North Fork Burnt River Mining Final Environmental Impact Statement Summary Unity Office of the Whitman Unit Wallowa-Whitman National Forest Location and Overview of the Area The North Fork Burnt River (NFBR) Watershed (approximately 106,500 acres) is located in the Blue Mountains of Eastern Oregon and is within the administrative boundaries of the Unity Ranger District of the Whitman Unit, Wallowa-Whitman National Forest. It lies to the northwest of the town of Unity, Oregon, in Baker County. The legal description for the watershed is: Township 9 South, Range 35½ and 36 East; Township 10 South, Range 35, 35½, 36, and 37 East; Township 11 South, Range 36 and 37 East; and Township 12 South, Range 36 and 37 East, Willamette Meridian. The NFBR is a tributary to the Burnt River, which is a tributary to the Snake River. The NFBR originates near Greenhorn Mountain, 25 miles northwest of the town of Unity, Oregon. The NFBR Watershed does not include any designated wilderness, wild and scenic rivers, research natural areas, or inventoried roadless areas. Mining began in the NFBR Watershed in the 1860s with placer mining. Miners armed with only picks and shovels found rich gold deposits on the Burnt River and its tributaries. Placer mining was at its peak from 1863-1866. Placer mining began to decline about 1890 as the richest placers were worked out. But the placer mining activity had uncovered many rich veins, and lode mining began in earnest. One of the largest mines, the Bonanza, operated from 1879-1898 and produced several million dollars in gold. By 1911, lode mining was on the decline, but a new gold rush began with the advent of bucket line dredges. In 1942, War Production Board Order L-208 closed all precious metals mines. Increased operating costs and a fixed gold price precluded the reopening of all but a few mines after World War II. (Wallowa-Whitman Land and Resource Management Plan, page 2-15) Large bucket dredge operations shut down in 1957. Inflation and high gold prices in the early 1980s caused renewed interest in gold mining. Page S-1 of 19 Today, 34 mine operators work the placer and lode deposits on public lands in the North Fork Burnt River Watershed. Approximately 10 percent of these operators work hard rock mines; the remaining 90 percent work the placers. Purpose and Need for Action Existing Condition The 36 Code of Federal Regulations (CFR) 228.4 states that if a mine proposal is likely to cause significant disturbance of surface resources, a Plan of Operations (Plan) is required. 36 CFR 228.5 states that proposed operations requiring a Plan will be analyzed by the authorized officer to determine the reasonableness of the requirements for surface resource protection. In the North Fork Burnt River Watershed, 34 mining Plans are currently approved. Some were approved in the early 1980s, and many have no expiration dates. Environmental conditions have changed in this watershed since those approvals were granted. Five streams in the watershed have been listed as water-quality impaired under Section 303(d) of the Clean Water Act. While the existing Plans have a variety of requirements to address water quality impacts, these requirements do not necessarily address Section 303(d) of the Clean Water Act. Redband trout (Oncorhynchus mykiss), which exists in the watershed, has been added to the Regional Forester’s list of sensitive species; and three plant species currently on the Regional Forester’s sensitive plant list (Botrychium montanum, Botrychium minganense and Pellaea bridgesii) have documented locations in the watershed. There are 747 miles of road (closed and open) in the NFBR Watershed. The NFBR Roads Analysis (2002) has identified 241 of these miles as contributors to water quality problems. The NFBR Watershed Analysis Cumulative Effects Addendum (Bradford and Fedora, 2000) identified roads as the largest contributor of activity-generated sediment in the watershed. Additionally, the NFBR Watershed is not within the Wallowa-Whitman Land and Resources Management Plan (LRMP) guidelines for road density for any of the management areas in the watershed. Several new Plan proposals have recently been submitted by claimants for analysis and approval. These proposals include amendments to some of the current Plans; and some of the currently approved Plans will expire soon and the operators have requested