ANNUAL PERFORMANCE EVALUATION REPORT FOR THE KATHU WASTE WATER TREATMENT WORKS NORTHERN CAPE CHIEF DIRECTORATE: BULK INFRASTRUCTURE PROGRAMME PERIOD: 01 APRIL 2013 – 31 MARCH 2014 2 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME APRIL 2014 Table of Contents 1. INTRODUCTION ............................................................................................................................ 3 2. BACKGROUND TO THE PROJECT .............................................................................................. 3 2.1. Project description ................................................................................................................... 3 2.2. Project History .......................................................................... Error! Bookmark not defined. 2.3. Project concept, design and plan ............................................................................................. 4 2.4. Start date – duration of the programme ................................................................................... 4 2.5. Funds previously allocated to the project ................................................................................. 5 3. PROGRESS TO DATE ................................................................................................................... 5 3.1. Implementation of the approved business plan ........................................................................ 6 3.2. Schedules of work and phasing of the activities ....................................................................... 6 3.3. Risks taken and management thereof ...................................................................................... 6 3.4. Capacities dedicated to the programme ................................................................................... 6 3.5. Key challenges within the project ............................................................................................. 7 4. 3.5.1. Water Conditions .............................................................................................................. 7 3.5.2. Tie-in to existing services .................................................................................................. 7 3.5.3. Delays .............................................................................................................................. 7 PROJECT RESULTS AND BENEFICIARIES ................................................................................ 7 4.1. Outcomes and Outputs ............................................................................................................ 7 4.2. Beneficiaries and project results .............................................................................................. 8 5. CONCLUSION / LESSONS LEARNED .......................................................................................... 9 5.1. Main successes and failures of the project to date ................................................................... 9 5.2. Ownership and sustainability of infrastructure works ................................................................ 9 6. RECOMMENDATIONS................................................................................................................... 9 Annexure A: Project Implementation Photo’s Annexure B: Contract details Annexure C: Job opportunities Annexure D: Commissioning Protocol Annexure E: EPWP sheet 3 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME 1. APRIL 2014 INTRODUCTION In terms of Section 10(7)(b) of the Division of Revenue Act No 2 of 2013 (DORA) as promulgated in Government Gazette No 36555 dated 10 June 2013, the transferring national officer must submit an annual performance report for Schedule 6 within four months in respect of a province and six months in respect of a municipality after the end of the financial year to the National Treasury. The Regional Bulk Infrastructure Grant (RBIG) is a Schedule 6 indirect conditional grant for the benefit in kind of municipalities. The objective of this Report is to provide an annual performance evaluation report covering the 4th quarter of RBIG funded projects, in compliance with the DORA. The objective of this evaluation was to determine whether the progress on the project is commensurate with the expenditure to date as well as to determine whether the project is still on course in terms of the original planning. This performance evaluation report, covering quarter 4 and the annual report of the 2013/14 fiscal year, is for the Kathu Waste Water Treatment Works, a Regional Bulk Infrastructure Grant project being implemented by the Gamagara Local Municipality in the Northern Cape Province, with Department of Water Affairs (DWA) as funder. 2. BACKGROUND TO THE PROJECT 2.1. Project description The project entails the construction of a new 5700 m3 reactor, two 24 m diameter clarifiers, new RAS\WAS pump station, new supernatant pump station and tanker discharge area, new sludge drying beds, renovation of the existing chlorination building, interconnecting pipework and general site works for the Upgrade of the Kathu Waste Water Treatment Works. The existing Kathu WWTW with a capacity of 3.5 Mℓ/day is the only WWTW serving Kathu. The current measured inflow is in the order of 4.5 Mℓ/day, which exceeds the aeration capacity of the existing Works resulting in poor effluent quality. The poor condition of the existing equipment further necessitates the upgrading of the Works Gamagara Local Municipality comprises of an area of 2619 square kilometres, and is located in the North Eastern sector of the Northern Cape, on the N14 National Road between Upington and Vryburg. It is approximately 200 km North East of Upington and 280 km North West of Kimberley. 