Why do I need to calculate the total cost of my waste? There are six basic cost categories to include in a total waste cost analysis. These include: 1. Wasted Raw Material Cost 2. Waste Disposal Cost 3. Waste Transportation Cost 4. Waste Related Labor Cost 5. Miscellaneous Waste Costs 6. Future Disposal Liability Costs All of these cost categories should be included in an economic analysis to determine the feasibility of a waste prevention idea. If only some of the cost components are included in an analysis, then costly mistakes are likely to occur as explained in the following three steps: Step 1. The graph below compares the cost of waste prevention to the cost of waste disposal. The vertical axis represents money and the horizontal axis represents waste quantity. The cost of waste disposal is zero for disposing of zero waste quantity. In this example, the cost of waste disposal linearly increases as waste quantity increases. The cost of waste prevention is zero to reduce zero waste quantity. In this example, the cost of waste prevention slowly increases initially to represent the “low hanging fruit”. Then the cost of waste prevention increases exponentially as waste quantity increases. To achieve maximum savings and waste prevented, waste must be reduced until the cost of waste prevention is equal to the total cost of waste generation. Point A represents the economically feasible waste quantity in this example. Waste quantities to the left of point A can be reduced at a savings to the facility. Waste quantities to the right of point A cost more to prevent then to continue generating. Step 2. The graph below compares the cost of waste prevention to the total cost of waste generation. In this example, the total cost of waste generation is linearly increasing at a greater slope than the waste disposal cost. This represents the total waste cost being greater than waste disposal cost. Here Point B represents is the economically feasible waste quantity. Waste quantities to the left of point B can be reduced at a savings to the facility. Waste quantities to the right of point B cost more to prevent then to continue generating. Step 3. The graph below compares the total cost of waste generation to only the cost of waste disposal. Conclusion: By using only the waste disposal cost in an economic analysis, the waste quantity going from point A to point B would not be prevented and its associated savings would not be realized. EXAMPLE: An engineer wants to install two new dedicated pipe runs from the paint mix room to the spray booths to reduce line cleaning waste. However, he doesn’t have the time to calculate the total cost of the waste. So the engineer uses only the waste disposal cost in the calculations! Engineering Calculations: Total Implementation Cost: $10,000 Estimated Waste Prevented: 5,000 gallons per year Disposal Cost Analysis: Disposal Cost: $0.40/gallon Annual Savings: $0.40/gallon x 5,000 gallons/year = $2,000/year Payback Period: $10,000/($2,000/year) = 5 years Result: Management rejects the idea of two new dedicated pipes! So the engineer goes back and collects more cost data to calculate the total cost of the waste: Waste Disposal . . . . . . . . . . . . . Waste Transportation . . . . . . . . Wasted Raw Materials . . . . . . Waste Related Labor . . . . . . . . . . $0.40/gallon $0.04/gallon $3.05/gallon $0.03/gallon Total Waste Cost: $3.52/gallon The total Annual Savings is really: $3.52/gallon x 5,000 gallons/year = $17,600/year Payback Period: $10,000/($17,600/year) = 7 months Result: Management decides to install the dedicated pipes! Conclusion: By using the total cost of the waste instead of just the waste disposal cost component the following was achieved: Reduced Waste: 5,000 gallons/year Annual Savings: $17,600/year Improved Quality (reduced cleaning contamination)