that the expiration dates on their Plans be extended. If these new proposals are approved, the number of Plans in the watershed will increase from 34 to 49, with an increase in acres potentially disturbed from 68 to 116. Desired Condition Desired conditions for the surface resources on the mining claims in the NFBR Watershed are derived from goals, objectives, standards, and guidelines from the LRMP, public scoping and interdisciplinary team input. Desired conditions provide a future Page S-2 of 19 vision for the area and can help in development of management options for the mining operations in the NFBR Watershed over time. Plans of Operations are approved for the mining operations in the NFBR Watershed. Requirements are included in all Plans of Operations to ensure that adverse impacts to surface resources are minimized. The number of 303(d)-listed streams is reduced or eliminated. Protect watershed values to the fullest extent possible under existing laws in evaluating and developing mineral operating plans (LRMP, page 4-25). A safe and efficient road system is in place. It provides access for fuelwood cutting, gathering of forest products, private land access, mining access, hunting, fishing, and other recreational activities, and Forest administration, while not contributing to impaired water quality. The desired condition for this analysis area includes rehabilitation of soil and water resources that are in a less than satisfactory condition as a result of past human activities. In addition, all proposed actions within the analysis area will be designed to minimize impacts to the soil and water resources (LRMP, page 4-21 and 4-23). Streamside vegetation along reaches that are currently shaded adequately will be preserved (LRMP, page 4-44). Water temperatures of perennial streams within the analysis area will be managed in an effort to meet Oregon Department of Environmental Quality water quality standards (LRMP, page 4-22). Where stable banks and channels occur, activities will be designed so that stability is not jeopardized, and resulting degradation of water quality is avoided. On reaches with unstable banks and channels, rehabilitation measures will be designed to restore stability and eliminate additional adverse impacts on water quality (LRMP, page 4-23). As these treatments are accomplished and begin to be effective, input of sediment to the streams will decrease and water quality will improve. Ground vegetation and the shrub communities within the riparian areas will be utilized by livestock and big game at levels that will allow sustained use without a decline in the health of these communities (LRMP, pages 4-51 and 4-52). Areas of detrimental soil compaction will be eliminated so that they no longer present a hazard to watershed health (LRMP, page 4-21). Road systems will be developed so that the area can be accessed for necessary management with minimum roading in riparian areas. Existing roads within riparian areas that are no longer needed will be eliminated (LRMP, pages 4-24 and 4-25). The desired condition for scenery is to manage all National Forest System (NFS) lands to obtain the highest possible visual quality, commensurate with other appropriate public Page S-3 of 19 uses, costs, and benefits (LRMP, page 4-42). The goal of scenery management is to a) minimize immediate impacts to scenery, and b) restore landscapes to a sustainable condition. Purpose and Need The purpose and need for action is: 1) the unforeseen and changed conditions in the North Fork Burnt River Watershed that did not exist or were not recognized at the time approvals were granted to the currently approved Plans; 2) the submittals of amendments to some of these existing Plans; 3) submittals of several new proposed Plans; 4) the Forest Service’s responsibility to approve or require modifications to these existing and proposed Plans in accordance with Federal mining and environmental laws; and 5) several reaches of the North Fork Burnt River and its tributaries do not meet State water quality standards for temperature and sediment. As a consequence, these reaches are listed as impaired under Section 303(d) of the Clean Water Act by the State of Oregon. It is the responsibility of the Forest Service to address 303(d)-listed waters on NFS lands and to develop strategies that will improve water quality, based on the specific