4 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME APRIL 2014 Figure 1: Locality Map 2.2. Project concept, design and plan The intention of the project is to upgrade the WWTW to improve the quality and increase the capacity of the existing works and as such the key drivers of the project are: Provision of basic services to the community Compliance with the requirements of the National Water Act Supporting economic growth and developments The present wastewater flow to the works varies between 4 and 4.5 Mℓ/day while the works have a capacity of approximately 4 Mℓ/day and an aeration capacity of 3.5 Mℓ/day. The works is thus hydraulically as well as organically overloaded. The new 6.5 Mℓ/day activated sludge module will accommodate the flow for approximately 10 years after which the existing pasveer ditches will be re-commissioned to allow the works to accommodate the estimated 2030 population of approximately 50 000 people. Provision was also made on site for a second and third phase upgrade (each 6.5 Mℓ) once the treatment capacity requirements exceed the projected 2030 population figures. The Gamagara Local Municipality lies within the John Gaetsewe District Municipality’s area of jurisdiction and includes the towns of Kathu, Sesheng, Dibeng, Dingleton and Olifantshoek with a population of ± 40 000 people. 2.3. Start date – duration of the programme The contract details are mentioned below: Contract Number Contract name Contractor Contract start date Contract completion date Revised completion date GM2012/10 Upgrading of Kathu WWTW: Civil Engineering Works Civils 2000 6 September 2012 16 October 2013 28 July 2014 5 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME APRIL 2014 Contract value Percentage complete (overall) R34 485 000.00 (VAT included) 95% Contract Number Contract name GM2012/11 Upgrading of Kathu WWTW: Mechanical & Electrical Engineering Works Lektratek Water Technology 06 September 2012 06 November 2013 30 May 2014 R13 281 939.21 (VAT included) 98% Contractor Contract start date Contract completion date Revised completion date Contract value Percentage complete (overall) (See annexure B) 2.4. Funds previously allocated to the project The project is managed by the Department of Water Affairs, jointly through the Regional Bulk Infrastructure Programme and coordinated by the DWA Regional Office in the Region. The total project cost is R61 486 000.00 (VAT included) and the revised completion date of the civil works is 28 July 2014. Table 1: RBIG funding that was made available to the project to date. 2011/12 2012/13 2013/2014 Approved RBIG allocation amount Spent amount RBIG Spent amount Counter Funding N.A N.A N.A Total (vat included) R17 283 672.00 R628 000.00 R17 911 672.00 R16 655 915.34 R628 000.00 R17 283 915.34 R19 941 311.98 R19 941 311.98 R 0.00 EXPENDITURE UNTIL END MARCH 2014 ON BUDGET Total (RBIG & Counter Funding) expenditure to end March 2014 = R37 225 227.32 (Vat included). 3. PROGRESS TO DATE The performance evaluation was conducted on 14 May 2014 by a team consisting out of the following people: L Mditshane MF Hanyane L Guqa P Kekana K More B de Waal : DWA RBIG – National office : DWA RBIG : DWA – Regional office NC : Gamagara Municipality : Gamagara Municipality : Worley Parsons RSA 6 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME APRIL 2014 3.1. Implementation of the approved business plan Product Feasibility Study Start date Name of Organization compiling/ developing Completion date Gamagara Local Municipality in conjunction with WorleyParsons Jan 2011 March 2011 Implementation Readiness Study Gamagara Local Municipality in conjunction with WorleyParsons Feb 2011 June 2011 Preliminary Design WorleyParsons Aug 2011 Jan 2012 EIA MDA N/A WUL Gamagara LM WorleyParsons N/A In place ROD issued on 9/9/2012 13/3/2014 In place WorleyParsons Funding secured Funding secured Operation and Maintenance Plan Financial Funding Plan 3.2. Schedules of work and phasing of the activities Please see Annexure D: Commissioning protocol 3.3. Risks taken and management thereof The most significant risk associated with this project is the volume of hard rock that is encountered just below the ground level. As such all excavation quantities were measured as 100% rock and priced accordingly by the contractor. A further risk was the level of operator skill required to operate and maintain the new works. This risk was addressed by making allowance for an accredited service provider to operate and maintain the works during the defects liability period. This period would then be used transfer knowledge and skills to the staff currently operating the works. 