includes the CPO lands. At paragraph 5.4.2 of the Report it states as follows: “The capacity of this section of stream various considerably. Extensive lengths of stream are inadequate to cater for a storm with a return period of 5 years – Table 4.1. Some isolated short lengths of stream are capable of carrying storms with a return period of 10 years and 50 respectively.” 4.18 The report goes on to make certain recommendations to upgrade the Three Trout Stream in capacity terms in the context of future development within the stream catchment, “in particular when development is contiguous to the stream itself” (see paragraph 6.8.1) which would include the proposed development in the present case. The principal recommendation was that the stream should be upgraded for a capacity to cater for a storm with a 30 year return period. The recommended option for stream improvement works in the area of the CPO lands was works to include the deepening, widening, regrading and realignment of the existing stream, with the preferred option being the open channel – earth lined (trapezoidal). In addition floor levels proposed for developments adjacent to the stream should be pitched at a minimum 1.0 m above the design top water level. 4.19 It appears to me from my review of the relevant files that the Council always believed that both of the Barry recommendations could be complied with in the development of this site, so as to avert the risk of flooding to the site. This was the essential response of the Council from the outset to Mr. Nolan’s objection to the CPO in relation to site suitability, as set out in the Council’s letter to An Bord Pleanála dated the 9th February 2005. This was repeated and amplified in the evidence given by Mr. Mangan on behalf of the Council at the oral hearing conducted by An Bord Pleanála 59 in March 2005. Mr. Mangan emphasised that any proposed development would take place on the higher southern side of the field away from the stream, allowing the linear park or green corridor to run along as required within the area adjacent to the stream. It appears from Appendix 1 to the Inspector’s report that the Inspector had sight of the Barry Report before completing his report. At page 21 of his report he concluded that it seemed quite plausible that a road and services located at levels close to the river might be flooded but he was, however, satisfied that the Local Authority would in their detailed plans include necessary measures to counteract such a possibility. 4.20 In conclusion on this issue, I think it is overstating the matter quite a bit suggest that the Council were aware that the lands in question were subject to serious flooding or were in fact a flood plain. At its height the Council were aware from the Barry Report that there was a risk that flooding could occur in the lower levels of the field immediately adjacent to the stream, and that this lower level area could constitute an area of flood plain. However this area would be used for the provision of a linear park and walkway in the northern section of the subject site, and detailed flood prevention measures could be introduced at the design stage by the Council to safeguard this area. In these circumstances, it does not appear to me correct to claim that the Council was acting in contradiction of national building policy and base common sense. 4.21 The second stated concern which is in part relevant to this review was as follows: “(2) In 2008, the Department of the Environment sanctioned a loan approval of €5 million for the purchase of this land. However, the Department had initially expressed in writing to WCC their serious concerns at this funding application and have raised issues surrounding the price being paid and the requirement of the Council to purchase this land when they had adequate stock of a land bank for social housing that remained un-used in the area. 60 Who in the Department overruled these initial well founded concerns by the Department and sanctioned the provision of the €5m being the fund requested.” 4.22 I dealt with this stated concern at paragraph 4.02 of first report, insofar as this concern related to the role of the Department. It is now necessary to consider this concern a little further given that there are some underlying issues which relate to the role of the Council. As stated at paragraph 4.02 of my first report, the files do not appear to contain any document containing any such expression in writing of “serious concerns” by the Department, or even raising issues in precisely the same terms as stated by the Councillors. The closest documentary record of any such expression of concern by the Department appears to be an internal Council memorandum from Ms. Halligan to Mr. Nicholson dated the 25th July 2008. In that memorandum Ms. Halligan states that she has not been dealing with the technical advisors in the Department with regard to this CPO, but they have asked a Senior Engineer in the Council to explain why we did this CPO