parameters listed. A roads analysis completed for this analysis area indicates that roads are a primary human-caused contributor to water quality degradation. Based on the number and nature of mining operations in the drainage, the existence of sensitive plant and animal species in the watershed, the number of roads and their potential impacts to the North Fork Burnt River and its tributaries, and the current water quality-limited status of 5 streams in the watershed, it has been determined that cumulative environmental impacts exist and are significant to the NFBR Watershed, and therefore an EIS is required to disclose those impacts in detail, to analyze alternatives to the proposals, and to determine possible means of mitigating those cumulative impacts. This EIS analyzes the direct, indirect, and cumulative effects of mining operations and of management actions designed to improve listed water quality parameters. Proposed Action The Proposed Action is to approve the current, new, modified or amended Plans of Operations for several mining claims in the NFBR as submitted by the claim owners. Table S-2 lists the Plans of Operations analyzed in this EIS. The Plans of Operations that make up the Proposed Action are those listed under Alternative 2. Issues Key issues are those points of concern that would change among the alternatives. Alternatives to the proposed action are based on changes to impacts to these issues. Key Issue 1: Water Quality Water quality in the North Fork Burnt River Watershed has been impaired by past management practices and other human activities. Past timber harvest and road Page S-4 of 19 building has negatively affected water quality in the watershed. Hydraulic, placer, and dredge mining have affected many of the streams. Road density is high in many of the subwatersheds and many roads are located in riparian areas. These factors can alter physical processes in streams and on hill slopes, leading to changes in flow regimes, the movement and storage of sediment, bank stability and substrate composition. Table S-1 shows the North Fork Burnt River and several tributaries in the analysis area that have been listed as water-quality impaired under Section 303(d) of the Clean Water Act and their reasons for listing. (ODEQ 2002) Table S-1 303(d)-Listed Streams in the NFBR Watershed Subwatershed Location Reason for Listing Stream Name North Fork Burnt River, Mouth to Pete Mann Ditch Trout Creek 83A, 83C, 83E, 83G Summer Temperature 83D Sedimentation Summer Temperature Sedimentation Summer Temperature Sedimentation Sedimentation Patrick Creek 83E Camp Creek Geiser Creek 83F 83G Measurements used to compare the alternatives in relation to this issue: Key Indicators 1. The number of Plans of Operations that include consistent requirements to minimize impacts to water quality. 2. The total estimated acres of disturbance in the riparian habitat conservation areas (RHCAs). 3. Total miles of road maintenance, reconstruction, closure, and decommissioning of roads contributing to water quality improvement. Key Issue 2: Fisheries Ongoing placer mining operations, in an effort to expose placer deposits in the NFBR Watershed, have removed trees, shrubs, and ground cover in the flood-prone areas immediately adjacent to the North Fork Burnt River, Camp, Greenhorn, Simpson, Snow, Tony, Winterville, Dry, Pinus, Jackknife, Gimlet and Geiser Creeks. This mining-caused ground disturbance has adversely affected pool frequencies, large woody material (LWM), and bank stability. Redband trout, a fish species listed as sensitive by the Pacific Northwest Region of the Forest Service (Region 6) is present. The exposed soil on the mining access roads and the disturbed flood-prone areas immediately adjacent to the North Fork Burnt River and several of its tributaries, could increase the amount of sediment entering these streams, resulting in the loss of Page S-5 of 19 existing redband trout spawning, incubating and rearing habitat in the North Fork Burnt River, and its tributaries. Key Indicators: 1. Risk to pool habitat 2. Risk to large woody material recruitment 3. Risk to bank stability 4. Number of Plans of Operations with consistent requirements to minimize adverse effects to fish habitat 5. Acres of disturbance in RHCAs 6. Miles of road closed, maintained, reconstructed, or decommissioned 7. Number of Plans of Operations