3.4. Capacities dedicated to the programme The project is managed by the Department of Water Affairs, jointly through the Regional Bulk Infrastructure Programme and the Construction Unit of the Department and coordinated by the DWA Regional Office in Kimberley. The capacities dedicated to the project are as follows: Funder: DWA Regional Infrastructure Grant Co-funded by Gamagara Municipality Implementing agent: Gamagara Municipality Operation & Maintenance: Gamagara Municipality Consulting Engineer: WorleyParsons RSA Contractor (current): Civil contractor: Civils 2000 & Mechanical Contractor: Lektratek Water Technology 7 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME APRIL 2014 3.5. Key challenges within the project 3.5.1. Water Conditions Water is found at about 2m below ground level across the site. As such, backfilling of over break has to be done with a soil cement mixture instead of normal fill material. Pipes laid in pipe trenches has to be bedded in 19mm aggregate, acting as a sacrificial layer, to overcome water conditions. All of this adds to slower work rates and has a negative impact on the programme. 3.5.2. Tie-in to existing services a) With the current inflow of water to the Kathu WWTW, the plant has to be in operation full time and this makes it very difficult to connect to existing services. The most significant challenge so far was to move the pipes at the inlet works division box while the plant was still in operation. This was done by closing one sluice at a time inside the box and moving the pipes one by one. Water inside the reactor basins was controlled by pumping water from one to the other. b) To accommodate the tie-in of the new works to the existing chlorination sump, the chlorination lay-out was revised to ensure that the time needed to do the actual tie-in is minimal. A new inlet and outlet chamber was designed to let effluent water from the new works and the existing works flow together over a newly created sharp-crested weir. By doing this, optimal chlorine dosing is applied to the effluent water. New sluices were added to the Inlet and Outlet chambers so that water can either be directed to the chlorination sump or the retention pond. The pipe connecting the outlet chamber to the retention pond also has a dual purpose, in that in periods of low flow, water can be returned from the retention pond to the chlorination sump. Provision was also made for a suction point for water to be used as irrigation water across the site after installation of an irrigation system. The actual tie-in is planned for the week of 5 May 2014 and 12 May 2014. 3.5.3. Delays Due to the fact that Kathu is situated in a rich mining area, suppliers of material and plant often gives preference to the mines instead of commercial or private entities, which results in delays with delivery and availability. 4. PROJECT RESULTS AND BENEFICIARIES 4.1. Outcomes and Outputs Civil work include the following: Site clearance and excavations, including the demolition & removal of existing civil structures; Alteration to the existing inlet works including the relocation of the existing wash water tank to the chlorination building; Constructon of a new biological reactor; 8 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME APRIL 2014 Construction of two new settling tanks; Construction of new return activated sludge (RAS) and waste activated sludge (WAS) pump station (including ablution facilities, office & laboratory on the second floor; Laying & bedding of interconnecting pipework; General site- & road works, including paving around selected structures & buildings; Construction of new sludge drying beds; Construction of new supernatant pump station & tanker discharge area; Renovation of the existing chlorination building. Mechanical and Electrical work include the following: 5 off 4 kW vertical shaft mixers; 5 off 55 kW vertical shaft aerator; 2 off axial flow pumps; Tilting weir at the reactor outlet; 1 off 150 mm diameter knife gate valve complete with electric actuator at the Secondary. Settling Tank feed box: Three self-priming centrifugal Return Activated Sludge (RAS) pumps (2 duty, 1 standby), complete with pipe work and valves; Two self-priming centrifugal Waste Activated Sludge (WAS) pumps (1 duty,1 standby) complete with pipe work and valves; Two self-priming centrifugal Supernatant Return (SRP) pumps (1 duty, 1 standby) complete with pipe work, valves, screenings basket and gantry; Two rotating bridges with scraper mechanisms for the new 24 meter diameter secondary. Settling tanks complete with ancillary equipment: Sluice gates and hand stops; A gas chlorination system with a gas leakage detection system and safety equipment for disinfecting the treated effluent including makeup water filtration system; Two magnetic flow meters and ancillary equipment at the RAS/WAS pump station for measuring RAS and WAS; Monitoring and metering equipment and instrumentation Decommissioning of existing mechanical and electrical equipment Alterations to the mechanical and electrical equipment at the Inlet Works Electrical switchboards, switchgear and cables, including electrical cable reticulation on site; Grouting in of pipes through walls will be executed by the civil contractor. The mechanical contractor shall however grout base plates of pumps and other mechanical equipment to concrete plinths. Area lighting; 4.2. Beneficiaries and project results The upgrading of the works aims to improve the capacity of the existing works and also to ensure that the final effluent quality complies with General Limit Values as determined by the Department of Water Affairs. Once the Works have been upgraded the Works will be able to serve a population of 40 000 and all the households