as the Council had land next to this and that the amount of the claims are also a big concern. It may be that the two underlying issues of price and need flow from this document, but in any event the position regarding these two issues is as follows. As regards the price being paid for the amount of the claims, the position was that from approximately the end of September 2006 the Council was legally obliged to complete the CPO process, and it was stuck with having to pay compensation by reference to the market value of the property as of July 2006, close to the peak of the market. It would not be surprising if the amount of the claims for compensation were a big concern for the Department in the same way that they were a big concern for the Council, as the Department might have to pick up the tab if the Council could not meet any award of compensation that might ultimately be made by the Property Arbitrator. Trying to estimate what that ultimate award might be was a matter which gave rise to a fair amount of speculation and uncertainty, and in those circumstances there was a strong argument in favour of trying to arrive at a reasonable settlement that was put forward. The files reviewed by me suggest that a reasonable settlement was arrived at having regard to the best expert advice available to the Council. 61 4.23 As regards the issue of issue of need, Ms. Halligan states in her memorandum that the Department had asked the Council to explain why they did this CPO “as the Council had land next to this”. This appears to be a reference to the Council lands of 10 hectares (approximately 25 acres) to the north east of the CPO lands, which lands featured at the oral hearing conducted by An Bord Pleanála into the proposed CPO in March 2005. As set out in Chapter 3, in his report the Inspector referred to the evidence given by the Council that some of the 10 hectares would be severed by the construction of the new road, and being located next to business uses would be more suitable for a hotel. While the remaining 7 hectares (approximately 16 acres) could accommodate 160 units, it was not the Council policy to accommodate such an amount in one block for social housing, but rather to integrate social and private housing so the maximum number of houses that could be provided would be 100. In the light of the above and in the light of certain other information provided during the hearing, the Inspector was satisfied that the need arising was in excess of the lands in the ownership of the local authority and social housing that would be provided through Part V requirement of development permitted in the immediate area, and the housing that could be provided in the recently purchased lands at the southern end, (Prettybush). Notwithstanding the above I sought further clarification from the Council in relation to this matter in the light of the reference in Ms. Halligan’s memorandum to Mr. O’Brien having said that the Council had “to bankroll” this land. The Council informed me that the 10 hectare or 25 acres was acquired from AMD in 1993, but was not available for social housing when the CPO was made in 2004. The site was originally intended to guarantee or part-fund the development of Greystones Harbour and both the Councillors and the Department were aware of these plans. When it became clear from 2005 onwards that the Harbour project might be developed as a self-funded PP Project, part of this site was earmarked for disposal to finance the Greystones swimming pool and community centre. The site was also earmarked for disposal to redeem the €9m loan for the acquisition and development of Claremount College, Rathnew. All of this appears to be a matter of policy and of course there could be legitimate arguments about the merits of this policy. However, it papers from the confirmation procedure before An Bord Pleanála that even if the remainder 7 hectares or 16 acres of this site had been available for social housing in late 2004 this would not have been adequate to meet the existing need at that time, let 62 alone provide a land bank to meet future needs, and this appears to have been accepted by the Inspector and by An Bord Pleanála itself. 4.24 The third stated concern relates to the Council not drawing down the loan finance of €5m as originally approved before the end of 2009, and this has been dealt with at paragraph 4.03 of my first report, and nothing further arises. 4.25 The fourth concern stated by the Councillors was as follows: “(4) Have WCC ever declared to the Department of Environment the revised valuation report of Donal O’Buachalla of August 2010?. What valuation report have WCC relied upon when seeking the €3 million loan approval from the Department of Environment in July 2011.” 