National Roads Authority 2010 Project Management Guidelines Phase 7 Handover, Review & Closeout A7.1 Land Disposal Strategy Report (Sample Template) The following template outlines the items to be included in a Land Disposal Strategy Report: 1.0 Background Scheme Description; Overview of CPO/MO process including relevant dates (confirmation, Notice to Treat, Notice of Entry) together with details of additional lands, if any, bought by agreement as part of the land acquisition process; Overview of the Main Construction Contract including principal Contractor, start and end dates etc. Table 1 Project Summary Details Item Description Project Name NRA Project Reference No. Scheme Length (mainline) (km) NRA Marker Plate References (if available) Mainline Road Type Total Number of Structures Total Length of Side Roads (km) Principal Interchanges (No. & Type) Minor Structures (e.g. underpasses and culverts) Table 2 Land Acquisition Details Item Description Total Area of Land Acquired (Ha/Acres) Total Cost of Land Acquisition* (€) Total Number of Land Plots for Disposal Total Area of Land for Disposal *Include cost of land only. Exclude other lands costs such as interest and fees Working Document Page 1 of 3 Version 1.0 January 2010 National Roads Authority 2010 Project Management Guidelines 2.0 Phase 7 Handover, Review & Closeout Land Disposal Strategy Following completion of the N[___] Road Scheme, there are [___] No. separate plots of surplus lands, which [__________] County Council proposes to dispose of as they are no longer required for any of its functions. Details of these lands are summarised in Table 3 hereunder Table 3 Land Disposal Details Plot No. 1 Address Area Disposal Strategy Acquired From Townland: [______] [____] Ha DED: ([______] Acres) Auction / Offer for Sale in consideration of a sum of €[____] / Transfer per Clause [___] of land agreement to [Name and Address of Landowner]* Name and Address of person(s) from whom property was acquired [________] County: [________] 2 (Include CPO/MO Map Reference No. where applicable) Insert additional properties as required per Plot No. 1 above *Delete as appropriate 3.0 Disposal Strategy Details 3.1 Plot No. 1 3.1.1 Particulars of Land Land, comprising [__________] Ha ([__________] Acres) in area, situate in the townland(s) of [_________], District Electoral Division(s) of [__________] and County of [__________] as outlined in Drawing No. [__________], a copy of which is enclosed in Appendix 1. The land is not required by [__________] County Council in connection with the maintenance of the scheme or in connection with any of its functions. 3.1.2 Person(s) from whom the Land was acquired The land was acquired from [Insert Name and Address of person(s)] pursuant to Compulsory Purchase / Motorway Order Ref. [__________] and forming part of Property No. [__________] Map No. [__________] of the Deposited Map. Working Document Page 2 of 3 Version 1.0 January 2010 National Roads Authority 2010 Project Management Guidelines Phase 7 Handover, Review & Closeout 3.1.3 Person(s) to whom the Land is to be disposed of The land is to be disposed of to [Insert Name and Address of person(s)] 3.1.4 Consideration proposed in respect of the disposal Enter either The lands are to be disposed of to the person(s) outlined above in consideration of a sum of €[__________] payable to [__________] County Council. or The lands are to be disposed of by public auction, the proceeds of which shall be payable to [__________] County Council. or There is no consideration proposed in respect of this disposal as it forms part of a land agreement condition as described hereunder. 3.1.5 Covenants, Conditions or Agreements having effect in connection with this disposal Insert, as appropriate, agreements for the purchase of land or relevant Clause of Land Agreement outlining particulars of proposed land transfer. 3.2 Plot No 2 Insert, as required, for 2nd and subsequent land plots as outlined above 4.0 Recommendation It is recommended that [__________] County Council’s Land Disposal Strategy for the N[___] Road Scheme as outlined in this Report be approved by the National Roads Authority. Appendices Appendix 1 Land Disposal Drawings Appendix 2 Copies of covenants, agreements or conditions relating to the Land Disposal Strategy Appendix 3 Working Document Photographs. Page 3 of 3 Version 1.0 January 2010