in Kathu and Sesheng will benefit from this project. This will enhance economic development towards achieving the national services target by 2014. The eradication of the housing backlog and future development cannot proceed without the additional treatment capacity that will be provided by the Works 9 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME APRIL 2014 The Gamagara Local Municipality lies within the John Gaetsewe District Municipality’s area of jurisdiction and includes the towns of Kathu, Sesheng, Dibeng, Dingleton and Olifantshoek with a population of ± 40 000 people Jobs created Job creation details are summarized in Annexure C EPWP Sheets (see Annexure E) 5. CONCLUSION / LESSONS LEARNED 5.1. Main successes and failures of the project to date Successes: a) Accurate pricing or rock: Hard calcrete material is found across the site at a depth of ±200mm below NGL. As such rock quantities were priced at 100%. b) The quality of concrete work is of outstanding quality. The standard as set right in the beginning of the project was maintained throughout the project and quality was not sacrificed because of a delay in program as is normally the case on a delayed construction project. c) Aesthetics: The design team incorporated an irrigation system and a lot of paving in their design of the site, so that it would not resemble a typical waste water treatment plant. The final shaping will be done once all water testing has been completed. Failures a) The time estimated for excavation: The contractor allowed too little time for the excavation of structures and this has directly led to the delay in the project. b) Volume of overbreak: the nature of the excavated material and an incompetent blasting contractor that had no previous experience of material in the area resulted in the large amount of material that had to be imported for filling overbreak. This in turn resulted in a further delay of the project because the estimated time for filling of overbreak at the Bioreactor was not enough and at the SST’s there was no provision made. 5.2. Ownership and sustainability of infrastructure works The Gamagara Municipality will take ownership and will sustain the infrastructure works. (Refer to paragraph 3.3). 6. RECOMMENDATIONS None 10 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME Annexure 1: PHOTOGRAPHS ON THE IMPLEMENTATION OF THE PROJECT Figure 1: Sludge drying beds Figure 2: Turning circle APRIL 2014 11 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME Figure 3: Clarifier 2 Figure 4: Clarifier 1 APRIL 2014 12 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME Figure 5: Pumps inside the RAS|WAS pump station Figure 6: Electrical panels inside the RAS|WAS pump station APRIL 2014 13 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME Figure 7: Bioreactor Figure 8: Joint sealing around the aerator base APRIL 2014 14 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME Figure 9: Axial flow pumps at the Bioreactor APRIL 2014 Annexure B: Contract details Contractor Contract No Civils 2000 GM2012/10 Lekratek GM2012/11 Contract amount (VAT included) Construction start date Revised completion date R 34 485 000.00 6-Sep-13 28 July 2014 R 13 281 939.21 6-Nov-13 30 May 2014 Amount spent to date (VAT Included) R R 22 765 428.33 9 094 798.27 Annexure C: Job opportunities Project Name and Number Kathu WWTW - April 2013 - March 2014 Summary of Decent Job Opportunities Decent job opportunities Decent job opportunities for the financial year 2013/14 for people employed at Adult Men various occupational Person Days Actual cost No No levels: Decent = Full time on job for at least 5 months or opportunities more Clerical Ongoing Clerical New Labourers Ongoing Labourers New Managerial Ongoing Managerial New Semi-Skilled Ongoing Semi-Skilled New Skilled Ongoing Skilled New Supervisor Ongoing Supervisor New Other Ongoing Other New TOTAL Ongoing TOTAL New 46,801 1 236 2 258 7 236 564,682 11 237 921,798 3 236 1 74 25 0 1,277 0 1,533,281 0 2 1 29 18 2 1 29 18 0 0 27 236 1,402,409 2 236 119,891 1 236 5 249 35 0 957 0 1,522,300 0 1 212 1 0 34 15 2 0 246 15 47,189 47,189 0 TOTAL Person Actual cost on job Days opportunities Disabled Person Actual cost No on job Days opportunities Youth Women Person Days Actual cost No on job opportunities Youth Men Person Days Actual cost No on job opportunities Adult Women Person Days Actual cost No on job opportunities 0 0 0 0 0 0 0 0 29 0 2 0 7 0 13 0 4 0 10 1 64 1 0 0 684 0 258 0 236 0 473 0 472 0 385 33 2,508 33 0 0 1,496,399 0 0 0 564,682 0 1,041,689 0 0 0 0 0 3,102,770 0 Annexure D: Commissioning Protocol KATHU WWTW Commissioning Protocol Completion of mechanical/electrical installation Completion of adjustments and rotational testing (DRY commisioning) Completion of commisioning and training (WET commisioning) Completion of testing of equipment for acceptance by Engineer Acceptance by Engineer Commencement of 12 month defects liability period Completion of all civil work by Civils 2000 17-Apr-14 4 days 2 days 5 days 2 days 25-Apr-14 2&3 June 2014 4,5&6 June 2014 9&10 June 2014 Lektratek Operating manuals 3 Manuals should be supplied prior to handover acceptance therefore before the 9 June 2014 Operation of Works for 12 months by Service Provider Service provider should commence as of 10 June 2014 until 9 June 2015 10 June 2014 to 9 June 2015 28-Jul-14 Annexure E: EPWP Sheet