4.26 This concern was already dealt with at paragraph 4.04 of my first report, but it may be appropriate to address it further and to focus on the role of the Council as opposed to the role of the Department. As stated earlier, in my opinion there was no revised valuation report of O’Buachalla of August 2010 but there was a revised valuation in Mr. Devlin’s précis of evidence dated the 18th October 2010 and later amended on the 24th March 2011. The Council do not appear to have furnished the Department with any revised valuation of O’Buachallas after August 2010, but I would not expect them to have done so, at least in the context of an application for loan approval. It might have become necessary to furnish the Department with any revised valuation in the context of any on-going application for Capital funding under the Social Housing Investment Programme for a proposed housing project on the lands being acquired, but as stated at paragraph 3.08 of my first report this application went into abeyance some time in 2008. As regards the Council’s application to the Department for sanction to borrow €3m in July 2011, the Council did not rely upon any valuation report but simply stated in an email dated the 5th August 2011 that a settlement figure for compensation of €3m had been agreed between the parties in March 2011 and that the money had to be paid by the 31st August 2011. In my opinion the settlement 63 figure of €3m had now superceded any pre-existing valuation reports, and it was not necessary for the Council to rely upon any such reports when seeking loan approval. 4.27 The fifth concern was stated as follows: “(5) Have WCC ever made available to the Department the information in their possession with regard to the serious flood plain difficulties on this site and if they did so, who in the Department gave sanction for the funding of the land in question with such knowledge?” 4.28 The first part of this concern is referable to the role of the Council, but it was necessary to deal with this previously at paragraph 4.05 of my first report. As described earlier in Chapter 3 of my first report, the Council made available to the Department certain information with regard to flooding issues, in the context of the application for capital funding under SHIP. The Council submitted a detailed project brief by letter dated the 10th June 2008, and this document stated that part of the site was within the catchment area for the Three Trout Stream, and that land nearby was flooded during Hurricane Charlie. It referred to a report having been commissioned, and that the main recommendation affecting the subject site by J B Barry Consulting Engineers was that floor levels should be raised to development nearby. After receipt of the project brief Mr. Altman of the Department reverted to the Council by email dated the 27th June 2008 with a number of remaining queries, and included a reference to flooding difficulties. It appears that a draft reply was prepared by Wicklow County Council on or about the 7th July 2008 but that this reply was never sent to the Department, in circumstances where the proposed scheme was effectively “mothballed” around this time, as set out at paragraph 3.08 of my first report. It should be noted that the language of this stated concern refers to information in the Council’s possession “with regard to the serious flood plain difficulties on this site”. In my opinion this language is something of a mis-description and an overstatement of the nature of any information in the Council’s possession with regard to the risk of flooding issue. At its height the Council had information in its possession which suggested that approximately one third of the total area, being the area to the north at the lower levels which are immediately adjacent to the stream, could constitute a 64 flood plain in the sense that it was then liable to flooding, having regard to ground levels in that area and the maximum predicted flood levels. However, the information in the Council’s possession did not suggest serious flood plain difficulties on this site, but on the contrary suggested that a possible risk of flooding could be counteracted by detailed flood prevention measures which could be introduced at the design stage by the Council. 4.29 The sixth concern stated by the Councillors was as follows: “Contrary to suggestions in the media, there was no arbitration decision on the value of this particular site as it was agreed at a private meeting to pay the €3 million compensation plus costs to both the Nolan and Irwin estates. This had been formulated or agreed at the three hours of negotiations held on the 24/3/11 between parties including a statutory body WCC involved in these private negotiations involving public funding contrary to regulations. Extraordinarily there are no written memos, records or any documentation of this meeting. Why was this?” 4.30 It is clear from the Council’s files that the parties entered into a settlement agreement on the 24th March 2011 and there was therefore no requirement for the Arbitrator to give a reasoned award. I have had no sight of any suggestions to the contrary in the media, and the Councillors did not furnish me with any such media reports during the course