with in-stream activities 8. Sedimentation – number of placer Plans without stream buffers Key Issue 3: Access/Road Densities The roads analysis indicates that Subwatersheds 83F and 83G (where most of the mining activity is concentrated in the watershed) have open road densities of 4.2 and 4.4 miles per square mile compared to LRMP recommendations of 1.5-2.5 miles per square mile for the management areas represented in the subwatersheds. Key Indicators: 1. Open road densities by management area 2. Number of miles of road to be closed, maintained, reconstructed or decommissioned Other Resource Concerns Other issues discussed in the EIS include noxious weeds, sensitive plant species, wildlife, rangeland management, heritage resources, visual quality, and social and economic concerns. Alternatives Four alternatives were considered in detail. Alternative 1 represents the “No Action/No Change” Alternative, which includes the 34 currently approved Plans of Operations. These Plans would continue to operate as approved. No new or amended Plans of Operations would be approved. See Table S-2. Alternative 2 is the Proposed Action, which approves the currently approved, modified, and new Plans of Operations as submitted by the miners, a total of 49 Plans of Operations. These Plans vary in their requirements to protect water quality, fish habitat, and surface resources. See Table S-2. Page S-6 of 19 Alternative 3 approves the 49 Plans of Operations described in Alternative 2, but with additional requirements designed to protect and improve water quality, fish habitat, and surface resources. These requirements will be applied consistently across all Plans of Operations in the NFBR Watershed, depending on the activities approved in the Plan. See Table S-2. Alternative 4 is the same as Alternative 3, but addresses those portions of the transportation system used for mine access which contribute to the degradation of water quality in the North Fork Burnt River system. The activities to be implemented under Alternative 4 are summarized in Table S-3. Table S-2 compares the Plans of Operations approved under each alternative. For Plans of Operations, Alternative 3 and Alternative 4 are the same. Table S-2 Plans of Operations by Alternative Operation Name Alternative 1 Currently Approved Operations August Placer Nothing Approved Burnt Lode/PL Nothing Approved Camp Hale PL Equipment: Backhoe, dozer, trommel, pump. Activities: Sampling with backhoe, processing, use of settling ponds. Alternative 2 Proposed Operations Alternative 3 Added Requirements Proposed Equipment: Track hoe, backhoe, dump truck, dozer, trommel, sluice, pumps. Proposed Activities: Exploration testing of placer gravels, processing, settling ponds, ditch maintenance, use of log bridge Equipment: Backhoe, dozer, trommel, pumps, suction dredge. Activities: Testing and mining of placer gravels, processing, suction dredging pond construction. Same as Alternative 1 Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; R1-R23 Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; L1-L2; R1-R22 Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; R1-R22 Page S-7 of 19 Operation Name Dominion Ld Group Don Juan LD/PL Dream Chaser PL EJ Placers Page S-8 of 19 Alternative 1 Currently Approved Operations Equipment: Excavator, backhoe, dozer, mucker, generators, compressors. Activities: Exploration / development, portal construction, trenching, drilling, road upgrade, use of ponds. Equipment: Dozer, backhoe, dump truck, compressors, trommel, pumps, crusher, suction dredge. Activities: Testing and mining of placer gravels, processing, underground sampling including use of explosives, re-timber portal, suction dredging, use of ford, construction of ponds. Equipment: Backhoe or excavator, dozer, trommel, pumps, generator, hand tools, suction dredge. Activities: Exploration and mining in placer gravels, processing, settling ponds, suction dredging, use of ford. Nothing Approved Alternative 2 Proposed Operations Alternative 3 Added Requirements Same as Alternative 1 Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; L1-L2; R1-R23 Dropped Dropped Same as Alternative 1 Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; R1-R22 Proposed Equipment: Excavator, dump truck, loader, trommel. Proposed Activities: Testing of placer gravels, bulk sample, processing, use of ford. Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; R1-R22 Operation Name Alternative 1 Currently Approved Operations Geiser Stream Diversion PL/LD Nothing Approved Gimlet PL Equipment: Dozer, excavator, portable mill, generator, compressor, pumps, suction dredge. Activities: Excavate and process placer gravels and old tailings, suction dredging. Equipment: Backhoe or excavator, dozer, dump truck, trommel, pumps, generator, suction dredge. Activities: Exploration pits, processing, use of settling ponds, suction dredging. Nothing Approved Glory B PL Gold Busters PL Alternative 2 Proposed Operations Alternative 3 Added Requirements Proposed Equipment: Excavator, backhoe, dozer, loader, dump truck, trommel Proposed Activity: Divert Geiser Creek into new 200-foot channel, mine placer gravels in creek bed, reclaim and return creek to original channel, processing, lode and placer exploration, new portal, underground mining, road construction (100’) feet and a new bridge constructed across the channel. Same as Alternative 1 Activity: Same as Alternative 2 except that new creek channel will be constructed and stream will not be returned to original channel. Additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; L1-L2; R1-R23 Same as Alternative 1 Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; R1-R22 Proposed Equipment: Backhoe, trommel, high-bankers, sluice, pumps, generators, suction dredge. Proposed Activities: Excavations in placer gravels, processing, 3 settling ponds, suction dredging, group camping. Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; R1-R22 Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; R1-R22 Page S-9 of 19 Operation Name Alternative 1 Currently Approved Operations Alternative 2 Proposed Operations Alternative 3 Added Requirements Same as Alternative 1 Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; R1-R22 Same as Alternative 1 Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; L1-L2; R1-R22 Golden Donk PL Equipment: Backhoe, dump truck, dozer, pumps, trommel, generator, suction dredges, high-bankers. Activities: Testing and mining placer gravels, high-banking and suction dredging, processing, use of ponds, group camping. Equipment: Core or rotary drill, trommel, impact mill, backhoe, dozer, pumps. Activities: Drilling (holes 50' or less), exploration testing of placer gravels, processing, use of ponds. Nothing Approved Proposed Equipment: Backhoe, trommel. Proposed Activities: Repair ponds, excavation of placer gravels and stockpiles, processing. Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; R1-R22 Goldy PL and Mill Nothing Approved Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; R1-R22 Gopher PL Equipment: Backhoe, dozer, small tractor, trommel, pumps. Activities: Exploration testing, processing, repair & construction of settling ponds. Proposed Equipment: Loader, trommel, pump, gold spinner, 5-yd dump truck. Proposed Activities: Processing site for mining at Pyx and King Solomon Mines (Granite Creek watershed); process concentrates and mill tailings, exploration testing of placer gravels, use of settling ponds, campsite. Same as Alternative 1 Gold Camp PL Golden Bandit PL/LD Page S-10 of 19 Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; R1-R22 Operation Name Alternative 1 Currently Approved Operations Jackpot (Silver Eagle) PL Nothing approved. Jay Gould LD Equipment: Backhoe or excavator, mucker, dump truck, dozer, generators. Activities: Clean and repair 2 portals, trenching, underground mining, milling done off site. Equipment: Backhoe or excavator, mucker, dump truck, dozer, generators. Activities: Clean and repair 2 portals, trenching, underground mining, milling done off site. Nothing Approved Jay Gould Mine Works Jim Bob PL Ladder, Rusty Bucket PL Nothing Approved Alternative 2 Proposed Operations Alternative 3 Added Requirements Proposed Equipment: Backhoe, dozer, hand tools. Proposed Activities: Improve access road, site leveling & clearing, testing with hand tools, processing. Same as Alternative 1 Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; R1-R22 Same as Alternative 1 Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; L1-L2; R1-R23 Equipment: Backhoe, 4" and 8" suction dredges, trommel, sluice, pumps, hand tools. Proposed Activities: Activities: Exploration test holes in placer gravels, processing, construct settling pond, suction dredging, use of ford. Proposed Equipment: Backhoe, excavator, dozer, 2 5-yard dump trucks, wash plant, test plant, pumps. Proposed Activities: Exploration testing and mining, processing, use of ponds. Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; R1-R22 Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; L1-L2; R1-23 Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; R1-R22 Page S-11 of 19 Operation Name Lucky 7 PL Lucky One PL/LD Lucky John PL Lucky PL Mary Dixie LD Page S-12 of 19 Alternative 1 Currently Approved Operations Equipment: Backhoe, dozer, suction dredge, sluice, hand tools. Activities: Road construction, exploration trenching, processing, suction dredging. Nothing Approved Equipment: Backhoe, dozer, dump truck, trommel, pumps. Activities: Exploration and mining of placer gravels, processing, construct settling ponds. Nothing Approved Equipment: Backhoe or excavator, loader, dump truck. Activities: Repair portals, exploration trenching. Alternative 2 Proposed Operations Alternative 3 Added Requirements Dropped Dropped Proposed Equipment: Backhoe, dozer, dump truck, wash plant, pumps, generator. Proposed Activities: Exploration testing in placer gravels, processing, repair or construct new settling ponds, road repair and construction (1000’) of temporary road, reopen and sample existing adit, drill well. Dropped Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; L1-L2; R1-R23 Proposed Equipment: Excavator or backhoe, dump truck, wash plant, high-bankers, dozer. Proposed Activities: Exploration testing in placer gravels, panning and high-banking in existing ponds, processing at Gold Busters site. Same as Alternative 1 Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; R1-R22 Dropped Same as Alternative 2 with additional requirements G1-G19; G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1P2; W1-W7; L1-L2; R1R4; R6-14; R16-R23 Operation Name Midas/Lady Bug PL Monarch LD North Fork PL Old Channel PL Alternative 1 Currently Approved Operations Equipment: Backhoe, sluice, wash plant, 3" suction dredge, highbanker. Activities: Temporary check dam in stream, suction dredging, road repair; exploration and mining of placer gravels, processing, construct settling ponds. Equipment: Backhoe or excavator, dump trucks, loader, dozer, generator, compressor, portable ball mills, jig, centrifugal concentrators, portable saw mill. Activities: Milling with ball mill, construct settling ponds; new portal and test portal construction, timber cutting and milling for portal, underground mining, trenching, phone line and road repair Equipment: Backhoe or excavator, dozer, trommel, dump truck, loader, pumps, generator, suction dredge. Activities: Exploration testing and mining of placer gravels, processing, use of settling ponds, suction dredging. Equipment: Backhoe, dozer, loader, sluice. Activities: Excavate and process placer gravels. Alternative 2 Proposed Operations Alternative 3 Added Requirements Same as Alternative 1 Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; R1-R22 Same as Alternative 1 Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; L1-L2; R1-R23 Same as Alternative 1 Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; R1-R22 Same as Alternative 1 Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; R1-R22 Page S-13 of 19 Operation Name Parkerville PL Parkerville PL Mining Playboy Placers Prudent (#9) PL Page S-14 of 19 Alternative 1 Currently Approved Operations Equipment: Backhoe, excavator, dozer, loader, dump truck, trommel, pumps, generator. Activities: Exploration testing of placer gravels, processing on site or adjacent private land, use of settling ponds, road maintenance. Nothing Approved Equipment: Backhoe, trommel, 3" suction dredge. Activities: Excavation of placer gravels, processing, construction of settling ponds, suction dredging. Equipment: Backhoe or excavator, dozer, dump truck, trommel, pumps, generator, suction dredge. Activities: Excavation of placer gravels, processing, construction of settling ponds, suction dredging. Alternative 2 Proposed Operations Alternative 3 Added Requirements Dropped - Replaced with Parkerville Placer Mining Dropped - Replaced with Parkerville Placer Mining Proposed Equipment: Backhoe, excavator, dozer, loader, dump truck, trommel, pumps, generator. Proposed Activities: Exploration & mining of