Agenda Item No 11 Community and Environment Board 11 June 2007 Report of the Assistant Director (Leisure and Community Development) Play Area Development Programme 1 Summary 1.1 This report sets out progress in respect of the corporate priority to install new play areas across the Borough. 2 Recommendation to the Board a That the Board comments upon the progress made to date in respect of the Play Area Development Programme; and, Recommendation to the Executive Board b That the Executive Board be recommended to approve the carry forward of those capital funds allocated to undertake the identified drainage works at Hurley and Wood End Recreation Grounds into the 2007/08 capital programme. 3 Introduction 3.1 A progress report on the corporate priority to install new play areas across the Borough was presented to the Board at its meeting held in March 2007. The latest position in respect of the development programme is summarised in the action plan attached at Appendix A. The action plan includes all Borough Council play areas, in order that the development programme can be considered in the context of the Council’s overall provision. 4 Phase 1: 2005 - 2006 4.1 As previously reported, the projects at Ansley Common Bretts Hall (phase 1 – teen provision), Austrey, Cole End Park in Coleshill, Piccadilly and Abbey Green Park, Polesworth, are complete. 5 Phase 2: 2006 - 2007 5.1 Also as previously reported, new play areas have been installed in Corley, Hurley and Wood End, although a number of outstanding issues remain to be resolved in each case. ... 11/1 D:\533565750.doc 5.2 The sites in Hurley and Wood End are subject to extremely wet ground conditions, which impede both reinstatement works and the all-year round use of these facilities. A drainage consultant has been appointed to prepare designs and technical specifications for drainage schemes at both sites and to oversee implementation of the works. It is expected that the available capital funding should enable land drainage in the immediate vicinity of the play facilities at both sites and mole drainage over the remaining area of the field at Hurley. To optimise the chances of successful implementation, drainage works need to be undertaken at the most favourable time of the year, depending on the type of scheme being installed. In this regard, it is hoped that the land drainage schemes can be completed in the late summer of this year, with the mole drainage being undertaken by spring 2008. 5.3 Despite extensive local consultation, concern has been expressed by residents neighbouring the play area about the nature of the equipment that has been installed in Corley. In this regard, officers will listen to these concerns at a public meeting to be held in late May, feedback from which will be reported verbally to the Board. 5.4 Hartshill Parish Council has now received an offer of funding support from WREN for the installation of the new play area at Snow Hill Recreation Ground. Subject to the exchange of contracts between the Parish Council and WREN, installation works will be undertaken in June/July, with a view to the new play area being available for public use during the school summer holidays. The previously agreed removal of the play equipment at Moorwood Estate and Grange Road, Hartshill, will be undertaken after the new play area has been developed at Snow Hill Recreation Ground 6 Phase 3: 2007 - 2008 6.1 Given its identification as a priority within the North Warwickshire Play Strategy, the proposed replacement of Mancetter play area has been included in a bid for Big Lottery funding, the outcome of which will be known by the end of June 2007. In the meantime, consultation has been completed with local children and young people and this will be used to inform the design and specification of the scheme, which will be installed in the autumn. 6.2 As instructed by the Board, officers are continuing to work in partnership with Atherstone Town Council to deliver this Authority’s commitment to develop play provision in the town, in respect of which the first stage of community-based consultation is underway in order to establish whether or not there is local support for the currently identified priority to develop play opportunities at Royal Meadow Drive Recreation Ground. The second stage of consultation, with local children and young people, which will determine the nature of the equipment to be provided, will follow during the summer. This timetable allows for design and specification to be completed by September, in order to meet potential external funding application deadlines. Clarification has been sought from the Town Council about whether it is able and willing to make a capital contribution to the development of a new play facility in Atherstone. 6.3 Negotiations are continuing with Atherstone Town Council in respect of the transfer of the play areas in Minions Close, St. George’s Road and Warwick Drive on terms to be agreed by the Solicitor to the Council and subject to their being retained as play areas for public use. The Town Council has been informed that these terms are likely to include a long-term lease and a peppercorn rent. 11/2 D:\533565750.doc ... 6.4 An engineering consultant has been appointed to prepare designs and technical specifications for remedial works to the known problems of land/bank slippage at Minions Close and to oversee implementation of the works, which will be undertaken prior to any transfer of the play area to the Town Council. 6.5 Consultation on the final site, Kitwood Avenue in Dordon, will take place in the autumn, with a view to installation taking place in spring 2008. 