of my review. The Councillors claim that the negotiations between the parties, which on the face of it were a normal part of these type of proceedings, were in some way “contrary to regulations” but the Councillors failed to identify any such regulations which were allegedly breached during the course of my review, and I would have been very surprised if they had been able to do so. The Councillors also state that “Extraordinarily there are no written memos, records or any documentation of this meeting” – i.e. of the settlement meeting between the parties during the course of the lunch break and thereafter on the 24th March 2011. This claim by the Councillors appears to be entirely incorrect and I have sight of the following relevant documentation on the Council’s files: 65 (a) The text of the handwritten settlement agreement signed by the parties (or their representatives) which was arrived at during the course of the settlement meeting. (b) The transcript of the Arbitration hearing which records the fact that the parties had reached an agreement that had been reduced to writing and signed by the parties. (c) There is an attendance note dated the 24th March 2011 prepared by the Law Agent, which describes the events of the day in question including the fact that during the lunch break discussions broke out in respect of settlement and throughout the afternoon the terms of settlement were discussed and ultimately agreed and signed. (d) There is a memorandum dated the 25th March 2011 from the Law Agent to Ms. Halligan which again describes the events of the day but in somewhat greater detail. 4.31 The seventh concern was stated as follows: “A signed handwritten agreement of this private meeting which committed WCC to purchase this land is undated. Why was such an important document of contract not dated?” 4.32 In my opinion, the fact that a handwritten settlement agreement was undated was undoubtedly due to an oversight on the part of the legal representatives who drafted and / or approved the text of the settlement agreement. Such an oversight can easily occur in the pressurised atmosphere of trying to wrap up and reduce to writing a settlement deal acceptable to all parties. In the present case the omission of the date was of no significance as there was plenty of secondary evidence available to verify the date if necessary. 4.33 The eighth stated concern was as follows: 66 “On the 24/3/11 the arbitrator Mr. Eoin O’Buachalla sought a copy from the legal representatives of the Council following this private agreed contract but none was available to be given to the arbitrator.” 4.34 The transcript of the arbitration hearing on the 24th March 2011 records at page 57 that the Arbitrator was informed after the luncheon adjournment that the parties had reached an agreement which had been reduced to writing and signed by the parties. It then records the Arbitrator as seeking to “take back the draft from Mr. O’Donnell”, the Junior Counsel representing the Irwin estate. This language suggests to me that the Arbitrator had been given sight of the text of the settlement agreement by the parties and wanted to take it back for a further look at some aspect of same. It is unclear from the transcript whether the text was handed back up to the Arbitrator, and the transcript might not necessarily record same. In any event, this issue is of no significance, as in many cases a copy of any settlement agreement is not made available to an Arbitrator, or indeed to a Judge in Court proceedings, and he simply is asked to make whatever Order that is required arising out of the settlement agreement and he is simply told the details of the Order requested. 4.35 The ninth concern stated by the Councillors was as follows: “(9) In May 2011 the Law Agent of WCC wrote to the legal representatives of the Irwin estate requesting that they would come to an arrangement with the legal representatives of the Nolan estate that would allow the Council to issue just one payment of €3 million of compensation to the Irwin estate contrary to the original agreement of two separate payments of €2 million to the Irwin estate and €1 million to the Nolan estate. As the law agent expressed his concerns that the head of finance in WCC might raise awkward questions that could cause delays to the process. What awkward questions would a Council’s Law agent be concerned about with regards to questions being raised by the 67 Council’s Finance officer and why would this be discussed with a private Solicitor representing a party seeking compensation against the local authority?” 