SHUROB HPP The necessity of Shurob HPP Costuction has been made clear while was working out the Rogun HPP in 1973-1974. It had to play the role of “contrregulation” as requirement to optimization of work all of Vakhsh HPP Cascade and in particular Roghun HPP. The Site of Shurob HPP is defined lower of 12,5 km from the Rogun HPP Damsite . The difference of NHL (Normal Headwater Level) between NHL of Nurek HPP(costructed in 1980) reservoir and NHL of Shurob HPP is 66 meters. Shurob HPP will be operation jointly with Rogun HPP implementing restricted daily regulation. GENERAL PARAMETERS OF SHUROBSKAYA HPP Normal Headwater Level, m Installed Capacity, MW: Average annual power out put GW.hour: Earth Dam Concrete Dam Earth Dam Concrete Dam Reservoir Storage Capacity million m3: full usable 977,0 850 900 3100 3200 27,0 5,0 COMPOSITION OF MAIN STRUCTURES, HYDRO POWER PLANT AND TYPE OF DAM The type of dam construction is traditional and accepted as - the rock fill-earth dam with the central core consists of clayly loam The mound volume - 2600 thousand m3 Heigh of Dam - 83,0 m Length of Dam Crest - 235,0 m Level of Dam Crest (6 meters upper than NHL) - 983,0 m The high of up stream constructing cofferdam is 40 meters and a part of Dam construction. The cofferdam is rock fill-earth type including screen made from clayly and rock crush loam materials. The two lines of outlet structures have to be located on the right bank of the Vakhsh River. The outlet tunnels are trough-section - 11x 11meters, concrete reinforced lining thickness up to 1 meter, length 960 and 1040 meters Power House and Water Conveying Structures are located on left bank of the Vakhsh River presented as follow: - Tower type HPP Water Intake - Headrace Tunnels - Open-type House of Hydro Power Plant - Tailrace Channel The Power House of Hydro Power Plant accommodating 4-hydro units - Hydro turbine РО-75/728М-В-670 – vertical shaft Francis- type; - Hydro transformer type of СВ 1430/225-64 Capacity 212, 5/250 Watt/m. The size of Power House (on plane) 61,3х123,3 m. The Delivery Pressure Tunnels 9,0 m in diameters and length 600,0 meters. Shurob HPP Generated electricity is conveyed to the consumers at a voltage of 220 and 500 kVolt by means of interconnection to High Voltage Line – 500 kVolt Rogun HPP – Dushanbe TS. The Concrete Dam designed as- gravity type is cut on 30 meters width section. The HHP Water Intakes and four Head Water Conduits 8,8 m in diameter with steel lining are mounted in body of the Dam. THE MAIN CONSTRUCTION WORKS The main construction works are given according to composition recommended with Eart and Concrete Dam, shown in following table: №№ пп 1. Description of Construction Works Open-cut earth excavation - Total Unit of Measure Thou.m3 Earth Dam 2369 Concrete Dam 1321 1.1. 1.2. 2. 3. 4. Non-rock excavation Rock excavation Underground rock excavation - Total Emban Concrete and Reinforced Concrete -*-*Thou.m3 -*-*- 1038 1331 678 2958 510 741 580 243 488 1052 THE CONSTRUCTION COST OF HPP INDEXES OF WATER POWER DEVELOPMENT CONSTRUCTION COST ESTIMATED BOTH IN $ U.S.: №№ пп 1. 2. Descriptions Production purposed objects Reservoir TOTAL: Unit Thous. $U.S. -*-*- Earth Dam Concrete Dam 823000 164000 987000 748000 164000 912000