7 Finance 7.1 The Borough Council has committed £600,000 of capital funding to the three-year Play Area Development Programme, of which 2007 – 2008 is the last year. 7.2 The eight schemes completed to date have cost the Authority £433,148 (revenue and capital costs) and have attracted external funding of £78,810, thereby resulting in a total cost of £511,958. Partners have contributed a further £3,432 in third party funding in order to draw down landfill tax grant from SITA Environmental Trust. 7.3 The scheme proposed at Snow Hill Recreation Ground, Hartshill, is expected to cost £106,218, of which the Borough Council will contribute £44,500, with £61,718 being contributed by partners and external funding agencies. In this instance, the Borough Council will contribute a further £5,500 in third party funding to draw down grant from WREN. 7.4 A detailed breakdown of funding is provided in Appendix B to this report. 7.5 Through its partnership with the Borough Council, Hags Play Ltd. is committed to achieving 10% “added value” on the contract. This is measured by the difference between the final cost of each scheme and the cost that would have applied had the works been commissioned through a standard specification contract. There are two elements that contribute to achieving the added value: a) discounts on the price of equipment and b) savings that are achieved by the contractor through efficient working and cost effective procurement, which are passed on to the Council. On the eight play areas installed to date, Hags Play Ltd has achieved 14% added value (£73,506), as detailed in Appendix C to this report. 8 Report Implications 8.1 Financial Implications 8.1.1 Appropriate capital and revenue provision has been made to support the Play Area Development Programme, and remedial works at Minions Close, Atherstone are to be funded by a reserve held for grounds maintenance. The land drainage capital works at Hurley and Wood End require final approval from the Executive Board which meets on June 25. 8.2 Safer Communities Implications 8.2.1 Appropriately designed and located play opportunities for children and young people provide constructive alternatives to anti-social and/or criminal behaviour. Improving the quality and accessibility of play areas will also help to reduce the likelihood of disorder within the community. ... 11/3 D:\533565750.doc 8.3 Legal and Human Rights Implications 8.3.1 The new play area installations will comply with the requirements of all appropriate legislation, including the Disability Discrimination Act 1995. 8.4 Environment and Sustainability Implications 8.4.1 The provision of opportunities for constructive activity within communities enhances local cohesion, social inclusion and individual and collective quality of life. It also impacts positively upon the creation of sustainable communities, within which people feel safe, healthy and valued. 8.5 Portfolio Holder, Shadow Portfolio Holder and Ward Members Consultation 8.5.1 The Portfolio and Shadow Portfolio Holders for Safer Communities, Health, Wellbeing and Leisure, Environment, Community Life and Resources, as well as all appropriate Ward Members have been consulted on the content of this report. 8.6 Risk Management Implications 8.6.1 The risk management implications of the Play Area Development Programme were set out in reports to the Community and Environment Board at its meetings held in June 2005 and March 2006. 8.7 Equalities 8.7.1 The provision of new and improved play areas is designed to enhance the quality of life for everyone in local communities. There is a need to undertake an Equality Impact and Needs Assessment of the Development Programme, but it remains a positive initiative that seeks to meet expressed needs throughout communities that have been actively engaged in service design. 8.8 Links to Council’s Priorities 8.8.1 The Play Area Development Programme has positive and direct links to the corporate priorities to “address equalities in all aspects of our policies and services”, “enhance community engagement and access to services”, “improve the broader public realm”, “work in partnership to improve our market towns” and to “work with our partners to tackle crime and the fear of crime”. The Contact Officers for this report are Simon Powell (719352) and Alethea Wilson (719212). 11/4 D:\533565750.doc Background Papers Local Government Act 1972 Section 100D, as substituted by the Local Government Act, 2000 Section 97 Background Paper No 1 2 3 4 5 6 7 8 9 10 Author Assistant Director (Leisure and Facilities) Assistant Director (Leisure and Facilities) Assistant Director (Leisure and Facilities) Assistant Director (Leisure and Facilities) Assistant Director (Community Development) Assistant Director (Community Development) Assistant Director (Community Development) Assistant Director (Leisure and Community Development) Assistant Director (Leisure and Community Development) Assistant Director (Leisure and Community Development) Nature of Background Paper Report to the Community and Environment Board Report to the Community and Environment Board Report to the Community and Environment Board Report to the Community and Environment Board Report to the Community and Environment Board Date 06 Sept. 2004 06 June 2005 05 Sept. 2005 31 Oct. 2005 20 March 2006 Report to Leaders’ Group 24 April 2006 Report to Leaders’ Group 18 Sept 2006 Report to the Community and Environment Board 30 Oct 2006 Report to Management Team 20 Feb 2007 Report to the Community and Environment Board 19 Mar 2007 11/5 D:\533565750.doc