4.36 This concern relates to correspondence between the Council’s Law Agent and Felton McKnight, Solicitors for the Irwin estate in May 2011. The background was the conflicting claims to ownership of the CPO lands originally made on behalf of Mr. Irwin and Mr. Nolan, and the compromise of that dispute between them by the time the matter came before the Property Arbitrator in March 2011. Back on the 9th December 2010 the Law Agent was writing to Esmonde Keane S.C., and in that letter he referred to a recent discussion with his opposite number Mr. McKnight wherein Mr. McKnight had indicated that a deal had been done whereby Mr. Irwin’s estate would take two thirds of any compensation payable and Mr. Nolan’s estate would take the remaining one third. The Law Agent had said that in practice what he suspected would happen was that the matter would be run by Messrs. Felton McKnight on behalf of the Irwin estate and afterwards the compensation, when either agreed or determined by the Arbitrator, would be divided up between them. One might note that the Law Agent was proved correct in his suspicion. As I have noted earlier, at the commencement of the Arbitration hearing the Arbitrator was informed that there was no longer any claim to the subject property by the Nolan family, and that the title issue had been resolved by agreement between the Nolan estate and the Irwin estate. The settlement agreement dated the 24th March 2011 then provided that the Irwin claimants agreed to convey the registered title to the lands to the acquiring authority, and the acquiring authority agreed to pay the sum of €3m in consideration of the said conveyance, with the sale to close on the 31st August 2011. 4.37 This then was the background to the May 2011 correspondence between the Law Agent and Felton McKnight Solicitors. By letter dated 4th May 2011 the Law Agent raised the issue of the underlying third party interest and he queried whether the Solicitors for the third party would attend a closing and whether they should have more than one Paying Order on closing, or whether in the alternative would those Solicitors accept Felton McKnight’s undertaking to issue what the Law Agent understood to be a portion of the proceeds of sale to them once completion took place. 68 Mr. Felton replied by letter dated the 20th May 2011 and confirmed that on completion Felton McKnight would require two separate bank drafts, i.e. one draft made payable to Felton McKnight Solicitors and one draft made payable to Rutherford Solicitors. By further letter dated the 24th May 2011 the Law Agent stated that the Council normally would proceed by way of a Paying Order, and if he were to seek his clients getting two Paying Orders that was likely to cause difficulties in terms of the accounting system within the Council. He asked in the circumstances would it be possible for Mr. Felton to arrange with Messrs. Rutherfords that the Law Agent would hand over the proceeds directly to Felton McKnight and they in turn would cash the Council’s Paying Order and make the appropriate “sub payment” to Rutherfords in due course. He then continued as follows: “I do not wish to be difficult but I can foresee that my client’s head of finance may well raise queries at the last minute and if the matter could be dealt with on a streamlined basis as possible this hopefully will alleviate all of these likely queries.” 4.38 Turning now to the precise concern as stated by the Councillors, it should be noted first that the description of the Law Agent’s letter is somewhat loose and inaccurate. The Law Agent’s request was not contrary to the original agreement of two separate payments of €2m to the Irwin estate and €1m to the Nolan estate. The terms of the settlement agreement dated the 24th March 2011 provided for one single payment of €3m by the Council to the Irwin claimants for the conveyance of the registered title, and the Council was not privy to any separate agreement between the Irwin estate and the Nolan estate for the division of those sale proceeds. Secondly, when the Councillors suggest that the Law Agent expressed his “concerns” that the head of finance in the Council might “raise awkward questions that could cause delays to the process”, it can be seen from the actual quotation as set out above that this is something of an overstatement and an embellishment of what the Law Agent actually said. The Law Agent did foresee that the Council’s head of finance might raise “queries” if there were to be two Paying Orders rather than one, and the Law Agent has clarified that the type of queries which he foresaw as possibly arising would have related to practical issues including: 69 (1) The settlement referred to as a single payment of €3m and not “split payments”. The Head of Finance would therefore have required an explanation and supporting documentation for releasing split payments; (2) Tax Clearance Certificates would also have been required from the Nolan estate before any payment could be made to them; (3) The Nolan estate would have to be set up as a supplier on the Council’s accounting system before a payment could be processed. 4.39 All of these potential issues could have caused delay at closing if they had not been properly dealt with, and in my opinion it was entirely in order for the Law Agent to raise with his opposite number the issue of potential queries arising at the last minute, in the event that he was asked to furnish two Paying Orders rather than one at the time of closing. 