placer gravels, processing, construction and use of 3 off-channel ponds. Same as Alternative 1 Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; R1-22 Same as Alternative 1 Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; R1-R22 Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; R1-R22 Operation Name Alternative 1 Currently Approved Operations R&RK #2, #3 PL Nothing Approved R&RK #4, #5 PL Nothing Approved Racer Group/Keystone Korners PL Nothing Approved Red Dog PL Equipment: Dozer, backhoe, excavator, dump truck, loader, trommel, pumps, generators. Activities: Mining of placer gravels, processing, 3 ponds, road maintenance. Alternative 2 Proposed Operations Alternative 3 Added Requirements Proposed Equipment: Backhoe, wash plant, pumps, generator, suction dredge. Proposed Activities: Exploration testing of placer gravels, processing, construction of settling ponds, suction dredging, construction of 200’ of temporary road, use of ford. Proposed Equipment: Backhoe, trommel, suction dredge. Proposed Activities: Excavation of placer gravels, processing, suction dredging. Proposed Equipment: Wash plant, backhoe, dozer, dump truck, pumps, generator, hand tools, suction dredge. Proposed Activities: Exploration testing in placer gravels, processing, construction of settling ponds, road repair and construction of 400 feet of temporary road, culverts installed, suction dredging. Proposed Equipment: Same as Alternative 1 Proposed Activities: Gate installation, additional placer exploration and mining, new settling ponds. Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; R1-R22 Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; R1-R22 Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; R1-R22 Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; R1-R22 Page S-15 of 19 Operation Name Roberts LD Rocker Group PL Shamrock PL Alternative 1 Currently Approved Operations Equipment: Dozer, excavator, compressor. Activities: Reopen and stabilize adit, underground mining including use of explosives, stockpiled ore on site, ore removed from site for processing, close access road. Equipment: Backhoe or excavator, dozer, dump truck, trommel, pumps, generator. Activities: Exploration and mining of placer gravels, processing, use of settling ponds. Nothing Approved Silver Bell PL Equipment: Backhoe, wash plant, pumps. Activities: Excavation of trenches in placer gravels, modify existing in-channel ponds, processing. Silver Eagle LD Equipment: Backhoe, dozer. Activities: Open and repair portal, sampling underground and on waste dumps, trees cut for mine timbers, on-site & off-site processing. Page S-16 of 19 Alternative 2 Proposed Operations Alternative 3 Added Requirements Same as Alternative 1 Same as Alternative 2 with additional requirements G1-G19; G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1P2; W1-W7; L1-L2; R1R4; R6-R14; R16-R23 Same as Alternative 1 Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; R1-R22 Proposed Equipment: Backhoe, dozer, suction dredge, trommel, pumps. Proposed Activities: Exploration testing in placer gravels, processing, suction dredging, use of fords, put culvert in NFBR to access south side of river Proposed Equipment: Generator, excavator, loader, trammel. Proposed Activities: Same as Alternative 1 without use of in-stream ponds, construct and use 4 off-channel ponds, construct short spur road, install gates on 2 access roads. Same as Alternative 1 with the addition of a dump truck and loader. Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; R1-R22 Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; R1-R22 Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; L1-L2; R1-R23 Alternative 1 Currently Approved Operations Alternative 2 Proposed Operations Alternative 3 Added Requirements Sluice Box PL Equipment: Backhoe or excavator, trommel. Activities: Exploration and mining of placer gravels on north and south sides of river, processing sites, use of settling ponds, use of ford. Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; R1-R22 Snow Creek PL Equipment: Backhoe, dozer, trommel, generator, pumps, dump truck. Activities: Mining of 3 to 4 acres of placer gravels, processing site with 3-pond settling/recycling system, additional exploration testing, fords in creek. Nothing Approved Proposed Equipment: Same as Alternative 1 with suction dredge. Proposed Activities: Same as Alternative 1 with additional exploration testing upstream on both sides of river, water source off-channel ponds or spring, suction dredging. Proposed Equipment: Same as Alternative 1 Proposed Activities: Additional mining and exploration testing along creek with 10-foot buffer, mining of flood channel and inland channel areas, additional testing excavations, construction of short spur roads. Proposed Equipment: Backhoe, wash plant, pumps. Proposed Activities: Construct 600’ temporary road, exploration testing of placer gravels in existing and new pits, processing, construction of settling ponds. Proposed Equipment: Backhoe, hand tools. Proposed Activities: Exploration testing in placer gravels, use of ford, processing on private land. Operation Name Standby/McNamee PL Star (Pinus) PL Nothing Approved Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; R1-R22 Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; R1-R22 Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; R1-R22 Page S-17 of 19 Operation Name Alternative 1 Currently Approved Operations Alternative 2 Proposed Operations Sunshine PL Equipment: Backhoe, trommel. Activities: Excavate and process old tailings, dump material, and placer gravels, pond in ephemeral drainage. Same as Alternative 1 Three Cent LD Equipment: Core drill, water tank, backhoe. Activities: Core drilling at 2 sites, excavations of catchments, exploration trenches. Equipment: Dozer, backhoe, excavator, dump truck, trommel. Activities: Exploration testing and mining of placer gravels, two processing sites with settling ponds, road maintenance. Equipment: Backhoe or excavator, loader, dump truck. Activities: Exploration testing along Geiser Creek and ridge area west of creek, processing at Upper Geiser processing site. Equipment: Backhoe or excavator, loader, dump truck. Activities: Exploration testing of placer gravels, processing at Upper Geiser processing site, use of ford. Dropped Three Cent PL Upper Geiser Creek PL/LD Upper Winterville PL/LD Page S-18 of 19 Alternative 3 Added Requirements Same as Alternative 2 except that pond must be moved out of draw, and new off-channel settling ponds constructed; additional requirements G1-G22; C1-C5; H1H12; F1-F9; NW1NW9; P1-P2; W1-W7; R1-R22 Dropped Proposed Equipment: Same as Alternative 1 Proposed Activities: Same as Alternative 1 along with mining and processing in East Three Cent area, pond repair/upgrade, water well, pipeline. Same as Alternative 1 Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; R1-R22 Same as Alternative 1 Same as Alternative 2 with additional requirements G1-G19; G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1P2; W1-W7; R1-R4; R6R14; R16-R22 Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; L1-L2; R1-R23 Alternative 1 Currently Approved Operations Operation Name West Parkerville PL Nothing Approved Wild Flower PL Equipment: Backhoe or excavator, dump truck, pumps, generator, hand tools, suction dredge. Activities: Excavations of placer gravels, processing, use of settling ponds, suction dredging. Alternative 2 Proposed Operations Alternative 3 Added Requirements Proposed Equipment: Backhoe or excavator, dump truck. Proposed Activities: Exploration testing of placer gravels and old channels, processing at adjacent Parkerville site (private land), with settling ponds on NFS, existing ponds cleaned and repaired. Same as Alternative 1 Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; R1-22 Same as Alternative 2 with additional requirements G1-G22; C1-C5; H1-H12; F1-F9; NW1-NW9; P1-P2; W1W7; R1-22 Alternative 4 Table S-3. Road Activities Under Alternative 4. Maintenance NFBR Watershed Totals Closure Reconstruction Decommission ERS Total Miles Miles in RHCA Total Miles Miles in RHCA Total Miles Miles in RHCA Total Miles Miles in RHCA Extreme Severe Serious N/A Total 0 1.6 2.6 11.49 15.69 0 0.2 0.94 0.37 1.51 2.82 3.89 9.15 47.62 63.48 2.75 2.33 2.94 0.07 8.09 7.24 3.09 6.93 7.13 24.39 3.51 0.19 0.89 0.08 4.67 2.64 1.31 0.64 6.89 11.48 2.39 1.11 0.16 0 3.66 Preferred Alternative Alternative 4 best meets the Purpose and Need of approving mining Plans of Operations while still meeting 36 CFR 228.8, minimizing adverse environmental impacts on National Forest surface resources, and minimizing the impacts to water quality in the North Fork Burnt River Watershed. Page S-19 of 19