FOREST SERVICE HANDBOOK
GRAND MESA, UNCOMPAHGRE AND GUNNISON
NATIONAL FORESTS
FSH 2409.22 – TIMBER APPRAISAL HANDBOOK
CHAPTER 40 – COSTING GUIDELINES FOR INDIVIDUAL SALE ITEMS
Supplement No.: 2409.22, 40-2004-01.
Effective Date: 04/19/2004.
Duration: Effective until superseded or removed.
Approved: ROBERT L. STORCH
Date Approved: 04/19/2004
Forest Supervisor
Posting Instructions: Supplements are numbered consecutively by Handbook number
and calendar year. Post by document name. Remove entire document and replace with this
supplement. Retain this transmittal as the first page of this document. The last supplement to
this title was 2409.22, 44.2-90-1.
New Document(s):
Superseded Document(s):
2409.22_40
FSH 2409.22, 44.2 (Supplement 90-1)
Dated: 01/26/1990
4 Pages
6 Pages
Digest:
44.22 – Corrects reference number. Removes outdated and irrelevant direction. Updates
procedures and rates for calculation of surface rock replacement.
GMUG SUPPLEMENT
EFFECTIVE DATE: 04/19/2004
DURATION: Effective until superseded or removed
2409.22_40
Page 2 of 4
FSH 2409.22 – TIMBER APPRAISAL HANDBOOK
CHAPTER 40 – COSTING GUIDELINES FOR INDIVIDUAL SALE ITEMS
44.22 – Surface Rock Replacement. It shall be policy on the Grand Mesa, Uncompahgre and
Gunnison National Forests to charge commensurate use surface rock replacement on all
commercial timber sales that use Forest Service controlled roads.
Costs for gravel replacement vary with the size of the crushing operation and the distance from
the pit to the application point. Our charge should be based on the average-sized crushing
operation of approximately 10,000 to 15,000 cubic yards. If the forest average cost is not
appropriate, obtain current costs from Engineering.
The following Surface Rock Replacement Cost Bulletin will be used for calculating costs for
timber sales and shall be included in timber sale packages when surface rock replacement
deposits are being collected. Document all assumptions upon which the costs are based. This
process will provide uniformity in calculating the surface rock replacement deposits.
Engineering will revise the costs annually or when new data is available.
A revised surface rock replacement deposit calculation must be prepared if an alternate haul
route is selected by the purchaser. The revision must be documented in the same manner as the
original calculation and incorporated into the contract folder.
SURFACE ROCK REPLACEMENT COST BULLETIN
2002
Project:
Total Net Appraisal Volume:
Road(s):
AVERAGE HAUL
Dead Haul
= ______ mi.
Center of project = ______ mi. NOTE: Case No.___ from Haul Distance Calculations
below. Contact S.O. Engineering to determine mileages.
Average Haul = Dead Haul + Haul to Center of Project
Average Haul =
mi. +
mi. =
mi.
HAUL DISTANCE CALCULATIONS
Case 1
X Pit
Begin Project
End Project
|<-------- d ------->|<---------- a -------->|
Haul = d + a/2
GMUG SUPPLEMENT
EFFECTIVE DATE: 04/19/2004
DURATION: Effective until superseded or removed
2409.22_40
Page 3 of 4
FSH 2409.22 – TIMBER APPRAISAL HANDBOOK
CHAPTER 40 – COSTING GUIDELINES FOR INDIVIDUAL SALE ITEMS
Case 2
Begin Project
X Pit
End Project
|<------ a ------>|<------- b ------->|
Case 3
Begin Project
End Project
|<------ a ------>|<----------- b ----------->|
|
d
|
X Pit
Haul = (a2 + b2) / [2 (a + b)]
Haul = d + {(a2 + b2) / [2 (a + b)]}
HAUL COST IN $ PER CU. YD. PER MILE
NOTE: Haul Cost for any mileage over 10 miles, use 10 mile cost/cu. yd./mile.
GMUG SUPPLEMENT
EFFECTIVE DATE: 04/19/2004
DURATION: Effective until superseded or removed
2409.22_40
Page 4 of 4
FSH 2409.22 – TIMBER APPRAISAL HANDBOOK
CHAPTER 40 – COSTING GUIDELINES FOR INDIVIDUAL SALE ITEMS
ROCK COSTS
Haul = $
/cu. yd./ mile 1/ X
average haul mi. = $
/cu. yd.
Rock Cost (Forest average crushed & loaded) 2/
= $
8.75 /cu. yd.
Apply (Process, water, & compact)
= $
1.10 /cu. yd.
Subtotal Cost/cu. yd.
= $
/cu. yd. (Present Cost)
Add 24.5% of Present Cost 3/
= $
(Govt. O.H.)
TOTAL ROCK COST
= $
/ cu.yd. (A)
1/ Use previous graph for haul costs per cu. yd. per mile.
2/ Use local costs if forest average is not applicable.
3/ GMUG Supplement to FSM 6520.42, Chapter 20 (CWFS)
CUBIC YARD LOSS CALCULATION
Gravel loss = 100 cu. yd./ MMCF/mile,
20 cu. yd./MMBF/mile,
or 0.100 cu. yd. /Semi Truck Load/mile.
Miles of Gravel Road = _____ mi.
Total Gravel Loss = _____ cu. yd./Unit/mile X
Units X _____ miles =
cu.yd. (B)
Example: Loss = 100 cu. yd./MMCF/mile X 0.32 MMCF X 30 miles = 960 _ cu. yd.
COST SUMMARY
$
/cu. yd. X
(A)
cu. yd. = $ _______ Total Surface Rock Replacement Cost
(B)