4.40 The tenth concern was stated as follows: “(10) The decision taken within WCC not to inform the site valuer Mr. Donal O’Buachalla of the serious legal conflict between the Nolan and Irwin estates with regard to the ownership of the site along with the withholding from the valuer of the flood risks involved on this land had a profound impact on the ability of the valuer to give an informed estimate of site valuation. On who’s instructions was this critical information withheld and for who’s benefit.” 4.41 The factual matters arising under this concern have already been dealt with above. It is clear from my review of the files that no decision was taken within Wicklow County Council to withhold any relevant information from the Council's valuer, Mr. Jack Devlin of O’Buachallas. There is no evidence of any lack of information having any impact on the ability of the valuer, to give an informed estimate of site valuation. The last sentence of this concern appears to imply some wrongdoing by some 70 unnamed member of the Council’s staff, and in my opinion this entire concern is inaccurate and misconceived and unfair to the staff of the Council. 4.41 The eleventh stated concern was as follows: “(11) In the formal response to notice to treat compensation claims, the Councils Law agent valued the lands in question at €600,000. In a written report planning officials state that .53 hectares of this site cannot be built on due to flooding concerns and in another report from a housing prospective the land is deemed useless. Has WCC made this information available to the Department in their consideration of loan approval?” 4.42 This concern was previously dealt with at paragraph 4.06 of my first report. The alleged factual information referred to has already been dealt with earlier in this report. Firstly, the Council’s Law Agent is not a valuer and it is inaccurate to state that he valued the lands in question at €600,000 in the formal response to the Notice to Treat compensation claims. As previously set out, the Law Agent circulated the claimants’ Statement of Claim to Mr. Devlin by letter dated the 9th August 2010, and then by letter dated the 24th August 2010 sought his views on a draft Reply which the Law Agent had prepared. By letter dated the 27th August 2010 Mr. Devlin suggested pleading a market value of approximately €693,000, based on a rate of €200,000 per acre as previously suggested to Mr. Lennox some months beforehand. Mr. Devlin’s letter went on to state that the Law Agent would appreciate that this suggested rate was purely for negotiation purposes, and that O’Buachallas believed that the date of valuation coincided with the height of the market and the comparable evidence would in all likelihood result in a substantially higher award from the Arbitrator. Secondly, the reference to .53 hectares of this site appears to have featured not in a written report from planning officials, but rather in a statement by Mr. Devlin in his précis of evidence dated the 18th October 2010 wherein he states that he had been advised by the Council that approximately .53 hectares of the subject area were below the 17.50 metre flood level. This may have been a figure extrapolated from a map or draft drawing prepared by Mr. Devereux, a Senior Engineer with the Council as referred to 71 at paragraph 3.53 above. Thirdly, the Councillors suggest that in another report from a housing perspective the land is deemed useless. This appears to be a loose translation of a statement by Mr. Devlin in his report back to Ms. Halligan dated the 1st April 2010, following his meeting with Mr. Lennox on the 29th March 2010, as already dealt with earlier. Mr. Devlin stated that for the purposes of negotiations O’Buachallas had advised Mr. Lennox that in their opinion “the lands were of little value”, given the deficiency in access and accordingly the maximum figure which they were prepared to recommend for the Council’s acceptance was €200,000. He added the important qualification that clearly this position would not be sustainable at arbitration, but they had endeavoured to reduce the claimants’ expectations by making an offer at the lowest possible level. As stated at paragraph 4.06 of my first report, it does not appear from the files that the Council made any of this information available to the Department in their consideration of loan approval, but this is probably because neither the Council nor the Department would have regarded any such information as particularly relevant in the context of an application for sanction to borrow the cost of acquisition of the land. Any earlier information relating to the potential valuation of the land had now been overtaken by the agreed compensation figure, and neither the Council nor the Department had any reason to go behind the agreed figure as conveyed by the Council. 4.43 The twelfth stated concern was as follows: “(12) Despite making a compensation claim against WCC for the sum €6.349 million for the lands in question and over a number of years strongly pursuing this claim represented by among others the present Attorney General on the 30/08/11 the Nolan estate in writing abandoned and waivered all claims to this land. How and why was this claim withdrawn?” 4.44 The factual matters underlying this concern have already been dealt with above. The claim by the Nolan estate to a possessory title was withdrawn after a deal was done between the Irwin estate and the Nolan estate. The Council was not privy to this agreement between the competing claimants, but it appears from the Law Agent’s 72 letter to Esmonde Keane S.C. dated the 9th December 2010 that a deal was done in or about early December 2010 whereby Mr. Irwin’s estate would take two thirds of any compensation payable and Mr. Nolan’s estate would take the remaining one third. The resolution of this issue and the withdrawal of the claim by the Nolan estate was announced to the Arbitrator at the commencement of the hearing on the 24th March 2011. As regards why this claim was withdrawn, one can easily surmise that the Nolan family were not confident that their claim would ultimately succeed in the High Court, and they must have felt it prudent to accept a deal whereby they would be paid off by the Irwin estate in return for withdrawing their claim. 4.45 The thirteenth concern was stated as follows: “(13) It now appears that WCC have an existing land bank of 16 acres in the Greystones area which could be used in part or all for the provision of social housing without the requirement to purchase this landlocked and flood plain site. Would it not have been more reasonable to obtain Departmental sanction of funding to construct social housing on these existing councils lands as was suggested by the Department in 2008.” 4.46 This concern has already been largely dealt with in dealing with the second stated concern above. As regards the suggestion that the site was landlocked, the Council gave evidence at the oral hearing in March 2005 regarding the proposed access via Burnaby Lawns and a new bridge over the Three Trout Stream, and this evidence was accepted by the Inspector and by An Bord Pleanála. 4.47 The fourteenth stated concern was as follows: “(14) John Nolan claimed on record at the An Bord Pleanála hearing into the CPO, that WCC were using their CPO powers to obtain this land for the benefit of “Zapi Developments” whose lands border the site in question and that this would be brought about by a subsequent land swap.” 73 4.48 This matter arose during the evidence of Mr. Al Nolan, nephew of John Nolan at the resumed oral hearing held by An Bord Pleanála on the 21st March 2006. At page 8 of the transcript Mr. Nolan stated that certain land beside Mr. John Nolan’s land, a little over three acres, went up for sale the previous year and was bought by one of the developers involved in the Zapi Development for over €3m. He referred to the fact that there were problems with vehicular access to this land, so he found it very difficult to see how this land could be of any value to the developers. He suggested that the only other access to this land would be via the County Council estate and the Church property, so it appeared to him to be more suited to the Council’s needs than the developer’s needs. He then asked the question “did Wicklow County Council consider purchasing this land or is there a possibility that the Council are planning to do a land swap with the developer and give them the CPO’d land in return for the field they had bought”. He stated that the Zapi plan showed a road running right up to the boundary of the CPO field as if they always intended to build there, yet the Council had stated at the last oral hearing that they intended to build a bridge over the river to access the field. 4.49 It appears from the transcript that Mr. Nolan was more asking a question about a possible land swap with Zapi than making a claim as to such. The question appears to have amounted to pure speculation, in the absence of any supporting evidence. My review of the relevant files shows no evidence of any discussion between the Council and Zapi in relation to this site. When I consulted with the Councillors as to whether they had any evidence they said that they were simply drawing to the Minister’s attention the question raised by Mr. Nolan. 4.50 The fifteenth stated concern was as follows: “(15) Following the initial Council meeting in July where serious concerns were expressed by a number of Councillors about the price being paid for this land, an urgent meeting was arranged to seek loan approval for the land purchased with the Minister for Housing, Mr. Willie Penrose T.D. 74 Without consultation or explanation delegates from both the Labour Group (the second largest group on WCC) were not notified of this meeting and were excluded along with a Sinn Fein delegate. Why were the representatives of both those parties not allowed to meet Minister Penrose? Was this decision at the behest of the Department or WCC?” 4.51 I dealt with this concern at paragraph 4.08 of my first report. When I consulted with the Councillors during the course of the present review they did not really dispute what I stated therein regarding the nature of the meeting which was arranged for the 11th July 2011, and the stipulation from the Minister’s Private Secretary that the delegation from the Council was to be limited to four people. The Councillors maintain, however, that even if this was the case and even if the Director of Housing was expected to be one of the four, then it was inappropriate and contrary to established practice for Mr. Nicholson to have agreed the remainder of the delegation with the Cathaoirleach and that, according to long established practice, the remainder of the delegation should have been picked by the elected members group. When I put this to the Council the essential response was that the Cathaoirleach is the political leader of the Council, and it was neither inappropriate nor contrary to established practice for Mr. Nicholson to have agreed the remainder of the delegation with him. It appeared to the Council that the representation agreed between the Cathaoirleach and the Director of Services, of themselves plus the Leas Cathaoirleach of the Council and the Chair of the Housing SPC, ensured that the Council turned out as strong as possible a team for the meeting with the Minister, and also a team which was broadly representative of the political diversity of the Council. There is therefore a dispute as to what the established practice was, and I have been unable to resolve this by my review of the files or by consulting with the relevant officers of the Council and with the public representatives. 75 Chapter 5 5.01 Conclusions and Recommendations In conclusion, I have set out in Chapter 3 the process followed by the Council in regard to compulsory land acquisition at Charlesland, Co. Wicklow. In my opinion, for the reasons set out in Chapter 3, there was no deviation by the Council from the relevant legal requirements and administrative requirements or practices. 5.02 As discussed in Chapter 3, it seems to me that the site selection procedure was somewhat bare and inadequate, even if it did not lead to a poor outcome in this particular case. Circular N7/2007 issued by the Department set out revised arrangements relating to the appraisal, approval and management of housing projects under the Department’s Social Housing Investment Programme (“SHIP”). This Circular requires a written project brief for any project with a capital value of €500,000 or more to be included in SHIP. The project brief has to address certain elements, including the issue of site selection, and it may be that since 2007 there is more comprehensive treatment of the important issues of site selection. However, it may be that in many cases the making of a CPO Order and the confirmation of same would precede any submission of a project brief for funding under SHIP, as in the present case, and in that sense the treatment of site selection in the project brief could well be retrospective and after the event. 5.03 In Chapter 4 I have examined the specific concerns of the public representatives regarding the role of the Council, as set out in the documents annexed to my Terms of Reference. I have concluded that almost all of the concerns are not well founded or are misconceived. 5.04 As regards any recommendations, I would suggest that consideration be given to putting in place a more comprehensive site selection procedure as discussed above. 5.05 I would also draw attention to the multiplicity of applications or procedures relating to a CPO which include: (a) Application to An Bord Pleanála for confirmation of a CPO; 76 (b) Application to a Property Arbitrator for determination of a claim for compensation; (c) Application by a local authority to the Department for capital funding under SHIP; and (d) Application to the Department for sanction to borrow pursuant to Section 106 of the Local Government Act, 2001. 5.06 This multiplicity of different applications and different decision-makers is a recipe for overlap and duplication, and yet at the same time a potential cause of confusion and lack of “joined up thinking”. A local authority is liable to minimise any deficiency in certain lands under the first procedure above, and yet to seek to maximise any such deficiency under the second procedure. This is liable to cause some confusion for the Department in dealing with the third and fourth procedures, and may also have caused some confusion for the public representatives in the present case. 77 6. Table of Appendices Appendix Appendix 1 Terms of Reference. Appendix 2 Letter from Secretary General to Mr. Liam O’Daly, Director General, Office of the Attorney General dated the 16th November 2011. Appendix 3 CPO Order. Appendix 4 Draft drawing dated October 2010 entitled “Lay Out Proposed New Roadway”. 78